USACE / NAVFAC / AFCESA / NASA                  UFGS-02 56 14 (April 2006)<BRK/>
                                                --------------------------<BRK/>
Preparing Activity:  <PRA>USACE</PRA>                      Replacing without change<BRK/>
                                                UFGS-02377 (August 2004)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 02 56 14</SCN><BRK/>
<BRK/>
<STL>CLAY BARRIER LAYER</STL><BRK/>
<DTE>04/06</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>construction of 
a clay barrier layer to isolate contaminated material from the environment</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification.  The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
<BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
<BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM D 1140</RID><RTL>(2000; R 2006) Amount of Material in Soils Finer than the No. 200 (75-micrometer) Sieve</RTL><BRK/><BRK/><RID>ASTM D 1556</RID><RTL>(2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method</RTL><BRK/><BRK/><RID>ASTM D 1557</RID><RTL>(2007) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)</RTL><BRK/><BRK/><RID>ASTM D 1587</RID><RTL>(2008) Thin-Walled Tube Sampling of Soils for Geotechnical Purposes</RTL><BRK/><BRK/><RID>ASTM D 2167</RID><RTL>(2008) Density and Unit Weight of Soil in Place by the Rubber Balloon Method</RTL><BRK/><BRK/><RID>ASTM D 2216</RID><RTL>(2005) Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass</RTL><BRK/><BRK/><RID>ASTM D 2488</RID><RTL>(2006) Description and Identification of Soils (Visual-Manual Procedure)</RTL><BRK/><BRK/><RID>ASTM D 3740</RID><RTL>(2008) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction</RTL><BRK/><BRK/><RID>ASTM D 422</RID><RTL>(1963; R 2007) Particle-Size Analysis of Soils</RTL><BRK/><BRK/><RID>ASTM D 4220</RID><RTL>(1995; R 2007) Preserving and Transporting Soil Samples</RTL><BRK/><BRK/><RID>ASTM D 4318</RID><RTL>(2005) Liquid Limit, Plastic Limit, and Plasticity Index of Soils</RTL><BRK/><BRK/><RID>ASTM D 5084</RID><RTL>(2003) Measurement of Hydraulic Conductivity of Saturated Porous Materials Using a Flexible Wall Permeameter</RTL><BRK/><BRK/><RID>ASTM D 6938</RID><RTL>(2007a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)</RTL><BRK/><BRK/><RID>ASTM D 698</RID><RTL>(2007e1) Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/cu. ft. (600 kN-m/cu. m.))</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   UNIT PRICES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete this paragraph when work is covered by a lump-sum contract price.  
Weight measurement may be used to supplement volume measurement surveys if significant 
subgrade settlement (landfill cover applications) is anticipated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Measurement and payment for the clay barrier layer shall be based on the unit price schedule for each<MET> cubic meter</MET><ENG>
 cubic yard</ENG> of clay in place.  This unit price shall include the cost for development of the clay borrow source, 
cost of clay, excavation, hauling, equipment, placement, testing, and other incidental work required to construct 
the clay barrier layer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy, Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for [Contractor Quality Control approval.][information only.  When used, a designation following the "G" 
designation identifies the office that will review the submittal for the Government.]  The following shall be 
submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Protection</SUB></ITM><BRK/>
<ITM><SUB>Equipment</SUB></ITM><BRK/>
<BRK/>
<ITM>  Materials Handling Plan describing the following:  processing and placement of the clay; type, 
model number, weight and critical dimensions of equipment to be used for soil processing, compaction, 
scarification, and smooth rolling; method of protecting clay from changes in moisture content 
and freezing after placement.</ITM><BRK/>
<BRK/>
<ITM><SUB>Commercial Testing Laboratory</SUB></ITM><BRK/>
<BRK/>
<ITM>  Name and qualifications of the proposed commercial testing laboratory.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-04 Samples</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Clay</SUB></ITM><BRK/>
<ITM><SUB>Quality Assurance Samples</SUB></ITM><BRK/>
<BRK/>
<ITM>  A minimum of<MET> 46 kg</MET><ENG> 100 pounds</ENG> of each principal type of material or combination of materials 
to the Government's designated laboratory at least [30] [_____] days prior to placement.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Borrow Source Assessment</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<ITM><SUB>Assessment Tests</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<ITM><SUB>Moisture Content and Density Tests of In-Place Clay</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<ITM><SUB>Hydraulic Conductivity Tests of In-Place Clay</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Borrow Source Assessment Report at least [15] [_____] days prior to clay placement.  No clay 
shall be placed until the Borrow Source Assessment Report is approved.  The report shall include 
the following: location of each borrow source; plan view and estimated available quantity of 
clay; locations and logs of subsurface explorations; laboratory test results; moisture-density 
curves showing the "Acceptable Zone" of moisture contents and densities which achieve the required 
hydraulic conductivity for each principal type of material or combination of materials.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4   <SUB>EQUIPMENT</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  A soil stabilizer or road regrader is often specified for use on soils 
that have clods or particles which are difficult to reduce to an acceptable 
size.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Equipment used to place the clay barrier layer shall not brake suddenly, turn sharply, or be operated at speeds 
exceeding<MET> 8 km</MET><ENG> 5.0 miles</ENG> per hour.<BRK/>
<BRK/></TXT>
<SPT><TTL>1.4.1   Compaction Equipment</TTL><BRK/>
<BRK/>
<TXT>Compaction equipment shall consist of tamping foot rollers which have a minimum weight of<MET> 18,140 kg</MET><ENG> 40,000 pounds</ENG>
.  At least one tamping foot shall be provided for each<MET> 71,000 square mm</MET><ENG> 110 square inches</ENG> of drum surface.  
The length of each tamping foot, from the outside surface of the drum, shall be equal to or greater than the 
loose lift thickness.  During compaction operations, the spaces between the tamping feet shall be maintained 
clear of materials which would impair the effectiveness of the tamping foot rollers.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.2   Scarification Equipment</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Tamping foot rollers create a roughened surface on each lift of clay.  
The designer must determine if scarification is required to further roughen 
the surface of the clay layer prior to placement of additional lifts of clay.  
If additional scarification is not required, omit this paragraph and other references 
to scarification throughout this section.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Disks, rotor tillers, or other approved means shall be provided to scarify the surface of each lift of clay prior 
to placement of the next lift.  The scarification equipment shall be capable of uniformly disturbing the upper<MET>
 25 mm</MET><ENG> 1 inch</ENG> of the clay surface to provide good bonding between lifts.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.3   Steel Wheeled Rollers</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The upper surface of the clay layer must be smooth rolled if a geosynthetic 
will be placed on top of the clay layer.  Remove this paragraph and all other 
references to smooth rolling if a geosynthetic will not be placed on top of 
the clay layer.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>A smooth, non-vibratory steel wheeled roller shall be used to produce a smooth compacted surface on the clay 
barrier layer.  Steel wheeled rollers shall weigh a minimum of<MET> 9,070 kg</MET><ENG> 20,000 pounds</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.4   Hand Operated Tampers</TTL><BRK/>
<BRK/>
<TXT>Hand operated tampers shall consist of rammers or other impact type equipment.  Vibratory type equipment will 
not be allowed.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   <SUB>CLAY</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The physical criteria listed in Table 1 are minimum requirements.  More 
restrictive criteria may be appropriate depending on local soils.  For composite 
geomembrane/clay covers and liners, the maximum particle size should be reduced 
to 12.5 mm (0.5 inches) in the upper lift of clay layer to prevent puncturing 
of the geomembrane.</NPR><BRK/>
<BRK/>
<NPR>Bentonite is often added to soils that do not contain enough clay to achieve 
the desired hydraulic conductivity.  Refer to EPA/600/R-93/182 - Quality Assurance 
and Quality Control for Waste Containment Facilities if bentonite will be used 
as an additive to the available soils.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Clay shall be free of roots, debris, organic or frozen material, and shall have a maximum clod size of<MET> 50 mm</MET><ENG> 
2 inches</ENG> at the time of compaction.  Clay material shall comply with the criteria listed in Table 1.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>TABLE 1</HL4><BRK/>
<HL4>REQUIRED PHYSICAL PROPERTIES OF CLAY</HL4><BRK/>
<BRK/>
                                      Test            Test<BRK/>
       Property                       Value           Method<BRK/>
       ________                       ______          ______<BRK/></THD>
<BRK/>
Max. particle size (mm)                25       <RID>ASTM D 422</RID><BRK/>
Min. percent passing 4.75 mm sieve     80       <RID>ASTM D 422</RID><BRK/>
Min. percent passing 0.075 mm sieve    50       <RID>ASTM D 1140</RID><BRK/>
Min. liquid limit                      35       <RID>ASTM D 4318</RID><BRK/>
Min. plasticity index                  10       <RID>ASTM D 4318</RID><BRK/>
Max. plasticity index                  40       <RID>ASTM D 4318</RID><BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>TABLE 1</HL4><BRK/>
<HL4>REQUIRED PHYSICAL PROPERTIES OF CLAY</HL4><BRK/>
<BRK/>
                                      Test            Test<BRK/>
       Property                       Value          Method<BRK/>
       ________                       ______         _______<BRK/></THD>
<BRK/>
Max. particle size (inches)             1       <RID>ASTM D 422</RID><BRK/>
Min. percent passing No. 4 sieve       80       <RID>ASTM D 422</RID><BRK/>
Min. percent passing No. 200 sieve     50       <RID>ASTM D 1140</RID><BRK/>
Min. liquid limit                      35       <RID>ASTM D 4318</RID><BRK/>
Min. plasticity index                  10       <RID>ASTM D 4318</RID><BRK/>
Max. plasticity index                  40       <RID>ASTM D 4318</RID><BRK/></TBL>
</ENG><BRK/></SPT>
</PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   <SUB>BORROW SOURCE ASSESSMENT</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Shear strength testing is often required for landfill covers and liners 
placed on steep slopes which contain geosynthetics.  Criteria for shear strength 
testing is described in Section 02 56 13 WASTE CONTAINMENT GEOMEMBRANE or Section 
02 56 15 GEOSYNTHETIC CLAY LINER (GCL).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Borrow source <SUB>assessment tests</SUB> shall be performed on each principal type or combination of materials proposed 
for use in the clay barrier layer to assure compliance with specified requirements and to develop compaction 
requirements for placement.  A minimum of one set of borrow assessment tests shall be performed for each borrow 
source proposed.  A set of borrow source assessment tests shall consist of classification testing, moisture-density 
(compaction) testing, and hydraulic conductivity testing.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.1   Classification Testing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Test pits should be used, if possible, because they provide a better 
method of characterizing borrow sources than borings.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Test pits] [Borings] placed in a grid pattern shall be used to characterize each proposed borrow source.  The 
[test pits] [borings] shall extend to the full depth of the proposed borrow source.  Visual classification as 
described in <RID>ASTM D 2488</RID> shall be performed over the full depth of each [test pit] [boring] by a [qualified] 
[registered] geologist or geotechnical engineer.  Soils shall be grouped into "principal types" based on visual 
classification.  Classification testing shall be performed on representative samples of each principal type or 
combination of materials.  At a minimum, one set of classification tests shall be performed per<MET> 5000 cubic meters</MET><ENG>
 6500 cubic yards</ENG> of proposed borrow.  Classification testing shall consist of liquid and plastic limits in accordance 
with <RID>ASTM D 4318</RID> and particle size analysis in accordance with <RID>ASTM D 422</RID>.  Moisture content testing of proposed 
borrow shall be performed at a frequency of once per<MET> 2000 cubic meters</MET><ENG> 2600 cubic yards</ENG> in accordance with <RID>ASTM D 2216</RID>
.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2   Compaction Testing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  A minimum of two compaction efforts are recommended to adequately define 
the relationship between moisture-density and hydraulic conductivity.  A reduced 
compaction procedure may also be used.  The reduced compaction procedure is 
the same as ASTM D 698 except 15 drops of the hammer per lift are used instead 
of 25.  The reduced compactive effort is expected to correspond to a reasonable 
minimum level of compactive energy for a typical soil liner or cover.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>A representative sample from each principal type or combination of borrow materials shall be tested to establish 
compaction curves using [_____], <RID>ASTM D 698</RID> and <RID>ASTM D 1557</RID>.  A minimum of one set of compaction curves shall 
be developed per<MET> 5,000 cubic meters</MET><ENG> 6,500 cubic yards</ENG> of each proposed borrow material.  A minimum of [5] [_____] 
points shall be used to develop each compaction curve.  The compaction curves for each principal type or combination 
of borrow materials shall be plotted on a single graph of dry density versus moisture content.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3   Hydraulic Conductivity Testing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  When performing hydraulic conductivity testing, the average effective 
confining pressure should be representative of post construction conditions.  
The minimum effective confining pressure should be equal to or greater than 
21 kpa (3 psi) to avoid side wall leakage.</NPR><BRK/>
<BRK/>
<NPR>If the clay layer will be placed beneath hazardous waste, chemical compatibility 
testing may be appropriate.  Chemical compatibility testing consists of performing 
hydraulic conductivity tests on the clay liner material using a representative 
leachate sample as the permeant.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>A set of hydraulic conductivity tests shall be performed on representative samples of each principal type or 
combination of borrow materials.  A minimum of one set of tests shall be performed per<MET> 5,000 cubic meters</MET><ENG> 6,500 
cubic yards</ENG> of proposed borrow material.  A set of tests shall consist of one hydraulic conductivity test run 
on a representative sample corresponding to each point from each compaction curve at or above <RID>ASTM D 1557</RID> optimum 
moisture content.  Hydraulic conductivity testing referenced in this section shall be conducted in accordance 
with <RID>ASTM D 5084</RID>.  In addition, the following procedures shall be adhered to when performing the hydraulic conductivity 
testing:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Saturation of test specimens shall be verified by determination of the B coefficient.  The 
B coefficient must be at least 0.95.  The B coefficient is defined as the change in pore water 
pressure divided by the change in confining pressure.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  During consolidation of the test specimens, outflow volumes versus time shall be recorded 
on a semi-log graph to confirm primary consolidation has been completed prior to permeation 
of the specimens.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  The permeant used for back pressure saturation and permeation shall be 0.01 molar calcium 
chloride solution created from deaired, distilled water as specified in <RID>ASTM D 5084</RID>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  The average effective confining pressure shall be [_____]<MET> kPa</MET><ENG> psi</ENG>.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.4   Acceptable Zone Development</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Additional testing may be required to determine the "Acceptable Zone" 
based on shear strength considerations.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>An "Acceptable Zone" of moisture contents and densities shall be developed and displayed with the compaction 
curve graphs for each principal type of borrow material or combination of borrow materials.  The "Acceptable 
Zone" shall consist of moisture-density values that meet the following requirements:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Maximum Allowable Hydraulic Conductivity = [1 x 10 to the -7 cm per second] [_____].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  The minimum allowable moisture content shall be no less than [optimum moisture content] 
[_____] based on <RID>ASTM D 1557</RID>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  The minimum allowable density shall be no less than [90] [_____] percent of maximum dry 
density based on <RID>ASTM D 698</RID>.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.5   Chemical Contamination Testing</TTL><BRK/>
<BRK/>
<TXT>Borrow used for the clay barrier layer shall be free of contamination.  Each proposed borrow source shall be 
sampled and analyzed for chemical contamination in accordance with Section <SRF>01 35 45.00 10</SRF> CHEMICAL DATA QUALITY 
CONTROL.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.6   <SUB>Commercial Testing Laboratory</SUB></TTL><BRK/>
<BRK/>
<TXT>Tests for the clay barrier layer shall be performed by an approved testing laboratory furnished by the Contractor.  
No testing will be permitted until the facilities have been inspected and approved.  The inspection will be performed 
to determine if the laboratory has a quality system in place for personnel, equipment, reporting procedures, 
record keeping, and equipment calibration that ensures the laboratory is capable of accurately performing the 
specified testing.  The quality system shall be in accordance with <RID>ASTM D 3740</RID> or as approved by the Government 
Inspector.  The first inspection will be at the Government's expense.  Cost incurred for subsequent inspections 
required because of deficiencies found during the first inspection will be charged to the Contractor.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2   INSTALLATION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.1   Clay Placement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Verify subgrade requirements are covered in another section of the specification 
package.  The subgrade must provide adequate support for compaction of the clay 
barrier layer.</NPR><BRK/>
<BRK/>
<NPR>For clay barrier layers placed above geosynthetics, require the placement and 
compaction equipment work from the base of the slope up to prevent damage to 
underlying geosynthetics.</NPR><BRK/>
<BRK/>
<NPR>Clay is generally placed parallel to the direction of maximum slope.  Clay placement 
parallel to the slope becomes difficult on slopes steeper than 3 horizontal 
on 1 vertical.  Horizontal lifts should be considered for clay placement on 
slopes steeper than 3 horizontal on 1 vertical.</NPR><BRK/>
<BRK/>
<NPR>The U.S. Environmental Protection Agency document, EPA/600/R-93/182 Quality 
Assurance and Quality Control for Waste Containment Facilities discourages the 
use of grade stakes which penetrate the clay layer to control lift thickness.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Clay shall be placed to the lines and grades shown on the drawings.  The clay shall be placed in loose lifts 
not to exceed<MET> 200 mm</MET><ENG> 8 inches</ENG> in thickness.  In areas where hand operated tampers must be used, the loose lift 
thickness shall not exceed<MET> 100 mm</MET><ENG> 4 inches</ENG>.  [Grade stakes shall not be driven into the clay layer.]  [If grade 
stakes are driven into the clay layer to control lift thickness, they shall be numbered and accounted for at 
the end of each shift.  When removing grade stakes, no broken portion of the grade stakes shall be left in the 
clay layer.  Holes left by grade stakes shall be backfilled and compacted.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.2   Moisture Control</TTL><BRK/>
<BRK/>
<TXT>Clay shall be placed and compacted within the "Acceptable Zone" moisture content range in the approved Borrow 
Source Assessment Report.  The moisture content shall be maintained uniform throughout each lift.  Water added 
shall be thoroughly incorporated into the clay to ensure uniformity of moisture content prior to compaction.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.3   Compaction</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Special compaction procedures are required if geosynthetic layers are 
located immediately beneath the clay layer.  The minimum initial lift thickness 
over geosynthetic layers is typically 300 mm (12 inches).  This lift of soil 
is typically placed with low ground pressure track mounted equipment with a 
track pressure of 21 to 41 kPa (3 to 6 psi).  No compaction requirements are 
generally specified for this first lift of clay.</NPR><BRK/>
<BRK/>
<NPR>For clay barrier layers placed on soft subgrades, lighter equipment and the 
relaxation or elimination of compaction criteria is often specified for the 
first lift of clay.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Clay shall be compacted to meet the density requirements in the approved Borrow Source Assessment Report and 
by at least [5] [_____] passes of the approved compaction equipment over all areas of each lift.  For self-propelled 
compactors, one pass is defined as one pass of the entire vehicle.  For towed rollers, one pass of the drum constitutes 
a pass.  Hand operated tampers shall be used in areas where standard compaction equipment cannot be operated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.4   Scarification</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For geomembrane/clay composites, the final lift of clay is generally 
smooth rolled instead of being scarified to allow intimate contact between the 
clay surface and the overlying geomembrane.  Smooth rolling also helps to prevent 
desiccation during delays in construction.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Scarification shall be performed on all areas of the upper surface of each clay lift prior to placement of the 
next lift.  Scarification shall be accomplished with approved equipment.  The final lift of clay shall not be 
scarified.  The final lift shall be smooth rolled with at least [3] [_____] passes of the approved smooth steel 
wheeled roller to provide a smooth surface with no ridges or depressions.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.5   Repair of Voids</TTL><BRK/>
<BRK/>
<TXT>Voids created in the clay barrier layer during construction (including, but not limited to, penetrations for 
test samples, grade stakes, and other penetrations necessary for construction) shall be repaired by removing 
sand or other non-clay material, placing clay backfill in lifts no thicker than<MET> 76 mm</MET><ENG> 3 inches</ENG> and tamping each 
lift with a steel rod.  Each lift shall be tamped a minimum of 25 times altering the location of the rod within 
the void for each blow.  Other ruts and depressions in the surface of the lifts shall be scarified, filled, and 
then compacted to grade.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.3   CONSTRUCTION TOLERANCES</TTL><BRK/>
<BRK/>
<TXT>The top surface of the clay barrier layer shall be no greater than<MET> [76] [_____] mm</MET><ENG> [3] [_____] inches</ENG> above the 
lines and grades shown on the drawings.  No minus tolerance will be permitted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4   CONSTRUCTION TESTS</TTL><BRK/>
<BRK/>
<SPT><TTL>3.4.1   Clay Material Tests</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The definition of unclassified materials must be determined on a site 
specific basis.  Unclassified materials are typically defined using Atterberg 
limits, grain size distribution, or compaction testing.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>During construction of the clay barrier layer, representative samples shall be taken for testing at the frequencies 
listed in Table 2 [from the borrow source] [from onsite stockpiles] [after a loose lift of clay has been placed] 
[_____].  Test results shall meet the requirements listed in Table 1.  Unclassified material shall be defined 
as follows:  [_____].  Where test results indicate an unclassified material type, additional testing shall be 
performed as described in paragraph BORROW SOURCE ASSESSMENT.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>TABLE 2</HL4><BRK/>
<HL4>CLAY MATERIAL PROPERTIES</HL4><BRK/>
<BRK/>
                                                      Test<BRK/>
  Property                          Frequency        Method<BRK/>
  ________                          _________        ______<BRK/></THD>
<BRK/>
Particle size analysis           800 cubic meters  <RID>ASTM D 422</RID><BRK/>
(Note 1)<BRK/>
Atterberg limits                 800 cubic meters  <RID>ASTM D 4318</RID><BRK/>
(Note 1)<BRK/>
Compaction                     5,000 cubic meters  <RID>ASTM D 698</RID><BRK/>
(Note 2)<BRK/></TBL>
</MET><BRK/>
<TXT>Note 1:  At least one test shall be performed each day that soil is placed.<BRK/>
Note 2:  Compaction test results shall be compared to previous results on the same material type to verify the 
compaction characteristics have remained the same.</TXT><ENG><TBL><THD><BRK/>
<HL4>TABLE 2</HL4><BRK/>
<HL4>CLAY MATERIAL PROPERTIES</HL4><BRK/>
<BRK/>
                                                      Test<BRK/>
  Property                          Frequency        Method<BRK/>
  ________                          _________        ______<BRK/></THD>
<BRK/>
Particle size analysis         1,000 cubic yards   <RID>ASTM D 422</RID><BRK/>
(Note 1)<BRK/>
Atterberg limits               1,000 cubic yards   <RID>ASTM D 4318</RID><BRK/>
(Note 1)<BRK/>
Compaction                     6,500 cubic yards   <RID>ASTM D 698</RID><BRK/>
(Note 2)<BRK/></TBL>
</ENG><BRK/>
<TXT>Note 1:  At least one test shall be performed each day that soil is placed.<BRK/>
Note 2:  Compaction test results shall be compared to previous results on the same material type to verify the 
compaction characteristics have remained the same.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2   <SUB>Moisture Content and Density Tests of In-Place Clay</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>Note:  Test results using ASTM D 6938 may show a significant amount of scatter 
in some situations.  ASTM D 4643 (microwave method) can be used as an alternative 
to ASTM D 6938 for quick determinations of moisture content.</NPR><BRK/>
<BRK/>
<NPR>Density and hydraulic conductivity testing requirements are often waived for 
the first lift of clay placed on a soft subgrade or above a geosynthetic layer 
which could be damaged by compaction equipment.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Moisture content and density tests shall be performed in a grid pattern.  The grid pattern shall be staggered 
for successive lifts so that sampling points are not at the same location in each lift.  Moisture content and 
density tests shall be performed in accordance with Table 3.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>TABLE 3</HL4><BRK/>
<HL4>MOISTURE CONTENT AND DENSITY TESTS OF IN-PLACE CLAY</HL4><BRK/>
<BRK/>
                                                       Test<BRK/>
  Property                        Frequency           Method<BRK/>
                                  Per Lift<BRK/>
  ________                        _________           ______<BRK/></THD>
<BRK/>
Rapid Moisture Content        800 square meters   <RID>ASTM D 6938</RID><BRK/>
<BRK/>
Standard Moisture Content     1 for every         <RID>ASTM D 2216</RID><BRK/>
                              10 rapid tests<BRK/>
<BRK/>
Rapid Density                 800 square meters   <RID>ASTM D 6938</RID><BRK/>
<BRK/>
Standard Density              1 for every         <RID>ASTM D 1556</RID> or<BRK/>
                              20 rapid tests      <RID>ASTM D 2167</RID><BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>TABLE 3</HL4><BRK/>
<HL4>MOISTURE CONTENT AND DENSITY TESTS OF IN-PLACE CLAY</HL4><BRK/>
<BRK/>
                                                       Test<BRK/>
  Property                        Frequency           Method<BRK/>
                                  Per  Lift<BRK/>
  ________                        _________           ______<BRK/></THD>
<BRK/>
Rapid Moisture Content        8,500 square feet   <RID>ASTM D 6938</RID><BRK/>
<BRK/>
Standard Moisture Content     1 for every         <RID>ASTM D 2216</RID><BRK/>
                              10 rapid tests<BRK/>
<BRK/>
Rapid Density                 8,500 square feet   <RID>ASTM D 6938</RID><BRK/>
<BRK/>
Standard Density              1 for every         <RID>ASTM D 1556</RID> or<BRK/>
                              20 rapid tests      <RID>ASTM D 2167</RID></TBL></ENG><BRK/>
<BRK/>
<SPT><TTL>3.4.2.1   Rapid Tests</TTL><BRK/>
<BRK/>
<TXT>Each day that clay is compacted, a minimum of one set of moisture content and density tests shall be performed 
using standard procedures.  Rapid tests shall be checked at the frequencies shown in Table 3.  Standard tests 
shall be performed at locations which are as close as possible to the location of the rapid tests being checked.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2.2   Nuclear Density and Moisture Content Tests</TTL><BRK/>
<BRK/>
<TXT>Nuclear density readings shall be taken in the direct transmission mode.  When <RID>ASTM D 6938</RID> is used, the calibration 
curves shall be checked and adjusted using only the sand cone method as described in <RID>ASTM D 1556</RID>.  <RID>ASTM D 6938</RID>
 results in a wet unit weight of soil and when using this method <RID>ASTM D 6938</RID> shall be used to determine the moisture 
content of the soil.  The calibration curves furnished with the moisture gauges shall also be checked along with 
density calibration checks as described in <RID>ASTM D 6938</RID>; the calibration checks of both the density and moisture 
gauges shall be made at the beginning of a job on each different type of material encountered and at intervals 
as directed by the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2.3   Test Results</TTL><BRK/>
<BRK/>
<TXT>The field moisture content and density test results shall be plotted on the "Acceptable Zone" plot that corresponds 
to the appropriate material type being tested.  If test results are not within the "Acceptable Zone" for moisture 
content or density, [3] [_____] additional tests shall be performed near the location of the failed parameter.  
If all retests pass, no additional action shall be taken.  If any of the retests fail, the lift of soil shall 
be repaired out to the limits defined by passing tests for that parameter.  The area shall then be retested as 
directed.  Repairs to the clay layer shall be documented including location and volume of soil affected, corrective 
action taken, and results of retests.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.4.3   <SUB>Hydraulic Conductivity Tests of In-Place Clay</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Laboratory hydraulic conductivity tests constitute a major inconvenience 
because the tests usually take several days to perform.  For this reason, the 
use of laboratory hydraulic conductivity tests should be minimized or eliminated 
if possible.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Undisturbed samples shall be taken for hydraulic conductivity testing at a frequency of once per<MET> 3,720 square 
meters</MET><ENG> 40,000 square feet</ENG> for each lift of clay placed.  Samples shall be cut from the lift in accordance with <RID>
ASTM D 1587</RID> and transported in the vertical position in accordance with <RID>ASTM D 4220</RID>, Group C.  Each undisturbed 
sample shall be tested for hydraulic conductivity in accordance with <RID>ASTM D 5084</RID>, [moisture content in accordance 
with <RID>ASTM D 2216</RID>], [particle size analysis in accordance with <RID>ASTM D 422</RID>], and [liquid and plastic limits in 
accordance with <RID>ASTM D 4318</RID>].  Hydraulic conductivity testing shall be conducted in accordance with the requirements 
in paragraph Hydraulic Conductivity Testing.  If any test result is greater than the "Maximum Allowable Hydraulic 
Conductivity", modifications shall be proposed and approved for future placement of clay of that type.  If the 
hydraulic conductivity of any test is more than one-half of one order of magnitude greater than the "Maximum 
Allowable Hydraulic Conductivity",[3] [_____] additional tests shall be performed near the location of the original 
failed test.  If all retests pass, no additional action shall be taken.  If any of the retests fail, the area 
shall be repaired out to the limits defined by passing hydraulic conductivity tests.  The area shall then be 
retested as directed.  Repairs to the clay layer shall be documented including location and volume of soil affected, 
corrective action taken, and results of retests.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.4   <SUB>Quality Assurance Samples</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Remove or modify this paragraph if the quality assurance laboratory will 
not perform hydraulic conductivity testing.  On some projects, the Contractor 
is also tasked to periodically provide samples of borrow soil to the quality 
assurance laboratory for classification testing.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Quality assurance samples shall be taken at locations as directed.  Samples shall be taken at a frequency of 
once per [_____]<MET> square meters</MET><ENG> square feet</ENG> for each lift of clay placed.  Samples shall be cut from the lift 
in accordance with <RID>ASTM D 1587</RID> and shipped in the vertical position in accordance with <RID>ASTM D 4220</RID>, Group C.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5   <SUB>PROTECTION</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>3.5.1   Moisture Content</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Smooth rolling or other measures may be necessary to limit moisture loss 
and/or promote run-off of surface water.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>After placement, moisture content shall be maintained or adjusted to meet the acceptable zone criteria.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2   Erosion</TTL><BRK/>
<BRK/>
<TXT>Erosion that occurs in the clay layer shall be repaired and grades re-established.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.3   Freezing and Desiccation</TTL><BRK/>
<BRK/>
<TXT>Freezing and desiccation of the clay layer shall be prevented.  If freezing or desiccation occurs, the affected 
soil shall be removed or reconditioned as directed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.4   Retests</TTL><BRK/>
<BRK/>
<TXT>Areas that have been repaired shall be retested as directed.  Repairs to the clay layer shall be documented including 
location and volume of soil affected, corrective action taken, and results of retests.</TXT><BRK/>
<BRK/></SPT>