<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA          UFGS-03 41 33 (August 2008)<BRK/>
                                        ----------------------------------<BRK/>
Preparing Activity:  <PRA>NASA</PRA>               Superseding<BRK/>
                                        UFGS-03 41 33.00 40 (January 2008)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 03 41 33</SCN><BRK/>
<BRK/>
<STL>PRECAST STRUCTURAL PRETENSIONED CONCRETE</STL><BRK/>
<DTE>08/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This specification covers the requirements for <SCP>fabrication and erection 
of precast structural concrete framing elements, floor units, and roof units 
for buildings</SCP> including, as required by the project, the following:.</NPR><BRK/>
<BRK/>
<NPR>Precast conventionally reinforced concrete floor and roof units for clear spans 
up to<MET> 10.5 meter</MET><ENG> 35 feet</ENG></NPR><BRK/>
<BRK/>
<NPR>Precast conventionally reinforced concrete columns, joists, beams, and other 
structural framing elements.</NPR><BRK/>
<BRK/>
<NPR>Precast prestressed concrete single- and double-tee slabs, hollow-cored flat 
slabs, tee- or keystone- joists, columns, and other structural elements</NPR><BRK/>
<BRK/>
<NPR>Precast concrete cellular floor units with cells suitable for use as electrical 
raceways</NPR><BRK/>
<BRK/>
<NPR>Drawings must include a complete design indicating the character of the work 
to be performed and giving the following:</NPR><BRK/>
<BRK/>
<NPR>Assumed loads, including floor live load, roof live load, wind load, concentrated 
loads such as partitions, and equipment mounted on or suspended from precast 
concrete construction, concrete floor topping weight, and other design data 
as may be required for the proper preparation of shop drawings</NPR><BRK/>
<BRK/>
<NPR>Layout of the framing system indicating the relative location of the various 
precast structural concrete sections, floor elevations, column centers and offsets, 
openings, and sufficient dimensions to adequately convey the quantity and nature 
of the required precast structural concrete framing system</NPR><BRK/>
<BRK/>
<NPR>Details of all precast structural concrete sections indicating cross-sections 
and dimensions</NPR><BRK/>
<BRK/>
<NPR>Location of precast structural concrete sections having an architectural finish 
on exposed-to-view surfaces when required</NPR><BRK/>
<BRK/>
<NPR>Details of reinforcement indicating reinforcing-bar schedules; location and 
size of welded-wire fabric; and tenons for prestressed concrete indicating the 
final stressing force in kips, as required</NPR><BRK/>
<BRK/>
<NPR>Details of connections indicating end bearing minimums and anchorage devices 
and other items embedded in the precast structural concrete sections</NPR><BRK/>
<BRK/>
<NPR>Location and details of concrete floor topping, when required</NPR><BRK/>
<BRK/>
<NPR>Details of openings including the size of steel framing members as required</NPR><BRK/>
<BRK/>
<NPR>Details of precast concrete filler blocks, as required</NPR><BRK/>
<BRK/>
<NPR>Details of hangers for suspended ceilings, ducts, piping, lighting fixtures, 
conduit, or other construction, as required</NPR><BRK/>
<BRK/>
<NPR>Precast concrete floor-unit cells that will be used for electrical raceways, 
when required</NPR><BRK/>
<BRK/>
<NPR>When both fire-resistance-rated construction and nonrated construction are required, 
the location of fire-resistance-rated construction</NPR><BRK/>
<BRK/>
<NPR>Cast-in-place normal-weight concrete, including concrete floor topping, is specified 
in Section <SRF>03 30 53</SRF> MISCELLANEOUS CAST-IN-PLACE CONCRETE.</NPR><BRK/>
<BRK/>
<NPR>Precast conventionally reinforced concrete wall panels, solid-section type, 
are specified in Section <SRF>03 45 00.00 40</SRF> PRECAST ARCHITECTURAL CONCRETE.</NPR><BRK/>
<BRK/>
<NPR>Precast-concrete roof slabs placed over purlings or joists spaced not more than 
8 feet on center are specified in Section <SRF>03 41 16</SRF> PRECAST CONCRETE SLABS (MAX. 
SPAN 8' - 0" 0.C).</NPR><BRK/>
<BRK/>
<NPR>Sealing joints in exposed-to-view surfaces of precast concrete slabs, such as 
at ceilings and walls, is specified in Section <SRF>07 92 00</SRF> JOINT SEALANTS.</NPR><BRK/>
<BRK/>
<NPR>Painting exposed-to-view surfaces of precast concrete units such as ceilings, 
is specified in Section <SRF>09 90 00.00 40</SRF> PAINTING AND COATING.</NPR><BRK/>
<BRK/>
<NPR>When cells of precast concrete cellular floor units will be used for electrical 
raceways, the inspection of cells to be used for electrical raceways, cutting 
the floor units for inserts, and electrical raceway fittings are specified in 
Section <SRF>26 05 00.00 40</SRF> COMMON WORK RESULTS FOR ELECTRICAL.</NPR><BRK/>
<BRK/>
<NPR>Fire-resistance-rated construction using precast structural concrete sections 
is described in Underwriters Laboratories, Inc., "Fire Resistance Ratings (BXUV)" 
included in UL Fire Resistance Directory and the "Fire-Resistance Ratings" contained 
in AIA CO-1. Fire-resistance-rated construction limits the types of precast 
structural concrete sections; the requirements for end restraint; the concrete 
materials and proportions of concrete mix for floor top fill; the requirements 
for grouting and sealing joints; and the type of roof insulation and roof covering.</NPR><BRK/>
<BRK/>
<NPR>Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.</NPR><BRK/>
<BRK/>
<NPR>Remove information and requirements not required in respective project, whether 
or not brackets are present.</NPR><BRK/>
<BRK/>
<NPR>Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.</NPR><BRK/>
<BRK/>
<NPR>Recommended changes to a UFGS should be submitted as a <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
<BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
<BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ACI INTERNATIONAL (ACI)</ORG><BRK/><BRK/><RID>ACI 211.1</RID><RTL>(1991; R 2002) Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete</RTL><BRK/><BRK/><RID>ACI 318/318R</RID><RTL>(2008; Errata 2008) Building Code Requirements for Structural Concrete and Commentary</RTL><BRK/><BRK/><RID>ACI 318M</RID><RTL>(2008) Metric Building Code Requirements for Structural Concrete and Commentary</RTL><BRK/><BRK/><RID>ACI SP-66</RID><RTL>(2004) ACI Detailing Manual</RTL><BRK/><BRK/><RID>ACI/MCP 205</RID><RTL>(2008) Manual of Concrete Practice Part 2 - ACI 224R-01 to ACI 313R-97</RTL><BRK/><BRK/><RID>ACI/MCP 305</RID><RTL>(2008) Manual of Concrete Practice Part 3:315-99 to 343R-95</RTL><BRK/><BRK/><RID>ACI/MCP 405</RID><RTL>(2008) Manual of Concrete Practice Part 4:345R-91(97) to 355.2R-04</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)</ORG><BRK/><BRK/><RID>AASHTO M 200</RID><RTL>(1973; R 2007) Standard Specification for Epoxy Protective Coatings</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN HARDBOARD ASSOCIATION (AHA)</ORG><BRK/><BRK/><RID>AHA A135.4</RID><RTL>(2004) Basic Hardboard</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)</ORG><BRK/><BRK/><RID>ANSI A48.1</RID><RTL>(1986) Concrete Construction - Forms for One Way Concrete Joist Construction</RTL><BRK/><BRK/><RID>ANSI A48.2</RID><RTL>(1986) Concrete Construction - Forms for Two Way Concrete Joist Construction</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN WELDING SOCIETY (AWS)</ORG><BRK/><BRK/><RID>AWS A5.1/A5.1M</RID><RTL>(2004; Errata 2004) Carbon Steel Electrodes for Shielded Metal Arc Welding</RTL><BRK/><BRK/><RID>AWS D1.1/D1.1M</RID><RTL>(2008) Structural Welding Code - Steel</RTL><BRK/><BRK/><RID>AWS D1.4/D1.4M</RID><RTL>(2005; Errata 2005) Structural Welding Code - Reinforcing Steel</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM A 153/A 153M</RID><RTL>(2005) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware</RTL><BRK/><BRK/><RID>ASTM A 185/A 185M</RID><RTL>(2007) Standard Specification for Steel Welded Wire Reinforcement, Plain, for Concrete</RTL><BRK/><BRK/><RID>ASTM A 283/A 283M</RID><RTL>(2003; R 2007) Standard Specification for Low and Intermediate Tensile Strength Carbon Steel Plates</RTL><BRK/><BRK/><RID>ASTM A 322</RID><RTL>(2007) Standard Specification Steel Bars, Alloy, Standard Grades</RTL><BRK/><BRK/><RID>ASTM A 36/A 36M</RID><RTL>(2008) Standard Specification for Carbon Structural Steel</RTL><BRK/><BRK/><RID>ASTM A 370</RID><RTL>(2008b) Standard Test Methods and Definitions for Mechanical Testing of Steel Products</RTL><BRK/><BRK/><RID>ASTM A 416/A 416M</RID><RTL>(2006) Standard Specification for Steel Strand, Uncoated Seven-Wire for Prestressed Concrete</RTL><BRK/><BRK/><RID>ASTM A 421/A 421M</RID><RTL>(2005) Standard Specification for Uncoated Stress-Relieved Wire for Prestressed Concrete</RTL><BRK/><BRK/><RID>ASTM A 615/A 615M</RID><RTL>(2008b) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement</RTL><BRK/><BRK/><RID>ASTM A 675/A 675M</RID><RTL>(2003e1) Standard Specification for Steel Bars, Carbon, Hot-Wrought, Special Quality, Mechanical Properties</RTL><BRK/><BRK/><RID>ASTM A 82/A 82M</RID><RTL>(2007) Standard Specification for Steel Wire, Plain, for Concrete Reinforcement</RTL><BRK/><BRK/><RID>ASTM C 109/C 109M</RID><RTL>(2008) Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2-in. or (50-mm) Cube Specimens)</RTL><BRK/><BRK/><RID>ASTM C 1107/C 1107M</RID><RTL>(2008) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)</RTL><BRK/><BRK/><RID>ASTM C 114</RID><RTL>(2007) Standard Test Methods for Chemical Analysis of Hydraulic Cement</RTL><BRK/><BRK/><RID>ASTM C 115</RID><RTL>(1996a; R 2003) Standard Test Method for Fineness of Portland Cement by the Turbidimeter</RTL><BRK/><BRK/><RID>ASTM C 117</RID><RTL>(2004) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing</RTL><BRK/><BRK/><RID>ASTM C 123</RID><RTL>(2004) Standard Test Method for Lightweight Particles in Aggregate</RTL><BRK/><BRK/><RID>ASTM C 126</RID><RTL>(1999; R 2005) Standard Specification for Ceramic Glazed Structural Clay Facing Tile, Facing Brick, and Solid Masonry Units</RTL><BRK/><BRK/><RID>ASTM C 127</RID><RTL>(2007) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate</RTL><BRK/><BRK/><RID>ASTM C 128</RID><RTL>(2007a) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Fine Aggregate</RTL><BRK/><BRK/><RID>ASTM C 131</RID><RTL>(2006)Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine</RTL><BRK/><BRK/><RID>ASTM C 136</RID><RTL>(2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates</RTL><BRK/><BRK/><RID>ASTM C 138/C 138M</RID><RTL>(2008) Standard Test Method for Density ("Unit Weight"), Yield, and Air Content (Gravimetric) of Concrete</RTL><BRK/><BRK/><RID>ASTM C 142</RID><RTL>(1997; R 2004) Standard Test Method for Clay Lumps and Friable Particles in Aggregates</RTL><BRK/><BRK/><RID>ASTM C 143/C 143M</RID><RTL>(2008) Standard Test Method for Slump of Hydraulic-Cement Concrete</RTL><BRK/><BRK/><RID>ASTM C 150</RID><RTL>(2007) Standard Specification for Portland Cement</RTL><BRK/><BRK/><RID>ASTM C 151</RID><RTL>(2005) Standard Test Method for Autoclave Expansion of Hydraulic Cement</RTL><BRK/><BRK/><RID>ASTM C 157/C 157M</RID><RTL>(2008) Standard Test Method for Length Change of Hardened Hydraulic-Cement Mortar and Concrete</RTL><BRK/><BRK/><RID>ASTM C 172</RID><RTL>(2008) Standard Practice for Sampling Freshly Mixed Concrete</RTL><BRK/><BRK/><RID>ASTM C 173/C 173M</RID><RTL>(2008) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method</RTL><BRK/><BRK/><RID>ASTM C 183</RID><RTL>(2002) Standard Practice for Sampling and the Amount of Testing of Hydraulic Cement</RTL><BRK/><BRK/><RID>ASTM C 185</RID><RTL>(2008) Standard Test Method for Air Content of Hydraulic Cement Mortar</RTL><BRK/><BRK/><RID>ASTM C 191</RID><RTL>(2008) Standard Test Method for Time of Setting Hydraulic Cement by Vicat Needle</RTL><BRK/><BRK/><RID>ASTM C 192/C 192M</RID><RTL>(2007) Standard Practice for Making and Curing Concrete Test Specimens in the Laboratory</RTL><BRK/><BRK/><RID>ASTM C 204</RID><RTL>(2007) Standard Test Method for Fineness of Hydraulic Cement by Air Permeability Apparatus</RTL><BRK/><BRK/><RID>ASTM C 231</RID><RTL>(2008c) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method</RTL><BRK/><BRK/><RID>ASTM C 232</RID><RTL>(2007) Standard Test Methods for Bleeding of Concrete</RTL><BRK/><BRK/><RID>ASTM C 233</RID><RTL>(2007) Standard Test Method for Air-Entraining Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM C 260</RID><RTL>(2006) Standard Specification for Air-Entraining Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM C 266</RID><RTL>(2008) Standard Test Method for Time of Setting of Hydraulic-Cement Paste by Gillmore Needles</RTL><BRK/><BRK/><RID>ASTM C 29/C 29M</RID><RTL>(2007) Standard Test Method for Bulk Density ("Unit Weight") and Voids in Aggregate</RTL><BRK/><BRK/><RID>ASTM C 31/C 31M</RID><RTL>(2008a) Standard Practice for Making and Curing Concrete Test Specimens in the Field</RTL><BRK/><BRK/><RID>ASTM C 33</RID><RTL>(2007) Standard Specification for Concrete Aggregates</RTL><BRK/><BRK/><RID>ASTM C 330</RID><RTL>(2005) Standard Specification for Lightweight Aggregates for Structural Concrete</RTL><BRK/><BRK/><RID>ASTM C 39/C 39M</RID><RTL>(2005e1e2) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens</RTL><BRK/><BRK/><RID>ASTM C 40</RID><RTL>(2004) Standard Test Method for Organic Impurities in Fine Aggregates for Concrete</RTL><BRK/><BRK/><RID>ASTM C 403/C 403M</RID><RTL>(2008) Standard Test Method for Time of Setting of Concrete Mixtures by Penetration Resistance</RTL><BRK/><BRK/><RID>ASTM C 404</RID><RTL>(2007) Standard Specification for Aggregates for Masonry Grout</RTL><BRK/><BRK/><RID>ASTM C 42/C 42M</RID><RTL>(2004) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete</RTL><BRK/><BRK/><RID>ASTM C 451</RID><RTL>(2008) Standard Test Method for Early Stiffening of Hydraulic Cement (Paste Method)</RTL><BRK/><BRK/><RID>ASTM C 535</RID><RTL>(2003e1) Standard Test Method for Resistance to Degradation of Large-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine</RTL><BRK/><BRK/><RID>ASTM C 566</RID><RTL>(1997; R 2004) Standard Test Method for Total Evaporable Moisture Content of Aggregate by Drying</RTL><BRK/><BRK/><RID>ASTM C 595</RID><RTL>(2008) Standard Specification for Blended Hydraulic Cements</RTL><BRK/><BRK/><RID>ASTM C 618</RID><RTL>(2008a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete</RTL><BRK/><BRK/><RID>ASTM C 70</RID><RTL>(2006) Standard Test Method for Surface Moisture in Fine Aggregate</RTL><BRK/><BRK/><RID>ASTM C 78</RID><RTL>(2008) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading)</RTL><BRK/><BRK/><RID>ASTM C 88</RID><RTL>(2005) Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate</RTL><BRK/><BRK/><RID>ASTM C 94/C 94M</RID><RTL>(2007) Standard Specification for Ready-Mixed Concrete</RTL><BRK/><BRK/><RID>ASTM C 989</RID><RTL>(2006) Standard Specification for Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars</RTL><BRK/><BRK/><RID>ASTM D 1149</RID><RTL>(2007) Standard Test Method for Rubber Deterioration - Surface Ozone Cracking in a Chamber</RTL><BRK/><BRK/><RID>ASTM D 2103</RID><RTL>(2008) Standard Specification for Polyethylene Film and Sheeting</RTL><BRK/><BRK/><RID>ASTM D 2240</RID><RTL>(2005) Standard Test Method for Rubber Property - Durometer Hardness</RTL><BRK/><BRK/><RID>ASTM D 312</RID><RTL>(2000; R 2006) Standard Specification for Asphalt Used in Roofing</RTL><BRK/><BRK/><RID>ASTM D 3744</RID><RTL>(2003) Standard Test Method for Aggregate Durability Index</RTL><BRK/><BRK/><RID>ASTM D 395</RID><RTL>(2003; R 2008) Standard Test Methods for Rubber Property - Compression Set</RTL><BRK/><BRK/><RID>ASTM D 412</RID><RTL>(2006ae1e2) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension</RTL><BRK/><BRK/><RID>ASTM D 4397</RID><RTL>(2008) Standard Specification for Polyethylene Sheeting for Construction, Industrial, and Agricultural Applications</RTL><BRK/><BRK/><RID>ASTM D 471</RID><RTL>(2006; R 2008) Standard Test Method for Rubber Property - Effect of Liquids</RTL><BRK/><BRK/><RID>ASTM D 573</RID><RTL>(2004) Standard Test Method for Rubber - Deterioration in an Air Oven</RTL><BRK/><BRK/><RID>ASTM D 75</RID><RTL>(2003) Standard Practice for Sampling Aggregates</RTL><BRK/><BRK/><RID>ASTM E 165</RID><RTL>(2002) Standard Test Method for Liquid Penetrant Examination</RTL><BRK/><BRK/><RID>ASTM E 648</RID><RTL>(2008a) Standard Test Method for Critical Radiant Flux of Floor-Covering Systems Using a Radiant Heat Energy Source</RTL><BRK/><BRK/><RID>ASTM E 709</RID><RTL>(2008) Standard Guide for Magnetic Particle Examination</RTL><BRK/><BRK/></REF><REF><ORG>CONCRETE REINFORCING STEEL INSTITUTE (CRSI)</ORG><BRK/><BRK/><RID>CRSI 10MSP</RID><RTL>(2001; 27Ed) Manual of Standard Practice</RTL><BRK/><BRK/></REF><REF><ORG>PRECAST/PRESTRESSED CONCRETE INSTITUTE (PCI)</ORG><BRK/><BRK/><RID>PCI MNL-116</RID><RTL>(1999) Manual for Quality Control for Plants and Production of Structural Precast Concrete Products</RTL><BRK/><BRK/><RID>PCI MNL-120</RID><RTL>(2004) Design Handbook - Precast and Prestressed Concrete</RTL><BRK/><BRK/></REF><REF><ORG>U.S. GENERAL SERVICES ADMINISTRATION (GSA)</ORG><BRK/><BRK/><RID>FS MMM-A-001993</RID><RTL>(1978) Adhesive, Epoxy, Flexible, Filled (For Binding, Sealing, and Grouting)</RTL><BRK/><BRK/><RID>FS UU-B-790</RID><RTL>(Rev A) Building Paper, Vegetable Fiber:  (Kraft, Waterproofed, Water Repellent and Fire Resistant)</RTL><BRK/><BRK/></REF><REF><ORG>UNDERWRITERS LABORATORIES (UL)</ORG><BRK/><BRK/><RID>UL Electrical Constructn</RID><RTL>(2008) Electrical Construction Equipment Directory</RTL><BRK/><BRK/><RID>UL Fire Resistance</RID><RTL>(2008) Fire Resistance Directory</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review Submittal Description (SD) definitions in Section <SRF>01 33 00</SRF> SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  Submit the following 
in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
<ITM>Submit <SUB>Fabrication Drawings</SUB> in accordance with the paragraphs entitled, "Fabrication" and "Drawings," 
of this section.</ITM><BRK/>
<BRK/>
<ITM>Submit <SUB>Installation Drawings</SUB> in accordance with the paragraph entitled, "Drawings," of this 
section.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-05 Design Data</SUB></LST><BRK/>
<BRK/>
<ITM>Submit mix design data in accordance with the paragraph entitled, "Concrete Design Mixes," of 
this section.</ITM><BRK/>
<BRK/>
<ITM><SUB>Normal Weight Concrete</SUB><BRK/>
<SUB>Lightweight Structural Concrete</SUB></ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM>Submittest reports for the following items in accordance with paragraph entitled, "Concrete 
Sampling and Testing," of this section.  Include within each report the project name and number, 
date, name of Contractor, name of precast-concrete manufacturer, name of concrete testing service, 
type of concrete, structural-member identification letter and number, design compressive strength 
at 28 calendar days, concrete-mix proportions and materials, compressive breaking strength and 
type of break, a record of gage pressures or dynamometer readings, compression strength of concrete 
at time of detensioning, and type of reinforcement.  Design mix reports must be approved at 
least 15 calendar days prior to start of work.</ITM><BRK/>
<BRK/>
<ITM><SUB>Air Content</SUB><BRK/>
<SUB>Air Entrainment</SUB><BRK/>
<SUB>Compressive Strength</SUB><BRK/>
<SUB>Slump</SUB><BRK/>
<SUB>Moisture Content</SUB><BRK/>
<SUB>Design Mix</SUB><BRK/>
<SUB>Unit Weight</SUB></ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM>Include within the certificates of Compliance for the following items; qualifications of personnel, 
location of plant, concrete batching facilities, manufacturer equipment and facilities, a list 
of projects similar to specified work, handling and erection equipment, and performance requirements.  
Certificates for welder qualifications must be in accordance with the paragraph entitled, "<SUB>Qualifications 
for Welding Work</SUB>," of this section.</ITM><BRK/>
<BRK/>
<ITM><SUB>Installers</SUB><BRK/>
<SUB>Manufacturer</SUB><BRK/>
<SUB>Aggregate</SUB><BRK/>
<SUB>Pretensioning</SUB><BRK/>
<SUB>Detensioning</SUB></ITM><BRK/>
<BRK/>
<ITM>Submit <SUB>Welding Procedures</SUB>  in accordance with <RID>AWS D1.1/D1.1M</RID>.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-08 Manufacturer's Instructions</SUB></LST><BRK/>
<BRK/>
<ITM>Indicate within the <SUB>Installation Instructions</SUB> the manufacturer's recommended sequence and methods 
of installation for the following items:</ITM><BRK/>
<BRK/>
<ITM><SUB>Welding Sequence and Procedure</SUB><BRK/>
<SUB>Epoxy-Resin Grout</SUB><BRK/>
<SUB>Epoxy-Resin Adhesive</SUB></ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   QUALIFICATIONS FOR PRECAST-CONCRETE MANUFACTURER</TTL><BRK/>
<BRK/>
<TXT>Precast structural concrete sections must be manufactured by an organization experienced in the manufacture of 
precast concrete.</TXT><BRK/>
<BRK/>
<TXT>Submit a written description of the <SUB>Manufacturer</SUB> giving the qualifications of personnel, location of plant, concrete 
batching facilities, manufacturing equipment and facilities, list of projects similar to specified work, and 
other information as may be required.</TXT><BRK/>
<BRK/>
<TXT>Produce sections/units under plant-controlled conditions conforming to <RID>PCI MNL-116</RID> by a firm certified under 
the PCI Plant Certification Program and specializing in providing precast/prestressed products and related services.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4   QUALIFICATIONS FOR INSTALLER</TTL><BRK/>
<BRK/>
<TXT>Install members by an organization experienced in the installation of precast structural-concrete sections.</TXT><BRK/>
<BRK/>
<TXT>Submit a written description of <SUB>Installers</SUB> giving the qualifications of personnel, handling and erection equipment, 
list of projects similar to specified work, and other information as may be required.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5   <SUB>QUALIFICATIONS FOR WELDING WORK</SUB></TTL><BRK/>
<BRK/>
<TXT>[Section <SRF>05 05 23</SRF> WELDING, STRUCTURAL applies to work specified in this section.]</TXT><BRK/>
<BRK/>
<TXT>[<SUB>Welding Procedures</SUB> must be in accordance with <RID>AWS D1.1/D1.1M</RID>.]</TXT><BRK/>
<BRK/>
<TXT>[Welders must be qualified by tests in accordance with <RID>AWS D1.1/D1.1M</RID>.]</TXT><BRK/>
<BRK/>
<TXT>[Welders are to make only those types of weldments for which each is specifically qualified.]</TXT><BRK/>
<BRK/>
<TXT>Provide <SUB>installation instructions</SUB> for the <SUB>Welding Sequence and Procedure</SUB> which indicates the manufacturer's recommended 
sequence and method of installation.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6   PERFORMANCE REQUIREMENTS</TTL><BRK/>
<BRK/>
<SPT><TTL>1.6.1   Design Methods</TTL><BRK/>
<BRK/>
<TXT>Design must be in accordance with <RID>ACI/MCP 305</RID>, <RID>ACI 318/318R</RID>, <RID>ACI 318M</RID> and <RID>PCI MNL-120</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6.2   Allowable Design Loads and Deflections</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Allowable design loads must be indicated and include dead loads, live 
loads, stationary loads, concentrated moving loads, deflection of roof slab 
sections, etc.<BRK/>
<BRK/>
Recommended design loads are specified in article ix of the National Building 
Code, recommended by the American Insurance Association AIA CO-1 and ANSI A58.1.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Allowable design loads and deflections must be as indicated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6.3   UL Fire-Resistance Listing and Label</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraph when UL-listed fire-resistant 
precast structural concrete sections are not required.  The UL lists several 
manufacturers of prestressed precast-concrete hollow-core flat slabs and single-tee 
and double-tee slabs.  Location and fire-resistance classification of fire-resistant-rated 
structural sections must be indicated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Sections indicated requiring a fire-resistance classification must be listed in <RID>UL Fire Resistance</RID>, part entitled, 
"Precast Concrete Units (CFTV)," and bear the UL label and marking.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6.4   Electrical Raceway UL Listing and Label</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraph when hollow-core 
floor-slab precast structural sections will not be used for electrical raceways, 
either under this contract or in the future.  Location of electrical raceway 
structural sections must be indicated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Hollow-core floor slabs indicated as electrical raceways must be listed in <RID>UL Electrical Constructn</RID>, part entitled, 
"Raceways (RGKT) Cellular Concrete Floor (RGYR)," and bear the UL label and marking.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.7   CONCRETE SAMPLING AND TESTING</TTL><BRK/>
<BRK/>
<SPT><TTL>1.7.1   Tests for Concrete Materials</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following materials and tests that are not required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><TST>Sample and test concrete materials proposed for use in the work </TST> as follows:</TXT><BRK/>
<MET><TBL><THD><BRK/>
            <HL1>MATERIAL</HL1>     <HL1>REQUIREMENT</HL1>    <HL1>TEST METHOD</HL1>        <HL1>NUMBER OF TESTS</HL1><BRK/></THD>
<BRK/>
            Concrete     Sampling        <RID>ASTM D 75</RID>          One for each<BRK/>
            aggregates                                      material source<BRK/>
            for normal-  Sieve analysis  <RID>ASTM C 136</RID>         and grading<BRK/>
            weight                                          size<BRK/>
            concrete     Calculating     <RID>ASTM C 126</RID><BRK/>
                         fineness<BRK/>
                         modulus<BRK/>
<BRK/>
                         Amount of       <RID>ASTM C 117</RID><BRK/>
                         material pass-<BRK/>
                         ing 75 micrometer<BRK/>
                         sieve<BRK/>
<BRK/>
                         Amount of fri-  <RID>ASTM C 142</RID><BRK/>
                         able particles<BRK/>
<BRK/>
                         Amount of       <RID>ASTM C 40</RID><BRK/>
                         organic<BRK/>
                         impurities<BRK/>
<BRK/>
                         Amount of coal  <RID>ASTM C 123</RID><BRK/>
                         and lignite<BRK/>
<BRK/>
                         Magnesium sul-  <RID>ASTM C 88</RID><BRK/>
                         fate soundness<BRK/>
                         test<BRK/>
<BRK/>
                         Aggregate dura- <RID>ASTM D 3744</RID><BRK/>
                         bility<BRK/>
<BRK/>
                         Compact unit    <RID>ASTM C 29/C 29M</RID><BRK/>
                         weight of slag<BRK/>
                         (coarse<BRK/>
                         aggregate)<BRK/>
<BRK/>
                         Resistance to   <RID>ASTM C 131</RID> or<BRK/>
                         abrasion test   <RID>ASTM C 535</RID><BRK/>
                         of small size<BRK/>
                         coarse<BRK/>
                         aggregate<BRK/>
<BRK/>
            Lightweight  Sampling        <RID>ASTM D 75</RID>          One for each<BRK/>
            aggregates                                      material source<BRK/>
            for struc-   Sieve           <RID>ASTM C 136</RID>         and grading<BRK/>
            tural con-   analysis        <RID>ASTM C 330</RID>         size<BRK/>
            crete<BRK/>
<BRK/>
                         Compact unit    <RID>ASTM C 29/C 29M</RID><BRK/>
                         Unit weight        and<BRK/>
                         (loose)         <RID>ASTM C 330</RID><BRK/>
<BRK/>
            Lightweight  Specimen        <RID>ASTM C 192/C 192M</RID>  As required for<BRK/>
            structural   preparation        and             each type of<BRK/>
            concrete us-                 <RID>ASTM C 330</RID>         test to deter-<BRK/>
            ing the pro-                                    mine<BRK/>
                                                            conformance<BRK/>
            posed light- Compressive     <RID>ASTM C 39/C 39M</RID><BRK/>
            weight       strength<BRK/>
            aggregates<BRK/>
<BRK/>
                         Unit-weight     <RID>ASTM C 330</RID><BRK/>
<BRK/>
                         Shrinkage       <RID>ASTM C 157/C 157M</RID><BRK/>
                                            and<BRK/>
                                         <RID>ASTM C 330</RID><BRK/>
<BRK/>
            Hydraulic    Sampling        <RID>ASTM C 183</RID>         One for each<BRK/>
            cement                                          material<BRK/>
                                                            source,<BRK/>
                         Chemical        <RID>ASTM C 114</RID>         type, and <BRK/>
                                                            color<BRK/>
                         analysis <BRK/>
<BRK/>
                         Fineness        <RID>ASTM C 115</RID><BRK/>
                                             or<BRK/>
                                         <RID>ASTM C 204</RID><BRK/>
<BRK/>
                         Autoclave       <RID>ASTM C 151</RID><BRK/>
                         expansion<BRK/>
<BRK/>
                         Time of         <RID>ASTM C 191</RID><BRK/>
                         setting            or<BRK/>
                                         <RID>ASTM C 266</RID><BRK/>
<BRK/>
                         Air content     <RID>ASTM C 185</RID><BRK/>
                         of mortar<BRK/>
<BRK/>
                         Compressive     <RID>ASTM C 109/C 109M</RID><BRK/>
                         strength<BRK/>
<BRK/>
                         Heat of         <RID>ASTM C 185</RID><BRK/>
                         hydration<BRK/>
<BRK/>
                         False set       <RID>ASTM C 451</RID><BRK/>
<BRK/>
            Air entrain- Materials       <RID>ASTM C 233</RID>         One set of<BRK/>
            ing admix-   for tests                          tests for each<BRK/>
            ture using                                      type of port-<BRK/>
            air-entrain- Number of       <RID>ASTM C 233</RID>,        land cement<BRK/>
            ing concrete specimens       Table 1            proposed for<BRK/>
            made of the                                     use and for<BRK/>
            proposed                                        each type of<BRK/>
            concrete     Bleeding        <RID>ASTM C 232</RID>         concrete<BRK/>
            materials<BRK/>
<BRK/>
                         Time of         <RID>ASTM C 403/C 403M</RID><BRK/>
                         setting            and<BRK/>
                                         <RID>ASTM C 233</RID><BRK/>
<BRK/>
                         Compressive-    <RID>ASTM C 192/C 192M</RID><BRK/>
                         strength test      and<BRK/>
                         specimen        <RID>ASTM C 233</RID><BRK/>
<BRK/>
                         Compressive-    <RID>ASTM C 39/C 39M</RID><BRK/>
                         strength           and<BRK/>
                         test at 3, 7,   <RID>ASTM C 233</RID><BRK/>
                         and 28 calendar<BRK/>
                         days<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
            <HL1>MATERIAL</HL1>     <HL1>REQUIREMENT</HL1>       <HL1>TEST METHOD</HL1>      <HL1>NUMBER OF TESTS</HL1><BRK/></THD>
<BRK/>
            Concrete     Sampling        <RID>ASTM D 75</RID>          One for each<BRK/>
            aggregates                                      material source<BRK/>
            for normal-  Sieve analysis  <RID>ASTM C 136</RID>         and grading<BRK/>
            weight                                          size<BRK/>
            concrete     Calculating     <RID>ASTM C 126</RID><BRK/>
                         fineness<BRK/>
                         modulus<BRK/>
<BRK/>
                         Amount of       <RID>ASTM C 117</RID><BRK/>
                         material pass-<BRK/>
                         ing No. 200<BRK/>
                         sieve<BRK/>
<BRK/>
                         Amount of fri-  <RID>ASTM C 142</RID><BRK/>
                         able particles<BRK/>
<BRK/>
                         Amount of       <RID>ASTM C 40</RID><BRK/>
                         organic<BRK/>
                         impurities<BRK/>
<BRK/>
                         Amount of coal  <RID>ASTM C 123</RID><BRK/>
                         and lignite<BRK/>
<BRK/>
                         Magnesium sul-  <RID>ASTM C 88</RID><BRK/>
                         fate soundness<BRK/>
                         test<BRK/>
<BRK/>
                         Aggregate dura- <RID>ASTM D 3744</RID><BRK/>
                         bility<BRK/>
<BRK/>
                         Compact unit    <RID>ASTM C 29/C 29M</RID><BRK/>
                         weight of slag<BRK/>
                         (coarse<BRK/>
                         aggregate)<BRK/>
<BRK/>
                         Resistance to   <RID>ASTM C 131</RID> or<BRK/>
                         abrasion test   <RID>ASTM C 535</RID><BRK/>
                         of small size<BRK/>
                         coarse<BRK/>
                         aggregate<BRK/>
<BRK/>
            Lightweight  Sampling        <RID>ASTM D 75</RID>          One for each<BRK/>
            aggregates                                      material source<BRK/>
            for struc-   Sieve           <RID>ASTM C 136</RID>         and grading<BRK/>
            tural con-   analysis        <RID>ASTM C 330</RID>         size<BRK/>
            crete<BRK/>
<BRK/>
                         Compact unit    <RID>ASTM C 29/C 29M</RID><BRK/>
                         Unit weight        and<BRK/>
                         (loose)         <RID>ASTM C 330</RID><BRK/>
<BRK/>
            Lightweight  Specimen        <RID>ASTM C 192/C 192M</RID>  As required for<BRK/>
            structural   preparation        and             each type of<BRK/>
            concrete us-                 <RID>ASTM C 330</RID>         test to deter-<BRK/>
            ing the pro-                                    mine conformance<BRK/>
            posed light- Compressive     <RID>ASTM C 39/C 39M</RID><BRK/>
            weight       strength<BRK/>
            aggregates<BRK/>
<BRK/>
                         Unit-weight     <RID>ASTM C 330</RID><BRK/>
<BRK/>
                         Shrinkage       <RID>ASTM C 157/C 157M</RID><BRK/>
                                            and<BRK/>
                                         <RID>ASTM C 330</RID><BRK/>
<BRK/>
            Hydraulic    Sampling        <RID>ASTM C 183</RID>         One for each<BRK/>
            cement                                          material source,<BRK/>
                         Chemical        <RID>ASTM C 114</RID>         type, and color<BRK/>
                         analysis<BRK/>
<BRK/>
                         Fineness        <RID>ASTM C 115</RID><BRK/>
                                             or<BRK/>
                                         <RID>ASTM C 204</RID><BRK/>
<BRK/>
                         Autoclave       <RID>ASTM C 151</RID><BRK/>
                         expansion<BRK/>
<BRK/>
                         Time of         <RID>ASTM C 191</RID><BRK/>
                         setting            or<BRK/>
                                         <RID>ASTM C 266</RID><BRK/>
<BRK/>
                         Air content     <RID>ASTM C 185</RID><BRK/>
                         of mortar<BRK/>
<BRK/>
                         Compressive     <RID>ASTM C 109/C 109M</RID><BRK/>
                         strength<BRK/>
<BRK/>
                         Heat of         <RID>ASTM C 185</RID><BRK/>
                         hydration<BRK/>
<BRK/>
                         False set       <RID>ASTM C 451</RID><BRK/>
<BRK/>
            Air entrain- Materials       <RID>ASTM C 233</RID>         One set of<BRK/>
            ing admix-   for tests                          tests for each<BRK/>
            ture using                                      type of port-<BRK/>
            air-entrain- Number of       <RID>ASTM C 233</RID>,        land cement<BRK/>
            ing concrete specimens       Table 1            proposed for<BRK/>
            made of the                                     use and for<BRK/>
            proposed                                        each type of<BRK/>
            concrete     Bleeding        <RID>ASTM C 232</RID>         concrete<BRK/>
            materials<BRK/>
<BRK/>
                         Time of         <RID>ASTM C 403/C 403M</RID><BRK/>
                         setting            and<BRK/>
                                         <RID>ASTM C 233</RID><BRK/>
<BRK/>
                         Compressive-    <RID>ASTM C 192/C 192M</RID><BRK/>
                         strength test      and<BRK/>
                         specimen        <RID>ASTM C 233</RID><BRK/>
<BRK/>
                         Compressive-    <RID>ASTM C 39/C 39M</RID><BRK/>
                         strength           and<BRK/>
                         test at 3, 7,   <RID>ASTM C 233</RID><BRK/>
                         and 28 calendar<BRK/>
                         days<BRK/></TBL>
</ENG><BRK/></SPT>
<SPT><TTL>1.7.2   Concrete Design Mixes</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following types of concrete and tests not required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><TST>Determine and test concrete <SUB>Design Mix</SUB> for concrete used </TST>as follows:</TXT><BRK/>
<TBL><THD><BRK/>
            TYPE OF<BRK/>
            <HL1>CONCRETE</HL1>     <HL1>REQUIREMENT</HL1>       <HL1>TEST METHOD</HL1>      <HL1>NUMBER OF TESTS</HL1><BRK/></THD>
<BRK/>
            Normal     Specific           <RID>ASTM C 128</RID>        As required for<BRK/>
            weight     gravity and                          the concrete<BRK/>
            concrete   absorption of                        aggregates for<BRK/>
                       fine aggregate                       each trial mix<BRK/>
<BRK/>
                       Specific           <RID>ASTM C 127</RID><BRK/>
                       gravity and<BRK/>
                       absorption of<BRK/>
                       coarse<BRK/>
                       aggregate<BRK/>
<BRK/>
                       <SUB>Moisture Content</SUB>   <RID>ASTM C 70</RID><BRK/>
                       tent of both          and<BRK/>
                       fine and           <RID>ASTM C 566</RID><BRK/>
                       coarse<BRK/>
                       aggregate<BRK/>
<BRK/>
                       Dry-rodded         <RID>ASTM C 29/C 29M</RID><BRK/>
                       <SUB>Unit Weight</SUB> of<BRK/>
                       coarse<BRK/>
                       aggregate<BRK/>
<BRK/>
                       Trial mixes us-    <RID>ACI 211.1</RID>         As required to<BRK/>
                       ing at least                         determine the<BRK/>
                       three different                      concrete mix<BRK/>
                       water/cement                         having the<BRK/>
                       ratios, minimum                      properties<BRK/>
                       allowable cement                     specified in<BRK/>
                       content, maxi-                       the paragraph<BRK/>
                       mum allowable                        entitled,<BRK/>
                       slump; all with                      "Quality of<BRK/>
                       <SUB>Air Entrainment</SUB>                      Concrete"<BRK/>
<BRK/>
                       Making and         <RID>ASTM C 192/C 192M</RID> Two sets of<BRK/>
                       curing concrete                      three specimens<BRK/>
                       specimens in                         for each design<BRK/>
                       the laboratory                       mix<BRK/>
<BRK/>
                       Sampling fresh     <RID>ASTM C 192/C 192M</RID> One for each<BRK/>
                       concrete in the                      set of design<BRK/>
                       laboratory                           mix specimens<BRK/>
<BRK/>
                       <SUB>Slump</SUB>              <RID>ASTM C 143/C 143M</RID><BRK/>
<BRK/>
                       <SUB>Air Content</SUB>        <RID>ASTM C 231</RID><BRK/>
<BRK/>
                       Yield              <RID>ASTM C 138/C 138M</RID><BRK/>
<BRK/>
                       Compressive        <RID>ASTM C 39/C 39M</RID>   Three specimens<BRK/>
                       strength                             tested at 28<BRK/>
                                                            calendar days<BRK/>
<BRK/>
          Lightweight  Dry loose unit   <RID>ASTM C 29/C 29M</RID>     As required for<BRK/>
          structural   weight of             and            the lightweight<BRK/>
          concrete     aggregates         <RID>ASTM C 330</RID>        aggregate for<BRK/>
                                                            each trial mix<BRK/>
                       Moisture con-      <RID>ASTM C 566</RID><BRK/>
                       tent of<BRK/>
                       aggregate<BRK/>
<BRK/>
                       Trial mixes us-    <RID>ACI 211.1</RID>         As required to<BRK/>
                       ing at least                         determine the<BRK/>
                       three different                      concrete mix<BRK/>
                       water/cement                         having the<BRK/>
                       ratios, maxi-                        properties<BRK/>
                       mum allowable                        specified in<BRK/>
                       slump; both                          the paragraph<BRK/>
                       with and with-                       entitled,<BRK/>
                       out air en-                          "Quality of<BRK/>
                       trainment                            Concrete"<BRK/>
<BRK/>
                       Making and         <RID>ASTM C 192/C 192M</RID> Two sets of<BRK/>
                       curing concrete                      for each design <BRK/>
                       the laboratory                       mix<BRK/>
<BRK/>
                       Sampling fresh     <RID>ASTM C 192/C 192M</RID> One for each<BRK/>
                       concrete in the                      set of design<BRK/>
                       laboratory                           mix specimens<BRK/>
<BRK/>
                       Slump              <RID>ASTM C 143/C 143M</RID><BRK/>
<BRK/>
                       Air content        <RID>ASTM C 173/C 173M</RID><BRK/>
<BRK/>
                       Yield              <RID>ASTM C 138/C 138M</RID><BRK/>
<BRK/>
                       Compressive        <RID>ASTM C 39/C 39M</RID>   Three specimens<BRK/>
                       strength                             tested at 7<BRK/>
                                                            calendar days<BRK/>
                                                            and three<BRK/>
                                                            specimens tested<BRK/>
                                                            at 28 calendar<BRK/>
                                                            days<BRK/>
<BRK/>
                       Air-dried          <RID>ASTM C 330</RID>        Two specimens<BRK/>
                       unit weight                          tested after<BRK/>
                                                            curing 28<BRK/>
                                                            calendar days<BRK/></TBL>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when normal-weight concrete is not required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>From the results of the tests for normal-weight concrete, plot a curve showing the relationships between water/cement 
ratios and compressive strengths.  Do not exceed the maximum water/cement ratio specified for normal-weight concrete 
properties shown by the curve to produce a design-minimum laboratory Compressive Strength at 28 calendar days 
not less than that specified.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when lightweight structural concrete is 
not required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>From the results of the tests for lightweight structural concrete, plot a curve showing the relationships between 
cement contents and compressive strengths.  Do not provide less then the minimum cement content specified for 
lightweight structural properties shown by the curve to produce a design-minimum laboratory compressive strength 
at 28 calendar days not less than that specified.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.3   Quality Control Testing During Fabrication</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following types of concrete not required by the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><TST>Sample and test concrete </TST>for quality control during fabrication as follows:</TXT><BRK/>
<TBL><THD><BRK/>
        TYPE OF<BRK/>
        <HL1>CONCRETE</HL1>     <HL1>REQUIREMENT</HL1>     <HL1>TEST METHOD</HL1>            <HL1>NUMBER OF TESTS</HL1><BRK/></THD>
<BRK/>
         Normal       Sampling of     <RID>ASTM C 172</RID>            As required for<BRK/>
         weight       fresh           except                each test<BRK/>
         concrete     concrete        modified for<BRK/>
                                      slump per<BRK/>
                                      <RID>ASTM C 94/C 94M</RID><BRK/>
<BRK/>
                      <SUB>Slump</SUB> test      <RID>ASTM C 143/C 143M</RID>     One for each<BRK/>
                                                            concrete load<BRK/>
                                                            at point of<BRK/>
                                                            discharge and<BRK/>
                                                            one for each<BRK/>
                                                            set of<BRK/>
                                                            compressive<BRK/>
                                                            strength test<BRK/>
<BRK/>
                      <SUB>Air Content</SUB>     <RID>ASTM C 231</RID>            One for each<BRK/>
                      by pressure                           set of compres-<BRK/>
                      method                                sive-strength<BRK/>
                                                            tests<BRK/>
<BRK/>
                      Compression     <RID>ASTM C 31/C 31M</RID>       One set of six<BRK/>
                      test                                  standard cyl-<BRK/>
                      specimens                             inder speci-<BRK/>
                                                            mens for each<BRK/>
                                                            compressive<BRK/>
                                                            strength test<BRK/>
<BRK/>
            Curing of compression test specimens must be the same as<BRK/>
            the curing method used for the precast-concrete structural<BRK/>
            members.<BRK/>
<BRK/>
                      Concrete                              Each time a set<BRK/>
                      temperature                           of compression-<BRK/>
                                                            test specimens<BRK/>
                                                            is made<BRK/>
<BRK/>
                      Compressive     <RID>ASTM C 39/C 39M</RID>       One set for<BRK/>
                      strength tests                        every ten<BRK/>
                                                            structural mem-<BRK/>
                                                            bers, or frac-<BRK/>
                                                            tion thereof,<BRK/>
                                                            cast in any one<BRK/>
                                                            day; two speci-<BRK/>
                                                            mens tested at<BRK/>
                                                            7 calendar<BRK/>
                                                            days, three<BRK/>
                                                            specimens<BRK/>
                                                            tested at 28<BRK/>
                                                            calendar days,<BRK/>
                                                            and one<BRK/>
                                                            specimen re-<BRK/>
                                                            tained in<BRK/>
                                                            reserve for<BRK/>
                                                            testing if<BRK/>
                                                            required<BRK/>
<BRK/>
         Lightweight  Sampling        <RID>ASTM C 172</RID>            As required for<BRK/>
         structural   fresh           except                each test<BRK/>
         concrete     concrete        modified for<BRK/>
                                      slump per<BRK/>
                                      <RID>ASTM C 94/C 94M</RID><BRK/>
<BRK/>
                      Slump test      <RID>ASTM C 143/C 143M</RID>     One for each<BRK/>
                      and unit        <RID>ASTM C 138/C 138M</RID>     concrete load<BRK/>
                      weight of                             at point of<BRK/>
                      fresh                                 discharge and<BRK/>
                      concrete                              one for each<BRK/>
                                                            set of compres-<BRK/>
                                                            sive-strength<BRK/>
                                                            tests<BRK/>
<BRK/>
                      Air content     <RID>ASTM C 173/C 173M</RID>     One for each<BRK/>
                      by volumetric                         set of compres-<BRK/>
                      method                                sive-strength<BRK/>
                                                            tests<BRK/>
<BRK/>
                      Compressive     <RID>ASTM C 31/C 31M</RID>       One set of six<BRK/>
                      test                                  standard<BRK/>
                      specimens                             cylinder speci-<BRK/>
                                                            mens for each<BRK/>
                                                            compressive-<BRK/>
                                                            strength test<BRK/>
<BRK/>
            The curing of Compressive Strength test specimens must be the<BRK/>
            same as the curing method used for the precast-concrete<BRK/>
            structural members.<BRK/>
<BRK/>
                      Concrete                              Each time a set<BRK/>
                      temperature                           of compression<BRK/>
                                                            test specimens<BRK/>
                                                            is made<BRK/>
<BRK/>
                      Compressive-    <RID>ASTM C 39/C 39M</RID>       One set for<BRK/>
                      strength tests                        every ten<BRK/>
                                                            structural mem-<BRK/>
                                                            bers, or frac-<BRK/>
                                                            tion thereof,<BRK/>
                                                            as in any one<BRK/>
                                                            day; two speci-<BRK/>
                                                            mens tested at<BRK/>
                                                            7 calendar<BRK/>
                                                            days, three<BRK/>
                                                            specimens<BRK/>
                                                            tested at 28<BRK/>
                                                            calendar days,<BRK/>
                                                            and one<BRK/>
                                                            specimen re-<BRK/>
                                                            tained in re-<BRK/>
                                                            serve for test-<BRK/>
                                                            ing if required<BRK/>
<BRK/>
                      Air-dried       <RID>ASTM C 330</RID>            One for each<BRK/>
                      <SUB>Unit Weight</SUB>                           compressive<BRK/>
                      at 28 calendar                        strength test<BRK/>
                      days</TBL><BRK/>
<BRK/>
<TXT>Submit test results on the same day that tests are made.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.8   DRAWINGS</TTL><BRK/>
<BRK/>
<TXT>Show type and location of all reinforcement, size and spacing of welds within <SUB>Fabrication Drawings</SUB>.</TXT><BRK/>
<BRK/>
<TXT>Indicate type and location of all anchorage devices, size and spacing of all welded connections, grouting and 
joint sealant details, and dimensions and locations of all openings in structural concrete sections within <SUB>Installation 
Drawings</SUB>.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   QUALITY OF CONCRETE</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.1   <SUB>Normal-Weight Concrete</SUB> Properties</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when normal-weight 
concrete will not be required.</NPR><BRK/>
<AST/><BRK/></NTE>
<MET><TBL><THD><BRK/>
                    <HL1>PROPERTY</HL1>                      <HL1>VALUE</HL1><BRK/></THD>
<BRK/>
         Design <SUB>Compressive Strength</SUB>           Not less than<BRK/>
         at 28 calendar days                   34.5 Megapascal<BRK/>
<BRK/>
         Maximum <SUB>Aggregate</SUB> size                19 millimeter<BRK/>
<BRK/>
         Maximum water/cement ratio            16 liter per<BRK/>
                                               42.5 kilogram<BRK/>
                                               sack of cement<BRK/>
<BRK/>
         Slump at point of concrete            Not to exceed<BRK/>
         discharge                             75 millimeter<BRK/>
<BRK/>
         Total air content by volume           Not less than 4 percent nor<BRK/>
         at point of concrete                  more than 8 percent<BRK/>
         discharge<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
                    <HL1>PROPERTY</HL1>                      <HL1>VALUE</HL1><BRK/></THD>
<BRK/>
         Design <SUB>Compressive Strength</SUB>           Not less than<BRK/>
         at 28 calendar days                   5,000 psi<BRK/>
<BRK/>
         Maximum <SUB>Aggregate</SUB> size                3/4 inch<BRK/>
<BRK/>
         Maximum water/cement ratio            4.25 gallons per<BRK/>
                                               94-pound <BRK/>
                                               sack of cement<BRK/>
<BRK/>
         Slump at point of concrete            Not to exceed<BRK/>
         discharge                             3 inches<BRK/>
<BRK/>
         Total air content by volume           Not less than 4 percent nor<BRK/>
         at point of concrete                  more than 8 percent<BRK/>
         discharge<BRK/></TBL>
</ENG><BRK/></SPT>
<SPT><TTL>2.1.2   <SUB>Lightweight Structural Concrete</SUB> Properties</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when light-weight 
structural concrete will not be required.</NPR><BRK/>
<AST/><BRK/></NTE>
<MET><TBL><THD><BRK/>
                     <HL1>PROPERTY</HL1>                   <HL1>VALUE</HL1><BRK/></THD>
<BRK/>
         Design compressive strength          Not less than<BRK/>
         at 28 calendar days                  34.5 Megapascal<BRK/>
<BRK/>
         Maximum size <SUB>Aggregate</SUB>               19 millimeter<BRK/>
<BRK/>
         Minimum cement content               Seven 42.5 kilogram<BRK/>
                                              sacks of cement per<BRK/>
                                              0.75 cubic meter<BRK/>
<BRK/>
         Slump at point of concrete           Not to exceed<BRK/>
         discharge                            75 millimeter<BRK/>
<BRK/>
         Total air content by volume          Not less than 4 percent<BRK/>
         at point of concrete                 nor more than 8 percent<BRK/>
         discharge<BRK/>
<BRK/>
         Air-dry density at 28 calendar       Not less than 1440 nor more<BRK/>
         days                                 than 1840 kilogram<BRK/>
                                              per cubic meter<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
                     <HL1>PROPERTY</HL1>                   <HL1>VALUE</HL1><BRK/></THD>
<BRK/>
         Design compressive strength          Not less than<BRK/>
         at 28 calendar days                  5,000 psi<BRK/>
<BRK/>
         Maximum size <SUB>Aggregate</SUB>               3/4 inch<BRK/>
<BRK/>
         Minimum cement content               Seven 94-pound<BRK/>
                                              sacks of cement per<BRK/>
                                              cubic yard <BRK/>
<BRK/>
         Slump at point of concrete           Not to exceed<BRK/>
         discharge                            3 inches <BRK/>
<BRK/>
         Total air content by volume          Not less than 4 percent<BRK/>
         at point of concrete                 nor more than 8 percent<BRK/>
         discharge<BRK/>
<BRK/>
         Air-dry density at 28 calendar       Not less than 90 nor more<BRK/>
         days                                 than 115 pounds<BRK/>
                                              per cubic foot<BRK/></TBL>
</ENG><BRK/></SPT>
</SPT><SPT><TTL>2.2   CONCRETE MATERIALS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Aggregates</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when precast structural-concrete 
sections will be fabricated of lightweight structural concrete.  Precast concrete 
elements that will be exposed to the weather must be fabricated of normal-weight 
concrete.  When an architectural finish, such as exposed aggregate, is required 
for exposed-to-view surfaces, refer to Section <SRF>03 45 00.00 40</SRF> PRECAST ARCHITECTURAL 
CONCRETE for concrete aggregate specifications.<BRK/>
<BRK/>
Delete the following paragraph when both normal-weight concrete and lightweight 
structural concrete is required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Aggregates must be fine and coarse conforming to <RID>ASTM C 33</RID> and the following:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when precast structural concrete sections 
will be fabricated of normal-weight concrete.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>Aggregates for normal-weight concrete must be fine and coarse conforming to <RID>ASTM C 33</RID> and the following:</LST><BRK/>
<BRK/>
<ITM>Where a structural member will be exposed to the weather meet the requirements of <RID>ASTM C 33</RID> 
for fine aggregate subject to abrasion, for coarse aggregate subject to severe exposure, and 
for all concrete aggregates where surface appearance of the concrete is important.<BRK/>
<BRK/>
Maximum size of coarse aggregate must be as specified.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2   Lightweight Aggregates</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraph when all precast 
structural-concrete sections will be fabricated of normal-weight concrete.  
Fire-resistance-rated structural sections may be fabricated of lightweight structural 
concrete, especially when the fire-resistance rating exceeds 2 hours.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Conform to <RID>ASTM C 330</RID> for  fine and coarse aggregates in structural concrete.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3   Portland Cement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If high early strength concrete is required, add Type III.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Portland cement must conform to <RID>ASTM C 150</RID>, Type [_____].]</TXT><BRK/>
<BRK/>
<TXT>[Blended hydraulic cement must conform to <RID>ASTM C 595</RID>, Type [_____].]</TXT><BRK/>
<BRK/>
<TXT>Use one brand and type of cement for formed concrete having exposed-to-view finished surfaces.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.4   Fly Ash</TTL><BRK/>
<BRK/>
<TXT>Fly ash [is required] [used] as an admixture [and] must conform to <RID>ASTM C 618</RID>, Class [C or F] with 4 percent 
maximum loss on ignition and between 15 to 35 percent maximum cement replacement by weight.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Ground granulated blast furnace slag is one of the materials listed in 
the EPA's Comprehensive Procurement Guidelines (CPG)<BRK/>
(<URL HREF="www.epa.gov/cpg/products/paint.htm">http://www.epa.gov/cpg/</URL>).  If the Architect/Engineer determines that use of 
certain materials meeting the CPG content standards and guidelines would result 
in inadequate competition, do not meet quality/ performance specifications, 
are available at an unreasonable price or are not available within a reasonable 
time frame, the Architect/Engineer may submit written justification and supporting 
documentation for not procuring designated items containing recovered material. 
Written justification may be submitted on a Request for Waiver Form to the NASA 
Environmental Program Manager for approval.  The Request for Waiver Form is 
located in the NASA Procedures and Guidelines (NPG 8830.1) (<URL HREF="http://nodis3.gsfc.nasa.gov">http://nodis3.gsfc.nasa.gov</URL>
).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/></SPT>
<SPT><TTL>2.2.5   Ground Granulated Blast Furnace (GGBF) Slag</TTL><BRK/>
<BRK/>
<TXT>GGBF slag [is required] [used] as an admixture [and] must conform to <RID>ASTM C 989</RID>, Grade [120] with between 25 
to 50 percent maximum cement replacement by weight.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.6   Air-Entraining Admixture</TTL><BRK/>
<BRK/>
<TXT>Admixture must be free of sodium chloride and nitrates and conform to <RID>ASTM C 260</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.7   Water</TTL><BRK/>
<BRK/>
<TXT>Water must be potable.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3   REINFORCEMENT MATERIALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following reinforcement materials that are not required.  
Concrete reinforcement materials are required for both conventionally reinforced 
and prestressed precast structural-concrete sections.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.3.1   Reinforcement Bars</TTL><BRK/>
<BRK/>
<TXT>Bars must be deformed and conform to <RID>ASTM A 615/A 615M</RID>, Grade 60, except that<MET> 9.5 millimeter diameter</MET> bars may 
be Grade 40.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when galvanized reinforcing bars for concrete 
reinforcement will not be required.  Galvanizing is recommended when the concrete 
cover over reinforcing bars is less than<MET> 38 millimeter</MET><ENG> 1-1/2 inches</ENG> for structural 
sections exposed to the weather.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Galvanize bars for structural sections exposed to the weather in accordance with <RID>ASTM A 153/A 153M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.2   Cold-Drawn Steel Wire</TTL><BRK/>
<BRK/>
<TXT>Wire must conform to <RID>ASTM A 82/A 82M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.3   Welded-Wire Fabric</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select one of the following paragraphs as applicable to the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide uncoated wire fabric conforming to <RID>ASTM A 185/A 185M</RID>.  Provide galvanized wire fabric in structural sections 
exposed to the weather.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.4   Supports for Concrete Reinforcement</TTL><BRK/>
<BRK/>
<TXT>Include bolsters, chairs, spacers, and other devices necessary for proper spacing, supporting, and fastening 
reinforcement bars and wire in place.</TXT><BRK/>
<BRK/>
<TXT>Provide wire supports conforming to <RID>ACI/MCP 405</RID>, <RID>ANSI A48.1</RID>, <RID>ANSI A48.2</RID>, <RID>ASTM E 648</RID>, <RID>ACI SP-66</RID> and <RID>CRSI 10MSP</RID>
.</TXT><BRK/>
<BRK/>
<TXT>Legs of supports in contact with formwork for sections that will be exposed to weather must be hot-dip galvanized 
after fabrication, plastic coated, or corrosion-resistant steel bar supports.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.4   PRESTRESSING MATERIALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when prestressed 
structural-concrete sections are not required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.4.1   Strand Tendons</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Strand tendons for prestressed concrete are primarily intended for use 
in pretensioned, bonded, prestressed concrete construction.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide uncoated, 7-strand, stress-relieved, steel wire conforming to <RID>ASTM A 416/A 416M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.2   Wire Tendons</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraph when wire tendons 
for prestressed concrete will not be required.  Prestressing steel wire is commonly 
used in prestressed linear concrete construction in which the steel wire ends 
are anchored by cold-end deformation (that is, button anchorage) or in which 
the steel wire ends are anchored by wedges.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide tendons conforming to <RID>ASTM A 421/A 421M</RID>, Type BA or Type WA, as required to suit the steel-wire anchorage 
method used.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.3   Steel-Bar Tendons</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when steel-bar 
tendons for prestressed concrete will not be required.  Steel bars are principally 
used in post tensioning.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide uncoated round steel bars conforming to <RID>ASTM A 322</RID>.<BRK/>
<BRK/>
Tensile properties of the bars after processing, when tested in accordance with <RID>ASTM A 370</RID>, must be as follows:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select one of the following values of tensile property and value as applicable 
to the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<MET><TBL><THD><BRK/>
     <HL1>TENSILE PROPERTY</HL1>       <HL1>VALUE NO. 1</HL1>           <HL1>VALUE NO. 2</HL1><BRK/></THD>
<BRK/>
     Ultimate tensile       1000 Megapascal min   1100 Megapascal min<BRK/>
     strength<BRK/>
<BRK/>
     Yield strength (0.2-   900 Megapascal min    970 Megapascal min<BRK/>
     percent offset)<BRK/>
<BRK/>
     Elongation at rupture  4 percent min         4 percent min<BRK/>
     in 20 diameters<BRK/>
<BRK/>
     Reduction on area at   25 percent min        20 percent min<BRK/>
     rupture<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
     <HL1>TENSILE PROPERTY</HL1>       <HL1>VALUE NO. 1</HL1>           <HL1>VALUE NO. 2</HL1><BRK/></THD>
<BRK/>
     Ultimate tensile       145,000 psi min       160,000 psi min <BRK/>
     strength<BRK/>
<BRK/>
     Yield strength (0.2-   130,000 psi min       140,000 psi min <BRK/>
     percent offset)<BRK/>
<BRK/>
     Elongation at rupture  4 percent min         4 percent min<BRK/>
     in 20 diameters<BRK/>
<BRK/>
     Reduction on area at   25 percent min        20 percent min<BRK/>
     rupture<BRK/></TBL>
</ENG><BRK/></SPT>
<SPT><TTL>2.4.4   Tendon Anchorages for Pretensioning</TTL><BRK/>
<BRK/>
<TXT>Provide tendon anchorages capable of anchoring reinforcement without slippage after seating.</TXT><BRK/>
<BRK/>
<TXT>Steel cases for prestressing steel strand must be prooftested by the manufacturer to at least 90 percent of the 
ultimate tensile strength of the strand.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.5   Tendon Anchorages for Post Tensioning</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when tendon anchorages 
for post tensioning will not be required.  Normally, pretensioning only is required 
for prestressed precast structural concrete sections for building construction.  
Post tensioning may be required for field connections.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Anchorages must be capable of developing 100 percent of the guaranteed ultimate tensile strength of the reinforcement 
for prestressed concrete without excessive deformation.  Provide anchorage plates of sufficient size to keep 
bearing pressures within the stress allowed by <RID>ACI/MCP 305</RID> and <RID>ACI 318/318R</RID> for the specified concrete strength 
at stressing.</TXT><BRK/>
<BRK/>
<TXT>Submit test data confirming the adequacy of anchorages.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.5   CONNECTION MATERIALS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.5.1   Steel Plates, Shapes, and Bars</TTL><BRK/>
<BRK/>
<TXT>Plates must conform to <RID>ASTM A 283/A 283M</RID>, Grade C, or to <RID>ASTM A 36/A 36M</RID>.</TXT><BRK/>
<BRK/>
<TXT>Structural-steel shapes must conform to <RID>ASTM A 36/A 36M</RID>.</TXT><BRK/>
<BRK/>
<TXT>Bar shapes, flats, and rounds must conform to <RID>ASTM A 675/A 675M</RID>, Grade 65, or <RID>ASTM A 36/A 36M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.2   Steel Anchor Bolts</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraph when anchor bolts 
will not be required. Anchor bolts are normally required for precast concrete 
column base connections.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Anchor bolts must be steel with steel hexagon nuts and steel washers.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.3   Electrodes for Welding</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when welded connections 
will not be required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Electrodes for manual shielded metal-arc welding connections consisting of structural quality carbon-steel members 
must conform to the AWS Code and be covered mild-steel electrodes conforming to <RID>AWS A5.1/A5.1M</RID>, E60 series.</TXT><BRK/>
<BRK/>
<TXT>Electrodes for welding steel bars for concrete reinforcement must conform to <RID>AWS D1.4/D1.4M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.4   Flexible Bearing Pads</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete one of the following paragraphs as applicable to the project.  
Delete paragraph heading and the following paragraphs when flexible bearing 
pads are not required.  Hardboard bearing pads are recommended for gravity connections 
having a bearing load not exceeding<MET> 1725 kilopascal</MET><ENG> 250 pounds per square inch 
(psi)</ENG>.  Elastomeric nonlaminated bearing pads are recommended for gravity connections 
having a bearing load not exceeding<MET> 5500 kilopascal</MET><ENG> 800 psi</ENG>.  Where the bearing 
load exceeds<MET> 5500 kilopascal</MET><ENG> 800 psi</ENG> or where there are small rotations, laminated 
type bearing pads designed and constructed to meet the requirements for loading 
and movement must be considered.  The location and size of flexible bearing 
pads must be indicated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide tempered hardboard pads not less than<MET> 3 millimeter</MET><ENG> 1/8 inch</ENG> in thickness, smooth-two-sides, conforming 
to <RID>AHA A135.4</RID>.</TXT><BRK/>
<BRK/>
<TXT>Pads must be molded or cut from elastomeric material.  Provide pad dimensions as indicated and within the following 
tolerances: thickness, plus or minus<MET> 1.5 millimeter</MET><ENG> 1/16 inch</ENG>; width, minus<MET> 3 to plus 6.5 millimeter</MET><ENG> 1/8 to plus 
1/4 inch</ENG>; length, plus or minus<MET> 3 millimeter</MET>.<ENG> 1/8 inch</ENG>  Material must be a vulcanized, chloroprene elastomeric 
compound conforming to the following tests:</TXT><BRK/>
<MET><TBL><THD><BRK/>
                <HL1>PROPERTY</HL1>                 <HL1>TEST METHOD</HL1>    <HL1>PERFORMANCE</HL1><BRK/></THD>
<BRK/>
            Hardness Shore A durometer   <RID>ASTM D 2240</RID>    70 plus or minus<BRK/>
                                                        5 points<BRK/>
<BRK/>
            Tensile strength             <RID>ASTM D 412</RID>,    Not less than<BRK/>
                                         Die C          17.2 Megapascal<BRK/>
<BRK/>
            Ultimate elongation          <RID>ASTM D 412</RID>,    Not less than<BRK/>
                                         Die C          300 percent<BRK/>
<BRK/>
            Resistance to oil aging:     <RID>ASTM D 471</RID>     Not more than<BRK/>
            change in volume after 70-                  plus 120<BRK/>
            hour immersion in ASTM                      percent<BRK/>
            oil No. 3 at 100 degrees C<BRK/>
<BRK/>
            Resistance to heat aging:    <RID>ASTM D 573</RID>     Plus 15<BRK/>
            change in original proper-                  percent,<BRK/>
            ties after 70 hours at 100                  minus 40<BRK/>
            degrees C tensile strength                  percent,<BRK/>
            ultimate elongation                         0 to plus 15<BRK/>
            hardness                                    points<BRK/>
<BRK/>
            Resistance to permanent      <RID>ASTM D 395</RID>     Not more than<BRK/>
            set:  compression set after  Method B       35 percent<BRK/>
            22 hours at 100 degrees C<BRK/>
<BRK/>
            Resistance to ozone:         <RID>ASTM D 1149</RID>    No cracks<BRK/>
            condition after exposure<BRK/>
            of a sample kept under a<BRK/>
            surface tensile strain of<BRK/>
            20 percent to an ozone<BRK/>
            concentration of 100 parts<BRK/>
            per million of air by<BRK/>
            volume in air for 100<BRK/>
            hours at 40 degrees C<BRK/>
<BRK/>
                                                        Not less than<BRK/>
                                                        91 kilogram per<BRK/>
                                                        25 linear millimeter<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
                <HL1>PROPERTY</HL1>                 <HL1>TEST METHOD</HL1>    <HL1>PERFORMANCE</HL1><BRK/></THD>
<BRK/>
            Hardness Shore A durometer   <RID>ASTM D 2240</RID>    70 plus or minus<BRK/>
                                                        5 points<BRK/>
<BRK/>
            Tensile strength             <RID>ASTM D 412</RID>,    Not less than<BRK/>
                                         Die C          2,500 psi <BRK/>
<BRK/>
            Ultimate elongation          <RID>ASTM D 412</RID>,    Not less than<BRK/>
                                         Die C          300 percent<BRK/>
<BRK/>
            Resistance to oil aging:     <RID>ASTM D 471</RID>     Not more than<BRK/>
            change in volume after 70-                  plus 120<BRK/>
            hour immersion in ASTM                      percent<BRK/>
            oil No. 3 at 212 degrees F<BRK/>
<BRK/>
            Resistance to heat aging:    <RID>ASTM D 573</RID>     Plus 15<BRK/>
            change in original proper-                  percent,<BRK/>
            ties after 70 hours at 212                  minus 40<BRK/>
            degrees F tensile strength                  percent,<BRK/>
            ultimate elongation                         0 to plus 15<BRK/>
            hardness                                    points<BRK/>
<BRK/>
            Resistance to permanent      <RID>ASTM D 395</RID>     Not more than<BRK/>
            set:  compression set after  Method B       35 percent<BRK/>
            22 hours at 212 degrees F<BRK/>
<BRK/>
            Resistance to ozone:         <RID>ASTM D 1149</RID>    No cracks<BRK/>
            condition after exposure<BRK/>
            of a sample kept under a<BRK/>
            surface tensile strain of<BRK/>
            20 percent to an ozone<BRK/>
            concentration of 100 parts<BRK/>
            per million of air by<BRK/>
            volume in air for 100<BRK/>
            hours at 104 degrees F<BRK/>
<BRK/>
                                                        Not less than<BRK/>
                                                        200 pounds per<BRK/>
                                                        linear inch <BRK/></TBL>
</ENG><BRK/></SPT>
</SPT><SPT><TTL>2.6   GROUTING MATERIALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraphs that are not applicable to the project.  
When fire-resistance rated precast structural-concrete sections are required, 
the applicable fire agency's requirements for grouting materials must be consulted.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Ground granulated blast furnace slag is one of the materials listed in 
the EPA's Comprehensive Procurement Guidelines (CPG)<BRK/>
(<URL HREF="www.epa.gov/cpg/products/paint.htm">http://www.epa.gov/cpg/</URL>).  If the Architect/Engineer determines that use of 
certain materials meeting the CPG content standards and guidelines would result 
in inadequate competition, do not meet quality/ performance specifications, 
are available at an unreasonable price or are not available within a reasonable 
time frame, the Architect/Engineer may submit written justification and supporting 
documentation for not procuring designated items containing recovered material. 
Written justification may be submitted on a Request for Waiver Form to the NASA 
Environmental Program Manager for approval.  The Request for Waiver Form is 
located in the NASA Procedures and Guidelines (NPG 8830.1) (<URL HREF="http://nodis3.gsfc.nasa.gov">http://nodis3.gsfc.nasa.gov</URL>
).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Portland cement must conform to <RID>ASTM C 150</RID>, Type I.</TXT><BRK/>
<BRK/>
<TXT>Blended hydraulic cement must conform to <RID>ASTM C 595</RID>, Type [_____].</TXT><BRK/>
<BRK/>
<TXT>Aggregate for cement grout must conform to <RID>ASTM C 404</RID>, Size No. 2.</TXT><BRK/>
<BRK/>
<TXT>Shrinkage-resistant grouting compound must be premixed and packaged ferrous aggregate conforming to <RID>ASTM C 1107/C 1107M</RID>
, for expansive grouts.</TXT><BRK/>
<BRK/>
<TXT>Water must be potable.</TXT><BRK/>
<BRK/>
<TXT>Provide two-component, mineral-filled, epoxy-polysulfide <SUB>epoxy-Resin Grout</SUB>  conforming to <RID>FS MMM-A-001993</RID>, Type 
I.</TXT><BRK/>
<BRK/>
<TXT>Provide two-component, epoxy-polyamide cured type <SUB>epoxy-Resin Adhesive</SUB>  conforming to <RID>AASHTO M 200</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7   BITUMINOUS JOINT SEALING MATERIALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when single- or 
double-tee roof slab structural sections are not required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Use asphalt bituminous cement conforming to <RID>ASTM D 312</RID>, Type IV.</TXT><BRK/>
<BRK/>
<TXT>Joint sealing tape must be<MET> 150 millimeter</MET><ENG> 6 inches</ENG> wide, multilayered, asphalt treated, glass-fiber reinforced, 
conforming to [<RID>ASTM D 2103</RID>] [<RID>ASTM D 4397</RID>] [<RID>FS UU-B-790</RID>, Type I, Grade C, Style 4,] with the following modification:</TXT><BRK/>
<BRK/>
<LST>Dry tensile strength must not be less than<MET> 6130 newton per meter</MET><ENG> 35 pounds per inch</ENG> width, both directions.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8   FABRICATION</TTL><BRK/>
<BRK/>
<SPT><TTL>2.8.1   Fabrication Tolerances</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following fabrication tolerances that are not required by 
the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Fabricate sections within the following tolerances:</TXT><BRK/>
<MET><TBL><BRK/>
            Overall dimensions               Plus or minus 3 millimeter<BRK/>
                                             per 3048 millimeter but not<BRK/>
                                             greater than 19.1 millimeter<BRK/>
                                             overall<BRK/>
<BRK/>
            Cross-sectional dimensions of    Plus or minus 3 millimeter<BRK/>
            up to 150 millimeter<BRK/>
<BRK/>
            Over 150 to 460 millimeter       Plus or minus 4.8 millimeter<BRK/>
<BRK/>
            Over 460 to 915 millimeter       Plus or minus 6.4 millimeter<BRK/>
<BRK/>
            Over 915 millimeter              Plus or minus 9.5 millimeter<BRK/>
<BRK/>
            Deviation from straight line     Not over 9.5 millimeter<BRK/>
            parallel to centerline of<BRK/>
            section up to 12.2 meter in<BRK/>
            length<BRK/>
<BRK/>
            12.2 to 18.3 meter in length     Not over 12.7 millimeter<BRK/>
<BRK/>
            Over 18.3 meter in length        Not over 19.1 millimeter<BRK/>
<BRK/>
            Deviation from camber indicated  Plus or minus 3 millimeter<BRK/>
            on the drawings                  per 3 meter<BRK/>
<BRK/>
            Ends out of square, up to 305    0.80 millimeter per 25.4<BRK/>
            millimeter in width or depth     millimeter of width or depth<BRK/>
<BRK/>
            Over 300 millimeter in width     0.80 plus 0.40 millimeter<BRK/>
            or depth                         per 25.4 millimeter of<BRK/>
                                             width or depth<BRK/>
<BRK/>
            Position of block-outs           Plus or minus 12.7 millimeter<BRK/>
<BRK/>
            Position of voids in hollow      Plus or minus 12.7 millimeter<BRK/>
            cored flat slabs, for both<BRK/>
            vertical and horizontal<BRK/>
            dimensions<BRK/>
<BRK/>
            Concrete cover over              Plus 6.4, minus 0 millimeter<BRK/>
            reinforcement<BRK/>
<BRK/>
            Position of tendons for pre-     Plus or minus 3.2 millimeter<BRK/>
            stressed concrete<BRK/>
<BRK/>
            Position of deflection points    Plus or minus 152 millimeter<BRK/>
            for deflected strand tendons<BRK/>
            for prestressed concrete<BRK/>
<BRK/>
            Position of weld plates          Plus or minus 25.4 millimeter<BRK/>
<BRK/>
            Position of lateral              Plus or minus 25.4 millimeter<BRK/>
            anchorage points<BRK/>
<BRK/>
            Position of pickup devices       Plus or minus 152 millimeter<BRK/></TBL>
</MET><ENG><TBL><BRK/>
            Overall dimensions               Plus or minus 1/8 inch per<BRK/>
                                             10 feet but not greater<BRK/>
                                             than 3/4 inch overall<BRK/>
<BRK/>
            Cross-sectional dimensions of    Plus or minus 1/8 inch<BRK/>
            up to 6 inches<BRK/>
<BRK/>
            Over 6 to 18 inches              Plus or minus 3/16 inch<BRK/>
<BRK/>
            Over 18 to 36 inches             Plus or minus 1/4 inch<BRK/>
<BRK/>
            Over 36 inches                   Plus or minus 3/8 inch<BRK/>
<BRK/>
            Deviation from straight line     Not over 3/8 inch<BRK/>
            parallel to centerline of<BRK/>
            section up to 40 feet in<BRK/>
            length<BRK/>
<BRK/>
            40 to 60 feet in length          Not over 1/2 inch<BRK/>
<BRK/>
            Over 60 feet in length           Not over 3/4 inch<BRK/>
<BRK/>
            Deviation from camber indicated  Plus or minus 1/8 inch per<BRK/>
            on the drawings                  10 feet<BRK/>
<BRK/>
            Ends out of square, up to 12     1/32 inch per inch of<BRK/>
            inches in width or depth         width or depth<BRK/>
<BRK/>
            Over 12 inches in width or       1/32 inch plus 1/64 inch<BRK/>
            depth                            per inch of width or depth<BRK/>
<BRK/>
            Position of block-outs           Plus or minus 1/2 inch<BRK/>
<BRK/>
            Position of voids in hollow      Plus or minus 1/2 inch<BRK/>
            cored flat slabs, for both<BRK/>
            vertical and horizontal<BRK/>
            dimensions<BRK/>
<BRK/>
            Concrete cover over              Plus 1/4, minus 0 inch<BRK/>
            reinforcement<BRK/>
<BRK/>
            Position of tendons for pre-     Plus or minus 1/8 inch<BRK/>
            stressed concrete<BRK/>
<BRK/>
            Position of deflection points    Plus or minus 6 inches<BRK/>
            for deflected strand tendons<BRK/>
            for prestressed concrete<BRK/>
<BRK/>
            Position of weld plates          Plus or minus 1 inch<BRK/>
<BRK/>
            Position of lateral              Plus or minus 1 inch<BRK/>
            anchorage points<BRK/>
<BRK/>
            Position of pickup devices       Plus or minus 6 inches<BRK/></TBL>
</ENG><BRK/></SPT>
<SPT><TTL>2.8.2   Forms</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Structural-section dimensions, cross-sections, and other details as required 
by the project must be indicated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Use forms and form-facing materials that are nonreactive with concretesuch as wood, metal, plastic, or other 
approved materials.  Conform to the shapes, lines, and dimensions indicated and are within the limits of the 
specified fabrication tolerances.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.3   Reinforcement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Reinforcement types, sizes, and arrangement as required for structural 
strength after the structural sections have been installed must be indicated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide types, sizes, and arrangement as indicated on the approved drawings.  Details of reinforcement must be 
in accordance with <RID>ACI/MCP 305</RID> and <RID>ACI 318/318R</RID>, unless otherwise specified.</TXT><BRK/>
<BRK/>
<TXT>Place and secure steel bars, welded-wire fabric, and other reinforcement by means of metal bar supports and spacers.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when prestressed structural-concrete sections 
are not required by the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Place tendons and anchorages in accordance with <RID>ACI/MCP 305</RID> and <RID>ACI 318/318R</RID>.  End anchorages that will be permanently 
protected with concrete must be free of loose rust, grease, oil, paint, and other foreign matter.  Bearing surface 
between anchorages and concrete must be perpendicular to and concentric with the tendons and the line of action 
prestressing force.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Revise the following paragraphs when not applicable to the project.  
Concrete cover for reinforcement must be indicated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Concrete cover for reinforcement must be in accordance with <RID>ACI/MCP 305</RID> and <RID>ACI 318/318R</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.4   Built-In Anchorage Devices</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Anchorage devices that are to be embedded in the precast structural concrete 
sections must be indicated.  Anchorage devices include weld plates, bearing 
plates and steel shapes.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Position, anchor, and locate anchorage devices where they do not affect the position of the main reinforcement 
or placing concrete. Bearing plates must be set level, aligned properly, and anchored in the exact location indicated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.5   Lifting Devices</TTL><BRK/>
<BRK/>
<TXT>Provide lifting devices designed for 100-percent impact, and of materials sufficiently ductile to ensure visible 
deformation before fracture.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.6   Blockouts</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Blockouts or openings in slabs that would require the cutting of primary 
reinforcement if such openings were to be cut in the field must be cast in the 
unit during fabrication and must be indicated. The maximum size of field-cut 
openings may be from<MET> 150 to 300 millimeter</MET><ENG> 6 to 12 inches</ENG> depending on the type 
of unit used such as the inside diameter of the voids in hollow cored flat slabs 
and the spacing of reinforcement.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide blockouts as indicated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.7   <SUB>Pretensioning</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when prestressed 
structural-concrete sections are not required by the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Pretensioning of tendons may be accomplished either by the single-strand or multiple-strand tensioning method.  
Determine the prestressing force by measuring the tendon elongation, either by checking the jack pressure on 
a recently calibrated gage or by use of a recently calibrated dynamometer. Correct any discrepancy that exceeds 
5 percent.  Base elongation requirements on the load-elongation curves for the type of tendon used.  The total 
loss of prestress due to unreplaced broken tendons must not exceed 2 percent of the total prestress.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.8   Concrete Mixing and Conveying</TTL><BRK/>
<BRK/>
<TXT>Measure concrete materials, concrete batching plant, concrete mixers, and concrete mixing in accordance with <RID>
ASTM C 94/C 94M</RID>.<BRK/>
<BRK/>
Handle concrete to prevent segregation and loss of concrete mix materials.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.9   Preparations for Placing Concrete</TTL><BRK/>
<BRK/>
<TXT>Keep form interiors and reinforcement free of accumulations of hardened concrete, form-parting compound, standing 
water, ice, snow, or other deleterious substances.  Secure in position, inspect and approve reinforcement and 
other embedded items .</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.10   Weather Limitations</TTL><BRK/>
<BRK/>
<TXT>Do not place concrete when temperature of the atmosphere is below<MET> 5 degrees C</MET><ENG> 40 degrees F</ENG> nor during rain, sleet, 
and snow unless adequate protection is provided.  Protection during inclement weather must prevent the entry 
of rain, sleet, or snow into the forms or into the fresh concrete.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.11   Concrete Placing</TTL><BRK/>
<BRK/>
<TXT>Depost concrete so that no concrete will be placed on concrete that has hardened sufficiently to cause formation 
of seams or planes of weakness.  Consolidate concrete in a manner that will prevent segregation and will produce 
concrete free of honeycomb or rock pockets and with the required surface finish.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.12   Identification Markings</TTL><BRK/>
<BRK/>
<TXT>Clearly mark each structural section in a permanent manner to indicate its location and orientation in the building 
and the pickup points.</TXT><BRK/>
<BRK/>
<TXT>Each structural section must have the date of casting plainly indented in the unexposed face of the concrete.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.13   Finishing Unformed Surfaces</TTL><BRK/>
<BRK/>
<TXT>Trowel finish unformed surfaces unless otherwise specified. <TST>Provide smooth surface  free of trowel marks, uniform 
in texture and appearance, and be plane to a tolerance not exceeding<MET> 3.2 millimeter in 3048 millimeter</MET><ENG> 1/8 inch 
in 10 feet</ENG> when tested with a<MET> 3000 millimeter</MET><ENG> 10-foot</ENG> straightedge.</TST></TXT><BRK/>
<BRK/>
<TXT>Provide top surfaces of sections that are to receive concrete topping after installation with a transversely 
scarified scratch finish and remove laitance.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.14   Curing</TTL><BRK/>
<BRK/>
<TXT>Cure concrete by keeping the concrete damp for not less than 7 calendar ays if made of Type I portland cement 
and for not less than 3 calendar days if made of Type III portland cement.  For each decrease of<MET> 3 degrees below 
21 degrees C</MET><ENG> 5 degrees below 70 degrees F</ENG> in the average curing temperature, increase the curing period by 4 
calendar days for concrete made of Type I portland cement and by 2 calendar days for concrete made of Type III 
portland cement.</TXT><BRK/>
<BRK/>
<TXT>Curing by low-pressure steam, steam vapor, radiant heat and moisture, or other acceptable process may be employed 
provided that the compressive strength of the concrete is equal to that obtained by moist curing and the 28-day 
compressive strength of the concrete meets the requirements specified, as determined by test cylinders of the 
same concrete cured by the same curing process.</TXT><BRK/>
<BRK/>
<TXT>Do not remove sections from their casting beds until the curing period is completed or concrete has attained 
at least 75 percent of its design compressive strength.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.15   Protection of Concrete After Placing</TTL><BRK/>
<BRK/>
<TXT>Protection must meet the requirements of <RID>ACI/MCP 205</RID> for hot or cold weather, as applicable.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.16   <SUB>Detensioning</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when prestressed 
structural-concrete sections are not required by the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Detensioning of tendons must not be done until the concrete compressive strength, as indicated by test cylinders, 
is as follows:</TXT><BRK/>
<MET><TBL><THD><BRK/>
    <HL1>TYPE OF REINFORCEMENT</HL1>       <HL1>TRANSFER STRENGTH OF CONCRETE</HL1><BRK/></THD>
<BRK/>
    Concentrically stressed     Not less than 20 Megapascal<BRK/>
    sections<BRK/>
<BRK/>
    Eccentrically stressed      Not less than 24.1 Megapascal<BRK/>
    sections<BRK/>
<BRK/>
    Beams or other sections     Not less than 27.6 Megapascal<BRK/>
    in which camber must be<BRK/>
    minimized<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
    <HL1>TYPE OF REINFORCEMENT</HL1>       <HL1>TRANSFER STRENGTH OF CONCRETE</HL1><BRK/></THD>
<BRK/>
    Concentrically stressed     Not less than 3,000 psi<BRK/>
    sections<BRK/>
<BRK/>
    Eccentrically stressed      Not less than 3,500 psi<BRK/>
    sections<BRK/>
<BRK/>
    Beams or other sections     Not less than 4,000 psi<BRK/>
    in which camber must be<BRK/>
    minimized<BRK/></TBL>
</ENG><BRK/>
<TXT>Remove test cylinders to be used to establish the compressive strength of the concrete from the casting bed at 
least 1 hour prior to the start of the detensioning operation.  Allow test cylinders from heat-cured casting 
beds to cool for approximately 1/2 hour prior to capping, and allow caps of sulfur compound to cure for 1/2 hour 
prior to the compressive-strength test.</TXT><BRK/>
<BRK/>
<TXT>If concrete has been heat cured, the detensioning operation must be done following the curing period while the 
concrete is still warm and moist to avoid cracking or undesirable stresses in the concrete.</TXT><BRK/>
<BRK/>
<TXT>Prior to detensioning operations, forms, ties, inserts, holddowns, or other devices that would restrict the longitudinal 
movement of the sections along the casting bed must be removed or loosened to provide free movement of the structural 
section.  Alternately, perform detensioning so that longitudinal movement is precluded.</TXT><BRK/>
<BRK/>
<TXT>In detensioning operations, prestressing forces must be kept nearly symmetrical about the vertical axis of the 
section and be applied in a manner that will minimize sudden or shock loading.  Limit maximum eccentricity about 
the vertical axis to one strand.  Detensioning of pretensioned tendons may be accomplished either by gradual 
release of the tensioning jacks or by heat-cutting the tendons in accordance with an approved pattern and sequence 
to prevent severe unbalancing of the loading.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.17   Finishing Formed Surfaces</TTL><BRK/>
<BRK/>
<TXT>Upon removal of forms, repair and patch defective areas. Limit defective areas to holes left by tie rods and 
other temporary inserts and to honeycomb or rock pockets not deep enough to expose the reinforcement and not 
located in bearing areas.  Cut out defective areas to solid concrete and cleaned.  Patches on lower side of sections, 
near the center or in areas of variable tensile strength, must be bonded by a two-component epoxy-polysulfide 
or epoxy-polyamine bonding adhesive.  Other areas will be dampened with water and patched with portland cement 
grout.  Where the concrete surface will be exposed to view, the patches, when dry, must match the surrounding 
concrete.</TXT><BRK/>
<BRK/>
<TXT>Formed surfaces of sections that will be concealed by other construction can have the standard smooth finish 
having the texture imparted by the forms.  Repair and patch defective areas  as specified and all fins and other 
projections removed.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph and specify the required finish when an 
architectural finish is required.  For an exposed-aggregate finish refer to 
Section <SRF>03 45 00.00 40</SRF> PRECAST ARCHITECTURAL CONCRETE.  The location of precast 
structural concrete sections having an architectural finish must be indicated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide grout finish on formed surfaces of sections that are to be exposed-to-view after installation.  Final 
color of the grout, when dry, must be the same for all concrete surfaces.  Spread over dampened concrete surface 
with clean burlap pads, carpet, or sponge rubber floats to fill pits, air bubbles, and surface holes.  Remove 
excess grout by scraping and then rubbing the surface with clean burlap or carpet to remove visible grout film.  
In hot dry weather, kept grout damp by means of fog-spraying during the setting period.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   GENERAL</TTL><BRK/>
<BRK/>
<TXT>Install sections in accordance with the approved drawings and as specified.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2   ANCHORAGE ITEMS EMBEDDED IN OTHER CONSTRUCTION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the paragraph heading and the following paragraph when precast 
structural-concrete sections will not be connected to cast-in-place concrete 
construction or masonry construction.  Such anchorage items include anchor bolts, 
steel dowels, and steel bearing plates.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Deliver items to the site before the start of other construction.  Provide setting drawings, templates, instructions, 
and directions for the installation of anchorage items.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3   INSTALLATION OF FLEXIBLE BEARING PADS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when flexible bearing 
pads are not required.  Bearing pads must be indicated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Install pads where indicated, set in correct position, and have a uniform bearing.  Keep in the correct position 
while placing sections.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4   STRENGTH OF STRUCTURAL SECTIONS AT INSTALLATION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete one of the following paragraphs as applicable to the project.  
Select the first paragraph except when the project schedule indicates installation 
of 28-day structural sections.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Do not install sections until concrete has attained the specified minimum laboratory strength at 28 calendar 
days.</TXT><BRK/>
<BRK/>
<TXT>Do not install sections before 28 calendar days from the date of casting has elapsed unless approval has been 
obtained to make one compressive-strength test, <RID>ASTM C 39/C 39M</RID>, and one flexural strength test using simple 
beam with third point loading, <RID>ASTM C 78</RID>, on field cured concrete test specimens, <RID>ASTM C 31/C 31M</RID>, for each individual 
structural section to determine the strength of the concrete.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5   INSTALLATION TOLERANCES</TTL><BRK/>
<BRK/>
<TXT>Install sections within the following tolerances:</TXT><BRK/>
<MET><TBL><BRK/>
          Deviation in location from       Plus or minus 6.4 millimeter<BRK/>
          indicated<BRK/>
<BRK/>
          Deviation from plumb for         Not over 6.4 millimeter<BRK/>
          columns in any story or 6.1<BRK/>
          meter maximum<BRK/>
<BRK/>
          In 12.2 meter or more            Not over 12.7 millimeter<BRK/>
<BRK/>
          Deviation from elevations        Not over 6.4 millimeter<BRK/>
          indicated for girders, beams,<BRK/>
          joists, and slabs in any bay or<BRK/>
          6.1 meter maximum<BRK/>
<BRK/>
          In 12.2 meter or more            Not over 12.7 millimeter<BRK/>
<BRK/>
          Difference between adjacent      Plus or minus 1.6 millimeter<BRK/>
          structural sections in erected   per 3000 millimeter but not<BRK/>
          position                         greater than 6.4 millimeter<BRK/>
                                           overall<BRK/></TBL>
</MET><ENG><TBL><BRK/>
          Deviation in location from       Plus or minus 1/4 inch<BRK/>
          indicated<BRK/>
<BRK/>
          Deviation from plumb for         Not over 1/4 inch<BRK/>
          columns in any story or 20<BRK/>
          feet maximum<BRK/>
<BRK/>
          In 40 feet or more               Not over 1/2 inch<BRK/>
<BRK/>
          Deviation from elevations        Not over 1/4 inch<BRK/>
          indicated for girders, beams,<BRK/>
          joists, and slabs in any bay or<BRK/>
          20 feet maximum<BRK/>
<BRK/>
          In 40 feet or more               Not over 1/2 inch<BRK/>
<BRK/>
          Difference between adjacent      Plus or minus 1/16 inch<BRK/>
          structural sections in erected   per 10 feet but not<BRK/>
          position                         greater than 1/4 inch<BRK/>
                                           overall<BRK/></TBL>
</ENG><BRK/></SPT>
<SPT><TTL>3.6   PLACING FRAMING STRUCTURAL SECTIONS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when framing structural 
sections such as columns, beams, girders, and joists will not be required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Place supporting sections, including anchorage items attached to or embedded in other construction before placing 
sections is started.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraphs when precast concrete columns with attached 
steel bearing plates will not be required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Installation of precast concrete columns with attached steel bearing plates must be as follows:</TXT><BRK/>
<BRK/>
<LST>Concrete and steel plate bearing surfaces must be cleaned of laitance, dirt, oil, grease, and other foreign 
materials.  Roughen concrete surface.</LST><BRK/>
<BRK/>
<LST>Space between the top of the concrete bearing surface and the bottom of the steel plate must be approximately 
1/24 of the width of the bearing plate, but not less than<MET> 12.7 millimeter</MET><ENG> 1/2 inch</ENG> for bearing plate 
that is less than<MET> 300 millimeter</MET><ENG> 12 inches</ENG> wide.  Support and align bearing plate on steel wedges or 
shims.</LST><BRK/>
<BRK/>
<LST>After precast concrete columns have been positioned and braced and anchor bolts tightened, the space 
between the top of the bearing surface and the bottom of the steel bearing plate must be grouted.</LST><BRK/>
<BRK/>
<TXT>Do not remove wedges or shims shall not be removed but, when protruding, cut off flush with the edge of the steel 
bearing plate prior to grouting.</TXT><BRK/>
<BRK/>
<TXT>Install sections plumb, level, and in alignment within the limits of the installation tolerances specified.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7   PLACING SLAB STRUCTURAL SECTIONS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the paragraph heading and the following paragraphs when slab structural 
sections, such as single- and double-tee slabs and hollow-cored flat slabs will 
not be required.  Slab structural-sections may be placed over structural-steel 
framing members, precast structural-concrete framing sections, cast-in-place 
structural-concrete framing sections, or bearing walls, or a combination thereof.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Supporting sections, including bearing pads or plates, must be in place before placing sections is started.  
Slab structural sections must be placed on supporting construction with ends bearing on the structural framing 
sections or bearing walls as indicated.  End bearings must  not be less than<MET> 75 millimeter</MET><ENG> 3 inches</ENG>.  Accurately 
align slabs end to end with sides and ends butted together.  Provide grouting void at sides and ends of the slabs 
as indicated.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when electrical-raceway hollow-cored flat-slab 
structural sections will not be required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Place electrical raceway hollow-cored flat-slab structural sections in straight alignment for the entire length 
of run of the hollow cores and with close alignment between hollow cores at the ends of abutting slab structural 
sections.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8   WELDED CONNECTIONS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Welded connections are the most commonly used type of connection.  Other 
types of connections that may be employed are gravity, structural-steel bolted, 
post-tensioned, cast-in-place reinforced-concrete, and doweled connections. 
Connection details must be indicated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Welding reinforcing steel, metal inserts, and connections in precast-concrete structural-member construction 
must be in accordance with <RID>AWS D1.4/D1.4M</RID>.</TXT><BRK/>
<BRK/>
<TXT>Welding structural steel connections must be in accordance with <RID>AWS D1.1/D1.1M</RID> Code.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9   GROUTING CONNECTIONS AND JOINTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when precast structural-concrete 
framing sections or floor-slab structural sections or both will not be required.  
When fire-resistance-rated precast structural-concrete sections are required, 
consult the applicable fire agency's requirements for grouting joints.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>After sections have been placed and connected, grout open spaces at connections and joints.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when shrink-resistant grout only is required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Cement grout must be of 1 part cement, 2-1/2 parts of specified aggregate for cement grout, and not more than<MET>
 17 liter</MET><ENG> 4-1/2 gallons</ENG> of water per<MET> 42.6 kilogram</MET><ENG> 94-pound</ENG> sack of cement.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when cement grout only is required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Mix shrink-resistant grout compound with water to provide a flowable mixture without segregation or bleeding.</TXT><BRK/>
<BRK/>
<TXT>Provide forms or other approved methods to retain the grout in place.  Pack spaces with grout until the voids 
are completely filled.  Flush grout at slab structural sections with top surface of the slab and remove excess.  
Keep grout damp for not less than 24 hours.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraphs when cement grout only is required or 
when epoxy-resin grout or adhesive instead of shrink-resistant grout is not 
required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Epoxy-resin grout or adhesive may be used in lieu of shrink-resistant grout.  Installation of epoxy-resin grout 
or adhesive must be in accordance with the manufacturer's printed instructions.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when electrical raceway hollow-cored flat-slab 
structural sections are not required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Open spaces at abutting ends of electrical raceway hollow-cored flat-slab structural sections must be sealed 
with pressure-sensitive tape.  Hollow cores used for electrical raceways must be kept free from grout and other 
foreign materials.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10   SEALING JOINTS IN ROOF SLABS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when roof slab 
structural sections will not be required.  Where fire-resistance-rated roof 
slab structural sections are required, the applicable fire agency's requirements 
for sealing joints must be consulted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>After precast-concrete roof slab sections have been placed and connected, seal open spaces at connections and 
the top portion of joints.</TXT><BRK/>
<BRK/>
<TXT>Fill keyways and joints at ridges, hips, and connections with cement grout.  Level with the top surfaces of slabs, 
remove excess grout, and apply a smooth finish.</TXT><BRK/>
<BRK/>
<TXT>Seal other joints with bituminous joint-sealing material. Center joint-sealing tape over the joint and embedded 
in hot bituminous cement.  Lap Ends not less than<MET> 100 millimeter</MET><ENG> 4 inches</ENG>.  Remove excess bitumen and provide 
a smooth tape surface.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11   OPENINGS IN SLAB STRUCTURAL SECTIONS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The maximum size of field-cut openings is governed by the spacing of 
reinforcement and the inside diameter of the voids in hollow-cored flat slabs.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Cut and fit sections as required for other work projecting through, or adjacent to, the members.  Cuts must be 
straight and at 90 degrees to the surfaces without breaking or spalling the edges.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when hollow-cored flat-slab structural 
sections will not be required.  Openings larger than the width of a slab structural 
section must be framed with supporting members.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Openings in hollow-core flat-slab sections having any dimension more than the inside diameter of the hollow cores 
and not exceeding the width of the slab structural section must be reinforced by means of hung steel angle saddle 
headers.  Headers must be shop prime-coat painted and as indicated on the approved drawings.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.12   TOUCHUP PAINTING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraph when precast structural-concrete 
sections will not be supported by steel structural members.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>After sections have been installed, scarred surfaces on steel supporting members and weld plates must be wire 
brushed, cleaned, and touchup painted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.13   PROTECTION AND CLEANING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Where architectural finishes such as exposed-aggregate finish are specified 
for exposed-to-view surfaces, such surfaces must be cleaned as specified in 
Section <SRF>03 45 00.00 40</SRF> PRECAST ARCHITECTURAL CONCRETE.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Protect exposed-to-view surfaces against staining and other damage until completion of the work.</TXT><BRK/>
<BRK/>
<TXT>Upon completion of installation, swept clean and leave ready slab surfaces  to receive concrete floor topping, 
roofing, or other covering.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.14   INSPECTION AND ACCEPTANCE PROVISIONS</TTL><BRK/>
<BRK/>
<SPT><TTL>3.14.1   Evaluation of Compressive Strength Tests</TTL><BRK/>
<BRK/>
<TXT>Concrete quality control tests will be evaluated as specified.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when normal-weight concrete will not be 
required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Normal-weight concrete delivered to the point of placement having a slump or total air content outside the values 
specified must not be used in the work.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraph when lightweight structural concrete will 
not be required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Lightweight structural concrete delivered to the point of placement having a unit weight of fresh concrete that 
varies more than 2 percent from the design mix wet unit weight or having a slump or total air content outside 
the values specified must not be used in the work.</TXT><BRK/>
<BRK/>
<TXT>Compressive-strength tests will be considered satisfactory if the average of any group of 5 consecutive compressive-strength 
tests that may be selected is in each instance equal to or greater than the 28-day design compressive strength 
or if not more than one compressive-strength test in 10 has a value less than 90 percent of the 28-day design 
compressive-strength.</TXT><BRK/>
<BRK/>
<TXT>If the compressive-strength tests fail to meet the minimum requirements specified, the sections fabricated of 
concrete represented by such tests will be considered deficient in strength and subject to the provisions specified.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.14.2   Dimensional Tolerances</TTL><BRK/>
<BRK/>
<TXT>Members having any dimension outside the limits for fabrication tolerances specified will be rejected.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.14.3   Surface-Finish Requirements</TTL><BRK/>
<BRK/>
<TXT>Sections will be rejected for any of the following surface-finish deficiencies:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the first of the following paragraphs when architectural finishes 
such as exposed-aggregate finish, are not required for exposed-to-view surfaces.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>Exposed-to-view surfaces having architectural finishes that do not match the color, aggregate size and 
distribution, and texture of the approved sample for the exposed-to-view finish</LST><BRK/>
<BRK/>
<LST>Exposed-to-view formed surfaces that contain cracks, spalls, air bubbles, honeycomb, rock pockets, or 
stains or other discoloration that cannot be removed by cleaning</LST><BRK/>
<BRK/>
<LST>Concealed formed surfaces that contain cracks in excess of<MET> 0.25 millimeter</MET><ENG> 0.01 inch</ENG> wide; cracks or 
any other surface deficiency that penetrates to the reinforcement regardless of the width of crack or 
size of other deficiency; honeycomb and rock pockets located in bearing surfaces; and spalls except minor 
breakage at corners</LST><BRK/>
<BRK/>
<LST>Unformed surfaces that contain cracks and other surface deficiencies as specified for concealed formed 
surfaces</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.14.4   Strength of Structural Members</TTL><BRK/>
<BRK/>
<TXT>Strength of precast structural-concrete sections will be considered potentially deficient if they fail to comply 
with the requirements that control the strength of the structural members, including the following conditions:</TXT><BRK/>
<BRK/>
<LST>Failure to meet compressive strength tests</LST><BRK/>
<BRK/>
<LST>Reinforcement and pretensioning and detensioning of tendons of prestressed concrete not conforming to 
the requirements specified</LST><BRK/>
<BRK/>
<LST>Concrete curing and protection of structural sections against extremes in temperature during curing not 
conforming to the requirements specified</LST><BRK/>
<BRK/>
<LST>Structural sections damaged during handling and erection</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.14.5   Testing Structural Sections for Strength</TTL><BRK/>
<BRK/>
<TXT>When there is evidence that the strength of precast structural-concrete sections does not meet specification 
requirements, cores drilled in hardened concrete for compressive strength determination must be made in accordance 
with <RID>ASTM C 42/C 42M</RID> and as follows:</TXT><BRK/>
<BRK/>
<LST><TST>Take at least three representative cores from the precast structural concrete sections that are considered 
potentially deficient.</TST><BRK/>
<BRK/>
<TST>Test cores saturated-surface-dry if the concrete they represent will be wet at all times during the use 
of the completed structure.</TST><BRK/>
<BRK/>
<TST>Test cores air-dry if the concrete they represent will be dry at all times during the use of the completed 
structure.</TST></LST><BRK/>
<BRK/>
<LST>Strength of cores will be considered satisfactory if their average is equal to or greater than the 28-day 
design compressive strength of<MET> 150 by 300 millimeter</MET><ENG> 6-by 12-inch</ENG> cylinders.</LST><BRK/>
<BRK/>
<LST>Fill core holes solidly with patching mortar and finished to match the adjacent concrete surfaces.</LST><BRK/>
<BRK/>
<TXT>If the results of the core tests are unsatisfactory or if core tests are impractical to obtain, <TST>static load tests 
must be made of a structural section</TST> and will be evaluated in accordance with <RID>ACI/MCP 305</RID> and <RID>ACI 318/318R</RID>, except 
that the superimposed test load must be as specified for the proof-test method of strength design.</TXT><BRK/>
<BRK/>
<TXT>Sections that are found inadequate by the core tests or by the results of static load tests must be replaced 
with sections that meet the specified requirements.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.14.6   Inspection of Welding</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph heading and the following paragraphs when inspection 
of welding will not be required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><TST>Perform inspection of welding</TST>in accordance with <RID>AWS D1.1/D1.1M</RID>, Section entitled, "Inspection," and as follows:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the following paragraphs that are not applicable to the project.  
The location of welds requiring inspection and the type of inspection must be 
indicated.  The liquid-penetration inspection of welds is the most economical 
and commonly used method.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>Liquid-penetration inspection of welds must conform to <RID>ASTM E 165</RID>.<BRK/>
<BRK/>
Magnetic-particle inspection of welds must conform to <RID>ASTM E 709</RID>.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.14.7   Structural Sections-in-Place</TTL><BRK/>
<BRK/>
<TXT>Sections-in-place will be rejected for any one of the following deficiencies:</TXT><BRK/>
<BRK/>
<LST>Sections not conforming to the requirements for installation tolerances specified</LST><BRK/>
<BRK/>
<LST>Sections that are damaged during construction operations</LST><BRK/>
<BRK/>
<NED/><LST>Sections having exposed-to-view surface finishes that develop surface finish deficiencies specified</LST><BRK/>
<BRK/></SPT>
</SPT></PRT>    <END/><BRK/></SEC>