<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><BRK/>
<HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA                UFGS-32 12 10 (August 2008)<BRK/>
                                              ---------------------------<BRK/>
Preparing Activity:  <PRA>USACE</PRA>                    Superseding<BRK/>
                                              UFGS-32 12 10 (October 2006)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 32 12 10</SCN><BRK/>
<BRK/>
<STL>BITUMINOUS TACK AND PRIME COATS</STL><BRK/>
<DTE>08/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>bituminous tack 
and prime coats for airfield pavements, roads, parking areas and general paving 
needs</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   UNIT PRICES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete unit price paragraphs when lump sum bidding is used.  Edit submittal 
requirements accordingly.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1.1   Measurement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  When the bituminous material is measured in liters (gallons), the appropriate 
ASTM method will be retained for the type of bituminous material specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The bituminous material paid for will be the measured quantities used in the accepted work, provided that the 
measured quantities are not 10 percent over the specified application rate.  Any amount of bituminous material 
more than 10 percent over the specified application rate for each application will be deducted from the measured 
quantities, except for irregular areas where hand spraying of the bituminous material is necessary.  Express 
measured quantities in [<MET>metric tons</MET><ENG> 2000 pound tons</ENG>] [<MET>liters at 15.6 degrees C</MET><ENG> gallons at 60 degrees F</ENG>.  Volumes 
measured at temperatures other than<MET> 15.6 degrees C</MET><ENG> 60 degrees F</ENG> shall be corrected [in accordance with <RID>ASTM D 1250</RID>
] [using a coefficient of expansion of<MET> 0.00045 per degree C</MET><ENG> 0.00025 per degree F</ENG> for asphalt emulsion]].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.1.2   Payment</TTL><BRK/>
<BRK/>
<TXT>The quantities of bituminous material, determined as specified above, will be paid for at the respective contract 
unit prices.  Payment shall constitute full compensation for all operations necessary to complete the work as 
specified herein.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.1.3   <SUB>Waybills and Delivery Tickets</SUB></TTL><BRK/>
<BRK/>
<TXT>Before the final statement is allowed, file with the Contracting Officer certified waybills and certified delivery 
tickets for all bituminous materials used in the construction of the pavement covered by the contract.  These 
submittals are required for Unit Pricing bid only.  Do not remove bituminous material from storage until the 
initial outage and temperature measurements have been taken.  The delivery or storage units will not be released 
until the final outage has been taken.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.2   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification.  The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
<BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
<BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)</ORG><BRK/><BRK/><RID>AASHTO M 20</RID><RTL>(1970; R 2004) Penetration-Graded Asphalt Cement</RTL><BRK/><BRK/><RID>AASHTO M 226</RID><RTL>(1980; R 2004) Viscosity Graded Asphalt Cement</RTL><BRK/><BRK/><RID>AASHTO M 81</RID><RTL>(1992; R 2004) Cut-Back Asphalt (Rapid-Curing Type)</RTL><BRK/><BRK/><RID>AASHTO M 82</RID><RTL>(1975; R 2004) Cut-Back Asphalt (Medium-Curing Type)</RTL><BRK/><BRK/><RID>AASHTO T 102</RID><RTL>(1983; R 2004) Spot Test of Asphaltic Materials</RTL><BRK/><BRK/><RID>AASHTO T 40</RID><RTL>(2002; R 2006) Sampling Bituminous Materials</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM D 1250</RID><RTL>(2007) Standard Guide for Use of the Petroleum Measurement Tables</RTL><BRK/><BRK/><RID>ASTM D 140</RID><RTL>(2001; R 2007) Sampling Bituminous Materials</RTL><BRK/><BRK/><RID>ASTM D 2026</RID><RTL>(1997; R 2004) Cutback Asphalt (Slow-Curing Type)</RTL><BRK/><BRK/><RID>ASTM D 2027</RID><RTL>(1997; R 2004) Cutback Asphalt (Medium-Curing Type)</RTL><BRK/><BRK/><RID>ASTM D 2028</RID><RTL>(1997; R 2004) Cutback Asphalt (Rapid-Curing Type)</RTL><BRK/><BRK/><RID>ASTM D 2397</RID><RTL>(2005) Standard Specification for Cationic Emulsified Asphalt</RTL><BRK/><BRK/><RID>ASTM D 2995</RID><RTL>(1999; R 2004) Determining Application Rate of Bituminous Distributors</RTL><BRK/><BRK/><RID>ASTM D 3381</RID><RTL>(2005) Viscosity-Graded Asphalt Cement for Use in Pavement Construction</RTL><BRK/><BRK/><RID>ASTM D 946</RID><RTL>(1982; R 2005) Penetration-Graded Asphalt Cement for Use in Pavement Construction</RTL><BRK/><BRK/><RID>ASTM D 977</RID><RTL>(2005) Emulsified Asphalt</RTL><BRK/><BRK/></REF><REF><ORG>U.S. GREEN BUILDING COUNCIL (USGBC)</ORG><BRK/><BRK/><RID>LEED</RID><RTL>(2002; R 2005) Leadership in Energy and Environmental Design(tm) Green Building Rating System for New Construction (LEED-NC)</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.3   SYSTEM DESCRIPTION</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1   General Requirements</TTL><BRK/>
<BRK/>
<TXT>Plant, equipment, machines and tools used in the work are subject to approval and shall be maintained in a satisfactory 
working condition at all times.  Calibrated equipment such as asphalt distributors, scales, batching equipment, 
spreaders and similar equipment, should have been recalibrated by a calibration laboratory within [12] [_____] 
months prior to commencing work [and every [_____] months thereafter, by such laboratory from the date of recalibration, 
during the term of the contract].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2   Bituminous Distributor</TTL><BRK/>
<BRK/>
<TXT>Provide a distributor with pneumatic tires of such size and number that the load produced on the base surface 
does not exceed<MET> 295 kg/25 mm</MET><ENG> 650 psi</ENG> of tire width to prevent rutting, shoving or otherwise damaging the base 
surface or other layers in the pavement structure.  Design and equip the distributor to spray the bituminous 
material in a uniform coverage at the specified temperature, at readily determined and controlled rates from<MET> 
0.23 to 9.05 L/square meter</MET><ENG> 0.05 to 2.0 gallons per square yard</ENG>, with a pressure range of<MET> 172.4 to 517.1 kPa</MET><ENG> 
25 to 75 psi</ENG> and with an allowable variation from the specified rate of not more than plus or minus 5 percent, 
and at variable widths.  Include with the distributor equipment a separate power unit for the bitumen pump, full-circulation 
spray bars, tachometer, pressure gauges, volume-measuring devices, adequate heaters for heating of materials 
to the proper application temperature, a thermometer for reading the temperature of tank contents, and a hand 
hose attachment suitable for applying bituminous material manually to areas inaccessible to the distributor.  
Equip the distributor to circulate and agitate the bituminous material during the heating process.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.3   Heating Equipment for Storage Tanks</TTL><BRK/>
<BRK/>
<TXT>The equipment for heating the bituminous material shall be steam, electric, or hot oil heaters.  Provide steam 
heaters consisting of steam coils and equipment for producing steam, so designed that the steam cannot get into 
the material.  Fix an armored thermometer to the tank with a temperature range from<MET> 4.4 to 204.4 degrees C</MET><ENG> 40 
to 400 degrees F</ENG> so that the temperature of the bituminous material may be determined at all times.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.4   Power Brooms and Power Blowers</TTL><BRK/>
<BRK/>
<TXT>Use power brooms and power blowers suitable for cleaning the surfaces to which the bituminous coat is to be applied.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section <SRF>01 33 00</SRF> SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.</NPR><BRK/>
<BRK/>
<NPR>For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy, Air Force, 
and NASA projects. projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for [Contractor Quality Control approval.] [information only.  When used, a designation following the "G" 
designation identifies the office that will review the submittal for the Government.]  Submit the following in 
accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Waybills and Delivery Tickets</SUB></ITM><BRK/>
<BRK/>
<ITM>  Waybills and delivery tickets, during progress of the work.</ITM><BRK/>
<BRK/>
[<ITM><SUB>Local/Regional Materials</SUB></ITM><BRK/>
<BRK/>
<ITM>  Documentation indicating distance between manufacturing facility and the project site.  Indicate 
distance of raw material origin from the project site.  Indicate relative dollar value of local/regional 
materials to total dollar value of products included in project in accordance with <RID>LEED</RID>.</ITM>]<BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Sampling and Testing</SUB></ITM><BRK/>
<BRK/>
<ITM>  Copies of all test results for emulsified asphalt, and bituminous materials, within 24 hours 
of completion of tests.  Certified copies of the manufacturer's test reports indicating temperature 
viscosity relationship for cutback asphalt, compliance with applicable specified requirements, 
not less than [30] [_____] days before the material is required in the work.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5   QUALITY ASSURANCE</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Using local materials can help minimize transportation impacts, including 
fossil fuel consumption, air pollution, and labor.  Using materials harvested 
and manufactured within a 800 km (500 mile) radius from the project site contributes 
to the following LEED credit: MR5.  Coordinate with Section <SRF>01 33 29</SRF> LEED(tm) 
DOCUMENTATION.  Use second option if Contractor is choosing local materials 
in accordance with Section <SRF>01 33 29</SRF> LEED(tm) DOCUMENTATION.  Use second option 
for USACE projects.  Army projects should include option, only if pursuing this 
LEED credit.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Use <SUB>Local/Regional Materials</SUB> or products extracted, harvested, or recovered, as well as manufactured, within 
a<MET> [800][_____] km</MET><ENG> [500][_____] mile</ENG> radius from the project site, if available from a minimum of three sources.][See 
Section <SRF>01 33 29</SRF> LEED(tm) DOCUMENTATION for cumulative total local material requirements.  Tack and prime coat 
materials may be locally available.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6   DELIVERY, STORAGE, AND HANDLING</TTL><BRK/>
<BRK/>
<TXT>Inspect the materials delivered to the site for contamination and damage.  Unload and store the materials with 
a minimum of handling.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7   ENVIRONMENTAL REQUIREMENTS</TTL><BRK/>
<BRK/>
<TXT>Apply bituminous coat only when the surface to receive the bituminous coat is dry.  Apply bituminous coat only 
when the atmospheric temperature in the shade is<MET> 10 degrees C</MET><ENG> 50 degrees F</ENG> or above and when the temperature 
has not been below<MET> 2 degrees C</MET><ENG> 35 degrees F</ENG> for the 12 hours prior to application, unless otherwise directed.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   PRIME COAT</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Remove brackets from around the material to be allowed in the contract 
specifications and delete the other materials and references.</NPR><BRK/>
<BRK/>
<NPR>a.  With growing environmental/safety regulations, more and more states are 
prohibiting the use of cutback asphalts in favor of emulsified asphalt materials.  
If cutback asphalts are used, one of the following types and grades can be recommended:</NPR><BRK/>
<BRK/>
<NPR>Slow-Curing Type (ASTM D 2026):  SC-70, SC-250.</NPR><BRK/>
<BRK/>
<NPR>Medium-Curing Type (ASTM D 2027 or AASHTO M 82): MC-30, MC-70, MC-250.</NPR><BRK/>
<BRK/>
<NPR>Rapid-Curing Type (ASTM D 2028 or AASHTO M 81): RC-70, RC-250.</NPR><BRK/>
<BRK/>
<NPR>Selection of a particular type and grade should consider the nature of the surface 
to be treated.  An open base course material will be penetrated readily, and 
all of the above types and grades can be considered except for the low viscosity 
MC-30.  A tight surface is not going to be penetrated as readily; therefore, 
the less viscous materials are recommended such as RC-70, MC-30, MC-70 and SC-70.  
Some caution might be urged in using RC-70 or RC-250 because the solvent may 
separate or be absorbed by the base course fines and leave the asphalt deposited 
on the surface.  Cutback asphalts can be used in cold-weather construction with 
less concern than emulsions which contain water.  Less viscous grades may be 
used for cold-weather construction such as RC-70, MC-30 and MC-70.</NPR><BRK/>
<BRK/>
<NPR>b.  There are two types of emulsions that can be used for prime coats.  A list 
of recommended emulsion grades by type is as follows:</NPR><BRK/>
<BRK/>
<NPR>Anionic Emulsions ASTM D 977:  SS-1, SS-1h.</NPR><BRK/>
<BRK/>
<NPR>Cationic Emulsions ASTM D 2397:  CSS-1, CSS-1h.</NPR><BRK/>
<BRK/>
<NPR>Penetration and coating will be most efficient at about optimum moisture content.  
Water dilution of the emulsion is also required to reduce viscosity.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide asphalt conforming to [<RID>AASHTO M 81</RID>] [<RID>AASHTO M 82</RID>], Grade [_____] and specified in the following two subparagraphs.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.1.1   Cutback Asphalt</TTL><BRK/>
<BRK/>
<TXT>Provide cutback asphalt conforming to [<RID>ASTM D 2026</RID>, Grade SC-70] [<RID>ASTM D 2027</RID>, Grade [MC-30] [MC-70]] [<RID>ASTM D 2028</RID>
, Grade RC-70].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.2   Emulsified Asphalt</TTL><BRK/>
<BRK/>
<TXT>Provide emulsified asphalt conforming to [<RID>ASTM D 977</RID>, Type [SS-1] [SS1h]] [<RID>ASTM D 2397</RID>, Type [CSS-1] [CSS-1h]].</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2   TACK COAT</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Tack coat prevents water from penetrating pavement and should not be 
used in pervious pavement systems.  When a pervious pavement system is specified, 
delete all references to tack coat in this section.</NPR><BRK/>
<BRK/>
<NPR>Emulsified asphalt grades listed are suitable for normal tack coat applications.  
The following considerations should be included in the evaluation of alternate 
grades to be specified for the project:</NPR><BRK/>
<BRK/>
<NPR>a.  Local practice as well as availability and cost of various grades within 
the area.</NPR><BRK/>
<BRK/>
<NPR>b.  The advantage of the SS grade over the RS grades is that they can be diluted 
with water while dilution of the RS grades is more difficult.  Dilution of the 
emulsified asphalt with water normally provides good coverage and economy, adequate 
bond, with less chance of leaving surplus asphalt.  Where a rapid-setting emulsion 
is required, consider use of RS-1 and CRS-1.</NPR><BRK/>
<BRK/>
<NPR>c.  Anionic emulsions such as SS-1 provide better adhesion to basic aggregates 
such as limestone, while cationic emulsions such as CSS-1 are better with acidic 
aggregates such as silicates.  For the majority of applications, the two types 
will perform equally as well as a tack coat.</NPR><BRK/>
<BRK/>
<NPR>d.  In warmer climates, consider the use of "h" grade emulsions with a harder 
base asphalt and lower penetration such as SS-1h and CSS-1h.</NPR><BRK/>
<BRK/>
<NPR>e.  If ASTM D 2028 or AASHTO M 81 is used, then Note A in TABLE 1 of ASTM D 
2028 or AASHTO M 82 should be reviewed and the material specified by viscosity 
or penetration.  Except for Navy projects, cutback asphalt grades recommended 
for tack are RC-70 and RC-250; they may be used generally as a tack in pavement 
construction.  In cold-weather construction, they can be used with less concern 
than emulsions which contain water.</NPR><BRK/>
<BRK/>
<NPR>f.  Paving grade asphalts can also be used in tack applications.  More heat 
is required to achieve spraying consistency for these materials.  Selection 
of a grade involves consideration of the various grading systems used.  The 
following materials are recommended:</NPR><BRK/>
<BRK/>
<HL4>Penetration Grades (ASTM D 946 or AASHTO M 20)</HL4><BRK/>
<NPR>------------------------------------------</NPR><BRK/>
<NPR>200-300</NPR><BRK/>
<NPR>120-150</NPR><BRK/>
<NPR>85-100</NPR><BRK/>
<BRK/>
<HL4>Viscosity Grades (ASTM D 3381 or AASHTO M 226, TABLE 1 or 2)</HL4><BRK/>
<NPR>-------------------------------------------------</NPR><BRK/>
<NPR>AC 2.5</NPR><BRK/>
<NPR>AC 5</NPR><BRK/>
<NPR>AC 10</NPR><BRK/>
<BRK/>
<HL4>Aged Residue Viscosity Grades (ASTM D 3381 or AASHTO M 226)</HL4><BRK/>
<NPR>-------------------------------------------------</NPR><BRK/>
<NPR>AR 1000</NPR><BRK/>
<NPR>AR 2000</NPR><BRK/>
<NPR>AR 4000</NPR><BRK/>
<BRK/>
<NPR>The harder grades, 85-100 penetration, AC 10, and AR 4000 viscosity grades, 
are recommended for airfields.  These grades are harder and would be better 
able to resist uplift pressures causes by jet engines.  The other grades may 
be considered for more general use.  The temperature-viscosity relation for 
the job asphalt should be checked to ensure that a spraying consistency can 
be achieved in the recommended temperature range of paragraph APPLICATION TEMPERATURE.</NPR><BRK/>
<BRK/>
<NPR>g.  Either anionic or cationic emulsions can be used for tack.  A list of recommended 
emulsions is as follows:</NPR><BRK/>
<BRK/>
<HL4>Anionic Emulsion ASTM D 977</HL4><BRK/>
<NPR>---------------------------------</NPR><BRK/>
<NPR>RS-1</NPR><BRK/>
<NPR>MS-1</NPR><BRK/>
<NPR>HFMS-1</NPR><BRK/>
<NPR>SS-1</NPR><BRK/>
<NPR>SS-1h</NPR><BRK/>
<BRK/>
<HL4>Cationic Emulsions ASTM D 2397</HL4><BRK/>
<NPR>----------------------------------</NPR><BRK/>
<NPR>CRS-1</NPR><BRK/>
<NPR>CSS-1</NPR><BRK/>
<NPR>CSS-1h</NPR><BRK/>
<BRK/>
<NPR>Grades SS-1h and CSS-1h are made with a harder base asphalt and are recommended 
for airfields.  The other grades can be considered for general use. Grades RS-1, 
SS-1, and SS-1h are widely used tack materials.</NPR><BRK/>
<BRK/>
<NPR>h.  An asphalt-based tack or tar tack may be used between an asphalt and tar 
or tar-rubber concrete course, but a tar tack should be used between tar and 
tar-rubber concrete courses.  This specification must be altered for a tar tack 
coat.</NPR><BRK/>
<BRK/>
<NPR>i.  Emulsified asphalt mixing grades such as SS-1, SS-1h, CSS-1, and CSS-1h 
perform best when diluted with equal parts of water and applied at the rate 
of 0.23-0.68 liter of diluted emulsion per square meter (0.05-0.15 gallon of 
diluted emulsion per square yard).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide asphalt conforming to [<RID>ASTM D 2028</RID>] [<RID>ASTM D 946</RID>] [<RID>ASTM D 3381</RID>] [<RID>ASTM D 977</RID>] [<RID>ASTM D 2397</RID>] or [<RID>AASHTO M 81</RID>
] [<RID>AASHTO M 20</RID>] [<RID>AASHTO M 226</RID>] Grade [_____].</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Cutback Asphalt</TTL><BRK/>
<BRK/>
<TXT>Provide cutback asphalt conforming to [<RID>ASTM D 2026</RID>, Grade SC-70] [<RID>ASTM D 2027</RID>, Grade [MC-30] [MC-70]] [<RID>ASTM D 2028</RID>
, Grade RC-70].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2   Emulsified Asphalt</TTL><BRK/>
<BRK/>
<TXT>Provide emulsified asphalt conforming to [<RID>ASTM D 977</RID>, Type [SS-1] [SS1h]] [<RID>ASTM D 2397</RID>, Type [CSS-1] [CSS-1h]].  
Dilute the emulsified asphalt with equal parts of water.  The base asphalt used to manufacture the emulsion shall 
show a negative spot when tested in accordance with <RID>AASHTO T 102</RID> using standard naphtha.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   PREPARATION OF SURFACE</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If the surface to be treated requires repairs, the method of repairs 
and extent of work involved should be shown or described.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Immediately before applying the bituminous coat, remove all loose material, dirt, clay, or other objectionable 
material from the surface to be treated by means of a power broom or blower supplemented with hand brooms.  The 
surface shall be dry and clean at the time of treatment.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2   APPLICATION RATE</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The range of application rates for the bituminous materials is for the 
bituminous residue content and does not include water or solvents that are contained 
in emulsified or liquid bituminous materials.  The use of liquid or emulsified 
material requires that the application rates be corrected.  Any prescribed application 
should be corrected and divided into two applications 24 hours apart when necessary 
to avoid flowing off the surface because of grade or slope.</NPR><BRK/>
<BRK/>
<NPR>Emulsified asphalt mixing grades such as SS-1, SS-1h, CSS-1, and CSS-1h perform 
best when diluted with equal parts of water and applied at the rate of 0.23-0.68 
liter of diluted emulsion per square meter (0.05-0.15 gallon of diluted emulsion 
per square yard).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The exact quantities within the range specified, which may be varied to suit field conditions, will be determined 
by the Contracting Officer.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.2.1   Tack Coat</TTL><BRK/>
<BRK/>
<TXT>Apply bituminous material for the tack coat in quantities of not less than<MET> 0.20 L</MET><ENG> 0.05 gallon</ENG> nor more than<MET> 0.70 
L/square meter</MET><ENG> 0.15 gallon per square yard</ENG> of pavement surface.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.2   Prime Coat</TTL><BRK/>
<BRK/>
<TXT>Apply bituminous material for the prime coat in quantities of not less than<MET> 0.70 L</MET><ENG> 0.15 gallon</ENG> nor more than<MET> 
1.80 L/square meter</MET><ENG> 0.40 gallon per square yard</ENG> of pavement surface.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.3   APPLICATION TEMPERATURE</TTL><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Viscosity Relationship</TTL><BRK/>
<BRK/>
<TXT>Asphalt application temperature shall provide an application viscosity between 10 and 60 seconds, Saybolt Furol, 
or between<MET> 20 and 120 square mm/sec</MET><ENG> 20 and 120 centistokes</ENG>, kinematic.  Furnish the temperature viscosity relation 
to the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.2   Temperature Ranges</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Normal spray application temperatures are as follows.  Edit and coordinate 
materials with Part 2 PRODUCTS.  Remove brackets from the material to be allowed 
in the specification and delete the other materials in brackets.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The viscosity requirements determine the application temperature to be used.  The following is a normal range 
of application temperatures:</TXT><BRK/>
<MET><TBL><BRK/>
<HL4>Liquid Asphalts</HL4><BRK/>
                            -------------------<BRK/>
<BRK/>
                [SC-250                       75-132 degrees C]<BRK/>
                [MC-30                        29-87 degrees C]<BRK/>
                [MC-70                        50-107 degrees C]<BRK/>
                [MC-250                       75-132 degrees C]<BRK/>
                [RC-70                        50-90 degrees C*]<BRK/>
                [RC-250                       75-12 degrees C*]<BRK/>
<BRK/>
<HL4>Paving Grade Asphalts</HL4><BRK/>
                         -------------------------<BRK/>
<BRK/>
<HL4>Penetration Grades</HL4><BRK/>
                           ----------------------<BRK/>
<BRK/>
                [200-300                      plus 130 degrees C]<BRK/>
                [120-150                      plus 132 degrees C]<BRK/>
                [85-100                       plus 137 degrees C]<BRK/>
<BRK/>
<HL4>Viscosity Grades</HL4><BRK/>
                            --------------------<BRK/>
<BRK/>
                [AC 2.5                       plus 132 degrees C]<BRK/>
                [AC 5                         plus 137 degrees C]<BRK/>
                [AC 10                        plus 137 degrees C]<BRK/>
<BRK/>
                [AR 1000                      plus 135 degrees C]<BRK/>
                [AR 2000                      plus 140 degrees C]<BRK/>
                [AR 4000                      plus 143 degrees C]<BRK/>
<BRK/>
<HL4>Emulsions</HL4><BRK/>
                               -------------<BRK/>
<BRK/>
                   [RS-1                         20-60 degrees C]<BRK/>
                   [MS-1                         20-70 degrees C]<BRK/>
                   [HFMS-1                       20-70 degrees C]<BRK/>
                   [SS-1                         20-70 degrees C]<BRK/>
                   [SS-1h                        20-70 degrees C]<BRK/>
                   [CRS-1                        52-85 degrees C]<BRK/>
                   [CSS-1                        20-70 degrees C]<BRK/>
                   [CSS-1h                       20-70 degrees C]<BRK/></TBL>
</MET><ENG><TBL><BRK/>
<HL4>Liquid Asphalts</HL4><BRK/>
                            -------------------<BRK/>
<BRK/>
                [SC-70                        120-225 degrees F]<BRK/>
                [SC-250                       165-270 degrees F]<BRK/>
                [MC-30                         85-190 degrees F]<BRK/>
                [MC-70                        120-225 degrees F]<BRK/>
                [MC-250                       165-270 degrees F]<BRK/>
                [RC-70                        120-200 degrees F*]<BRK/>
                [RC-250                       165-250 degrees F*]<BRK/>
<BRK/>
<HL4>Paving Grade Asphalts</HL4><BRK/>
                         -------------------------<BRK/>
<BRK/>
<HL4>Penetration Grades</HL4><BRK/>
                           ----------------------<BRK/>
<BRK/>
                [200-300                      plus 265 degrees F]<BRK/>
                [120-150                      plus 270 degrees F]<BRK/>
                [85-100                       plus 280 degrees F]<BRK/>
<BRK/>
<HL4>Viscosity Grades</HL4><BRK/>
                            --------------------<BRK/>
<BRK/>
                [AC 2.5                       plus 270 degrees F]<BRK/>
                [AC 5                         plus 280 degrees F]<BRK/>
                [AC 10                        plus 280 degrees F]<BRK/>
<BRK/>
                [AR 1000                      plus 275 degrees F]<BRK/>
                [AR 2000                      plus 285 degrees F]<BRK/>
                [AR 4000                      plus 290 degrees F]<BRK/>
<BRK/>
<HL4>Emulsions</HL4><BRK/>
                              -------------<BRK/>
                [RS-1                         70-140 degrees F]<BRK/>
                [MS-1                         70-160 degrees F]<BRK/>
                [HFMS-1                       70-160 degrees F]<BRK/>
                [SS-1                         70-160 degrees F]<BRK/>
                [SS-1h                        70-160 degrees F]<BRK/>
                [CRS-1                       125-185 degrees F]<BRK/>
                [CSS-1                        70-160 degrees F]<BRK/>
                [CSS-1h                       70-160 degrees F]</TBL></ENG><BRK/>
<BRK/>
<TXT>These temperature ranges exceed the flash point of the material and care should be taken in their heating.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.4   APPLICATION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Prime coats are required for Navy projects.  If the designer for Army 
jobs chooses not to specify a prime coat at the time of design, delete all references 
to a prime coat within this section.  If the drainage layer is used beneath 
the surfacing material (Asphalt cement hot mix concrete), the underlying material 
(base course) will not be primed and the appropriate paragraphs dealing with 
the prime coat will be deleted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.4.1   General</TTL><BRK/>
<BRK/>
<TXT>Following preparation and subsequent inspection of the surface, apply the bituminous prime or tack coat with 
the Bituminous Distributor at the specified rate with uniform distribution over the surface to be treated.  Properly 
treat all areas and spots missed by the distributor with the hand spray.  Until the succeeding layer of pavement 
is placed, maintain the surface by protecting the surface against damage and by repairing deficient areas at 
no additional cost to the Government.  If required, spread clean dry sand to effectively blot up any excess bituminous 
material.  No smoking, fires, or flames other than those from the heaters that are a part of the equipment are 
permitted within<MET> 8 meters</MET><ENG> 25 feet</ENG> of heating, distributing, and transferring operations of bituminous material 
other than bituminous emulsions.  Prevent all traffic, except for paving equipment used in constructing the surfacing, 
from using the underlying material, whether primed or not, until the surfacing is completed. The bituminous coat 
shall conform to all requirements as described herein.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2   Prime Coat</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Conditions where a prime coat may be beneficial include: preventing lateral 
movement of the unbound base during pavement construction, waterproofing during 
pavement construction, and forming a tight base to which the asphalt pavement 
will adhere.  To specify the application of a prime coat, retain the first bracketed  
sentence and deleted the text within the second set of brackets.  Add prime 
coat details on drawings.</NPR><BRK/>
<BRK/>
<NPR>If the prime coat will be retained as a Contractor's option, delete the first 
sentence and retain the bracketed text in the second set of brackets.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Apply a prime coat at locations shown on the Drawings.] [The prime coat is required if it will be at least [7] 
[_____] days before the surfacing (Asphalt cement hot mix concrete) layer is constructed on the underlying (base 
course, etc.) compacted material.  The type of liquid asphalt and application rate will be as specified herein.  
Protect the underlying from any damage (water, traffic, etc.) until the surfacing is placed.  If the Contractor 
places the surfacing within seven days, the choice of protection measures or actions to be taken is at the Contractor's 
option.  Repair (recompact or replace) damage to the underlying material caused by lack of, or inadequate, protection 
by approved methods at no additional cost to the Government.  If the Contractor opts to use the prime coat, apply 
as soon as possible after consolidation of the underlying material.] Apply the bituminous material uniformly 
over the surface to be treated at a pressure range of<MET> 172.4 to 517.1 kPa</MET><ENG> 25 to 75 psi</ENG> and at the rate of not 
less than<MET> [0.91] [_____] L not more than [1.36] [_____] L/square m</MET><ENG> [0.20] [_____] gallon not more than [0.30] 
[_____] gallon per square yard</ENG>.  To obtain uniform application of the prime coat on the surface treated at the 
junction of previous and subsequent applications, spread building paper on the surface for a sufficient distance 
back from the ends of each application to start and stop the prime coat on the paper and to ensure that all sprayers 
will operate at full force on the surface to be treated.  Immediately after application remove and destroy the 
building paper.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.3   Tack Coat</TTL><BRK/>
<BRK/>
<TXT>Apply tack coat at the locations shown on the drawings.  Apply the tack coat when the surface to be treated is 
dry.  Immediately following the preparation of the surface for treatment, apply the bituminous material by means 
of the bituminous distributor, within the limits of temperature specified herein and at a rate of not less than<MET>
 [0.23] [_____] L nor more than [0.68] [_____] L of diluted emulsion per square meter</MET><ENG> [0.05] [_____] gallon nor 
more than [0.15] [_____] gallon of diluted emulsion per square yard</ENG>.  Apply the bituminous material so that uniform 
distribution is obtained over the entire surface to be treated.  Treat lightly coated areas and spots missed 
by the distributor with the bituminous material.  Following the application of bituminous material, allow the 
surface to cure without being disturbed for period of time necessary to permit setting of the tack coat.  Apply 
the bituminous tack coat only as far in advance of the placing of the overlying layer as required for that day's 
operation.  Maintain and protect the treated surface from damage until the succeeding course of pavement is placed.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5   CURING PERIOD</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Retain bracketed sentence if prime coat is specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Following application of the bituminous material and prior to application of the succeeding layer of pavement, 
allow the bituminous coat to cure and to obtain evaporation of any volatiles or moisture.  Maintain the coated 
surface until the succeeding layer of pavement is placed, by protecting the surface against damage and by repairing 
and recoating deficient areas.  [Allow the prime coat to cure without being disturbed for a period of at least 
48 hours or longer, as may be necessary to attain penetration into the treated course.  Furnish and spread enough 
sand to effectively blot up and cure excess bituminous material.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6   <TST>FIELD QUALITY CONTROL</TST></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select the appropriate paragraph based on the amount of bituminous material 
required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Samples of the bituminous material [shall be tested for compliance with the applicable specified requirements.  
A sample shall be obtained and tested by the Contractor for every [[_____]<MET> metric tons</MET><ENG> tons</ENG>] [[_____]<MET> liters</MET><ENG> 
gallons</ENG>] of bituminous material used] [used shall be obtained by the Contractor as directed, under the supervision 
of the Contracting Officer.  The sample may be retained and tested by the Government at no cost to the Contractor].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7   <SUB>SAMPLING AND TESTING</SUB></TTL><BRK/>
<BRK/>
<TXT>Perform sampling and testing by an approved commercial testing laboratory or by facilities furnished by the Contractor.  
No work requiring testing will be permitted until the facilities have been inspected and approved.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.7.1   Sampling</TTL><BRK/>
<BRK/>
<TXT>The samples of bituminous material, unless otherwise specified, shall be in accordance with <RID>ASTM D 140</RID> or <RID>AASHTO T 40</RID>
.  Sources from which bituminous materials are to be obtained shall be selected and notification furnished the 
Contracting Officer within 15 days after the award of the contract.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.2   <TST>Calibration Test</TST></TTL><BRK/>
<BRK/>
<TXT>Furnish all equipment, materials, and labor necessary to calibrate the bituminous distributor.  Calibration shall 
be made with the approved job material and prior to applying the bituminous coat material to the prepared surface.  
Calibrate the bituminous distributor in accordance with <RID>ASTM D 2995</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.3   <TST>Trial Applications</TST></TTL><BRK/>
<BRK/>
<TXT>Before providing the complete bituminous coat, apply three lengths of at least<MET> 30 meters</MET><ENG> 100 feet</ENG> for the full 
width of the distributor bar to evaluate the amount of bituminous material that can be satisfactorily applied.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.7.3.1   Tack Coat Trial Application Rate</TTL><BRK/>
<BRK/>
<TXT>Unless otherwise authorized, apply the trial application rate of bituminous tack coat materials in the amount 
of<MET> 0.20 L/square meter</MET><ENG> 0.05 gallons per square yard</ENG>.  Other trial applications shall be made using various amounts 
of material as may be deemed necessary.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.3.2   Prime Coat Trial Application Rate</TTL><BRK/>
<BRK/>
<TXT>Unless otherwise authorized, apply the trial application rate of bituminous materials in the amount of<MET> 1.10 L/square 
meter</MET><ENG> 0.25 gallon per square yard</ENG>.  Other trial applications shall be made using various amounts of material 
as may be deemed necessary.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.7.4   <TST>Sampling and Testing During Construction</TST></TTL><BRK/>
<BRK/>
<TXT>Perform quality control sampling and testing as required in paragraph FIELD QUALITY CONTROL.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.8   TRAFFIC CONTROLS</TTL><BRK/>
<BRK/>
<TXT>Keep traffic off surfaces freshly treated with bituminous material.  Provide sufficient warning signs and barricades 
so that traffic will not travel over freshly treated surfaces.</TXT><BRK/>
<BRK/></SPT>
</PRT>    <END/><BRK/>
 </SEC>