| Name | Last modified | Size | Description | |
|---|---|---|---|---|
| Parent Directory | - | |||
| 10. SECTION IIIC - CHANGE ORDER 12.10.15.doc | 2025-08-15 14:31 | 45K | ||
| 2018 DOY Calendar.pdf | 2025-08-15 14:31 | 69K | ||
| Abney Elementary Recorded Certification of Substantial Completion.pdf | 2025-08-15 14:31 | 581K | ||
| CO #1 - Change Bldg A Roof Slope/ | 2025-08-15 14:31 | - | ||
| CO #2 - Additional Fascia Bldg 4/ | 2025-08-15 14:31 | - | ||
| Contractor Summary, Breakdown & Comment Sheets.xls | 2025-08-15 14:31 | 76K | ||
| Example - Additional Time Letter 2015-07-08.doc.docx | 2025-08-15 14:31 | 181K | ||
| Example Breakdown.pdf | 2025-08-15 14:31 | 1.0M | ||
| Pay app #2.pdf | 2025-08-15 14:31 | 793K | ||
| Pay app#3.pdf | 2025-08-15 14:31 | 758K | ||