<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><BRK/>
<HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA      UFGS-32 13 13.03 (April 2006)<BRK/>
                                    -------------------------<BRK/>
Preparing Activity:  <PRA>NAVFAC</PRA>         Replacing without change<BRK/>
                                    UFGS-02751 (July 2004)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 32 13 13.03</SCN><BRK/>
<BRK/>
<STL>AIRFIELDS AND HEAVY-DUTY CONCRETE PAVEMENT LESS THAN 10000 CUBIC YARDS</STL><BRK/>
<DTE>04/06</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>construction of 
concrete pavement for Army, Navy and Air Force airfields and heavy-duty roads 
and hardstands, and vehicular pavement less than 8000 cubic meters (10,000 cubic 
yards</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.<BRK/>
<BRK/>
This guide specification includes tailoring options for ARMY/AIR FORCE, AIR 
FORCE and NAVY.  Selection or deselection of a tailoring option will include 
or exclude that option in the section, but editing the resulting section to 
fit the project is still required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  In preparing contract specifications for concrete pavement, the designer 
will use UFC 3-250-04 STANDARD PRACTICE FOR CONCRETE PAVEMENTS for guidance.  
State highway specifications may only be used for non organizational parking, 
roads, streets, and driveways where the paving index is less than 5.  All organizational 
vehicle parking, roads and airfield concrete pavements will use the Unified 
Facilities guide specifications without exception.  This UFGS or UFGS 02751N 
may be used for smaller quantity Navy projects.  For smaller quantity Army or 
Air Force projects, use this UFGS or UFGS 02754A.<BRK/>
<BRK/>
Contact the Corps of Engineers Transportation Systems Center (TSMCX), the Air 
Force Civil Engineer Support Agency (AFCESA), or the Navy's Engineering Field 
Divisions (EFD) or Naval Facilities Engineering Service Center (NFESC) for guidance 
on interpreting and editing this specification section.<BRK/>
<BRK/>
This specification section is structured for Contractor sampling and testing 
of materials and mixture proportioning.  If Government sampling, testing and 
mixture proportioning is required, contact the TSMCX, AFCESA, Navy EFD or NFESC 
for specification language.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
 <BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
 <BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ACI INTERNATIONAL (ACI)</ORG><BRK/><BRK/><RID>ACI 211.1</RID><RTL>(1991; R 2002) Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete</RTL><BRK/><BRK/><RID>ACI 214R</RID><RTL>(2002) Recommended Practice for Evaluation of Strength Test Results of Concrete</RTL><BRK/><BRK/><RID>ACI 301</RID><RTL>(2005; Errata 2008) Specifications for Structural Concrete</RTL><BRK/><BRK/><RID>ACI 305R</RID><RTL>(1999; Errata 2006) Hot Weather Concreting</RTL><BRK/><BRK/><RID>ACI 306R</RID><RTL>(1988; R 2002) Cold Weather Concreting</RTL><BRK/><BRK/><RID>ACI 325.9R</RID><RTL>(1991; R 1997) Guide for Construction of Concrete Pavements and Bases</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM A 184/A 184M</RID><RTL>(2006) Standard Specification for Fabricated Deformed Steel Bar Mats for Concrete Reinforcement</RTL><BRK/><BRK/><RID>ASTM A 497/A 497M</RID><RTL>(2007) Standard Specification for Steel Welded Wire Reinforcement, Deformed, for Concrete</RTL><BRK/><BRK/><RID>ASTM A 615/A 615M</RID><RTL>(2008b) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement</RTL><BRK/><BRK/><RID>ASTM A 775/A 775M</RID><RTL>(2007b) Standard Specification for Epoxy-Coated Steel Reinforcing Bars</RTL><BRK/><BRK/><RID>ASTM A 996/A 996M</RID><RTL>(2006a) Standard Specification for Rail-Steel and Axle-Steel Deformed Bars or Concrete Reinforcement</RTL><BRK/><BRK/><RID>ASTM C 1017/C 1017M</RID><RTL>(2007) Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete</RTL><BRK/><BRK/><RID>ASTM C 1064/C 1064M</RID><RTL>(2008) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete</RTL><BRK/><BRK/><RID>ASTM C 1077</RID><RTL>(2008) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation</RTL><BRK/><BRK/><RID>ASTM C 1116/C 1116M</RID><RTL>(2008) Standard Specification for Fiber-Reinforced Concrete</RTL><BRK/><BRK/><RID>ASTM C 117</RID><RTL>(2004) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing</RTL><BRK/><BRK/><RID>ASTM C 123</RID><RTL>(2004) Standard Test Method for Lightweight Particles in Aggregate</RTL><BRK/><BRK/><RID>ASTM C 1260</RID><RTL>(2007) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)</RTL><BRK/><BRK/><RID>ASTM C 131</RID><RTL>(2006)Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine</RTL><BRK/><BRK/><RID>ASTM C 136</RID><RTL>(2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates</RTL><BRK/><BRK/><RID>ASTM C 142</RID><RTL>(1997; R 2004) Standard Test Method for Clay Lumps and Friable Particles in Aggregates</RTL><BRK/><BRK/><RID>ASTM C 143/C 143M</RID><RTL>(2008) Standard Test Method for Slump of Hydraulic-Cement Concrete</RTL><BRK/><BRK/><RID>ASTM C 150</RID><RTL>(2007) Standard Specification for Portland Cement</RTL><BRK/><BRK/><RID>ASTM C 172</RID><RTL>(2008) Standard Practice for Sampling Freshly Mixed Concrete</RTL><BRK/><BRK/><RID>ASTM C 174/C 174M</RID><RTL>(2006) Standard Test Method for Measuring Thickness of Concrete Elements Using Drilled Concrete Cores</RTL><BRK/><BRK/><RID>ASTM C 192/C 192M</RID><RTL>(2007) Standard Practice for Making and Curing Concrete Test Specimens in the Laboratory</RTL><BRK/><BRK/><RID>ASTM C 231</RID><RTL>(2008c) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method</RTL><BRK/><BRK/><RID>ASTM C 260</RID><RTL>(2006) Standard Specification for Air-Entraining Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM C 29/C 29M</RID><RTL>(2007) Standard Test Method for Bulk Density ("Unit Weight") and Voids in Aggregate</RTL><BRK/><BRK/><RID>ASTM C 294</RID><RTL>(2005) Standard Descriptive Nomenclature for Constituents of Concrete Aggregates</RTL><BRK/><BRK/><RID>ASTM C 295</RID><RTL>(2008) Petrographic Examination of Aggregates for Concrete</RTL><BRK/><BRK/><RID>ASTM C 309</RID><RTL>(2007) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete</RTL><BRK/><BRK/><RID>ASTM C 31/C 31M</RID><RTL>(2008a) Standard Practice for Making and Curing Concrete Test Specimens in the Field</RTL><BRK/><BRK/><RID>ASTM C 33</RID><RTL>(2007) Standard Specification for Concrete Aggregates</RTL><BRK/><BRK/><RID>ASTM C 39/C 39M</RID><RTL>(2005e1e2) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens</RTL><BRK/><BRK/><RID>ASTM C 42/C 42M</RID><RTL>(2004) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete</RTL><BRK/><BRK/><RID>ASTM C 494/C 494M</RID><RTL>(2008a) Standard Specification for Chemical Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM C 595</RID><RTL>(2008) Standard Specification for Blended Hydraulic Cements</RTL><BRK/><BRK/><RID>ASTM C 618</RID><RTL>(2008a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete</RTL><BRK/><BRK/><RID>ASTM C 78</RID><RTL>(2008) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading)</RTL><BRK/><BRK/><RID>ASTM C 88</RID><RTL>(2005) Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate</RTL><BRK/><BRK/><RID>ASTM C 881/C 881M</RID><RTL>(2002) Standard Specification for Epoxy-Resin-Base Bonding Systems for Concrete</RTL><BRK/><BRK/><RID>ASTM C 94/C 94M</RID><RTL>(2007) Standard Specification for Ready-Mixed Concrete</RTL><BRK/><BRK/><RID>ASTM C 989</RID><RTL>(2006) Standard Specification for Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars</RTL><BRK/><BRK/><RID>ASTM D 1751</RID><RTL>(2004; R 2008) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)</RTL><BRK/><BRK/><RID>ASTM D 1752</RID><RTL>(2004a; R 2008) Standard Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion</RTL><BRK/><BRK/><RID>ASTM D 2995</RID><RTL>(1999; R 2004) Determining Application Rate of Bituminous Distributors</RTL><BRK/><BRK/><RID>ASTM D 4791</RID><RTL>(2005e1) Flat Particles, Elongated Particles, or Flat and Elongated Particles in Coarse Aggregate</RTL><BRK/><BRK/><RID>ASTM D 75</RID><RTL>(2003) Standard Practice for Sampling Aggregates</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA)</ORG><BRK/><BRK/><RID>NRMCA QC 3</RID><RTL>(2002) Quality Control Manual: Section 3, Plant Certifications Checklist: Certification of Ready Mixed Concrete Production Facilities</RTL><BRK/><BRK/></REF><REF><ORG>U.S. ARMY CORPS OF ENGINEERS (USACE)</ORG><BRK/><BRK/><RID>COE CRD-C 114</RID><RTL>(1997) Test Method for Soundness of Aggregates by Freezing and Thawing of Concrete Specimens</RTL><BRK/><BRK/><RID>COE CRD-C 130</RID><RTL>(2001) Standard Recommended Practice for Estimating Scratch Hardness of Coarse Aggregate Particles</RTL><BRK/><BRK/><RID>COE CRD-C 171</RID><RTL>(1994) Standard Test Method for Determining Percentage of Crushed Particles in Aggregate</RTL><BRK/><BRK/><RID>COE CRD-C 300</RID><RTL>(1990) Specifications for Membrane-Forming Compounds for Curing Concrete</RTL><BRK/><BRK/></REF><REF><ORG>U.S. DEPARTMENT OF DEFENSE (DOD)</ORG><BRK/><BRK/><RID>MIL-DTL-24441/20</RID><RTL>(Rev A) Paint, Epoxy-Polyamide, Green Primer, Formula 150, Type III</RTL><BRK/><BRK/><RID>UFC 3-270-03</RID><RTL>Concrete Crack and Partial-Depth Spall Repair</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   SYSTEM DESCRIPTION</TTL><BRK/>
<BRK/>
<TXT>This section is intended to stand alone for construction of concrete pavement.  However, where the construction 
covered herein interfaces with other sections, the construction at each interface must conform to the requirements 
of both this section and the other section, including tolerances for both.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  The following shall 
be submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Equipment</SUB></ITM><BRK/>
<BRK/>
<ITM>  a.  A certified copy of the NRMCA QC Manual Section 3 Concrete Plant Certification Checklist.</ITM><BRK/>
<BRK/>
 <ITM>  b.  A description of the equipment proposed for the machine and hand placing, consolidating 
and curing of the concrete mixture, method of control, and manufacturer's literature on the 
paver and finisher.</ITM><BRK/>
<BRK/>
<ITM><SUB>Proposed Techniques</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Placing and protection methods; paving sequence; jointing pattern; data on curing equipment; 
demolition of existing pavements; as specified.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-05 Design Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Proportioning Studies</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>][<SUB>G, ED</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  The results of the mixture proportioning studies must be signed and stamped by the registered 
professional engineer having technical responsibility for the mix design study and submitted 
at least 30 days prior to commencing concrete placing operations.  The results must include 
a statement giving the maximum nominal coarse aggregate size and the weights and volumes of 
each ingredient proportioned on a one cubic <MET> meter </MET><ENG>yard</ENG> basis.  Base aggregate quantities on 
the mass in a saturated surface dry condition.  Accompany the recommended mixture proportions 
by test results demonstrating that the proportions selected will produce concrete of the qualities 
indicated. The submittal must include:</ITM><BRK/>
<BRK/>
<ITM>   a.  Coarse and fine aggregate gradations and plots.</ITM><BRK/>
<ITM>   b.  Combined aggregate gradation and [coarseness/workability] plots.</ITM><BRK/>
<ITM>   c.  Coarse aggregate quality test results, including deleterious materials.</ITM><BRK/>
<ITM>   d.  Fine aggregate quality test results.</ITM><BRK/>
<ITM>   e.  Mill certificates for cement, pozzolan, and GGBF slag.</ITM><BRK/>
<ITM>   f.  Certified test results for air entraining, water reducing, retarding, non-chloride accelerating[, 
and Lithium Nitrate] admixtures.</ITM><BRK/>
<ITM>   g.  Specified flexural strength, slump, and air content.</ITM><BRK/>
<ITM>   h.  Documentation for average CQC flexural strength increase.</ITM><BRK/>
<ITM>   i.  Recommended proportions/volumes for proposed mixture and trial water-cementitious materials 
ratios.</ITM><BRK/>
<ITM>   j.  Individual beam [and cylinder] breaks.</ITM><BRK/>
<ITM>   k.  Flexural [and compressive ]strength summaries and plots.</ITM><BRK/>
<ITM>   l.  Correlation ratios for acceptance testing and CQC testing.</ITM><BRK/>
<ITM>   m.  Historical record of test results, documenting production standard deviation (if available).</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Sampling and Testing</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>][<SUB>G, ED</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Certified copies of laboratory test reports and sources for cement, pozzolan, GGBF, aggregates, 
admixtures, curing compound, epoxy, and proprietary patching materials proposed for use on this 
project.  All aggregate tests must have been performed no earlier than 6 months prior to contract 
award.</ITM><BRK/>
<BRK/>
<ITM><SUB>Concrete Slump</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Air Content</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Pavement Thickness</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Flexural Strength</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Control Charts</SUB></ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Contractor Quality Control Staff</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>][<SUB>G, ED</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  American Concrete Institute certification for Contractor Quality Control staff.  [Qualifications 
and resumes for petrographer and surveyor.]</ITM><BRK/>
<BRK/>
<ITM><SUB>Laboratory Accreditation</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>][<SUB>G, ED</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Accreditation of the commercial laboratory by an independent evaluation authority, indicating 
conformance to <RID>ASTM C 1077</RID>, including all applicable test procedures.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The USACE validation letter requirement does not apply to the Navy.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TAI OPT="ARMY/AIR FORCE"><ITM><SUB>Commercial Laboratory</SUB>; <SUB>G, ED</SUB></ITM><BRK/>
<BRK/>
<ITM>  USACE validation letter for commercial laboratory.</ITM></TAI><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4   MEASUREMENT AND PAYMENT</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Any project small enough to use this guide specification may use Unit 
Price or Lump Sum payment.  If lump sum payment is used, delete the following 
paragraphs on Measurement and Payment.  For Navy projects, obtain the permission 
of the affected Contracting Officer before using pay-for-performance.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.4.1   Measurement</TTL><BRK/>
<BRK/>
<TXT>The quantity of concrete to be paid for will be the volume of concrete in cubic <MET>meters</MET> <ENG>yards</ENG> including monolithic 
curb, where required, placed in the completed and accepted pavement.  Concrete will be measured in place in the 
completed and accepted pavement only within the neat line dimensions shown in the plan and cross section.  No 
deductions will be made for rounded edges or the space occupied by embedded items or voids.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.2   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made at the contract price per cubic <MET>meter</MET> <ENG>yard</ENG> for the scheduled item.  Payment will constitute 
full compensation for furnishing all materials, equipment, plant and tools, and for all labor and other incidentals 
necessary to complete the concrete pavement.  No separate payment will be made for any cementitious materials, 
admixtures, steel reinforcement, dowels or tie bars, or for any joint materials.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.5   ACCEPTABILITY OF WORK</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Correlate this paragraph with paragraph SPECIFIED CONCRETE STRENGTH AND 
OTHER PROPERTIES and all other specification requirements.  The District Pavement 
Engineer or Geotechnical Branch should be consulted for guidance.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The pavement will be accepted on the basis of tests made by the Government and by the Contractor or its suppliers, 
in accordance with paragraph: Testing and Inspection for Contractor Quality Control and as specified herein.  
The Government may, at its discretion, make check tests to validate the results of the Contractor's testing.  
Take concrete samples at the placement to determine the slump, air content, and strength of the concrete.  Make 
test [beams] [cylinders] for determining conformance with the strength requirements of these specifications and, 
when required, for determining the time at which pavements may be placed into service.  Determine all air content 
measurements in accordance with <RID>ASTM C 231</RID>.  Perform all slump tests in accordance with <RID>ASTM C 143/C 143M</RID>.  Fabricate 
all test [beams] [cylinders] in accordance with <RID>ASTM C 192/C 192M</RID>; cure in accordance with <RID>ASTM C 31/C 31M</RID>; and 
test in accordance with [<RID>ASTM C 78</RID>] [<RID>ASTM C 39/C 39M</RID>].  Ensure core samples to determine in-place thickness of 
the concrete pavement are in accordance with paragraph: Test for Pavement Thickness.  Furnish all materials, 
labor, and facilities required for molding, curing, testing, and protecting test specimens and core samples at 
the site and in the laboratory.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.5.1   Evaluation Sampling</TTL><BRK/>
<BRK/>
<TXT>Ensure sampling, testing, and mixture proportioning is performed by a commercial Testing Laboratory, conforming 
with <RID>ASTM C 1077</RID>.  The individuals who sample and test concrete and concrete constituents must be certified as 
American Concrete Institute (ACI) Concrete Field Testing Technicians, Grade I.  The individuals who perform the 
inspection of concrete must be certified as ACI Concrete Construction Inspector, Level II.  All mix design, weekly 
quality control reports, smoothness reports, and project certification reports must be signed by a Registered 
Engineer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2   Surface Testing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Drawings should clearly show all pavement joint intersection elevations, 
and specific required deviations from a plane surface for such special features 
as crowns, drainage inlets, etc.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Perform surface testing for surface smoothness [, edge slump] and plan grade as indicated below by the Testing 
Laboratory.  Properly reference the measurements in accordance with paving lane identification and stationing, 
and a report given to the Government within 24 hours after measurement is made.  Provide a final report of surface 
testing, signed by a Registered Engineer, containing all surface measurements and a description of all actions 
taken to correct deficiencies, to the Government upon conclusion of surface testing.</TXT><BRK/>
<BRK/>
<BRK/>
<SPT><TTL>1.5.2.1   Smoothnesss</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Delete or retain paragraphs in brackets for roads and streets features, 
as required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Straightedge Testing:  Ensure the finished surfaces of the pavements have no abrupt change of <MET>6 mm </MET><ENG>1/4 inch</ENG> or 
more, and all pavements are within the limits specified hereinafter when checked with an approved <MET>4 m </MET><ENG>12 foot</ENG>
 straightedge.  Ensure runways and taxiways have a variation from the specified straight edge not greater than <MET>
3 mm </MET><ENG>1/8 inch</ENG> in the longitudinal direction and not greater than <MET>6 mm </MET><ENG>1/4 inch</ENG> in the transverse direction.  
Ensure all other airfield areas have a variation from a straight edge not greater than <MET>6 mm </MET><ENG>1/4 inch</ENG> in either 
the longitudinal or transverse direction.  [Ensure roads, streets, tank hardstands, vehicular parking areas, 
and open storage areas have a variation from the specified straight edge not greater than <ENG>6 mm </ENG><ENG>1/4 inch</ENG> in either 
the longitudinal or transverse direction.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.2   Testing Method</TTL><BRK/>
<BRK/>
<TXT>Test the entire area of the pavement in both a longitudinal and a transverse direction on parallel lines approximately <MET>
4.5 m</MET> <ENG>15 feet</ENG> apart.  Hold the straightedge in contact with the surface and moved ahead one-half the length of 
the straightedge for each successive measurement.  Determine the amount of surface irregularity by placing the 
straightedge on the pavement surface and allowing it to rest upon the two highest spots covered by its length 
and measuring the maximum gap between the straightedge and the pavement surface, in the area between these two 
high points.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.3   Plan Grade</TTL><BRK/>
<BRK/>
<TXT>Within 5 days after paving, test the finished surface of the pavement area by running lines of levels at intervals 
corresponding with every longitudinal and transverse joint to determine the elevation at each joint intersection.  
Record the results of this survey and provide a copy to the Government at the completion of the survey.  Ensure 
the finished surfaces of airfield runway, taxiway, and apron pavements vary not more than <MET>12 mm </MET><ENG>1/2 inch</ENG> above 
or below the plan grade line or elevation indicated.  Ensure the surfaces of other pavements vary not more than <MET>
18 mm </MET><ENG>3/4 inch</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.4   Areas Defective in Plan Grade or Smoothness</TTL><BRK/>
<BRK/>
<TXT>In areas not meeting the specified limits for surface smoothness and plan grade, reduce high areas to attain 
the required smoothness and grade, at no additional cost to the Government.  Reduce high areas by grinding the 
hardened concrete with an approved diamond grinding machine after the concrete is 14 days or more old.  Ensure 
the depth of diamond grinding does not exceed <MET>6 mm </MET><ENG>1/4 inch</ENG>.  Remove and replace all pavement areas requiring 
plan grade or surface smoothness corrections in excess of the limits specified above, in conformance with paragraph 
REPAIR, REMOVAL, REPLACEMENT OF NEWLY CONSTRUCTED SLABS.  </TXT></SPT></SPT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6   ACCEPTABILITY OF WORK</TTL><BRK/>
<BRK/>
<TXT>The materials and the pavement itself will be accepted on the basis of tests made by the Contractor, using an 
approved <SUB>commercial laboratory</SUB>. All <SUB>sampling and testing</SUB> for preconstruction testing of materials shall be performed 
by, and at the expense of, the Contractor, using an approved commercial laboratory or, for cementitious materials 
and chemical admixtures, a laboratory maintained by the manufacturer of the material. During construction, the 
Contractor is responsible for sampling and testing aggregates, cementitious materials, and concrete as specified 
herein.  The Government will sample and test concrete and ingredient materials as considered appropriate.  The 
Contractor must provide facilities and labor as may be necessary for procurement of representative test samples.  
Testing by the Government will in no way relieve the Contractor of the specified testing requirements. </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7   QUALIFICATIONS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Where they are available, specify only ACI certified personnel.  Check 
the American Concrete Institute (ACI) web site for local availability (www.concrete.org/Certification).  
Delete petrographer requirements for Navy projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.7.1   <SUB>Contractor Quality Control Staff</SUB></TTL><BRK/>
<BRK/>
<TXT>All Contractor Quality Control personnel assigned to concrete construction must be American Concrete Institute 
(ACI) certified in the following grade (or have written evidence acceptable to the Contracting Officer's representative 
of having completed similar qualification programs):</TXT><BRK/>
<BRK/>
<LST>1. CQC personnel responsible for inspection of concrete paving operations: ACI Concrete Transportation 
Inspector.</LST><BRK/>
<BRK/>
<LST>2. Lead Foreman or Journeyman of the Concrete Placing, Finishing, and Curing Crews: ACI Concrete Flatwork 
Technician/Finisher</LST>.<BRK/>
<BRK/>
<LST>3. Field Testing Technicians: ACI Concrete Field Testing Technician, Grade I.</LST><BRK/>
<BRK/>
<LST>4. Laboratory Testing Technicians: ACI Concrete Strength Testing Technician and Laboratory Testing Technician, 
Grade I or II.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.2   Other Staff</TTL><BRK/>
<BRK/>
<TXT>Submit for approval, the qualifications and resumes for the following staff</TXT>:<BRK/>
<BRK/>
<LST>1.  Petrographer: Bachelor of Science degree in geology or petrography, trained in petrographic examination 
of concrete aggregate according to <RID>ASTM C 294</RID> and <RID>ASTM C 295</RID> and trained in identification of the specific 
deleterious materials and tests identified in this specification.  Resume must detail the education, 
training and experience related to the project-specific test methods and deleterious materials and be 
submitted at least 20 days before petrographic and deleterious materials examination is to commence</LST>.<BRK/>
<BRK/>
<LST>2.  Licensed Surveyor: All survey work must be performed under the supervision of a Licensed Surveyor.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.3   <SUB>Laboratory Accreditation</SUB></TTL><BRK/>
<BRK/>
<TXT>Laboratory and testing facilities must be provided by and at the expense of the Contractor.  The laboratories 
performing the tests must be accredited in accordance with <RID>ASTM C 1077</RID>, including <RID>ASTM C 78</RID> and <RID>ASTM C 1260</RID>.  
The accreditation must be current and must include the required and optional test methods, as specified throughout 
this SECTION.  Provide onsite temperature-controlled concrete curing facilities.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.8   DELIVERY, STORAGE, AND HANDLING OF MATERIALS</TTL><BRK/>
<BRK/>
<TXT>Deliver, store and handle cementitious materials, fine and coarse aggregates and other concreting materials in 
accordance with <RID>ASTM C 94/C 94M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.9   <SUB>EQUIPMENT</SUB></TTL><BRK/>
<BRK/>
<TXT>Maintain all plant, equipment, tools, and machines used in the work in satisfactory working conditions at all 
times.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.9.1   Batching and Mixing Plant</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The batching and mixing plant should be on the construction site or as 
close as possible, but should be no farther than 30 minutes haul time from the 
placing site during all periods of the work day.  Edit bracketed items as appropriate.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure the batching and mixing plant conforms to the requirements of <RID>NRMCA QC 3</RID> [and be no more than 30 minutes 
haul time from the placing site].  There must be operable telephonic or radio communication between the plant 
and the placing site at all times concreting is taking place.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.9.2   Truck Mixers</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Retain this subparagraph only if truck mixers have been permitted above.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure truck mixers, the mixing of concrete therein, and concrete uniformity and testing thereof conforms to 
the requirements of <RID>ASTM C 94/C 94M</RID>.  Additional water may be added to bring the slump within the specified range 
provided the approved water-cement ratio is not exceeded.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.9.3   Paver-Finisher</TTL><BRK/>
<BRK/>
<TXT>The paver-finisher must be a heavy-duty, self-propelled machine designed specifically for paving and finishing 
high quality pavement.  Clary screeds, other rotating tube floats, or bridge deck finishers must not be allowed 
on mainline paving, but may be allowed on irregular or odd-shaped slabs, and near buildings or trench drains, 
subject to the Contracting Officer's approval.  Bridge deck finishers must have a minimum operating weight of <MET>
4100 kg </MET><ENG>9000 pounds</ENG> and must have a transversely operating carriage containing a knock-down auger and a minimum 
of two immersion vibrators.  Use vibrating screeds or pans only for isolated slabs where hand finishing is permitted 
as specified, and only where specifically approved.  Concrete finishing equipment of types other than specified 
above may be demonstrated on a test section outside the production pavement if approved in writing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.9.4   Curing Equipment</TTL><BRK/>
<BRK/>
<TXT>Equipment must be self-propelled, with spraying nozzles and pressure that can be controlled and operated with 
a fine nozzle to completely and uniformly cover pavement surface with required amount of curing compound.  It 
must mechanically agitate curing compound throughout application.  Small or irregular areas may be sprayed by 
hand methods.  Calibrate the spraying system in accordance with <RID>ASTM D 2995</RID>, Method A, for the rate of application 
required in paragraph: MEMBRANE CURING.  Any hand-operated sprayers allowed by paragraph: MEMBRANE CURING must 
be compressed air supplied by a mechanical air compressor.  Immediately replace curing equipment that fails to 
apply an even coating of compound at the specified rate.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.9.5   Sawing Equipment</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Retain bracketed sentence as necessary to correlate with paragraph REMOVAL 
OF EXISTING PAVEMENT SLAB.  Otherwise delete.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure equipment for sawing joints and for other similar sawing of concrete is standard diamond-type concrete 
saws mounted on a wheeled chassis which can be easily guided to follow the required alignment.  Use diamond tipped 
blades.  If demonstrated to operate properly, abrasive blades may be used.  Provide spares as required to maintain 
the required sawing rate.  [Wheel saws used in the removal of concrete must be saws with large diameter tungsten 
carbide tipped blades mounted on a heavy-duty chassis which will produce a saw kerf at least <MET>40 mm </MET><ENG>1-1/2 inch</ENG>
 wide.]  Use saws capable of sawing to the full depth required.  Early-entry saws may be used, subject to demonstration 
and approval of the Contracting Officer.  No change to the initial sawcut depth is permitted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.9.6   Straightedge</TTL><BRK/>
<BRK/>
<TXT>Furnish and maintain at the job site, in good condition, one <MET>4 m </MET><ENG>12 foot</ENG> straightedge for each paving train for 
testing the hardened portland cement concrete surfaces.  These straightedges must be constructed of aluminum 
or magnesium alloy and have blades of box or box-girder cross section with flat bottom, adequately reinforced 
to insure rigidity and accuracy.  Straightedges must have handles for operation on the pavement.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.10   <SUB>PROPOSED TECHNIQUES</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit plans for placing and protection methods; paving sequence; jointing pattern; data on curing equipment; 
demolition of existing pavements; and other techniques as specified to the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete any reference to any products which are not to be used on the 
project.  Coordinate all product requirements with the appropriate federal Government 
Pavements or Materials Engineer.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.1   CEMENTITIOUS MATERIALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit these paragraphs as appropriate for the particular project.  Guidance 
for use of cementitious materials should be sought from the Pavement Materials 
engineer or from the TSMCX, Navy EFD, NFESC, or AFCESA, especially for areas 
subject to alkali-aggregate reactivity, or sulfate attack.</NPR><BRK/>
<BRK/>
<NPR> When sulfate bearing soil or water is encountered, specify Type II cement for 
moderate sulfate concentration and Type V cement for high concentration and 
consider requiring use of fly ash or GGBF slag for partial replacement.  Do 
not specify Type I or III cement.  See UFC 3-250-04 for guidance.  Specify limit 
on false set if it is a problem in the area.</NPR><BRK/>
<BRK/>
<NPR>Type III cement should not be specified unless accelerated paving is involved 
and then only after laboratory mixture proportioning studies and tests during 
the design stage of the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure cementitious materials are portland cement, [blended cement] or only portland cement in combination with 
natural pozzolan or fly ash [or ground granulated blast furnace slag] and conforms to appropriate specifications 
listed below.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.1.1   Portland Cement</TTL><BRK/>
<BRK/>
<TXT>Ensure portland cement conforms to <RID>ASTM C 150</RID>, Type [I] [II] [V], low alkali [except that the maximum amount 
of C3A in Type I cement shall be 15 percent] [including false set requirements] [Type III with C3A limited to 
8 percent].  [Use Type III cement only in concrete in the following locations [_____].] </TXT><BRK/>
<BRK/></SPT>
<TAI OPT="ARMY/AIR FORCE"><SPT><TTL>2.1.2   Blended Cements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Blended cement is not used by the Navy.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Blended cement shall conform to <RID>ASTM C 595</RID>, Type [IP] [IP (MS)] [IS] [IS (MS)], including the optional requirement 
for mortar expansion.</TXT><TAI OPT="NAVY">Not Used.</TAI><BRK/>
<BRK/></SPT>
</TAI><SPT><TTL>2.1.3   Pozzolan </TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.3.1   Fly Ash</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For Navy projects, Class F fly ash is required in all paving concrete.  
For Army and Air Force projects, Class F fly ash is recommended, but not mandatory.  
Class C fly ash is not permitted for paving concrete.  Use loss on ignition 
not exceeding 3 percent for frost areas to reduce carbon interference with air 
entraining admixture.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure fly ash conforms to <RID>ASTM C 618</RID>, Class F, including the optional requirements for drying shrinkage, uniformity, 
and effectiveness in controlling Alkali-Silica reaction and has a loss on ignition not exceeding [3] [6] percent.  
Ensure class F fly ash has a Calcium Oxide (CaO) content of less than 8 percent.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.3.2   Raw or Calcined Natural Pozzolan</TTL><BRK/>
<BRK/>
<TXT>Ensure natural pozzolan is raw or calcined and conforms to <RID>ASTM C 618</RID>, Class N, including the optional requirements 
for drying shrinkage, uniformity, and effectiveness in controlling Alkali-Silica reaction and shall have a loss 
on ignition not exceeding [3] [6] percent.  Ensure class N pozzolan has a Calcium Oxide (CaO) content of less 
than 5 percent.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.1.4   Ground Granulated Blast-Furnace (GGBF) Slag</TTL><BRK/>
<BRK/>
<TXT>Ensure Ground Granulated Blast-Furnace Slag conforms to <RID>ASTM C 989</RID>, Grade 100 or Grade 120.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2   AGGREGATES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The designer will ensure that aggregates available in the area meet the 
requirements of these specifications.  Otherwise, the specification requirements 
must be modified to allow use of available material.  This concern must be discussed 
and validated in the Design Analysis before preparation of the project specifications.  
During the design stage, the designer must assure that all aggregate materials 
in the area which meet the project specifications will also produce concrete 
of the specified flexural strength with a reasonable cementitious material content.  
Otherwise, specifications and design assumptions must be modified.  It is imperative 
that all aggregate be investigated for problems related to alkali-aggregate 
reactions.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.2.1   Aggregate Sources</TTL><BRK/>
<BRK/>
<SPT><TTL>2.2.1.1   Durability</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use first option for Army and Air Force; second option is for Navy projects 
only.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><TAI OPT="ARMY/AIR FORCE">Aggregate must have a satisfactory service record in freezing and thawing of at least 5 years successful service 
in three concrete paving projects.  The service record must include a condition survey of the existing concrete 
and a review of the concrete-making materials, including coarse and fine aggregates, cement, and mineral admixtures.  
This review should consider the previous aggregate source and test results, cement mill certificate data, mineral 
admixture chemical and physical composition, and the mix design (cement factor and water-cementitious material 
ratio).  Aggregate not having a satisfactory demonstrable service record must have a durability factor of 50 
or more when subjected to freezing and thawing in concrete in accordance with <RID>COE CRD-C 114</RID>.  </TAI><TAI OPT="NAVY">Evaluate and test 
fine and coarse aggregates to be used in all concrete for durability in accordance with <RID>ASTM C 88</RID>.  Results must 
not show more than 18 percent loss when subjected to 5 cycles using Magnesium Sulfate.  If Sodium Sulfate is 
used, results must not show more than 12 percent loss when subjected to 5 cycles.</TAI></TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.1.2   Alkali-Silica Reactivity</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use first and third options for Navy projects; use second option for 
Army and Air Force.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Evaluate and test fine and coarse aggregates to be used in all concrete for alkali-aggregate reactivity in accordance 
with <RID>ASTM C 1260</RID>.  Test both coarse aggregate size groups if from different sources.  Evaluate the fine and coarse 
aggregates separately and in combination, which matches the Contractor's proposed mix design proportioning<TAI OPT="NAVY">, utilizing 
the modified version of <RID>ASTM C 1260</RID></TAI>.  Test results of the combination must have a measured expansion equal to 
or less than 0.08 percent at 16 days after casting.  <TAI OPT="ARMY/AIR FORCE">Should the test data indicate an expansion of greater than 
0.08 percent, reject the aggregate(s) or perform additional testing, using a modified version of <RID>ASTM C 1260</RID> 
using one of the following options:</TAI><TAI OPT="NAVY">Modify <RID>ASTM C 1260</RID> as follows to included one of the following options:</TAI></TXT><BRK/>
<BRK/>
<LST>a. Utilize the Contractor's proposed low alkali portland cement and Class F fly ash or Class N pozzolan 
in combination with the proposed aggregate percentage for the test proportioning.  Use Class F fly ash 
or Class N pozzolan in the range of 25 percent to 40 percent of the total cementitious material by mass.  
Determine the quantity that will meet all the requirements of these specifications and that will lower 
the expansion equal to or less than 0.08 percent at 16 days after casting.</LST><BRK/>
<BRK/>
<LST>b. Utilize the Contractor's proposed low alkali portland cement and ground granulated blast furnace (GGBF) 
slag in combination with the proposed aggregate percentage for the test proportioning.  Use GGBF slag 
in the range of 40 percent to 50 percent of the total cementitious material by mass.  Determine the quantity 
that will meet all the requirements of these specifications and that will lower the expansion equal to 
or less than 0.08 percent at 16 days.</LST><TAI OPT="NAVY"><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The use of Lithium Nitrate for mitigation of alkali-silica reaction is 
an alternative for Navy projects only.  However, do not include in a project 
specification without Navy EFD or NFESC concurrence.</NPR><BRK/>
<AST/><BRK/></NTE>
</TAI><BRK/>
<TAI OPT="NAVY"><LST>c. Utilize the Contractor's proposed low alkali portland cement and a lithium nitrate admixture.  The 
lithium nitrate admixture may be used in combination with either Class "F" fly ash, Class N pozzolan, 
or ground granulated blast furnace (GGBF) slag, at a dosage rate as recommended by the manufacturer.</LST></TAI><BRK/>
<BRK/>
<TXT>If any of the above options does not lower the expansion to less than 0.08 percent at 16 days after casting, 
reject the aggregate(s) and submit new aggregate sources for retesting.  Submit the results of testing to the 
Contracting Officer for evaluation and acceptance.</TXT><BRK/>
<BRK/></SPT>
<TAI OPT="AIR FORCE"><SPT><TTL>2.2.1.3   Combined Aggregate Gradation</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For Air Force Projects include the following gradation requirements </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>In addition to the grading requirements specified for coarse aggregate and for fine aggregate, the combined aggregate 
grading must meet the following requirement.</TXT><BRK/>
<BRK/>
<LST>a.  The materials selected and the proportions used must be such that when the Coarseness Factor (CF) 
and the Workability Factor (WF) are plotted on a diagram as described in d. below, the point thus determined 
falls within the parallelogram described therein.</LST><BRK/>
<BRK/>
<LST>b.  Determine the Coarseness Factor (CF) from the following equation:</LST><BRK/>
<BRK/>
<ITM><MET>CF = (cumulative percent retained on the 9.5 mm sieve)(100)/(cumulative percent retained on 
the 2.36 mm sieve) </MET><ENG>CF = (cumulative percent retained on the 3/8 in. sieve)(100)/(cumulative 
percent retained on the No. 8 sieve)</ENG></ITM><BRK/>
<BRK/>
<LST>c.  The Workability Factor WF is defined as the cumulative percent passing the <MET>2.36 mm </MET><ENG>No. 8</ENG> sieve.  
However, adjust WF upwards only, by 2.5 percentage points for each <MET>42 kg </MET><ENG>94 pounds</ENG> of cementitious material 
per cubic <MET>meter </MET><ENG>yard</ENG> greater than <MET>335 kg per cubic meter </MET><ENG>564 pounds per cubic yard</ENG>.</LST><BRK/>
<BRK/>
<LST>d.  Plot a diagram using a rectangular scale with WF on the Y-axis with units from 20 (bottom) to 45 
(top), and with CF on the X-axis with units from 80 (left side) to 30 (right side).  On this diagram, 
plot a parallelogram with corners at the following coordinates (CF-75, WF-28), (CF-75, WF-40), (CF-45, 
WF-32.5), and (CF-45, WF-44.5.  If the point determined by the intersection of the computed CF and WF 
does not fall within the above parallelogram, change the grading of each size of aggregate used and the 
proportions selected as necessary.)</LST><BRK/>
<BRK/>
<LST>e.  Use a blending aggregate to meet the required combined grading. This blending aggregate must be batched 
separately.  Compute the combined grading of all aggregates used, in the proportions selected, on the 
basis of cumulative percent retained on each sieve specified for fine and coarse aggregate.</LST><BRK/>
<BRK/></SPT>
</TAI></SPT><SPT><TTL>2.2.2   Coarse Aggregate</TTL><BRK/>
<BRK/>
<SPT><TTL>2.2.2.1   Material Composition</TTL> <BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Crushing gravel tends to improve quality and bond characteristics and 
generally results in higher flexural strength of concrete.  When mixture proportioning 
studies or local experience indicates that low flexural strength concrete will 
be produced with an uncrushed gravel, the possibility of producing higher strength 
concrete by crushing the gravel should be investigated.  When desirable to limit 
coarse aggregate to crushed materials, modify this paragraph appropriately.</NPR><BRK/>
<BRK/>
<NPR>Do not, under any conditions, permit use of steel furnace slag for any aggregate.  
(It is markedly different from iron blast furnace slag.)</NPR><BRK/>
<BRK/>
<NPR>In power check pads, the high temperatures from jet blast can cause distress 
in aggregates in the concrete.  Include bracketed item if power check pads are 
to be constructed.  If no service record is available, lab study of available 
aggregates should be made.</NPR><BRK/>
<BRK/>
<NPR>Special attention should be given to aggregates to be used for compass calibration 
pads.  Aggregates with magnetic properties, such as, but not limited to, magnetite 
in granites, high-iron minerals in traprock, pyrite in limestone, and free iron 
or iron oxide in slag aggregate should not be used.  When the paving of compass 
calibration pads is required, add the bracketed item concerning compass pads 
as additional requirements for coarse and fine aggregates.</NPR><BRK/>
<BRK/>
<NPR>If reclaimed portland cement concrete is permitted, retain the bracketed portion 
regarding reclaimed PCC; otherwise, delete.  If reclaimed PCC is permitted to 
be used, laboratory studies must be performed during the design stage to validate 
mixture proportions and to evaluate relative durability of the concrete produced.</NPR><BRK/>
<BRK/>
<NPR>Retain the bracketed requirement for washing coarse aggregate if aggregates 
in the area require it.  Add the requirement to use a log washer or other specific 
equipment if experience in the area shows the need.  Delete if not needed.  
It is permissible to list certain aggregate sources that do not require washing, 
if that is appropriate.  The designer must make the decision during preparation 
of specifications; do not make the Resident Engineer decide after award if aggregates 
need to be washed.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure coarse aggregate consists of [[crushed] [uncrushed] gravel], crushed stone, [crushed adequately seasoned 
air-cooled iron blast-furnace slag; steel furnace slag will not be permitted], [reclaimed portland cement concrete] 
[or a combination thereof].  [Ensure crushed gravel contains not less than 75 percent of crushed particles by 
mass in each sieve size, as determined by <RID>COE CRD-C 171</RID>.] [Ensure aggregate used for paving compass calibration 
hardstands is free of materials having undesirable magnetic properties, including magnetite in granite, high-iron 
minerals in traprock, and pyrite in limestone.]  [Ensure coarse aggregate used for paving power check pads is 
limestone, dolomite, basalt or other approved material which will not cause thermal distress from jet blast.] 
[Reclaimed concrete pavement or granular base produced from required removal operations may be used for aggregate, 
provided it meets all requirements specified herein for aggregates.]  Ensure aggregates as delivered to the mixers 
consist of clean, hard, uncoated particles meeting the requirements of <RID>ASTM C 33</RID> except as specified herein.  
[Wash coarse aggregate.  Ensure washing is sufficient to remove dust and other coatings.] [Clean coarse aggregate 
by processing with an approved log washer.]  [Ensure iron blast-furnace slag conforming to the grading to be 
used in the concrete has a compact density of not less than <MET>1125 kg/cubic meter </MET><ENG>70 lb/cu. ft.</ENG> determined in accordance 
with <RID>ASTM C 29/C 29M</RID>].  Ensure coarse aggregate does not show more than 40 percent loss when subjected to the 
Los Angeles abrasion test in accordance with <RID>ASTM C 131</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2.2   Particle Shape Characteristics</TTL><BRK/>
<BRK/>
<TXT>Ensure particles of the coarse aggregate are generally spherical or cubical in shape.  Ensure the quantity of 
flat and elongated particles in any size group does not exceed 20 percent by weight as determined by the Flat 
Particle Test and the Elongated Particle Test of <RID>ASTM D 4791</RID>.  A flat particle is defined as one having a ratio 
of width to thickness greater than 3; an elongated particle is one having a ratio of length to width greater 
than 3.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2.3   Size and Grading</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Fill in the blank according to the size aggregate available in the project 
area, and the type of paving.  For thin bonded overlays, limit the nominal maximum 
aggregate size to less than one-third of the uniform overlay thickness (not 
including levelling portion).  Use nominal maximum aggregate size of 37.5 mm 
(1-1/2 inch) whenever possible.  A 25 mm (1-inch) nominal maximum aggregate 
size may be used to avoid durability problems associated with some larger size 
aggregate.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure the nominal maximum size of the coarse aggregate is <MET>[37.5] [_____] mm </MET><ENG>[1.5] [_____] inches</ENG>.  When the 
nominal maximum coarse size is greater than <MET>25 mm </MET><ENG>1 inch</ENG>, grade the coarse aggregates and furnish in two size 
groups meeting the individual grading requirements of <RID>ASTM C 33</RID>, Size No. 4 <MET>(37.5 to 19.0 mm) </MET><ENG>(1.5 to 0.75 inches)</ENG>
 and Size No. 67 <MET>(19.0 to 4.75 mm) </MET><ENG>(0.75 inches to No. 4)</ENG>.</TXT><BRK/>
<BRK/></SPT>
[<SPT><TTL>2.2.2.4   Deleterious Materials - Airfield Pavements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include these deleterious material requirements for airfield paving projects 
only, otherwise, delete.  In Table 5 select columns showing appropriate percentage 
by weight in accordance with the following.  Delete the inapplicable column 
in the table and the heading of the column used.</NPR><BRK/>
<TBL><BRK/>
<THD>                             Air Freezing            Average<BRK/>
                              Index             Precipitation for any<BRK/>
         Weather            Coldest year        Single Month during<BRK/>
         Severity           in 30 (a)           the Freezing Period<BRK/>
       _____________       ________________     ________________________<BRK/>
<BRK/></THD>
         Moderate           500 or less             Any Amount<BRK/>
<BRK/>
         Moderate (b)       501 or more         Less than 25 mm (1 inch)<BRK/>
<BRK/>
         Severe             501 or more         25 mm (1 inch) or more<BRK/></TBL>
<BRK/>
<NPR>(a)  Calculated as described in TM 5-852-1.  See ASTM C 33 for simplified map 
of CONUS weather severity.</NPR><BRK/>
<BRK/>
<NPR>(b)  In poorly drained areas, the weather should be considered severe even though 
the other criteria indicate a rating of moderate.</NPR><BRK/>
<BRK/>
<TAI OPT="NAVY"><NPR>(c)  For Navy projects, select "Negligible Weather" column of Table 5. Delete 
the inapplicable columns and delete paragraphs a through h. </NPR></TAI><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure the amount of deleterious material in each size group of coarse aggregate doesl not exceed the limits 
shown in Table 5 below, determined in accordance with the test methods shown.</TXT><BRK/>
<TBL><THD><BRK/>
<HL4>TABLE 5</HL4><BRK/>
<HL4>LIMITS OF DELETERIOUS MATERIALS IN COARSE AGGREGATE</HL4><BRK/>
<HL4>FOR AIRFIELD PAVEMENTS</HL4><BRK/>
<HL4>Percentage by Mass</HL4><BRK/>
<BRK/>
                                       <BRK/>
                                       Severe   Moderate  Negligible     <BRK/>
          Materials <SPS>(h)</SPS>                 Weather  Weather   Weather<BRK/>
         ____________                 _______________________________________<BRK/>
<BRK/></THD>
<BRK/>
  Clay lumps and friable                  0.2     0.2        1.0<BRK/>
  particles (<RID>ASTM C 142</RID>)<BRK/>
<BRK/>
  Shale (a) (<RID>ASTM C 295</RID>)                  0.1     0.2         --<BRK/>
<BRK/>
  Material finer than 0.075 mm            0.5     0.5        1.0<BRK/>
  (No. 200 sieve) (b) (<RID>ASTM C 117</RID>)<BRK/>
<BRK/>
  Lightweight particles (c)               0.2     0.2        1.0<BRK/>
  (<RID>ASTM C 123</RID>)<BRK/>
<BRK/>
  Clay ironstone (d)                      0.1     0.5         -- <BRK/>
  (<RID>ASTM C 295</RID>)<BRK/>
<BRK/>
  Chert and cherty stone (less than       0.1     0.5         --<BRK/>
  2.40 Mg/cubic meter density SSD<BRK/>
  (2.40 Sp. Gr.)) (e) <BRK/>
<RID>ASTM C 123</RID> followed by <RID>ASTM C 295</RID>)<BRK/>
<BRK/>
  Claystone, mudstone, and                0.1     0.1         --  <BRK/>
  siltstone (f) (<RID>ASTM C 295</RID>)<BRK/>
<BRK/>
  Shaly and argillaceous                  0.2     0.2         -- <BRK/>
  limestone (g) (<RID>ASTM C 295</RID>)<BRK/>
<BRK/>
  Other soft particles                    1.0     1.0         1.0 <BRK/>
  <RID>COE CRD-C 130</RID><BRK/>
<BRK/>
  Total of all deleterious                1.0     2.0         3.0 <BRK/>
  substances exclusive of material<BRK/>
  finer than 0.075 mm (No. 200 sieve)<BRK/></TBL>
<BRK/>
<LST>a.  Shale is defined as a fine-grained, thinly laminated or fissile sedimentary rock.  It is commonly 
composed of clay or silt or both.  It has been indurated by compaction or by cementation, but not so 
much as to have become slate.</LST><BRK/>
<BRK/>
<LST>b.  Limit for material finer than 0.075 mm (No. 200 sieve) will be increased to 1.5 percent for crushed 
aggregates if the fine material consists of crusher dust that is essentially free from clay or shale.</LST><BRK/>
<BRK/>
<LST>c.  The separation medium must have a density of 2.0 Mg/cubic meter (Sp. Gr. of 2.0).  This limit does 
not apply to coarse aggregate manufactured from blast-furnace slag unless contamination is evident.</LST><BRK/>
<BRK/>
<LST>d.  Clay ironstone is defined as an impure variety of iron carbonate, iron oxide, hydrous iron oxide, 
or combinations thereof, commonly mixed with clay, silt, or sand.  It commonly occurs as dull, earthy 
particles, homogeneous concretionary masses, or hard-shell particles with soft interiors.  Other names 
commonly used for clay ironstone are "chocolate bars" and limonite concretions.</LST><BRK/>
<BRK/>
<LST>e.  Chert is defined as a rock composed of quartz, chalcedony or opal, or any mixture of these forms 
of silica.  It is variable in color.  The texture is so fine that the individual mineral grains are too 
small to be distinguished by the unaided eye.  Its hardness is such that it scratches glass but is not 
scratched by a knife blade.  It may contain impurities such as clay, carbonates, iron oxides, and other 
minerals.  Cherty stone is defined as any type of rock (generally limestone) that contains chert as lenses 
and nodules, or irregular masses partially or completely replacing the original stone.</LST><BRK/>
<BRK/>
<LST>f.  Claystone, mudstone, or siltstone, is defined as a massive fine-grained sedimentary rock that consists 
predominantly of indurated clay or silt without laminations or fissility.  It may be indurated either 
by compaction or by cementation.</LST><BRK/>
<BRK/>
<LST>g.  Shaly limestone is defined as limestone in which shale occurs as one or more thin beds or laminae.  
These laminae may be regular or very irregular and may be spaced from a few inches down to minute fractions 
of an inch.  Argillaceous limestone is defined as a limestone in which clay minerals occur disseminated 
in the stone in the amount of 10 to 50 percent by weight of the rock; when these make up from 50 to 90 
percent, the rock is known as calcareous (or dolomitic) shale (or claystone, mudstone, or siltstone).</LST><BRK/>
<BRK/>
<LST>h.  Perform testing in accordance with the referenced test methods, except that the minimum sample size 
must be as specified in Paragraph: TESTING DELETERIOUS MATERIALS-AIRFIELDS ONLY.</LST><BRK/>
<BRK/></SPT>
]<SPT><TTL>2.2.2.5   Testing Sequence  Deleterious Materials -- Airfields Only</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Contact TSMCX for guidance on available petrographers in USACE.  Use 
first option for Navy projects; second option applies to Army and Air Force.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The Contractor will not be entitled to any extension of time or additional payment due to any delays caused by 
the testing, evaluation, or personnel requirements.<TAI OPT="NAVY"> Sample sizes must be in accordance with the referenced test 
methods.</TAI>  <TAI OPT="ARMY/AIR FORCE">The size of the sample must be at least <MET>90 kg </MET><ENG>200 pounds</ENG> for the <MET>19 to 37 mm </MET><ENG>3/4 to 1-1/2 inch</ENG> size 
and <MET>12 kg </MET><ENG>25 pounds</ENG> for the <MET>4.75 to 19 mm </MET><ENG>No. 4 to 3/4 inch</ENG> coarse aggregate and <MET>5 kg </MET><ENG>10 pounds</ENG> for the fine 
aggregate.  Provide facilities for the ready procurement of representative test samples.  The testing procedure 
on each sample of coarse aggregate for compliance with limits on deleterious materials is as follows:</TAI></TXT><BRK/>
<BRK/>
<TAI OPT="ARMY/AIR FORCE"><LST>Step 1:  Test full sample for material finer than the <MET>0.075 mm </MET><ENG>No. 200</ENG> sieve.  Discard material finer 
than the <MET>0.075 mm </MET><ENG>No. 200</ENG> sieve.</LST><BRK/>
<BRK/>
<LST>Step 2:  Test remaining full sample for clay lumps and friable particles and remove.</LST><BRK/>
<BRK/>
<LST>Step 3:  Test remaining full sample for lightweight particles (Sp.Gr.2.0) and remove.</LST><BRK/>
<BRK/>
<LST>Step 4.  Test remaining full sample for chert and/or cherty stone with SSD density of less than 2.40 
Mg/cubic meter (Sp. Gr. 2.40).  Remove lightweight chert and/or cherty stone.  Restore other materials 
less than 2.40 to the sample.</LST><BRK/>
<BRK/>
<LST>Step 5:  Test remaining sample for clay-ironstone, shale, claystone, mudstone, siltstone, shaly and/or 
argillaceous limestone, and remove.</LST><BRK/>
<BRK/>
<LST>Step 6:  Test approximately one-fifth of remaining full sample for other soft particles.</LST></TAI><BRK/>
<BRK/></SPT>
[<SPT><TTL>2.2.2.6   Deleterious Material-Road Pavements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use this paragraph only for heavy-duty pavements, roads, streets, and 
parking lots for vehicular and tracked traffic.  Otherwise, delete.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The amount of deleterious material in each size group of coarse aggregate shall not exceed the limits in the 
following table when tested as indicated.</TXT><BRK/>
<TBL><THD><BRK/>
<HL4>LIMITS OF DELETERIOUS MATERIALS IN COARSE</HL4><BRK/>
<HL4>AGGREGATE FOR ROAD PAVEMENTS</HL4><BRK/>
<HL4>Percentage by Mass</HL4><BRK/></THD>
<BRK/>
          Clay lumps and friable particles                    2.0<BRK/>
          (<RID>ASTM C 142</RID>)<BRK/>
<BRK/>
          Material finer than 0.075 mm                        1.0<BRK/>
          (No. 200 sieve) (<RID>ASTM C 117</RID>)<BRK/>
<BRK/>
          Lightweight particles                               1.0<BRK/>
          (<RID>ASTM C 123</RID>)<BRK/>
<BRK/>
          Other soft particles                                2.0<BRK/>
          (<RID>COE CRD-C 130</RID>)<BRK/>
<BRK/>
         Total of all deleterious substances,                 5.0 <BRK/>
         exclusive of material finer than <BRK/>
         <MET>0.075 mm </MET><ENG>No. 200 sieve</ENG><BRK/></TBL>
<BRK/>
<TXT>The limit for material finer than the <MET>0.075 mm </MET><ENG>No. 200</ENG> sieve will be increased to 1.5 percent for crushed aggregates 
consisting of crusher dust that is essentially free from clay or shale.  The separation medium for lightweight 
particles must have a density of 2.0 Mg/cubic meter (Sp. Gr. 2.0).  This limit does not apply to coarse aggregate 
manufactured from blast-furnace slag unless contamination is evident.</TXT><BRK/>
<BRK/></SPT>
]</SPT><SPT><TTL>2.2.3   Fine Aggregate</TTL><BRK/>
<BRK/>
<SPT><TTL>2.2.3.1   Composition</TTL><BRK/>
<BRK/>
<TXT>Ensure fine aggregate consists of natural sand, manufactured sand, or a combination of the two, and is composed 
of clean, hard, durable particles.  [Ensure aggregate used for paving compass calibration hardstands is free 
of materials having undesirable magnetic properties, including magnetite in granite, high-iron minerals in traprcok, 
and pyrite in limestone.] Irrespective of the source from which it is obtained, all fine aggregate must be composed 
of clean, hard, durable particles meeting the requirements of <RID>ASTM C 33</RID>.  Stockpile and batch each type of fine 
aggregate separately.  Particles of the fine aggregate must be generally spherical or cubical in shape.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3.2   Grading</TTL><BRK/>
<BRK/>
<TXT>Ensure grading of the fine aggregate, as delivered to the mixer, conforms to the requirements of <RID>ASTM C 33</RID> and 
has a fineness modulus of not less than 2.50 nor more than 3.00.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3.3   Deleterious Material</TTL><BRK/>
<BRK/>
<TXT>The amount of deleterious material in the fine aggregate must not exceed the following limits by mass:</TXT><BRK/>
<BRK/>
<TBL><THD>                   Material                        Percentage by Mass<BRK/>
                  __________                       ___________________<BRK/>
<BRK/></THD>
  Clay lumps and friable particles <RID>ASTM C 142</RID>                    1.0<BRK/>
<BRK/>
  Material finer than 0.075 mm (No. 200 sieve) <RID>ASTM C 117</RID>        3.0<BRK/>
<BRK/>
  Lightweight particles <RID>ASTM C 123</RID> using a medium                0.5<BRK/>
  with a density of 2.0 Mg/cubic meter (Sp. Gr. of 2.0))<BRK/>
<BRK/>
                        Total of all above                       3.0</TBL><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>2.3   CHEMICAL ADMIXTURES</TTL><BRK/>
<BRK/>
<SPT><TTL>2.3.1   General Requirements</TTL><BRK/>
<BRK/>
<TXT>Chemical admixtures may only be used when the specific admixture type and manufacturer is the same material used 
in the mixture proportioning studies.  The air-entraining admixture must conform to <RID>ASTM C 260</RID>.  An accelerator 
conforming to <RID>ASTM C 494/C 494M</RID>, Type C, may be used only when specified in paragraph: SPECIFIED CONCRETE STRENGTH 
AND OTHER PROPERTIES and must not be used to reduce the amount of cementitious material used.  Calcium chloride 
and admixtures containing calcium chloride must not be used.  Ensure retarding or water-reducing admixture meets 
the requirements of <RID>ASTM C 494/C 494M</RID>, Type A,  B, or D, except that the 6-month and 1-year compressive strength 
tests are waived.  <RID>ASTM C 494/C 494M</RID>, Type F and G high range water reducing admixtures and <RID>ASTM C 1017/C 1017M </RID>
 admixtures must not be used.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.2   Lithium Nitrate</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Contact the TSCMX, Navy EFD, NFESC, or AFCESA before specifying Lithium 
Nitrate to mitigate Aggregate-Silica Reaction (ASR).  Coordinate with manufacturer 
regarding Lithium Nitrate dosage.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure the lithium admixture is a nominal 30 percent aqueous solution of Lithium Nitrate, with a density of <MET>1.2 
kilograms per liter </MET><ENG>10 pounds per gallon</ENG>, and has the approximate chemical form as shown below:</TXT><BRK/>
<TBL><BRK/>
<THD>              <HL1> Constituent</HL1>             <HL1> Limit (Percent by Mass</HL1>)</THD><BRK/>
            LiNo (Lithium Nitrate)           30 +/- 0.5<BRK/>
            SO   (Sulfate Ion)              0.1  (max)<BRK/>
            Cl   (Chloride Ion)             0.2  (max)<BRK/>
            Na   (Sodium Ion)               0.1  (max)<BRK/>
            K    (Potassium Ion)            0.1  (max)</TBL><BRK/>
<BRK/>
<TXT>The Lithium Nitrate manufacturer must provide a trained representative to supervise the lithium nitrate admixture 
dispensing and mixing operations.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.4   MEMBRANE FORMING CURING COMPOUND</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  ASTM C 309 may be used for roads and streets and Navy airfield pavements.  
Use CRD-C 300 for Army or Air Force airfield pavement projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Membrane forming curing compound shall [be a white pigmented compound conforming to <RID>COE CRD-C 300</RID>.] [conform 
to <RID>ASTM C 309</RID>, white-pigmented Type 2, Class B].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5   WATER</TTL><BRK/>
<BRK/>
<TXT>Water for mixing and curing must be fresh, clean, potable, and free of injurious amounts of oil, acid, salt, 
or alkali, except that non-potable water may be used if it meets the requirements of <RID>ASTM C 94/C 94M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6   JOINT MATERIALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit as appropriate for project requirements.  Coordinate with UFGS 02760 
and 02762 for Army and Air Force projects.  </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.6.1   Expansion Joint Material</TTL><BRK/>
<BRK/>
<TXT>Expansion joint filler must be a preformed material conforming to [<RID>ASTM D 1751</RID> or] [<RID>ASTM D 1752</RID> Type [II] [III].]  
Expansion joint filler must be <MET>20 mm </MET><ENG>3/4 inch</ENG> thick, and must be furnished in a single full depth piece.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6.2   Slip Joint Material</TTL><BRK/>
<BRK/>
<TXT>Slip joint material must be <MET>6 mm </MET><ENG>1/4 inch</ENG> thick expansion joint filler conforming to para: EXPANSION JOINT MATERIAL.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.7   REINFORCING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit these paragraphs to conform to project requirements.  Delete those 
not needed.  Add epoxy-coated bars (ASTM A 775) or low-alloy bars (ASTM A 706) 
when required by design.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure all reinforcement is free from loose, flaky rust, loose scale, oil, grease, mud, or other coatings that 
might reduce the bond with concrete.  Removal of thin powdery rust and tight rust is not required.  However, 
do not use reinforcing steel which is rusted to the extent that it does not conform to the required dimensions 
or mechanical properties.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.7.1   Reinforcing Bars and Bar Mats</TTL><BRK/>
<BRK/>
<TXT>ensure reinforcing bars conform to [<RID>ASTM A 615/A 615M</RID>, billet-steel] [<RID>ASTM A 996/A 996M</RID>, rail and axle steel], 
Grade 60 [_____].  Ensure bar mats conform to <RID>ASTM A 184/A 184M</RID>.  The bar members must be [billet] [rail] [axle] 
steel.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.2   Deformed Welded Wire Reinforcement</TTL><BRK/>
<BRK/>
<TXT>Esure deformed Welded Wire Reinforcement conforms to <RID>ASTM A 497/A 497M</RID>, and is furnished in flat sheets.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.7.2.1   Fiber Reinforcement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Fibers may be used as an alternate for welded wire fabric used for secondary 
"reinforcement" (help control plastic shrinkage).  Do not use fibers for a structural 
value. Fibers are required in concrete for AV-8 landing pad high temperature 
pavements.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASTM C 1116/C 1116M</RID>.  Use 100 percent virgin nylon or polypropylene fibers, 23 micron diameter,<MET> 19 mm</MET><ENG> 3/4 inch</ENG>
 length with a minimum tensile strength of<MET> 482 MPa</MET><ENG> 70 ksi</ENG>.  Add fibers to the concrete mix at the batch plant 
at the rate of<MET> 0.89 kg per cubic meter</MET><ENG> 1.5 lbs. per cubic yard</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>2.8   DOWELS AND TIE BARS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Retain paragraph on dowels.  Even if not required, design should normally 
allow dowels as an option.  Edit tie bars as required by design.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.8.1   Dowels</TTL><BRK/>
<BRK/>
<TXT>Dowels must be single piece bars fabricated or cut to length at the shop or mill before delivery to the site.  
Ensure dowels are free of loose, flaky rust and loose scale and are clean and straight.  Dowels may be sheared 
to length provided that the deformation from true shape caused by shearing does not exceed <MET>1 mm </MET><ENG>0.04 inch</ENG> on 
the diameter of the dowel and does not extend more than <MET>1 mm </MET><ENG>0.04 inch</ENG> from the end of the dowel.  Dowels must 
be plain (non-deformed) steel bars conforming to <RID>ASTM A 615/A 615M</RID>, Grade 40 or 60; <RID>ASTM A 996/A 996M</RID>, Grade 
50 or 60.  Ensure paint for dowels conforms to <RID>MIL-DTL-24441/20</RID>.  As an alternate to paint, epoxy coatings conforming 
to <RID>ASTM A 775/A 775M</RID> may be used.  Ensure grout retention rings are fully circular metal or plastic devices capable 
of supporting the dowel until the epoxy hardens.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.2   Dowel Bar Assemblies</TTL><BRK/>
<BRK/>
<TXT>Dowel bar assemblies must consist of a framework of metal bars or wires arranged to provide rigid support for 
the dowels throughout the paving operation, with a minimum of four continuous bars or wires extending along the 
joint line.  ensure the dowels are welded to the assembly or held firmly by mechanical locking arrangements that 
will prevent them from rising, sliding out, or becoming distorted during paving operations.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.3   Tie Bars</TTL><BRK/>
<BRK/>
<TXT>Ensure tie bars are deformed steel bars conforming to <RID>ASTM A 615/A 615M</RID>, or <RID>ASTM A 996/A 996M</RID>, Grade 60 [_____], 
and of the sizes and dimensions indicated.  Deformed rail steel bars and high-strength billet or axle steel bars, 
Grade 50 or higher, must not be used for bars that are bent and straightened during construction.  Refer to Section 
<SRF>34 73 13</SRF> MOORING AND GROUNDING POINTS FOR AIRCRAFT.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.9   EPOXY RESIN</TTL><BRK/>
<BRK/>
<TXT>Ensure all epoxy-resin materials are two-component materials conforming to the requirements of <RID>ASTM C 881/C 881M</RID>
, Class as appropriate for each application temperature to be encountered, except that in addition, the materials 
must meet the following requirements:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Material for use for embedding dowels and anchor bolts must be Type IV, Grade 3.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Material for use as patching materials for complete filling of spalls and other voids and 
for use in preparing epoxy resin mortar must be Type III, Grade as approved.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Material for use for injecting cracks must be Type IV, Grade 1.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Material for bonding freshly mixed portland cement concrete or mortar or freshly mixed epoxy 
resin concrete or mortar to hardened concrete must be Type V, Grade as approved.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.10   SPECIFIED CONCRETE STRENGTH AND OTHER PROPERTIES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Fill in blanks as appropriate.  Specified strength must be the flexural 
strength used in the structural design of the pavement and should not exceed 
650 psi (4.5 MPa) at 90 days of age.  Designer must also ensure that this strength 
is attainable with the available aggregates, without excessive cement content.  
Air content should be specified as 6 percent where freezing and thawing is a 
concern and 4 percent where it is not a concern.  Specify strength at 90 days.  
However, modify to 28-days in line 2 if 28-day strength is used in paragraph, 
Flexural Strength and Thickness.  Be sure this and succeeding paragraphs correlate.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.10.1   Specified Flexural Strength</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The designer has the option BEAMS or CYLINDERS/BEAMS to specify flexural 
strength for concrete.  Use first sentence option for BEAMS and second sentence 
option for CYLINDERS/BEAMS.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Specified flexural strength, R, for concrete is [_____] <MET>MPa </MET><ENG>psi</ENG> at [28] [90] days, [as determined by tests made 
in accordance with <RID>ASTM C 78</RID> of beams fabricated and cured in accordance with <RID>ASTM C 192/C 192M</RID>][as determined 
by equivalent flexural strength, as specified in paragraph: Mixture Proportioning for Flexural Strength].  Maximum 
allowable water-cementitious material ratio is 0.45.  The water-cementitious material ratio will be the equivalent 
water-cement ratio as determined by conversion from the weight ratio of water to cement plus pozzolan, and ground 
granulated blast furnace slag by the mass equivalency method described in <RID>ACI 211.1</RID>.  The concrete must be air-entrained 
with a total air content of [_____] plus or minus 1.5 percentage points, at the point of placement.  Determine 
air content in accordance with <RID>ASTM C 231</RID>.  The maximum allowable slump of the concrete at the point of placement 
is <MET>50 mm </MET><ENG>2 inches</ENG> for pavement constructed with fixed forms.  For slipformed pavement, at the start of the project, 
select a maximum allowable slump which will produce in-place pavement meeting the specified tolerances for control 
of edge slump.  The selected slump is applicable to both pilot and fill-in lanes.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.10.2   Concrete Temperature</TTL><BRK/>
<BRK/>
<TXT>The temperature of the concrete as delivered must conform to the requirements of paragraphs: PAVING IN HOT WEATHER 
and PAVING IN COLD WEATHER.  Determine temperature of concrete in accordance with <RID>ASTM C 1064/C 1064M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.10.3   Concrete Strength for Final Acceptance</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The designer has the option to specify concrete strength by using CYLINDERS/BEAMS 
or BEAMS.  Use first bracketed sentence for CYLINDERS/BEAMS and the scond bracketed 
sentence for BEAMS.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[The strength of the concrete will be considered acceptable when the average equivalent [90-day] [28-day] flexural 
strengths for each lot are above the'Specified Flexural Strength' as determined by correlation with 14-day compressive 
strength tests.][The strength of the concrete will be considered acceptable when the [90-day] [28-day] flexural 
strengths for each lot are above the'Specified Flexural Strength'.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.11   MIXTURE PROPORTIONS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit bracketed items as appropriate.  Normally, permit accelerator only 
with fast-track paving.  If approval has been obtained and airfield pavement 
has been designed and specified for 28-day flexural strength in paragraph: SPECIFIED 
FLEXURAL STRENGTH, modify the following subparagraphs accordingly.  Do the same 
if this is road pavement designed for 28-day strength.  Use the higher bracketed 
cement content if pozzolan is used.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.11.1   Composition</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the first option for Army and Air Force jobs; use the second option 
for Navy jobs only.<BRK/>
<BRK/>
For concrete exposed to high temperatures under F/A-18 or B-1 auxiliary power 
unit exhaust the following mix (per cubic yard) can be used as a guide:<BRK/>
<BRK/>
Type I-II low alkali cement       529 pounds   <BRK/>
Fly ash Class F                   176 pounds      <BRK/>
Expanded Shale Coarse Aggregate   800 pounds   <BRK/>
(e.g. Stalite or Haydite 3/4 to #4)<BRK/>
Expanded Shale Fine Aggregate     926 pounds   <BRK/>
(e.g. Stalite or Haydite minus #4)<BRK/>
Water                             35 gallons   <BRK/>
Slump (superplasticizer allowed)  4 inches   <BRK/>
Air                               5-8%             <BRK/>
Water/Cementitious Ratio          0.41<BRK/>
Flexural Strength at [56] days    4.5 MPa [650 psi]<BRK/>
Compressive Strength at [56] days 34.5 MPa [5000psi]<BRK/>
<BRK/>
Final weight (per cubic yard) will be affected by the actual aggregate density. 
Solite aggregate has also been used successfully.<BRK/>
<BRK/>
For AV-8 applications add fibers in accordance with paragraph 2.1.4., or use 
trap rock.<BRK/>
<BRK/>
Magnesium ammonium phosphate cement (such as Set 45) will provide increased 
resistance to thermal and chemical deterioration, but will result in very expensive 
concrete that sets very quickly.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure concrete is composed of cementitious material, water, fine and coarse aggregates, and admixtures.  <TAI OPT="ARMY/AIR FORCE">Class 
F flyash or Class N Pozzolan, if used with non alkali reactive aggregates, must consist of not less than 15 percent 
of the cementitious material by mass and not more than 35 percent. GGBF slag, if used with non alkali reactive 
aggregates, must consist of not less than 20 percent of the cementitious material by mass and not more than 50 
percent.  If Class F fly ash, Class N pozzolan, or GGBF slag is required to mitigate potential alkali-aggregate 
reactivity, the percentage by mass, as determined from the modified <RID>ASTM C 1260</RID> testing must be used in the mixture 
proportioning studies.  </TAI><TAI OPT="NAVY">Use Class F pozzolan or GGBF slag in all concrete mixtures.  Class F pozzolan must consist 
of not less than 25 percent of cementitious materials by mass and not more than 40 percent.  GGBF slag must consist 
of not less than 40 percent of the cementitious material by mass and not more than 50 percent.  </TAI>The total cementitious 
material content must be at least [<MET>280 kg/cubic meter </MET><ENG>470 lb./cu. yd.</ENG>] [<MET>310 kg/cubic meter </MET><ENG>517 lb./cu. yd.</ENG>].  
Ensure admixtures consist of air entraining admixture [and also includes] [and may also include, as approved] 
[accelerator] [retarder] [water-reducing admixture].</TXT><BRK/>
<BRK/>
<SPT><TTL>2.11.1.1   Concrete for High Temperature Pavements</TTL><BRK/>
<BRK/>
<TXT>Ensure concrete exposed to high temperatures under jet exhaust conforms to one of the following mixes:</TXT>  <BRK/>
<BRK/>
<LST>Concrete exposed to the auxiliary power unit of F/A-18 and B-1 aircraft should use expanded shale for 
both the coarse and fine aggregate.</LST> <BRK/>
<BRK/>
<LST>Concrete in AV-8 landing pads should use expanded shale for both the coarse and fine aggregate, and fibers 
in accordance with paragraph: FIBER REINFORCEMENT.</LST> <BRK/>
<BRK/>
<LST>Alternatively, concrete in continuously reinforced AV-8 landing pads can include fine grained trap rock 
from unweathered diabase or basalt.</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.11.2   <SUB>Proportioning Studies</SUB></TTL><BRK/>
<BRK/>
<TXT>Trial design batches, mixture proportioning studies, and testing requirements are the responsibility of the Contractor.  
Base trial mixtures having proportions, slumps, and air content suitable for the work on methodology described 
in <RID>ACI 211.1</RID>, modified as necessary to accommodate flexural strength.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.11.2.1   Water-Cement Ratio</TTL><BRK/>
<BRK/>
<TXT>Use at least three different water-cement ratios, which will produce a range of strength encompassing that required 
on the project.  The maximum allowable water-cement ratio required in paragraph: SPECIFIED FLEXURAL STRENGTH 
will be the equivalent water-cement ratio as determined by conversion from the mass ratio of water to cement 
plus pozzolan, and ground granulated blast furnace (GGBF) slag by the weight equivalency method as described 
in <RID>ACI 211.1</RID>.  In the case where GGBF slag is used, include the mass of the GGBF slag in the equations in <RID>ACI 211.1</RID>
 for the term P, which is used to denote the mass of pozzolan.  Proporation laboratory trial mixtures for maximum 
permitted slump and air content.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.11.2.2   Trial Mixture Studies</TTL><BRK/>
<BRK/>
<TXT>Make separate sets of trial mixture studies for each combination of cementitious materials and each combination 
of admixtures proposed for use.  Do not use a combination of either until proven by such studies, except that, 
if approved in writing and otherwise permitted by these specifications, an accelerator or a retarder may be used 
without separate trial mixture study.  Design each mixture to promote easy and suitable concrete placement, consolidation 
and finishing, and to prevent segregation and excessive bleeding.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.11.2.3   Mixture Proportioning Procedure</TTL><BRK/>
<BRK/>
<TXT>The Contractor must perform the following:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Fabricate, cure and test 6 test specimens per age for each mixture at 28 [ ] and 90 [ ] 
days.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Using the average strength for each w/(c+p), plot the results from each mixture on separate 
graphs for w/(c+p) versus 28-day strength.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  From the graphs select a w/(c+p) which will produce a mixture giving a 28-day strength equal 
to the required strength.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.11.3   Average Strength Required for Mixtures</TTL><BRK/>
<BRK/>
<TXT>In order to ensure meeting, during production, the strength requirements specified, the mixture proportions selected 
must produce a required average strength, f'cr, exceeding the specified strength, f'c, in accordance with procedures 
in Chapter 3 of <RID>ACI 301</RID>, "Proportioning."</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   PREPARATION FOR PAVING</TTL><BRK/>
<BRK/>
<TXT>Before commencing paving, perform the following:</TXT><BRK/>
<BRK/>
<ITM>Ensure forms are in place, cleaned, coated, and adequately supported. </ITM> <BRK/>
<BRK/>
<ITM>Ensure equipment for spreading, consolidating, screeding, finishing, and texturing concrete 
is at the paving site, clean and in proper working order.</ITM> <BRK/>
<BRK/>
<ITM>Ensure all equipment and material for curing and for protecting concrete from weather or mechanical 
damage is at the paving site, in proper working condition, and in sufficient amount for the 
entire placement.</ITM><BRK/>
<BRK/>
<SPT><TTL>3.1.1   Weather Prevention</TTL><BRK/>
<BRK/>
<TXT>When windy conditions during paving appear probable, equipment and material must be at the paving site to provide 
windbreaks, shading, fogging, or other action to prevent plastic shrinkage cracking or other damaging drying 
of the concrete.</TXT><BRK/>
<BRK/></SPT>
<BRK/></SPT>
<SPT><TTL>3.2   CONDITIONING OF UNDERLYING MATERIAL</TTL><BRK/>
<BRK/>
<TXT>Underlying material, [subgrade] [base course] [subbase course], upon which concrete is to be placed must be clean, 
damp, and free from debris, waste concrete or cement, frost, ice, and standing or running water.  After the underlying 
material has been prepared for concrete placement, no equipment is permitted thereon.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3   WEATHER LIMITATIONS</TTL><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Placement and Protection During Inclement Weather</TTL><BRK/>
<BRK/>
<TXT>Follow practice found in <RID>ACI 325.9R</RID>, Chapter 10.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.2   Paving in Hot Weather</TTL><BRK/>
<BRK/>
<TXT>The temperature of concrete must not exceed <MET>32 degrees C.</MET> <ENG>90 degrees F.</ENG>  Ensure steel forms, dowels and reinforcing 
is cooled prior to concrete placement when steel temperatures are greater than <MET>49 degrees C</MET> <ENG>120 degrees F</ENG>. Follow 
practices found in <RID>ACI 305R</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.3   Prevention of Plastic Shrinkage Cracking</TTL><BRK/>
<BRK/>
<TXT>During weather with low humidity, and particularly with high temperature and appreciable wind, develop and institute 
measures to prevent plastic shrinkage cracks from developing.  If plastic shrinkage cracking occurs, halt further 
placement of concrete until protective measures are in place to prevent further cracking.  Periods of high potential 
for plastic shrinkage cracking can be anticipated by use of Fig. 2.1.5 of <RID>ACI 305R</RID>.  </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.4   Paving in Cold Weather</TTL><BRK/>
<BRK/>
<TXT>Ensure cold weather paving conforms to <RID>ACI 306R</RID>.  Do not begin placement of concrete unless the ambient temperature 
is at least <MET>2 degrees C </MET><ENG>35 degrees F</ENG> and rising.  Thereafter, halt placement of concrete whenever the ambient 
temperature drops below <MET>5 degrees C </MET><ENG>40 degrees F</ENG>.  When the ambient temperature is less than <MET>10 degrees C </MET><ENG>50 
degrees F</ENG>, ensure the temperature of the concrete when placed is not less than <MET>10 degrees C </MET><ENG>50 degrees F</ENG> nor 
more than <MET>25 degrees C </MET><ENG>75 degrees F</ENG>.  Ensure materials entering the mixer are free from ice, snow, and frozen 
lumps.  Do not incorporate salt, chemicals or other materials in the concrete to prevent freezing.  If allowed 
under paragraph: MIXTURE PROPORTIONS, an accelerating admixture may be used when the ambient temperature is below <MET>
10 degrees C </MET><ENG>50 degrees F</ENG>.  Provide covering and other means for maintaining the concrete at a temperature of 
at least <MET>10 degrees C </MET><ENG>50 degrees F</ENG> for not less than 72 hours after placing, and at a temperature above freezing 
for the remainder of the curing period.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.4   CONCRETE PRODUCTION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Designer must correlate these paragraphs with paragraph EQUIPMENT.  Delete 
item in brackets if truck mixers are not permitted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensuyre batching, mixing, and transporting conforms to <RID>ASTM C 94/C 94M</RID>.  The equipment must have a capacity sufficient 
to maintain a continuous, uniform forward movement of the paver.  A batch ticket from the operator of the batching 
plant must accompany every load of concrete delivered to the paving site.  Ensure tickets are on approved forms 
and show at least the mass, or volume, of all ingredients in each batch delivered, [the water meter and revolution 
meter reading on truck mixers] and the time of day.  Deliver tickets to the placing foreman who must keep them 
on file and deliver them to the Government weekly.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5   PAVING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Designer must correlate these paragraphs with paragraph EQUIPMENT.  UFGS 
02753 should be used if slip form paving operations are anticipated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.5.1   General Requirements</TTL><BRK/>
<BRK/>
<TXT>Construct pavement with paving and finishing equipment utilizing rigid fixed forms or by use of slipform paving 
equipment.  Control paving equipment and its operation, and coordinate with all other operations, such that the 
paver-finisher has a continuous forward movement, at a reasonably uniform speed, from beginning to end of each 
paving lane, except for inadvertent equipment breakdown.  </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2   Consolidation</TTL><BRK/>
<BRK/>
<TXT>Consolidate concrete with the specified type of lane-spanning, gang-mounted, mechanical, immersion type vibrating 
equipment mounted in front of the paver, supplemented, in rare instances as specified, by hand-operated vibrators.  
Insert the vibrators into the concrete to a depth that will provide the best full-depth consolidation but not 
closer to the underlying material than <MET>50 mm </MET><ENG>2 inches</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.3   Fixed Form Paving</TTL><BRK/>
<BRK/>
<TXT>Ensure paving equipment for fixed-form paving and its operation conforms to the requirements of paragraph EQUIPMENT, 
all requirements specified above under paragraph PAVING and as specified herein.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.5.3.1   Forms for Fixed Form Paving</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete subparagraph d. when overlay pavements are not required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>a.  Ensure straight forms are made of steel and furnished in sections not less than <MET>3 m </MET><ENG>10 feet</ENG>
 in length.  Use flexible or curved forms of proper radius for curves of <MET>31 m </MET><ENG>100-foot</ENG> radius 
or less.  Ensure wood forms for curves and fillets are made of well-seasoned, surfaced plank 
or plywood, straight, and free from warp or bend.  Ensure wood forms are adequate in strength 
and rigidly braced.  Forms must have a depth equal to the pavement thickness at the edge.  Maximum 
vertical deviation of top of any side form, including joints, must not vary from a true plane 
more than <MET>3 mm </MET><ENG>1/8 inch</ENG> in <MET>3 m </MET><ENG>10 feet</ENG>, and the upstanding leg shall not vary more than <MET>6 mm </MET><ENG>
1/4 inch</ENG>.  </ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Tightly lock form sections and ensure they are free from play or movement in any direction.  
Provide forms with adequate devices for secure settings so that when in place they will withstand, 
without visible spring or settlement, the impact and vibration of the consolidating and finishing 
equipment.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Set forms for full bearing on foundation for entire length and width and in alignment with 
edge of finished pavement.  Support forms during entire operation of placing, compaction, and 
finishing so that forms will not deviate vertically more than <MET>3 mm </MET><ENG>0.01 foot</ENG> from required grade 
and elevations indicated.  Do not place concrete until setting of forms has been checked and 
approved by the CQC team.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  For overlay pavements and for other locations where forms must be set on existing pavements, 
hold forms securely in place with stakes or by other approved methods.  Holes in existing pavements 
for form stakes must be carefully drilled by methods which will not crack or spall the existing 
pavement.  After use, fill the holes flush with the surrounding surface using approved material, 
prior to overlying materials being placed.  Immediately discontinue any method which does not 
hold the form securely or which damages the existing pavement.  Prior to setting forms for paving 
operations, demonstrate the proposed form setting procedures at an approved location and do 
not proceed further until the proposed method is approved by the Contracting Officer.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5.4   Slipform Paving</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Retain slipform paving as an option unless there are specific, valid 
reasons for deleting it.  Be sure all other paragraphs correlate with choice 
made here.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.5.4.1   General</TTL><BRK/>
<BRK/>
<TXT>Ensure paving equipment for slipform paving and its operation conforms to the requirement of paragraph EQUIPMENT 
and all requirements specified above. </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.4.2   Guidelines for Slipform Paving</TTL><BRK/>
<BRK/>
<TXT>Guidelines must be accurately and securely installed well in advance of concrete placement.  Provide supports 
at necessary intervals to eliminate all sag in the guideline when properly tightened.  Ensure the guideline is 
high strength wire set with sufficient tension to remove all sag between supports.  Securely stake supports to 
the underlying material or make other provisions to ensure that the supports will not be displaced when the guideline 
is tightened or when the guideline or supports are accidentally touched by workmen or equipment during construction.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.4.3   Laser Controls</TTL><BRK/>
<BRK/>
<TXT>If the Contractor proposes to use any type of automatic laser controls, a detailed description of the system 
must be submitted and a trial field demonstration performed in the presence of the Contracting Officer at least 
one week prior to start of paving.  Approval of the control system is based on the results of the demonstration 
and on continuing satisfactory operation during paving.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5.5   Placing Reinforcing Steel</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete bracketed item if CRCP is not being constructed.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Position the reinforcement on suitable chairs securely fastened to the subgrade prior to concrete placement.  
Vibrate concrete after the steel has been placed.  Regardless of placement procedure, ensure the reinforcing 
steel is free from coatings which could impair bond between the steel and concrete, and indicate laps in the 
reinforcement as indicated.  In lieu of the above, automatic reinforcement depressing attachments may be used 
to position the reinforcement provided the entire operation is approved by the Contracting Officer.  Regardless 
of the equipment or procedures used for installing reinforcement, ensure that the entire depth of concrete is 
adequately consolidated.  </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.6   Placing Dowels and Tie Bars</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete references to slipform paving installation of dowels and tie bars 
if slipform paving is not allowed.  Delete references to installation in contraction 
joints if not required.  Delete bracketed references to tie bars, if tie bars 
are not used.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The method used in installing and holding dowels in position must ensure that the error in alignment of any dowel 
from its required horizontal and vertical alignment after the pavement has been completed will not be greater 
than <MET>3 mm per 300 mm </MET><ENG>1/8 in. per ft</ENG>.  Except as otherwise specified below, horizontal spacing  of dowels must 
be within a tolerance of plus or minus <MET>15 mm </MET><ENG>5/8 inch</ENG>.  Check the horizontal alignment with a framing square.  
Do not place dowels [and tie bars] closer than 0.6 times the dowel bar [tie bar] length to the planned joint 
line.  If the last regularly spaced dowel [tie bar] is closer than that dimension, it must be moved away from 
the joint to a location 0.6 time the dowel bar [tie bar] length.  Install dowels as specified in the following 
subparagraphs.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.5.6.1   Contraction Joints</TTL><BRK/>
<BRK/>
<TXT>Hold dowels [and tie bars] in longitudinal and transverse contraction joints within the paving lane securely 
in place, as indicated, by means of rigid metal frames or basket assemblies of an approved type.  Hold the basket 
assemblies securely in the proper location by means of suitable pins or anchors.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.6.2   Construction Joints-Fixed Form Paving</TTL><BRK/>
<BRK/>
<TXT>Install dowels [and tie bars] using the bonded-in-place method.  Do not install by removing and replacing in 
preformed holes.  Prepare dowels [and tie bars] and place across joints where indicated, correctly aligned, and 
securely held in the proper horizontal and vertical position during placing and finishing operations, by means 
of devices fastened to the forms.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.6.3   Dowels Installed In Hardened Concrete</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The first option is for "Cylinders/Beams" and the second option is for 
"Beams".</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Install dowels in hardened concrete by bonding the dowels into holes drilled into the hardened concrete.  Drill 
holes approximately <MET>3 mm </MET><ENG>1/8 inch</ENG> greater in diameter than the dowels into the hardened concrete.  Repair any 
damage to the concrete face during drilling as directed.  Bond dowels in the drilled holes using epoxy resin.  
Inject epoxy resin at the back of the hole before installing the dowel and extruded to the collar during insertion 
of the dowel so as to completely fill the void around the dowel.  Do not apply by buttering the dowel.  Hold 
the dowels in alignment at the collar of the hole, after insertion and before the grout hardens, by means of 
a suitable metal or plastic grout retention ring fitted around the dowel.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.6.4   Lubricating Dowel Bars</TTL><BRK/>
<BRK/>
<TXT>Wipe clean the portion of each dowel intended to move within the concrete or expansion cap and coat with a thin, 
even film of lubricating oil before the concrete is placed.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.6   FINISHING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit bracketed items as appropriate.  Retain slipform paving subparagraph 
only when it is acceptable.  Delete Other Types of Finishing Equipment here 
and in PART 1, if not wanted.  Hand finishing is to be allowed only for isolated, 
small, odd-shaped slabs or places inaccessible to the paver.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Finishing operations shall be a continuing part of placing operations starting immediately behind the strike-off 
of the paver.  Provide initial finishing by the transverse screed or extrusion plate.  The sequence of operations 
are transverse finishing, longitudinal machine floating if used, straightedge finishing, texturing, and then 
edging of joints.  Finish by the machine method.  Use the hand method only on isolated areas of odd slab widths 
or shapes and in the event of a breakdown of the mechanical finishing equipment.  Keep supplemental hand finishing 
for machine finished pavement to an absolute minimum.  Make every effort to prevent bringing excess paste to 
the surface and halt any operations which produce more than <MET>3 mm </MET><ENG>1/8 inch</ENG> of paste (mortar, water, laitance, 
etc.) over the top layer of coarse aggregate immediately and the equipment, mixture, or procedures modified as 
necessary.  </TXT><BRK/>
<BRK/>
<SPT><TTL>3.6.1   Machine Finishing With Fixed Forms</TTL><BRK/>
<BRK/>
<TXT>Use a machine designed to ride the forms and operate to screed and consolidate the concrete.  Replace machines 
that cause displacement of the forms.  The machine shall make only one pass over each area of pavement.  If the 
equipment and procedures do not produce a surface of uniform texture, true to grade, in one pass, immediately 
stop the operation and the equipment, mixture, and procedures adjusted as necessary.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.2   Machine Finishing with Slipform Pavers.</TTL><BRK/>
<BRK/>
<TXT>Operate the slipform paver so that only a very minimum of additional finishing work is required to produce pavement 
surfaces and edges meeting the specified tolerances.  A self-propelled nonrotating pipe float may be used  while 
the concrete is still plastic, to remove minor irregularities and score marks.  allow only one pass of the pipe 
float.  If there is concrete slurry or fluid paste on the surface that runs over the edge of the pavement, immediately 
stop the paving operation and the equipment, mixture, or operation modified to prevent formation of such slurry.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.3   Surface Correction and Testing</TTL>   <BRK/>
<BRK/>
<TXT>After all other finishing is completed but while the concrete is still plastic, eliminate minor irregularities 
and score marks in the pavement surface by means of cutting straightedges.  Use straightedges <MET>4 m </MET><ENG>12 feet</ENG> in 
length and operate from the sides of the pavement and from bridges.  Equip a straightedge operated from the side 
of the pavement with a handle <MET>1 m </MET><ENG>3 feet</ENG> longer than one-half the width of the pavement.  Then test the  surface 
for trueness with a straightedge held in successive positions parallel and at right angles to the center line 
of the pavement, and the whole area covered as necessary to detect variations.  Advance the straightedge along 
the pavement in successive stages of not more than one-half the length of the straightedge.  Immediately fill 
depressions with freshly mixed concrete, then strike off, consolidate, and refinish.  Strike off and refinish 
projections above the required elevation.  Produce the surface finish of the pavement essentially by the finishing 
machine and not by subsequent hand finishing operations.  All hand finishing operations are subject to approval 
and must be modified when directed.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.6.3.1   Edge Slump</TTL><BRK/>
<BRK/>
<TXT>Determine slump of edges with a<MET> 3.66 m</MET><ENG> 12 foot</ENG> straightedge.  Before the concrete hardens, correct edge slump 
of pavement exceeding<MET> 6 mm</MET><ENG> 1/4 inch</ENG> at edge of pavement.  Limit the area affected by the downward movement of 
the concrete along the pavement edge to not more than<MET> 450 mm</MET><ENG> 18 inches</ENG> from the edge.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.6.4   Hand Finishing</TTL><BRK/>
<BRK/>
<TXT>As soon as placed and consolidated, strike off and screed concrete to required cross section.  If necessary, 
place and screed additional concrete and float until a satisfactory surface has been produced.  Advance floating 
operation not more than half the length of the float and then continue over new and previously floated surfaces.  
Limit hand finishing to small irregular areas not accessible with finishing machine.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.5   Texturing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Designer must select type of texturing desired, retain that subparagraph, 
and delete the others.  A genuine effort should be made to determine the type 
of texturing, if any, desired by the using service.  If no guidance is given, 
the usual default method should be burlap drag.  Edit bracketed phrases as appropriate.  
For Air Force airfield paving projects, do not specify artificial turf or wire 
comb textures.  Use UFGS-02981A, GROOVING FOR AIRFIELD PAVEMENTS,  to specify 
saw-cut grooves. If other then a burlap drag textured finish is required, add 
the appropriate paragraph(s) as shown below.  Spring tine grooving is limited 
to use on roads and streets only.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Before the surface sheen has disappeared and before the concrete hardens, give the surface of the pavement a 
texture as described herein.  After curing is complete, thoroughly power broom all textured surfaces to remove 
all debris.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.6.5.1   Burlap Drag Surface</TTL><BRK/>
<BRK/>
<TXT>Apply surface texture by dragging the surface of the pavement, in the direction of the concrete placement, with 
an approved burlap drag.  Operate the drag with the fabric moist, and the fabric clean; change as required to 
keep clean.  Perform the dragging so as to produce a uniform finished surface having a fine sandy texture without 
disfiguring marks.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.5.2   Artificial Turf Drag Surface</TTL><BRK/>
<BRK/>
<TXT>Apply artificial turf texture by dragging the surface of the pavement in the direction of concrete placement 
with an approved full-width drag made with artificial turf. Ensure at least <MET>600 mm </MET><ENG>2 feet</ENG> of the artificial turf 
is in contact with the concrete surface during texturing operations.  Ensure the corrugations are uniform in 
appearance and approximately <MET>2 mm </MET><ENG>1/16 inch</ENG> in depth.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.5.3   Broom Texturing</TTL><BRK/>
<BRK/>
<TXT>Apply surface texture using an approved mechanical stiff bristle broom drag of a type that will uniformly score 
the surface transverse to the pavement center line.  The broom must be capable of traversing the full width of 
the pavement in a single pass at a uniform speed and with a uniform pressure.  Overlap successive passes of the 
broom the minimum necessary to obtain a uniformly textured surface.  Wash brooms thoroughly at frequent intervals 
during use.  Remove worn or damaged brooms from the job site.  Complete crooming before the concrete has hardened 
to the point where the surface will be unduly torn or roughened, but after hardening has progressed enough so 
that the mortar will not flow and reduce the sharpness of the scores.  Ensure the scores are uniform in appearance 
and approximately <MET>1.5 mm </MET><ENG>1/16 inch</ENG> in depth but not more than <MET>3 mm </MET><ENG>1/8 inch</ENG> in depth.  Hand brooming is permitted 
only on isolated odd shaped slabs or slabs where hand finishing is permitted.  For hand brooming, use brooms 
with handles longer than half the width of slab to be finished.  Draw the hand brooms transversely across the 
surface from the center line to each edge with slight overlapping strokes.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.5.4   Wire-Comb Texturing</TTL><BRK/>
<BRK/>
<TXT>Apply surface texture using an approved mechanical wire comb drag operated to comb the surface transverse to 
the pavement center line.  Use a comb capable of traversing the full width of the pavement in a single pass at 
a uniform speed and with a uniform pressure.  Overlap successive passes of the comb the minimum necessary to 
obtain a continuous and uniformly textured surface.  Complete texturing before the concrete has hardened to the 
point where the surface and edges will be unduly torn, but after hardening has progressed to the point where 
the serrations will not close up.  Ensure the serrations are <MET>2 to 5 mm </MET><ENG>1/16 to 3/16 inch</ENG> deep, <MET>1.5 to 3 mm </MET><ENG>1/16 
to 1/8 inch</ENG> wide, and spaced <MET>9.5 mm </MET><ENG>3/8 inch</ENG> apart.  Produce transverse texturing grooves in straight lines across 
each lane within a tolerance of plus or minus <MET>12 mm </MET><ENG>1/2 inch</ENG> of a true line.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.6.6   Edging</TTL><BRK/>
<BRK/>
<TXT>After texturing has been completed, carefully finish the edge of the slabs along the forms, along the edges of 
slipformed lanes, and at the joints with an edging tool to form a smooth rounded surface of <MET>3 mm </MET><ENG>1/8 inch</ENG> radius.  
Eliminate tool marks, smooth the edges and make true to line.  Do not add water to the surface during edging.  
Take extreme care to prevent overworking the concrete.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.7   Outlets in Pavement</TTL><BRK/>
<BRK/>
<TXT>Construct recesses for the tie-down anchors, lighting fixtures, and other outlets in the pavement to conform 
to the details and dimensions shown.  Carefully finish the concrete in these areas to provide a surface of the 
same texture as the surrounding area that will be within the requirements for plan grade and surface smoothness.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.7   CURING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Retain bracketed item at end of first paragraph mandating 24 hour moist 
cure only where locally required and only where approved by the using service.  
Membrane curing should be the first choice of curing methods.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.7.1   Protection of Concrete</TTL><BRK/>
<BRK/>
<TXT>Continuously protect concrete against loss of moisture and rapid temperature changes for at least 7 days from 
the completion of finishing operations.  Keep all equipment needed for adequate curing and protection of the 
concrete on hand and ready for use before actual concrete placement begins.  If any selected method of curing 
does not afford the proper curing and protection against concrete cracking, remove and replace the damaged pavement, 
and employ another method of curing as directed.  Accomplish curing by one of the following methods [except use 
only moist curing for the first 24 hours].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.2   Membrane Curing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The first option is for Army and Air Force jobs; the second option is 
for Navy projects only.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Apply a uniform coating of white-pigmented, membrane-forming, curing compound to the entire exposed surface of 
the concrete as soon as the free water has disappeared from the surface after [finishing] [moist curing ceases].  
Along the formed edge faces, apply it immediately after the forms are removed.  Do not allow concrete to dry 
before the application of the membrane.  If any drying has occurred, moisten the surface of the concrete with 
a fine spray of water, and apply the curing compound as soon as the free water disappears.  Apply the curing 
compound to the finished surfaces by means of an approved automatic spraying machine.  <TAI OPT="ARMY/AIR FORCE">Apply the curing compound 
with an overlapping coverage that will give a two-coat application at a coverage of <MET>10 square meters per L </MET><ENG>400 
square feet per gallon</ENG>, plus or minus 5.0 percent for each coat.  A one-coat application may be applied provided 
a uniform application and coverage of <MET>5 square meters per L </MET><ENG>200 square feet per gallon</ENG>, plus or minus 5.0 percent 
is obtained.</TAI><TAI OPT="NAVY">  Apply the curing compound with a single overlapping application that will give a uniform coverage 
of <MET>3.7 square meters/L </MET><ENG>150 square feet per gallon</ENG>.</TAI>  Permit the application of curing compound by hand-operated, 
mechanical powered pressure sprayers only on odd widths or shapes of slabs and on concrete surfaces exposed by 
the removal of forms.  When the application is made by hand-operated sprayers, apply a second coat in a direction 
approximately at right angles to the direction of the first coat.  If pinholes, abrasions, or other discontinuities 
exist, apply an additional coat to the affected areas within 30 minutes.  Respray concrete surfaces that are 
subjected to heavy rainfall within 3 hours after the curing compound has been applied by the method and at the 
coverage specified above.  Immediately respray areas where the curing compound is damaged by subsequent construction 
operations within the curing period.  Protect concrete surfaces to which membrane-curing compounds have been 
applied during the entire curing period from pedestrian and vehicular traffic, except as required for joint-sawing 
operations and surface tests, and from any other possible damage to the continuity of the membrane.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.3   Moist Curing</TTL><BRK/>
<BRK/>
<TXT>Maintain concrete to be moist-cured continuously wet for the entire curing period, or until curing compound is 
applied, commencing immediately after finishing.  If forms are removed before the end of the curing period, perform 
curing as on unformed surfaces, using suitable materials.  Cure surfaces by ponding, by continuous sprinkling, 
by continuously saturated burlap or cotton mats, or by continuously saturated plastic coated burlap.  Use burlap 
and mats that are clean and free from any contamination and completely saturate before placing on the concrete.  
Lap sheets to provide full coverage.  The Contractor must have an approved work system to ensure that moist curing 
is continuous 24 hours per day and that the entire surface is wet.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.8   JOINTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit bracketed items in following subparagraphs to conform to design 
requirements.  Even if not required, dowels should be permitted for construction 
joints.  The effect of tie bars on the pavement action and potential cracking 
should be analyzed before requiring or permitting their use.  Remove joint types 
not required in the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.8.1   General Requirements for Joints</TTL><BRK/>
<BRK/>
<TXT>Joints must conform to the locations and details indicated and must be perpendicular to the finished grade of 
the pavement.  Ensure all joints are straight and continuous from edge to edge or end to end of the pavement 
with no abrupt offset and no gradual deviation greater than <MET>12 mm </MET><ENG>1/2 inch</ENG>.  Where any joint fails to meet these 
tolerances, remove the slabs adjacent to the joint and replace at no additional cost to the Government.  Make 
no change from the jointing pattern shown on the drawings without written approval of the Contracting Officer.  
Seal joints immediately following curing of the concrete or as soon thereafter as weather conditions permit.  
Seal joints as specified in Section [<SRF>32 01 19</SRF> FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS] [
<SRF>32 13 73</SRF> COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.2   Longitudinal Construction Joints</TTL><BRK/>
<BRK/>
<TXT>Install dowels [or tie bars] in the longitudinal construction joints, or thicken the edges as indicated.  Install 
[dowels] [tie bars] in conformance with paragraph, Placing Dowels and Tie Bars.  After the end of the curing 
period, saw longitudinal construction joints to provide a groove at the top for sealant conforming to the details 
and dimensions indicated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.3   Transverse Construction Joints</TTL><BRK/>
<BRK/>
<TXT>Install transverse construction joints at the end of each day's placing operations and at any other points within 
a paving lane when concrete placement is interrupted for 30 minutes or longer.  Install the transverse construction 
joint at a planned transverse joint.  Construct transverse construction joints by utilizing headers or by paving 
through the joint, then full-depth sawcutting the excess concrete.  Construct pavement with the paver as close 
to the header as possible, and run out the paver completely past the header.  Construct transverse construction 
joints installed at a planned transverse joint as shown or, if not shown otherwise, use dowels.  Insert dowels 
through the header into the fresh concrete and consolidated with hand-held vibrators.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.4   Expansion Joints</TTL><BRK/>
<BRK/>
<TXT>Form expansion joints where indicated, and about any structures and features that project through or into the 
pavement, using joint filler of the type, thickness, and width indicated, and install to form a complete, uniform 
separation between the structure and the pavement.  Attach the filler to the original concrete placement with 
adhesive or other fasteners and extend the full slab depth.  Fit adjacent sections of filler tightly together, 
and extend the filler across the full width of the paving lane or other complete distance in order to prevent 
entrance of concrete into the expansion space.  Finish edges of the concrete at the joint face with an edger 
with a radius of <MET>3 mm </MET><ENG>1/8 inch</ENG>.  Install the joint filler strips <MET>20 mm </MET><ENG>3/4 inch</ENG> below the pavement surface with 
a slightly tapered, dressed-and-oiled wood strip or other approved material temporarily secured to the top of 
the filler to form a recess to be filled with joint sealant.  Construct expansion joints with [dowels] [thickened 
edges] for load transfer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.5   Slip Joints</TTL><BRK/>
<BRK/>
<TXT>Install slip joints where indicated using the specified materials.  Attach preformed joint filler material to 
the face of the original concrete placement with adhesive or other fasteners.  Construct a <MET>20 mm </MET><ENG>3/4 inch</ENG> deep 
reservoir for joint sealant at the top of the joint.  Finish edges of the joint face with an edger with a radius 
of <MET>3 mm </MET><ENG>1/8 inch</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.6   Contraction Joints</TTL><BRK/>
<BRK/>
<TXT>Construct transverse and longitudinal contraction joints by sawing an initial groove in the concrete with a <MET>3 
mm </MET><ENG>1/8 inch</ENG> blade to the indicated depth.  During sawing of joints, and again 24 hours later, the CQC team must 
inspect all exposed lane edges for development of cracks below the saw cut, and immediately report results to 
the Contracting Officer.  If the Contracting Officer determines that there are more uncracked joints than desired, 
the Contractor will be directed to saw succeeding joints 25 percent deeper than originally indicated at no additional 
cost to the Government.  Commence sawing of the joints as soon as the concrete has hardened sufficiently to permit 
cutting the concrete without chipping, spalling, or tearing.  Use a chalk line or other suitable guide to mark 
the alinement of the joint.  Immediately after the joint is sawed, thoroughly flush the saw cut and adjacent 
concrete surface with water and vacuum until all waste from sawing is removed from the joint and adjacent concrete 
surface.  Respray the surface with curing compound as soon as free water disappears.  Take necessary precautions 
to ensure that the concrete is properly protected from damage and cured at sawed joints, but that no curing compound 
enters the joints.  Tightly seal the top of the joint opening and the joint groove at exposed edges with cord 
backer rod before the concrete in the region of the joint is resprayed with curing compound, and maintain until 
removed immediately before sawing joint sealant reservoir.  After expiration of the curing period, widen the 
upper portion of the groove by sawing to the width and depth indicated for the joint sealer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.7   Thickened Edge Joints</TTL><BRK/>
<BRK/>
<TXT>Construct thickened edge joints as indicated on the drawings.  Grade underlying material in the transition area 
as shown and meet the requirements for smoothness and compaction specified for all other areas of the underlying 
material.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.9   REPAIR, REMOVAL, REPLACEMENT OF NEWLY CONSTRUCTED SLABS</TTL><BRK/>
<BRK/>
<SPT><TTL>3.9.1   General Criteria</TTL><BRK/>
<BRK/>
<TXT>Remove and replace or repair new pavement slabs that are broken, have spalled edges, or contain cracks, as specified 
hereinafter at no cost to the Government.  Removal of partial slabs is not permitted.  Do not spall more than 
15.0 percent of each slab's edge.  Slabs with spalls exceeding this quantity, regardless of spall size, must 
be sawn full depth to remove the spalled face, or removed, as directed.  The Contracting Officer will determine 
whether cracks extend full depth of the pavement and may require cores to be drilled on the crack to determine 
depth of cracking.  Ensure such cores are at least <MET>150 mm </MET><ENG>6 inch</ENG> diameter, and drilled and backfilled with a 
well consolidated concrete mixture bonded to the walls of the hole with Type V, Grade 3 epoxy resin.  Drilling 
of cores and refilling holes shall be performed by the Contractor at no expense to the Government.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.2   Slabs with Cracks </TTL><BRK/>
<BRK/>
<TXT>Clean cracks that do not exceed 25 percent of the design thickness in depth and then pressure inject full depth 
with epoxy resin, Type IV, Grade 1.  Remove slabs containing cracks deeper than 25 percent of the design thickness.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.3   Repairing Spalls Along Joints</TTL><BRK/>
<BRK/>
<TXT>Repair details and materials must conform to <RID>UFC 3-270-03</RID>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.10   EXISTING CONCRETE PAVEMENT REMOVAL AND REPAIR</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  It is imperative that sufficient exploration be made (not just reference 
to as-built drawings) for the designer to know exactly what the in-place existing 
pavement thickness and load-transfer are at the jointing area--dowels, keys, 
tie bars, etc--and its condition.  Normally, the joint between the new pavement 
and existing pavement should be made at an existing joint in the old pavement.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Remove existing concrete pavement at locations indicated on the drawings.  Prior to commencing pavement removal 
operations, the Contractor must inventory the pavement distresses (cracks, spalls, and corner breaks) along the 
pavement edge to remain.  After pavement removal, the Contractor must again survey the remaining edge to quantify 
any damage caused by Contractor's removal operations.  Both surveys must be performed by the Contractor, in the 
presence of the Contracting Officer.  Make repairs  as indicated and as specified herein.  Carefully control 
all operations to prevent damage to the concrete pavement and to the underlying material to remain in place.  
Make all saw cuts perpendicular to the slab surface, forming rectangular areas.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.10.1   Removal of Existing Pavement Slab</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The saw cut at a distance from the joint should be sawed with a wheel 
saw which produces a 38 mm (1-1/2 inch) or wider kerf and better prevents stress 
from propagating across the saw cut.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>When existing concrete pavement is to be removed and adjacent concrete is to be left in place, first cut the 
joint between the removal area and adjoining pavement to stay in place full depth with a standard diamond-type 
concrete saw.  Next, make a full depth saw cut parallel to the joint at least <MET>600 mm </MET><ENG>24 inches</ENG> from the joint 
and at least <MET>150 mm </MET><ENG>6 inches</ENG> from the end of any dowels.  Make this saw cut with a wheel saw as specified in 
paragraph: Sawing Equipment.  Remove all pavement to be removed beyond this last saw cut in accordance with the 
approved demolition work plan.  Remove all pavement between this last saw cut and the joint line by carefully 
pulling pieces and blocks away from the joint face with suitable equipment and then picking them up for removal.  
In lieu of this method, this strip of concrete may be carefully broken up and removed using hand-held jackhammers, <MET>
14 kg </MET><ENG>30 lb</ENG> or less, or other approved light-duty equipment which will not cause stress to propagate across the 
joint saw cut and cause distress in the pavement which is to remain in place.  In lieu of the above specified 
removal method, the slab may be sawcut full depth to divide it into several pieces and each piece lifted out 
and removed.  Use suitable equipment to provide a truly vertical lift, and use safe lifting devices for attachment 
to the slab.  </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2   Edge Repair</TTL><BRK/>
<BRK/>
<TXT>Protect the edge of existing concrete pavement against which new pavement abuts from damage at all times.  Remove 
areas which are damaged during construction and replaced as directed by the Contracting Officer at no cost to 
the Government. Repair of previously existing damage areas will be considered a subsidiary part of concrete pavement 
construction.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.10.2.1   Spall Repair</TTL><BRK/>
<BRK/>
<TXT>Not more than 15.0 percent of each slab's edge shall be spalled as a result of the Contractor's actions.  Slabs 
with spalls exceeding this quantity, regardless of spall size, must be sawn full depth to remove the spalled 
face.  Repair spalls along joints and along cracks where indicated and where directed.  Use repair materials 
and procedures as previously specified in paragraph: Repairing Spalls Along Joints.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.2   Underbreak and Underlying Material</TTL><BRK/>
<BRK/>
<TXT>Repair all underbreak by removal and repair of the damaged slabs in accordance with paragraph:  Removal and Replacement 
of Full Slabs.  Protect the underlying material adjacent to the edge of and under the existing pavement which 
is to remain in place from damage or disturbance during removal operations and until placement of new concrete, 
and shape as shown on the drawings or as directed.  Keep sufficient underling material in place outside the joint 
line to completely prevent disturbance of material under the pavement which is to remain in place.  Carefuly 
remove any material under the portion of the concrete pavement to remain in place which is disturbed or loses 
its compaction and replace with concrete.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.11   PAVEMENT PROTECTION</TTL><BRK/>
<BRK/>
<TXT>Protect the pavement against all damage prior to final acceptance by the Government.  Do not pile aggregates, 
rubble, or other similar construction materials on airfield pavements.  Block traffic from the new pavement by 
erecting and maintaining barricades and signs until the concrete is at least 14 days old, or for a longer period 
if so directed.  As a construction expedient in paving intermediate lanes between newly paved pilot lanes, permit 
operation of the hauling equipment on the new pavement after the pavement has been cured for 7 days and the joints 
have been sealed or otherwise protected.  Also, permit the subgrade planer, concrete paving and finishing machines, 
and similar equipment to ride upon the edges of previously constructed slabs when the concrete has attained a 
minimum field cured flexural strength of <MET>3.6 MPa </MET><ENG>550 psi</ENG> and approved means are furnished to prevent damage to 
the slab edge.  Keep all new and existing pavement carrying construction traffic or equipment completely clean, 
and clean up spillage of concrete or other materials immediately upon occurrence.  </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.12   TESTING AND INSPECTION FOR CONTRACTOR QUALITY CONTROL</TTL><BRK/>
<BRK/>
<TXT>Sampling and testing shall be conducted on site at the expense of the Contractor, by a laboratory approved by 
the Contracting Officer.  Supply samples as specified at the expense of the Contractor.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.12.1   Sampling</TTL><BRK/>
<BRK/>
<SPT><TTL>3.12.1.1   Aggregates</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Specify frequency of sampling aggregates during concrete placement; e.g.,<MET>
 1360 metric tons</MET><ENG> 1500 tons</ENG> for coarse aggregates;<MET> 907 metric tons</MET><ENG> 1000 tons</ENG>
 for fine aggregate.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Sample fine and coarse aggregates at the batch plant. During concrete placement, sample coarse aggregates for 
each [_____]<MET> metric tons</MET><ENG> tons</ENG> and fine aggregates for each [_____]<MET> metric tons</MET><ENG> tons</ENG>.  Sample in accordance with <RID>
ASTM D 75</RID>.  </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.12.1.2   Concrete</TTL><BRK/>
<BRK/>
<TXT>Obtain samples of plastic concrete in accordance with <RID>ASTM C 172</RID>.  <TST>Quality control samples may be taken at the 
concrete batch plant; however, samples for verification of concrete strength and slump for submittal to the Government 
shall be taken in accordance with <RID>ASTM C 172</RID> at the job-site as concrete is delivered.</TST>  From each sample, mold 
the required number of beams and cylinders for each group of test specimens.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.12.1.3   Sample Identification</TTL><BRK/>
<BRK/>
<TXT>Tag each for identification.  Tag must contain the following information:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">Contract No.     [_____]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">Sample No.       [_____]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">Date of Sample   [_____]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">Sample           [_____]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">Source           [_____]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">Intended Use     [_____]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">For Testing      [_____]</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.12.2   Testing</TTL><BRK/>
<BRK/>
<SPT><TTL>3.12.2.1   Aggregate Tests</TTL><BRK/>
<BRK/>
<TXT><TST>Perform gradation tests on each sample.</TST>  Make other aggregate tests on initial source samples, and repeat tests 
whenever there is a change of source.  During progress of concrete placement, perform gradation tests for fine 
and coarse aggregates.  Include sieve analysis according to <RID>ASTM C 136</RID> for each fractional size and gradation 
analysis of the combined material representing the aggregate part of the concrete mix.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.12.2.2   Concrete Testing</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  <SUB>Concrete Slump</SUB>:  <TST>Test consistency of concrete slump in accordance with <RID>ASTM C 143/C 143M</RID>
.  Determine consistency of concrete at the start of each day's concrete placement and for each 
group of test specimens.</TST></ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  <SUB>Air Content</SUB>:  <TST>Determine air content at the start of concrete placement and for each group 
of test specimens.  Record results with test specimens.  Determine air content in accordance 
with <RID>ASTM C 231</RID>.</TST></ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Surface Tests:  Perform straightedge testing in accordance with paragraph: Surface Testing.  
Where defective areas of pavement are removed or replaced, the portion of the slab which remains 
in the pavement abutting the replacement slab shall have length and width not less than<MET> 3 m</MET><ENG> 
10 feet</ENG> from the nearest edge or joint.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Test for <SUB>Pavement Thickness</SUB>:  <TST>Obtain<MET> 100 mm</MET><ENG> 4 inch</ENG> diameter core samples to determine in-place 
thickness of concrete pavement.  Obtain cores in accordance with <RID>ASTM C 42/C 42M</RID>.</TST>  Remove cores 
at varying intervals but in no case less than two cores for each<MET> [850] [_____] square meters</MET><ENG>
 [1000] [_____] square yards</ENG>.  Repair core holes with non-shrink grout.  <TST>Measure cores in accordance 
with <RID>ASTM C 174/C 174M</RID>.</TST>  A tolerance in pavement thickness of plus or minus<MET> 13 mm</MET><ENG> 1/2 inch</ENG> is 
permitted for individual core; however, the average thickness of cores must be at least [_____]<MET>
 mm</MET><ENG> inches</ENG>.  When determining the average, assign cores with a thickness of more than<MET> 13 mm</MET><ENG> 
1/2 inch</ENG> greater than specified, a thickness of the specified thickness plus<MET> 13 mm</MET><ENG> 1/2 inch</ENG>.  
If measured pavement thickness is less than that shown by more than<MET> 13 mm</MET><ENG> 1/2 inch</ENG>, remove deficient 
areas and replace with pavement of the specified strength, quality and thickness.  When a core 
indicates unsatisfactory thickness, determine limits of the pavement to be removed and replaced 
as follows:  Take one core for each slab of lane in question in both directions from unsatisfactory 
core until satisfactory thickness is indicated; remove and replace pavement in each panel, for 
the full width of the lane, in which a core indicated unsatisfactory thickness. Include the 
following information in each of the reports of corings:</ITM><BRK/>
<BRK/>
<ITM>(1)  Date concrete represented by core was placed</ITM><BRK/>
<BRK/>
<ITM>(2)  Date core was taken</ITM><BRK/>
<BRK/>
<ITM>(3)  Location of Core:  Lane number, station number</ITM><BRK/>
<BRK/>
<ITM>(4)  Thickness of core</ITM><BRK/>
<BRK/>
<ITM>(5)  Condition of Core:  Appearance, concrete texture, condition of bottom of core</ITM><BRK/>
<BRK/>
<ITM>(6)  Disposition of Cores:  In Contracting Officer or Contractor possession.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  <SUB>Flexural Strength</SUB>:  <TST>During progress of work verify flexural strength by testing beams made 
from concrete taken from the delivery vehicle at intervals specified herein.  Mold and cure 
beams in accordance with <RID>ASTM C 31/C 31M</RID>.  Perform tests in accordance with <RID>ASTM C 78</RID>.</TST>  Mold 
at least eight beams each day from concrete placed that day.  Select one group of four beams 
near the beginning of the work and a second group of four beams from the final third of concrete 
to be placed that day.  Ensure an approved laboratory furnishes necessary labor, concrete and 
facilities for molding, handling, and storing the beams at the site of the work and testing 
beams.  Perform tests at 28 days and 90 days.  Earlier tests may be performed at the contractor's 
request, with no additional cost to the Government.  Concrete must meet the following requirements:</ITM><BRK/>
<BRK/>
<ITM>(1)  From each group of four beams, three beams tested at the end of 90 [ ] days must have an 
average flexural strength equal to or greater than the specified strength.  Do not conside specimens 
obviously defective in the determination of the strengths.</ITM><BRK/>
<BRK/>
<ITM>(2)  No individual beam of the three beams tested shall have a flexural strength less than<MET> 4.1 
MPa</MET><ENG> 600 psi</ENG>.  Discard defective beams.</ITM><BRK/>
<BRK/>
<ITM>(3)  Test one beam of the group at 28 [ ] days.  If the ratio of the 28[ ]-day strength test 
to the specified 90-day strength is less than expected, make necessary adjustments for conformance.</ITM><BRK/>
<BRK/>
<ITM>(4)  When a satisfactory relationship between 28[ ]-day and 90-day strengths has been established 
and approved by the Contracting Officer or his authorized representative, the 28[ ]-day test 
results may be used as an indication of the 90-day strengths.  Remove or otherwise correct concrete 
which does not meet the specified strength, at the Contractor's expense, with corrective methods 
subject to the approval of the Contracting Officer or his authorized representative.</ITM><BRK/>
<BRK/>
<ITM>(5)  If the 90 day strength test results do not meet the requirements specified herein, the 
contractor shall take a minimum of three <RID>ASTM C 42/C 42M</RID> core samples from the in-place work 
represented by the low strength test results and test, at no cost to the Government, as long 
as compressive strength test results were performed at the same time as flexural strength tests 
and were submitted with the original mix design.  Consider concrete represented by core tests 
structurally adequate if the average of the three cores is equal to at least 100 percent of 
the specified design strength.  Remove concrete not meeting the strength criteria and provide 
new, acceptable concrete.  Repair core holes with non-shrink grout.  Match color and finish 
of adjacent concrete.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the text below for contracts which require concrete quantities of<MET>
 1500 cubic meters</MET><ENG> 2000 cubic yards</ENG> and more.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM INDENT="-0.33">f.  <SUB>Control Charts</SUB>:  Maintain control charts for concrete flexural strength in accordance with <RID>
ACI 214R</RID> Appendix, except as otherwise modified herein.  Post copies of charts at the job site. 
Indicate specified strength and average strength determined by the mix design.  Each control 
chart must consist of the following plots:</ITM><BRK/>
<BRK/>
<ITM>(1)  Test Results:  At the same location, plot each individual test strength (the beam tested 
at 28 [ ] days and the average results of three beams tested at 90 days).</ITM><BRK/>
<BRK/>
<ITM>(2)  Moving Average for Strength:  Moving average of five consecutive tests <RID>ACI 214R</RID></ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.12.3   Reports</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a. Report all results of tests or inspections conducted informally as they are completed and 
in writing daily. Prepare a weekly report for the updating of control charts covering the entire 
period from the start of the construction season through the current week.  During periods of 
cold-weather protection, make reports of pertinent temperatures daily.  These requirements do 
not relieve the Contractor of the obligation to report certain failures immediately as required 
in preceding paragraphs.  Confirm such reports of failures and the action taken in writing in 
the routine reports.  The Contracting Officer has the right to examine all contractor quality 
control records.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b. Provide hardcopy documentation on Compact Disc (CD) for all preconstruction, production quality 
control, and acceptance testing for cementitious materials, aggregates, mineral and chemical 
admixtures, and fresh/hardened concrete.  Cross-reference all production quality control and 
acceptance testing by pavement lot number and correlate to a placement map.  The required format 
for the database will be provided by [_____].</ITM><BRK/>
<BRK/></SPT>
</SPT></PRT>    <END/><BRK/></SEC>