<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA   UFGS-26 11 16 (April 2007)<BRK/>
                                 -------------------------------<BRK/>
Preparing Activity:  <PRA>NAVFAC</PRA>      Replacing without change <BRK/>
                                 UFGS-26 11 16 (April 2006) <BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 26 11 16</SCN><BRK/>
<BRK/>
<STL>SECONDARY UNIT SUBSTATIONS</STL><BRK/>
<DTE>04/07</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:<BRK/>
<BRK/>
1.  This guide specification covers the requirements for three phase <SCP>secondary 
unit substations for step-down operation at primary voltages of 601 volts through 
38 kilovolts, and secondary voltages, of 600 volts or less</SCP>.<BRK/>
<BRK/>
2.  When feasible, provide a separate liquid-filled pad-mounted transformer 
outside of the facility and a separately erected switchboard/switchgear assembly 
inside the respective facility in lieu of a secondary unit substation.  For 
LANTNAVFACENGCOM projects, do not use secondary unit substations with secondary 
current greater than 5000 amperes.<BRK/>
<BRK/>
3.  For LANTNAVFACENGCOM projects, where the available fault current is less 
than 12,000 amperes rms symmetrical, provide pad-mounted switchgear with a fault 
interrupting switch-way as the transformer primary protection device in lieu 
of a load interrupting switch.  Clearly indicate requirements for identifying 
signage at switch-ways and at the transformer.<BRK/>
<BRK/>
USE THE FOLLOWING RELATED GUIDE SPECIFICATIONS FOR POWER DISTRIBUTION EQUIPMENT:<BRK/>
<BRK/>
--Section <SRF>26 08 00</SRF> APPARATUS INSPECTION AND TESTING<BRK/>
--Section <SRF>26 12 19.10</SRF> THREE-PHASE PAD-MOUNTED TRANSFORMERS<BRK/>
--Section <SRF>26 12 19.20</SRF> SINGLE-PHASE PAD-MOUNTED TRANSFORMERS<BRK/>
--Section <SRF>26 11 14.00 10</SRF> MAIN ELECTRIC SUPPLY STATION AND SUBSTATION<BRK/>
--Section <SRF>26 13 00.00 20</SRF> SF6 INSULATED PAD-MOUNTED SWITCHGEAR<BRK/>
--Section <SRF>26 11 13.00 20</SRF> PRIMARY UNIT SUBSTATIONS<BRK/>
--Section <SRF>33 71 01</SRF> UNDERGROUND TRANSMISSION AND DISTRIBUTION SYSTEM, AERIAL<BRK/>
--Section <SRF>33 70 02.00 10</SRF> UNDERGROUND TRANSMISSION AND DISTRIBUTION SYSTEM, UNDERGROUND<BRK/>
--Section <SRF>26 28 00.00 10</SRF> MOTOR CONTROL CENTERS, SWITCHBOARDS AND PANELBOARDS<BRK/>
--Section <SRF>26 22 00.00 20</SRF> 480-VOLT STATION SERVICE SWITCHGEAR AND TRANSFORMERS<BRK/>
--Section <SRF>26 23 00</SRF> SWITCHBOARDS AND SWITCHGEAR<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestion on this specification are welcome and should be directed 
to the technical proponent of the specification.  A listing of the <URL HREF="http://www.ccb.org/UFGS/ufgstoc.htm">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This section utilizes the following energy cost and loss value tables.  
Graphics/Tables files contain all graphics/tables for the specification. </NPR><BRK/>
<BRK/>
<NPR>NOTE: TO DOWNLOAD UFGS GRAPHICS<BRK/>
<BRK/>
Go to <URL HREF="http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf">http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf</URL>.</NPR><BRK/>
<BRK/>
<NPR>Do not include list of tables, or tables themselves, in project specifications.  
Use tables to obtain values required in Part 2 of the specification.</NPR><BRK/>
<BRK/>
<NPR>For SOUTHNAVFACENGCOM facilities use table US-2.</NPR><BRK/>
<BRK/>
<TBL><THD>  <HL1>TABLE NUMBER</HL1>                                 <HL1>TITLE</HL1><BRK/>
<BRK/></THD>
     US-1           Transformer Loss &amp; Impedance Data - for Energy <BRK/>
                     Cost (EC) Less Than or Equal to $0.04  (2 pages)<BRK/>
<BRK/>
     US-2           Transformer Loss &amp; Impedance Data - for Energy <BRK/>
                     Cost (EC) Greater Than $0.04 and Less Than or <BRK/>
                     Equal to $0.08  (2 pages)<BRK/>
<BRK/>
     US-3           Transformer Loss &amp; Impedance Data - for Energy <BRK/>
                     Cost (EC) Greater Than $0.08 and Less Than or <BRK/>
                     Equal to $0.12  (2 pages)<BRK/>
<BRK/>
     EC-1           Energy costs at LANTNAVFACENGCOM Activities<BRK/>
                     (2 pages)</TBL><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The following information shall be shown on the project drawings:</NPR><BRK/>
<BRK/>
<NPR>1.  Single-line diagram showing transformers, buses, and interrupting devices 
with interrupting capacities; current transformers with ratings; instruments 
and meters required; and description of instruments and meters.</NPR><BRK/>
<BRK/>
<NPR>2.  Location, space available, arrangement and elevations of unit substations.</NPR><BRK/>
<BRK/>
<NPR>3.  Grounding Plan.</NPR><BRK/>
<BRK/>
<NPR>4.  Type and number of cables, size of conductors for each power circuit, and 
point of entry (top or bottom).</NPR><BRK/>
<BRK/>
<NPR>5.  Transformer primary and secondary voltages. (Use IEEE C57.12.00, Table 11(b), 
"Designation of voltage ratings of three-phase windings".)  State the primary 
voltage (nominal) actually in service and not the voltage class.</NPR><BRK/>
<BRK/>
<NPR>6.  Special conditions, such as altitude, temperature and humidity, exposure 
to fumes, vapors, dust, and gases; and seismic requirements.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
 <BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
 <BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to in the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ACI INTERNATIONAL (ACI)</ORG><BRK/><BRK/><RID>ACI 318M</RID><RTL>(2008) Metric Building Code Requirements for Structural Concrete and Commentary</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)</ORG><BRK/><BRK/><RID>ANSI C39.1</RID><RTL>(1981; R 1992) Requirements for Electrical Analog Indicating Instruments</RTL><BRK/><BRK/><RID>ANSI C57.12.13</RID><RTL>(1982) Conformance Requirements for Liquid-Filled Transformers</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM A 123/A 123M</RID><RTL>(2008) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products</RTL><BRK/><BRK/><RID>ASTM A 153/A 153M</RID><RTL>(2005) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware</RTL><BRK/><BRK/><RID>ASTM A 167</RID><RTL>(1999; R 2004) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip</RTL><BRK/><BRK/><RID>ASTM A 653/A 653M</RID><RTL>(2008) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process</RTL><BRK/><BRK/><RID>ASTM A 780</RID><RTL>(2001; R 2006) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings</RTL><BRK/><BRK/><RID>ASTM C 260</RID><RTL>(2006) Standard Specification for Air-Entraining Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM D 117</RID><RTL>(2002) Standard Guide for Sampling, Test Methods, Specifications and Guide for Electrical Insulating Oils of Petroleum Origin</RTL><BRK/><BRK/><RID>ASTM D 1535</RID><RTL>(2008) Specifying Color by the Munsell System</RTL><BRK/><BRK/><RID>ASTM D 3487</RID><RTL>(2008) Standard Specification for Mineral Insulating Oil Used in Electrical Apparatus</RTL><BRK/><BRK/><RID>ASTM D 709</RID><RTL>(2001; R 2007) Laminated Thermosetting Materials</RTL><BRK/><BRK/><RID>ASTM D 877</RID><RTL>(2002; R 2007) Standard Test Method for Dielectric Breakdown Voltage of Insulating Liquids Using Disk Electrodes</RTL><BRK/><BRK/><RID>ASTM D 92</RID><RTL>(2005a) Standard Test Method for Flash and Fire Points by Cleveland Open Cup Tester</RTL><BRK/><BRK/><RID>ASTM D 97</RID><RTL>(2008) Pour Point of Petroleum Products</RTL><BRK/><BRK/></REF><REF><ORG>FM GLOBAL (FM)</ORG><BRK/><BRK/><RID>FM P7825</RID><RTL>(2005) Approval Guide</RTL><BRK/><BRK/></REF><REF><ORG>INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)</ORG><BRK/><BRK/><RID>IEEE C2</RID><RTL>(2007; Errata 2007; INT 2008) National Electrical Safety Code</RTL><BRK/><BRK/><RID>IEEE C37.121</RID><RTL>(1989; R 2006) American National Standard for Switchgear Unit Substations Requirements</RTL><BRK/><BRK/><RID>IEEE C37.20.3</RID><RTL>(2001; R 2006) Metal-Enclosed Interrupter Switchgear</RTL><BRK/><BRK/><RID>IEEE C37.90.1</RID><RTL>(2002; Errata 2003; Errata 2004) Surge Withstand Capability (SWC) Tests for Relays and Relay Systems Associated with Electric Power Apparatus</RTL><BRK/><BRK/><RID>IEEE C57.12.00</RID><RTL>(2006) Standard General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers</RTL><BRK/><BRK/><RID>IEEE C57.12.01</RID><RTL>(2005) General Requirements for Dry-Type Distribution and Power Transformers Including Those with Solid-Cast and/or Resin-Encapsulated Windings</RTL><BRK/><BRK/><RID>IEEE C57.12.29</RID><RTL>(2005) Pad-Mounted Equipment - Enclosure Integrity for Coastal Environments</RTL><BRK/><BRK/><RID>IEEE C57.12.50</RID><RTL>(1981; R 1998) Sealed Dry-Type Distribution Transformers 1 to 500 kVA, Single-Phase; and 15 to 500 kVA, Three-Phase with High-Voltage 601 to 34 500 Volts, Low-Voltage 120 to 600 Volts</RTL><BRK/><BRK/><RID>IEEE C57.12.51</RID><RTL>(1981; R 1998) Ventilated Dry-Type Power Transformers, 501 kVA and Larger, Three-Phase, with High-Voltage 601 to 34 500 Volts, Low-Voltage 208Y/120 to 4160 Volts</RTL><BRK/><BRK/><RID>IEEE C57.12.80</RID><RTL>(2002) Standard Terminology for Power and Distribution Transformers</RTL><BRK/><BRK/><RID>IEEE C57.12.90</RID><RTL>(2006) Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers</RTL><BRK/><BRK/><RID>IEEE C57.12.91</RID><RTL>(2001; INT 2005) Test Code for Dry-Type Distribution and Power Transformers</RTL><BRK/><BRK/><RID>IEEE C57.124</RID><RTL>(1991; R 2002) Recommended Practice for the Detection of Partial Discharge and the Measurement of Apparent Charge in Dry-Type Transformers</RTL><BRK/><BRK/><RID>IEEE C57.13</RID><RTL>(2008) Standard Requirements for Instrument Transformers</RTL><BRK/><BRK/><RID>IEEE C57.98</RID><RTL>(1993; R 1999) Guide for Transformer Impulse Tests</RTL><BRK/><BRK/><RID>IEEE C62.11</RID><RTL>(2005; Amendment A 2008) Standard for Metal-Oxide Surge Arresters for Alternating Current Power Circuits (&gt;1kV)</RTL><BRK/><BRK/><RID>IEEE Std 100</RID><RTL>(2000) The Authoritative Dictionary of IEEE Standards Terms</RTL><BRK/><BRK/><RID>IEEE Std 386</RID><RTL>(2006) Standard for Separable Insulated Connector Systems for Power Distribution Systems Above 600V</RTL><BRK/><BRK/></REF><REF><ORG>INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)</ORG><BRK/><BRK/><RID>NETA ATS</RID><RTL>(2003) Acceptance Testing Specifications</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)</ORG><BRK/><BRK/><RID>NEMA C12.1</RID><RTL>(2008) Electric Meters; Code for Electricity Metering</RTL><BRK/><BRK/><RID>NEMA C12.10</RID><RTL>(2004) Physical Aspects of Watthour Meters</RTL><BRK/><BRK/><RID>NEMA C12.4</RID><RTL>(1984; R 2002) Mechanical Demand Registers</RTL><BRK/><BRK/><RID>NEMA ICS 6</RID><RTL>(1993; R 2006) Standard for Industrial Controls and Systems Enclosures</RTL><BRK/><BRK/><RID>NEMA LI 1</RID><RTL>(1998) Industrial Laminated Thermosetting Products</RTL><BRK/><BRK/><RID>NEMA ST 20</RID><RTL>(1992; R 1997) Standard for Dry-Type Transformers for General Applications</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)</ORG><BRK/><BRK/><RID>NFPA 70</RID><RTL>(2007; AMD 1 2008) National Electrical Code - 2008 Edition</RTL><BRK/><BRK/></REF><REF><ORG>ORGANISATION FOR ECONOMIC CO-OPERATION AND DEVELOPMENT (OECD)</ORG><BRK/><BRK/><RID>OECD Test 203</RID><RTL>(1992) Fish Acute Toxicity Test</RTL><BRK/><BRK/></REF><REF><ORG>U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)</ORG><BRK/><BRK/><RID>EPA 600/4-90/027F</RID><RTL>(1993) Methods for Measuring the Acute Toxicity of Effluents and Receiving Waters to Freshwater and Marine Organisms</RTL><BRK/><BRK/><RID>EPA 712-C-98-075</RID><RTL>(1996) Fate, Transport and Transformation Test Guidelines - OPPTS 835.3100- "Aerobic Aquatic Biodegradation"</RTL><BRK/><BRK/></REF><REF><ORG>UNDERWRITERS LABORATORIES (UL)</ORG><BRK/><BRK/><RID>UL 467</RID><RTL>(2007) Standard for Grounding and Bonding Equipment</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   RELATED REQUIREMENTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include Section 26 08 00 APPARATUS INSPECTION AND TESTING on all projects 
involving medium voltage and specialized power distribution equipment.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Section <SRF>26 08 00</SRF> APPARATUS INSPECTION AND TESTING applies to this section, with the additions and modifications 
specified herein.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   DEFINITIONS</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, 
and on the drawings, shall be as defined in <RID>IEEE Std 100</RID>.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>Include the bracketed paragraph for Navy projects for SOUTHNAVFACENGCOM or LANTNAVFACENGCOM.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  Submit the following 
in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
[<TXT>In addition, submit in accordance with paragraph entitled "Coordinated Submittal Reviews" herein.</TXT>]<BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Do not use the following submittal exception paragraph with dry-type 
transformers.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>As an exception to the transformer submittal requirements specified herein, liquid-filled transformers manufactured 
by ABB in South Boston, VA; by Cooper Power Systems in Waukesha, WI; or by Howard Industries in Laurel, MS need 
not meet the submittal requirements of this contract.  Instead, the following shall be submitted:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  A certification, from the manufacturer, that the technical requirements of this specification shall 
be met.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  An outline drawing of the transformer with devices identified (paragraph entitled "Transformer Drawings," 
item a).</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  ANSI nameplate data of the transformer (paragraph entitled "Transformer Drawings", item b).</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use "will" on all SOUTHNAVFACENGCOM projects.   Coordinate with paragraph 
entitled "Source Quality Control."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">d.  Routine and other tests (paragraph entitled "Routine and Other Tests"), shall be conducted by the 
manufacturer and [may][will] be witnessed by the government (paragraph entitled "Source Quality Control").  
Provide transformer test schedule required by submittal item "SD-11 Closeout Submittals".  Provide certified 
copies of the tests.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Provide acceptance test reports required by submittal item "SD-06 Test Reports".</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Provide operation and maintenance manuals required by submittal item "SD-10 Operation and Maintenance 
Data".</LST><BRK/>
<BRK/>
<SPT><TTL>1.4.1   Coordinated Submittal Reviews</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include bracketed items "a" and "b" for LANTNAVFACENGCOM and SOUTHNAVFACENGCOM 
projects. Choose the bracketed option "CI44" or "CI46" for LANTNAVFACENGCOM 
projects, and "074" for SOUTHNAVFACENGCOM projects.  For other projects, submittal 
review shall be performed by the designer of record.  If submittal review by 
LANTNAVFACENGCOM or SOUTHNAVFACENGCOM is specifically desired, the responsible 
Government agency must coordinate with the respective Code CI44, CI46, or 074 
during the design process.  Add appropriate information in Section 01 33 00 
SUBMITTAL PROCEDURES to coordinate with the special requirements.  For LANTNAVFACENGCOM, 
submit liquid-filled transformers to CI44 and dry-type transformers to CI46.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[a.  Submit transformer submittals to Code [[CI44][CI46], Atlantic][074, Southern] Division, Naval Facilities 
Engineering Command for approval.  In addition, submit one set of the remaining substation components 
for surveillance.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[b.  Submit remaining substation component submittals to Engineer of Record for approval. In addition, 
submit one set of transformer submittals for surveillance and to insure alignment of equipment and coordination 
for interconnections.]</LST><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Unit Substation Drawings</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>[<SUB>Transformer drawings</SUB> (to Code [[CI44][CI46]][074])[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]]</ITM><BRK/>
<BRK/>
<ITM>Include wiring diagrams and installation details of equipment indicating proposed location, 
layout and arrangement, control panels, accessories, piping, ductwork, and other items that 
must be shown to ensure a coordinated installation.  Wiring diagrams shall identify circuit 
terminals and indicate the internal wiring for each item of equipment and the interconnection 
between each item of equipment.  Drawings shall indicate adequate clearance for operation, maintenance, 
and replacement of operating equipment devices.  Submittals shall include the nameplate data, 
size, and capacity.  Submittals shall also include applicable federal, military, industry, and 
technical society publication references.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM>[<SUB>Fuse curves</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use bracketed options referring to Codes CI44 or CI46 for LANTNAVFACENGCOM 
and to Code 074 for SOUTHNAVFACENGCOM projects.  This requires the designer 
of record to review and approve the substation equipment submittals except for 
the transformer.  The EFD will review and approve the transformer submittals.  
For LANTNAVFACENGCOM submit liquid-filled transformers to CI44 and dry-type 
to CI46.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM><SUB>Secondary unit substation</SUB>[ excluding transformer data][; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>[Unit substation <SUB>transformer (liquid-filled)</SUB> (to Code [CI44][074])[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]]</ITM><BRK/>
<BRK/>
<ITM>[Unit substation <SUB>transformer (dry-type)</SUB> (to Code [CI46][074])[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]]</ITM><BRK/>
<BRK/>
<ITM>Submittal shall include manufacturer's information for each component, device, and accessory 
provided with the transformer.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Acceptance checks and tests</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Paint coating system</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Transformer Losses</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-09 Manufacturer's Field Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Load Interrupter Switch production tests</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Unit substation <SUB>transformer design tests (liquid-filled)</SUB>[ (to code [CI44][074])][; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>
]</ITM><BRK/>
<BRK/>
<ITM>Unit substation <SUB>transformer routine and other tests (liquid-filled)</SUB>[ (to code [CI44][074])][; <SUB>
G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For dry-type transformers, use the following bracketed options.  Delete 
the previous three options for liquid filled transformers along with their associated 
subparagraphs in the paragraph entitled "Source Quality Control."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[Unit substation transformer <SUB>design tests (dry-type)</SUB>[ (to code [CI46][074])][; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>
]]</ITM><BRK/>
<BRK/>
<ITM>[Unit substation transformer <SUB>routine and other tests (dry-type)</SUB>[ (to code [CI46][074])][; <SUB>G</SUB>][; <SUB>
G, [_____]</SUB>]]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-10 Operation and Maintenance Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Unit substations</SUB>, Data Package 5[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-11 Closeout Submittals</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Assembled Operation and Maintenance Manuals</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Equipment test schedule</SUB>[ (to Code [[CI44 for liquid-filled units][CI46 for dry-type units]][074])][; <SUB>
G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.5   QUALITY ASSURANCE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.5.1   Drawing Requirements</TTL><BRK/>
<BRK/>
<SPT><TTL>1.5.1.1   <SUB>Unit Substation Drawings</SUB></TTL><BRK/>
<BRK/>
<TXT>Drawings shall include, but are not limited to the following:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  An outline drawing, with front, top, and side views showing incoming, transformer, and outgoing sections.[  
Include [switchboard][switchgear] information from  Section[ <SRF>26 28 00.00 10</SRF> MOTOR CONTROL CENTERS, SWITCHBOARDS 
AND PANELBOARDS][ <SRF>26 23 00</SRF> SWITCHBOARDS AND SWITCHGEAR] as part of the total unit substation.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  One-line diagram showing[[ fused] load interrupter switch,][ current transformers, meters,] and ampere 
rating of bus bars.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Elementary diagrams and wiring diagrams with terminals identified, and indicating prewired interconnections 
between items of equipment and the interconnection between the items.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[d.  Provisions for future extension[ and future forced air equipment].]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[e.  Time-current characteristic <SUB>fuse curves</SUB> (on full size logarithmic paper) for the load interrupter 
switch fuse.]</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.1.2   <SUB>Transformer Drawings</SUB></TTL><BRK/>
<BRK/>
<TXT>Drawings shall include, but are not limited to the following:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  An outline drawing, with front, top, and side views.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  ANSI nameplate data.</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.5.2   <SUB>Paint Coating System</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit <RID>IEEE C57.12.29</RID> coating system performance requirement tests.  When interrupter switchgear and transformer 
are provided by two different manufacturers, each one shall provide certification.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.3   <SUB>Transformer Losses</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use this paragraph, without the bracketed sentence, for oil-filled transformers.  
Also use this paragraph for dry-type transformers on LANTNAVFACENGCOM projects 
and include the bracketed sentence.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Submit certification from the manufacturer indicating conformance with the paragraph entitled "Specified Transformer 
Losses".[  If tests on transformers of "basically the same design" are not available, provide written certification 
by manufacturer that transformers will meet the specified losses, and state what the losses will be.  Submit 
report with transformer shop drawings and product data.] </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.4   Substation Product Data</TTL><BRK/>
<BRK/>
<TXT>Submittal shall include manufacturer's information for each component, device, and accessory provided with the 
equipment.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.5   Test Reports</TTL><BRK/>
<BRK/>
<TXT>Submit report of acceptance test results as specified by paragraph entitled "Field Quality Control."</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.6   Regulatory Requirements</TTL><BRK/>
<BRK/>
<TXT>In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the 
word, "shall" had been substituted for "should" wherever it appears.  Interpret references in these publications 
to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer.  Equipment, 
materials, installation, and workmanship shall be in accordance with the mandatory and advisory provisions of <RID>
NFPA 70</RID> unless more stringent requirements are specified or indicated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.7   Standard Products</TTL><BRK/>
<BRK/>
<TXT>Provide materials and equipment that are products of manufacturers regularly engaged in the production of such 
products which are of equal material, design and workmanship.  Products shall have been in satisfactory commercial 
or industrial use for 2 years prior to bid opening.  The 2-year period shall include applications of equipment 
and materials under similar circumstances and of similar size.  The product shall have been on sale on the commercial 
market through advertisements, manufacturers' catalogs, or brochures during the 2-year period.  Where two or 
more items of the same class of equipment are required, these items shall be products of a single manufacturer; 
however, the component parts of the item need not be the products of the same manufacturer unless stated in this 
section.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.5.7.1   Alternative Qualifications</TTL><BRK/>
<BRK/>
<TXT>Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory 
field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is 
furnished.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.7.2   Material and Equipment Manufacturing Date</TTL><BRK/>
<BRK/>
<TXT>Products manufactured more than 3 years prior to date of delivery to site shall not be used, unless specified 
otherwise.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>1.6   MAINTENANCE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.6.1   <SUB>Assembled Operation and Maintenance Manuals</SUB></TTL><BRK/>
<BRK/>
<TXT>Manuals shall be assembled in durable, hard covered, water resistant binders.  The manual shall be assembled 
and indexed in the order noted in a table of contents.  The contents of the assembled operation and maintenance 
manuals shall be as follows:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Manufacturer's O&amp;M information required by the paragraph entitled, "SD-10 Operation and Maintenance 
Data."</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Catalog data required by the paragraph entitled, "SD-03 Product Data."</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Drawing required by the paragraph entitled, "SD-02 Shop Drawings."</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Price for spare parts and supply list</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Routine and field acceptance test reports</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6.2   Operation and Maintenance Data</TTL><BRK/>
<BRK/>
<TXT>Submit operation and maintenance data in accordance with Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE DATA and 
as specified herein.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.7   WARRANTY</TTL><BRK/>
<BRK/>
<TXT>The equipment items shall be supported by service organizations which are reasonably convenient to the equipment 
installation in order to render satisfactory service to the equipment on a regular and emergency basis during 
the warranty period of the contract.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   PRODUCT COORDINATION</TTL><BRK/>
<BRK/>
<TXT>Products and materials not considered to be secondary unit substations and related accessories are specified 
in Section[ <SRF>33 71 02.00 20</SRF> UNDERGROUND ELECTRICAL DISTRIBUTION][  <SRF>33 70 02.00 10</SRF> UNDERGROUND TRANSMISSION AND 
DISTRIBUTION SYSTEM, UNDERGROUND] and Section <SRF>26 20 00</SRF> INTERIOR DISTRIBUTION SYSTEM.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2   <SUB>SECONDARY UNIT SUBSTATION</SUB></TTL><BRK/>
<BRK/>
<TXT>Secondary <SUB>Unit substations</SUB> shall comply with <RID>IEEE C37.121</RID> regardless of the kVA rating specified.  Substation 
shall consist of [one][_____] incoming section[s], [one][_____] transformer section[s], and [one][_____] outgoing 
section[s].[  Substation shall be designed for outdoor service with ventilation openings and gasketing provided 
to ensure a weatherproof assembly under rain, snow, sleet, and hurricane conditions.]  Substations shall be subassembled 
and coordinated by one manufacturer and shall be shipped in complete sections ready for connection at the site.  
Where practicable, substation shall be shipped as one unit.  External doors shall have provisions for padlocking.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Incoming Section[s]</TTL><BRK/>
<BRK/>
<TXT>The incoming section shall consist of [a metal-enclosed interrupter switchgear section][an air-filled terminal 
chamber] for connecting the incoming circuit [directly][through a [fused][nonfused] load interrupter switch] 
to the transformer.  If required for proper connection and alignment, include a transition section with the incoming 
section.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.1.1   Incoming Section Enclosure</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If medium voltage breakers are required for the main protective device, 
add information from Section 26 11 13.00 20  PRIMARY UNIT SUBSTATION  for Navy 
projects and Section 26 11 14.00 10 MAIN ELECTRIC SUPPLY STATION AND SUBSTATION 
for other projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The incoming section enclosure shall be <RID>NEMA ICS 6</RID> Type [3R][1][__][as indicated][, fabricated entirely of <RID>ASTM A 167</RID>
 type 304 or 304L stainless steel].[  Bases, frames and channels of enclosure shall be corrosion resistant and 
shall be fabricated of [<RID>ASTM A 167</RID> type 304 or 304L stainless steel][ or ][galvanized steel].  Base shall include 
any part of enclosure that is within<MET> 75 mm</MET><ENG> 3 inches</ENG> of concrete pad.][  Galvanized steel shall be <RID>ASTM A 123/A 123M</RID>
, <RID>ASTM A 653/A 653M</RID> G90 coating, and <RID>ASTM A 153/A 153M</RID>, as applicable.]  Paint enclosure, including bases, <RID>ASTM D 1535</RID>
 light gray No. 61 or No. 49.  Paint coating system shall comply with <RID>IEEE C57.12.29</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.1.2   Cable Terminations</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select insulated high-voltage connectors only when connecting directly 
to a dead-front transformer without using a load interrupter switch.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Provide medium voltage cable terminations as specified in Section[ <SRF>33 71 02.00 20</SRF> UNDERGROUND UNDERGROUND TRANSMISSION 
AND DISTRIBUTION][ <SRF>33 70 02.00 10</SRF> UNDERGROUND TRANSMISSION AND DISTRIBUTION SYSTEM, UNDERGROUND].]</TXT><BRK/>
<BRK/>
<TXT>[<RID>IEEE Std 386</RID>.  Insulated High-Voltage Connectors.  Connectors shall have steel reinforced hook-stick eye, grounding 
eye, test point, and arc-quenching contact material.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Coordinate with connector and bushings specified in transformer section.  
If available fault is greater than 10,000 rms symmetrical amperes or if cable 
size is greater than No. 4/0 AWG, do not use 200 ampere loadbreak connectors.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[a.  200 ampere loadbreak connector ratings:  Voltage:  [15kV, 95 kV BIL][25 kV, 125 kV BIL][35 kV, 150 
kV BIL].  Short time rating:  10,000 rms symmetrical Amperes.]</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: For LANTNAVFACENGCOM projects, provide 600 ampere connectors with 200 
ampere bushing interface.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[b.  600 ampere deadbreak connector ratings:  Voltage:  [15 kV, 95 kV BIL][25 kV, 125 kV BIL][35 kV, 
150 kV BIL].  Short time rating:  40,000 rms symmetrical amperes.[  Connectors shall have 200 ampere 
bushing interface[ for surge arresters][ as indicated].]]</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include the following paragraph only when the activity requires additional 
grounding elbows and feed-thru inserts.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[c.  Provide one set of three grounding elbows[ and one set of three feed-thru inserts] for each secondary 
unit substation.  Grounding elbows and feed-thru inserts shall be delivered to the contracting officer.]]</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.1.3   Surge Arresters</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Surge arresters should be located at both the riser pole (where applicable) 
and at the equipment.  Specify surge arrestors at the riser pole in Section 
33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION .  Dead front surge arresters 
are only available as distribution class.  Substations utilizing station class 
arresters are covered by Section 26 11 13.00 20 PRIMARY UNIT SUBSTATION for 
Navy projects and Section 26 11 14.00 10 MAIN ELECTRIC SUPPLY STATION AND SUBSTATION 
for other projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>IEEE C62.11</RID>, rated [3][6][9][10][12][15][___][kV][as indicated][, fully shielded, dead-front, metal-oxide-varistor, 
elbow type with resistance-graded gap, suitable for plugging into inserts].  Arresters shall be [intermediate] 
[distribution] class.  Arresters for use at elevations in excess of 6000 feet above mean sea level shall be specifically 
rated for that purpose.  Arresters shall be equipped with mounting brackets suitable for the indicated installations.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.1.4   Load Interrupter Switch</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Verify UL listing is available for specified equipment before including 
bracketed option.  UL listing may not be available for equipment operating above 
15 kV.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>IEEE C37.20.3</RID>[, UL listed and labeled load interrupter switchgear].  Provide a three-pole, single-throw, deadfront, 
metal-enclosed, load interrupter switch with manual stored energy operator. Switch shall be [fused, with fuses 
mounted on a single frame][non-fused] and designed for easy inspection[ and fuse replacement].  The switch shall 
be operated by a manually charged spring stored energy mechanism which shall simultaneously disconnect or connect 
ungrounded conductors.  The moveable blade of the switch shall be deenergized when in the open position.  The 
mechanism shall enable the switch to close against a fault equal to the momentary rating of the switch without 
affecting its continuous current carrying or load interrupting ability.  A ground bus shall extend the width 
of the switch enclosure and shall be bolted directly thereto.  Connect frame of unit to ground bus.  The door 
shall have an inspection window to allow full view of the position of the three switch blades through the closed 
door.  Switch shall have provision for padlocking in the open and closed positions.  [Switch][Switch/fuse integrated] 
ratings shall be as follow:</TXT><BRK/>
<BRK/>
<TBL><THD>     Rated        Rated         Continuous     Short-Circuit     Short-Time/<BRK/>
     Maximum      Withstand     and Load       Current kA        Fault-Close<BRK/>
     Voltage,     Impulse       Interrupting   rms Sym           Current kA<BRK/>
     kV           Voltage,      Current, A<BRK/>
                  kV BIL        <BRK/>
<BRK/></THD>
     [4.76        60            [600][1200]    [25][38]           [40][61]]<BRK/>
     [15          95            [600][1200]    [25][38]           [40][61]]<BRK/>
     [25.8        125           [600][1200]    [25][38]           [40][61]]<BRK/>
     [38          150           [600][1200]    [25]               [40]]</TBL><BRK/>
<BRK/>
<TXT>[Fuses shall be current limiting type rated [[_____] amperes continuous, and [_____] amperes interrupting capacity][approximately 
[_____] percent of the transformer full-load rating and in accordance with the fuse manufacturer's recommendation]].</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>2.2.1.5   Primary Protective Device Connection</TTL><BRK/>
<BRK/>
<TXT>Connections between the primary protective device and transformer shall be [cable][bus] mounted on porcelain 
insulators, and sized and braced to withstand the specified short-circuit and short-time currents.</TXT><BRK/>
<BRK/>
]</SPT></SPT><SPT><TTL>2.2.2   <SUB>Transformer (Liquid-Filled)</SUB> Section[s]</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Indicate and specify the type of transformers required for the project.</NPR><BRK/>
<BRK/>
<NPR>1.  Previously the use of mineral oil filled transformers were recommended wherever 
possible.  The recent availability of biodegradable less-flammable transformer 
liquids may have altered that recommendation.  For LANTNAVFACENGCOM, choose 
less-flammable transformer liquids as specified below for all projects unless 
there is a specific requirement to do otherwise.  Where adequate distance from 
structures cannot be attained, consult NAVFAC design manuals and UFC 3-600-01, 
"Design: Fire Protection Engineering For Facilities."  Silicon-filled and R-temp 
filled transformers shall not be used for less-flammable requirements.</NPR><BRK/>
<BRK/>
<NPR>2.  Use dry type transformers in unique applications only where their use can 
be thoroughly justified.  Identify the intent to utilize dry type units in the 
basis of design and obtain approval from the applicable reviewing engineering 
field division.  Dry type transformers, available in a variety of styles (including 
Cast Coil, Cast / Encapsulated Coil, Vacuum Pressure Encapsulated (VPE), Vacuum 
Pressure Impregnated (VPI) and Sealed) are normally less efficient and more 
expensive than oil filled transformers.  There are, however, certain applications 
which warrant their use.  This specification is limited to a choice of cast 
coil and vacuum pressure insulated (VPI) types of transformers which are available 
from at least three major manufacturers.  Cast coil transformers (primary and 
secondary individually cast in epoxy) are recommended for use when planning 
de-energization of transformer for extended periods of time, when located outdoors, 
or in an extremely corrosive chemical environment.  VPI transformers are recommended 
when used in a clean, limited space, indoor environment for continuous service.</NPR><BRK/>
<BRK/>
<NPR>3.  Use the following option(s) when additional capacity is required.  This 
involves special coordination with transformer KVA ratings, as well as sizes 
and ratings of fuses and secondary breakers.</NPR><BRK/>
<BRK/>
<NPR>a.  If it is anticipated that future load requirements will necessitate increasing 
the capacity of the transformer, the specification for the transformer should 
require the provision of components and brackets for future forced air cooling 
and mechanical circulation for the coolant fluid.</NPR><BRK/>
<BRK/>
<NPR>b.  On rare occasions, for liquid-filled transformers, change "...insulation 
system rated for a 65 degrees C rise..." to read "...insulation system rated 
for a 55/65 degrees C rise to allow transformer(s) to have a continuous overload 
capacity of 12 percent at rated voltage without exceeding 65 degrees C winding 
temperature rise."</NPR><BRK/>
<BRK/>
<NPR>4.  Use IEEE C57.12.00, Table 11(b), "Designation of voltage ratings of three-phase 
windings", such as "4160 V - 480Y / 277 V."</NPR><BRK/>
<BRK/>
<NPR>5.  Tap ratings may vary from those indicated especially in lower kVA ratings.</NPR><BRK/>
<BRK/>
<NPR>6.  For liquid-filled transformers, select impedance value in accordance with 
technical note under paragraph entitled "Specified Transformer Losses."</NPR><BRK/>
<BRK/>
<NPR>7.  Dry-type transformers below 750 kVA usually have impedance values in the 
range of 2.5 to 5.0 percent.   Perform fault current calculations to determine 
minimum acceptable transformer impedance.  Be sure that specified impedance 
is available in the size and type transformer required.</NPR><BRK/>
<BRK/>
<NPR>8.  Delete last sentence, referring to removable ground strap, if transformer 
secondary winding is delta type.</NPR><BRK/>
<BRK/>
<NPR>9.  Choose stainless steel fabrication where environmental conditions are not 
suitable for mild steel or where a higher level of corrosion protection is desired 
(i.e. directly on waterfront).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ANSI C57.12.13</RID>.  [Mineral oil liquid-filled][Less-flammable liquid-filled].  Transformer [base][,including the 
tank, radiators, flanges, base, lifting provisions, and hardware,] shall be fabricated of <RID>ASTM A 167</RID> type 304, 
304L, or 316 stainless steel.[  Transformer base shall include any part of the transformer that is within<MET> 75 
mm</MET><ENG> 3 inches</ENG> of concrete pad.]  Paint coating system shall comply with <RID>IEEE C57.12.29</RID>.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.2.1   Transformer Ratings</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Cooling Class:  [ONAN-Liquid-filled, self-cooled][ONAN/ONAF-Liquid-filled, self-cooled/forced air 
cooled][____].</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Frequency:  [50][60] Hz.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Phases:  Three phase.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Rated Kilovolt Amperes:  [_____] kVA</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Voltage Rating:  [_____] v - [_____] V.[  For GrdY - GrdY transformers, provide transformer with 
five-legged core design for third harmonic suppression.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Impedance:  Minimum tested impedance shall not be less than [_____] percent at 85 degrees C.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Insulation Level:  [60][95][150][_____] kV BIL</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">h.  Temperature Rise:  65 degree C average winding temperature rise above a 30 degree ambient.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Delete kVA ranges and sound levels for kVA ratings not used in the job.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">i.  Audible Sound Levels:  Audible sound levels shall comply with the following:</LST><BRK/>
<BRK/>
<TBL><THD>                   <HL1>kVA Range</HL1>            <HL1>DECIBELS (MAX)</HL1><BRK/>
<BRK/></THD>
                   225-300                 55<BRK/>
                   301-500                 56<BRK/>
                   501-700                 57<BRK/>
                   701-1000                58<BRK/>
                   1001-1500               60<BRK/>
                   1501-2000               61<BRK/>
                   2001-2500               62<BRK/>
                   2501-3000               63<BRK/>
                   3001-4000               64</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2.2   Transformer Accessories</TTL><BRK/>
<BRK/>
<TXT>The transformer shall have the following accessories:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  [Four][_____] 2.5 percent full capacity taps, [two][_____] above and [two][_____] below rated primary 
voltage.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Tap changer, with external, pad-lockable, manual type operating handle, for changing tap setting 
when transformer is de-energized.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[c.  Dead-front high-voltage bushings; <RID>IEEE Std 386</RID>.  [15 kV, 95 kV BIL][25kV, 125 kV BIL][35 kV, 150 
kV BIL].  Provide [200 ampere bushing wells with bushing well inserts][600 ampere one piece deadbreak 
apparatus bushings].]</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include standoff bushings only when the Activity requires the additional 
items.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[d.  Parking stands:  Provide a parking stand near each dead-front bushing.[  Provide insulated standoff 
bushings for parking of energized load-break connectors on each parking stands.]]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Insulated low-voltage neutral bushing with lugs for ground cable and removable ground strap.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Ground pads.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Liquid-level indicator.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">h.  Pressure-vacuum gage.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">i.  Liquid temperature indicator.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">j.  Drain and filter valves.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">k.  Pressure relief device, top mounted, Qualitrol series 208.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">l.  Diagrammatic stainless steel or laser-etched anodized aluminum nameplate in accordance with <RID>IEEE C57.12.00</RID>
 and as modified or supplemented by this section.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">m.  Transformer base with provisions for jacking and for rolling in either direction.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">n.  Lifting provisions.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">o.  Bolted transformer top or welded top with bolted handhole access.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[p.  Auxiliary cooling equipment and controls.</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">[1.  Transformer shall have provisions for future addition of automatically controlled fans 
for forced-air-cooling.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[2.  Transformer shall be forced-air-cooled.  Forced-air-cooling fans shall have [automatic 
temperature control relay][winding temperature indicator with sequence contacts].]]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2.3   Specified Transformer Losses</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Steps to specifying transformer losses for oil-filled transformers:</NPR><BRK/>
<BRK/>
<NPR>1.  Print Tables US-1, US-2, US-3, and EC-1 or EC-2 as applicable (directions 
included at the front of this specification).</NPR><BRK/>
<BRK/>
<NPR>2.  Obtain energy cost for the specific activity from the cognizant EFD or PWC.  
Energy costs should be based on the cost of energy without the demand charge 
factors scaled in.  Use Table EC - 1 for energy costs at the indicated LANTNAVFACENGCOM 
activities.  Use Table US-2 for energy costs at all SOUTHNAVFACENGCOM activities.  
(Additional tables will be added for other EFD's as the information becomes 
available.)</NPR><BRK/>
<BRK/>
<NPR>3.  Use Tables US-1, US-2, and US-3 to specify losses and impedances for transformers 
based on energy cost range, and transformer primary and secondary voltages.</NPR><BRK/>
<BRK/>
<NPR>4.  Perform fault current calculations to verify that distribution equipment 
is coordinated with impedance specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>No-load losses (NLL) shall be [____] watts at 20 degrees C and load losses (LL) shall be [____] watts at 85 degrees 
C.</TXT><BRK/>
<BRK/>
<TXT>The values for the specified losses shall be used for comparison with the losses determined during the routine 
tests.  If the routine test values for no-load losses exceed the specified no-load losses by more than 10 percent, 
or the total losses exceed the specified total losses (sum of no-load and load losses) by more than 6 percent, 
the transformer is unacceptable.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2.4   Insulating Liquid</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options.  For LANTNAVFACENGCOM, choose less-flammable 
transformer liquids for all projects unless there is a specific requirement 
to do otherwise.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[a.  Mineral oil:  <RID>ASTM D 3487</RID>, Type II, tested in accordance with <RID>ASTM D 117</RID>.  Provide identification 
of transformer as "non-PCB" and "Type II mineral oil" on the nameplate.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[b.  Less-flammable transformer liquids:  <RID>NFPA 70</RID> and <RID>FM P7825</RID> for less-flammable liquids having a fire 
point not less than 300 degrees C tested per <RID>ASTM D 92</RID> and a dielectric strength not less than 33 kV 
tested per <RID>ASTM D 877</RID>.  Provide identification of transformer as "non-PCB" and "manufacturer's name and 
type of fluid" on the nameplate.</LST><BRK/>
<BRK/>
<LST>The fluid shall be a biodegradable electrical insulating and cooling liquid classified by UL and approved 
by FM as "less flammable" fluids.  The fluid shall meet the following fluid properties:</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Pour point:  <RID>ASTM D 97</RID>, less than -15 degree C</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Aquatic biodegradation:  <RID>EPA 712-C-98-075</RID>, 100%</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Trout toxicity:  <RID>OECD Test 203</RID>, zero mortality of <RID>EPA 600/4-90/027F</RID>, pass]</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT>[<TTL>2.2.3   <SUB>Transformer (Dry-Type)</SUB> Section[s]</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the paragraphs on Dry-Type Transformers when Liquid-Filled Transformers 
are used.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>IEEE C57.12.01</RID>, and [<RID>IEEE C57.12.50</RID> for dry-type transformers rated up to 500 kVA][<RID>IEEE C57.12.51</RID> for dry-type 
transformers rated 501 kVA and larger].  Transformer [base][, including the enclosure, flanges, base, lifting 
provisions, and hardware,] shall be fabricated of <RID>ASTM A 167</RID> type 304 or 304L  stainless steel.[  Transformer 
base shall include any part of the transformer that is within<MET> 75 mm</MET><ENG> 3 inches</ENG> of concrete pad.]  Paint coating 
system shall comply with <RID>IEEE C57.12.29</RID>.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select either cast coil or VPI transformer.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Provide a cast coil type transformer with primary and secondary windings individually cast in epoxy.  Resin-encapsulated 
windings are not acceptable.  Transformer[s] shall have an insulation system rated 185 degrees C, with an 80 
degree C average winding temperature rise above a 40 degrees C maximum ambient.]</TXT><BRK/>
<BRK/>
<TXT>[Provide a vacuum pressure impregnated (VPI) type transformer with an insulation system rated 220 degrees C, 
and with an 80 degree C average winding temperature rise above a 40 degrees C maximum ambient.]</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.3.1   Transformer Ratings</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use 95 kV BIL for 15 kV systems in lieu of the 60 kV BIL allowed by the 
referenced standards.  10 kV BIL is the standard secondary rating for up to 
600 volts.  30 kV BIL is an optional secondary rating that can be specified 
when required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">a.  Transformer shall be rated [_____] kVA, [95][60][_____] kV BIL Primary and 10 kV BIL Secondary.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Transformer voltage ratings:  [____] V - [____] V.[  For GrdY - GrdY transformers, provide transformer 
with five-legged core design for third harmonic suppression.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Provide four 2.5 percent full capacity taps, two above and two below rated primary voltage.  Locate 
tap adjustments on the face of the high voltage coil.  Adjustments shall be accessible by removing the 
front panel and shall be made when the transformer is de-energized.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Minimum tested impedance shall not be less than [_____] percent at 80 degrees C.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Edit kVA and sound levels for those used in job - delete those not used. </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">e.  Audible sound levels shall comply with the following:</LST><BRK/>
<BRK/>
<TBL><THD>                   <HL1>kVA</HL1>            <HL1>DECIBELS (MAX)</HL1><BRK/>
<BRK/></THD>
                   225                 58<BRK/>
                   300                 58<BRK/>
                   500                 60<BRK/>
                   750                 64<BRK/>
                   1000                64<BRK/>
                   1500                65<BRK/>
                   2000                66<BRK/>
                   2500                68</TBL><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Diagrammatic stainless steel or laser-etched anodized aluminum nameplate</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Transformer shall include ground pads, lifting lugs and provisions for jacking under base.  The transformer 
base construction shall be suitable for using rollers or skidding in any direction.  The transformer 
shall have an insulated low-voltage neutral bushing with lugs for ground cable, and with removable ground 
strap.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">h.  Dry type transformer shall have the following accessories.</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Winding temperature indicator</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[2.  Auxiliary cooling equipment and controls</ITM><BRK/>
<BRK/>
<ITM>[(a)  Transformer shall have provisions for future addition of automatically controlled fans 
for forced-air-cooling.]</ITM><BRK/>
<BRK/>
<ITM>[(b)  Transformer shall be forced-air-cooled.  Forced-air-cooling fans shall have [automatic 
temperature control relay][winding temperature indicator with sequence contacts].]]</ITM><BRK/>
<BRK/></SPT>
<SPT>[<TTL>2.2.3.2   Specified Transformer Losses</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  On LANTNAVFACENGCOM and SOUTHNAVFACENGCOM projects only, include the 
paragraphs entitled "Specified Transformer Losses."  The appropriate NLL and 
LL values for each transformer will be provided by Code CI46 or Code 074 at 
the 100 percent review.  Until that time, leave the following bracketed values 
blank.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>No-load losses (NLL) shall be [____] watts at 80 degrees C, and load losses (LL) shall be [____] watts at 100 
degrees C.  The values for the specified losses shall be used for comparison with the losses determined during 
the routine tests.  If the routine test values for no-load losses exceed the specified no-load losses by more 
than 10 percent, or the total losses exceed the specified total losses (sum of no-load and load losses) by more 
than 6 percent, the transformer is unacceptable.</TXT><BRK/>
<BRK/>
]</SPT>]</SPT><SPT><TTL>2.2.4   Outgoing Section</TTL><BRK/>
<BRK/>
<TXT>[The outgoing section shall consist of a full height air terminal compartment for physical protection of and 
connection point for the secondary conductors between the transformer and the [switchboard][_____] located [in 
the building][_____].]</TXT><BRK/>
<BRK/>
<TXT>[The outgoing section shall consist of a full height air terminal compartment.  This compartment shall contain 
the indicated metering,[ instruments,][ and][ control power transformers] and shall be the connection point for 
the secondary conductors between the transformer and the [switchboard][_____] located [in the building][_____].  
Provide one three point latching hinged door, either full height or on the upper half of the outgoing section 
to provide access to metering.  The upper section shall contain the current transformers and a watthour meter 
mounted to a dead front interior barrier as defined below.  If using upper half section door only, the lower 
section shall be bolt on type and contain bus bars and lugs to terminate the service entrance conductors.  Provide 
insulated barriers between the upper and lower sections to permit the bus bars to pass between the sections.  
Provide locking access handle to eliminate unauthorized access.]</TXT><BRK/>
<BRK/>
<TXT>[The outgoing section shall consist of a secondary transition section for connecting to a low-voltage [switchboard][switchgear 
section].  The [switchboard][switchgear] shall be as specified in Section[ <SRF>26 28 00.00 10</SRF> MOTOR CONTROL CENTERS, 
SWITCHBOARDS AND PANELBOARDS][ <SRF>26 22 00.00 10</SRF> 480-VOLT STATION SERVICE SWITCHGEAR AND TRANSFORMERS][ 
<SRF>26 23 00</SRF> SWITCHBOARDS AND SWITCHGEAR].  Connections between the transformer secondary bushings and the outgoing 
section transition bus shall be flexible braid bus.  The secondary transition section shall have a hinged front 
panel.]</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.4.1   Outgoing Section Enclosure</TTL><BRK/>
<BRK/>
<TXT>Provide outgoing section enclosure in accordance with the requirements in paragraph entitled, "Incoming Section 
Enclosure".</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT>[<TTL>2.2.5   Watthour and Digital Meters</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  When Section 23 09 54.00 20 DIRECT DIGITAL CONTROL SYSTEMS or Section 
23 09 23 DIRECT DIGITAL CONTROL FOR HVAC AND OTHER LOCAL BUILDING SYSTEMS is 
used, coordinate meter data with  communication requirements.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.2.5.1   Electronic Watthour Meter</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  On standard projects, use of the electronic meter versus the optional 
electro-mechanical meter is recommended due to decreasing availability of electromechanical 
meters.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>NEMA C12.10</RID>.  Provide a switchboard style electronic programmable watthour meter, semi-drawout, semi-flush mounted, 
as indicated.  Meter shall either be programmed at the factory or shall be programmed in the field.  When field 
programming is performed, turn field programming device over to the Contracting Officer at completion of project.  
Meter shall be coordinated to system requirements.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Form 9S, in text below, is for three-phase, four-wire wye systems, for 
other system configurations, designer shall determine the appropriate form designation.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">a.  Design:  Provide meter designed for use on a 3-phase, 4-wire, [208Y/120][480Y/277] volt system with 
3 current transformers.  Include necessary KYZ pulse initiation hardware for Energy Monitoring and Control 
System (EMCS)[ as specified in Section[ <SRF>23 09 23</SRF> DIRECT DIGITAL CONTROL FOR HVAC AND OTHER LOCAL BUILDING 
SYSTEMS][ <SRF>23 09 23</SRF> DIRECT DIGITAL CONTROL FOR HVAC AND OTHER LOCAL BUILDING SYSTEMS]].</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Coordination;  Provide meter coordinated with ratios of current transformers and transformer secondary 
voltage.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Class 20.  Form:  [9S][_____].  Accuracy:  +/- 1.0 percent.<BRK/>
Finish:   Class II.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Kilowatt-hour Register:  5 digit electronic programmable type.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Demand Register:</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Provide solid state.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Meter reading multiplier:  Indicate multiplier on the meter face.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Demand interval length:  shall be programmed for [15][30][60] minutes with rolling demand 
up to six subintervals per interval.</ITM><BRK/>
<BRK/></SPT>
<SPT>[<TTL>2.2.5.2   Electro-Mechanical Watthour Meters</TTL><BRK/>
<BRK/>
<TXT><RID>NEMA C12.10</RID>.  Kilowatt-hour meters shall be [two][three][four]-stator, transformer rated, polyphase, 60 hertz, 
[surface][semiflush] mounted, [drawout][semi drawout] switchboard meters [120 volt for use on a four-wire wye, 
three phase, 208Y/120 Volt system][240 volt for use on a four-wire wye, three-phase 480Y/277 volt system].  Meter 
shall have a five-dial pointer type register.[  The kilowatt-hour meter shall have a [sweep-hand][cumulative] 
type kilowatt demand register with [15][30][60]-minute interval conforming to <RID>NEMA C12.4</RID>.]  Provide correct multiplier 
on face of meter.</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.2.5.3   Digital Meters</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Digital metering incorporates the latest technology and provides additional 
information, often without additional cost. A control power transformer (115 
V or 130 V) is normally required with this type of metering.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>IEEE C37.90.1</RID> for surge withstand.  Provide true rms, plus/minus one percent accuracy, programmable, microprocessor-based 
meters enclosed in sealed cases with a simultaneous three line display.  Meters shall have<MET> 16 mm</MET><ENG> 0.56 inch</ENG>, minimum, 
LED's.[  Watthour meter shall have a single line display with<MET> 16 mm</MET><ENG> 0.56 inch</ENG>, minimum, LED's.] The meters shall 
accept[ input from standard 5A secondary instrument transformers][ and][ direct voltage monitoring range to [300][600] 
volts, phase to phase to phase].  Programming shall be via a front panel display and a communication interface 
with a computer.  Password secured programming shall be stored in non-volatile EEPROM memory.  Digital communications 
shall be Modbus [ASCII][RTU] protocol via an [RS232C][RS485] serial port[ and an independently addressable [RS232C][RS485] 
serial port].  The meter shall calculate and store average max/min demand values for all readings based on a 
user selectable sliding window averaging period.  The meter shall have programmable hi/low set limits with two 
Form C dry contact relays when exceeding alarm conditions.[  Meter shall provide THD measurement to the thirty-first 
order.][  Historical trend logging capability shall include ability to store up to 100,000 data points with intervals 
of 1 second to 180 minutes.  The unit shall also store and time stamp up to 100 programmable triggered conditions.][  
Event waveform recording shall be triggered by the rms of 2 cycles of voltage or current exceeding programmable 
set points.  Waveforms shall be stored for all 6 channels of voltage and current for a minimum of 10 cycles prior 
to the event and 50 cycles past the event.]</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">[a.  Multi-Function Meter:  Meter shall simultaneously display a selected phase to neutral voltage, phase 
to phase voltage, percent phase to neutral voltage THD, percent phase to phase voltage THD; a selected 
phase current, neutral current, percent phase current THD, percent neutral current; selected total PF, 
kW, kVA, kVAR, FREQ, kVAh, kWh.  Detected alarm conditions include over/under current, over/under voltage, 
over/under kVA, over/under frequency, over/under selected PF/kVAR, voltage phase reversal, voltage imbalance, 
reverse power, over percent THD.  The meter shall have a Form C KYZ pulse output relay.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[b.  Power Meter:  Meter shall simultaneously display Watts, VARs, and selected kVA/PF.  Detected alarm 
conditions include over/under kVA, over/under PF, over/under VARs, over/under reverse power.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[c.  Volt Meter:  Meter shall be selectable between simultaneous display of the three phases of phase 
to neutral voltages and simultaneous display of the three phases of the phase to phase voltages.  Detected 
alarm conditions include over/under voltage, over/under voltage imbalance, and over percent THD.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[d.  Ammeter:  Meter shall simultaneously display phase A, B, and C current.  Detected alarm conditions 
include over/under current, and over percent THD.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[e.  Digital Watthour Meter:  Meter shall have a single selectable display for watts, total kilowatt 
hours (kWh) and watt demand (Wd).  The meter shall have a Form C KYZ pulse output relay.]</LST><BRK/>
<BRK/>
]</SPT>]</SPT><SPT>[<TTL>2.2.6   Instruments</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  On projects where voltage or amperage readings are required, use of the 
digital metering equipment versus individual ammeters and voltmeters may be 
justified due to technological advances and reduced costs of electronic equipment.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ANSI C39.1</RID> for electrical indicating switchboard style instruments, with 2 percent accuracy.  The ac ammeters 
and voltmeters shall be minimum of<MET> 50.8 mm (2 inches)</MET><ENG> 2 inches</ENG> square, with<MET> 4.36 rad (250-degree)</MET><ENG> 250-degree</ENG> 
scale.  Provide single phase indicating instruments with flush-mounted transfer switches for reading three phases.</TXT><BRK/>
<BRK/>
<SPT>[<TTL>2.2.6.1   Ac Ammeters</TTL><BRK/>
<BRK/>
<TXT>[Self-contained][Transformers rated, 5-ampere input, for use with a [_____] to 5-ampere current transformer ratio], 
0 to [_____]-ampere scale range, 60 hertz.</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.2.6.2   Ac Voltmeters</TTL><BRK/>
<BRK/>
<TXT>Self-contained.</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.2.6.3   Instrument Control Switches</TTL><BRK/>
<BRK/>
<TXT>Provide rotary cam-operated type with positive means of indicating contact positions.  Switches shall have silver-to-silver 
contacts enclosed in a protective cover which can be removed to inspect the contacts.</TXT><BRK/>
<BRK/>
]</SPT>]</SPT><SPT>[<TTL>2.2.7   Current Transformers</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select the appropriate current transformer (CT) ratio, continuous-thermal-current 
rating factor (RF) at 30 degrees C and ANSI Metering Accuracy Class values based 
on the CT ratio which is just below the rating of the main protective device.<BRK/>
<BRK/>
Select an ANSI Metering Accuracy Class in accordance with the following table:</NPR><BRK/>
<BRK/>
<TBL><THD>              CT Ratio     RF       Accuracy Class<BRK/>
<BRK/></THD>
                200/5      4.0      0.3 thru B-0.1<BRK/>
                300/5      3.0      0.3 thru B-0.2<BRK/>
                400/5      4.0      0.3 thru B-0.2<BRK/>
                600/5      3.0      0.3 thru B-0.5<BRK/>
                800/5      2.0      0.3 thru B-0.5<BRK/>
               1200/5      1.5      0.3 thru B-0.5<BRK/>
               1500/5      1.5      0.3 thru B-0.9<BRK/>
               2000/5      1.5      0.3 thru B-1.8<BRK/>
               2500/5      1.5      0.3 thru B-1.8<BRK/>
               3000/5      1.5      0.3 thru B-1.8<BRK/>
               3500/5      1.5      0.3 thru B-1.8<BRK/>
               4000/5      1.5      0.3 thru B-1.8<BRK/>
               5000/5      1.5      0.3 thru B-1.8</TBL><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>IEEE C57.13</RID>.  Transformers shall be single ratio, 60 hertz, [_____] to 5-ampere ratio, [_____] rating factor, 
with a metering accuracy class of 0.3 through [_____].</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.2.8   Control Power Transformers</TTL><BRK/>
<BRK/>
<TXT>Transformer shall conform to the requirements of Section <SRF>26 20 00</SRF> INTERIOR DISTRIBUTION SYSTEM.</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.2.9   Meter Fusing</TTL><BRK/>
<BRK/>
<TXT>Provide a fuse block mounted in the metering compartment containing one fuse per phase to protect the voltage 
input to voltage sensing meters.  Size fuses as recommended by the meter manufacturer.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>2.2.10   Heaters</TTL><BRK/>
<BRK/>
<TXT>Provide 120-volt heaters in[ incoming section,][ dry-type transformer section,][ and][ outgoing section].  Heaters 
shall be of sufficient capacity to control moisture condensation in the compartments, shall be 250 watts minimum, 
and shall be controlled by a thermostat[ and humidistat] located in each section.  Thermostat shall be industrial 
type, high limit, to maintain compartments within the range of<MET> 15.5 to 32.2 degrees C</MET><ENG> 60 to 90 degrees F</ENG>.[  Humidistat 
shall have a range of 30 to 60 percent relative humidity.]  If heater voltage is different than substation equipment 
voltage, provide transformer rated to carry 125 percent of heater full load rating.  Transformer shall have 220 
degrees C insulation system with a temperature rise not exceeding 115 degrees C and shall conform to <RID>NEMA ST 20</RID>
.[  Energize electric heaters while the equipment is in storage or in place prior to being placed in service.  
Provide method for easy connection of heater to external power source.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.11   Insulated Barriers</TTL><BRK/>
<BRK/>
<TXT>Where insulated barriers are required by reference standards, provide barriers in accordance with <RID>NEMA LI 1</RID>, 
Type GPO-3,<MET> 6.35 mm (0.25 inch)</MET><ENG> 0.25 inch</ENG> minimum thickness.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.12   Terminal Boards</TTL><BRK/>
<BRK/>
<TXT>Provide with engraved plastic terminal strips and screw type terminals for external wiring between components 
and for internal wiring between removable assemblies.  Terminal boards associated with current transformers shall 
be short-circuiting type.  Terminate conductors for current transformers with ring-tongue lugs.  Terminal board 
identification shall be identical in similar units.  External wiring shall be color coded consistently for similar 
terminal boards.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.13   Wire Marking</TTL><BRK/>
<BRK/>
<TXT>Mark control and metering conductors at each end.  Provide factory-installed, white, plastic tubing, heat stamped 
with black block type letters on factory-installed wiring.  On field-installed wiring, provide white, preprinted, 
polyvinyl chloride (PVC) sleeves, heat stamped with black block type letters.  Each sleeve shall contain a single 
letter or number, shall be elliptically shaped to securely grip the wire, and shall be keyed in such a manner 
to ensure alignment with adjacent sleeves.  Provide specific wire markings using the appropriate combination 
of individual sleeves.  Each wire marker shall indicate the device or equipment, including specific terminal 
number to which the remote end of the wire is attached.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.14   Grounding and Bonding</TTL><BRK/>
<BRK/>
<TXT>Provide as specified in Section[ <SRF>33 71 02.00 20</SRF> UNDERGROUND UNDERGROUND TRANSMISSION AND DISTRIBUTION][ 
<SRF>33 70 02.00 10</SRF> UNDERGROUND TRANSMISSION AND DISTRIBUTION SYSTEM, UNDERGROUND].</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>2.2.15   Padlocks</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Designer must assure that Section 08 71 00 DOOR HARDWARE, is included 
and is edited to include padlocks.  Delete this paragraph if padlocks are not 
to be provided by the contractor.<BRK/>
<BRK/>
Do not use this paragraph for LANTNAVFACENGCOM projects unless there is a specific 
requirement.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Padlocks shall be provided for secondary unit substation equipment[ and for each fence gate].  Padlocks shall 
be keyed[ alike][ as directed by the Contracting Officer].  Padlocks shall comply with Section <SRF>08 71 00</SRF> DOOR 
HARDWARE.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>2.2.16   Cast-in-Place Concrete</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the first bracketed paragraph when project includes a concrete section 
in Division 3; otherwise, the second bracketed paragraph may be used.  Coordinate 
requirements with Section 03 31 00.00 10, CAST-IN-PLACE STRUCTURAL CONCRETE, 
Section 03 30 00 CAST-IN-PLACE CONCRETE.  Use the section appropriate for the 
specific agency.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Concrete associated with electrical work for other than encasement of underground ducts shall be<MET> 30 MPa</MET><ENG> 4000 
psi</ENG> minimum 28-day compressive strength unless specified otherwise.  All concrete shall conform to the requirements 
of Section[ <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE][ <SRF>03 31 00.00 10</SRF> CAST-IN-PLACE STRUCTURAL CONCRETE].]</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If concrete requirements are detailed and no cast-in-place concrete section 
is to be included in the project specification, refer to Section 03 31 00.00 
10, CAST-IN-PLACE STRUCTURAL CONCRETE, Section 03 30 00 CAST-IN-PLACE CONCRETE, 
and select such portions as needed to provide complete requirements in addition 
to the requirements below.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Shall be composed of fine aggregate, coarse aggregate, portland cement, and water so proportioned and mixed 
as to produce a plastic, workable mixture.  Fine aggregate shall be of hard, dense, durable, clean, and uncoated 
sand.  The coarse aggregate shall be reasonably well graded from<MET> 4.75 mm to 25 mm</MET><ENG> 3/16 inch to one inch</ENG>.  The 
fine and coarse aggregates shall be free from injurious amounts of dirt, vegetable matter, soft fragments or 
other deleterious substances.  Water shall be fresh, clean, and free from salts, alkali, organic matter, and 
other impurities.  Concrete associated with electrical work for other than encasement of underground ducts shall 
be<MET> 30 MPa</MET><ENG> 4000 psi</ENG> minimum 28-day compressive strength unless specified otherwise.  Slump shall not exceed<MET> 100 
mm</MET><ENG> 4 inches</ENG>.  Retempering of concrete will not be permitted.  Exposed, unformed concrete surfaces shall be given 
a smooth, wood float finish.  Concrete shall be cured for a period of not less than 7 days, and concrete made 
with high early strength portland cement shall be repaired by patching honeycombed or otherwise defective areas 
with cement mortar as directed by the Contracting Officer.  Air entrain concrete exposed to weather using an 
air-entraining admixture conforming to <RID>ASTM C 260</RID>.  Air content shall be between 4 and 6 percent.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3   MANUFACTURER'S NAMEPLATES</TTL><BRK/>
<BRK/>
<TXT>Each item of equipment shall have a nameplate bearing, as a minimum, the manufacturer's name, address, model 
number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent will 
not be acceptable.  Include additional information as applicable to fully identify the equipment.  Nameplates 
shall be made of noncorrosive metal.[  Equipment containing liquid dielectric shall include the type of dielectric 
on the nameplate.][  Sectionalizer switch nameplates shall have a schematic with all switch positions shown and 
labeled.]  As a minimum, provide nameplates for transformers, circuit breakers, meters, switches, and switchgear.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4   FIELD FABRICATED NAMEPLATES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the bracketed sentence to specify labels for secondary unit substations 
where emergency breakers are located within the secondary unit substations.  
Provide note on the drawings to indicate where red labels are required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASTM D 709</RID>.  Provide laminated plastic nameplates for each secondary unit substation, equipment enclosure, relay, 
switch, and device; as specified in this section or as indicated on the drawings.  Each nameplate inscription 
shall identify the function and, when applicable, the position.  Nameplates shall be melamine plastic,<MET> 3 mm</MET><ENG> 0.125 
inch</ENG> thick, white with [black][_____] center core.[  Provide red laminated plastic label with white center core 
where indicated.]  Surface shall be matte finish.  Corners shall be square.  Accurately align lettering and engrave 
into the core.  Minimum size of nameplates shall be<MET> 25 by 65 mm</MET><ENG> one by 2.5 inches</ENG>.  Lettering shall be a minimum 
of<MET> 6.35 mm</MET><ENG> 0.25 inch</ENG> high normal block style.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5   WARNING SIGNS</TTL><BRK/>
<BRK/>
<TXT>Provide warning signs for the enclosures of secondary unit substations having a nominal rating exceeding 600 
volts.</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  When the enclosure integrity of such equipment is specified to be in accordance with <RID>IEEE C57.12.29</RID>
, such as for secondary unit substations, provide self-adhesive warning signs on the outside 
of the high voltage compartment door(s).  Sign shall be a decal and shall have nominal dimensions 
of<MET> 178 by 255 mm</MET><ENG> 7 by 10 inches</ENG> with the legend "DANGER HIGH VOLTAGE" printed in two lines of 
nominal<MET> 50 mm</MET><ENG> 2 inch</ENG> high letters.  The word "DANGER" shall be in white letters on a red background 
and the words "HIGH VOLTAGE" shall be in black letters on a white background.  Decal shall be 
Panduit No. PPSO710D72 or approved equal.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[b.  When such equipment is guarded by a fence, mount signs on the fence.  Provide metal signs 
having nominal dimensions of<MET> 355 by 255 mm</MET><ENG> 14 by 10 inches</ENG> with the legend "DANGER HIGH VOLTAGE 
KEEP OUT" printed in three lines of nominal<MET> 75 mm</MET><ENG> 3 inch</ENG> high white letters on a red and black 
field.]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6   SOURCE QUALITY CONTROL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use "reserves the right to" on all projects, except those for SOUTHNAVFACENGCOM.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.6.1   <SUB>Equipment Test Schedule</SUB></TTL><BRK/>
<BRK/>
<TXT>The Government [reserves the right to][will] witness tests.  Provide equipment test schedules for tests to be 
performed at the manufacturer's test facility.  Submit required test schedule and location, and notify the Contracting 
Officer 30 calendar days before scheduled test date.  Notify Contracting Officer 15 calendar days in advance 
of changes to scheduled date.</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Test Instrument Calibration</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  The manufacturer shall have a calibration program which assures that all applicable test 
instruments are maintained within rated accuracy.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  The accuracy shall be directly traceable to the National Institute of Standards and Technology.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Instrument calibration frequency schedule shall not exceed 12 months for both test floor 
instruments and leased specialty equipment.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Dated calibration labels shall be visible on all test equipment.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Calibrating standard shall be of higher accuracy than that of the instrument tested.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Keep up-to-date records that indicate dates and test results of instruments calibrated or 
tested.  For instruments calibrated by the manufacturer on a routine basis, in lieu of third 
party calibration, include the following:</ITM><BRK/>
<BRK/>
<ITM>(a)  Maintain up-to-date instrument calibration instructions and procedures for each test instrument.</ITM><BRK/>
<BRK/>
<ITM>(b)  Identify the third party/laboratory calibrated instrument to verify that calibrating standard 
is met.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6.2   <SUB>Load Interrupter Switch Production Tests</SUB></TTL><BRK/>
<BRK/>
<TXT><RID>IEEE C37.20.3</RID>.  Furnish reports of production tests performed on the actual equipment for this project.  Required 
tests shall be as follows:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Production Tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Dielectric</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Mechanical operation</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[3.  Grounding of instrument transformer case]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[4.  Electrical operation and control wiring]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6.3   <SUB>Transformer Design Tests (Liquid-Filled)</SUB></TTL><BRK/>
<BRK/>
<TXT>In accordance with <RID>IEEE C57.12.00</RID> and <RID>IEEE C57.12.90</RID>.  Additionally, <RID>IEEE C57.12.80</RID> section 5.1.2 states that 
"design tests are made only on representative apparatus of basically the same design."  Submit design test reports 
(complete with test data, explanations, formulas, and results), in the same submittal package as the product 
data and shop drawings for[ each of] the specified transformer[s]. Design tests shall have been performed prior 
to the award of this contract.</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Tests shall be certified and signed by a registered professional engineer.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Temperature rise:  "Basically the same design" for the temperature rise test means a unit-substation 
transformer with the same coil construction (such as wire wound primary and sheet wound secondary), the 
same kVA, the same cooling type (ONAN), the same temperature rise rating, and the same insulating liquid 
as the transformer specified.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Lightning impulse:  "Basically the same design" for the lightning impulse dielectric test means a 
unit-substation transformer with the same BIL, the same coil construction (such as wire wound primary 
and sheet wound secondary), and a tap changer, if specified.  Design lightning impulse tests shall include 
both the primary and secondary windings of that transformer.</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  <RID>IEEE C57.12.90</RID> paragraph 10.3 entitled "Lightning Impulse Test Procedures," and <RID>IEEE C57.98</RID>
.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  State test voltage levels.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Provide photographs of oscilloscope display waveforms or plots of digitized waveforms with 
test report.</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Lifting and moving devices:  "Basically the same design"  for the lifting and moving devices test 
means a transformer in the same weight range as the transformer specified.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Pressure:  "Basically the same design" for the pressure test means a unit-substation transformer 
with a tank volume within 30 percent of the tank volume of the transformer specified.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6.4   <SUB>Transformer Routine and Other Tests (Liquid-Filled)</SUB></TTL><BRK/>
<BRK/>
<TXT>In accordance with <RID>IEEE C57.12.00</RID> and <RID>IEEE C57.12.90</RID>.  Routine and other tests shall be performed by the manufacturer 
on[ each of] the actual transformer[s] prepared for this project to ensure that the design performance is maintained 
in production.  Submit test reports, by serial number and receive approval before delivery of equipment to the 
project site.  Required tests and testing sequence shall be as follows:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Cold resistance measurements (provide reference temperature)</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Phase relation</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Ratio</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Insulation power-factor by manufacturer's recommended test method.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  No-load losses (NLL) and excitation current</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Load losses (LL) and impedance voltage</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Dielectric</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Impulse:  Per <RID>IEEE C57.12.90</RID> paragraph 10.3 entitled "Lightning Impulse Test Procedures," 
and <RID>IEEE C57.98</RID>.  Test the primary winding only.</ITM><BRK/>
<BRK/>
<ITM>(a)  State test voltage levels</ITM><BRK/>
<BRK/>
<ITM>(b)  Provide photographs of oscilloscope display waveforms or plots of digitized waveforms with 
test reports.[  As an alternative, photographs of oscilloscope display waveforms or plots of 
digitized waveforms may be hand-delivered at the factory witness test.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Applied voltage</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Induced voltage</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">h.  Leak</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">i.  Sample insulating liquid.  Sample shall be tested for:</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Dielectric breakdown voltage</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Acid neutralization number</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Specific gravity</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Interfacial tension</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Color</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Visual condition</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">7.  Water in insulating liquid</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">8.  Measure dissipation factor or power factor</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">j.  Perform dissolved gas analysis (DGA)</LST><BRK/>
<BRK/></SPT>
<SPT>[<TTL>2.6.5   Transformer <SUB>Design Tests (Dry-Type)</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the paragraphs on Dry-Type Transformers when Liquid-Filled Transformers 
are used.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>In accordance with <RID>IEEE C57.12.01</RID> and <RID>IEEE C57.12.91</RID>.  Additionally, <RID>IEEE C57.12.80</RID> section 5.1.2 states that 
"design tests are made only on representative apparatus of basically the same design."  Submit design test reports 
in the same submittal package as the product data, shop drawings, and certificates of transformer losses for[ 
each of] the specified transformer[s].  Design tests shall have been performed prior to the award of this contract.</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Provide required submittals in a hard-covered binder with index and tabs.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Tests shall be certified and signed by a registered professional engineer.  Engineers stamp and signature 
shall appear on at least the first page of the factory test reports.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Temperature rise:</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  "Basically the same design" for the temperature rise test means a unit-substation transformer 
with the same coil construction (such as wire wound primary and sheet wound secondary), the 
same kVA, the same cooling type (AA), the same temperature rise rating, the same insulating 
class and the same insulating medium as the transformer specified.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Provide temperature rise readings, formulas, calculations of average temperature rise, and 
description of test method.</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Lightning impulse:</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  "Basically the same design" for the lightning impulse dielectric test means a unit-substation 
transformer with the same BIL and the same coil construction (such as wire wound primary and 
sheet wound secondary).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  <RID>IEEE C57.12.91</RID> and <RID>IEEE C57.98</RID>.  Provide design lightning impulse tests consisting of a 
reduced full-wave, two-chopped waves, and one full wave test for each phase of the primary and 
secondary windings of the same transformer.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  State test voltage levels.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Provide photographs of oscilloscope display waveforms or plots of digitized waveforms with 
test report.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Partial Discharge Test per <RID>IEEE C57.124</RID>.  Provide transformer ratings, description and diagram 
of test method used, test readings and final results.</ITM><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.6.6   Transformer <SUB>Routine and Other Tests (Dry-Type)</SUB></TTL><BRK/>
<BRK/>
<TXT>In accordance with <RID>IEEE C57.12.01</RID> and <RID>IEEE C57.12.91</RID>.  Routine and other tests shall be performed by the manufacturer 
on[ each of] the actual transformer[s] prepared for this project to ensure that the design performance is maintained 
in production.  Submit test reports, by serial number and receive approval before delivery of equipment to the 
project site.  Required tests and testing sequence shall be as follows:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Resistance measurements</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Phase relation</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Ratio</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Insulation power-factor by manufacturer's recommended test method.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  No-load losses (NLL) and excitation current</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Load losses (LL) and impedance voltage</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Lightning impulse:  Perform the complete design type impulse tests on the transformer primary winding 
only.</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  <RID>IEEE C57.12.91</RID> and <RID>IEEE C57.98</RID></ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  State test voltage levels</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Provide photographs of oscilloscope display waveforms or plots of digitized waveforms with 
test reports.[  As an alternative, photographs of oscilloscope display waveforms or plots of 
digitized waveforms may be hand delivered at the factory witness test.]</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">h.  Low frequency dielectric</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Applied voltage</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Induced voltage</ITM><BRK/>
<BRK/>
]</SPT></SPT></PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   INSTALLATION</TTL><BRK/>
<BRK/>
<TXT>Electrical installations shall conform to <RID>IEEE C2</RID>, <RID>NFPA 70</RID>, and to the requirements specified herein.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2   GROUNDING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Where rock or other soil conditions prevent obtaining a specified ground 
value, specify other methods of grounding.  Where it is impractical to obtain 
the indicated ground resistance values, make every effort to obtain ground resistance 
values as near as possible to the indicated values.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>NFPA 70</RID> and <RID>IEEE C2</RID>, except that grounds and grounding systems shall have a resistance to solid earth ground 
not exceeding 5 ohms.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.2.1   Grounding Electrodes</TTL><BRK/>
<BRK/>
<TXT>Provide driven ground rods as specified in Section[ <SRF>33 71 02.00 20</SRF> UNDERGROUND UNDERGROUND TRANSMISSION AND DISTRIBUTION][ 
<SRF>33 70 02.00 10</SRF> UNDERGROUND TRANSMISSION AND DISTRIBUTION SYSTEM, UNDERGROUND].   Connect ground conductors to 
the upper end of the ground rods by exothermic weld or compression connector.  Provide compression connectors 
at equipment end of ground conductors.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.2   Substation Grounding</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Where the rated secondary current exceeds 400 amperes, increase the size 
of the substation transformer neutral ground connection to not less than 12.5 
percent of the cross-sectional area of the secondary phase conductors.  Provide 
a "detail" for surge arrester grounding.  For ungrounded and single-grounded 
systems, modify paragraph in accordance with IEEE C2.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide bare copper cable not smaller than No. 4/0 AWG not less than<MET> 610 mm</MET><ENG> 24 inches</ENG> below grade interconnecting 
the indicated ground rods.  Surge arrester and neutrals shall be bonded directly to the transformer enclosure 
and then to the grounding electrode system with bare copper conductors, sized as shown.  Lead lengths shall be 
kept as short as practicable with no kinks or sharp bends.  Substation transformer neutral connections shall 
not be smaller than No. 1/0 AWG.  When work in addition to that indicated or specified is directed to obtain 
the specified ground resistance, the provision of the contract covering "Changes" shall apply.[  Fence and equipment 
connections shall not be smaller than No. 4 AWG.  Ground fence at each gate post and cornerpost and at intervals 
not exceeding<MET> 3050 mm</MET><ENG> 10 feet</ENG>.  Bond each gate section to the fence post through a<MET> 3 by 25 mm (1/8 by one inch)</MET><ENG>
 1/8 by one inch</ENG> flexible braided copper strap and clamps.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.3   Connections</TTL><BRK/>
<BRK/>
<TXT>Make joints in grounding conductors and loops by exothermic weld or compression connector.  Exothermic welds 
and compression connectors shall be installed as specified in Section[ <SRF>33 71 02.00 20</SRF> UNDERGROUND UNDERGROUND 
TRANSMISSION AND DISTRIBUTION, paragraph entitled "Grounding"][ <SRF>33 70 02.00 10</SRF> UNDERGROUND UNDERGROUND TRANSMISSION 
AND DISTRIBUTION, paragraph entitled "Grounding"].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.4   Grounding and Bonding Equipment</TTL><BRK/>
<BRK/>
<TXT><RID>UL 467</RID>, except as indicated or specified otherwise.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.3   INSTALLATION OF EQUIPMENT AND ASSEMBLIES</TTL><BRK/>
<BRK/>
<TXT>Install and connect unit substations furnished under this section as indicated on project drawings, the approved 
shop drawings, and as specified herein.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Interrupter Switchgear</TTL><BRK/>
<BRK/>
<TXT><RID>IEEE C37.20.3</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>3.3.2   Meters and Instrument Transformers</TTL><BRK/>
<BRK/>
<TXT><RID>NEMA C12.1</RID>.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.3.3   Field Applied Painting</TTL><BRK/>
<BRK/>
<TXT>Where field applied painting of enclosures is required to correct damage to the manufacturer's factory applied 
coatings, provide manufacturer's recommended coatings and apply in accordance with manufacturer's instructions.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.4   Field Fabricated Nameplate Mounting</TTL><BRK/>
<BRK/>
<TXT>Provide number, location, and letter designation of nameplates as indicated.  Fasten nameplates to the device 
with a minimum of two sheet-metal screws or two rivets.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.5   Warning Sign Mounting</TTL><BRK/>
<BRK/>
<TXT>Provide the number of signs required to be readable from each accessible side, but space the signs a maximum 
of<MET> 9 meters</MET><ENG> 30 feet</ENG> apart.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>3.3.6   Galvanizing Repair</TTL><BRK/>
<BRK/>
<TXT>Repair damage to galvanized coatings using <RID>ASTM A 780</RID>, zinc rich paint, for galvanizing damaged by handling, 
transporting, cutting, welding, or bolting.  Do not heat surfaces that repair paint has been applied to.</TXT><BRK/>
<BRK/>
]</SPT></SPT><SPT><TTL>3.4   FOUNDATION FOR EQUIPMENT AND ASSEMBLIES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Mounting slab connections may have to be given in detail depending on 
the requirements for the seismic zone in which the equipment is located.   Include 
construction requirements for concrete slab only if slab is not detailed in 
drawings.  Curbs or raised edges may also be required around liquid filled transformer.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.4.1   Exterior Location</TTL><BRK/>
<BRK/>
<TXT>Mount unit substation on concrete slab.  Unless otherwise indicated, the slab shall be at least<MET> 200 mm</MET><ENG> 8 inches</ENG>
 thick, reinforced with a<MET> 152 x 152 - MW19 x MW19 (6 x 6 - W2.9 x W2.9)</MET><ENG> 6 x 6 - W2.9 x W2.9</ENG> mesh placed uniformly<MET>
 100 mm</MET><ENG> 4 inches</ENG> from the top of the slab.  Slab shall be placed on a<MET> 150 mm</MET><ENG> 6 inch</ENG> thick, well-compacted gravel 
base.  Top of concrete slab shall be approximately<MET> 100 mm</MET><ENG> 4  inches</ENG> above the finished grade.  Edges above grade 
shall have<MET> 15 mm</MET><ENG> 1/2 inch</ENG> chamfer.  The slab shall be of adequate size to project at least<MET> 200 mm</MET><ENG> 8 inches</ENG> beyond 
the equipment.  Provide conduit turnups and cable entrance space required by the equipment to be mounted.  Seal 
voids around conduit openings in slab with water- and oil-resistant caulking or sealant.  Seals shall be of sufficient 
strength and durability to protect all energized live parts of the equipment from rodents, insects, or other 
foreign matter.  Cut off and bush conduits<MET> 75 mm</MET><ENG> 3 inches</ENG> above slab surface.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2   Interior Location</TTL><BRK/>
<BRK/>
<TXT>Mount unit substation on concrete slab.  Unless otherwise indicated, the slab shall be at least<MET> 100 mm</MET><ENG> 4 inches</ENG>
 thick. The top of the concrete slab shall be approximately<MET> 100 mm</MET><ENG> 4 inches</ENG> above finished floor.  Edges above 
floor shall have<MET> 15 mm</MET><ENG> 1/2 inch</ENG> chamfer.  The slab shall be of adequate size to project at least<MET> 100 mm</MET><ENG> 4 inches</ENG>
 beyond the equipment.  Provide conduit turnups and cable entrance space required by the equipment to be mounted.  
Seal voids around conduit openings in slab with water- and oil-resistant caulking or sealant.  Seals shall be 
of sufficient strength and durability to protect all energized live parts of the equipment from rodents, insects, 
or other foreign matter.  Cut off and bush conduits<MET> 75 mm</MET><ENG> 3 inches</ENG> above slab surface.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.3   Cast-in-Place Concrete</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the first bracketed option when project includes a concrete section 
in Division 3; otherwise the second bracketed option may be used.  Choose Section 
03 30 00 for Navy and NASA projects, and Section 03 31 00.00 10 for Army and 
Air Force projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Cast-in-place concrete work shall conform to the requirements of[[ Section <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE][ 
Section <SRF>03 31 00.00 10</SRF> CAST-IN-PLACE STRUCTURAL CONCRETE]][ <RID>ACI 318M</RID>].</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT>[<TTL>3.5   Padlocks</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete this paragraph if padlocks are not to be provided by the contractor.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide padlocks for secondary unit substation equipment[ and for each fence gate].</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.6   FIELD QUALITY CONTROL</TTL><BRK/>
<BRK/>
<SPT><TTL>3.6.1   Performance of <SUB>Acceptance Checks and Tests</SUB></TTL><BRK/>
<BRK/>
<TXT><TST>Perform in accordance with the manufacturer's recommendations</TST> and include the following visual and mechanical 
inspections and electrical tests, performed in accordance with <RID>NETA ATS</RID>.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.6.1.1   Interrupter Switchgear (Air Switches)</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Visual and Mechanical Inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Compare equipment nameplate data with specifications and approved shop drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Inspect physical and mechanical condition.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Confirm correct application of manufacturer's recommended lubricants.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Verify appropriate anchorage and required area clearances.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Verify appropriate equipment grounding.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Verify correct blade alignment, blade penetration, travel stops, and mechanical operation.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[7.  Verify that fuse sizes and types correspond to approved shop drawings.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[8.  Verify that each fuse holder has adequate mechanical support.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">9.  Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, 
verifying tightness of accessible bolted electrical connections by calibrated torque-wrench 
method, or performing thermographic survey.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">10.  Test interlocking systems for correct operation and sequencing.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">11.  Verify correct phase barrier materials and installation.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">12.  Compare switch blade clearances with industry standards.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">13.  Inspect all indicating devices for correct operation</ITM> <BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Electrical Tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Perform insulation-resistance tests.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Perform over-potential tests.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Perform resistance measurements through all bolted connections with low-resistance ohmmeter, 
if applicable.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Measure closed contact-resistance across each switch blade[ and fuse holder].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[5.  Measure fuse resistance.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Verify heater operation.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.1.2   Transformers (Liquid-Filled)</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Visual and mechanical inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Compare equipment nameplate data with specifications and approved shop drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Inspect physical and mechanical condition.  Check for damaged or cracked insulators and 
leaks.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[3.  Verify that cooling fans and pumps operate correctly and that fan and pump motors have 
correct overcurrent protection.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[4.  Verify operation of all alarm, control, and trip circuits from temperature and level indicators, 
pressure relief device, and fault pressure relay.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, 
verifying tightness of accessible bolted electrical connections by calibrated torque-wrench 
method, or performing thermographic survey.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Verify correct liquid level in transformer tank.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">7.  Perform specific inspections and mechanical tests as recommended by manufacturer.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">8.  Verify correct equipment grounding.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">9.  Verify the presence of transformer surge arresters.</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Electrical Tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Perform resistance measurements through all bolted connections with low-resistance ohmmeter, 
if applicable.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Perform dissolved gas analysis (DGA).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Verify that the tap-changer is set at specified ratio.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Verify proper secondary voltage phase-to-phase and phase-to-neutral after energization and 
prior to loading.</ITM><BRK/>
<BRK/></SPT>
<SPT>[<TTL>3.6.1.3   Transformers - (Dry-Type)</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Visual and Mechanical Inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Compare equipment nameplate information with specifications and approved shop drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Inspect physical and mechanical condition.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Verify that control and alarm settings on temperature indicators are as specified.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Verify that cooling fans operate correctly and that fan motors have correct overcurrent 
protection.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, 
verifying tightness of accessible bolted electrical connections by calibrated torque-wrench 
method, or performing thermographic survey.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Perform specific inspections and mechanical tests as recommended by manufacturer.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">7.  Verify that resilient mounts are free and shipping brackets have been removed.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">8.  Verify that winding core, frame, and enclosure groundings are correct.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">9.  Verify the presence of transformer surge arresters.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">10.  Verify that as-left tap connections are as specified.</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">b. Electrical Tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Perform insulation-resistance tests.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Perform power-factor tests or dissipation-factor tests in accordance with the test equipment 
manufacturer's instructions.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Perform resistance measurements through all bolted connections with low-resistance ohmmeter, 
if applicable.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Perform turns-ratio tests.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Perform  overpotential test on all high- and low-voltage windings-to-ground.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Verify correct secondary voltage phase-to-phase and phase-to-neutral after energization 
and prior to loading.</ITM><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.6.1.4   Current Transformers</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Visual and Mechanical Inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Compare equipment nameplate data with specifications and approved shop drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Inspect physical and mechanical condition.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Verify correct connection.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Verify that adequate clearances exist between primary and secondary circuit.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, 
verifying tightness of accessible bolted electrical connections by calibrated torque-wrench 
method, or performing thermographic survey.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Verify that all required grounding and shorting connections provide good contact.</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Electrical Tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Perform resistance measurements through all bolted connections with low-resistance ohmmeter, 
if applicable.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Perform insulation-resistance tests.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Perform polarity tests.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Perform ratio-verification tests.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.1.5   Metering and Instrumentation</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Visual and Mechanical Inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Compare equipment nameplate data with specifications and approved shop drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Inspect physical and mechanical condition.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Verify tightness of electrical connections.</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Electrical Tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Verify accuracy of meters at 25, 50, 75, and 100 percent of full scale.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Calibrate watthour meters according to manufacturer's published data.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Verify all instrument multipliers.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Verify that current transformer[ and voltage transformer] secondary circuits are intact.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.1.6   Grounding System</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Visual and Mechanical Inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Inspect ground system for compliance with contract plans and specifications.</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Electrical Tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Perform ground-impedance measurements utilizing the fall-of-potential method.  On systems 
consisting of interconnected ground rods, perform tests after interconnections are complete.  
On systems consisting of a single ground rod perform tests before any wire is connected.  Take 
measurements in normally dry weather, not less than 48 hours after rainfall.  Use a portable 
ground testing megger in accordance with manufacturer's  instructions to test each ground or 
group of grounds.  The instrument shall be equipped with a meter reading directly in ohms or 
fractions thereof to indicate the ground value of the ground rod or grounding systems under 
test.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Submit the measured ground resistance of each ground rod or grounding system, indicating 
the location of the rod or grounding system.  Include the test method and test setup (i.e., 
pin location) used to determine ground resistance and soil conditions at the time the measurements 
were made.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT>[<TTL>3.6.2   Protective Relays</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Do not use this paragraph for NAVY projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Protective relays shall be visually and mechanically inspected, adjusted, tested, and calibrated in accordance 
with the manufacturer's published instructions.  Tests shall include pick-up, timing, contact action, restraint, 
and other aspects necessary to ensure proper calibration and operation.  Relay settings shall be implemented 
as directed by the Contracting Officer.  Relay contacts shall be manually or electrically operated to verify 
that the proper breakers and alarms initiate.  Relaying current transformers shall be field tested in accordance 
with <RID>IEEE C57.13</RID>.</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>3.6.3   Pre-Energization Services</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Do not use this paragraph for NAVY projects or projects where Section 
26 08 00 APPARATUS INSPECTION AND TESTING is included.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Calibration, testing, adjustment, and placing into service of the installation shall be accomplished by a manufacturer's 
product field service engineer or independent testing company with a minimum of 2 years of current product experience.  
The following services shall be performed subsequent to testing but prior to the initial energization.  The equipment 
shall be inspected to ensure that installation is in compliance with the recommendations of the manufacturer 
and as shown on the detail drawings.  Terminations of conductors at major equipment shall be inspected to ensure 
the adequacy of connections.  Bare and insulated conductors between such terminations shall be inspected to detect 
possible damage during installation.  If factory tests were not performed on completed assemblies, tests shall 
be performed after the installation of completed assemblies.  Components shall be inspected for damage caused 
during installation or shipment to ensure packaging materials have been removed.  Components capable of being 
both manually and electrically operated shall be operated manually prior to the first electrical operation.  
Components capable of being calibrated, adjusted, and tested shall be calibrated, adjusted, and tested in accordance 
with the instructions of the equipment manufacturer.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.6.4   Follow-Up Verification</TTL><BRK/>
<BRK/>
<TXT><TST>Upon completion of acceptance checks, settings, and tests, the Contractor shall show by demonstration in service 
that circuits and devices are in good operating condition and properly performing the intended function.</TST>  <TST>Test 
shall require each item to perform its function not less than three times.</TST>  As an exception to requirements stated 
elsewhere in the contract, the Contracting Officer shall be given 5 working days' advance notice of the dates 
and times for checks, settings, and tests.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT>    <END/><BRK/></SEC>