<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><BRK/>
<HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA                UFGS-04 01 21 (October 2007)<BRK/>
                                              ----------------------------<BRK/>
Preparing Activity:  <PRA>USACE</PRA>                    Superseding<BRK/>
                                              UFGS-04 01 21 (April 2006)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 04 01 21</SCN><BRK/>
<BRK/>
<STL>REHABILITATION OF REINFORCED AND UNREINFORCED MASONRY WALLS USING SURFACE APPLIED FRP COMPOSITES</STL><BRK/>
<DTE>10/07</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>rehabilitation of 
masonry walls and is intended for use in defining those requirements for procurement 
of structural strengthening using fiber reinforced polymer (FRP) composite systems.</SCP><BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  In general, reinforced masonry is defined as masonry construction containing 
vertical bar reinforcement, horizontal bar or joint reinforcement, mortar, and 
grout combined so that the component materials will act together to resist the 
design loading conditions.<BRK/>
<BRK/>
Masonry not meeting the above definition but bonded together with mortar and 
containing, if necessary, the minimum amount of reinforcement for crack control 
and vertical stiffeners, is classified as non-reinforced or unreinforced masonry (URM).<BRK/>
<BRK/>
The project drawings should show all necessary details, architectural and structural, 
including wall sections, masonry bond and pattern, control joint locations, 
joint dimensions, reinforcement locations, anchors, bond beam and special units, 
masonry dimensions, and FRP composite details to complement this section.<BRK/>
<BRK/>
Work covered by this specification will include the installation of near surface 
embedded fiber reinforced polymer (FRP) composite systems as structural repointing 
applied to masonry members.  The work shall include:<BRK/>
<BRK/>
a. Inspection of the structural members specified on the contract drawings to 
be reinforced with FRP.  The inspection shall check the location for cracks 
and existing conditions of the masonry substrate.<BRK/>
<BRK/>
b. Furnishing of materials, labor, equipment and all items necessary for rehabilitation 
of existing masonry members by application of externally bonded FRP composite 
systems as specified on the contract drawings and specifications.<BRK/>
<BRK/>
c. Cooperation and coordination with all other trades in executing the work 
described in the overall contract.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification.  The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
<BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
<BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ACI INTERNATIONAL (ACI)</ORG><BRK/><BRK/><RID>ACI 440.2R</RID><RTL>(2008) Guide for the Design and Construction of Externally Bonded FRP Systems for Strengthening Concrete Structures</RTL><BRK/><BRK/><RID>ACI 440.3R</RID><RTL>(2004) Guide Test Methods for Fiber Reinforced Polymer (FRP) for Reinforcing or Strengthening Concrete Structures</RTL><BRK/><BRK/><RID>ACI 503.1-503.4</RID><RTL>(1992, R2003) Standard Specification for Repairing Concrete with Epoxy Mortars</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENISTS (ACGIH)</ORG><BRK/><BRK/><RID>ACGIH Publication 0028</RID><RTL>(2006) TLVs and BEIs</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM C 581</RID><RTL>(2003; R 2008e1) Standard Practice for Determining Chemical Resistance of Thermosetting Resins Used in Glass-Fiber-Reinforced Structures, Intended for Liquid Service</RTL><BRK/><BRK/><RID>ASTM D 2240</RID><RTL>(2005) Standard Test Method for Rubber Property - Durometer Hardness</RTL><BRK/><BRK/><RID>ASTM D 2563</RID><RTL>(2008) Classifying Visual Defects in Glass-Reinforced Plastic Laminate Parts</RTL><BRK/><BRK/><RID>ASTM D 3039/D 3039M</RID><RTL>(2008) Tensile Properties of Polymer Matrix Composite Materials</RTL><BRK/><BRK/><RID>ASTM D 3045</RID><RTL>(1992; R 2003) Practice for Heat Aging of Plastics Without Load</RTL><BRK/><BRK/><RID>ASTM D 3171</RID><RTL>(2006) Standard Test Method for Constituent Content of Composite Materials</RTL><BRK/><BRK/><RID>ASTM D 4541</RID><RTL>(2002) Pull-Off Strength of Coatings Using Portable Adhesion Testers</RTL><BRK/><BRK/><RID>ASTM G 154</RID><RTL>(2006) Operating Fluorescent Light Apparatus for UV Exposure of Nonmetallic Materials</RTL><BRK/><BRK/></REF><REF><ORG>INTERNATIONAL CODE COUNCIL (ICC)</ORG><BRK/><BRK/><RID>ICC ES AC125</RID><RTL>(2003) Interim Criteria for Concrete and Reinforced and Unreinforced Masonry Strengthening Using Fiber-Reinforced Polymer (FRP) Composite Systems</RTL><BRK/><BRK/><RID>ICC ES AC178</RID><RTL>(2003) Interim Criteria for Inspection and Verification of Concrete and Reinforced and Unreinforced Masonry Strengthening Using Fiber-Reinforced Polymer (FRP) Composite Systems</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)</ORG><BRK/><BRK/><RID>NFPA 255</RID><RTL>(2005; Errata 2006) Standard Method of Test of Surface Burning Characteristics of Building Materials</RTL><BRK/><BRK/></REF><REF><ORG>U.S. DEPARTMENT OF DEFENSE (DOD)</ORG><BRK/><BRK/><RID>EI 042XX</RID><RTL>(200X) Design of Fiber Reinforced Polymer Composites Systems for Rehabilitation of Unreinforced and Lightly Reinforced Masonry Walls</RTL><BRK/><BRK/></REF><REF><ORG>U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)</ORG><BRK/><BRK/><RID>29 CFR 1910.1200</RID><RTL>Hazard Communication</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section <SRF>01 33 00</SRF> SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy, Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for [Contractor Quality Control approval.] [information only.  When used, a designation following the "G" 
designation identifies the office that will review the submittal for the Government.]  The following shall be 
submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-01 Preconstruction Submittals</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Quality Control</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  A quality assurance plan for installation and curing of all FRP materials to include personnel 
safety issues, installer certification, application and inspection of the FRP system, location 
and placement of splices, curing provisions, means to assure dry surfaces, quality assurance 
samples and cleanup.  The plan will indicate the testing that will be performed and identify 
the party or parties responsible for this testing.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Composite System</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Complete shop drawings for each installation of the composite system showing details of fiber 
architecture, fiber type, dimensions, number and thickness of layers, direction of fiber layers, 
sequence of layer applications, lap splices, joint and end details, anchorage of the FRP composite 
system, proposed connections to diaphragms and adjacent walls, and locations to be applied as 
specified.  Include any calculations prepared by or on behalf of the Contractor to determine 
the layout of the FRP materials to be installed.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Materials</SUB></ITM><BRK/>
<BRK/>
<ITM>  Manufacturer's product data sheets indicating physical, mechanical, and chemical characteristics 
of all materials used in the FRP system application.</ITM><BRK/>
<BRK/>
<ITM><SUB>Tensile Properties</SUB></ITM><BRK/>
<BRK/>
<ITM>  Values as determined by tensile testing in accordance with <RID>ASTM D 3039/D 3039M</RID>, elastic modulus 
determined by the strength and rupture strain values and ultimate tensile strength and rupture 
strain values determined by subtracting three (3) standard deviations from the average values 
of twenty (20) or more tensile tests.</ITM><BRK/>
<BRK/>
<ITM><SUB>Material Safety Data Sheets (MSDS)</SUB></ITM><BRK/>
<BRK/>
<ITM>  Data sheets for all materials to be used at the job site in accordance with OSHA and <RID>29 CFR 1910.1200</RID>
.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-04 Samples</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Materials</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  FRP plate<MET> 300 x 300 mm</MET><ENG> 12 x 12 inches</ENG> or plate of equivalent area when one of the fiber reinforcing 
dimensions is less than<MET> 300 mm</MET><ENG> 12 inches</ENG>.</ITM><BRK/>
<BRK/>
<ITM><SUB>Anchors</SUB></ITM><BRK/>
<BRK/>
<ITM>  Provide two of each type of anchor to be used.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-05 Design Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Design Calculations</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Design calculations for the FRP composite system shall be submitted for approval to the Contracting 
Officer, and shall be stamped by a registered professional civil or structural engineer.  Calculations 
shall conform to requirements set forth in <RID>EI 042XX</RID> and in the <RID>ICC ES AC125</RID> Acceptance Criteria 
and are based on tension force and strain limits.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Field Testing</SUB></ITM><BRK/>
<ITM><SUB>Laboratory Testing</SUB></ITM><BRK/>
<BRK/>
<ITM>  System environmental durability test results conducted and reported by an independent testing 
facility; the report shall provide the following information:</ITM><BRK/>
<BRK/>
<ITM>a.  FRP System nomenclature</ITM><BRK/>
<ITM>b.  Testing facility name</ITM><BRK/>
<ITM>c.  Testing facility address</ITM><BRK/>
<ITM>d.  Testing facility telephone number</ITM><BRK/>
<ITM>e.  Testing facility point of contact</ITM><BRK/>
<ITM>f.  Freeze-thaw test results</ITM><BRK/>
<ITM>g.  UV test results</ITM><BRK/>
<ITM>h.  Fire resistance test results</ITM><BRK/>
<BRK/>
<ITM><SUB>Wall Tests</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Test results by an independent testing facility on walls which are representative of the actual 
configuration and loading conditions for this contract, showing the following information:</ITM><BRK/>
<BRK/>
<ITM>a.  FRP System nomenclature</ITM><BRK/>
<ITM>b.  Primer/filler system nomenclature</ITM><BRK/>
<ITM>c.  Coating/finishing system nomenclature</ITM><BRK/>
<ITM>d.  Testing facility name</ITM><BRK/>
<ITM>e.  Testing facility address</ITM><BRK/>
<ITM>f.  Testing facility telephone number</ITM><BRK/>
<ITM>g.  Testing facility point of contact</ITM><BRK/>
<ITM>h.  Test wall substrate material</ITM><BRK/>
<ITM>i.  Test wall aspect ratio</ITM><BRK/>
<ITM>j.  FRP fiber orientation and fiber density</ITM><BRK/>
<ITM>k.  FRP composite application process</ITM><BRK/>
<ITM>l.  Cyclic in-plane test results in accordance with <RID>EI 042XX</RID> and <RID>ICC ES AC125</RID> to include the 
following:</ITM><BRK/>
<BRK/>
<ITM>      (1)  Description of test setup.</ITM><BRK/>
<ITM>      (2)  Rate and method of loading.</ITM><BRK/>
<ITM>      (3)  Deformation and strain measurements.</ITM> <BRK/>
<ITM>      (4)  Modes of failure.</ITM><BRK/>
<BRK/>
<ITM><SUB>Hardness Test</SUB></ITM><BRK/>
<BRK/>
<ITM>  Minimum Shore hardness values at 24 and at 48 hours in ten-degree intervals between<MET> 4 and 
38 degrees C</MET><ENG> 40 and 100 degrees F</ENG> for both neat resin and for FRP laminate on masonry substrate.  
Provide minimum Shore hardness values for fully cured resin and fully cured FRP laminate on 
masonry substrate.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Materials</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Certification from the system manufacturer of the guaranteed material and section properties 
for the supplied material.</ITM><BRK/>
<BRK/>
<ITM><SUB>Regulatory Requirements</SUB></ITM><BRK/>
<BRK/>
<ITM>  Certification that resins proposed for use meet Federal VOC regulations and those of the local 
Air Pollution Control Districts having jurisdiction over the geographical area in which the 
project is located.</ITM><BRK/>
<BRK/>
<ITM><SUB>System Manufacturer</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  A list of a minimum ten (10) FRP composite strengthening projects completed with the manufacturer's 
composite system.  The list shall include:  the dates of work, type, description and amount 
of work performed, as well as a point of contact for the Contractor doing the work, and an owner 
representative to include name, address and telephone number.</ITM><BRK/>
<BRK/>
<ITM><SUB>Contractor</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  A list of a minimum five (5) completed FRP composite strengthening projects performed by the 
Contractor to include a minimum of three (3) with the manufacturer's composite system.  Include 
the dates of work, type, description and amount of work performed, the FRP system installed 
for each project, and the name and telephone number of a contact person or owner for which the 
work was completed.</ITM><BRK/>
<BRK/>
<ITM><SUB>Field Representative</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  The name of the Contractor's field representative who will perform the actual work supervision, 
the date certification course completed, and a list of a minimum of ten (10) completed FRP composite 
strengthening projects of similar applications using the manufacturer's composite system.  Include 
the dates of work, type, description and amount of work performed, and the name and telephone 
number of a contact person or owner for which the work was completed.</ITM><BRK/>
<BRK/>
<ITM><SUB>Applicators</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Certificates of training by the FRP system manufacturer for all FRP applicators, a syllabus 
of the certification course, as well as listing of past application projects completed by the 
applicators.  Include the dates of work, type, description and amount of work performed, and 
the name and telephone number of a contact person or owner for which the work was completed.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-08 Manufacturer's Instructions</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Composite System</SUB>; <SUB>G, [____]</SUB></ITM><BRK/>
<BRK/>
<ITM>  Submit the manufacturer's printed installation instructions to include the following:</ITM><BRK/>
<BRK/>
<ITM>a.  Brand name</ITM><BRK/>
<BRK/>
<ITM>b.  Catalog numbers</ITM><BRK/>
<BRK/>
<ITM>c.  Names of manufacturers for each material to be used.  Include with instructions the estimated 
quantity of each material to be used on the job.</ITM><BRK/>
<BRK/>
<ITM>d.  Detailed mixing and application instructions to include:</ITM><BRK/>
<ITM>      (1)  Mixing instructions</ITM><BRK/>
<ITM>      (2)  Curing times between coats or layers</ITM><BRK/>
<ITM>      (3)  Application procedures for surface coatings</ITM><BRK/>
<ITM>      (4)  Cold weather installation to include the minimum application temperature recommended 
by the FRP system manufacturer or<MET> 4 degrees C</MET><ENG> 40 degrees F</ENG> whichever is higher.  Application 
at temperatures below<MET> 4 degrees C</MET><ENG> 40 degrees F</ENG> shall be approved by the Contracting Officer 
and the minimum Shore hardness for the lower temperatures shall be provided.</ITM><BRK/>
<ITM>      (5)  Hot weather installation to include the maximum application temperature recommended 
by the FRP system manufacturer or<MET> 38 degrees C</MET><ENG> 100 degrees F</ENG> whichever is lower.  Application 
at temperatures above<MET> 38 degrees C</MET><ENG> 100 degrees F</ENG> shall be approved by the Contracting Officer 
and the minimum Shore hardness for the higher temperatures shall be provided.</ITM> <BRK/>
<ITM>      (6)  Inclement weather installations</ITM><BRK/>
<ITM>      (7)  Application procedures of top coating material</ITM><BRK/>
<BRK/>
<LST><SUB>SD-10 Operation and Maintenance Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Record Retention</SUB>; <SUB>G, [____]</SUB></ITM><BRK/>
<BRK/>
<ITM>  Procedures to properly maintain the installed FRP system as well as written manufacturer recommended 
repair procedures for damage to the in-place FRP system.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   <SUB>COMPOSITE SYSTEM</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Design Requirements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The resin system used in the FRP composite system seals up the surface 
of the wall where it is applied and can impede air and moisture migration through 
a wall.  If the wall should not be sealed tight, full coverage of the wall with 
the FRP system should be avoided thus allowing normal air and water vapor transmission.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The design of the FRP composite system shall conform to <RID>ACI 440.2R</RID> and shall provide [seismic] [wind] [and] [blast] 
strengthening for [clay] [and] [concrete] masonry walls.  The strengthening design requires that walls with the 
FRP system applied fail by cracking through the masonry units and mortar prior to any delamination or rupture 
of the FRP composite system.  The Contractor shall submit <SUB>Design Calculations</SUB> as specified in the Submittals 
paragraph.  Provide an FRP system that does not adversely affect air and moisture permeation through the masonry 
walls.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2   Performance Requirements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Provide the parameters of strength or force that must be provided by 
the rehab.  The following variables must be considered in determining the enhanced 
performance requirements:  the load on the wall, the size of the wall, the wall 
aspect ratio, wall openings, etc.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The FRP composite system shall provide [seismic] [wind] [and] [blast] strengthening for [clay] [concrete] masonry 
walls by [[_____]%] [the quantity indicated on the shop drawings].  The system shall transfer [seismic] [wind] 
[and] [blast] loading in concert with the existing masonry to the building foundation.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4   QUALIFICATIONS</TTL><BRK/>
<BRK/>
<SPT><TTL>1.4.1   <SUB>System Manufacturer</SUB></TTL><BRK/>
<BRK/>
<TXT>The FRP composite system manufacturer shall have used the proposed materials system on a minimum of ten (10) 
completed strengthening projects.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.2   <SUB>Contractor</SUB></TTL><BRK/>
<BRK/>
<TXT>The Contractor shall have completed a minimum of five (5) FRP composite strengthening projects on vertical flat 
surfaces and a minimum of three (3) of those jobs using the manufacturer's composite system.  The Contractor 
shall provide the qualifications for its <SUB>Field Representative</SUB> as specified in the Submittals paragraph.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.3   <SUB>Applicators</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>1.4.3.1   Training</TTL><BRK/>
<BRK/>
<TXT>The FRP composite applicators shall have completed, as a minimum, a certification course provided by the FRP 
manufacturer, which includes hands-on application of FRP systems to masonry substrates.  A field representative 
who has completed the course of instruction and has completed a minimum of ten (10) FRP composite strengthening 
projects, three (3) using the manufacturer's composite system, shall be present onsite during all installation 
of the FRP system.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.3.2   Experience</TTL><BRK/>
<BRK/>
<TXT>Only qualified applicators meeting these requirements and those having prior experience in the specified surface 
preparation and coating applications shall be assigned to perform the work described herein.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>1.5   WORK SITE SAFETY</TTL><BRK/>
<BRK/>
<TXT>Workers having access to the work area shall be informed of the contents of the applicable <SUB>material safety data 
sheets (MSDS)</SUB> and of potential health and safety hazards and protective controls associated with materials used 
on the project.  The work area is one that may receive mists and odors from the rehab application and curing 
operations.  Train workers in the safe handling and application of FRP materials and the exposure limit for each 
material that the worker will use or otherwise be exposed to during the course of the project.  Instruct personnel 
having a need to use respirators and masks in the use and maintenance of such equipment.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6   <SUB>REGULATORY REQUIREMENTS</SUB></TTL><BRK/>
<BRK/>
<TXT>Insure that the composite system used does not release volatile organic compounds (VOC) into the air in excess 
of the most restrictive of NIOSH RELs, OSHA PELs or ACGIH TLVs for worker or occupant exposure during installation 
and/or over the useful life of the structure.  If VOCs exceed any of these exposure limits during installation 
or use, provide additional ventilation for the duration of the excess outgassing.  Insure that at no time will 
they exceed STEL, even if additional ventilation or air supply is provided.  Provide the necessary equipment 
to comply with these requirements.  Once cured, insure the FRP composite system does not exhibit any detectable 
odor at a distance of<MET> 300 mm</MET><ENG> one foot</ENG> from the FRP surface.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7   PREINSTALLATION CONFERENCE</TTL><BRK/>
<BRK/>
<TXT>Prior to commencement of any work, the Contractor shall arrange and conduct a meeting between the Contracting 
Officer, Contractor, and the independent special inspector to discuss the project requirements.  The Contractor 
shall review the requirements of the Specification and overall project requirements.  Review and discuss all 
aspects of the project including containment, environmental control, surface preparation, strengthening system 
application, quality assurance, schedule requirements, and safety shall be reviewed and discussed.  Request clarification 
of any ambiguities, and advise the Contracting Officer of any potential conflicts and/or any technical requirements 
that appear improper or inappropriate.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.8   DELIVERY AND STORAGE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.8.1   Labeling</TTL><BRK/>
<BRK/>
<TXT>Deliver polymer resin materials in original factory-sealed containers with the manufacturer's labels intact and 
legible with verification of product nomenclature, manufacturer's name, product identification and batch number, 
date of manufacture and shelf life or expiration date.  Do not use polymer resin materials that have exceeded 
the shelf life.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.8.2   Storage</TTL><BRK/>
<BRK/>
<TXT>Store materials in a covered, well-ventilated area protected from exposure to any detrimental conditions including:  
airborne contaminants, dirt, dust, sunlight, temperatures lower than<MET> 4 or greater than 38 degrees C</MET><ENG> 40 or greater 
than 100 degrees F</ENG>, rainfall, sparks or flame and in accordance with the manufacturer's requirements.  Store 
polymer resins separate from their hardeners.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.9   PROJECT/SITE CONDITIONS</TTL><BRK/>
<BRK/>
<SPT><TTL>1.9.1   Environmental Requirements</TTL><BRK/>
<BRK/>
<SPT><TTL>1.9.1.1   Application Temperature</TTL><BRK/>
<BRK/>
<LST>a.  Do not apply primers, saturating resins and adhesives to cold or frozen surfaces.  When the surface 
temperature of the masonry surface falls below a minimum level, as specified by the FRP system manufacturer, 
the work will cease until both the air and masonry temperature rise above the specified minimum.  Supplemental 
sources of heat shall not be used to raise the air or masonry surface temperature unless approved by 
the FRP composite system manufacturer.</LST><BRK/>
<BRK/>
<LST>b.  When the surface temperature of the masonry and/or the air temperature rise above the maximum level 
as specified by the FRP system manufacturer, the work will cease until both the air temperature masonry 
temperature cool below the specified maximum.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.9.1.2   Wet or Damp Surfaces</TTL><BRK/>
<BRK/>
<TXT>Unless they have been formulated for such applications, do not apply resins and adhesives to damp or wet surfaces.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.9.1.3   Breathable Wall Surfaces</TTL><BRK/>
<BRK/>
<TXT>Do not completely cover masonry surfaces that are designed to allow air and vapor transmission with FRP systems.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.9.2   Existing Conditions</TTL><BRK/>
<BRK/>
<TXT>As-built drawings of the structure [are attached] [can be accessed at [_____]].</TXT></SPT>.<BRK/>
<BRK/>
<SPT><TTL>1.9.3   Work Coordination</TTL><BRK/>
<BRK/>
<TXT>Coordinate work to minimize exposure of building occupants, other Contractor personnel, and visitors to dust, 
mists, and odors from preparation, FRP system application and clean-up operations.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.10   WARRANTY</TTL><BRK/>
<BRK/>
<TXT>Furnish a warranty (either by the manufacturer or Contractor) for FRP composite system installation.  Insure 
the warranty covers the FRP composite system [design,] installation, bond to the substrate, and interlaminar 
bond, as well as mechanical property retention, and fabric-resin compatibility.  The warranty shall run directly 
to the Government and shall cover a period of not less than 5 years from the date of Government's acceptance.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  FRP system forms can be categorized based on how they are delivered to 
the work site and installed.  Externally applied FRP composite systems come 
in a variety of forms including wet lay-up systems, prepreg systems, and precured systems.<BRK/>
<BRK/>
Wet lay-up FRP systems consist of dry unidirectional or multi-directional fiber 
sheets or fabrics that are impregnated onsite with a saturating resin.  The 
saturating resin is used to bond the sheets to the masonry surface.  Wet lay-up 
systems are saturated with resin and cured in place and in this sense are analogous 
to cast-in-place concrete.  For dry lay-up systems, the fabric is placed on 
the wall and then saturated in-place with resin and cured in place.<BRK/>
<BRK/>
Prepreg FRP systems consist of unidirectional or multidirectional fiber sheets 
or fabrics that are preimpregnated with a saturating resin in the supplier's 
facility.  Prepreg systems are bonded to the concrete surface with or without 
an additional resin application, depending upon specific system requirements.  
Prepreg systems are saturated offsite and, like wet lay-up systems, are cured 
in place.  Prepreg systems usually require heat for cure.<BRK/>
<BRK/>
Precured FRP systems consist of composite shapes (plates, strips, ribbons, and 
bars configured as an open mesh grid or solid laminate) manufactured in the 
system supplier's facility and shipped to the job site.  Typically, an adhesive 
is used to bond the precured shapes to the masonry surface.<BRK/>
<BRK/>
It is important that only one system manufacturer supply all materials system 
components (reinforcements, resins and adhesives) for a specific job.  The arbitrary 
selection of a fiber reinforcement and a resin/matrix material can lead to failure 
of the FRP composites system due to matrix-reinforcement incompatibilities and 
are, therefore, not allowed.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.1   <SUB>MATERIALS</SUB></TTL><BRK/>
<BRK/>
<TXT>Do no substitute the submitted reinforced FRP composite system or any its components during the course of the 
project.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2   MANUFACTURED PRODUCTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The values listed in the following table should be provided by the design 
engineer and be based on the values and assumptions that were used in developing 
the rehab design.  The items in Table 1 below will be the minimum acceptable 
property values for the FRP system to be installed and potential FRP systems 
submitted which do not meet these minimums should be rejected.<BRK/>
<BRK/>
Submittals must demonstrate that the proposed materials will match the intent 
of the engineering design using the properties listed above.  Proposed FRP systems 
must utilize the same primary fiber reinforcement type (e.g., carbon fiber, 
aramid fiber, or E-glass fiber) as the system listed above.<BRK/>
<BRK/>
Proposals for material systems must include, at a minimum, documented evidence 
that the Manufacturer of the proposed system meets the requirements of Table 
1, and demonstrate the structural equivalency of the proposed system to the 
system(s) specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Table 1 lists the minimum allowable gross laminate properties for the cured [glass] [carbon] [aramid] [hybrid] 
reinforced FRP composite system.  The Contractor shall provide values for the <SUB>Tensile Properties</SUB> of the composite 
material as specified in the Submittals paragraph.</TXT><BRK/>
<BRK/>
<TBL><THD><HL3><HL4>TABLE 1</HL4></HL3><BRK/>
<BRK/>
                                FRP<BRK/>
                              COMPOSITE                            TEST<BRK/>
                             REQUIREMENT                          METHOD</THD><BRK/>
<BRK/>
Elongation:<BRK/>
max.                        [_____]%                    <RID>ASTM D 3039/D 3039M</RID><BRK/>
<BRK/>
Guaranteed Tensile<BRK/>
Strength, min., in          [_____] kPa (psi)           <RID>ASTM D 3039/D 3039M</RID><BRK/>
primary fiber<BRK/>
direction.<BRK/>
<BRK/>
Ult. Breaking Load,<BRK/>
min., in primary            [_____] kg/mm (lb/in)       <RID>ASTM D 3039/D 3039M</RID><BRK/>
fiber direction<BRK/>
width<BRK/>
<BRK/>
<BRK/>
Modulus of Elasticity,<BRK/>
min. based on cross         [_____] kPa (psi)           <RID>ASTM D 3039/D 3039M</RID><BRK/>
sectional area of<BRK/>
primary fibers<BRK/>
<BRK/>
Percent Tensile<BRK/>
Strength<BRK/>
Retained after:<BRK/>
[7 days exposure<BRK/>
at 100% humidity            [_____]%                    <RID>ASTM G 154</RID>]<BRK/>
<BRK/>
[2,000 hours<BRK/>
exposure to UV              [_____]%                    <RID>ASTM G 154</RID>]<BRK/>
<BRK/>
[3,000 hours<BRK/>
exposure to ozone           [_____]%                    <RID>ASTM C 581</RID>]<BRK/>
<BRK/>
[3,000 hours<BRK/>
exposure to alkali          [_____]%                    <RID>ASTM C 581</RID>]<BRK/>
<BRK/>
[3,000 hours<BRK/>
exposure to salt water      [_____]%                    <RID>ASTM C 581</RID>]<BRK/>
<BRK/>
[3,000 hours exposure<BRK/>
at 60 C (140 F).            [_____]%                    <RID>ASTM D 3045</RID>]<BRK/>
<BRK/>
[Guaranteed Tensile <BRK/>
Strength at 90 degrees      [_____] kPa (psi)           <RID>ASTM D 3039/D 3039M</RID><BRK/>
to primary fibers, min.]<BRK/>
<BRK/>
[Ultimate Tensile <BRK/>
Strength of Lap             [_____] kPa (psi)           <RID>ASTM D 3039/D 3039M</RID><BRK/>
Splices in Primary<BRK/>
Fiber Direction]<BRK/>
<BRK/>
[Ply Thickness              [_____] mm (in)             <RID>ASTM D 3039/D 3039M</RID>]<BRK/>
<BRK/>
[Fiber Volume Fraction      [_____]%                    <RID>ASTM D 3171</RID>]<BRK/>
<BRK/>
[Visual Defects              Acceptance                 <RID>ASTM D 2563</RID><BRK/>
                             Level [_____]]</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3   COMPONENTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.3.1   FRP Composite System</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select the appropriate system from the three choices below and delete 
the others.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.3.1.1   Wet Lay-up System</TTL><BRK/>
<BRK/>
<TXT>A wet lay-up FRP system consists of [glass] [carbon] [aramid] fiber in [an epoxy] [a polyester] [a polyurethane] 
resin.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.1.2   Prepreg System</TTL><BRK/>
<BRK/>
<TXT>A prepreg FRP system consists of [glass] [carbon] [aramid] fiber in an uncured polymer resin.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.1.3   Precured System</TTL><BRK/>
<BRK/>
<TXT>A precured FRP system consists of [glass] [carbon] [aramid] fiber, fabricated as [strips] [plates] [ribbons] 
[bars] in [an open mesh grid] [a solid laminate] configuration with a resin matrix of [vinyl ester] [polyester] 
[epoxy] [polyurethane] [specialty resin] applied to the surface of the masonry wall using [a polyurethane] [an 
epoxy] structural adhesive.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3.2   Use of Primer/Filler</TTL><BRK/>
<BRK/>
<TXT>The primer/filler used for the protective seal coat and for filling voids consists of a thickened [epoxy] [polyester].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.3   Finish and Coating</TTL><BRK/>
<BRK/>
<TXT>Perform final finish and apply architectural coatings as prescribed in architectural specifications and drawings 
[_____].</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.4   ACCESSORIES</TTL><BRK/>
<BRK/>
<SPT><TTL>2.4.1   <SUB>Anchors</SUB></TTL><BRK/>
<BRK/>
<TXT>Install anchors for the FRP system as prescribed by the FRP system manufacturer and designated in the Shop Drawings.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.2   Miscellaneous</TTL><BRK/>
<BRK/>
<TXT>Provide other materials as needed for the proper installation of the complete composite system as specified.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.5   MIXES</TTL><BRK/>
<BRK/>
<TXT>Mix [Resins] [Adhesive] in accordance with the FRP system manufacturer's recommended procedure.  Assure that 
all [resin] [adhesive] components are at a proper temperature and are mixed in the correct ratio until there 
is a complete mixing of components and a uniform color.  Mix each batch of [resin] [adhesive] in quantities sufficiently 
small to ensure that all mixed [resin] [adhesive] can be used within the [resin] [adhesive] pot life.  Do not 
use mixed [resin] [adhesive] that exceeds its pot life as defined by the system manufacturer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6   [FLAME SPREAD/FIRE PROTECTION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Unless stated otherwise by the local fire building code, this paragraph 
may be deleted if the FRP materials are installed on the exterior of a structure 
or if a flame barrier is installed between living space and the FRP materials 
system.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Meet requirements for Class 1 fire rating in accordance with <RID>NFPA 255</RID> and meet or exceed local building code 
requirements for flame spread and smoke generation.]</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   SUBSTRATE, TEMPERATURE, AND ENVIRONMENT</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1.1   Examination</TTL><BRK/>
<BRK/>
<TXT>Examine existing conditions to assess the quality of the masonry substrate, identify potential obstructions, 
and verify dimensions/geometries shown on shop drawings.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2   Environmental Temperature</TTL><BRK/>
<BRK/>
<TXT>Should the potential for adverse temperatures occur during installation, the application of FRP shall cease until 
temperatures return to within the range specified in the Manufacturer's Instructions.  Obtain approval from the 
FRP manufacturer and the Contracting Officer before using supplemental heating or cooling sources.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3   Other Environmental Factors</TTL><BRK/>
<BRK/>
<TXT>Should the potential for direct contact by rain, dust or dirt, excessive sunlight, high humidity, or vandalism 
occur during installation, temporary protection may be required until the resins have cured.  Provide and install 
tents and/or plastic screens as required to protect the FRP system as it cures.  Assure resins are cured before 
removal of temporary shoring or allowing the structure to be exposed to new loads.  In the event of suspected 
damage to the FRP system during installation, notify the Contracting Officer.  Repair any damage caused by installer 
negligence at no additional cost to the Government.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2   PREPARATION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.1   Materials Testing</TTL><BRK/>
<BRK/>
<TXT>Assure that delivered FRP materials meet the specified requirements prior to starting the project.  This may 
require laboratory testing.  Reject all materials that do not meet the minimum requirements, as specified in 
Table 1 and by the Contracting Officer.  In addition, determine the gel time, pot life, and curing hardness of 
the resins.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.2   Worksite Ventilation</TTL><BRK/>
<BRK/>
<TXT>Ventilate work areas during FRP application so that worker exposure to chemical substances do not exceed limits 
established by <RID>ACGIH Publication 0028</RID>, or required by a more stringent applicable local regulation.  Ventilate 
interior work zones having a volume of<MET> 280 cubic m</MET><ENG> 10,000 cubic ft</ENG> or less at a minimum of 2 air exchanges per 
hour.  Maintain ventilation in larger work zones by means of mechanical exhaust.  Exhaust solvent vapors outdoors, 
away from air intakes and workers.  Temporarily seal return air inlets in the work zone before start of work 
until the polymer resin has cured.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.3   Substrate Repair</TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.3.1   Surface</TTL><BRK/>
<BRK/>
<TXT>[The area to receive FRP composite is relatively sound structurally.] [There are known problems associated with 
the condition of the original masonry and the masonry substrate that can compromise the integrity of the FRP 
system.] [Surface cracks greater than<MET> 1.6 mm</MET><ENG> 1/16-inch</ENG> shall be filled to a minimum depth of<MET> 25 mm</MET><ENG> 1 inch</ENG>.] [Remove 
areas of loose or spalling masonry material.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.3.2   Sub-Surface</TTL><BRK/>
<BRK/>
<TXT>Do not apply externally bonded FRP systems to masonry substrates containing corroding reinforcing-steel.  Note 
and report evidence of localized cracking and/or spalling at grouted cells or of rust stains to the Contracting 
Officer.  Do not proceed with work until the cause(s) of the corrosion is addressed and the corrosion-related 
deterioration repaired.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2.4   Surface Preparation</TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.4.1   Surface Cleaning</TTL><BRK/>
<BRK/>
<TXT>Remove all loose or unsound materials and other conditions that would inhibit bond such as laitance, dust, dirt, 
oil, curing compound, existing paint or coatings, efflorescence, and any other matter that could interfere with 
the bond of the FRP system from the masonry or repaired surfaces to which the FRP system is to be applied.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.4.2   New Masonry Preparation</TTL><BRK/>
<BRK/>
<TXT>Unspoiled new masonry only requires wire brushing to remove loose surface particles.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.4.3   Old Clay Masonry Preparation</TTL><BRK/>
<BRK/>
<TXT>Prepare surface of older clay masonry using hand tools, power tools or water blasting techniques.  Do not use 
abrasive blasting.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.4.4   Old Concrete Masonry Preparation</TTL><BRK/>
<BRK/>
<TXT>Concrete masonry may be blasted using a light blast abrasive or cleaned using hand tools, power tools or water 
blasting techniques.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.4.5   Cleaned Surface Protection</TTL><BRK/>
<BRK/>
<TXT>After the cleaning operations are complete protect the surface prior to FRP installation so that no materials 
that may interfere with bond are redeposited on the surface.  Apply the FRP composite system to the prepared 
wall within 72 hours of performing the surface preparation.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2.5   Surface Plane Variation Tolerance</TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.5.1   Tooled Mortar Joints</TTL><BRK/>
<BRK/>
<TXT>Fill all tooled mortar joints with putty or another epoxy-based paste with adequate bonding properties to the 
masonry substrate to make them flush with the adjacent clay masonry unit or concrete block.  Assure localized 
out-of-plane variations between masonry units do not exceed<MET> 1.6 mm</MET><ENG> 1/16-inch</ENG> or the tolerances recommended by 
the FRP system manufacturer, whichever is less.  Smooth localized out-of-plane variations in the masonry units 
using putty as needed.  It is not necessary to screed filler onto the surface to fill all bug holes.  Fill larger 
holes greater than<MET> 6 mm</MET><ENG> 1/4 inch</ENG> in diameter and other voids with putty.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.5.2   Untooled Mortar Joints</TTL><BRK/>
<BRK/>
<TXT>Grind or chisel untooled mortar joints that protrude beyond the masonry surface or other protuberances or irregularities 
flush with the surface.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2.6   Obstructions, Corners and Non-Planar Surfaces</TTL><BRK/>
<BRK/>
<TXT>Obstructions, re-entrant corners, concave surfaces and embedded objects can affect the performance of the FRP 
system.  Modify as necessary.  Movable obstructions and embedded objects may need to be removed prior to installing 
the FRP system.  [Give special care to re-entrant corner detailing and concave surface detailing to ensure that 
the bond of the FRP system to the substrate is maintained.]</TXT><BRK/>
<BRK/></SPT>
<TTL>3.2.7   Surface Moisture</TTL><BRK/>
<BRK/>
<TXT>Assure all surfaces to receive the strengthening system are as dry as recommended by the FRP system manufacturer.  
Evaluate moisture content in accordance with the requirements of Section 2.3.2.5 of <RID>ACI 503.1-503.4</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3   FRP INSTALLATION</TTL><BRK/>
<BRK/>
<TXT>Do not install the FRP composite if the ambient air temperature or substrate surface temperature exceeds that 
recommended by the system manufacturer.  Do not install the FRP composite when surface moisture is present on 
the substrate or when rainfall or condensation is anticipated in the work areas.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Primer</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Wet lay-up systems typically require a primer to saturate and penetrate 
the masonry surface and enhance the bond strength of the FRP system.  Adhesives 
used with pre-cured systems, depending upon its chemistry, may not require use 
of a primer.<BRK/>
<BRK/>
Delete this paragraph if not required in the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  Mix primers according to the FRP system manufacturer's installation instructions.  Assure resin components 
are at a proper temperature and mixed in the Manufacturer's prescribed mix ratio for its prescribed mixing 
time until there is a uniform and complete mixing of components.</LST><BRK/>
<BRK/>
<LST>b.  Apply primers to areas on the masonry surface where the FRP system is to be placed.  Place primer 
uniformly on the prepared surface at the manufacturer's specified rate of coverage.  Allow primer to 
cure to the degree specified by the FRP manufacturer before applying subsequent materials.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.2   Putty/Filler</TTL><BRK/>
<BRK/>
<TXT>Assure putty/filler used is compatible with the FRP strengthening system and complies with the FRP system manufacturer's 
specifications.  Use putty or another epoxy-based paste with adequate bonding properties to masonry only to fill 
voids and smooth surface discontinuities prior to application of other materials.  Allow putty to cure to the 
degree specified by the FRP manufacturer before applying subsequent materials.  Grind rough edges or trowel lines 
of cured putty smooth prior to continuing the installation.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.3   Wet Lay-Up and Prepreg Systems</TTL><BRK/>
<BRK/>
<TXT>Install the FRP system in strict accordance with the FRP system manufacturer's recommendations.  Apply sufficient 
saturating resin to achieve full saturation of the fibers in accordance with the manufacturer's specifications.  
Release or roll out entrapped air between layers before the resin sets.  Place successive layers of saturating 
resin and fiber materials before complete cure of the previous layer of resin.  Handle sheet and fabric materials 
in a manner to maintain the fiber straightness and orientat  Remove and repair fabric kinks, folds, or other 
forms of severe waviness.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.4   Precured Systems</TTL><BRK/>
<BRK/>
<TXT>Install the FRP system in strict accordance with the FRP system manufacturer's recommendations.  Uniformly apply 
adhesives shall be to the prepared surfaces where pre-cured systems are to be placed.  Apply adhesives at a rate 
recommended by the FRP manufacturer to ensure full bonding of successive layers.  Release or roll out entrapped 
air between layers before the adhesive sets.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.5   Lap Splices</TTL><BRK/>
<BRK/>
<TXT>[Stagger lap splices unless noted otherwise in the Shop Drawings and by the Contracting Officer.] [Lap splices 
are not permitted except as shown in the Shop Drawings.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.6   Curing of Resins</TTL><BRK/>
<BRK/>
<TXT>Inspect the primer and FRP resin to assure proper cure according to the manufacturer's recommendation.  Field 
modification of resin chemistry is not permitted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.7   Surface Finish - Coating Application</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Only those surfaces exposed to direct sunlight and weather require surface 
finish coating.  There may also be applications where it is desired for architectural 
reasons or aesthetics.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.3.7.1   Preparation</TTL><BRK/>
<BRK/>
<TXT>Apply paints and coatings prior to final resin cure for best results.  After the FRP resin has cured, the coating 
can be applied by performing a light dust blast of 30-mesh silica sand (or equivalent method) to break the gloss 
finish in preparation of a finish coating.  Remove dust and residue from all surfaces by flushing with clean 
water before applying the coating.  Assure all surfaces are dry before applying the surface finish coating.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.7.2   Multiple Coats</TTL><BRK/>
<BRK/>
<TXT>Use coatings compatible with the FRP strengthening system and applied in accordance with the manufacturer's recommendations.  
Apply two finish layers of coating according to the coating manufacturer's instructions prior to full cure of 
the FRP system.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.3.8   Installation Procedure Modification</TTL><BRK/>
<BRK/>
<TXT>Installation procedures may be modified to achieve maximum results, subject to approval by the Contracting Officer.  
Procedural modifications approved by the Contracting Officer and Contracting Officer's Representative prior to 
implementation are allowed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.9   System Placement Tolerances</TTL><BRK/>
<BRK/>
<TXT>Follow FRP ply orientation and ply stacking sequence in accordance with that shown in the Shop Drawings.  Assure 
variations in angle from the intended direction of fiber alignment prescribed in the Shop Drawings are less than 
5 degrees.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.4   WALL FEATURE COMPATIBILITY</TTL><BRK/>
<BRK/>
<SPT><TTL>3.4.1   Weep Holes</TTL><BRK/>
<BRK/>
<TXT>Maintain all weep holes.  Assure that no resin enters existing weep holes.  Do not cover existing weep holes 
with the FRP composite.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2   Construction Joints</TTL><BRK/>
<BRK/>
<SPT><TTL>3.4.2.1   [Control Joints</TTL><BRK/>
<BRK/>
<TXT>Maintain all CMU control joints.  Insure that the FRP composite does not bridge existing control joints.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2.2   [Expansion Joints</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Design loads must be evaluated to determine whether or not to maintain 
existing expansion joints.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Maintain all clay masonry expansion joints.] [Those expansion joints indicated on the shop drawings shall be 
maintained.]  Insure that the FRP composite does not bridge existing expansion joints.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.4.3   [Diaphragms</TTL><BRK/>
<BRK/>
<TXT>Anchor the FRP system into the floor and ceiling diaphragms in accordance with the Shop Drawings.  Assure anchorage 
does not create local stresses that may locally fracture the walls when deflection occurs due to out-of-plane 
loading.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5   <SUB>QUALITY CONTROL</SUB></TTL><BRK/>
<BRK/>
<TXT>Maintain quality assurance and quality control (QA/QC) programs and criteria.  Provide full inspection of the 
surface preparation and composite systems applications to ensure full compliance with the specified requirements.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.5.1   Independent Special Inspector</TTL><BRK/>
<BRK/>
<TXT>Provide a special inspector, trained and certified by the FRP system manufacturer and approved by the Contracting 
Officer.  The special inspector shall not be an employee of the Contractor or be financially associated with 
the Contractor beyond the inspection contract.  The special inspector shall perform inspections in accordance 
with this specification and <RID>ICC ES AC178</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2   Laboratory Qualification</TTL><BRK/>
<BRK/>
<TXT>The testing laboratory shall be one approved by the Engineer of Record, the Contracting Officer and the Contractor.  
The laboratory shall have experience in testing FRP materials and have performed <RID>ASTM D 3039/D 3039M</RID> <SUB>wall tests</SUB>
 for at least three (3) different Contractors prior to this contract.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.6   <SUB>LABORATORY TESTING</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>3.6.1   Witness Panels</TTL><BRK/>
<BRK/>
<SPT><TTL>3.6.1.1   Wet Lay-up and Prepreg</TTL><BRK/>
<BRK/>
<TXT>Fabricate witness panels onsite using installation procedures identical to the method used to install the FRP 
system to the masonry surfaces.  Fabricate two witness panels for each day of production or one for each<MET> 46 square 
m</MET><ENG> 500 square ft</ENG> of production whichever is more.  From a standard polymer resin mix, saturate a<MET> 300 x 300 mm</MET><ENG> 
12 x 12 inch</ENG> piece of fabric according to specified fiber-resin ratio.  On a smooth, flat, level surface covered 
with polyethylene sheeting or<MET> 0.4 mm</MET><ENG> 16-mil</ENG> plastic film, prime the surface with polymer resin and then prepare 
the witness panel by placing two layers of saturated fabric oriented in the same direction on the flat surface.  
Apply an additional topping of polymer resin and cover the completed sample with plastic film and squeegee out 
all bubbles.  Store samples in a sample box at the work site and do not move them for a minimum 48 hours after 
casting.  Mark the panels with the date of fabrication, location of application, number of plies and primary 
fiber direction.  Ship the samples within two weeks of fabrication to the pre-approved testing laboratory for 
evaluation.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.1.2   Precured</TTL><BRK/>
<BRK/>
<TXT>Witness panel samples for precured sheet and strip material are the width of the procured sheet and a length 
sufficient to achieve<MET> 92,900 square mm</MET><ENG> 144 square inches</ENG> in total area taken randomly from the material received 
at the job site.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.6.2   Panel Testing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Due to the sensitivity of ASTM D 3039/D 3039M, not all testing laboratories 
are capable of performing this test.  The testing laboratory used shall have 
a history of performing ASTM D 3039/D 3039M tests prior to the contract.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Determine lap splice strength, tension strength, and elastic modulus of FRP materials.  Test not fewer than two 
(2) coupons from each witness panel in the laboratory in accordance with <RID>ASTM D 3039/D 3039M</RID>.  If one coupon 
from a witness panel fails to meet the minimum strength specified in Table 1, test five (5) additional coupons 
from the witness panel with the failed coupon.  If a second one fails, test five (5) coupons from all panels 
for that day of production.  Take appropriate remedial measures to ensure integrity of the FRP system applied 
for the day the failed witness panels were prepared.  In addition, test a minimum of five (5) coupons from each 
witness panel for the remainder of the job or until ten successive witness panels are tested with no coupon failures.  
Then two (2) coupon tests per witness panel may be resumed.  The Contracting Officer may waive or alter the frequency 
of testing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.3   Report</TTL><BRK/>
<BRK/>
<TXT>The laboratory shall report the mechanical properties of the witness panels in accordance with <RID>ASTM D 3039/D 3039M</RID>
.  Provide a copy of the report to the Contracting Officer and Special Inspector for review.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.7   <SUB>FIELD TESTING</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>3.7.1   Mixed Resin Hardness</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The term "resins" include primers, saturating resins, binders, and adhesive components.<BRK/>
<BRK/>
The required resin samples are a minimum of 1/4-inch (6.4 mm) in thickness, 
whereas FRP placed on a wall is much thinner, typically 1/8-inch (3.2 mm) or 
less.  During initial stages of curing, thicker cross sections tend to be softer 
than thin ones.  There is, therefore a variation in the required hardness to 
account for this phenomenon.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Prepare two samples of each mixed resin, primers, binders, saturants, and adhesives, per day from two, separate, 
nonconsecutive batches of each.  The resin samples should be a minimum of<MET> 3.2 mm</MET><ENG> 1/8-inch</ENG> thick and<MET> 50 mm</MET><ENG> 2 inches</ENG>
 in diameter.  Retain the mixed resin samples for testing to evaluate curing progress.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.7.1.1   Testing</TTL><BRK/>
<BRK/>
<TXT>Evaluate relative curing progress of the resin on the job site by measuring the hardness of the resin sample 
at 24 hours and 48 hours of cure in accordance with provisions of <RID>ASTM D 2240</RID>.  Insure the polymer resin exceeds 
the Shore hardness reported by the manufacturer evaluated at the lowest air temperature for the curing time period.  
Take measurements at a minimum of three different points distributed over the resin specimen's surface at least<MET>
 6.4 mm</MET><ENG> 1/4-inch</ENG> apart from each other.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.1.2   Report</TTL><BRK/>
<BRK/>
<TXT>Report the mean hardness value obtained, resin identification and manufacturer, resin batch number, resin mixing 
date and time, test date and time, air temperature when the resin was mixed, air temperature when the testing 
was performed, the minimum air temperature for the curing period, and the type and serial number of durometer 
used.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.1.3   Remedial Measures</TTL><BRK/>
<BRK/>
<TXT>In the event that measured hardness is less than the manufacturer's reported hardness for the temperature range, 
take remedial measures as specified.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.7.2   In-Place FRP Hardness</TTL><BRK/>
<BRK/>
<SPT><TTL>3.7.2.1   Testing</TTL><BRK/>
<BRK/>
<TXT>Evaluate relative curing progress of the in-place FRP resin at 24 hours and at 48 hours using the Shore Durometer <SUB>
hardness test</SUB> described in <RID>ASTM D 2240</RID>.  Perform a minimum of five tests on each<MET> 9.3 square m</MET><ENG> 100 square ft</ENG> of 
wall or portion thereof with FRP composite applied to it.  Insure the Shore hardness exceeds the manufacturer's 
values for the time period measured and the lowest air temperature during that time period.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.2.2   Report</TTL><BRK/>
<BRK/>
<TXT>Report both the individual and mean hardness values obtained, the locations where each hardness test was performed, 
the FRP application date, test date and time, air temperature when the FRP was applied, air temperature when 
testing performed, and the type and serial number of durometer used.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.2.3   Remedial Measures</TTL><BRK/>
<BRK/>
<TXT>In the event that hardness is less than the manufacturer's reported hardness for the temperature range, take 
remedial measures as specified.  For any structural member where testing indicates that the installed composite 
system does not meet the minimum specified hardness values, immediately halt the FRP installation and notify 
the Contracting Officer.  Remove the affected, installed FRP composite at no expense to the Government and replaced 
with FRP composite meeting or exceeding the minimum hardness values.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.7.3   Adhesion Strength</TTL><BRK/>
<BRK/>
<SPT><TTL>3.7.3.1   Testing</TTL><BRK/>
<BRK/>
<LST>a.  Using the method described by <RID>ACI 440.3R</RID> or <RID>ASTM D 4541</RID> conduct direct tension adhesion testing of 
cored samples.  Perform a minimum of three tests for each day of production or for each<MET> 46 square m</MET><ENG> 500 
square ft</ENG> of FRP application, whichever is less.  Perform pull-off tests on each area of fiber sheet 
installed on a single day.  Perform tests on each type of masonry substrate or for each surface preparation 
technique used.</LST><BRK/>
<BRK/>
<LST>b.  Allow the FRP system to cure a minimum of 24 hours before execution of the direct tension pull-off 
test.  The locations of the pull-off tests shall be representative and on flat surfaces.  If possible, 
conduct the tests on areas of the FRP system subjected to relatively low stress during service.  The 
minimum acceptable value for any single tension test is<MET> 1.2 MPa</MET><ENG> 175 psi</ENG>.  The average adhesion strength 
of the three tests at each location shall not be less than<MET> 1.38 MPa</MET><ENG> 200 psi</ENG>.  The tension adhesion tests 
shall exhibit failure of the masonry substrate indicated by a layer of masonry on at least 80 percent 
of the underside of the test puck following the test.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.3.2   Report</TTL><BRK/>
<BRK/>
<TXT>Report the adhesive strength values for each test and the average strength for each day's production.  Report 
the type of failure for each.  Report No adhesion of the masonry to the FRP surface adhered to the test puck 
to the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.3.3   Remedial Measures</TTL><BRK/>
<BRK/>
<TXT>In the event that the adhesive strength does not meet the minimum allowable strength, take remedial measures.  
Halt FRP installation and notify the Contracting Officer.  Remove affected, installed FRP composite at no expense 
to the Government.  Clean the substrate surface and apply FRP composite that meets or exceeds the minimum specified 
values.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.3.4   Test Repair</TTL><BRK/>
<BRK/>
<TXT>After testing, fill the hole in the FRP composite with putty and smooth it.  Apply a 4-inch (100 mm) or more 
overlapping sheet patch of equivalent plies over the location where the sample was taken.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.7.4   Laminate Thickness and Number of Plies</TTL><BRK/>
<BRK/>
<TXT>Measure the cured laminate thickness and count the number of plies.  Avoid taking samples from high stress areas 
or splice areas.  Where laminate is too thin or not having sufficient plies, add additional plies to meet design 
specifications.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.8   QC/QA INSPECTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.8.1   Special Inspector Duties</TTL><BRK/>
<BRK/>
<TXT>Inspect the FRP composite overlay during and immediately following application of the composite.  Inspect FRP 
systems and all associated work as required by the applicable codes and as described in the QA/QC plan.  Observe 
all aspects of onsite preparation and material application including surface preparation, resin component mixing, 
application of primer, application of resin and fiber sheet, curing of composite, and the application of protective 
coatings.  The special inspector shall require compliance with the design drawings and specifications.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.2   Daily Inspection Records</TTL><BRK/>
<BRK/>
<TXT>Include in daily inspection records:</TXT><BRK/>
<BRK/>
<LST>a.  Date and time of installation;</LST><BRK/>
<LST>b.  Ambient temperature, relative humidity, and general weather observations;</LST><BRK/>
<LST>c.  Surface temperature of the masonry receiving the FRP composite system;</LST><BRK/>
<LST>d.  Surface dryness;</LST><BRK/>
<LST>e.  Surface preparation methods;</LST><BRK/>
<LST>f.  Surface cleanliness;</LST><BRK/>
<LST>g.  Type of auxiliary heat source, if applicable;</LST><BRK/>
<LST>h.  Fiber or pre-cured laminate batch number(s) and location in structure;</LST><BRK/>
<LST>i.  Batch numbers, mix ratios, mixing times, and mixed color of all resins, including primers, putties, 
saturants, adhesives, and coatings mixed for the day;</LST><BRK/>
<LST>j.  Observations of progress of cure of resins;</LST><BRK/>
<LST>k.  Conformance with installation procedures;</LST><BRK/>
<LST>l.  Pull-off test results: bond strength, failure mode, and location;</LST><BRK/>
<LST>m.  FRP system properties from witness panel tests, if required;</LST><BRK/>
<LST>n.  Location and size of any delaminations or air voids;</LST><BRK/>
<LST>o.  General progress of work.</LST><BRK/>
<BRK/>
<TXT>Inspection and progress reports shall be submitted daily to the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.3   Void Detection</TTL><BRK/>
<BRK/>
<TXT>After allowing at least 24 hours for initial resin cure to occur, perform a visual and acoustic tap test inspection 
of the layered surface.  Other methods for detecting voids may be employed; all parties concerned shall agree 
upon these methods prior to the submission of bids or proposals.  Mark voids requiring corrective action in accordance 
with the specified FRP maintenance and repair procedure.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.4   Delaminations</TTL><BRK/>
<BRK/>
<TXT>Evaluate the cured FRP system for delaminations or air voids between multiple plies or between the FRP system 
and the masonry.  Use inspection methods capable of detecting delaminations of<MET> 1300 square mm</MET><ENG> 2 square inches</ENG>
 or greater.  Submit all delaminations or other anomalies to the Engineer of Record for evaluation.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.8.4.1   Wet lay-up and Prepreg Systems</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The cause of delamination shall be determined and corrected prior to 
application of the patch.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  Small delaminations or air voids less than<MET> 1300 square mm</MET><ENG> 2 square inches</ENG> each are permissible, so 
long as the delaminated area is less than 5 percent of the total laminate area and there are no more 
than 10 such delaminations or air voids per<MET> 0.93 square m</MET><ENG> 10 square ft</ENG>.</LST><BRK/>
<BRK/>
<LST>b.  Repair large delaminations or air voids, greater than<MET> 16,000 square mm</MET><ENG> 25 square inches</ENG> by selectively 
cutting away the affected sheet and applying a sheet patch of equivalent plies overlapping the undisturbed 
FRP sheet by a minimum of<MET> 100 mm</MET><ENG> 4 inches</ENG> on all sides.  Use anchors in reticent corners where overlapping 
is not possible.  The number and locations of the anchors require approval by the engineer of record.</LST><BRK/>
<BRK/>
<LST>c.  Delaminations or air voids less than<MET> 16,000 square mm</MET><ENG> 25 square inches</ENG> may be repaired by resin injection 
or ply replacement, depending upon the size and number of delaminations and their locations.  Consult 
the Contracting Officer on which repair method will be used.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.4.2   Pre-cured Systems</TTL><BRK/>
<BRK/>
<TXT>For pre-cured FRP systems, evaluate each delamination or air void and repair in accordance with the Contracting 
Officer's direction.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.8.5   Fiber Orientation</TTL><BRK/>
<BRK/>
<TXT>Evaluate fiber or pre-cured laminate orientation by visual inspection.  Evaluate for fiber waviness, a localized 
appearance of fibers that deviate from the general straight-fiber line in the form of kinks or waves.  Report 
fiber or pre-cured laminate misalignment of more than 5 degrees from that specified on the design drawings (approximately<MET>
 80 mm/m</MET><ENG> 1 in/ft</ENG>) to the Contracting Officer for evaluation and acceptance.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.6   <SUB>Record Retention</SUB></TTL><BRK/>
<BRK/>
<TXT>Retain the records of inspection and witness panels throughout the warranty period.  Retain samples of mixed 
resin and maintain a record of the placement of each batch.  Upon completion of repairs, re-inspect the laminate 
to verify that the repair was properly accomplished.  Evaluate the FRP systems and accept/reject based on conformance 
or nonconformance with the design drawings and specifications.  Include FRP system material properties, as-built 
fiber orientation, presence of delaminations, cure of resins, and adhesion to substrate in the evaluation.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.9   REPAIRS</TTL><BRK/>
<BRK/>
<SPT><TTL>3.9.1   Application Defects</TTL><BRK/>
<BRK/>
<TXT>Repair all defects spanning more than 5% of the surface area according to the FRP maintenance and repair procedure.  
There are two types of repairs: resin injection or removal and reapplication of the FRP system.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.2   Tears in the Reinforcing Fibers</TTL><BRK/>
<BRK/>
<TXT>Repair tears in the reinforcing fibers that cross fiber tows greater than<MET> 50 mm</MET><ENG> 2 inches</ENG> in length by adding 
additional plies of FRP material.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.3   Remedial Measures for Defects</TTL><BRK/>
<BRK/>
<TXT>In locations where the FRP adhesion does not meet the minimum adhesion requirements, remove the laminate from 
the wall surface and apply new laminate.  Review and get approval of the revised anchor details by the Contracting 
Officer prior to installation.  Should the Contracting Officer determine that anchors are inappropriate, remove 
the FRP composite and replace with new composite meeting the minimum adhesion requirements.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.10   WORK AREA CLEAN UP</TTL><BRK/>
<BRK/>
<TXT>Upon completion of the work, remove staging, scaffolding, and containers from the work site or destroy in an 
approved manner.  Remove FRP composite, resin, and other deposits on adjacent surfaces and leave the entire job 
cleaned to equal or better condition to that prior to the start of the job.  Place cloths, cotton waste and other 
debris that might constitute a fire hazard in closed metal containers and remove at the end of each day.  Dispose 
of all resins and adhesives properly as indicated on the MSDS sheets.  Store and transport all resins and adhesives 
as indicated in MSDS directions.  Contain and dispose of spent abrasive blast media properly as required by local 
authorities.  Contain all material to be discarded at the site until properly disposed.</TXT><BRK/>
<BRK/></SPT>
</PRT>   <END/><BRK/></SEC>