<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA          UFGS-23 05 93     (November 2008)<BRK/>
                                        ---------------------------------<BRK/>
Preparing Activity:  <PRA>NAVFAC</PRA>             Superseding<BRK/>
                                        UFGS-23 05 93.00 10   (July 2007)<BRK/>
                                        UFGS-23 08 00.00 20   (July 2007)<BRK/>
                                        UFGS-23-05-93.00 40   (June 2006)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 23 05 93</SCN><BRK/>
<BRK/>
<STL>TESTING, ADJUSTING, AND BALANCING FOR HVAC</STL><BRK/>
<DTE>11/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>testing, adjusting, 
and balancing (TAB) of heating, ventilating, and air-conditioning (HVAC) air 
and water distribution systems</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.<BRK/>
<BRK/>
This guide specification includes tailoring options for NASA, NAVFAC, and USACE.  
Selection or deselection of a tailoring option will include or exclude that 
option in the section, but editing the resulting section to fit the project 
is still required.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Show the following information on the project drawings:</NPR><BRK/>
<BRK/>
<NPR>1.  A unique number or mark for each piece of equipment or terminal.</NPR><BRK/>
<BRK/>
<NPR>2.  Air quantities at air terminals.</NPR><BRK/>
<BRK/>
<NPR>3.  Air quantities and temperatures in air handling unit schedules.</NPR><BRK/>
<BRK/>
<NPR>4.  Water quantities and temperatures in thermal energy transfer equipment schedules.</NPR><BRK/>
<BRK/>
<NPR>5.  Water quantities and heads in pump schedules.</NPR><BRK/>
<BRK/>
<NPR>6.  Water flow measurement fittings and balancing fittings.</NPR><BRK/>
<BRK/>
<NPR>7.  Ductwork Construction and Leakage Testing Table that defines the DALT test 
requirements, including each applicable HVAC duct system ID or mark, duct pressure 
class, duct seal class, and duct leakage test pressure. This table is included 
in the file for Graphics for Unified Facilities Guide Specifications:  <URL HREF="http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf">http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf</URL></NPR><BRK/>
<BRK/>
<NPR>8.  When applicable, provide notes on the drawings specifying and completely 
describing any special or out of the ordinary TAB work to be performed.  If 
required, provide special coordinating paragraphs in this section to compliment 
the special TAB notes on the design drawings.</NPR><BRK/>
<BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   <HL3>GENERAL</HL3></TTL><BRK/>
<TAI OPT="USACE"><NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use this specification for all projects which include new HVAC systems 
or modifications to existing HVAC systems.<BRK/>
<BRK/>
The "Design Agent's Representative" must be a member of the HVAC design team, 
from the AE or Engineering Division and must actively participate in the process, 
including review of all submittals contained herein and participation in testing, 
adjusting, and balancing (TAB) verification.  The planning and programming of 
either Title II services or in-house support is required as part of the participation 
of the "Design Agent's Representative".</NPR><BRK/>
<AST/><BRK/></NTE>
</TAI><BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
<BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
<BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ACOUSTICAL SOCIETY OF AMERICA (ASA)</ORG><BRK/><BRK/><RID>ASA S1.11</RID><RTL>(2004; Errata 2005) Specification for Octave- Band and Fractional-Octave-Band Analog and Digital Filters (ASA 65)</RTL><BRK/><BRK/><RID>ASA S1.4</RID><RTL>(1983; Amendment 1985; R 2006) Specification for Sound Level Meters (ASA 47)</RTL><BRK/><BRK/></REF><REF><ORG>AIR MOVEMENT AND CONTROL ASSOCIATION INTERNATIONAL (AMCA)</ORG><BRK/><BRK/><RID>AMCA 203</RID><RTL>(1990) Field Performance Measurements of Fan Systems</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING ENGINEERS (ASHRAE)</ORG><BRK/><BRK/><RID>ASHRAE 62.1</RID><RTL>(2007; INT 2007; INT 2-15 2008; Errata 2008; Addenda a, b, e, f and h 2008) Ventilation for Acceptable Indoor Air Quality</RTL><BRK/><BRK/><RID>ASHRAE HVAC APP IP HDBK</RID><RTL>(2007) HVAC Applications Handbook, I-P Edition</RTL><BRK/><BRK/><RID>ASHRAE HVAC APP SI HDBK</RID><RTL>(2007) HVAC Applications Handbook, SI Edition</RTL><BRK/><BRK/></REF><REF><ORG>ASSOCIATED AIR BALANCE COUNCIL (AABC)</ORG><BRK/><BRK/><RID>AABC MN-1</RID><RTL>(2002) National Standards for Total System Balance</RTL><BRK/><BRK/><RID>AABC MN-4</RID><RTL>(1996) Test and Balance Procedures</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL AERONAUTICS AND SPACE ADMINISTRATION (NASA)</ORG><BRK/><BRK/><RID>RCBEA GUIDE</RID><RTL>(2004) NASA Reliability Centered Building and Equipment Acceptance Guide</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)</ORG><BRK/><BRK/><RID>NEBB MASV</RID><RTL>(2006) Procedural Standards for Measurements and Assessment of Sound and Vibration</RTL><BRK/><BRK/><RID>NEBB PROCEDURAL STANDARDS</RID><RTL>(2005) Procedural Standards for TAB (Testing, Adjusting and Balancing) Environmental Systems</RTL><BRK/><BRK/></REF><REF><ORG>SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION (SMACNA)</ORG><BRK/><BRK/><RID>SMACNA 1143</RID><RTL>(1985) HVAC Air Duct Leakage Test Manual</RTL><BRK/><BRK/><RID>SMACNA 1780</RID><RTL>(2002; 3rd Ed) HVAC Systems - Testing, Adjusting and Balancing</RTL><BRK/><BRK/><RID>SMACNA 1858</RID><RTL>(2004) HVAC Sound And Vibration Manual - First Edition</RTL><BRK/><BRK/></REF><REF><ORG>U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)</ORG><BRK/><BRK/><RID>40 CFR 82</RID><RTL>Protection of Stratospheric Ozone</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   DEFINITIONS</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  AABC:  Associated Air Balance Council.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  COTR:  Contracting Officer's Technical Representative.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  DALT:  Duct air leakage test</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  DALT'd:  Duct air leakage tested</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  HVAC:  Heating, ventilating, and air conditioning; or heating, ventilating, and cooling.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  NEBB:  National Environmental Balancing Bureau</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Out-of-tolerance data:  Pertains only to field acceptance testing of Final DALT or TAB report.  
When applied to DALT work, this phase means "a leakage rate measured during DALT field acceptance 
testing which exceeds the leakage rate allowed by SMACNA Leak Test Manual for an indicated duct 
construction and sealant class."  When applied to TAB work this phase means "a measurement taken 
during TAB field acceptance testing which does not fall within the range of plus 5 to minus 
5 percent of the original measurement reported on the TAB Report for a specific parameter."</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Season of maximum heating load:  The time of year when the outdoor temperature at the project 
site remains within<MET> plus or minus 17.5 degrees Celsius</MET><ENG> plus or minus 30 degrees Fahrenheit</ENG> of 
the project site's winter outdoor design temperature, throughout the period of TAB data recording.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">i.  Season of maximum cooling load:  The time of year when the outdoor temperature at the project 
site remains within<MET> plus or minus 3 degrees Celsius</MET><ENG> plus or minus 5 degrees Fahrenheit</ENG> of the 
project site's summer outdoor design temperature, throughout the period of TAB data recording.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">j.  Season 1, Season 2:  Depending upon when the project HVAC is completed and ready for TAB, 
Season 1 is defined, thereby defining Season 2.  Season 1 could be the season of maximum heating 
load, or the season of maximum cooling load.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">k.  Sound measurements terminology:  Defined in <RID>AABC MN-1</RID>, <RID>NEBB MASV</RID>, or <RID>SMACNA 1858</RID> (TABB).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">l.  TAB:  Testing, adjusting, and balancing (of HVAC systems).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">m.  TAB'd:  HVAC Testing/Adjusting/Balancing procedures performed.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">n.  TAB Agency:  TAB Firm</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">o.  TAB team field leader:  <SUB>TAB team field leader</SUB></ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">p.  TAB team supervisor:  <SUB>TAB team engineer</SUB>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">q.  TAB team technicians:  <SUB>TAB team assistants</SUB>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">r.  TABB:  Testing Adjusting and Balancing Bureau.</ITM><BRK/>
<BRK/>
<SPT><TTL>1.2.1   Similar Terms</TTL><BRK/>
<BRK/>
<TXT>In some instances, terminology differs between the Contract and the TAB Standard primarily because the intent 
of this Section is to use the industry standards specified, along with additional requirements listed herein 
to produce optimal results.<BRK/>
<BRK/>
The following table of similar terms is provided for clarification only.  Contract requirements take precedent 
over the corresponding AABC, NEBB, or TABB requirements where differences exist.</TXT><BRK/>
<BRK/>
<TBL><THD><HL4>SIMILAR TERMS</HL4><BRK/>
<BRK/></THD>
Contract Term  AABC                   NEBB                    TABB<BRK/>
               Term                   Term                    Term<BRK/>
<BRK/>
TAB Standard   National Standards     Procedural Standards    International<BRK/>
               for                    for                     Standards for<BRK/>
               Testing and Balancing  Testing, Adjusting      Environmental<BRK/>
               Heating, Ventilating,  and Balancing of        Systems Balance<BRK/>
               and Air Conditioning   Environmental Systems<BRK/>
               Systems<BRK/>
<BRK/>
TAB Specialist TAB Engineer           TAB Supervisor          TAB Supervisor<BRK/>
<BRK/>
Systems        Construction Phase     Field Readiness         Field<BRK/>
Readiness      Inspection             Check &amp; Preliminary     Readiness<BRK/>
Check                                 Field Procedures.       Check &amp;<BRK/>
                                                              Prelim.<BRK/>
                                                              Field<BRK/>
                                                              Procedures<BRK/></TBL>
<BRK/></SPT>
</SPT><SPT><TTL>1.3   WORK DESCRIPTION </TTL><BRK/>
<BRK/>
<TXT>The work includes duct air leakage testing (DALT) and testing, adjusting, and balancing (TAB) of [new][ and existing] 
heating, ventilating, and cooling (HVAC) air[ and water] distribution systems including <TAI OPT="NASA,USACE"><SUB>equipment and performance 
data</SUB>,</TAI> ducts, and piping which are located within, on, under, between, and adjacent to buildings<TAI OPT="NASA,USACE">, including <SUB>records 
of existing conditions</SUB></TAI>.</TXT><BRK/>
<BRK/>
<TXT>Perform TAB in accordance with the requirements of the TAB procedural standard recommended by the TAB trade association 
that approved the TAB Firm's qualifications.  Comply with requirements of <RID>AABC MN-1</RID>, <RID>NEBB PROCEDURAL STANDARDS</RID>
, or <RID>SMACNA 1780</RID> (TABB)  as supplemented and modified by this specification section.  All recommendations and 
suggested practices contained in the TAB procedural standards are considered mandatory.</TXT><BRK/>
<BRK/>
<NTE><AST/><BRK/>
<NPR>NOTE:  When the measurement of existing conditions is desired, clearly indicate 
and/or specify all  requirements.</NPR><BRK/>
<AST/></NTE><BRK/>
<BRK/>
<TXT>Conduct DALT and TAB of the indicated existing systems and equipment and submit the specified DALT and TAB reports 
for approval.  Conduct DALT testing in compliance with the requirements specified in <RID>SMACNA 1143</RID>, except as supplemented 
and modified by this section.  Conduct DALT and TAB work in accordance with the requirements of this section.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Air Distribution Systems</TTL><BRK/>
<BRK/>
<TXT><TST>Test, adjust, and balance system[s] (TAB) in compliance with this section.</TST>  Obtain Contracting Officer's written 
approval before applying insulation to exterior of air distribution systems as specified under Section 
<SRF>23 07 00</SRF> THERMAL INSULATION FOR MECHANICAL SYSTEMS.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2   Water Distribution Systems</TTL><BRK/>
<BRK/>
<TXT>TAB system[s] in compliance with this section.  Obtain Contracting Officer's written approval before applying 
insulation to water distribution systems as specified under Section <SRF>23 07 00</SRF> THERMAL INSULATION FOR MECHANICAL 
SYSTEM.  At Contractor's option and with Contracting Officer's written approval, the piping systems may be insulated 
before systems are TAB'd.<BRK/>
<BRK/>
Terminate piping insulation immediately adjacent to each flow control valve, automatic control valve, or device.  
Seal the ends of pipe insulation and the space between ends of pipe insulation and piping, with waterproof vapor 
barrier coating.<BRK/>
<BRK/>
After completion of work under this section, insulate the flow control valves and devices as specified under 
Section <SRF>23 07 00</SRF> THERMAL INSULATION FOR MECHANICAL SYSTEMS.</TXT><BRK/>
<BRK/></SPT>
<TAI OPT="NASA,USACE"><SPT><TTL>1.3.3   TAB SCHEMATIC DRAWINGS</TTL><BRK/>
<BRK/>
<TXT>Show the following information on TAB Schematic Drawings:</TXT><BRK/>
<BRK/>
<LST>1.  A unique number or mark for each piece of equipment or terminal.</LST><BRK/>
<BRK/>
<LST>2.  Air quantities at air terminals.</LST><BRK/>
<BRK/>
<LST>3.  Air quantities and temperatures in air handling unit schedules.</LST><BRK/>
<BRK/>
<LST>4.  Water quantities and temperatures in thermal energy transfer equipment schedules.</LST><BRK/>
<BRK/>
<LST>5.  Water quantities and heads in pump schedules.</LST><BRK/>
<BRK/>
<LST>6.  Water flow measurement fittings and balancing fittings.</LST><BRK/>
<BRK/>
<LST>7.  Ductwork Construction and Leakage Testing Table that defines the DALT test requirements, including 
each applicable HVAC duct system ID or mark, duct pressure class, duct seal class, and duct leakage test 
pressure.  This table is included in the file for Graphics for Unified Facilities Guide Specifications:<BRK/>
<URL>http://www.wbdg.org/ccb/browse_org.php?o=70</URL></LST><BRK/>
<BRK/>
<TXT>The Testing, Adjusting, and Balancing (TAB) Specialist must review the Contract Plans and Specifications and 
advise the Contracting Officer of any deficiencies that would prevent the effective and accurate TAB of the system, 
including <SUB>records of existing conditions</SUB>, and <SUB>systems readiness check</SUB>.  The TAB Specialist must provide a <SUB>Design 
Review Report</SUB> individually listing each deficiency and the corresponding proposed corrective action necessary 
for proper system operation.</TXT><BRK/>
<BRK/>
<TXT>Submit [three][_____] copies of the <SUB>TAB Schematic Drawings and Report Forms</SUB> to the Contracting Officer, no later 
than [21][_____] days prior to the start of TAB field measurements.</TXT><BRK/>
<BRK/></SPT>
</TAI><SPT><TTL>1.3.4   Related Requirements</TTL><BRK/>
<TAI OPT="NASA"><NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If Section <SRF>23 00 00</SRF> AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST 
SYSTEMS is not included in the project specification, applicable requirements 
therefrom should be inserted and the following paragraph deleted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Section <SRF>23 00 00</SRF> AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS applies to work specified in this section.<BRK/>
<BRK/>
Specific requirements relating to Reliability Centered Maintenance (RCM) principals and Predictive Testing and 
Inspection (PTI), by the construction contractor to detect latent manufacturing and installation defects must 
be followed as part of the Contractor's Quality Control program.  Refer to the paragraph titled "Sustainability" 
for detailed requirements.</TXT></TAI><BRK/>
<TAI OPT="NAVFAC"><BRK/>
<TXT>Requirements for price breakdown of HVAC TAB work are specified in Section <SRF>01 20 00.00 20</SRF> PRICE AND PAYMENT PROCEDURES.</TXT><BRK/>
<BRK/>
<TXT>Requirements for construction scheduling related to HVAC TAB work are specified in Section <SRF>01 32 17.00 20</SRF> NETWORK 
ANALYSIS SCHEDULES.</TXT></TAI><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  Submit the following 
in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>If using this section for NAVFAC DALT and TAB projects, keep "G" for submittals.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Refer to the paragraph above entitled "Phasing of Work".  If this paragraph 
applies to the construction contract, modify the entire "SUBMITTALS" paragraph 
by phasing (maybe by repeating the various submittals for each phase) to facilitate 
the submittal process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TAI OPT="NASA,USACE"><LST><SUB>SD-01 Preconstruction Submittals</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Records of Existing Conditions</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>TAB Firm</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Designation of <SUB>TAB team assistants</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Designation of <SUB>TAB team engineer</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]or <SUB>TAB Specialist</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Designation of <SUB>TAB team field leader</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>TAB Schematic Drawings and Report Forms</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Equipment and Performance Data</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>TAB Related HVAC Submittals</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  A list of the TAB Related HVAC Submittals, no later than [7] [_____] days after the approval 
of the TAB team engineer [and assistant].</ITM><BRK/>
<BRK/>
<ITM><SUB>TAB Procedures</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Proposed procedures for TAB, submitted with the TAB Schematic Drawings and Report Forms.</ITM><BRK/>
<BRK/>
<ITM><SUB>Calibration</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Systems Readiness Check</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>TAB Execution</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>TAB Verification</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/></TAI>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>DALT and TAB Work Execution Schedule</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>DALT and TAB Procedures Summary</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Design review report</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Pre-Final DALT report</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Final DALT report</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>TAB report for Season 1</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>TAB report for Season 2</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<TAI OPT="NAVFAC"><ITM><SUB>Independent TAB agency and personnel qualifications</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Advance notice of Pre-Final DALT field work</SUB>; <SUB>G</SUB> </ITM><BRK/>
<BRK/>
<ITM><SUB>Completed Pre-Final DALT Work Checklist</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Advance Notice of [Season 1 ]TAB Field Work</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Completed [Season 1 ]Pre-TAB Work Checklist</SUB></ITM><BRK/>
<BRK/>
<ITM>[<SUB>Advance Notice of Season 2 TAB Field Work</SUB>; <SUB>G</SUB>]</ITM><BRK/>
<BRK/>
<ITM>[<SUB>Completed Season 2 Pre-TAB Work Checklist</SUB>]</ITM><BRK/></TAI>
<TAI OPT="NASA,USACE"><BRK/>
<ITM><SUB>TAB Firm</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Independent TAB Agency and Personnel Qualifications</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>DALT and TAB Submittal and Work Schedule</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Design review report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>[<SUB>Pre-field DALT preliminary notification</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]]</ITM><BRK/>
<BRK/>
<ITM><SUB>Pre-field TAB engineering report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Advanced notice for [Season 1] TAB field work</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Prerequisite HVAC Work Check Out List [For Season 1]</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>[<SUB>Advanced notice for Season 2 TAB field work</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]]</ITM><BRK/>
<BRK/>
<ITM>[<SUB>Prerequisite HVAC Work Check Out List For Season 2</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]]</ITM><BRK/></TAI>
<BRK/></SPT>
<SPT><TTL>1.5   QUALITY ASSURANCE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.5.1   <SUB>Independent Tab Agency and Personnel Qualifications</SUB></TTL><BRK/>
<BRK/>
<TXT>To secure approval for the proposed agency, submit information certifying that the TAB agency is a first tier 
subcontractor who is not affiliated with any other company participating in work on this contract, including 
design, furnishing equipment, or construction.  Further, submit the following, for the agency, to Contracting 
Officer for approval: </TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Independent AABC or NEBB or TABB TAB agency:</ITM><BRK/>
<BRK/>
<ITM>TAB agency:  AABC registration number and expiration date of current certification; or NEBB 
certification number and expiration date of current certification; or TABB certification number 
and expiration date of current certification.</ITM><BRK/>
<BRK/>
<ITM>TAB team supervisor:  Name and copy of AABC or NEBB or TABB TAB supervisor certificate and expiration 
date of current certification.</ITM><BRK/>
<BRK/>
<ITM>TAB team field leader:  Name and documented evidence that the team field leader has satisfactorily 
performed full-time supervision of TAB work in the field for not less than 3 years immediately 
preceding this contract's bid opening date.</ITM><BRK/>
<BRK/>
<ITM>TAB team field technicians:  Names and documented evidence that each field technician has satisfactorily 
assisted a TAB team field leader in performance of TAB work in the field for not less than one 
year immediately preceding this contract's bid opening date.</ITM><BRK/>
<BRK/>
<ITM>Current certificates:  Registrations and certifications are current, and valid for the duration 
of this contract.  Renew Certifications which expire prior to completion of the TAB work, in 
a timely manner so that there is no lapse in registration or certification.  TAB agency or TAB 
team personnel without a current registration or current certification are not to perform TAB 
work on this contract.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  TAB Team Members:  TAB team approved to accomplish work on this contract are full-time employees 
of the TAB agency.  No other personnel is allowed to do TAB work on this contract.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Replacement of TAB team members:  Replacement of members may occur if each new member complies 
with the applicable personnel qualifications and each is approved by the Contracting Officer.</ITM><BRK/>
<BRK/></SPT>
<TAI OPT="NASA,USACE"><SPT><TTL>1.5.2   Tab Standard</TTL><BRK/>
<BRK/>
<TXT>Perform TAB in accordance with the requirements of the standard under which the TAB Firm's qualifications are 
approved, i.e., <RID>AABC MN-1</RID>, <RID>NEBB PROCEDURAL STANDARDS</RID>, or <RID>SMACNA 1780</RID> unless otherwise specified herein.  All 
recommendations and suggested practices contained in the TAB Standard are considered mandatory.  Use the provisions 
of the TAB Standard, including checklists, report forms, etc., as nearly as practical, to satisfy the Contract 
requirements.  Use the TAB Standard for all aspects of TAB, including qualifications for the TAB Firm and Specialist 
and <SUB>calibration</SUB> of TAB instruments.  Where the instrument manufacturer calibration recommendations are more stringent 
than those listed in the TAB Standard, adhere to the manufacturer's recommendations.<BRK/>
<BRK/>
All quality assurance provisions of the TAB Standard such as performance guarantees are part of this contract.  
For systems or system components not covered in the TAB Standard, <SUB>TAB procedures</SUB> must be developed by the TAB 
Specialist.  Where new procedures, requirements, etc., applicable to the Contract requirements have been published 
or adopted by the body responsible for the TAB Standard used (AABC, NEBB, or TABB), the requirements and recommendations 
contained in these procedures and requirements are considered mandatory, including the latest requirements of <RID>
ASHRAE 62.1</RID>.</TXT><BRK/>
<BRK/></SPT>
</TAI><TAI OPT="NASA"><SPT><TTL>1.5.3   Sustainability</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Designer/specifier must select appropriate PTI procedures to develop 
acceptance criteria subject to the equipment and accessories used.  Detailed 
procedures are contained within the RCBEA Guide.  Delete the items and testing 
which do not apply to your specific project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Contractor must submit the following as part of the Quality Control Plan for acceptance testing:</TXT><BRK/>
<BRK/>
<TST><LST>a.  List all test equipment to be used, including its manufacturer,model number, calibration date, and 
serial number.</LST><BRK/>
<BRK/>
<LST>b.  Certificates of test personnel qualifications and certifications.  Provide certification of compliance 
with <RID>40 CFR 82</RID>.</LST><BRK/>
<BRK/>
<LST>c.  Proof of equivalency if the contractor desires to substitute a test requirement.</LST></TST><BRK/>
<BRK/>
<TXT>Perform the following PTI as an integral part of the TAB process per the most recent edition of the NASA <RID>RCBEA GUIDE</RID>
:</TXT><BRK/>
<BRK/>
[<LST>Compressors:</LST><BRK/>
<ITM>a.  Vibration Analysis</ITM><BRK/>
<ITM>b.  Balance Test and Measurement</ITM><BRK/>
<ITM>c.  Alignment (laser preferred)</ITM><BRK/>
<ITM>d.  Lubricating Oil Test</ITM><BRK/>
<ITM>e.  Thermodynamic Performance Test</ITM><BRK/>
][<ITM>f.  Hydraulic Oil Test (optional)</ITM><BRK/>
]<BRK/>
[<LST>Fans:</LST><BRK/>
<ITM>a.  Vibration Analysis</ITM><BRK/>
<ITM>b.  Balance Test and Measurement</ITM><BRK/>
<ITM>c.  Alignment (laser preferred)</ITM><BRK/>
<ITM>d.  Lubricating Oil Test</ITM><BRK/>
<ITM>e.  Thermodynamic Performance Test</ITM><BRK/>
]<BRK/>
[<LST>Heat Exchangers (General):</LST><BRK/>
<ITM>a.  Hydrostatic Test</ITM><BRK/>
<ITM>b.  Airborne Ultrasonic Test</ITM><BRK/>
<ITM>c.  Thermodynamic Performance Test</ITM><BRK/>
][<ITM>d.  Infrared Thermography (optional)</ITM>]<BRK/>
<BRK/>
[<LST>Heat Exchangers (Condenser Air Cooled):</LST><BRK/>
<ITM>a.  Hydrostatic Test</ITM><BRK/>
<ITM>b.  Thermodynamic Performance Test</ITM><BRK/>
][<ITM>c.  Airborne Ultrasonic Test (optional)</ITM>]<BRK/>
[<ITM>d.  Pulse Ultrasonic Test  (optional)</ITM>]<BRK/>
[<ITM>e.  Infrared Thermography (optional)</ITM>]<BRK/>
<BRK/>
[<LST>Heat Exchangers (Condenser Water Cooled):</LST><BRK/>
<ITM>a.  Hydrostatic Test</ITM><BRK/>
<ITM>b.  Thermodynamic Performance Test</ITM><BRK/>
][<ITM>c.  Airborne Ultrasonic Test (optional)</ITM>]<BRK/>
[<ITM>d.  Pulse Ultrasonic Test  (optional)</ITM>]<BRK/>
[<ITM>e.  Infrared Thermography (optional)</ITM>]<BRK/>
<BRK/>
[<LST>Heat Exchange Cooling Tower:</LST><BRK/>
<ITM>a.  Vibration Analysis</ITM><BRK/>
<ITM>b.  Balance Test and Measurement</ITM><BRK/>
<ITM>c.  Alignment (laser preferred)</ITM><BRK/>
<ITM>d.  Lubricating Oil Test</ITM><BRK/>
<ITM>e.  Performance Test</ITM><BRK/>
]<BRK/>
[<LST>HVAC Ducts:</LST><BRK/>
<ITM>a.  Operational Test</ITM><BRK/>
<ITM>b.  Ductwork Leak Testing (DALT); <SUB>Pre-Final DALT report</SUB>, <SUB>Final DALT report</SUB></ITM><BRK/>
]<BRK/>
[<LST>Piping Systems:</LST><BRK/>
<ITM>a.  Vibration Analysis</ITM><BRK/>
<ITM>b.  Infrared Thermography</ITM><BRK/>
]<BRK/>
[<LST>Steam Coils:</LST><BRK/>
<ITM>a.  Warranty Test</ITM><BRK/>
<ITM>b.  Vibration Analysis</ITM><BRK/>
<ITM>c.  Performance Test</ITM><BRK/>
<ITM>d.  Infrared Thermography</ITM><BRK/>
]<BRK/>
[<LST>Valves:</LST><BRK/>
<ITM>a.  Hydrostatic Test</ITM><BRK/>
<ITM>b.  Airborne Ultrasonic Test (optional)</ITM><BRK/>
<ITM>c.  Thermodynamic Performance Test (optional)</ITM><BRK/>
][<ITM>d.  Infrared Thermography (optional)</ITM><BRK/>
]<BRK/></SPT>
</TAI><TAI OPT="NASA,USACE"><SPT><TTL>1.5.4   Qualifications</TTL><BRK/>
<BRK/>
<SPT><TTL>1.5.4.1   <SUB>TAB Firm</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Where the size or complexity of the HVAC system(s) warrant, include in 
the project specification the bracketed requirement specifying that the TAB 
firm be certified for "building systems commissioning".</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The TAB Firm must be either a member of AABC or certified by the NEBB or the TABB and certified in all categories 
and functions where measurements or performance are specified on the plans and specifications, including [TAB 
of environmental systems] [the performance of clean rooms and clean air devices] [building systems commissioning] 
[and] [the measuring of sound and vibration in environmental systems].</TXT><BRK/>
<BRK/>
<TXT>Certification must be maintained for the entire duration of duties specified herein.  If, for any reason, the 
firm loses subject certification during this period, the Contractor must immediately notify the Contracting Officer 
and submit another TAB Firm for approval.  Any firm that has been the subject of disciplinary action by either 
the AABC, the NEBB, or the TABB within the five years preceding Contract Award is not be eligible to perform 
any duties related to the HVAC systems, including TAB.  All work specified in this Section and in other related 
Sections to be performed by the TAB Firm will be considered invalid if the TAB Firm loses its certification prior 
to Contract completion and must be performed by an approved successor.</TXT><BRK/>
<BRK/>
<TXT>These TAB services are to assist the prime Contractor in performing the quality oversight for which it is responsible.  
The TAB Firm must be a prime subcontractor of the Contractor and be financially and corporately independent of 
the mechanical subcontractor, reporting directly to and paid by the Contractor.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.4.2   <SUB>TAB Specialist</SUB></TTL><BRK/>
<BRK/>
<TXT>The TAB Specialist must be either a member of AABC,an experienced technician of the Firm certified by the NEBB, 
or a Supervisor certified by the TABB.  The certification must be maintained for the entire duration of duties 
specified herein.  If, for any reason, the Specialist loses subject certification during this period, immediately 
notify the Contracting Officer and submit another TAB Specialist for approval.  Any individual that has been 
the subject of disciplinary action by either the AABC, the NEBB, or the TABB within the five years preceding 
Contract Award is not eligible to perform any duties related to the HVAC systems, including TAB.  All work specified 
in this Section and in other related Sections performed by the TAB Specialist will be considered invalid if the 
TAB Specialist loses its certification prior to Contract completion and must be performed by the approved successor.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.4.3   TAB Specialist Responsibilities</TTL><BRK/>
<BRK/>
<TXT>TAB Specialist responsibilities include all TAB work specified herein and in related sections under his direct 
guidance.  The TAB specialist is required to be onsite on a daily basis to direct TAB efforts.  The TAB Specialist 
must participate in the commissioning process<TAI OPT="USACE">[ specified in Section <SRF>23 08 00.00 10</SRF> COMMISSIONING OF HVAC SYSTEMS]</TAI>
.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.4.4   <SUB>Tab Related HVAC Submittals</SUB></TTL><BRK/>
<BRK/>
<TXT>The TAB Specialist must prepare a list of the submittals from the Contract Submittal Register that relate to 
the successful accomplishment of all HVAC TAB.  Accompany the submittals identified on this list with a letter 
of approval signed and dated by the TAB Specialist when submitted to the Government.  Ensure that the location 
and details of ports, terminals, connections, etc., necessary to perform TAB are identified on the submittals.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.5.5   Responsibilities</TTL><BRK/>
<BRK/>
<TXT>The Contractor is responsible for ensuring compliance with the requirements of this section.  The following delineation 
of specific work responsibilities is specified to facilitate <SUB>TAB execution</SUB> of the various work efforts by personnel 
from separate organizations.  This breakdown of specific duties is specified to facilitate adherence to the schedule 
listed in paragraph entitled "TAB Submittal and Work Schedule."</TXT><BRK/>
<BRK/>
<SPT><TTL>1.5.5.1   Contractor</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  TAB personnel:  Ensure that the DALT work and the TAB work is accomplished by a group meeting 
the requirements specified in paragraph entitled "TAB Personnel Qualification Requirements."</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Pre-DALT/TAB meeting:  Attend the meeting with the TAB Supervisor, and ensure that a representative 
is present for the sheetmetal contractor, mechanical contractor, electrical contractor, and 
automatic temperature controls contractor.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  HVAC documentation:  Furnish one complete set of the following HVAC-related documentation 
to the TAB agency:</ITM><BRK/>
<BRK/>
<ITM>(1)  Contract drawings and specifications</ITM><BRK/>
<BRK/>
<ITM>(2)  Approved submittal data for equipment</ITM><BRK/>
<BRK/>
<ITM>(3)  Construction work schedule</ITM><BRK/>
<BRK/>
<ITM>(4)  Up-to-date revisions and change orders for the previously listed items</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Submittal and work schedules:  Ensure that the schedule for submittals and work required 
by this section and specified in paragraph entitled "TAB Submittal and Work Schedule," is met.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Coordination of supporting personnel:<BRK/>
<BRK/>
Provide the technical personnel, such as factory representatives or HVAC controls installer 
required by the TAB field team to support the DALT and the TAB field measurement work.<BRK/>
<BRK/>
Provide equipment mechanics to operate HVAC equipment and ductwork mechanics to provide the 
field designated test ports to enable TAB field team to accomplish the DALT and the TAB field 
measurement work.  Ensure these support personnel are present at the times required by the TAB 
team, and cause no delay in the DALT andthe TAB field work.<BRK/>
<BRK/>
Conversely, ensure that the HVAC controls installer has required support from the TAB team field 
leader to complete the controls check out.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Deficiencies:  Ensure that the TAB Agency supervisor submits all Design/Construction deficiency 
notifications directly to the Contracting officer within 3 days after the deficiency is encountered.  
Further,  ensure that all such notification submittals are complete with explanation, including 
documentation, detailing deficiencies.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Prerequisite HVAC work:  Complete check out and debugging of HVAC equipment, ducts, and 
controls prior to the TAB engineer arriving at the project site to begin the TAB work.  Debugging 
includes searching for and eliminating malfunctioning elements in the HVAC system installations, 
and verifying all adjustable devices are functioning as designed.  Include as prerequisite work 
items, the deficiencies pointed out by the TAB team supervisor in the design review report.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Prior to the TAB field team's arrival, ensure completion of the applicable inspections and 
work items listed in the TAB team supervisor's pre-field engineering report.  Do not allow the 
TAB team to commence TAB field work until all of the following are completed.</ITM><BRK/>
<BRK/>
<ITM>(1)  HVAC system installations are fully complete.</ITM><BRK/>
<BRK/>
<ITM>(2)  HVAC prerequisite checkout work lists specified in the paragraph "Pre-Field TAB Engineering 
Report" are completed, submitted, and approved.  Ensure that the TAB Agency gets a copy of the 
approved prerequisite HVAC work checklist.</ITM><BRK/>
<BRK/>
<ITM>(3)  DALT field checks for all systems are completed.</ITM><BRK/>
<BRK/>
<ITM>(4)  HVAC system filters are clean for both Season 1 and Season 2 TAB field work.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">i.  Advance notice:  Furnish to the Contracting Officer with advance written notice for the 
commencement of the DALT field work and for the commencement of the TAB field work.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">j.  Insulation work:  For required DALT work , ensure that insulation is not installed on ducts 
to be DALT'd until DALT work on the subject ducts is complete.  Later, ensure that openings 
in duct and machinery insulation coverings for TAB test ports are marked, closed and sealed.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.5.2   TAB Agency</TTL><BRK/>
<BRK/>
<TXT>Provide the services of a TAB team which complies with the requirements of paragraph entitled "Independent TAB 
Agency Personnel Qualifications".  The work to be performed by the TAB agency is limited to testing, adjusting, 
and balancing of HVAC air and water systems to satisfy the requirements of this specification section.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.5.3   TAB Team Supervisor</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Overall management:  Supervise and manage the overall TAB team work effort, including preliminary 
and technical DALT and TAB procedures and TAB team field work.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Pre-DALT/TAB meeting:  Attend meeting with Contractor.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Design review report:  Review project specifications and accompanying drawings to verify 
that the air systems and water systems are designed in such a way that the TAB engineer can 
accomplish the work in compliance with the requirements of this section.  Verify the presence 
and location of permanently installed test ports and other devices needed, including gauge cocks, 
thermometer wells, flow control devices, circuit setters, balancing valves, and manual volume 
dampers.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Support required:  Specify the technical support personnel required from the Contractor 
other than the TAB agency; such as factory representatives for temperature controls or for complex 
equipment.  Inform the Contractor in writing of the support personnel needed and when they are 
needed.  Furnish the notice as soon as the need is anticipated, either with the design review 
report, or the pre-field engineering report, the  during the DALT or TAB field work.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Pre-field DALT preliminary notification:  Monitor the completion of the duct installation 
of each system and provide the necessary written notification to the Contracting Officer.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Pre-field engineering report:  Utilizing the following HVAC-related documentation; contract 
drawings and specifications, approved submittal data for equipment, up-to-date revisions and 
change orders; prepare this report.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Prerequisite HVAC work checklist:  Ensure the Contractor gets a copy of this checklist at 
the same time as the pre-field engineering report is submitted.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Technical assistance for DALT work.</ITM><BRK/>
<BRK/>
<ITM>(1)  Technical assistance:  Provide immediate technical assistance to TAB field team.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The number of workdays for the TAB supervisor's visit to the contract 
site for DALT work, is based on the size, number, type, and complexity of the 
HVAC system to be DALT'd.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>(2) DALT field visit:  Near the end of the DALT field work effort, visit the contract site to 
inspect the HVAC installation and the progress of the DALT field work.  Conduct a site visit 
to the extent necessary to verify correct procedures are being implemented and to confirm the 
accuracy of the Pre-final DALT Report data which has been reported.  Also, perform sufficient 
evaluation  to allow the TAB supervisor to issue certification of the final report.  Conduct 
the site visit full-time for a minimum of [one] [two] [_____] 8 hour workday[s] duration.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">i.  Final DALT report:  Certify the DALT report.  This certification includes the following 
work:</ITM><BRK/>
<BRK/>
<ITM>(1)  Review:  Review the Pre-final DALT report data.  From these field reports, prepare the 
Certified Final DALT report.</ITM><BRK/>
<BRK/>
<ITM>(2)  <SUB>TAB Verification</SUB>:  Verify adherence, by the TAB field team, to the procedures specified 
in this section.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">j.  Technical Assistance for TAB Work:  Provide immediate technical assistance to the TAB field 
team for the TAB work.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The number of workdays for the TAB supervisor's visits to the contract 
work site for TAB work, is based on the size, number, type, and complexity of 
the HVAC system to be TAB'd.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Option 1:  Normally, use the following two subparagraphs, which requires 
two separate trips within a season to the contract site by the TAB field team 
(the first for the TAB field work, the second for the TAB quality assurance 
work) with the certified TAB report submitted between the trips.   This is intended 
to give the design engineer time to review the certified TAB report before the 
field check of that report is conducted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[(1) TAB field visit:  At the midpoint of the Season 1 and Season 2 TAB field work effort, visit 
the contract site to inspect the HVAC installation and the progress of the TAB field work. Conduct 
site visit full-time for a minimum of [one] [two] [_____] 8 hour workday[s] duration.]</ITM><BRK/>
<BRK/>
<ITM>[(2) TAB field visit:  Near the end of the TAB field work effort, visit the contract site to 
inspect the HVAC installation and the progress of the TAB field work.  Conduct site visit full-time 
for a minimum of [one] [two] [_____] 8 hour workday[s] duration.  Review the TAB final report 
data and certify the TAB final report.]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Option 2:  Use the following subparagraph when the contract site is remote, 
or the HVAC system is simple, and the specifier wants to reduce to one the number 
of trips to the contract site by the TAB field team within a season (TAB field 
work and TAB quality assurance accomplished in same trip).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[(1) TAB field visit:  Near the end of the TAB field work effort, visit the contract site to 
inspect the HVAC installation and the progress of the TAB field work.  Conduct site visit full-time 
for a minimum of [one] [two] [_____] 8 hour workday[s] duration.  Review the TAB final report 
data and certify the TAB final report.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">k.  Certified TAB report:  Certify the TAB report.  This certification includes the following 
work:</ITM><BRK/>
<BRK/>
<ITM>(1)  Review:  Review the TAB field data report.  From this field report, prepare the certified 
TAB report.</ITM><BRK/>
<BRK/>
<ITM>(2)  Verification:  Verify adherence, by the TAB field team, to the TAB plan prescribed by the 
pre-field engineering report and verify adherence to the procedures specified in this section.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">l.  Design/Construction deficiencies:  Within 3 working days after the TAB Agency has encountered 
any design or construction deficiencies, the TAB Supervisor must submit written notification 
directly to the Contracting Officer, with a separate copy to the Contractor, of all such deficiencies.  
Provide in this submittal a complete explanation, including supporting documentation, detailing 
deficiencies.  Where deficiencies are encountered that are believed to adversely impact successful 
completion of TAB, the TAB Agency must issue notice and request direction in the notification 
submittal.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">m.  TAB Field Check:  The TAB team supervisor must attend and supervise [Season 1] [and Season 
2] TAB field check.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.5.4   TAB Team Field Leader</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Field manager:  Manage, in the field, the accomplishment of the work specified in Part 3, 
"Execution."</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Full time:  Be present at the contract site when DALT field work or TAB field work is being 
performed by the TAB team; ensure day-to-day TAB team work accomplishments are in compliance 
with this section.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Prerequisite HVAC work:  Do not bring the TAB team to the contract site until a copy of 
the prerequisite HVAC Checklist, with all work items certified by the Contractor to be working 
as designed, reaches the office of the TAB Agency.</ITM><BRK/>
<BRK/></SPT>
</SPT></TAI><TAI OPT="NASA,USACE"><SPT><TTL>1.5.6   Test Reports</TTL><BRK/>
<BRK/>
<SPT><TTL>1.5.6.1   Data from DALT Field Work</TTL><BRK/>
<BRK/>
<TXT>Report the data for the Pre-final DALT Report and Certified Final DALT Report in compliance the following requirements:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Report format:  Submit report data on Air Duct Leakage Test Summary Report Forms as shown 
on Page 6-2 of <RID>SMACNA 1143</RID>.  In addition, submit in the report, a marked duct shop drawing which 
identifies each section of duct tested with assigned node numbers for each section.  Include 
node numbers in the completed report forms to identify each duct section.  The TAB supervisor 
must review and certify the report.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  The TAB supervisor must include a copy of all calculations prepared in determining the duct 
surface area of each duct test section.  In addition,provide the ductwork air leak testing (DALT) 
reports with a copy(s) of the calibration curve for each of the DALT test orifices used for 
testing.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Instruments:  List the types of instruments actually used to measure the data.  Include 
in the listing each instrument's unique identification number, calibration date, and calibration 
expiration date.  Instruments must have been calibrated within one year of the date of use in 
the field.  Instrument calibration must be traceable to the measuring standards of the National 
Institute of Standards and Technology.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Certification:  Include the typed name of the TAB supervisor and the dated signature of 
the TAB supervisor.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.6.2   Certified TAB Reports</TTL><BRK/>
<BRK/>
<TXT>Submit:  <SUB>TAB Report for Season 1</SUB> and <SUB>TAB Report for Season 2</SUB> in the following manner:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Report format:  Submit the completed pre-field data forms approved in the pre-field TAB 
Engineering Report completed by TAB field team, reviewed and certified by the TAB supervisor.  
Bind the report with a waterproof front and back cover.  Include a table of contents identifying 
by page number the location of each report.  Report forms and report data must be typewritten.  
Handwritten report forms or report data are not acceptable.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Temperatures:  On each TAB report form reporting TAB work accomplished on HVAC thermal energy 
transfer equipment, include the indoor and outdoor dry bulb temperature range and indoor and 
outdoor wet bulb temperature range within which the TAB data was recorded.  Include in the TAB 
report continuous time versus temperature recording data of wet and dry bulb temperatures for 
the rooms, or zones, as designated in the following list:</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The design engineer must list, in the paragraph below, those rooms, or 
zones, for which indoor dry bulb and wet bulb temperatures are compiled for 
the specified time duration.  Include a sufficient number of rooms, or zones, 
in the listing to ensure correct evaluation of performance for the installed 
HVAC systems.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>(1)  [Specifier:  List desired rooms and/or zones here].  Measure and compile data on a continuous 
basis for the period in which TAB work affecting those rooms is being done.</ITM><BRK/>
<BRK/>
<ITM>(2)  Measure and record data only after the HVAC systems installations are complete, the systems 
fully balanced and the HVAC systems controls operating in fully automatic mode.</ITM><BRK/>
<BRK/>
<ITM>(3)  Data may be compiled using direct digital controls trend logging where available.  Otherwise, 
temporarily install calibrated time versus temperature/humidity recorders for this purpose.  
The HVAC systems and controls must be fully operational a minimum of 24 hours in advance of 
commencing data compilation.  Include the specified data in the [Season I TAB Report] [Season 
I and Season 2 TAB Report].</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Paragraphs c., d., and e., below apply to air distribution systems to 
be TAB'd.  Delete all of these paragraphs if no air distribution systems are 
in the project, or delete the paragraphs not applicable and edit the terminology 
of the remaining paragraphs to agree with the drawings.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
[<ITM INDENT="-0.33">c. System Diagrams:  Provide updated diagrams with final installed locations of all terminals 
and devices, any numbering changes, and actual test locations.  Use a key numbering system on 
the diagram which identifies each outlet contained in the outlet airflow report sheets.</ITM>]<BRK/>
<BRK/>
[<ITM INDENT="-0.33">d.  Static Pressure Profiles:  Report static pressure profiles for air duct systems including:  
[_____].  Report static pressure data for all supply, return, relief, exhaust and outside air 
ducts for the systems listed.  Include the following in the static pressure report data, in 
addition to AABC/NEBB/TABB required data:</ITM><BRK/>
<BRK/>
<ITM>(1)  Report supply fan, return fan, relief fan, and exhaust fan inlet and discharge static pressures.</ITM><BRK/>
<BRK/>
<ITM>(2)  Report static pressure drop across chilled water coils, DX coils, hot water coils, steam 
coils, electric resistance heating coils and heat reclaim devices installed in unit cabinetry 
or the system ductwork.</ITM><BRK/>
<BRK/>
<ITM>(3)  Report static pressure drop across outside air, return air, and supply air automatic control 
dampers, both proportional and two-position, installed in unit cabinetry.</ITM><BRK/>
<BRK/>
<ITM>(4)  Report static pressure drop across air filters, acoustic silencers, moisture eliminators, 
air flow straighteners, air flow measuring stations or other pressure drop producing specialty 
items installed in unit cabinetry, or in the system ductwork.  Examples of these specialty items 
are smoke detectors, white sound generators, RF shielding, wave guides, security bars, blast 
valves, small pipes passing through ductwork, and duct mounted humidifiers.</ITM><BRK/>
<BRK/>
<ITM>Do not report static pressure drop across duct fittings provided for the sole purpose of conveying 
air, such as elbows, transitions, offsets, plenums, manual dampers, and branch takes-offs.</ITM><BRK/>
<BRK/>
<ITM>(5)  Report static pressure drop across outside air and relief/exhaust air louvers.</ITM>]<BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Below, delete the period at the end of the sentence and delete the brackets 
for projects with large air moving systems, i.e., include in the specification 
the pressure readings in the additional listed duct locations for air moving 
systems<MET> 4720 L/S</MET><ENG> 10000 CFM</ENG> and larger.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
[<ITM>(6)  Report static pressure readings of supply air, return air, exhaust/relief air, and outside 
air in duct at the point where these ducts connect to each air moving unit.[and also at the 
following locations:</ITM><BRK/>
<BRK/>
<ITM><HL1>Main Duct:</HL1> Take readings at four locations along the full length of the main duct, 25 percent, 
50 percent, 75 percent, and 100 percent of the total duct length.</ITM><BRK/>
<BRK/>
<ITM><HL1>Floor Branch Mains:</HL1> Take readings at floor branch mains served by a main duct vertical riser.</ITM><BRK/>
<BRK/>
<ITM><HL1>Branch Main Ducts:</HL1> Take readings at branch main ducts.</ITM><BRK/>
<BRK/>
<ITM><HL1>VAV Terminals:</HL1> Take readings at inlet static pressure at VAV terminal box primary air branch 
ducts.</ITM><BRK/>
<BRK/>
<ITM><HL1>VAV Terminals, Fan Powered:</HL1> Take readings at fan discharge and inlet static pressures for series 
and parallel fan powered VAV terminal boxes.]]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the brackets below for large air moving systems, i.e., include 
in the specification the duct traverses for the branch mains for air moving 
systems<MET> 4720 L/S</MET><ENG> 10000 CFM</ENG> and larger.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM INDENT="-0.33">e.  Duct Traverses:  Report duct traverses for main [and branch main] supply, return, exhaust, 
relief and outside air ducts.  This includes all ducts, including those which lack 7 1/2 duct 
diameters upstream and 2 1/2 duct diameters downstream of straight duct unobstructed by duct 
fittings/offsets/elbows.  The TAB Agency must evaluate and report findings on the duct traverses 
taken.  Evaluate the suitability of the duct traverse measurement based on satisfying the qualifications 
for a pilot traverse plane as defined by <RID>AMCA 203</RID>, "Field Measurements", Section 8, paragraph 
8.3, "Location of Traverse Plane."</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Instruments:  List the types of instruments actually used to measure the tab data.  Include 
in the listing each instrument's unique identification number, calibration date, and calibration 
expiration date.<BRK/>
<BRK/>
Instrumentation, used for taking wet bulb temperature readings must provide accuracy of plus 
or minus 5 percent at the measured face velocities.  Submit instrument manufacturer's literature 
to document instrument accuracy performance is in compliance with that specified.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Certification:  Include the typed name of the TAB supervisor and the dated signature of 
the TAB supervisor.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Performance Curves: The TAB Supervisor must include, in the TAB Reports, factory pump curves 
and fan curves for pumps and fans TAB'd on the job.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">i.  Calibration Curves:  The TAB Supervisor must include, in the TAB Reports, a factory calibration 
curve for installed flow control balancing valves, flow venturi's and flow orifices TAB'd on 
the job.</ITM><BRK/>
<BRK/></SPT>
</SPT></TAI></SPT>[<SPT><TTL>1.6   PROJECT/SITE CONDITIONS</TTL><BRK/>
<BRK/>
<NTE><AST/><BRK/>
<NPR>NOTE:  When the measurement of existing conditions is desired, clearly indicate 
and/or specify all  requirements.  If "existing conditions" does not apply, 
delete this paragraph.</NPR><BRK/>
<AST/></NTE><BRK/>
<BRK/>
<SPT><TTL>1.6.1   DALT and TAB Services to Obtain Existing Conditions</TTL><BRK/>
<BRK/>
<TXT>Conduct DALT and TAB of the indicated existing systems and equipment and submit the specified DALT and TAB reports 
for approval.  Conduct this DALT and TAB work in accordance with the requirements of this section.</TXT><BRK/>
<BRK/></SPT>
</SPT>]<SPT><TTL>1.7   SEQUENCING AND SCHEDULING</TTL><BRK/>
<BRK/>
<TAI OPT="NAVFAC"><SPT><TTL>1.7.1   <SUB>Dalt and Tab Submittal and Work Schedule</SUB></TTL><BRK/>
<BRK/>
<TXT>Comply with additional requirements specified in 23 05 93 - Appendix C:  DALT AND TAB SUBMITTAL AND WORK SCHEDULE 
included at the end of this section</TXT><BRK/>
<BRK/></SPT>
</TAI>[<SPT><TTL>1.7.2   Projects with Phased Construction</TTL><BRK/>
<NTE><AST/><BRK/>
<NPR>NOTE: Ensure all aspects of the HVAC work, including DALT work and TAB work, 
are incorporated in the contract's construction phases and fully covered in 
the contract documents.  Revise this paragraph accordingly based on your specific 
project.</NPR><BRK/>
<AST/></NTE><BRK/>
<TXT>This specification section is structured as though the HVAC construction, and thereby the TAB work, will be completed 
in a single phase.  When the construction is completed in phases, the DALT work and TAB work must be planned, 
completed, and accepted for each construction phase.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.7.2.1   Phasing of Work</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: In the following paragraph, DALT work is specified.  If DALT work is not 
required for a given project, delete references to DALT throughout.  This is 
facilitated by brackets locating these references to DALT work.  </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>This specification section is structured as though the HVAC construction, and thereby the TAB work, is going 
to be completed in a single phase[ in spite of the fact that there will be two seasons].  All elements of the 
TAB work are addressed on this premise.  When a contract is to be completed in construction phases, including 
the TAB work, and the DALT work, the TAB work and DALT work must be planned for, completed and approved by the 
Contracting Officer with each phase.  An example of this case would be one contract that requires the rehabilitation 
of the HVAC in each of several separated buildings.  At the completion of the final phase, compile  all approved 
reports and submit as one document.</TXT><BRK/>
<BRK/></SPT>
</SPT>]<TAI OPT="NASA,USACE"><SPT><TTL>1.7.3   <SUB>DALT and TAB Submittal and Work Schedule</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The calendar day requirements specified should apply to many construction 
projects.  However, the specifier, when preparing this paragraph for a specific 
contract, must review and modify this paragraph to suit the contract construction 
schedule.  Season 1 may be the season of maximum heating load or maximum cooling 
load, depending upon construction schedule.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Submit this schedule,and TAB Schematic Drawings, adapted for this particular contract, to the Contracting Officer 
(CO) for review and approval.  Include with the submittal the planned calendar dates for each submittal or work 
item.  Resubmit an updated version for CO approval every 90 calendar days days. Compliance with the following 
schedule is the Contractor's responsibility.</TXT><BRK/>
<BRK/>
<ITM>Qualify TAB Personnel:  Within [45] [_____] calendar days after date of contract award, submit 
TAB agency and personnel qualifications.</ITM><BRK/>
<BRK/>
<ITM>Pre-DALT/TAB Meeting:  Within [30] [_____] calendar days after the date of approval of the TAB 
agency and personnel, meet with the Contracting Officer's TAB representative.</ITM><BRK/>
<BRK/>
<ITM>Design Review Report:  Within [60] [_____] calendar days after the date of the TAB agency personnel 
qualifications approval, submit design review report.</ITM><BRK/>
<BRK/>
<ITM>Pre-Field DALT Preliminary Notification:  On completion of the duct installation for each system, 
notify the Contracting Officer in writing within 5 days after completion.<BRK/>
<BRK/>
Ductwork Selected for DALT:  Within 7 calendar days of Pre-Field DALT Preliminary Notification, 
the Contracting Officer's TAB representative (COTR) will select which of the project ductwork 
must be DALT'd.<BRK/>
<BRK/>
DALT Field Work:  Within 48 hours of COTR's selection, complete DALT field work on selected.<BRK/>
<BRK/>
Submit <SUB>Pre-final DALT Report</SUB>:  Within one working day after completion of DALT field work, submit 
Pre-final DALT Report. Separate Pre-final DALT reports may be submitted to allow phased testing 
from system to system.<BRK/>
<BRK/>
DALT Work Field Check:  Upon approval of the Pre-final DALT Report, schedule the COTR's DALT 
field check work with the Contracting Officer.<BRK/>
<BRK/>
Submit <SUB>Final DALT Report</SUB>:  Within [15] [_____] calendar days after completion of successful 
DALT Work Field Check, submit [Season 1] TAB report.</ITM><BRK/>
<BRK/>
<ITM>Pre-Field TAB Engineering Report:  Within [_____] calendar days after approval of the TAB agency 
Personnel Qualifications, submit the Pre-Field TAB Engineering Report.</ITM><BRK/>
<BRK/>
<ITM><SUB>Prerequisite HVAC Work Check Out List [For Season 1]</SUB> and <SUB>Advanced Notice For [Season 1] TAB 
Field Work</SUB>:  At a minimum of [115] [_____] calendar days prior to CCD, submit [Season 1] prerequisite 
HVAC work check out list certified as complete, and submit advance notice of commencement of 
[Season 1] TAB field work.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Option 1:  Normally, use the following four paragraphs, which requires 
two separate trips within Season 1 to the contract site by the TAB field team 
(the first for the TAB field work, the second for the TAB quality assurance 
work) with the TAB report submitted between trips.  This is intended to give 
the design engineer time to review the TAB report before the field check of 
that report is conducted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[[Season 1] TAB Field Work:  At a minimum of [90] [_____] calendar days prior to CCD, [and when 
the ambient temperature is within Season 1 limits,] accomplish [Season 1] TAB field work.<BRK/>
<BRK/>
Submit [Season 1] TAB Report:  Within [15] [_____] calendar days after completion of [Season 
1] TAB field work, submit [Season 1] TAB report.<BRK/>
<BRK/>
[Season 1] TAB Field Check:  [30] [_____] calendar days after Season 1 TAB report is approved 
by the Contracting Officer, conduct [Season 1] field check.<BRK/>
<BRK/>
Complete [Season 1] TAB Work:  Prior to CCD, complete all TAB work [except Season 2 TAB work].]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Option 2:  Use the following two paragraphs when the contract site is 
remote or the HVAC system is simple, and the specifier wants to reduce to one 
the number of trips to the contract site by the TAB field team within Season 
1 (TAB field work and TAB quality assurance accomplished in same trip).  Renumber 
remaining paragraphs appropriately.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[[Season 1] TAB Field Work:  At a minimum of [90] [___] calendar days prior to CCD, [and when 
the ambient temperature is within Season 1 limits,] accomplish [Season 1] TAB field work; submit 
[Season 1] TAB report; and conduct [Season 1] field check.<BRK/>
<BRK/>
Complete [Season 1] TAB Work:  Prior to CCD, complete all TAB work [except Season 2 TAB work].]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include the remaining submittals and items of work only if there is a 
season 2 TAB Work </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[<SUB>Prerequisite HVAC Work Check Out List For Season 2</SUB> and <SUB>Advanced Notice For Season 2 TAB Field 
Work</SUB>:  Within [150] [_____] calendar days after date of the commencement of the Season 1 TAB 
field work, submit the Season 2 prerequisite HVAC work check out list certified as complete 
and submit advance notice of commencement of Season 2 TAB field work.]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Option 1:  Normally, use the following four paragraphs, which requires 
two separate trips within Season 2 to the contract site by the TAB field team 
(the first for the TAB field work, the second for the TAB quality assurance 
work) with the TAB report submitted between trips.  This is intended to give 
the design engineer time to review the TAB report before the field check of 
that report is conducted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[Season 2 TAB Field Work:  Within [180] [_____] calendar days after date of commencement of 
the Season 1 TAB field work and when the ambient temperature is within Season 2 limits, accomplish 
Season 2 TAB field work.<BRK/>
<BRK/>
Submit Season 2 TAB Report:  Within [15] [_____] calendar days after completion of Season 2 
TAB field work, submit Season 2 TAB report.<BRK/>
<BRK/>
Season 2 TAB Field Check:  [30] [_____] calendar days after the Season 2 TAB report is approved 
by the Contracting Officer, conduct Season 2 field check.<BRK/>
<BRK/>
Complete Season 2 TAB Work:  Within [15] [_____] calendar days after the completion of Season 
2 TAB field data check, complete all TAB work.]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Option 2:  Use the following two paragraphs when the contract site is 
remote, or the HVAC system is simple, and the specifier wants to reduce to one 
the number of trips to the contract site by the TAB field team within Season 
2 (TAB field work and TAB quality assurance accomplished in same trip).  Renumber 
remaining paragraphs appropriately.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[Season 2 TAB Field Work:  Within [180] [_____] calendar days after date of commencement of 
the Season 1 TAB field work and when the ambient temperature is within Season 2 limits, accomplish 
[Season 2] TAB field work; submit [Season 2] TAB report; and conduct Season 2 field check.<BRK/>
<BRK/>
Complete Season 2 TAB Work:  Within [15] [_____] calendar days after the completion of Season 
2 field data check, complete TAB work.]</ITM><BRK/>
<BRK/>
<SPT><TTL>1.7.3.1   <SUB>Design Review Report</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit typed report describing omissions and deficiencies in the HVAC system's design that would preclude the 
TAB team from accomplishing the duct leakage testing work and the TAB work requirements of this section.  Provide 
a complete explanation including supporting documentation detailing the design deficiency.  State that no deficiencies 
are evident if that is the case.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.3.2   <SUB>Pre-Field DALT Preliminary Notification</SUB></TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Notification:  On completion of the installation of each duct system indicated to be DALT'd, 
notify the Contracting Officer in writing within 7 calendar days after completion.</ITM><BRK/>
 <BRK/></SPT>
<SPT><TTL>1.7.3.3   <SUB>Pre-Field TAB Engineering Report</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit report containing the following information:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Step-by-step TAB procedure:</ITM><BRK/>
<BRK/>
<ITM>(1) Strategy:  Describe the method of approach to the TAB field work from start to finish.  
Include in this description a complete methodology for accomplishing each seasonal TAB field 
work session.</ITM><BRK/>
<BRK/>
<ITM>(2) Air System Diagrams: Use the contract drawings and duct fabrication drawings if available 
to provide air system diagrams in the report showing the location of all terminal outlet supply, 
return, exhaust and transfer registers, grilles and diffusers. Use a key numbering system on 
the diagrams which identifies each outlet contained in the outlet airflow report sheets.  Show 
intended locations of all traverses and static pressure readings. </ITM><BRK/>
<BRK/>
<ITM>(3) Procedural steps:  Delineate fully the intended procedural steps to be taken by the TAB 
field team to accomplish the required TAB work of each air distribution system and each water 
distribution system.  Include intended procedural steps for TAB work for subsystems and system 
components.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Pre-field data:  Submit AABC or NEBB or <RID>SMACNA 1780</RID> data report forms with the following 
pre-field information filled in:</ITM><BRK/>
<BRK/>
<ITM>(1)  Design data obtained from system drawings, specifications, and approved submittals.</ITM><BRK/>
<BRK/>
<ITM>(2)  Notations detailing additional data to be obtained from the contract site by the TAB field 
team.</ITM><BRK/>
<BRK/>
<ITM>(3)  Designate the actual data to be measured in the TAB field work.</ITM><BRK/>
<BRK/>
<ITM>(4)  Provide a list of the types of instruments, and the measuring range of each, which are 
anticipated to be used for measuring in the TAB field work.  By means of a keying scheme, specify 
on each TAB data report form submitted, which instruments will be used for measuring each item 
of TAB data.  If the selection of which instrument to use, is to be made in the field, specify 
from which instruments the choice will be made.  Place the instrument key number in the blank 
space where the measured data would be entered.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Prerequisite HVAC work checkout list:  Provide a list of inspections and work items which 
are to be completed by the Contractor.  This list must be acted upon and completed by the Contractor 
and then submitted and approved by the Contracting Officer prior to the TAB team coming to the 
contract site. <BRK/>
<BRK/>
At a minimum, a list of the applicable inspections and work items listed in the <RID>NEBB PROCEDURAL STANDARDS</RID>
, Section III, "Preliminary TAB Procedures" under paragraphs titled, "Air Distribution System 
Inspection" and "Hydronic Distribution System Inspection" must be provided for each separate 
system to be TAB'd.</ITM><BRK/>
<BRK/></SPT>
</SPT></TAI></SPT><TAI OPT="NAVFAC"><SPT><TTL>1.8   SUBCONTRACTOR SPECIAL REQUIREMENTS</TTL><BRK/>
<BRK/>
<TXT>[Perform all work in this section in accordance with the paragraph entitled "Subcontractor Special Requirements" 
in Section <SRF>01 30 00</SRF> ADMINISTRATIVE REQUIREMENTS, stating that all contract requirements of this section must 
be accomplished directly by a first tier subcontractor.  No work may be performed by a second tier subcontractor.]</TXT><BRK/>
<BRK/></SPT>
</TAI><TAI OPT="NASA,USACE"><SPT><TTL>1.9   WARRANTY</TTL><BRK/>
<BRK/>
<TXT>Furnish workmanship and performance warranty for the [DALT and ] TAB system work performed for a period not less 
than [1] [2] [3] [5] [_____] years from the date of Government acceptance of the work; issued directly to the 
Government.  Include provisions that if within the warranty period the system shows evidence of major performance 
deterioration, or is significantly out of tolerance, resulting from defective TAB or DALT workmanship, the corrective 
repair or replacement of the defective materials and correction of the defective workmanship is the responsibility 
of the TAB firm.  Perform corrective action that becomes necessary because of defective materials and workmanship 
while system TAB and DALT is under warranty 7 days after notification, unless additional time is approved by 
the Contracting Officer.  Failure to perform repairs within the specified period of time constitutes grounds 
for having the corrective action and repairs performed by others and the cost billed to the TAB firm.  The Contractor 
must also provide a [1] [2] [3] [5] [_____] year contractor installation warranty.</TXT><BRK/>
<BRK/></SPT>
</TAI></PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<TXT>Not Used</TXT><BRK/>
<BRK/></PRT>
<PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   WORK DESCRIPTIONS OF PARTICIPANTS</TTL><BRK/>
<BRK/>
<TXT>Comply with requirements of this section<TAI OPT="NAVFAC"> as specified in 23 05 93 - Appendix A  WORK DESCRIPTIONS OF PARTICIPANTS</TAI>
.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2   PRE-DALT/TAB MEETING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Inclusion of this meeting requirement in the specification is based on 
the complexity of the HVAC systems and the location of the contract site.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Meet with the Contracting Officer's technical representative (COTR)[and the designing engineer of the HVAC systems] 
to develop a mutual understanding relative to the details of the DALT work and TAB work requirements.  Ensure 
that the TAB supervisor is present at this meeting.  Requirements to be discussed include required submittals, 
work schedule, and field quality control.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3   DALT PROCEDURES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:<TAI OPT="NASA,USACE">  It is the designer's decision/responsibility to decide whether, or not, 
to require duct air leak testing in accordance with this section.  Subjecting 
duct systems to acceptance testing likely results in higher quality ductwork.  
Only very simple duct systems, such as low velocity ductwork within a single 
room, do not justify DALT testing.</TAI>  Indicate on the drawings a duct construction 
schedule that defines the DALT test requirements, including each applicable 
HVAC duct system ID or mark, duct pressure class, duct seal class, and duct 
leakage test pressure.  Refer to SMACNA Leakage Test Mnl, Appendix B, "Sample 
Leakage Analysis" for guidance in determining leakage test pressures.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.3.1   Instruments, Consumables and Personnel</TTL>  <BRK/>
<BRK/>
<TXT>Provide instruments, consumables and personnel required to accomplish the DALT field work.  Follow the same basic 
procedure specified below for TAB Field Work, including maintenance and calibration of instruments, accuracy 
of measurements, preliminary procedures, field work, workmanship and treatment of deficiencies.  Calibrate and 
maintain instruments in accordance with manufacturer's written procedures.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.2   <SUB>Advance Notice of Pre-Final DALT Field Work</SUB></TTL><BRK/>
<BRK/>
<TXT>On completion of the installation of each duct system indicated to be DALT'd, notify the Contracting Officer 
in writing prior to the COTR's duct selection field visit.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.3   Ductwork To Be DALT'd</TTL><BRK/>
<BRK/>
<TXT>From each duct system indicated as subject to DALT, the COTR will randomly select sections of each completed 
duct system for testing by the Contractor's TAB Firm.  The sections selected will not exceed 20 percent of the 
total measured linear footage of duct systems indicated as subject to DALT.  Sections of duct systems subject 
to DALT will include 20 percent of main ducts, branch main ducts, branch ducts and plenums for supply, return, 
exhaust, and plenum ductwork.</TXT><BRK/>
<BRK/>
[<TXT>It is acceptable for an entire duct system to be DALT'd instead of disassembling that system in order to DALT 
only the 20 percent portion specified above.</TXT>]<BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.4   DALT Testing</TTL><BRK/>
<BRK/>
<TXT>Perform DALT on the HVAC duct sections of each system as selected by the COTR.  Use the duct class, seal class, 
leakage class and the leak test pressure data indicated on the drawings, to comply with the procedures specified 
in <RID>SMACNA 1143</RID>.<BRK/>
<BRK/>
In spite of specifications of <RID>SMACNA 1143</RID> to the contrary, DALT ductwork of construction class of<MET> 746 Pa</MET><ENG> 3-inch</ENG>
 water gauge static pressure and below if indicated to be DALT'd.  Complete DALT work on the COTR selected ductwork 
within 48 hours after the particular ductwork was selected for DALT.  Separately conduct DALT work for large 
duct systems to enable the DALT work to be completed in 48 hours.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.5   <SUB>Pre-final DALT Report</SUB></TTL><BRK/>
<BRK/>
<TAI OPT="NAVFAC"><TXT>After completion of the DALT work, prepare a Pre-final DALT Report meeting the additional requirements specified 
in UFGS-23 05 93 - Appendix B  REPORTS - DALT and TAB.  Data required by those data report forms shall be furnished 
by the TAB team.  Prepare the report neatly and legibly; the Pre-final DALT report shall provide the basis for 
the Final DALT Report. <BRK/>
<BRK/>
TAB supervisor shall review, approve and sign the Pre-Final DALT Report and submit this report within one day 
of completion of DALT field work.  Verbally notify the Contracting Officer's TAB representative that the field 
check of the Pre-Final DALT Report data can commence.</TXT></TAI><BRK/>
<TAI OPT="NASA,USACE"><BRK/>
<TXT>After completion of the DALT work, prepare a Pre-final DALT Report using the reporting forms specified.  TAB 
team to furnish data required by those data report forms .  Prepare the report neatly and legibly; the Pre-final 
DALT report is the basis for the Final DALT Report.  TAB supervisor must review and certify the Pre-final DALT 
Report and submit this report within one day of completion of DALT field work.  Verbally notify the Contracting 
Officer's TAB representative that the field check of the Pre-final DALT Report data can commence.</TXT></TAI><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.6   Quality Assurance - COTR DALT Field Acceptance Testing</TTL><BRK/>
<BRK/>
<TXT>In the presence of the COTR and TAB team field leader, verify for accuracy Pre-final DALT Report data selected 
by the COTR.   For each duct system, this acceptance testing shall be conducted on  a maximum of 50 percent of 
the duct sections DALT'd..<BRK/>
<BRK/>
Further, if any data on the Pre-final DALT report form for a given duct section is out-of-tolerance, then field 
acceptance testing shall be conducted on data for one additional duct section, preferably in the same duct system, 
in the presence of the COTR.<BRK/></TXT>
<BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.7   Additional COTR Field Acceptance Testing</TTL><BRK/>
<BRK/>
<TXT>If any of the duct sections checked for a given system are determined to have a leakage rate measured that exceeds 
the leakage rate allowed by SMACNA Leak Test Manual for an indicated duct construction class and sealant class, 
terminate data checking for that section.  The associated Pre-final DALT Report data for the given duct system 
will be disapproved.  Make the necessary corrections and prepare a revised Pre-final DALT Report.  Reschedule 
a field check of the revised report data with the Contracting Officer's TAB representative.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.8   Certified <SUB>Final DALT Report</SUB></TTL><BRK/>
<TAI OPT="NASA,USACE"><BRK/>
<TXT>On successful completion of all field checks of the Pre-final DALT Report data for all systems, the TAB Supervisor 
is to assemble, review, certify and submit the Final DALT Report to the Contracting Officer for approval.</TXT></TAI><BRK/>
<TAI OPT="NAVFAC"><BRK/>
<TXT>On successful completion of all field checks of the Pre-Final DALT Report data for all systems, the TAB Supervisor 
shall assemble, review, approve, sign and submit the Final DALT Report in compliance with 23 05 93 - Appendix 
B  REPORTS - DALT and TAB to the Contracting Officer for approval.</TXT></TAI><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.9   Prerequisite for TAB Field Work</TTL><BRK/>
<BRK/>
<TXT>Do not commence TAB field work prior to the completion and approval, for all systems, of the Final DALT Report.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.4   TAB PROCEDURES</TTL><BRK/>
<BRK/>
<SPT><TTL>3.4.1   TAB Field Work</TTL><BRK/>
<BRK/>
<TST><TXT>Test, adjust, and balance the listed HVAC systems to the state of operation indicated on and specified in the 
contract design documents.  That is, comply with the the requirements of <RID>AABC MN-1</RID> <TAI OPT="NASA">[and <RID>AABC MN-4</RID></TAI><TAI OPT="NASA">]</TAI>,<TAI OPT="NASA">[ <RID>NEBB PROCEDURAL STANDARDS</RID>
, <RID>NEBB MASV</RID>,]</TAI> or <RID>SMACNA 1780</RID> (TABB) and <RID>SMACNA 1858</RID> (TABB),except as supplemented and modified by this section.[  
Provide instruments and consumables required to accomplish the TAB work.  Calibrate and maintain instruments 
in accordance with manufacturer's written procedures.]</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For those projects having only a single season TAB report, delete the 
last sentence of the following paragraph.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Test, adjust, and balance the listed HVAC systems to the state of operation indicated on and specified in the 
contract design documents. Conduct TAB work, including measurement accuracy, and sound measurement work in conformance 
with the AABC MN-1 and AABC MN-4, or NEBB TABES and NEBB MASV, or SMACNA 1780 (used by TABB) and  SMACNA 1858 
sound measurement procedures, except as supplemented and modified by this section.[  The only water flow and 
air flow reporting which can be deferred until the Season 2 is that data which would be affected in terms of 
accuracy due to outside ambient conditions.]</TXT></TST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2   Preliminary Procedures</TTL><BRK/>
<BRK/>
<TXT>Use the approved pre-field engineering report as instructions and procedures for accomplishing TAB field work.  
TAB engineer is to locate, in the field, test ports required for testing.  It is the responsibility of the sheet 
metal contractor to provide and install test ports as required by the TAB engineer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.3   TAB Air Distribution Systems</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit, delete, and add to the paragraphs below to ensure that air distribution 
systems indicated on project drawings are listed for TAB work.  Explicitly identify 
new and existing systems and components which are to be TAB'd.  Exercise particular 
care in defining existing systems and components.  Specify the systems identically 
to labeling and terminology used on project drawings.  Delete the subparts which 
do not apply to your project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.4.3.1   Units With Coils</TTL><BRK/>
<BRK/>
<TXT>Report heating and cooling performance capacity tests for hot water, chilled water, DX and steam coils for the 
purpose of verifying that the coils meet the indicated design capacity.  Submit the following data and calculations 
with the coil test reports:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  For air handlers with capacities greater than<MET> 26,370 Watts</MET><ENG> 7.5 tons (90,000 Btu)</ENG> cooling, 
such as factory manufactured units, central built-up units and rooftop units, conduct capacity 
tests in accordance with <RID>AABC MN-4</RID>, procedure 3.5, "Coil Capacity Testing."<BRK/>
<BRK/>
Do not determine entering and leaving wet and dry bulb temperatures by single point measurement, 
but by the average of multiple readings in compliance with paragraph 3.5-5, "Procedures", (in 
subparagraph d.) of <RID>AABC MN-4</RID>, Procedure 3.5, "Coil Capacity Testing."<BRK/>
<BRK/>
Submit part-load coil performance data from the coil manufacturer converting test conditions 
to design conditions; use the data  for the purpose of verifying that the coils meet the indicated 
design capacity in compliance with <RID>AABC MN-4</RID>, Procedure 3.5, "Coil Capacity Testing," paragraph 
3.5.7, "Actual Capacity Vs. Design Capacity" (in subparagraph c.).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  For units with capacities of<MET> 26370 Watts</MET><ENG> 7.5 tons (90,000 Btu)</ENG> or less, such as fan coil 
units, duct mounted reheat coils associated with VAV terminal units, and unitary units, such 
as through-the-wall heat pumps:<BRK/>
<BRK/>
Determine the apparent coil capacity by calculations using single point measurement of entering 
and leaving wet and dry bulb temperatures; submit the calculations with the coil reports.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.3.2   Air Handling Units</TTL><BRK/>
<BRK/>
<TXT>Air handling unit systems including fans (air handling unit fans, exhaust fans and winter ventilation fans), 
coils, ducts, plenums, mixing boxes, terminal units, variable air volume boxes, and air distribution devices 
for supply air, return air, outside air, mixed air relief air, and makeup air.</TXT><BRK/>
<BRK/></SPT>
[<SPT><TTL>3.4.3.3   Rooftop Air Conditioning</TTL><BRK/>
<BRK/>
<TXT>Rooftop air conditioning systems including fans, coils, ducts, plenums, and air distribution devices for supply 
air, return air, and outside air.</TXT><BRK/>
<BRK/>
<TXT>For refrigeration compressors/condensers/condensing units/evaporators, report data as required by NEBB, AABC, 
and TABB standard procedures, including refrigeration operational data.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.3.4   Heating and Ventilating Units</TTL><BRK/>
<BRK/>
<TXT>Heating and ventilating unit systems including fans, coils, ducts, plenums, roof vents, registers, diffusers, 
grilles, and louvers for supply air, return air, outside air, and mixed air.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.3.5   Makeup Air Units</TTL><BRK/>
<BRK/>
<TXT>Makeup air unit systems including fans, coils, ducts, plenums, registers, diffusers, grilles, and louvers for 
supply air, return air, outside air, and mixed air.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.3.6   Return Air Fans</TTL><BRK/>
<BRK/>
<TXT>Return air fan system including fan ducts, plenums, registers, diffusers, grilles, and louvers for supply air, 
return air, outside air, and mixed air.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.3.7   Fan Coils</TTL><BRK/>
<BRK/>
<TXT>Fan coil unit systems including fans, coils, ducts, plenums, and air distribution devices for supply air, return 
air, and outside air.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.3.8   Exhaust Fans</TTL><BRK/>
<BRK/>
<TXT>Exhaust fan systems including fans, ducts, plenums, grilles, and hoods for exhaust air.</TXT><BRK/>
<BRK/></SPT>
]<TAI OPT="NASA,USACE">[<SPT><TTL>3.4.3.9   Cabinet Heaters</TTL><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.3.10   Cooling Units</TTL><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.3.11   Door Heaters</TTL><BRK/>
<BRK/>
<TXT>Door heater systems, including fans, coils, and diffusers.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.3.12   Unit Heaters</TTL><BRK/>
<BRK/></SPT>
]</TAI></SPT>[<SPT><TTL>3.4.4   TAB Water Distribution Systems</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit, delete, and add to the paragraphs below to ensure that water distribution 
systems indicated on project drawings are listed for TAB work.  Explicitly identify 
new and existing systems and components which are to be TAB'd.  Exercise particular 
care in defining existing systems and components.  Specify the systems identically 
to labeling and terminology used on project drawings.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.4.4.1   Chilled Water</TTL><BRK/>
<BRK/>
<TXT>Chilled water systems including chillers, condensers, cooling towers, pumps, coils, system balance valves and 
flow measuring devices.</TXT><BRK/>
<BRK/>
<TXT>For water chillers, report data as required by AABC, NEBB and TABB standard procedures, including refrigeration 
operational data.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.4.2   Heating Hot Water</TTL><BRK/>
<BRK/>
<TXT>Heating hot water systems including boilers, hot water converters (e.g., heat exchangers), pumps, coils, system 
balancing valves and flow measuring devices.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.4.3   Dual Temperature Water</TTL><BRK/>
<BRK/>
<TXT>Dual temperature water systems including boilers, converters, chillers, condensers, cooling towers, pumps, coils, 
and system balancing valves, and flow measuring devices.</TXT><BRK/>
<BRK/></SPT>
</SPT>][<SPT><TTL>3.4.5   Sound Measurement Work</TTL><BRK/>
<BRK/>
<SPT><TTL>3.4.5.1   Areas To Be Sound Measured</TTL><BRK/>
<BRK/>
<TXT>In the following spaces, measure and record the sound power level for each octave band listed in<MET> <RID>ASHRAE HVAC APP SI HDBK</RID></MET>
 Noise Criteria:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  All HVAC mechanical rooms, including machinery spaces and other spaces containing HVAC power 
drivers and power driven equipment.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  All spaces sharing a common barrier with each mechanical room, including rooms overhead, 
rooms on the other side of side walls, and rooms beneath the mechanical room floor.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select representative non-mechanical rooms which are occupied by any 
personnel and are served by each type of primary HVAC air moving system and 
HVAC water moving systems.  Include rooms served by like primary systems which 
have significantly different sound affecting configurations.  List, in the subparagraphs 
below, the rooms to be sound measured that will accomplish the aforementioned 
sound assessment philosophy.  List the rooms by terminology identical to labeling 
indicated on drawings.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM INDENT="-0.33">[c.  AHU No. 1 System:  Rooms: [_____]]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[d.  [_____] System:  Rooms: [_____]]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[e.  [_____] System:  Rooms:  [_____]]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.5.2   Procedure</TTL><BRK/>
<BRK/>
<TXT>Measure sound levels in each room, when unoccupied except for the TAB team, with all HVAC systems that would 
cause sound readings in the room operating in their noisiest mode.  Record the sound level in each octave band.  
Attempt to mitigate the sound level and bring the level to within the specified<MET> <RID>ASHRAE HVAC APP SI HDBK</RID></MET><ENG> <RID>ASHRAE HVAC APP IP HDBK</RID></ENG>
 noise criteria goals, if such mitigation is within the TAB team's control.  State in the report the<MET> <RID>ASHRAE HVAC APP SI HDBK</RID></MET><ENG>
 <RID>ASHRAE HVAC APP IP HDBK</RID></ENG> noise criteria goals.  If sound level cannot be brought into compliance, provide written 
notice of the deficiency to the Contractor for resolution or correction.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.5.3   Timing</TTL><BRK/>
<BRK/>
<TXT>Measure sound levels at times prescribed by AABC or NEBB or TABB.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.5.4   Meters</TTL><BRK/>
<BRK/>
<TXT>Measure sound levels with a sound meter complying with <RID>ASA S1.4</RID>, Type 1 or 2, and an octave band filter set complying 
with <RID>ASA S1.11</RID>.  Use measurement methods for overall sound levels and for octave band sound levels as prescribed 
by NEBB.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.5.5   Calibration</TTL><BRK/>
<BRK/>
<TXT>Calibrate sound levels as prescribed by AABC or NEBB or TABB, except that calibrators emitting a sound pressure 
level tone of 94 dB at 1000 hertz (Hz) are also acceptable.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.5.6   Background Noise Correction</TTL><BRK/>
<BRK/>
<TXT>Determine background noise component of room sound (noise) levels for each (of eight) octave bands as prescribed 
by AABC or NEBB or TABB.</TXT><BRK/>
<BRK/></SPT>
</SPT>][<SPT><TTL>3.4.6   TAB Work on Performance Tests Without Seasonal Limitations</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options:  TAB without Seasonal Limitations, 
or TAB with Seasonal Limitations..</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose the text immediately below or the text below entitled "TAB Work 
On Performance Tests Within Seasonal Limitations."  Use the text immediately 
below in the case where the winter outdoor design dry bulb temperature and the 
summer outdoor design dry bulb temperature are within<MET> 19.4 degrees C</MET><ENG> 35 degrees 
F</ENG> of each other.  This will reduce the number of trips to the contract site 
from two (one per season) to one for performance testing by the TAB field team.  
Use the second option, in the other cases.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.4.6.1   Performance Tests</TTL><BRK/>
<BRK/>
<TXT>In addition to the TAB proportionate balancing work on the air distribution systems and the water distribution 
systems, accomplish TAB work on the HVAC systems which directly transfer thermal energy.  TAB the operational 
performance of the [heating systems] [and] [cooling systems].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.6.2   Ambient Temperatures</TTL><BRK/>
<BRK/>
<TXT>On each tab report form used for recording data, record the outdoor and indoor ambient dry bulb temperature range 
and the outdoor and indoor ambient wet bulb temperature range within which the report form's data was recorded.  
Record these temperatures at beginning and at the end of data taking.</TXT><BRK/>
<BRK/></SPT>
[<SPT><TTL>3.4.6.3   Sound Measurements</TTL><BRK/>
<BRK/>
<TXT>Comply with paragraph entitled "Sound Measurement Work," specifically, the requirement that a room must be operating 
in its noisiest mode at the time of sound measurements in the room.  The maximum noise level measurements could 
depend on seasonally related heat or cooling transfer equipment.</TXT><BRK/>
<BRK/></SPT>
]<TAI OPT="NASA,USACE">[<SPT><TTL>3.4.6.4   Water Chillers</TTL><BRK/>
<BRK/>
<TXT>For water chillers, report data as required by NEBB Form TAB 15-83, <RID>NEBB PROCEDURAL STANDARDS</RID>, including refrigeration 
operational data.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.6.5   Refrigeration Units</TTL><BRK/>
<BRK/>
<TXT>For refrigeration compressors/condensers/condensing units, report data as required by NEBB Form TAB 15-83, <RID>NEBB PROCEDURAL STANDARDS</RID>
, including refrigeration operational data.</TXT><BRK/>
<BRK/></SPT>
]<SPT><TTL>3.4.6.6   Coils</TTL><BRK/>
<BRK/>
<TXT>Report heating and cooling performance capacity tests for [hot water], [chilled water], [DX] [and steam coils] 
for the purpose of verifying that the coils meet the indicated design capacity.  Submit the following data and 
calculations with the coil test reports:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">[a.  For Central station air handlers with capacities greater than<MET> 26,370 Watts</MET><ENG> 7.5 tons (90,000 
Btu)</ENG> cooling, such as factory manufactured units, central built-up units and rooftop units, 
conduct capacity tests in accordance with <RID>AABC MN-4</RID>, procedure 3.5, "Coil Capacity Testing".<BRK/>
<BRK/>
Entering and leaving wet and dry bulb temperatures are not determined by single point measurement, 
but the average of multiple readings in compliance with paragraph 3.5-5, "Procedures", (in subparagraph 
d.) of <RID>AABC MN-4</RID>, Procedure 3.5, "Coil Capacity Testing."<BRK/>
<BRK/>
Submit part-load coil performance data from the coil manufacturer converting test conditions 
to design conditions; use the data for the purpose of verifying that the coils meet the indicated 
design capacity in compliance with <RID>AABC MN-4</RID>, Procedure 3.5, "Coil Capacity Testing," paragraph 
3.5.7, "Actual Capacity Vs. Design Capacity" (in subparagraph c.).]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[b.  For units with capacities of<MET> 26370 Watts</MET><ENG> 7.5 tons (90,000 Btu)</ENG> or less, such as fan coil 
units, duct mounted reheat coils associated with VAV terminal units, and unitary units, such 
as through-the-wall heat pumps:<BRK/>
<BRK/>
Determine the apparent coil capacity by calculations using single point measurement of entering 
and leaving wet and dry bulb temperatures; submit the calculations with the coil reports.]</ITM><BRK/>
<BRK/></SPT>
</TAI></SPT><TAI OPT="NASA,USACE">]</TAI>[<SPT><TTL>3.4.7   TAB Work on Performance Tests With Seasonal Limitations</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose the text immediately below, or the text above entitled "TAB Work 
On Performance Tests Without Seasonal Limitations."  Refer to technical note 
immediately above.  The text immediately below requires one trip each for Seasons 
1 and 2.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.4.7.1   Performance Tests</TTL><BRK/>
<BRK/>
<TXT>Accomplish proportionate balancing TAB work on the air distribution systems and water distribution systems, in 
other words, accomplish adjusting and balancing of the air flows and water flows, any time during the duration 
of this contract, subject to the limitations specified elsewhere in this section.  However, accomplish, within 
the following seasonal limitations, TAB work on HVAC systems which directly transfer thermal energy.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.7.2   Season Of Maximum Load</TTL><BRK/>
<BRK/>
<TXT>Visit the contract site for at least two TAB work sessions for TAB field measurements.  [Visit the contract site 
during the season of maximum heating load] [and] [visit the contract site during the season of maximum cooling 
load], the goal being to TAB the operational performance of the [heating systems] [and] [cooling systems] under 
their respective maximum outdoor environment-caused loading.  During the seasonal limitations, TAB the operational 
performance of the [heating systems] [and] [cooling systems].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.7.3   Ambient Temperatures</TTL><BRK/>
<BRK/>
<TXT>On each tab report form used for recording data, record the outdoor and indoor ambient dry bulb temperature range 
and the outdoor and indoor ambient wet bulb temperature range within which the report form's data was recorded.  
Record these temperatures at beginning and at the end of data taking.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.7.4   Sound Measurements</TTL><BRK/>
<BRK/>
<TXT>Comply with paragraph entitled "Sound Measurement Work," specifically, the requirement that a room must be operating 
in its noisiest mode at the time of sound measurements in the room.  The maximum noise level measurements could 
depend on seasonally related heat or cooling transfer equipment.</TXT><BRK/>
<BRK/></SPT>
<TAI OPT="NASA,USACE">[<SPT><TTL>3.4.7.5   Water Chillers</TTL><BRK/>
<BRK/>
<TXT>Water chillers:  For water chillers,report data as required by NEBB Form TAB 15-83, <RID>NEBB PROCEDURAL STANDARDS</RID>
, including refrigeration operational data.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.7.6   Refrigeration Units</TTL><BRK/>
<BRK/>
<TXT>For refrigeration compressors/condensers/condensing units,report data as required by NEBB Form TAB 15-83, <RID>NEBB PROCEDURAL STANDARDS</RID>
, including refrigeration operational data.</TXT><BRK/>
<BRK/></SPT>
][<SPT><TTL>3.4.7.7   Coils</TTL><BRK/>
<BRK/>
<TXT>Report heating and cooling performance capacity tests for [hot water], [chilled water], [DX] [and steam coils] 
for the purpose of verifying that the coils meet the indicated design capacity.  Submit the following data and 
calculations with the coil test reports:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  For Central station air handlers with capacities greater than<MET> 26,370 Watts</MET><ENG> 7.5 tons (90,000 
Btu)</ENG> cooling, such as factory manufactured units, central built-up units and rooftop units, 
conduct capacity tests in accordance with <RID>AABC MN-4</RID>, procedure 3.5, "Coil Capacity Testing."<BRK/>
<BRK/>
Entering and leaving wet and dry bulb temperatures are not determined by single point measurement, 
but by the average of multiple readings in compliance with paragraph 3.5-5, "Procedures", (in 
subparagraph d.) of <RID>AABC MN-4</RID>, Procedure 3.5, "Coil Capacity Testing."<BRK/>
<BRK/>
Submit part-load coil performance data from the coil manufacturer converting test conditions 
to design conditions; use the data for the purpose of verifying that the coils meet the indicated 
design capacity in compliance with <RID>AABC MN-4</RID>, Procedure 3.5, "Coil Capacity Testing," paragraph 
3.5.7, "Actual Capacity Vs. Design Capacity" (in subparagraph c.).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  For units with capacities of<MET> 26370 Watts</MET><ENG> 7.5 tons (90,000 Btu)</ENG> or less, such as fan coil 
units, duct mounted reheat coils associated with VAV terminal units, and unitary units, such 
as through-the-wall heat pumps:<BRK/>
<BRK/>
Determine the apparent coil capacity by calculations using single point measurement of entering 
and leaving wet and dry bulb temperatures; submit the calculations with the coil reports.</ITM><BRK/>
<BRK/></SPT>
]</TAI></SPT>][<SPT><TTL>3.4.8   Workmanship</TTL><BRK/>
<BRK/>
<TXT>Conduct TAB work on specified HVAC systems, as installed, until measured flow rates are equal to the design flow 
rates as specified or indicated on the contract documents.  This TAB work includes adjustment of balancing valves, 
balancing dampers, and sheaves.  Further, this TAB work includes changing out fan sheaves and pump impellers 
if required to obtain air and water flow rates specified or indicated.  If, with these adjustments and equipment 
changes, the specified or indicated design flow rates cannot be attained, contact the Contracting Officer for 
direction.</TXT><BRK/>
<BRK/></SPT>
]<SPT><TTL>3.4.9   Deficiencies</TTL><BRK/>
<BRK/>
<TXT>Strive to meet the intent of this section to maximize the performance of the equipment as designed and installed.  
However, if deficiencies in equipment design or installation prevent TAB work from being accomplished within 
the range of design values specified in the paragraph entitled "Workmanship," provide written notice as soon 
as possible to the Contractor and the Contracting Officer describing the deficiency and recommended correction.</TXT><BRK/>
<BRK/>
<TXT>Responsibility for correction of installation deficiencies is the Contractor's.  If a deficiency is in equipment 
design, call the TAB team supervisor for technical assistance.  Responsibility for reporting design deficiencies 
to Contractor is the TAB team supervisor's.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.10   TAB Reports</TTL><BRK/>
<TAI OPT="NAVFAC"><BRK/>
<TXT>Additional requirements for TAB Reports are specified in 23 05 93 - Appendix B  REPORTS - DALT and TAB</TXT></TAI><TAI OPT="NASA,USACE"><NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the options below.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Option 1:  Normally, use the following paragraph, which requires two 
separate trips within a season to the contract site by the TAB field team (the 
first for the TAB field work, the second for the TAB quality assurance work) 
with the TAB report submitted between the trips.  This is intended to give the 
design engineer time to review the TAB report before the quality assurance field 
check of that report is conducted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[After completion of the TAB field work, prepare the TAB field data for TAB supervisor's review and certification, 
using the reporting forms approved in the pre-field engineering report.  Data required by those approved data 
report forms is to be furnished by the TAB team.  Except as approved otherwise in writing by the Contracting 
Officer, the TAB work and thereby the TAB report is considered incomplete until the TAB work is accomplished 
to within the accuracy range specified in the paragraph entitled "Workmanship."]</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Option 2:  Use the following paragraph when the contract site is remote 
or the HVAC system is simple, and the specifier wants to reduce to one the number 
of trips to the contract site by the TAB field team within a season.  (TAB field 
work and TAB quality assurance accomplished in same trip).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[After completion of the TAB work, prepare a pre-final TAB report using the reporting forms approved in the pre-field 
engineering report.  Data required by those approved data report forms is to be furnished by the TAB team.  Except 
as approved otherwise in writing by the Contracting Officer, the TAB work and the TAB report is considered incomplete 
until the TAB work is accomplished to within the accuracy range specified in the paragraph entitled "Workmanship" 
of this section.</TXT><BRK/>
<BRK/>
<TXT>Prepare the report neatly and legibly; the pre-final TAB report is the final TAB report minus the TAB supervisor's 
review and certification.  Obtain, at the contract site, the TAB supervisor's review and certification of the 
TAB report.</TXT><BRK/>
<BRK/>
<TXT>Verbally notify the Contracting Officer's TAB representative that the field check of the TAB report data can 
commence; give this verbal notice 48 hours in advance of field check commencement.  Do not schedule field check 
of the TAB report until the specified workmanship requirements have been met or written approval of the deviations 
from the requirements have been received from the Contracting Officer.]</TXT></TAI><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.11   Quality Assurance - COTR TAB Field Acceptance Testing</TTL><BRK/>
<BRK/>
<SPT><TTL>3.4.11.1   TAB Field Acceptance Testing</TTL><BRK/>
<BRK/>
<TXT>During the field acceptance testing, verify, in the presence of the Contracting Officer's TAB representative, 
random selections of data (water, air quantities, air motion, [sound level readings]) recorded in the TAB Report.   
Points and areas for field acceptance testing are to be selected by the Contracting Officer's TAB representative.  
Measurement and test procedures are the same as approved for TAB work for the TAB Report.  <BRK/>
<BRK/>
Field acceptance testing includes verification of TAB Report data recorded for the following equipment groups:</TXT><BRK/>
<BRK/>
<LST>Group 1:  All chillers, boilers, return fans, computer room units, and air handling units (rooftop and 
central stations).</LST><BRK/>
<BRK/>
<LST>Group 2:  25% of the VAV terminal boxes and associated diffusers and registers.</LST><BRK/>
<BRK/>
<LST>Group 3:  25% of the supply diffusers, registers, grilles associated with constant volume air handling 
units.</LST><BRK/>
<BRK/>
<LST>Group 4:  25% of the return grilles, return registers, exhaust grilles and exhaust registers.</LST><BRK/>
<BRK/>
<LST>Group 5:  25% of the supply fans, exhaust fans, and pumps.</LST><BRK/>
<BRK/>
<TXT>Further, if any data on the TAB Report for Groups 2 through 5 is found not to fall within the range of plus 5 
to minus 5 percent of the TAB Report data, additional group data verification is required in the presence of 
the COTR.   Verify TAB Report data for one additional piece of equipment in that group.  Continue this additional 
group data verification until out-of-tolerance data ceases to be found.  </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.11.2   Additional COTR TAB Field Acceptance Testing</TTL><BRK/>
<BRK/>
<TXT>If any of the acceptance testing measurements for a given equipment group is found not to fall within the range 
of plus 5 to minus 5 percent of the TAB Report data, terminate data verification for all affected data for that 
group.  The affected data for the given group will be disapproved.  Make the necessary corrections and prepare 
a revised TAB Report.  Reschedule acceptance testing of the revised report data with the Contracting Officer's 
TAB representative.</TXT><BRK/>
<TAI OPT="NASA,USACE"><BRK/>
<TXT>Further, if any data on the TAB Report for a given field acceptance test group is out-of-tolerance, then field 
test data for one additional field test group as specified herein.  Continue this increase field test work until 
out-of-tolerance data ceases to to be found.  This additional field testing is up and above the original 25 percent 
of the of reported data entries to be field tested. <BRK/>
<BRK/>
If there are no more similar field test groups from which to choose, additional field testing from another, but 
different, type of field testing group must be tested.</TXT></TAI><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.11.3   Prerequisite for Approval</TTL><BRK/>
<BRK/>
<TXT>Compliance with the field acceptance testing requirements of this section is a prerequisite for the final Contracting 
Officer approval of the TAB Report submitted.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.5   MARKING OF SETTINGS</TTL><BRK/>
<BRK/>
<TXT>Upon the final TAB work approval, permanently mark the settings of HVAC adjustment devices including valves, 
gauges, splitters, and dampers so that adjustment can be restored if disturbed at any time.  Provide permanent 
markings clearly indicating the settings on the adjustment devices which result in the data reported on the submitted 
TAB report.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6   MARKING OF TEST PORTS</TTL><BRK/>
<BRK/>
<TXT>The TAB team is to permanently and legibly mark and identify the location points of the duct test ports.  If 
the ducts have exterior insulation, make these markings on the exterior side of the duct insulation.  Show the 
location of test ports on the as-built mechanical drawings with dimensions given where the test port is covered 
by exterior insulation.</TXT><BRK/>
<BRK/></SPT>
<TAI OPT="NAVFAC"><SPT><TTL>3.7   APPENDICES</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">UFGS-23 05 93 - Appendix A  WORK DESCRIPTIONS OF PARTICIPANTS</LST><BRK/>
<LST INDENT="-0.33">UFGS-23 05 93 - Appendix B  REPORTS - DALT and TAB</LST><BRK/>
<LST INDENT="-0.33">UFGS-23 05 93 - Appendix C  DALT AND TAB SUBMITTAL AND WORK SCHEDULE</LST><BRK/>
<BRK/>
<BRK/>
<PGE/><BRK/>
<HL4>UFGS-23 05 93 - Appendix A</HL4><BRK/>
<BRK/>
<HL4>WORK DESCRIPTIONS OF PARTICIPANTS</HL4><BRK/>
<BRK/>
<TXT>The Contractor is responsible for ensuring compliance with all requirements of this specification section.  However, 
the following delineation of specific work items is provided to facilitate and co-ordinate execution of the various 
work efforts by personnel from separate organizations.  </TXT><BRK/>
<BRK/>
<TXT>1.  Contractor</TXT><BRK/>
<BRK/>
    <LST>a.  HVAC documentation:  Provide pertinent contract documentation to the TAB Firm, to include the following: 
the contract drawings and specifications; copies of the approved submittal data for all HVAC equipment, 
air distribution devices, and air/water measuring/balancing devices; the construction work schedule; 
and other applicable documents requested by the TAB Firm.  Provide the TAB Firm copies of contract revisions 
and modifications as they occur.</LST><BRK/>
<BRK/>
<LST>b.  Schedules: Ensure the requirements specified under the paragraph "DALT and TAB Schedule" are met.</LST><BRK/>
<BRK/>
<LST>c.  Pre-DALT and TAB meeting:  Arrange and conduct the Pre-DALT and TAB meeting.  Ensure that a representative 
is present for the sheet metal contractor, the mechanical contractor, the electrical contractor, and 
the automatic temperature controls contractor.</LST><BRK/>
<BRK/>
<LST>d.  Coordinate Support:  Provide and coordinate support personnel required by the TAB Firm in order to 
accomplish the DALT and TAB field work.  Support personnel may include factory representatives, HVAC 
controls installers, HVAC equipment mechanics, sheet metal workers, pipe fitters, and insulators.  Ensure 
support personnel are present at the work site at the times required.</LST><BRK/>
<BRK/>
<LST>e.  Correct Deficiencies:  Ensure the notifications of Construction Deficiencies are provided as specified 
herein.  Refer to the paragraph entitled "Construction Deficiencies."  Correct each deficiency as soon 
as practical with the Contracting Officer, and submit revised schedules and other required documentation.</LST> <BRK/>
<BRK/>
<LST>f.  Pre-TAB Work Checklists:  Complete check out and debugging of HVAC equipment, ducts, and controls 
prior to the TAB engineer arriving at the project site to begin the TAB work.  Debugging includes searching 
for and eliminating malfunctioning elements in the HVAC system installations, and verifying all adjustable 
devices are functioning as designed.  Include as pre-TAB work checklist items, the deficiencies pointed 
out by the TAB team supervisor in the design review report.</LST><BRK/>
<BRK/>
<LST>Prior to the TAB field team's arrival, ensure completion of the applicable inspections and work items 
listed in the TAB team supervisor's DALT and TAB Work Procedures Summary.  Do not allow the TAB team 
to commence TAB field work until all of the following are completed.</LST><BRK/>
<BRK/>
<LST>g.  Give Notice of Testing:  Submit advance notice of TAB field work accompanied by completed prerequisite 
HVAC Work List</LST><BRK/>
<BRK/>
<LST>h.  Insulation work:  Ensure that no insulation is shall not be installed on ducts to be DALT'd until 
DALT work on the subject ducts is complete.<BRK/>
 </LST> <BRK/>
<LST>Ensure the duct and piping systems are properly insulated and vapor sealed upon the successful completion 
and acceptance of the DALT and TAB work.</LST><BRK/>
<BRK/>
<TXT>2.  TAB Team Supervisor</TXT><BRK/>
<BRK/>
<LST>a.  Overall management:  Supervise and manage the overall TAB team work effort, including preliminary 
and technical DALT and TAB procedures and TAB team field work.</LST><BRK/>
<BRK/>
<LST>b.  Schedule:  Ensure the requirements specified under the paragraph "DALT and TAB Schedule" are met.</LST><BRK/>
<BRK/>
<LST>c.  Submittals:  Provide the submittals specified herein.</LST><BRK/>
<BRK/>
<LST>d.  Pre-DALT/TAB meeting:  Attend meeting with Contractor.  Ensure TAB personnel that will be involved 
in the TAB work under this contract attend the meeting.</LST><BRK/>
<BRK/>
<LST>e.  Design Review Report:  Submit typed report describing omissions and deficiencies in the HVAC system's 
design that would preclude the TAB team from accomplishing the duct leakage testing work and the TAB 
work requirements of this section.  Provide a complete explanation including supporting documentation 
detailing the design deficiency.  State that no deficiencies are evident if that is the case.</LST><BRK/>
<BRK/>
<LST>f.  Support required:  Specify the technical support personnel required from the Contractor other than 
the TAB agency; such as factory representatives for temperature controls or for complex equipment.  Inform 
the Contractor in writing of the support personnel needed and when they are needed.  Furnish the notice 
as soon as the need is anticipated, either with the design review report, or the DALT and TAB Procedures 
Summary, the during the DALT or TAB field work.<BRK/>
<BRK/>
Ensure the Contractor is properly notified and aware of all support personnel needed to perform the TAB 
work.  Maintain communication with the Contractor regarding support personnel throughout the duration 
of the TAB field work, including the TAB field acceptance testing checking.<BRK/>
<BRK/>
Ensure all inspections and verifications for the Pre-Final DALT and Pre-TAB Checklists are completely 
and successfully conducted before DALT and TAB field work is performed.</LST><BRK/>
<BRK/>
<LST>g.  Advance Notice:  Monitor the completion of the duct system installations and provide the Advance 
Notice for Pre-Final DALT field work as specified herein.</LST><BRK/>
<BRK/>
<LST>h.  Technical Assistance:  Provide technical assistance to the DALT and TAB field work.</LST><BRK/>
<BRK/>
<LST>i.  Deficiencies Notification:  Ensure the notifications of Construction Deficiencies are provided as 
specified herein.  Comply with requirements of the paragraph entitled "Construction Deficiencies."  Resolve 
each deficiency as soon as practical and submit revised schedules and other required documentation.</LST><BRK/>
<BRK/>
<LST>j. Procedures:  Develop the required TAB procedures for systems or system components not covered in the 
TAB Standard.</LST><BRK/>
<BRK/>
<TXT>3.  TAB Team Field Leader</TXT><BRK/>
<BRK/>
<LST>a.  Field manager:  Manage, in the field, the accomplishment of the work specified in Part 3, "Execution."</LST><BRK/>
<BRK/>
<LST>b.  Full time:  Be present at the contract site when DALT field work or TAB field work is being performed 
by the TAB team; ensure day-to-day TAB team work accomplishments are in compliance with this section.</LST><BRK/>
<BRK/>
<LST>c.  Prerequisite HVAC work:  Do not bring the TAB team to the contract site until a copy of the prerequisite 
HVAC work list, with all work items certified by the Contractor to be working as designed, reaches the 
office of the TAB Agency.</LST><BRK/>
<BRK/>
<PGE/><BRK/>
<HL4>UFGS-23 05 93 - Appendix B</HL4><BRK/>
<BRK/>
<HL4>REPORTS - DALT and TAB</HL4><BRK/>
<BRK/>
<BRK/>
<TXT>All submitted documentation must be typed, neat, and organized.  All reports must have a waterproof front and 
back cover, a title page, a certification page, sequentially numbered pages throughout, and a table of contents.  
Tables, lists, and diagrams must be titled. Generate and submit for approval the following documentation:</TXT><BRK/>
<BRK/>
<TXT>1.   <SUB>DALT and TAB Work Execution Schedule</SUB></TXT><BRK/>
<BRK/>
<TXT>Submit a detailed schedule indicating the anticipated calendar date for each submittal and each portion of work 
required under this section.  For each work entry, indicate the support personnel (such as controls provider, 
HVAC mechanic, etc.) that are needed to accomplish the work.  Arrange schedule entries chronologically.  </TXT><BRK/>
<BRK/>
<TXT>2.   <SUB>DALT and TAB Procedures Summary</SUB></TXT><BRK/>
<BRK/>
<TXT>Submit a detailed narrative describing all aspects of the DALT and TAB field work to be performed.  Clearly distinguish 
between DALT information and TAB information.  Include the following:</TXT><BRK/>
<BRK/>
<LST>a.  A list of the intended procedural steps for the DALT and TAB field work from start to finish.  Indicate 
how each type of data measurement will be obtained.  Include what Contractor support personnel are required 
for each step, and the tasks they need to perform.</LST><BRK/>
<BRK/>
<LST>b.  A list of the project's submittals that are needed by the TAB Firm in order to meet this Contract's 
requirements.</LST><BRK/>
<BRK/>
<LST>c.  The schematic drawings to be used in the required reports, which may include building floor plans, 
mechanical room plans, duct system plans, and equipment elevations.  Indicate intended TAB measurement 
locations, including where test ports need to be provided by the Contractor.</LST><BRK/>
<BRK/>
<LST>d.  The data presentation forms to be used in the report, with the preliminary information and initial 
design values filled in.</LST><BRK/>
<BRK/>
<LST>e.  A list of DALT and TAB instruments to be used, edited for this project, to include the instrument 
name and description, manufacturer, model number, scale range, published accuracy, most recent calibration 
date, and what the instrument will be used for on this project.</LST><BRK/>
<BRK/>
<LST>f.  A thorough checklist of the work items and inspections that need to be accomplished before DALT field 
work can be performed.  The Contractor must complete, submit, and receive approval of the <SUB>Completed Pre-Final 
DALT Work Checklist</SUB> before DALT field work can be accomplished.</LST><BRK/>
<BRK/>
<LST>g.  A thorough checklist of the work items and inspections that need to be accomplished before the [Season 
1 ]TAB field work can be performed.  The Contractor must complete, submit, and receive approval of the <SUB>
Completed [Season 1 ]Pre-TAB Work Checklist</SUB> before the [Season 1 ]TAB field work can be accomplished.</LST><BRK/>
<BRK/>
<LST>[h.  A thorough checklist of the work items and inspections that need to be accomplished before the Season 
2 TAB field work can be performed.  The Contractor must complete, submit, and receive approval of the <SUB>
Completed Season 2 Pre-TAB Work Checklist</SUB> before the Season 2 TAB field work can be accomplished.]</LST><BRK/>
<BRK/>
<LST>i.  The checklists specified above shall be individually developed and tailored specifically for the 
work under this contract.  Refer to <RID>NEBB PROCEDURAL STANDARDS</RID>, Section III, "Preliminary TAB Procedures" 
under the paragraphs titled, "Air Distribution System Inspection" and "Hydronic Distribution System Inspection" 
for examples of items to include in the checklists.</LST><BRK/>
<BRK/>
<TXT>3.  <SUB>Design Review Report</SUB></TXT><BRK/>
<BRK/>
<TXT>Submit report containing the following information:</TXT><BRK/>
<BRK/>
<LST>a.  Review the contract specifications and drawings to verify that the TAB work can be successfully accomplished 
in compliance with the requirements of this section.  Verify the presence and location of permanently 
installed test ports and other devices needed, including gauge cocks, thermometer wells, flow control 
devices, circuit setters, balancing valves, and manual volume dampers.</LST><BRK/>
<BRK/>
<LST>b.  Submit a typed report describing omissions and deficiencies in the HVAC system's design that would 
preclude the TAB team from accomplishing the DALT work and the TAB work requirements of this section.  
Provide a complete explanation including supporting documentation detailing the design deficiency.  If 
no deficiencies are evident, state so in the report.</LST><BRK/>
<BRK/>
<TXT>4.  Pre-Final DALT Report for COTR DALT Field Checks</TXT><BRK/>
<BRK/>
<TXT>Report the data for the Pre-Final DALT Report meeting the following requirements:</TXT><BRK/>
<BRK/>
<LST>a.  Submit a copy of the approved DALT and TAB Procedures Summary:  Provide notations describing how 
actual field procedures differed from the procedures listed.</LST><BRK/>
<BRK/>
<LST>b.  Report format:  Submit a comprehensive report for the DALT field work data using data presentation 
forms equivalent to the "Air Duct Leakage Test Summary Report Forms" located in the <RID>SMACNA 1143</RID>.   In 
addition, submit in the report, a marked duct shop drawing which identifies each section of duct tested 
with assigned node numbers for each section.  Node numbers shall be included in the completed report 
forms to identify each duct section.</LST>  <BRK/>
<BRK/>
<LST>c.  Calculations:  Include a copy of all calculations prepared in determining the duct surface area of 
each duct test section.  Include in the DALT reports copy(s) of the calibration curve for each of the 
DALT test orifices used for testing.</LST><BRK/>
<BRK/>
<LST>d.  Instruments:  List the types of instruments actually used to measure the data.  Include in the listing 
each instrument's unique identification number, calibration date, and calibration expiration date.  Instruments 
are to be calibrated within one year of the date of use in the field; instrument calibration is to be 
traceable to the measuring standards of the National Institute of Standards and Technology.</LST><BRK/>
<BRK/>
<LST>d.  TAB Supervisor Approval:  Include on the submitted report the typed name of the TAB supervisor and 
the dated signature of the TAB supervisor.</LST><BRK/>
<BRK/>
<TXT>5.   Final DALT Report</TXT><BRK/>
<BRK/>
<TXT>On successful completion of all COTR field checks of the Pre-final DALT Report data for all systems, the TABS 
Supervisor shall assemble, review, sign and submit the Final DALT Report to the Contracting Officer for approval.</TXT><BRK/>
<BRK/>
<TXT>6.  TAB Reports:  Submit <SUB>TAB Report for Season 1</SUB> and <SUB>TAB Report for Season 2</SUB> in the following manner:</TXT><BRK/>
<BRK/>
<LST>a.  Procedure Summary:  Submit a copy of the approved DALT and TAB Procedures Summary.  When applicable, 
provide notations describing how actual field procedures differed from the procedures listed.</LST><BRK/>
<BRK/>
<LST>b.  Report format:  Submit the completed data forms approved in the pre-field TAB Engineering Report 
completed by TAB field team, reviewed, approved and signed by the TAB supervisor.  Bind the report with 
a waterproof front and back cover.  Include a table of contents identifying by page number the location 
of each report.  Report forms and report data shall be typewritten.  Handwritten report forms or report 
data are not acceptable.</LST><BRK/>
<BRK/>
<LST>c.  Temperatures:  On each TAB report form reporting TAB work accomplished on HVAC thermal energy transfer 
equipment, include the indoor and outdoor dry bulb temperature range and indoor and outdoor wet bulb 
temperature range within which the TAB data was recorded.  Include in the TAB report continuous time 
versus temperature recording data of wet and dry bulb temperatures for the rooms, or zones, as designated 
in the following list:</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The design engineer shall list, in the paragraph below, those rooms, 
or zones, for which indoor dry bulb and wet bulb temperatures shall be compiled 
for the specified time duration.  Include a sufficient number of rooms, or zones, 
in the listing to ensure correct evaluation of performance for the installed 
HVAC systems.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[_____]</ITM><BRK/>
<BRK/>
<ITM>(1)  Data shall be measured and compiled on a continuous basis for the period in which TAB work 
affecting those rooms is being done.</ITM><BRK/>
<BRK/>
<ITM>(2)  Data shall be measured/recorded only after the HVAC systems installations are complete, 
the systems fully balanced and the HVAC systems controls operating in fully automatic mode.  
Provide a detailed explanation wherever a final measurement did not achieve the required value.</ITM><BRK/>
<BRK/>
<ITM>(3)  Data may be compiled using direct digital controls trend logging where available.  Otherwise, 
the Contractor shall temporarily install calibrated time versus temperature/humidity recorders 
for this purpose.  The HVAC systems and controls shall have been fully operational a minimum 
of 24 hours in advance of commencing data compilation.  The specified data shall be included 
in the [Season I TAB Report] [Season I and Season 2 TAB Report].</ITM><BRK/>
<BRK/>
<LST>d. Air System Diagrams:  Provided updated diagrams with final installed locations of all terminals and 
devices, any numbering changes, and actual test locations.</LST> <BRK/>
<BRK/>
<LST>e.  Air Static Pressure Profiles:  Report static pressure profiles for air duct systems including:  [AHU-1][RTAC-1][MUA-1][_____].  
Report static pressure data for all supply, return, relief, exhaust and outside air ducts for the systems 
listed.  The static pressure report data shall include, in addition to AABC or NEBB or TABB required 
data, the following:</LST><BRK/>
<BRK/>
<ITM>(1)  Report supply fan, return fan, relief fan, and exhaust fan inlet and discharge static pressures.</ITM><BRK/>
<BRK/>
<ITM>(2)  Report static pressure drop across chilled water coils, DX coils, hot water coils, steam 
coils, electric resistance heating coils and heat reclaim devices installed in unit cabinetry 
or the system ductwork.</ITM><BRK/>
<BRK/>
<ITM>(3)  Report static pressure drop across outside air, return air, and supply air automatic control 
dampers, both proportional and two-position, installed in unit cabinetry.</ITM><BRK/>
<BRK/>
<ITM>(4)  Report static pressure drop across air filters, acoustic silencers, moisture eliminators, 
air flow straighteners, air flow measuring stations or other pressure drop producing specialty 
items installed in unit cabinetry, or in the system ductwork.  Examples of these specialty items 
are smoke detectors, white sound generators, RF shielding, wave guides, security bars, blast 
valves, small pipes passing through ductwork, and duct mounted humidifiers.</ITM><BRK/>
<BRK/>
<ITM>Do not report static pressure drop across duct fittings provided for the sole purpose of conveying 
air, such as elbows, transitions, offsets, plenums, manual dampers, and branch takes-offs.</ITM><BRK/>
<BRK/>
<ITM>(5)  Report static pressure drop across outside air and relief/exhaust air louvers.</ITM><BRK/>
<BRK/>
<ITM>(6)  Report static pressure readings of supply air, return air, exhaust/relief air, and outside 
air in duct at the point where these ducts connect to each air moving unit. </ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the brackets below for large air moving systems, i.e., include 
in the specification the duct traverses for the branch mains for air moving 
systems<MET> 4720 L/S</MET><ENG> 10000 CFM</ENG> and larger.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>[f.  Duct Transverses:  Report duct traverses for main [and branch main] supply, return[, exhaust, relief 
and outside air] ducts.  [This shall include all ducts, including those which lack 7 1/2 duct diameters 
upstream and 2 1/2 duct diameters downstream of straight duct unobstructed by duct fittings/offsets/elbows.]  
The TAB Agency shall evaluate and report findings on the duct traverses taken.  Evaluate the suitability 
of the duct traverse measurement based on satisfying the qualifications for a pitot traverse plane as 
defined by <RID>AMCA 203</RID>, "Field Measurements", Section 8, paragraph 8.3, "Location of Traverse Plane".]</LST><BRK/>
<BRK/>
<LST>g.  Instruments:  List the types of instruments actually used to measure the tab data.  Include in the 
listing each instrument's unique identification number, calibration date, and calibration expiration 
date.</LST><BRK/>
<BRK/>
<LST>Instrumentation, used for taking wet bulb temperature readings shall provide accuracy of plus or minus 
5 percent at the measured face velocities.  Submit instrument manufacturer's literature to document instrument 
accuracy performance is in compliance with that specified.</LST><BRK/>
<BRK/>
<LST>h.  Performance Curves: The TAB Supervisor shall include, in the TAB Reports, factory pump curves and 
fan curves for pumps and fans TAB'd on the job.</LST><BRK/>
<BRK/>
<LST>i.  Calibration Curves:  The TAB Supervisor shall include, in the TAB Reports, a factory calibration 
curve for installed flow control balancing valves, flow venturis and flow orifices TAB'd on the job.</LST><BRK/>
<BRK/>
<LST>j.  Data From Tab Field Work:  After completion of the TAB field work, prepare the TAB field data for 
TAB supervisor's review and approval signature, using the reporting forms approved in the pre-field engineering 
report.  Data required by those approved data report forms shall be furnished by the TAB team.  Except 
as approved otherwise in writing by the Contracting Officer, the TAB work and thereby the TAB report 
shall be considered incomplete until the TAB work is accomplished to within the accuracy range specified 
in the paragraph entitled "Workmanship."</LST><BRK/>
<BRK/>
<BRK/>
<BRK/>
<BRK/>
<PGE/><BRK/>
<HL4>UFGS-23 05 93 - Appendix C</HL4><BRK/>
<BRK/>
<HL4>DALT AND TAB SUBMITTAL AND WORK SCHEDULE</HL4><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Modify this suggested number of calendar days to suit the contract construction 
schedule.  Season 1 may be the season of maximum heating load or maximum cooling 
load, depending upon the construction schedule.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Perform the following items of work in the order listed adhering to the dates schedule specified below.  Include 
the major items listed in this schedule in the project network analysis schedule required by Section 
<SRF>01 32 17.00 20</SRF> NETWORK ANALYSIS SCHEDULES. </TXT><BRK/>
<BRK/>
<LST>Submit TAB Agency and TAB Personnel Qualifications:  Within [42] [_____] calendar days after date of 
contract award.</LST><BRK/>
<BRK/>
<LST>Submit the DALT and TAB Work Execution Schedule:  within [14] [_____]  days after receipt of the TAB 
agency and TAB personnel qualifications approval.  Revise and re-submit this schedule 28 days prior to 
commencement of DALT work and 28 days prior to the commencement of TAB Season 1 work and TAB Season 2 
work.</LST><BRK/>
<BRK/>
<LST>Submit the DALT and TAB Work Procedures Summary:  within [14] [_____]  days after receipt of the initial 
approved DALT and TAB Work Execution Schedule.</LST><BRK/>
<BRK/>
<LST>Meet with the COTR at the Pre-DALT/TAB Meeting:  Within [28] [_____] calendar days after receipt of the 
approved initial DALT/TAB Execution Schedule.</LST><BRK/>
<BRK/>
<LST>Submit Design Review Report:  Within [56] [_____] calendar days after the receipt of the approved initial 
DALT and TAB Work Execution Schedule.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:   When the measurement of existing facility conditions is desired, delete 
the brackets from the paragraph below.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>[Conduct measurements and submit the Record of Existing Facility Conditions:  within [28] [_____] days 
after receipt of approved DALT and TAB Work Procedures Summary.]</LST><BRK/>
<BRK/>
<LST>Advance Notice of Pre-Final DALT Field Work:  After the completed installation of the HVAC duct system 
to be DALT'd,  submit to the Contracting Officer an Advance Notice of Pre-Final DALT Field Work accompanied 
by the <SUB>completed Pre-Final DALT Work Checklist</SUB>checklist for the subject duct system. </LST><BRK/>
<BRK/>
<LST>Ductwork Selected for DALT:  Within 14 calendar days after receiving an acceptable completed Pre-Final 
DALT Work Checklist, the Contracting Officer's technical representative (COTR) will select the project 
ductwork sections to be DALT'd. </LST><BRK/>
<BRK/>
<LST>DALT Field Work:  Within 48 hours of COTR's selection, complete DALT field work on selected project ductwork.</LST><BRK/>
<BRK/>
<LST>Submit Pre-Final DALT Report:  Within two working days after completion of DALT field work, submit Pre-final 
DALT Report. Separate Pre-final DALT reports may be submitted to allow phased testing from system to 
system.</LST><BRK/>
<BRK/>
<LST>Quality Assurance - COTR DALT Field Checks:  Upon approval of the Pre-final DALT Report, the COTR's DALT 
field check work shall be scheduled with the Contracting Officer.</LST><BRK/>
<BRK/>
<LST>Submit Final DALT Report:  Within [14] [_____] calendar days after completion of successful DALT Work 
Field Check, submit [Season 1 ]TAB report.</LST><BRK/>
<BRK/>
<LST><SUB>Advance Notice of [Season 1 ]TAB Field Work</SUB>:  At a minimum of [14][_____] calendar days prior to [Season 
1 ]TAB Field Work, submit advance notice of TAB field work accompanied by <SUB>completed <BRK/>
[Season 1 ]Pre-TAB Work Checklist</SUB>.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the following four paragraphs, which requires two separate trips 
within Season 1 to the contract site by the TAB field team (the first for the 
TAB field work, the second for the TAB quality assurance work) with the TAB 
report submitted between trips.  This is intended to give the design engineer 
time to review the TAB report before the field check of that report is conducted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>[Season 1 ]TAB Field Work:  At a minimum of [84][_____] calendar days prior to CCD, [and when the ambient 
temperature is within Season 1 limits,] accomplish [Season 1 ]TAB field work.</LST><BRK/>
<BRK/>
<LST>Submit [Season 1 ]TAB Report:  Within [14] [_____] calendar days after completion of [Season 1 ]TAB field 
work, submit initial [Season 1 ]TAB report.</LST><BRK/>
<BRK/>
<LST>[Season 1 ]Quality Assurance - COTR TAB Field Check:  [30] [_____] calendar days after initial [Season 
1 ]TAB report is approved by the Contracting Officer, conduct [Season 1 ]field check.</LST><BRK/>
<BRK/>
<LST>Complete [Season 1 ]TAB Work:  Prior to CCD, complete all TAB work [except Season 2 TAB work] and submit 
final.</LST><BRK/>
<BRK/>
<LST>Receive the approved TAB report: Within 21 calendar days, receive the report from Contracting Officer 
approved TAB report.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include the remaining submittals and items of work only if there is a 
season 2 TAB Work </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST><SUB>Advance Notice of Season 2 TAB Field Work</SUB>:  At a minimum of [126] [___]calendar days after CCD, submit 
advance notice of Season 2 TAB field work accompanied by <SUB>completed Season 2 Pre-TAB Work Checklist</SUB>.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the following four paragraphs, which requires two separate trips 
within Season 2 to the contract site by the TAB field team (the first for the 
TAB field work, the second for the TAB quality assurance work) with the TAB 
report submitted between trips.  This is intended to give the design engineer 
time to review the TAB report before the field check of that report is conducted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>[Season 2 TAB Field Work:  Within [14] [_____] calendar days after date of advance notice of Season 2 
TAB field work and when the ambient temperature is within Season 2 limits, accomplish Season 2 TAB field 
work</LST>.<BRK/>
<BRK/>
<LST>Submit Season 2 TAB Report:  Within [14] [_____] calendar days after completion of Season 2 TAB field 
work, submit Season 2 TAB report.</LST><BRK/>
<BRK/>
<LST>Season 2 Quality Assurance - COTR TAB Field Checks:  [28] [_____] calendar days after the Season 2 TAB 
report is approved by the Contracting Officer, conduct Season 2 field check.</LST><BRK/>
<BRK/>
<LST>Complete Season 2 TAB Work:  Within [14] [_____] calendar days after the completion of Season 2 TAB field 
data check, complete all TAB work.]</LST><BRK/>
<BRK/>
<LST>Receive the approved TAB report: Within calendar 21 days, receive the report from Contracting Officer.</LST><BRK/>
<BRK/></SPT>
</TAI></PRT>    <END/><BRK/></SEC>