<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA            UFGS-01 75 00 (October 2006)<BRK/>
                                          --------------------------------<BRK/>
Preparing Activity:  <PRA>NASA</PRA>                 Superseding<BRK/>
                                          NASA-01 75 00.00 40 (April 2006)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 01 75 00</SCN><BRK/>
<BRK/>
<STL>STARTING AND ADJUSTING</STL><BRK/>
<DTE>10/06</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This specification covers the requirements for <SCP>system testing and acceptance.</SCP></NPR><BRK/>
<BRK/>
<NPR>Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.</NPR><BRK/>
<BRK/>
<NPR>Remove information and requirements not required in respective project, whether 
or not brackets are present.</NPR><BRK/>
<BRK/>
<NPR>Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.</NPR><BRK/>
<BRK/>
<NPR>Recommended changes to a UFGS should be submitted as a <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   SUMMARY</TTL><BRK/>
<BRK/>
<TXT>Requirements of this Section apply to, and are a component part of, each section of the specifications.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review Submittal Description (SD) definitions in Section <SRF>01 33 00</SRF> SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.</NPR><BRK/>
<BRK/>
<NPR>A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.</NPR><BRK/>
<BRK/>
<NPR>For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.</NPR><BRK/>
<BRK/>
<NPR>Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  Submit the following 
in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit the following Submittals to fit the requirements of the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST><SUB>SD-01 Preconstruction Submittals</SUB></LST><BRK/>
<BRK/>
<ITM>Submit <SUB>Verification of Prior Experience</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>] and expertise with similar project 
scope</ITM><BRK/>
<BRK/>
<ITM>Submit <SUB>Documentation of Manufacturer's Prior Experience</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>] and expertise with 
similar project materials and systems</ITM><BRK/>
<BRK/>
<ITM><SUB>Quality Control Plan</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]<BRK/>
including testing and start-up schedule</ITM><BRK/>
<BRK/>
<ITM><SUB>Manufacturer's Sample Warranty</SUB> and <SUB>Operation and Maintenance Data</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Provide Evidence</SUB> that products used within this specification are manufactured in the United 
States.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
[<ITM><SUB>Drawings, Diagrams and Schedules</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>] specifically prepared to illustrate [some 
portion of the work][_____]</ITM>]<BRK/>
<BRK/>
[<ITM><SUB>Diagrams and Instructions</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>] from a manufacturer or fabricator for use in producing 
the product and as aids to the Contractor for integrating the product or system into the project</ITM>]<BRK/>
<BRK/>
[<ITM><SUB>Drawings</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>] prepared by or for the Contractor to show how multiple systems and 
interdisciplinary work will be coordinated</ITM>]<BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Catalog cuts</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>], illustrations, schedules, diagrams, performance charts, instructions 
and brochures illustrating size, physical appearance and other characteristics of materials, 
systems or equipment for some portion of the work</ITM><BRK/>
<BRK/>
<ITM><SUB>Samples of warranty language</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>] when the contract requires [extended][no dollar 
limit] product warranties</ITM><BRK/>
<BRK/>
<LST><SUB>SD-05 Design Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Design Calculations</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>], mix designs, analyses or other data pertaining to [a 
part of work][_____]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM>Submit test reports in accordance with the paragraphs entitled, "<SUB>Factory Tests</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>
]", "<SUB>Functional Field Test</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]" and "<SUB>Final Acceptance Test</SUB>,[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>
]" of this section.</ITM><BRK/>
<BRK/>
<ITM>Submit test procedures and the recording forms according to paragraph entitled, "<SUB>Test Procedures</SUB>
[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]."</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
[<ITM><SUB>Qualification of Manufacturer</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM>]<BRK/>
<BRK/>
<ITM><SUB>Qualification of [Applicator][Installer]</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Certify that the [applicator][installer] meets requirements specified under paragraph entitled 
"Qualification of [Applicator][Installer]."</ITM><BRK/>
<BRK/>
<LST><SUB>SD-08 Manufacturer's Instructions</SUB></LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit the manufacturer's instructions submission requirements as necessary 
for the system specified.  Include bracketed requirements only as applicable 
to the system being specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
[<ITM>Submit <SUB>Manufacturer's Administrative Requirements</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM>]<BRK/>
<BRK/>
[<ITM><SUB>Demonstration and Training Information</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM>]<BRK/>
<BRK/>
[<ITM>Submit <SUB>Manufacturer's Procedural Requirements</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>] for initial checkout, startup, 
and adjusting to ensure safe operation during acceptance testing and commissioning.</ITM>]<BRK/>
<BRK/>
<LST><SUB>SD-09 Manufacturer's Field Reports</SUB></LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit the manufacturer's field reports submission requirements as necessary 
for the system specified.  Include bracketed requirements only as applicable 
to the system being specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM><TST><SUB>Documentation of the Testing and Verification Actions</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>] taken by manufacturer's 
representative</TST> [at the job site][, in the vicinity of the job site][, or on a sample taken from 
the job site], on a portion of the work, [during][after] installation, to confirm compliance 
with manufacturer's standards or instructions</ITM><BRK/>
<BRK/>
<LST><SUB>SD-10 Operation and Maintenance Data</SUB></LST><BRK/>
<BRK/>
<TXT>Refer to Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE DATA for detailed requirements and procedures.</TXT><BRK/>
<BRK/>
<ITM><SUB>Operation and Maintenance Data</SUB> provided by the manufacturer to ensure the safe and efficient 
operation, maintenance and repair of the system or equipment provided.</ITM><BRK/>
<BRK/>
[<ITM><SUB>Safety and Security Data or Posters</SUB> provided by the manufacturer</ITM>]<BRK/>
<BRK/>
<SPT><TTL>1.2.1   Preconstruction and Pre-Testing Requirements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit the following testing information based on the requirements of the 
scope, equipment, and/or system.  For NASA projects, refer to the 2004 version 
of the Reliability Centered Building and Equipment Acceptance Guide (RCBEA) 
to select the recommended Predictive Testing and Inspection (PT&amp;I) procedures 
as stated in Article 2.1.<BRK/>
<BRK/>
For other UFGS members, the acceptance testing criteria may be defined by their 
respective established guidelines, and must be verified prior to editing this 
section.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The Contractor is responsible to deliver equipment and services to meet the requirements and specifications of 
their respective contract.  All equipment must be free of latent manufacturing and installation defects.  Acceptance 
criteria must be clearly defined to establish required baselines for future maintenance and life-cycle evaluations.  
The Government reserves the option to elect performance of acceptance testing by internal personnel, or a designated 
third party.  Regardless of who performs the acceptance testing, the requirements of acceptance must be met by 
the Contractor.</TXT><BRK/>
<BRK/>
<TXT>Submit the following for review and approval prior to the commencement of work and any testing, whether such 
testing is on site or elsewhere:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit the following Submittals to fit the requirements of the project 
as selected in the Submittal Article above.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM INDENT="-0.33">a.  <SUB>Verification of prior experience</SUB> and expertise with similar project scope</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  <SUB>Documentation of manufacturer's prior experience</SUB> and expertise with similar project materials 
and systems</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  <SUB>Quality control plan</SUB></ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  <SUB>Manufacturer's Sample Warranty</SUB> and <SUB>Operation and Maintenance Data</SUB>, with details regarding 
start-up procedures</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  <SUB>Manufacturer's administrative requirements</SUB></ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  <SUB>Manufacturer's procedural requirements</SUB></ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  <SUB>Demonstration and Training Information</SUB></ITM><BRK/>
<BRK/>
<TXT>Contractor must submit the following certifications:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  <SUB>Provide evidence</SUB> that products used within this specification are manufactured in the United 
States.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  <SUB>Qualification of Manufacturer</SUB>, including current licenses and insurance.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  <SUB>Qualification of [Applicator][Installer]</SUB>, including licenses and insurance.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.2   Shop Drawings and Diagrams</TTL><BRK/>
<BRK/>
<TXT>Submit the following shop drawings, record drawings, and diagrams as required to correctly execute the installation 
of the work:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit the following Submittals to fit the requirements of the project 
as selected in the Submittal Article above.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
[<ITM INDENT="-0.33">a.  <SUB>Drawings, diagrams and schedules</SUB> specifically prepared to illustrate [some portion of the 
work][_____]</ITM>]<BRK/>
<BRK/>
[<ITM INDENT="-0.33">b.  <SUB>Diagrams and instructions</SUB> from a manufacturer or fabricator for use in producing the product 
and as aids to the Contractor for integrating the product or system into the project</ITM>]<BRK/>
<BRK/>
[<ITM INDENT="-0.33">c.  <SUB>Drawings</SUB> prepared by or for the Contractor to show how multiple systems and interdisciplinary 
work will be coordinated</ITM>]<BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.3   Product and Design Data</TTL><BRK/>
<BRK/>
<TXT>Contractor must submit all product data and any <SUB>design calculations</SUB>, mix designs, analyses or other data pertaining 
to [a part of work][_____] to ensure a complete functional installation; including, but not limited to:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  <SUB>Catalog cuts</SUB>, illustrations, schedules, diagrams, performance charts, instructions and brochures 
illustrating size, physical appearance and other characteristics of materials, systems or equipment 
for some portion of the work</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  <SUB>Samples of warranty language</SUB> when the contract requires [extended][no dollar limit] product 
warranties</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  <SUB>Operation and Maintenance Data</SUB> provided by the manufacturer to ensure the safe and efficient 
operation, maintenance and repair of the system or equipment provided.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  <SUB>Safety and Security Data or posters</SUB> provided by the manufacturer to be posted in a conspicuous 
visible location for operational and maintenance personnel.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.4   Tests Required</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit the following testing information based on the requirements of the 
scope, equipment, and/or system.  Clearly define the acceptance criteria testing 
parameters and the recommended Predictive Testing and Inspection (PT&amp;I) 
procedures.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Perform tests to verify proper functioning of fire protection, fire suppression, HVAC, compressed air, electrical 
switchgear, protective relaying, fluid and gas systems, pump/motor combinations, boiler systems, hydraulic and 
pneumatic control, condition/performance monitoring systems, energy control and monitoring systems, and other 
assemblies and components that need to be tested as an interrelated whole.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.2.4.1   <TST><SUB>Factory Tests</SUB></TST></TTL><BRK/>
<BRK/>
<TXT>Submit certified copies of required tests performed at the factory to verify proper build.  These test results 
will be used in the "Final Acceptance Test" section to verify no shipping damage and proper installation.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.4.2   <TST><SUB>Functional Field Test</SUB></TST></TTL><BRK/>
<BRK/>
<TXT>Contractor must perform functional field tests test to verify that the system and components have been properly 
installed and are functioning properly.  Perform test(s) in the presence of the Contracting Officer.  Acceptance 
will be issued when system has performed per other sections and referenced industry standards.</TXT><BRK/>
<BRK/>
<TXT>Coordinate and submit <TST><SUB>documentation of the testing and verification actions</SUB> taken by manufacturer's representative</TST>
 [at the job site][, in the vicinity of the job site][, or on a sample taken from the job site], on a portion 
of the work, [during][after] installation, to confirm compliance with manufacturer's standards or instructions.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.4.3   <TST><SUB>Final Acceptance Test</SUB></TST></TTL><BRK/>
<BRK/>
<TXT>Perform a formal test with full documentation using the approved recording form.  Contracting Officer will witness 
this test and issue a written final acceptance.  Provide final test data to the Contracting Officer with a cover 
letter clearly marked with the system name, date, and the words " Final Test Data - Forward to the Systems Engineer/Condition 
Monitoring Office/Predictive Testing Group for inclusion in the Maintenance Database."</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.4.4   <SUB>Test Procedures</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test procedure and recording forms that document the test steps for approval to the Contracting Officer 
21 calendar days prior to the proposed test date.  Procedure must clearly state step by step instruction to verify 
system parameters, components, and functions.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT></PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<TXT>Not Used</TXT><BRK/>
<NED/><BRK/></PRT>
<PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<TXT>Not Used</TXT><BRK/>
<BRK/></PRT>
    <END/><BRK/></SEC>