<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA      UFGS-01 11 00 (January 2008)<BRK/>
                                    ------------------------------<BRK/>
Preparing Activity:  <PRA>NAVFAC</PRA>         Superseding <BRK/>
                                    UFGS-01 11 00 (July 2007)<BRK/>
                                    UFGS-01 11 00.00 40 (June 2006)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 01 11 00</SCN><BRK/>
<BRK/>
<STL>SUMMARY OF WORK</STL><BRK/>
<DTE>01/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>a description of 
work covered in this contract and is required for use in all projects</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.<BRK/>
<BRK/>
This guide specification includes tailoring options for regional requirements.  
Selection or deselection of a tailoring option will include or exclude that 
option in the section, but editing the resulting section to fit the project 
is still required.</NPR><BRK/>
<AST/><BRK/></NTE>
<TAI OPT="NAVY"><NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  When using this section, a Project Information Form should be filled 
out for the Contract Specialist.  This form is available from the Construction 
Criteria Base website at <URL HREF="http://www.wbdg.org/ccb">http://www.wbdg.org/ccb</URL>.  The form is found in the 
Specification Library, NAVFAC Specifications Category, Project Information Form.  
For SOUTHNAVFANCENGCOM projects, do not use this Project Information Form.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include on the drawing:</NPR><BRK/>
<BRK/>
<NPR>1.  Location of project.</NPR><BRK/>
<BRK/>
<NPR>2.  Limits of contractor's work area.</NPR><BRK/>
<BRK/>
<NPR>3.  Location of Government-furnished work.</NPR><BRK/>
<BRK/>
<NPR>4.  Location of Government installed work.</NPR><BRK/>
<BRK/>
<NPR>5.  Contractor's on-base route to site.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See "FAC 5252.211-9301, Phased Construction Schedule."</NPR><BRK/>
<AST/><BRK/></NTE>
</TAI><BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<TAI OPT="NAVY"><SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Issue (date) of references included in project specifications need not 
be more current than provided by the latest guide specification.  Use of SpecsIntact 
automated reference checking is recommended for projects based on older guide 
specifications.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM E 2114</RID><RTL>(2008) Standard Terminology for Sustainability Relative to the Performance of Buildings</RTL><BRK/><BRK/></REF><REF><ORG>GREEN BUILDING INITIATIVE (GBI)</ORG><BRK/><BRK/><RID>Green Globes</RID><RTL>(2004) Green Globes(tm) US Green Building Rating System</RTL><BRK/><BRK/></REF><REF><ORG>U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)</ORG><BRK/><BRK/><RID>Energy Star</RID><RTL>(1992; R 2006) Energy Star Energy Efficiency Labeling System</RTL><BRK/><BRK/></REF><REF><ORG>U.S. GREEN BUILDING COUNCIL (USGBC)</ORG><BRK/><BRK/><RID>LEED</RID><RTL>(2002; R 2005) Leadership in Energy and Environmental Design(tm) Green Building Rating System for New Construction (LEED-NC)</RTL><BRK/><BRK/></REF></SPT></TAI><TAI OPT="NASA,NAVY"><SPT><TTL>1.2   DEFINITIONS</TTL><BRK/>
<BRK/>
<TXT>Definitions pertaining to sustainable development are as defined in <RID>ASTM E 2114</RID>, [Section <SRF>01 35 40.00 20</SRF> ENVIRONMENTAL 
MANAGEMENT][Section <SRF>01 57 20.00 10</SRF> ENVIRONMENTAL PROTECTION], and as specified.</TXT><BRK/>
<BRK/>
<LST>a.  "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison 
to conventional products and services.  This comparison may consider raw materials acquisition, production, 
manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.</LST><BRK/>
<BRK/>
<LST>b.  "Indoor environmental quality" is the physical characteristics of the building interior that impact 
occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, 
and views.</LST><BRK/>
<BRK/>
<LST>c.  "Operational performance" is the functional behavior of the building as a whole or of the building 
components.</LST><BRK/>
<BRK/>
<LST>d.  "Sustainability" is the balance of environmental, economic, and societal considerations.</LST><BRK/>
<BRK/></SPT>
</TAI><SPT><TAI OPT="NASA,NAVY"><TTL>1.3   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Submittals must be limited to those necessary for adequate quality control.  
The importance of an item in the project should be one of the primary factors 
in determining if a submittal for the item should be required.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.</NPR><BRK/>
<BRK/>
<NPR>For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy projects.<BRK/>
<BRK/>
Submittal items not designated with a "G" are considered as being for information 
only for Army projects and for Contractor Quality Control approval for Navy 
projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for [Contractor Quality Control approval.] [information only.  When used, a designation following the "G" 
designation identifies the office that will review the submittal for the Government.]  The following shall be 
submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT></TAI><BRK/>
<BRK/>
<TAI OPT="NASA"><LST><SUB>SD-01 Preconstruction Submittals</SUB></LST><BRK/>
<BRK/>
<ITM>Upon receipt of Government Furnished Equipment, the Contractor shall submit records in accordance 
with paragraph entitled, "Government Furnished Property," of this section.</ITM><BRK/>
<BRK/>
<ITM>Submit the following items to the Contracting Officer:<BRK/>
<BRK/>
<SUB>Utility Outage Requests</SUB><BRK/>
<SUB>Utility Connection Requests</SUB><BRK/>
<SUB>Borrow Permits</SUB><BRK/>
<SUB>Excavation Permits</SUB><BRK/>
<SUB>Welding Permits</SUB><BRK/>
<SUB>Burning Permits</SUB></ITM><BRK/></TAI>
<TAI OPT="NAVY"><BRK/>
[<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Energy Performance Rating</SUB></ITM>]</TAI><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4   WORK COVERED BY CONTRACT DOCUMENTS</TTL><BRK/>
<BRK/>
<SPT><TTL>1.4.1   Project Description</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Describe the project and the types of work involved in sufficient detail 
so as to present a general picture which is self contained but does not refer 
to the drawings or to other parts of the specification.  Mention peculiar or 
hazardous work, and monitoring of archaeological resources. Do not provide quantities 
in the description.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The work includes [_____] and incidental related work.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.2   Location</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include station name and geographic location in the blank provided.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The work shall be located at the [_____], approximately as indicated.  The exact location will be shown by the 
Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
</SPT><TAI OPT="NASA"><SPT><TTL>1.5   CONTRACT DRAWINGS</TTL><BRK/>
<BRK/>
<TXT>The following drawings accompany this specification and are a part thereof.</TXT><BRK/>
<BRK/>
<LST>Drawing No. [_____]<BRK/>
Sheets 1 through [_____]</LST><BRK/>
<BRK/>
<TXT>[Five] [_____] sets of full size contract drawings, maps, and specifications will be furnished to the Contractor 
without charge. Reference publications will not be furnished.</TXT><BRK/>
<BRK/>
<TXT>Contractor shall immediately check furnished drawings and notify the Government of any discrepancies.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6   WORK RESCHEDULING</TTL><BRK/>
<BRK/>
<TXT>Contractor shall allow for a maximum of [_____] calendar days where construction activity is prohibitive.  Further 
allowance for [_____] calendar days of excavation and subsurface activity abeyance shall be imposed where other 
construction activities are permitted.  Government will provide 24 hour notification each time the restrictions 
are invoked.</TXT><BRK/>
<BRK/>
<TXT>Normal duty hours for work shall be from [_____] a.m. to [_____] p.m., Monday through Friday.  Requests for additional 
work shall require written approval from the Contracting Officer 7 days in advance of the proposed work period.</TXT><BRK/>
<BRK/></SPT>
</TAI><TAI OPT="NAVY"><SPT><TTL>1.7   PROJECT ENVIRONMENTAL GOALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Project environmental goals cannot be enforced, but are identified here 
to guide contractor means and methods, which may have significant environmental 
impacts.  Additionally, it may help the Contractor propose alternatives that 
are consistent with the project environmental goals.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer.  
The overall goal for design, construction, and operation is to produce a building that meets the functional program 
needs and incorporates the principles of sustainability.  Specifically:</TXT><BRK/>
<BRK/>
<LST>a.  Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion.  Minimize 
offsite environmental impact.</LST><BRK/>
<BRK/>
<LST>b.  Use the minimum amount of energy, water, and materials feasible to meet the design intent.  Select 
energy and water efficient equipment and strategies.</LST><BRK/>
<BRK/>
<LST>c.  Use environmentally preferable products and decrease toxicity level of materials used.</LST><BRK/>
<BRK/>
<LST>d.  Use renewable energy and material resources.</LST><BRK/>
<BRK/>
<LST>e.  Optimize operational performance (through commissioning efforts) in order to ensure energy efficient 
equipment operates as intended.  Consider the durability, maintainability, and flexibility of building 
systems.</LST><BRK/>
<BRK/>
<LST>f.  Manage construction site and storage of materials to ensure no negative impact on the indoor environmental 
quality of the building.</LST><BRK/>
<BRK/>
<LST>g.  Reduce construction waste through reuse, recycling, and supplier take-back.</LST><BRK/>
<BRK/>
<SPT><TTL>1.7.1   Independent Verification</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  There are multiple ways of certifying green buildings.  </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Army projects shall use the LEED rating system - include the following 
paragraph and delete other independent verification systems.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
[<SPT><TTL>1.7.1.1   US Green Building Council (USGBC) - LEED(tm) Rating System</TTL><BRK/>
<BRK/>
<TXT>Provide [completed project in compliance] [work consistent] with USGBC LEED-NC(tm) [v2.2][_____] (<RID>LEED</RID>), level 
[certified] [silver] [gold] [platinum] requirements.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>1.7.1.2   Green Globes US</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Green Globes US is the newest addition to the BREEAM/Green Leaf suite 
of environmental assessment tools.  BREEAM (BRE Environmental Assessment Method) 
is one of the world's most widely used means of reviewing and improving the 
environmental performance of buildings. </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide [completed project in compliance] [work consistent] with <RID>Green Globes</RID> US level [Two Globes] [Three Globes] 
[_____] requirements.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>1.7.1.3   EPA <SUB>Energy Performance Rating</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Determine the energy use target rating that meets or exceeds Energy Star.  
Provide Energy Star target using EPA Target Finder.  Use Target Finder to rate 
estimated energy use for the completed design.  If design achieves a rating 
of 75 or higher, provide Statement of Energy Design Intent (SEDI) generated 
from Target Finder to document results.  Contracting Officer shall submit the 
SEDI to EPA and will receive the "Designed to Earn the Energy Star" graphic 
to place on drawings to show that the energy use for the design meets EPA criteria 
for energy efficiency.  Include the following paragraph if graphic has been 
earned.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide work consistent with drawings in order to meet <RID>Energy Star</RID> in accordance with design.</TXT><BRK/>
<BRK/></SPT>
]</SPT></SPT></TAI><SPT><TTL>1.8   OCCUPANCY OF PREMISES</TTL><BRK/>
<BRK/>
<TXT>Building(s) will be occupied during performance of work under this Contract.  [Occupancy notifications will be 
posted in a prominent location in the work area.]</TXT><BRK/>
<BRK/>
<TXT>Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means 
of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>1.9   EXISTING WORK</TTL><BRK/>
<BRK/>
<TXT>In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Remove or alter existing work in such a manner as to prevent injury or damage to any portions 
of the existing work which remain.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Repair or replace portions of existing work which have been altered during construction 
operations to match existing or adjoining work, as approved by the Contracting Officer.  At 
the completion of operations, existing work shall be in a condition equal to or better than 
that which existed before new work started.</ITM><BRK/>
<BRK/>
]</SPT><TAI OPT="NASA"><SPT><TTL>1.10   ON-SITE PERMITS</TTL><BRK/>
<BRK/>
<SPT><TTL>1.10.1   <SUB>Utility Outage Requests</SUB> and <SUB>Utility Connection Requests</SUB></TTL><BRK/>
<BRK/>
<TXT>Notify the Contracting Officer at least [48 hours] [72 hours] prior to starting excavation work.  Contractor 
is responsible for marking and verifying all utilities not marked.</TXT><BRK/>
<BRK/>
<TXT>The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction 
not indicated or specified to be removed.  But indicated in locations to be transversed by piping, ducts, and 
other work to be installed.  [Verify elevations before installing new work closer than nearest manhole or other 
structure at which an adjustment in grade can be made.]</TXT><BRK/>
<BRK/>
<TXT>Work shall be scheduled to hold outages to a minimum.</TXT><BRK/>
<BRK/>
<TXT>[Utility outages and connections required during the prosecution of work that affect existing systems shall be 
arranged for at the convenience of the Government and shall be scheduled outside the regular working hours or 
on weekends.]</TXT><BRK/>
<BRK/>
<TXT>[Contracting Officer may permit utility outages at his discretion.]</TXT><BRK/>
<BRK/>
<TXT>[Contractor shall not be entitled to additional payment for utility outages and connections required to be performed 
outside the regular work hours.]</TXT><BRK/>
<BRK/>
<TXT>[Requests for utility outages and connections shall be made in writing to the Contracting Officer at least [_____] 
calendar days in advance of the time required.  Each request shall state the system involved, area involved, 
approximate duration of outage, and the nature of work involved.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.10.2   Borrow, Excavation, Welding, and Burning Permits</TTL><BRK/>
<BRK/>
<TBL><THD>  <HL1>ACTIVITY</HL1>                <HL1>SUBMISSION DATE</HL1>                 <HL1>SUBMISSION FORM</HL1><BRK/></THD>
<BRK/>
  [<SUB>Borrow Permits</SUB>      [_____] calendar days prior to work          [_____]]<BRK/>
  [<SUB>Burning Permits</SUB>     [_____] calendar days prior to work          [_____]]<BRK/>
  [<SUB>Excavation Permits</SUB>  [_____] calendar days prior to work          [_____]]<BRK/>
  [<SUB>Welding Permits</SUB>     [_____] calendar days prior to work          [_____]]<BRK/></TBL>
<BRK/>
<TXT>Permits shall be posted at a conspicuous location in the construction area.</TXT><BRK/>
<BRK/>
<TXT>Burning of trash or rubbish is [not] permitted at [_____] [on project site].</TXT><BRK/>
<BRK/>
<TXT>[Any burning of trash or rubbish shall be done in strict compliance with requirements established by the authority 
having jurisdiction.]</TXT><BRK/>
<BRK/></SPT>
</SPT></TAI><TAI OPT="ARMY,NAVY"><SPT>[<TTL>1.11   LOCATION OF UNDERGROUND FACILITIES</TTL><BRK/>
<BRK/>
<TAI OPT="PEARL HARBOR"><NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For projects at Pearl Harbor Shipyard, include the bracketed option for 
Ground Penetrating Radar.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/></TAI>
<BRK/>
<TXT>[Obtain digging permits prior to start of excavation<TAI OPT="EFA MW"> by contacting the Contracting Officer [15] [____] calendar 
days in advance</TAI>.]  [Scan the construction site with <TAI OPT="PEARL HARBOR">[Ground Penetrating Radar and]</TAI> electromagnetic or sonic equipment, 
and mark the surface of the ground[, pier deck or paved surface] where existing underground utilities [or utilities 
encased in pier structures] are discovered.  Verify the elevations of existing piping, utilities,and any type 
of underground [or encased] obstruction not indicated to be specified or removed but indicated or discovered 
udring scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed.]  
[Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment 
in grade can be made.]</TXT><BRK/>
<BRK/>
<SPT><TTL>1.11.1   Notification Prior to Excavation</TTL><BRK/>
<TAI OPT="LANTDIV"><NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For projects in the Tidewater, Virginia area, use 15 days and include 
the bracketed sentence.</NPR><BRK/>
<AST/><BRK/></NTE>
</TAI><BRK/>
<TXT>Notify the Contracting Officer at least [48 hours] [15 days] prior to starting excavation work.  <TAI OPT="LANTDIV">[Contact Miss 
Utility 48 hours prior to excavating.  Contractor is responsible for marking all utilities not marked by Miss 
Utility.]</TAI></TXT><BRK/>
<BRK/></SPT>
]</SPT></TAI><SPT>[<TTL>1.12   GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  There are situations in which equipment installation data or templates 
would allow the Contractor to prepare rough-in and proceed with construction 
prior to taking delivery of Government-furnished equipment.  This paragraph 
may be expanded to include scheduling delivery of installation data or templates 
as well as the equipment itself, if the data can be made available more quickly 
than the Government-furnished equipment and if advanced delivery would be helpful 
to the Government.  Obtain listing of material from the Government.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include this paragraph only when the contractor will be required to install 
Government-Furnished Materials and Equipment or provide utilities for same.  
Obtain information to identify the items from the Government.  Select FAR 52-245-2 
when the value of the Government-furnished property is greater than $100,000.  
Select FAR 52.245-4 when the value of the Government-furnished property is $100,000 
or less.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Pursuant to Contract Clause ["FAR 52.245-2, Government Property (Fixed Price Contracts)"] ["FAR 52-245-4, Government-Furnished 
Property (Short Form)"], the Government will furnish the following materials and equipment for installation by 
the Contractor:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Provide complete description and quantities for Government-furnished 
Contractor and installed material and equipment.  Identify manufacturer, make, 
model and operating characteristics.   Avoid generic descriptions especially 
for equipment requiring utilities such as water service, drains, natural gas, 
steam, or electricity.  This information should be made available by the activity 
furnishing the material or equipment to be installed through the Government.  
When a utility is required to serve the Government-furnished item, ensure that 
the appropriate Section for the utility needed is included in the project specification.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Salvage property to be removed and reused in the general work area shall 
be handled as a Contractor service and not listed here.</NPR><BRK/>
<AST/><BRK/></NTE>
<TBL><THD><BRK/>
  DESIGNATION NO.             DESCRIPTION                    QUANTITY<BRK/></THD>
<BRK/>
    [_____]                     [_____]                       [_____]<BRK/></TBL>
<BRK/>
<TXT>Quantities indicated for the above-listed items marked with an asterisk are estimates.  It is the intention of 
the Government to furnish all quantities of the asterisk items required to complete the work as specified and 
the various quantities will be adjusted when necessary.</TXT><BRK/>
<BRK/>
<TXT>Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government.  
Contractor shall furnish any additional quantities required.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.12.1   Delivery Schedule</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose the version of this paragraph which best satisfies the project 
conditions.  The first alternative is best suited for projects requiring careful 
scheduling of Government-furnished equipment.  The number of calendar days required 
for notification or that have elapsed before availability should be established 
after considering (1) a reasonable time between the Contract Award and the first 
need for Government-furnished equipment and (2) the lead time required for Government 
procurement.  The storage rate should be set at the commercial rate in the area 
of storage.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Notify the Contracting Officer in writing at least [_____] calendar days in advance of the date on which the 
materials and equipment are required. Pick up materials and equipment no later than 30 calendar days after such 
date.  When materials and equipment are not picked up by the 30th day, the Contractor will be charged for storage 
at the rate of [_____] per<ENG> 100 [pounds] [cubic feet]</ENG><MET> 450 [kg] [cubic meters]</MET> per month or fraction thereof.]</TXT><BRK/>
<BRK/>
<TXT>[Materials and equipment will be available on or after [_____] calendar days after the award of contract.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.12.2   Delivery Location</TTL><BRK/>
<BRK/>
<TXT>The materials and equipment [are located at [_____]] [are located within [_____] miles of the jobsite] [will 
be delivered to [_____]][the salvage receiving point [____]].</TXT><BRK/>
<BRK/></SPT>
]</SPT><SPT>[<TTL>1.13   GOVERNMENT-INSTALLED WORK</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include this paragraph if the Government is to install equipment or perform 
other work at the job site, excluding inspection and testing.  Define the extent 
and type of Government work that may impact on the operations of the Contractor.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[_____].</TXT><BRK/>
<BRK/>
]</SPT><TAI OPT="NAVY">[<SPT><TTL>1.14   Navy and Marine Corps (NMCI) Coordination Requirements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For Navy projects only.  In addition to the EIA/TIA standards for telecommunications, 
the architectural, stuctural, mechanical, plumbing, electrical and fire protection 
designs must comply with the guidance in the latest version of UFC 3-580-10N.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.14.1   NMCI Contractor Access</TTL><BRK/>
<BRK/>
<TXT>The NMCI Contractor must be allowed access to the facility towards the end of construction (finishes 90% complete, 
rough-in 100% complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment 
in the telecommunications rooms and make final connections.  The construction contractor will be required to 
coordinate his efforts with the NMCI contractor to facilitate joint use of building spaces during the final phases 
of construction.  After the Contracting Officer has facilitated coordination meetings between the two contractors, 
the construction contractor must, within one week, incorporate the effort of additional contractor coordination 
into his construction schedule to demonstrate his plan for maintaining the contract duration.</TXT><BRK/>
<BRK/></SPT>
</SPT>]</TAI><SPT><TTL>1.15   SALVAGE MATERIAL AND EQUIPMENT</TTL><BRK/>
<BRK/>
<TXT>Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.</TXT><BRK/>
<BRK/>
<TXT>The salvaged property shall be segregated, itemized, delivered, and off-loaded at the [Government designated] 
storage area located within [_____]<MET> kilometers</MET><ENG> miles</ENG> of the construction site.</TXT><BRK/>
<BRK/>
<TXT>Contractor shall maintain property control records for material or equipment designated as salvage.  Contractor's 
system of property control may be used if approved by the Contracting Officer.  Contractor shall be responsible 
for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<TXT>Not used.</TXT><BRK/>
<BRK/></PRT>
<PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<TXT>Not used.</TXT><BRK/>
<PGE/><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: For all LANTNAVFACENGCOM projects, do not use this spec cover sheet.  
Obtain electronic specification cover sheet required for use with electronic 
signature program from the LANTNAVFACENGCOM specifications branch.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: For Design Build projects, do not use this specification cover sheet.  
Use cover sheet provided by the NAVFAC component for whom the specification 
is being created. </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<HL4><HL3>SPECIFICATION COVER SHEET</HL3></HL4><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  FOR SPECIFICATION COVER SHEET:</NPR><BRK/>
<BRK/>
<NPR>A.  Technical specification cover sheet.  Prepare a cover sheet for use as camera-ready 
master for the first page of the specification.  Substitute appropriate information 
where the example has brackets with identifying numbers.  Do not include the 
identifying numbers in the final sheet.  Underlines indicate places for signatures, 
to appear on the final cover sheet.  Fill in the following at the identifying 
numbers listed.</NPR><BRK/>
<BRK/>
<NPR>1.  Appropriate Engineering Field Division or Engineering Field Activity.</NPR><BRK/>
<BRK/>
<NPR>2.  Specification number.</NPR><BRK/>
<BRK/>
<NPR>3.  UIC and Construction contract number.</NPR><BRK/>
<BRK/>
<NPR>4.  Exact name of project.</NPR><BRK/>
<BRK/>
<NPR>5.  Military location of the project.</NPR><BRK/>
<BRK/>
<NPR>6.  Geographic location of the project.</NPR><BRK/>
<BRK/>
<NPR>7.  Type names of each discipline engineer in blanks.</NPR><BRK/>
<BRK/>
<NPR>8.  Signature of Principal of A/E firm or follow local procedures for in-house 
work. </NPR><BRK/>
<BRK/>
<NPR>9.  For Government approval.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<BRK/></PRT>
    <END/><BRK/></SEC>