<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><BRK/>
<HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA            UFGS-32 13 16.16 (November 2008)<BRK/>
                                          --------------------------------<BRK/>
Preparing Activity:  <PRA>USACE</PRA>                Superseding<BRK/>
                                          UFGS-32 13 16.16 (July 2007)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 32 13 16.16</SCN><BRK/>
<BRK/>
<STL>ROLLER COMPACTED CONCRETE (RCC) PAVEMENT</STL><BRK/>
<DTE>11/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>roller compacted 
concrete (RCC) pavements for airfields, roads, streets, parking areas, repair 
yards, open-storage areas, and other utility grade pavements</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable item(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  In preparing contract specifications for RCC pavement construction, the 
Contracting Officer will use Appendix D of UFC 3-250-04FA for further guidance.<BRK/>
<BRK/>
Insert name and location of project.  Specification should be tailored for the 
specific site conditions, available materials, design requirements and construction 
practices.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1   MEASUREMENT AND PAYMENT PROCEDURES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The Designer must carefully correlate and edit the bid items, measurement 
and payment paragraphs, and all the technical paragraphs so use of Portland 
cement, pozzolan, Portland-pozzolan cement, and ground granulated blast furnace 
slag will be well coordinated.  Do not permit use of ground slag with pozzolan 
or Portland-pozzolan cement.  Either use no separate pozzolan or use only a 
reduced amount if Portland-pozzolan cement is used.<BRK/>
<BRK/>
Unit price bid items are recommended when the quantity of RCC and or the quantity 
of cementitious materials is not known or likely to be variable.  If the quantity 
could range beyond 15 percent of the bid item, split bid items should be used.  
If quantities are known at the time of bidding, lump sum bid items are recommended.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1.1   Concrete Quantity</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1.1.1   Measurement of Concrete Quantity</TTL><BRK/>
<BRK/>
<TXT>The quantity of concrete to be paid for will be the number of cubic<MET> meters</MET><ENG> yards</ENG>, rounded to the nearest tenth 
of a cubic<MET> meter</MET><ENG> yard</ENG>, placed in the completed and accepted pavements, including the accepted test section.  
Payment will not be made for wasted concrete, for concrete used for the convenience of the Contractor, or for 
concrete outside the neat lines shown on the drawing.  Concrete will be measured in the completed and accepted 
pavements in accordance with the dimensions shown in the plan and cross section.  No deductions will be made 
for rounded or beveled edges or the space occupied by pavement reinforcement, dowel bars, tie bars, or electrical 
conduits, nor for any void, drainage, or other structure extending into or through the pavement slab measuring<MET>
 1 cubic meter</MET><ENG> 3 cubic feet</ENG> or less in volume.  No other allowance for concrete will be made unless placed in 
specified locations in accordance with written instructions previously issued by the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.1.1.2   Payment for Concrete Quantity</TTL><BRK/>
<BRK/>
<TXT>The quantity of concrete measured as specified above, will be paid for at the contract unit price when placed 
in completed and accepted pavements[ or, where appropriate, at reduced prices adjusted in accordance with paragraph 
PAYMENT ADJUSTMENT].  The unit price will include the cost of labor and materials and the use of equipment and 
tools required to complete the work, except the cement, pozzolan, or ground granulated blast furnace slag that 
is specified for separate payment.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.1.2   Cement Quantity</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1.2.1   Measurement of Cement Quantity</TTL><BRK/>
<BRK/>
<TXT>The quantity of cement to be paid for will be the number of <MET> metric tons</MET><ENG> tons</ENG> of cement used in the completed 
and accepted pavements.  Payment will not be made for wasted cement or for cement used for the convenience of 
the Contractor.  The quantity to be paid for will be determined by multiplying the weight in<MET> kg</MET><ENG> pounds</ENG> of cement 
required by the mixture proportions per cubic<MET> m</MET><ENG> yard</ENG> by the number of cubic<MET> m</MET><ENG> yards</ENG> of the various mixtures placed 
and measured for payment, then dividing by<MET> 1000</MET><ENG>2000</ENG> and rounding off to the nearest tenth of a<MET> metric ton</MET><ENG> ton</ENG>
.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.1.2.2   Payment for Cement Quantity</TTL><BRK/>
<BRK/>
<TXT>The quantity of cement, determined as specified above, will be paid for at the contract unit price, which includes 
all costs of handling, hauling, and storage at the site.[  Adjustment in unit price because of requirements of 
paragraph PAYMENT ADJUSTMENT will not be made in the payment for Portland cement.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.1.3   Pozzolan Quantity</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This specification requires that pozzolan be used for all applications 
unless special circumstances exist.  If pozzolan must be eliminated because 
it is not locally and readily available or the available quality is unacceptable, 
remove this paragraph and all further reference to the material.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1.3.1   Measurement of Pozzolan Quantity</TTL><BRK/>
<BRK/>
<TXT>The quantity of pozzolan paid for will be the number of<MET> metric tons</MET><ENG> tons</ENG> used as a cementitious material in the 
completed and accepted pavements.  Payment will not be made for wasted pozzolan or for pozzolan used for the 
convenience of the Contractor.  The quantity to be paid for will be determined by multiplying the weight in<MET> kg/cubic 
meter</MET><ENG> pounds/cubic yard</ENG> of pozzolan used as a cementitious material, and required by the mixture proportions 
by the number of cubic<MET> m</MET><ENG> yards</ENG> of the various mixtures placed and measured for payment, then dividing by<MET> 1000</MET><ENG>
 2000</ENG> and rounding off to the nearest tenth of a<MET> metric ton</MET><ENG> ton</ENG>.  Payment will not be made for pozzolan used 
strictly as a Contractor's option to compensate for lack of fines in the aggregate.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.1.3.2   Payment for Pozzolan Quantity</TTL><BRK/>
<BRK/>
<TXT>The quantity of pozzolan, determined as specified above, will be paid for at the contract unit price, which includes 
costs of delivery, handling, and storage at the site.[  Adjustment in unit price because of requirements of paragraph 
PAYMENT ADJUSTMENT will not be made in the payment for pozzolan.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.1.4   Ground Granulated Blast Furnace Slag (GGBFS)</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If ground granulated blast furnace slag is not locally and readily available, 
remove this paragraph and all further reference to the material.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1.4.1   Measurement of GGBFS Quantity</TTL><BRK/>
<BRK/>
<TXT>The quantity of GGBFS to be paid for will be the number of<MET> metric tons</MET><ENG> tons</ENG> of GGBFS used in the completed and 
accepted pavements.  Payment will not be made for wasted ground iron blast furnace slag or for GGBFS used for 
the convenience of the Contractor.  The quantity to be paid for will be determined by multiplying the weight 
in<MET> kg</MET><ENG> pounds</ENG> of GGBFS required by the mixture proportions per cubic<MET> meter</MET><ENG> yard</ENG> by the number of cubic<MET> meters</MET><ENG> 
yards</ENG> of the various mixtures placed and measured for payment and then dividing by<MET> 1,000</MET><ENG> 2,000</ENG> and rounding off 
to the nearest tenth of a<MET> metric ton</MET><ENG> ton</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.1.4.2   Payment for GGBFS Quantity</TTL><BRK/>
<BRK/>
<TXT>The quantity of GGBFS, determined as specified above, will be paid for at the contract unit price, which includes 
costs of handling, hauling, and storage at the site.[  Adjustment in unit price because of requirements of paragraph 
PAYMENT ADJUSTMENT will not be made in the payment for GGBFS.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.1.5   Portland-Pozzolan Cement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If Portland-Pozzolan cement is not locally and readily available, remove 
this paragraph and all further references to the material.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1.5.1   Measurement of Portland-Pozzolan Cement Quantity</TTL><BRK/>
<BRK/>
<TXT>The quantity of Portland-pozzolan cement to be paid for will be the number of<MET> metric tons</MET><ENG> tons</ENG> of Portland-pozzolan 
cement used in the completed and accepted pavements.  Payment will not be made for wasted Portland-pozzolan cement 
or for Portland-pozzolan cement used for the convenience of the Contractor.  The quantity to be paid for will 
be determined by multiplying the weight in<MET> kg</MET><ENG> pounds</ENG> of Portland-pozzolan cement required by the mixture proportions 
per cubic<MET> meter</MET><ENG> yard</ENG> by the number of cubic<MET> meters</MET><ENG> yards</ENG> of the various RCC mixtures placed and measured for 
payment, then dividing by<MET> 1,000</MET><ENG> 2,000</ENG> and rounding off to the nearest tenth of a<MET> metric ton</MET><ENG> ton</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.1.5.2   Payment for Portland-Pozzolan Cement</TTL><BRK/>
<BRK/>
<TXT>The quantity of Portland-pozzolan cement, determined as specified above, will be paid for at the contract unit 
price, which includes costs of handling, hauling, and storage at the site.[  Adjustment in unit price because 
of requirements of paragraph PAYMENT ADJUSTMENT will not be made in the payment for Portland-pozzolan cement.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.1.6   RCC Lump Sum Contract</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For fixed-price contracts, inapplicable portions of the unit price paragraphs 
above should be deleted.  It may be necessary to add features of the RCC pavement 
included in the lump sum bid item.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The quantity of RCC will be paid for and included in the lump-sum contract price.  The lump sum payment will 
be for the completed RCC pavement in place at the location(s) as shown on the drawings and shall include all 
incidental work and materials necessary for the completed pavement.[  If less than 100 percent payment is due 
based on the pay factors stipulated in paragraph: PAYMENT ADJUSTMENTS, a unit price of [_____] per cubic<MET> meter</MET><ENG>
 yard</ENG> shall be used for purposes of calculating the payment reduction.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.2   PAYMENT ADJUSTMENT</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If Payment Adjustment is not used, the specification will have to be 
edited to delete references to payment adjustment.  In addition to other items, 
there will have to be inserted, at some appropriate location, the acceptance 
criteria to be used for surface smoothness and thickness, which are presently 
covered only in this paragraph.<BRK/>
<BRK/>
If it is absolutely necessary to cut down a minor amount on acceptance testing, 
the acceptance testing for aggregate gradation during paving operations can 
be deleted, and this entire paragraph must be very carefully edited.</NPR><BRK/>
<BRK/>
<NPR>Do not, under any conditions, reduce the requirements for density, surface smoothness, 
surface texture, or thickness or the testing required for those items.  Do not, 
under any conditions, reduce the requirements for daily calibration of the nuclear 
density meter with the cast block of RCC.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.2.1   General Considerations</TTL><BRK/>
<BRK/>
<TXT>Adjustment in payment for individual lots of RCC pavement will be made in accordance with the following paragraphs[ 
for all RCC pavement][ the pavement sections listed].  The parameters to be measured are aggregate gradation, 
pavement thickness, density, surface smoothness, and surface texture.  No adjustment in payment will be made 
for cementitious materials.  Unless otherwise specified, testing shall be done as specified in paragraph: Contractor 
Quality Control.  All tests shall be completed and reported within 24 hours after completion of construction 
of each lot.</TXT><BRK/>
<BRK/>
<LST>[a.  Location 1]</LST><BRK/>
<LST>[b.  Location 2]</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.2   Percent Payment/Acceptance of Lots</TTL><BRK/>
<BRK/>
<LST>a.  When a lot of material fails to meet the specification requirements for 100 percent payment as outlined 
in the following paragraphs, that lot shall be removed and replaced, or accepted at a reduced price, 
as specified herein.  The lowest computed payment factor for any pavement characteristic (i.e., gradation, 
density, surface smoothness, thickness, and surface texture) discussed below will be the actual percent 
payment for that lot.  Payment factors based on different criteria of the same lot will not be multiplied 
together to get a lower payment factor.  The actual percent payment is applied to the bid price and to 
the quantity of RCC pavement placed in the lot to determine actual payment.</LST><BRK/>
<BRK/>
<LST>b.  At the end of the project, an average of all lot pay factors will be calculated.  If this average 
lot pay factor exceeds 95.0 percent and no individual lot has a pay factor less than 75.1 percent, then 
the percent payment for the entire project will be 100 percent of the unit bid price.  If the average 
lot pay factor is less than 95.0 percent, then each lot will be paid for at the unit price multiplied 
by the lot's pay factor.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.3   Density</TTL><BRK/>
<BRK/>
<SPT><TTL>1.2.3.1   Field Density</TTL><BRK/>
<BRK/>
<LST>a.  To evaluate field density for acceptance, 4 nuclear density gauge tests to determine wet density 
will be performed at random locations on the interior of the paving lane immediately behind final rolling 
operations, and 4 similar tests will be performed at random locations on fresh joints and 4 at random 
locations on cold joints, if such exist, for each sublot, and each set will be averaged for the sublot.  
Field density for each sublot will be compared with the target density for that lot.  The locations of 
the tests on fresh joints will be alternated from side to side of the joint and will be between<MET> 75 and 
130 mm</MET><ENG> 3 and 5 inches</ENG> from the joint.</LST><BRK/>
<BRK/>
<LST>b.  For cold joints, it is expected that the primary (originally placed) lane will be placed with one 
sublot and the secondary lane with another sublot.  The cold joint evaluation for each of these sublots 
will be based on 4 density tests made for each sublot being evaluated on that sublot's side of the cold 
joint.  These tests will be between<MET> 75 and 130 mm</MET><ENG> 3 and 5 inches</ENG> from the proposed (sawed) joint line 
on the originally placed side of the cold joint and between<MET> 75 and 130 mm</MET><ENG> 3 and 5 inches</ENG> from the actual 
joint on the secondary placement side.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.3.2   Target Density</TTL><BRK/>
<BRK/>
<TXT>Determine, for each lot, the laboratory maximum wet density of an RCC sample tested in accordance with <RID>ASTM D 1557</RID>
 and as described for moisture-density testing in paragraph CONTRACTOR QUALITY CONTROL.  This procedure for determining 
the target density will be repeated for each lot and as necessary whenever the mixture proportions or materials 
change.  Since the "target density" for a lot will not be known until after the beginning of construction of 
the lot, the "target density" of the previous lot shall be used for quality control until the new "target density" 
is obtained.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.3.3   Computed Percent Payment for Density</TTL><BRK/>
<BRK/>
<LST>a.  The average field densities for the sublots for lane interior and for each type of joint will in 
turn be averaged to determine the lot density for the lane interior, for fresh joints, and, if such exist, 
for cold joints.  These lot average field densities will be compared with Table I and used to calculate 
the computed percent payment based on field density as described below.</LST><BRK/>
<BRK/>
<LST>b.  First, the percent payment deduction for lane interior density, for fresh joint density, and for 
cold joint density will each be computed by subtracting the percent payment values found in Table I from 
100.</LST><BRK/>
<BRK/>
<LST>c.  Second, the weighted percent payment deduction for fresh joint density will be computed by multiplying 
the percent payment deduction for fresh joint density, as computed above, by the ratio of the total amount 
of RCC pavement in the fresh joint strip to the total amount of RCC pavement in the entire area of the 
lot.  The area of fresh joint strip will be considered to be<MET> 3 m</MET><ENG> 10 feet</ENG> wide times the length of completed 
fresh longitudinal construction joint in the lot, but not to exceed the total lot size.</LST><BRK/>
<BRK/>
<LST>d.  Third, the weighted percent payment deduction for cold joint density will be computed by multiplying 
the percent payment deduction for cold joint density, as computed above, by the ratio of the total amount 
of RCC pavement in the cold joint strip to the total amount of RCC pavement in the entire area of the 
lot.  The area of cold joint strip will be considered to be<MET> 1.5 m</MET><ENG> 5 feet</ENG> wide times the length of each 
half of the cold joint (each side of the joint) completed with the lot being evaluated, but not to exceed 
the lot size.  (Although not probable, it could be possible that, for a full lot, both sides of a cold 
joint can be constructed in the same lot).</LST> <BRK/>
<BRK/>
<LST>e.  Finally, the percent payment reduction for the lane interior, the weighted percent payment deduction 
for fresh joint density, and the weighted percent payment deduction for cold joint density will be compared 
and the greatest value selected.  This selected percent payment deduction will be subtracted from 100 
to obtain the computed percent payment based on field density.</LST><BRK/>
<TBL><THD><BRK/>
<HL4>TABLE I - PERCENT PAYMENT FOR DENSITY</HL4><BRK/>
<BRK/>
   Average Lane Interior<BRK/>
   and Fresh Joint Density                    Average Cold Joint<BRK/>
   (16 Nuclear Density         Percent        Density (16 Nuclear<BRK/>
   Gauge Readings Each)        Payment        Density Readings)<BRK/></THD>
<BRK/>
     98.0 and above             100.0            96.0 and above<BRK/>
     97.9                        99.5            95.9<BRK/>
     97.8                        99.0            95.8<BRK/>
     97.7                        98.2            95.7<BRK/>
     97.6                        97.0            95.6<BRK/>
     97.5                        95.0            95.5<BRK/>
     97.4                        86.5            95.4<BRK/>
     97.3                        81.0            95.3<BRK/>
     97.2                        72.0            95.2<BRK/>
     97.1                        65.0            95.1<BRK/>
     97.0                        58.0            95.0<BRK/>
     96.9                        52.0            94.9<BRK/>
     96.8                        47.0            94.8<BRK/>
     below 96.8                 reject           below 94.8</TBL><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.2.4   Surface Smoothness</TTL><BRK/>
<BRK/>
<LST>a.  After completion of the final rolling of a lot, test compacted surface for smoothness with a straightedge.  
Measurements will be made transverse to the paving lane at equal distances along the lane not to exceed<MET>
 6 m</MET><ENG> 20 feet</ENG>.  These transverse measurements will be made completely across the paving lane and across 
the longitudinal construction joints.  Measurements will be made longitudinal to the paving lane at separate 
intervals spaced not more than<MET> 6 m</MET><ENG> 20 feet</ENG> apart longitudinally as well as across all transverse joints.  
Longitudinal measurements will be made at third points across the lane.  Other areas having visually 
obvious deviations will also be tested.  Location and deviation from straightedge for all measurements 
will be recorded.</LST><BRK/>
<BRK/>
<LST>b.  When more than 5.0 percent of all measurements within a lot (across the joints and within the lane) 
exceed the tolerance specified in Table III, after any reduction of high spots or removal and replacement, 
the computed percent payment based on surface smoothness will be 95 percent.  Regardless of the above, 
any separate joint or interior area surface deviation which exceeds the tolerance given in Table III 
by more than 50 percent shall be removed or corrected to meet the specification requirements.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.5   Thickness</TTL><BRK/>
<BRK/>
<LST>a.  The computed percent payment for thickness for the lot will be 100 percent if no core taken for that 
lot is deficient in thickness by<MET> 6 mm</MET><ENG> 1/4 inch</ENG> or more.</LST><BRK/>
<BRK/>
<ITM>1).  When the measurement of any core indicates that the pavement is deficient in thickness 
by<MET> 6 mm</MET><ENG> 1/4 inch</ENG> or more, additional cores shall be drilled parallel to the center line of the 
lane at<MET> 8 m</MET><ENG> 25 foot</ENG> intervals on each side of the deficient core until the cores indicate that 
the deficiency in thickness is less than<MET> 6 mm</MET><ENG> 1/4 inch</ENG>.</ITM><BRK/>
<BRK/>
<ITM>2).  When the deficiencies in thickness for a series of cores are between<MET> 6 and 13 mm</MET><ENG> 1/4 and 
1/2 inch</ENG>, the average thickness will be established from an average of all core thicknesses, 
considering any core less than<MET> 6 mm</MET><ENG> 1/4 inch</ENG> deficient as being full depth.</ITM><BRK/>
<BRK/>
<ITM>3).  Any areas<MET> 13 mm</MET><ENG> 1/2 inch</ENG> or more deficient in thickness shall be removed and replaced, 
recored and included in the measurements before the final calculation of computed percent payment 
for the lot is made.</ITM><BRK/>
<BRK/>
<LST>b.  The computed percent payment for thickness for the lot will then be determined as follows:  the proportional 
part of the total lot area (expressed in percent) for Categories I and II in Table II will be multiplied 
by their respective percent payment from the table and the 2 products then added to obtain the computed 
percent payment for the lot.</LST><BRK/>
<BRK/>
<LST>c.  The area of pavement for the percent payment calculations shall be considered to be the full paving 
lane width and midway between cores having thicknesses representing different categories.  When any core 
shows a deficiency in thickness of<MET> 13 mm</MET><ENG> 1/2 inch</ENG> or more, the area represented by that core shall be 
removed and replaced with pavement of the indicated thickness before any payment calculations are made.  
The area represented by the core shall be bound by the full paving lane width and a transverse line midway 
between the cores adjacent to the core in question, or the regularly scheduled transverse joint should 
such a joint fall between the cores.</LST><BRK/>
<BRK/>
<LST>d.  If the Contractor believes that the cores and measurement taken are not sufficient to indicate fairly 
the actual thickness of the pavement, additional cores shall be taken and will be measured provided the 
Contractor will bear the extra cost of drilling the cores.  When surface grinding is required that results 
in thickness deficiencies, the final surface will be considered in evaluation for thickness.</LST><BRK/>
<MET><TBL><THD><BRK/>
<HL4>TABLE II - PERCENT PAYMENT FOR THICKNESS</HL4><BRK/>
<BRK/>
<HL4>Deficiency in Thickness</HL4><BRK/>
<HL4>Determined by Cores</HL4><BRK/>
<BRK/>
    Percent Payment                                  (or Action<BRK/>
       Category                 mm                   Required)<BRK/>
    _______________         ___________              __________<BRK/></THD>
<BRK/>
        I                   0.0 to 6.3                 100<BRK/>
        II                  6.4 to 12.0                 65<BRK/>
        III                12.7 or greater           Remove and<BRK/>
                                                      replace<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>TABLE II - PERCENT PAYMENT FOR THICKNESS</HL4><BRK/>
<BRK/>
<HL4>Deficiency in Thickness</HL4><BRK/>
<HL4>Determined by Cores</HL4><BRK/>
<BRK/>
    Percent Payment                                  (or Action<BRK/>
       Category               Inches                 Required)<BRK/>
    _______________          ________                __________<BRK/></THD>
<BRK/>
        I                   0.00 to 0.24               100<BRK/>
        II                  0.25 to 0.49                65<BRK/>
        III                 0.50 or greater          Remove and<BRK/>
                                                      replace</TBL></ENG><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.6   Surface Texture</TTL><BRK/>
<BRK/>
<LST>a.  The surface texture of each lot will be visually examined by a representative of the Contractor's 
Quality Control immediately after construction to determine compliance with the surface texture requirements 
in paragraph RCC PAVEMENT PERFORMANCE REQUIREMENTS.  The classification of the surface texture of any 
area of the pavement as acceptable or deficient will be made on the basis of comparison with a selected 
portion of the test section which has been chosen and marked as having an acceptable surface texture 
as determined by the Contracting Officer.  The computed percent payment for surface texture requirements 
for the lot will be determined as shown in Table III.</LST><BRK/>
<BRK/>
<LST>b.  Regardless of payment, any area of any size of extremely poor surface texture as determined by the 
Contracting Officer shall be removed and replaced full depth with suitable pavement at mo cost to the 
Government.  No payment calculations will be made until all such defective material is removed and replaced.</LST><BRK/>
<TBL><THD><BRK/>
<HL4>TABLE III - PERCENT PAYMENT FOR SURFACE TEXTURE</HL4><BRK/>
<BRK/>
     Percent of Lot Area with                Percent Payment<BRK/>
     Deficient Surface Texture             for Action Required<BRK/>
     _________________________             ___________________<BRK/></THD>
<BRK/>
          0.0 to 5.0                              100<BRK/>
          5.1 to 10.0                              90<BRK/>
         10.1 to 20.0                              75<BRK/>
         20.1 and above                    Remove and replace</TBL><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.3   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification.  The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
<BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
<BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)</ORG><BRK/><BRK/><RID>AASHTO M 182</RID><RTL>(2005) Standard Specification for Burlap Cloth Made from Jute or Kenaf and Cotton Mats</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM C 1040/C 1040M</RID><RTL>(2008) Standard Test Methods for In-Place Density of Unhardened and Hardened Concrete, Including Roller Compacted Concrete, by Nuclear Methods</RTL><BRK/><BRK/><RID>ASTM C 1064/C 1064M</RID><RTL>(2008) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete</RTL><BRK/><BRK/><RID>ASTM C 1077</RID><RTL>(2008) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation</RTL><BRK/><BRK/><RID>ASTM C 1157</RID><RTL>(2008) Standard Specification for Hydraulic Cement</RTL><BRK/><BRK/><RID>ASTM C 117</RID><RTL>(2004) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing</RTL><BRK/><BRK/><RID>ASTM C 123</RID><RTL>(2004) Standard Test Method for Lightweight Particles in Aggregate</RTL><BRK/><BRK/><RID>ASTM C 1260</RID><RTL>(2007) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)</RTL><BRK/><BRK/><RID>ASTM C 127</RID><RTL>(2007) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate</RTL><BRK/><BRK/><RID>ASTM C 128</RID><RTL>(2007a) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Fine Aggregate</RTL><BRK/><BRK/><RID>ASTM C 131</RID><RTL>(2006)Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine</RTL><BRK/><BRK/><RID>ASTM C 136</RID><RTL>(2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates</RTL><BRK/><BRK/><RID>ASTM C 142</RID><RTL>(1997; R 2004) Standard Test Method for Clay Lumps and Friable Particles in Aggregates</RTL><BRK/><BRK/><RID>ASTM C 1435/C 1435M</RID><RTL>(2008) Standard Practice for Molding Roller-Compacted Concrete in Cylinder Molds Using a Vibrating Hammer</RTL><BRK/><BRK/><RID>ASTM C 150</RID><RTL>(2007) Standard Specification for Portland Cement</RTL><BRK/><BRK/><RID>ASTM C 1567</RID><RTL>(2008) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)</RTL><BRK/><BRK/><RID>ASTM C 171</RID><RTL>(2007) Standard Specification for Sheet Materials for Curing Concrete</RTL><BRK/><BRK/><RID>ASTM C 295</RID><RTL>(2008) Petrographic Examination of Aggregates for Concrete</RTL><BRK/><BRK/><RID>ASTM C 309</RID><RTL>(2007) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete</RTL><BRK/><BRK/><RID>ASTM C 31/C 31M</RID><RTL>(2008a) Standard Practice for Making and Curing Concrete Test Specimens in the Field</RTL><BRK/><BRK/><RID>ASTM C 39/C 39M</RID><RTL>(2005e1e2) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens</RTL><BRK/><BRK/><RID>ASTM C 40</RID><RTL>(2004) Standard Test Method for Organic Impurities in Fine Aggregates for Concrete</RTL><BRK/><BRK/><RID>ASTM C 42/C 42M</RID><RTL>(2004) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete</RTL><BRK/><BRK/><RID>ASTM C 494/C 494M</RID><RTL>(2008a) Standard Specification for Chemical Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM C 566</RID><RTL>(1997; R 2004) Standard Test Method for Total Evaporable Moisture Content of Aggregate by Drying</RTL><BRK/><BRK/><RID>ASTM C 595</RID><RTL>(2008) Standard Specification for Blended Hydraulic Cements</RTL><BRK/><BRK/><RID>ASTM C 618</RID><RTL>(2008a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete</RTL><BRK/><BRK/><RID>ASTM C 78</RID><RTL>(2008) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading)</RTL><BRK/><BRK/><RID>ASTM C 856</RID><RTL>(2004) Petrographic Examination of Hardened Concrete</RTL><BRK/><BRK/><RID>ASTM C 87</RID><RTL>(2005) Effect of Organic Impurities in Fine Aggregate on Strength of Mortar</RTL><BRK/><BRK/><RID>ASTM C 989</RID><RTL>(2006) Standard Specification for Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars</RTL><BRK/><BRK/><RID>ASTM D 1557</RID><RTL>(2007) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)</RTL><BRK/><BRK/><RID>ASTM D 2995</RID><RTL>(1999; R 2004) Determining Application Rate of Bituminous Distributors</RTL><BRK/><BRK/><RID>ASTM D 3665</RID><RTL>(2007) Random Sampling of Construction Materials</RTL><BRK/><BRK/><RID>ASTM D 4791</RID><RTL>(2005e1) Flat Particles, Elongated Particles, or Flat and Elongated Particles in Coarse Aggregate</RTL><BRK/><BRK/><RID>ASTM D 6938</RID><RTL>(2007a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA)</ORG><BRK/><BRK/><RID>NRMCA CPMB 100</RID><RTL>(2000) Concrete Plant Standards</RTL><BRK/><BRK/></REF><REF><ORG>U.S. ARMY CORPS OF ENGINEERS (USACE)</ORG><BRK/><BRK/><RID>COE CRD-C 130</RID><RTL>(2001) Standard Recommended Practice for Estimating Scratch Hardness of Coarse Aggregate Particles</RTL><BRK/><BRK/><RID>COE CRD-C 300</RID><RTL>(1990) Specifications for Membrane-Forming Compounds for Curing Concrete</RTL><BRK/><BRK/><RID>COE CRD-C 400</RID><RTL>(1963) Requirements for Water for Use in Mixing or Curing Concrete</RTL><BRK/><BRK/><RID>COE CRD-C 55</RID><RTL>(1992) Test Method for Within-Batch Uniformity of Freshly Mixed Concrete</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.4   DEFINITIONS</TTL><BRK/>
<BRK/>
<TXT>The following DEFINITIONS apply to materials in Table VI:</TXT><BRK/>
<BRK/>
<LST>a. Shale is defined as a fine-grained thinly laminated or fissile sedimentary rock.  It is commonly composed 
of clay or silt or both.  It has been indurated by compaction or by cementation, but not so much as to 
have become slate.</LST><BRK/>
<BRK/>
<LST>b. Limit for material finer than<MET> 0.075 mm</MET><ENG> (No. 200)</ENG> sieve will be increased to 1.5 percent for crushed 
aggregates if the fine material consists of crusher dust that is essentially free from clay or shale.</LST><BRK/>
<BRK/>
<LST>c. Clay ironstone is defined as an impure variety of iron carbonate, iron oxide, hydrous iron oxide, 
or combinations thereof, commonly mixed with clay, silt, or sand.  It commonly occurs as dull, earthy 
particles, homogeneous concretionary masses, or hard-shell particles with soft interiors.  Other names 
commonly used for clay ironstone are "chocolate bars" and limonite concretions.</LST><BRK/>
<BRK/>
<LST>d. Chert is defined as a rock composed of quartz, chalcedony or opal, or any mixture of these forms of 
silica.  It is variable in color.  The texture is so fine that the individual mineral grains are too 
small to be distinguished by the unaided eye.  Its hardness is such that it scratches glass but is not 
scratched by a knife blade.  It may contain impurities such as clay, carbonates, iron oxides, and other 
minerals.  Other names commonly applied to varieties of chert are:  flint, jasper, agate, onyx, hornstone, 
procellanite, novaculite, sard, carnelian, plasma, bloodstone, touchstone, chrysoprase, heliotrope, and 
petrified wood.  Cherty stone is defined as any type of rock (generally limestone) that contains chert 
as lenses and nodules, or irregular masses partially or completely replacing the original stone.</LST><BRK/>
<BRK/>
<LST>e. Claystone mudstone, or siltstone, is defined as a massive fine-grained sedimentary rock that consists 
predominantly of clay or silt without laminations or fissility.  It may be indurated either by compaction 
or by cementation.</LST><BRK/>
<BRK/>
<LST>f. Shaly limestone is defined as limestone in which shale occurs as one or more thin beds or laminae.  
These laminae may be regular or very irregular and may be spaced from a few inches down to minute fractions 
of an inch.  Argillaceous limestone is defined as a limestone in which clay minerals occur disseminated 
in the stone in the amount of 10 to 50 percent by weight of the rock; when these make up from 50 to 90 
percent, the rock is known as calcareous (or dolomitic) shale (or claystone, mudstone, or siltstone).</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5   SYSTEM DESCRIPTION</TTL><BRK/>
<BRK/>
<SPT><TTL>1.5.1   General Requirements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Fill in the bracket with the name and location of the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  The work covered by this section consists of furnishing all plant, material, and equipment, and performing 
all labor for the manufacturing, transporting, placing, compacting, finishing, jointing, and curing of 
roller-compacted concrete (RCC) pavement for [_____].</LST><BRK/>
<BRK/>
<LST>b.  Provide access to the Contracting Officer at all times to all parts of the mixing and paving plant, 
placement site, and materials sources for inspection, sampling, and testing to assure compliance with 
the specifications.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2   <SUB>Batching and Mixing Plant</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>1.5.2.1   Location of Plant</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The mixing plant should be on the construction site or as close as possible, 
but should be no further than 15 minutes haul time from the placing site.  This 
is especially true if the project is on a military facility.  The security delays 
at entrances are prohibitive.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Locate the mixing plant [onsite as indicated on the drawings][ and ][no more than 15 minutes haul time from the 
placing site].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.2   Type of Plant</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Plant capacity should be governed by the laydown pattern or the size 
of the job to help eliminate or minimize cold joints.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Design and operate the mixing plant to produce an RCC mixture within the specified tolerances.  The plant shall 
be a stationary-type plant having a twin-shift pug mill mixer and may be either weigh-batch type or continuous 
type and shall have a minimum rated capacity of<MET> [230][_____] metric tons</MET><ENG> [250][_____] tons</ENG> per hour.  The plant 
shall be equipped with positive means for controlling and adjusting the mixing time (amount of mixing), maintaining 
the time of mixing constant, and maintaining the speed of rotation of the pug mill shafts constant.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.3   Cementitious Material Feed Unit</TTL><BRK/>
<BRK/>
<TXT>Suitable equipment, incorporating either weighing or volumetric measurements, shall be provided to separately 
batch or feed the required percentage of each cementitious material in the mixture within tolerances specified.  
Silos and feeders shall be equipped and operated so that no caking of material or variation in feed will occur, 
including use of any necessary air pressure or vacuum vents on the silos.  Provision shall be made whereby each 
cementitious material can be readily sampled.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.4   Aggregate Bins</TTL><BRK/>
<BRK/>
<TXT>Aggregate bins shall be provided for aggregate storage, one for each size group.  Each bin shall be of sufficient 
capacity to supply the mixer continuously operating at full capacity.  The bins shall be arranged to ensure separate 
storage of appropriate fractions of aggregate.  Each compartment shall be provided with some means of preventing 
spilling of material into other bins.  Unless the aggregate in the bin is readily visible to operating personnel, 
each aggregate bin shall be equipped with mechanical or electrical telltales to indicate when the aggregate in 
the bin is below level to permit accurate proportioning to mixing unit.  Each bin shall be constructed or equipped 
so that a representative sample may be readily and safely obtained from each bin discharge during plant operations.  
When use of blending material is necessary, appropriate means shall be provided for separately storing, metering, 
and feeding into the mixer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.5   Water Control Units</TTL><BRK/>
<BRK/>
<TXT>Satisfactory means incorporating either weighing, metering, or volumetric measurements shall be provided to batch 
or feed the required quantity of water in the mixture within tolerances specified.  Adjusting controls shall 
be convenient to and capable of easy and accurate operation by the mixer operator.  When metering controls the 
quantity of water, provision shall be made whereby a fixed quantity of water delivered through the meter can 
be readily checked by weight or volume.  A water storage tank shall be provided to prevent surge drawdown effect.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.6   Batching or Feeding Tolerances</TTL><BRK/>
<BRK/>
<TXT>Batching or feeding shall conform to the mixture proportions directed within the following tolerances in Table 
IV.  For batch-type plants, the variation is in percent by weight from batch weight of each material based on 
the mixture proportions directed.  For continuous feeding and mixing plants, the variation is in percent by weight 
from the mixture proportions of each material designed to be in a total timed sample obtained from a designated 
location in the plant.</TXT><BRK/>
<TBL><THD><BRK/>
<HL4>TABLE IV - BATCHING OR FEEDING TOLERANCES</HL4><BRK/>
<BRK/>
              Material                            Plant Tolerance, percent<BRK/></THD>
<BRK/>
    Each cementitious material                    plus or minus 2.0<BRK/>
    Water                                         plus or minus 2.0<BRK/>
    Admixtures                                    zero to plus  4.0<BRK/>
    Each individual aggregate size group          plus or minus 2.0<BRK/>
    Total aggregate                               plus or minus 3.0</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.7   Additional Requirements for Batch-Type Mixing Plants</TTL><BRK/>
<BRK/>
<LST>a.  Plant Scales:  Plant scales shall conform to requirements of <RID>NRMCA CPMB 100</RID>, with modifications as 
follows:  Plant scales for any weigh box or hopper shall be of either beam or springless-dial type and 
shall be sensitive to 0.5 percent of maximum load required.  Beam-type scales shall have a separate beam 
for each size aggregate, with a single pointer actuated for each beam and a tare beam for balancing hopper.</LST><BRK/>
<BRK/>
<LST>b.  Weigh Box or Hopper for Aggregates:  Weigh box or hopper for aggregates shall conform to requirements 
of <RID>NRMCA CPMB 100</RID>, with modifications as follows:  Equipment shall include means for weighing each bin 
size of aggregate in a weigh box or hopper suspended on scales, ample in size to hold a full batch without 
running over.  The gates on both the bins and the hoppers shall prevent leakage of aggregate when closed.  
On manually or semi-automatically operated plants, an interlocking device shall be provided to prevent 
opening more than one gate at a time.  The interlocking device shall not be required on automatic plants 
designed for simultaneous weighing of all sizes of aggregate while the plant is operating under automatic 
control.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Modify or delete GGBFS (bracketed) sentence.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>c.  Weigh Hoppers for Cementitious Materials:  Weigh hoppers for cementitious materials shall conform 
to requirements of <RID>NRMCA CPMB 100</RID>, with modifications as follows:  The weigh hopper shall have sufficient 
capacity to hold not less than 10 percent in excess of the weight of the cementitious material required 
for one batch.  Portland cement and pozzolan may both be weighed cumulatively in the same hopper on the 
same scale, provided the Portland cement is weighed first, or the Portland cement and pozzolan may be 
weighed in separate hoppers on separate scales.  The hopper shall be suspended on dial or beam scales 
equipped with a pointer so the tare weight of the hopper will be shown for each weighing; net weight 
of cementitious material shall be measured within 1 percent of the weight required.[  Ground granulated 
blast furnace slag shall be [weighed on a separate scale][_____].]</LST><BRK/>
<BRK/>
<LST>d.  Mixer Unit:  The mixer for batch method shall be a stationary mixer of the twin pug mill-type capable 
of producing a uniform mixture within tolerances specified.  The mixer shall have a time lock, accurate 
within 5 seconds, to control operation of the complete mixing cycle by locking the weigh hopper gate 
after mixer is charged until closing of mixer gate throughout dry- and wet-mixing periods.  The dry-mixing 
period is defined as the interval of time between the opening of the weigh hopper and the application 
of water.  The wet-mixing period is the interval between application of water and the opening of the 
mixer gate.  Control of mixing time shall be flexible and capable of being set at intervals of not more 
than 5 seconds throughout cycles up to 3 minutes.  A mechanical batch counter shall be installed as part 
of the timing device and shall be designed to preclude register of dry batches or of any material run 
through during operation of pulling bins.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2.8   Additional Requirements for Continuous-Mixing Plants</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete the bracketed statement except for small or low-production jobs.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  Aggregate Feed:  Each bin shall have the feed rate controlled by a variable speed belt, [gate remotely 
operated from the central control panel, ]calibrated to accurately deliver any specified quantity of 
material within the required tolerance.  The feed rate from each bin shall be readily adjustable from 
the control panel to change aggregate proportions or to compensate for changes in moisture content.  
The feed rate controls shall automatically maintain the established proportions of aggregate from each 
bin when the combined aggregate delivery is increased or decreased.  The combined aggregate belt feeding 
the mixer shall be equipped with an approved belt scale.  The belt scale shall operate automatic controls, 
either electronic or mechanical, which will maintain the established proportion of each cementitious 
material and water as ratios of the total aggregate, with provisions for readily changing the proportions 
at the control panel.  Approved means shall be provided for storing, metering, and feeding blend material 
as a separate material when use of blending material is necessary.</LST><BRK/>
<BRK/>
<LST>b.  Cementitious Material Control:  Approved means shall be provided to separately meter the required 
amount of each cementitious material in the mix within the tolerance specified.  Metering shall be by 
readily adjustable vane feeders or other approved positive metering devices.  Metering and feed shall 
be designed and controlled so that the cementitious material is uniformly fed into the mixer or into 
the stream of aggregate on the feeder belt, all with necessary controls to prevent loss of cementitious 
material as dust or in any other form.  Control of the quantity of each cementitious material shall be 
automatically linked to the aggregate belt scales, as specified herein.  Provision shall be made so the 
amount of each cementitious material delivered can be readily sampled and checked by weight.</LST><BRK/>
<BRK/>
<LST>c.  Mixer Unit:  The mixer for the continuous method shall be a stationary mixer of the twin-shaft pug 
mill type capable of producing a uniform and homogeneous mixture within tolerances specified.  Blades 
shall be adjustable for angular position on shafts and reversible to retard flow of the mixture.  The 
mixer shall bear a manufacturer's plate indicating net volumetric contents of mixer at several heights 
permanently inscribed on the wall and the rate of feed of aggregate per minute at plant-operating speed.</LST><BRK/>
<BRK/>
<LST>d.  Discharge Hopper:  The pug mill shall be equipped with a discharge hopper having a capacity of at 
least one<MET> metric ton</MET><ENG> ton</ENG>.  The hopper shall be equipped with dump gates to assure rapid and complete 
discharge without segregation.</LST><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>1.6   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section <SRF>01 33 00</SRF> SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy, Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for [Contractor Quality Control approval.] [information only.  When used, a designation following the "G" 
designation identifies the office that will review the submittal for the Government.]  Submit the following in 
accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-01 Preconstruction Submittals</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Mixture Proportioning</SUB></ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Mixture proportioning studies include aggregate quality testing which 
may take considerable time.  The mixture trial phase and follow up testing will 
require several months.  Consider these time limits in selection when the submittal 
is required.  Generally, mixture proportioning studies through 28-day test results 
require at least 60 days to perform.  If later age strength results are necessary, 
more time is necessary.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>  At least [60][_____] days in advance of RCC test section construction and prior to plant assembly.  
Include:</ITM><BRK/>
<BRK/>
<ITM>a.  Laboratory report on mixture design studies with [28][90]-day strength test results.</ITM><BRK/>
<ITM>b.  Source information on all constituent materials.</ITM><BRK/>
<ITM>c.  Laboratory report of aggregate quality tests.</ITM><BRK/>
<ITM>d.  Manufacturer's literature including mill analysis and production test data on cementitious 
materials and admixture data.</ITM><BRK/>
<BRK/>
<ITM><SUB>Batching and Mixing Plant</SUB></ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Time for this Submittal is intended to provide advance information to 
the field staff so that timely plant inspection can be done.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>  Details and data on the RCC mixing plant at least [60][_____] days in advance of RCC test 
section construction and prior to plant assembly.  Include:</ITM><BRK/>
<BRK/>
<ITM>a.  Detailed layour of aggregate and RCC equipment.</ITM><BRK/>
<ITM>b.  Equipment manufacturer's literature on the:</ITM><BRK/>
<ITM>      1) Cementitious material storage, handling, and controls</ITM><BRK/>
<ITM>      2) Aggregate handling and controls</ITM><BRK/>
<ITM>      3) Water system and controls</ITM><BRK/>
<ITM>      4) Mixers and controls</ITM><BRK/>
<ITM>      5) Re-screening systems</ITM><BRK/>
<ITM>      6) Cooling systems</ITM><BRK/>
<ITM>      7) Plant conveyors, bins, and feeders.</ITM><BRK/>
<BRK/>
<ITM><SUB>Transporting and Placing Methods</SUB></ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The submittal is to be reviewed in advance of the test section construction.  
The test section is where the Contractor demonstrates the proposed processes.  
The processes may change as a result of the test section and the resubmittal 
documents that change.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>  Initial submittal [60][_____] days in advance of the test section construction.  A resubmittal 
shall be done after completion of a successful test section at least [14][_____] days in advance 
to the RCC pavement placement.</ITM><BRK/>
<BRK/>
<ITM>a.  Include narrative, equipment, crew list, and manufacturer's literature for the following 
operations for normal and adverse weather conditions:</ITM><BRK/>
<ITM>      1) Transporting RCC from plant to placement area</ITM><BRK/>
<ITM>      2) RCC feeders to the laydown equipment</ITM><BRK/>
<ITM>      3) Laydown equipment</ITM><BRK/>
<ITM>      4) Grade and alignment control</ITM><BRK/>
<ITM>      5) Compaction</ITM><BRK/>
<ITM>      6) Curing</ITM><BRK/>
<BRK/>
<ITM>b.  Instructions on adjustments and operating procedures including corrective action(s) necessary 
to assure a tight, smooth surface on the RCC pavement, free of tears and other surface imperfections, 
including surface pitting.</ITM><BRK/>
<BRK/>
<ITM><SUB>Test Section</SUB></ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The test section should demonstrate ALL the required elements specified 
and should be done after calibration of the mixing plant.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>  A detailde plan of the proposed test section layout, location, and placement sequence at least 
14 days prior to placement of the test section.</ITM><BRK/>
<BRK/>
<ITM><SUB>Placement Schedule</SUB></ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This requirement may be deleted if it is duplicated in the overall project 
schedule.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>  Schedule of paving operations, at least [28][_____] days prior to start of paving unless otherwise 
specified.</ITM><BRK/>
<BRK/>
<ITM><SUB>Contractor Quality Control</SUB></ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This submittal requires verification that the laboratory has passed COE 
laboratory validation.  Such validation does not preclude specific facility 
and staff qualifications specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>  A detailed plan of the proposed facility, equipment, procedures and qualifications at least 
[14][_____] days prior to placement of the test section.  Include:</ITM><BRK/>
<BRK/>
<ITM>a.  Qualifications of Contractor CQC Staff</ITM><BRK/>
<ITM>b.  Laboratory accreditation documents and staff certifications</ITM><BRK/>
<ITM>c.  Equipment list and calibration cerificates</ITM><BRK/>
<ITM>d.  Nuclear gage license and calibration curves.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Placing and Spreading</SUB></ITM><BRK/>
<BRK/>
<ITM>  If concrete is to be placed in or exposed to hot or cold weather conditions, a description 
of the placing and protection methods proposed, prior to construction of the test section.  
Unless otherwise directed or approved, placing shall begin along the low side of sloped areas.</ITM><BRK/>
<BRK/>
<ITM><SUB>Joints</SUB></ITM><BRK/>
<BRK/>
<ITM>  A detailed plan of the proposed paving pattern showing all planned construction joints and 
curing water runoff control.</ITM><BRK/>
<BRK/>
<ITM><SUB>Waybills and Delivery Tickets</SUB></ITM><BRK/>
<BRK/>
<ITM>  Copies of waybills or delivery tickets for cementitious material, during the progress of the 
work.  Before the final payment is allowed, waybills and certified delivery tickets shall be 
furnished for all cementitious material used in the construction.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7   QUALITY ASSURANCE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.7.1   Sampling and Testing</TTL><BRK/>
<BRK/>
<TXT>The Government may sample and test aggregates and concrete during construction and inspect production and placement 
facilities and equipment to determine compliance with the specifications as specified herein and as otherwise 
considered appropriate.  Provide facilities and labor as may be necessary for procurement of representative test 
samples.  Testing performed by the Government will not relieve the Contractor from the quality control testing 
requirements specified.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.2   Allowable Variations</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Table V is a comprehensive listing of geometric and testing limits and 
corresponding allowable variations.  Edit those values as appropriate for the 
project.  Edit line items as appropriate.  Where payment adjustment is not to 
be done, edit the exceedance action column to remove pay adjustment and add 
requirement.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Comply with the limits for parameters shown in Table V.  The table identifies specified limits and allowable 
variations from these limits.</TXT><BRK/>
<TBL><BRK/>
<THD>             TABLE V - LIMITS AND ALLOWABLE VARIATIONS<BRK/>
 Parameter    Specified Limit    Allowable Variation     Exceeding Action</THD><BRK/>
<BRK/>
Cementitious  Conforming to      Zero to plus 4% by   Remove and Replace if<BRK/>
Material      mix design         weight               further quantity <BRK/>
content       targets                                 reduction required<BRK/>
<BRK/>
Grade         As shown on the      Plus or minus 13     Remove and replace<BRK/>
              contract dwings      mm (1/2 inch)        <BRK/>
<BRK/>
Alignment     As shown on the      Up to 13 mm (1/2     Remove and replace<BRK/>
              contract dwings      inch) variation<BRK/>
<BRK/>
Thickness     As shown on the      Plus or minus 6 mm   [Pay adjustment up to<BRK/>
              contract             (1/4 inch)           13 mm (1/2 inch, <BRK/>
              drawings                                  otherwise] remove and<BRK/>
                                                        replace<BRK/>
<BRK/>
Density in accordance with <RID>ASTM D 1557</RID> 98.0% interior   [Pay adjustment or]<BRK/>
              Laboratory test      96.0% at joints      remove and replace<BRK/>
<BRK/>
Smoothness    Checked with         Up to 10% of all     [Pay adjustment or]<BRK/>
              appr 4 m (12 ft)     measurements with-   remove and replace<BRK/>
              straight edge        in specified limit<BRK/>
<BRK/>
[Tank hardstands Longitudinal      10 mm (3/8 inch)<BRK/>
parking areas,   Transverse        10 mm (3/8 inch)<BRK/>
open store areas]<BRK/>
<BRK/>
[Roads and Str.] Longitudinal      5 mm (3/16 inch)<BRK/>
                 Transverse        6 mm (1/4 inch)<BRK/>
<BRK/>
Abrupt Offsets   Any direction     3 mm (1/8 inch)      [Grind to specified<BRK/>
                                                        tolerance or] remove<BRK/>
                                                        and replace<BRK/>
<BRK/>
Surface Texture  Conforming to     Up to 5% of area     [Pay adjustment or]<BRK/>
                 designated test   less than test patch remove and replace<BRK/>
                 patch on test     surface textures<BRK/>
                 section<BRK/>
<BRK/>
Strength         Specified         Not more than [10%]  Remove and replace if<BRK/>
                 Strength          of strength results  more than [10%] of <BRK/>
                                   can be less than     test results is less<BRK/>
                                   f'c                  specified f'c</TBL><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.8   DELIVERY, STORAGE, AND HANDLING</TTL><BRK/>
<BRK/>
<SPT><TTL>1.8.1   Bulk Cementitious Materials</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Cement storage consists of dedicated plant silos for each cementitious 
material.  In addition, higher capacity storage tankers (aka guppies, pigs) 
are often stored on site.  Cementitious materials are usually truck hauled from 
the closest terminal or rail cars can be used as a temporary terminal.  Dual 
silos must contain a clear air space between silo sidewalls to prevent cross 
contamination.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Furnish cementitious material in bulk.  The temperature of the cementitious material, as delivered for storage 
at the site, shall not exceed<MET> 65 degrees C</MET><ENG> 150 degrees F</ENG>.  Provide separate facilities for unloading, transporting, 
storing, and handling of each type of cementitious material.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.8.1.1   Transporting Cementitious Materials</TTL><BRK/>
<BRK/>
<TXT>When bulk cementitious material is not unloaded from primary carriers directly into weather-tight hoppers at 
the batching plant, transportation from the railhead, mill, or intermediate storage to the batching plant shall 
be accomplished in adequately designed weather-tight trucks, conveyors, or other means that will completely protect 
the cementitious material from exposure to moisture.  Submit copies of the <SUB>Waybills and Delivery Tickets</SUB> to the 
Contracting Officer, as specified in the Submittals paragraph.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.8.1.2   Storage of Cementitious Materials</TTL><BRK/>
<BRK/>
<TXT>Immediately upon receipt at the site of the work, store cementitious materials in a dry and properly ventilated 
structure.  All storage facilities shall permit easy access for inspection and identification.  To prevent cement 
from becoming unduly aged after delivery, use any cement that has been stored at the site for 60 days or more 
before using cement of lesser age.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.8.2   Aggregate Materials</TTL><BRK/>
<BRK/>
<SPT><TTL>1.8.2.1   Storage</TTL><BRK/>
<BRK/>
<TXT>Aggregate shall be stored at the site of the mixing plant, avoiding breakage, segregation, or contamination by 
foreign materials.  Each size of aggregate from each source shall be stored separately in free-draining stockpiles.  
Aggregate shall remain in free-draining storage for at least 24 hours immediately prior to use.  At least [50] 
percent of the aggregate required for the [project][phase] shall be maintained at the site at all times to permit 
continuous uninterrupted operation of the mixing plant at the time RCC is being placed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.8.2.2   Handling</TTL><BRK/>
<BRK/>
<TXT>Aggregate shall be handled preventing segregation or degradation.  Vehicles used for stockpiling or moving aggregate 
shall be kept clean of foreign materials.  Selective withdrawal and loader mixing of aggregates from the stockpile 
shall be done to blend materials prior to loading the bins.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT></PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   MATERIAL SOURCES</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.1   Aggregate Sources</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The specification provides in Table VI a complete list of material properties 
that the aggregate must have to be used on the project.  It is the Contractor's 
responsibility to find sources that meet those requirements prior to the start 
of work and throughout the work.<BRK/>
<BRK/>
Where complete testing has been done to determine acceptable sources, it may 
be expedient to list the sources that have been tested and are acceptable.<BRK/>
<BRK/>
Where it is intended that a specific source or sources be used exclusively, 
they should be listed and so stated.<BRK/>
<BRK/>
Performance testing of aggregate will require at least 90 days to perform the 
required freezing and thawing tests.  Requirements for Contractor testing or 
design phase government testing of aggregate quality should be evaluated based 
on project schedule requirements.</NPR><BRK/>
<BRK/>
<NPR>Where service records are acceptable in lieu of performance testing, satisfactory 
service record for an aggregate will be determined based on the aggregate's 
ability to resist degradation under traffic and/or climatic conditions similar 
to that expected during its use.  If performance data indicate that an aggregate 
is susceptible to one or more of the above mentioned problems, that source of 
aggregate will be rejected.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Locate and test the sources from which the aggregates are to be obtained.  All aggregate for each nominal size 
group of aggregates shall be from a single aggregate source and shall meet specified quality requirements.  Complete 
aggregate quality testing prior to performing mixture proportion studies.[  The following sources are acceptable 
for RCC pavement construction:</TXT><BRK/>
<BRK/>
<LST>a.  Source a, name, location, owner, contact information.</LST><BRK/>
<LST>b.  Source [b][_____]]</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.2   Portland Cement Source</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Confirm that required portland cement is available in the required quantity 
from a single source.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide portland cement from sources actively producing portland cement that have a documented record of consistent 
physical and chemical properties meeting the specified provisions of [<RID>ASTM C 150</RID>][<RID>ASTM C 1157</RID>].  Submit production 
tests for the past 2 years to verify acceptable performance.  All portland cement for the project shall be from 
a single source.  A second source of portland cement may be used if documentation is provided that the primary 
source cannot provide for the entire project needs.  Test additional trial mixtures to confirm mixture performance.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.3   Aggregate Samples</TTL><BRK/>
<BRK/>
<TXT>Provide facilities for the ready procurement of representative test samples for Government testing.  Oobtain 
samples of aggregates during paving at the point of batching.  Additional tests and analyses of aggregates at 
various stages in the processing and handling operations may be made by the Government at the discretion of the 
Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4   Pozzolan Source</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>Note:  Confirm that required pozzolan is available in the required quantity 
from a single source.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide pozzolan from sources actively producing pozzolan that have a documented record of consistent physical 
and chemical properties meeting the specified provisions of <RID>ASTM C 618</RID>.  Submit production tests for the past 
2 years to verify acceptable performance.  All pozzolan for the project shall be from a single source.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.5   Ground Granulated Blast Furnace Slag Source</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Confirm that required GGBFS is available in the required quantity from 
a single source.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide GGBFS from sources actively producing GGBFS that have a documented record of consistent physical and 
chemical properties meeting the specified provisions of <RID>ASTM C 989</RID>.  Submit production tests for the past 2 years 
to verify acceptable performance.  All GGBFS for the project shall be from a single source.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2   CEMENTITIOUS MATERIALS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Portland Cement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The option of Type I or Type II portland cement should normally be specified, 
but only type II portland cement should be required when moderate resistance 
to sulfate attack is needed.  Low alkali cements should be required when alkali 
reactive aggregates are used in the concrete.  The false set requirement should 
be added if a history of false set exists for the area.  Portland cement may 
also be specified using performance specification ASTM C 1157.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Portland cement shall conform to <RID>ASTM C 150</RID>, Type [I][II][IV][, low alkali] [, including the false set requirement].  
Low alkali cement shall be used if the proposed aggregates are found to have greater than 0.04 percent expansion 
when tested in accordance with paragraph: Alkali-Silica Reactivity.  Portland cement shall conform to <RID>ASTM C 1157</RID>
, Type [GU][MS][HS][MH][LH], including [Option R, Low Reactivity with Alkali-Reactive Aggregates][Optional Physical 
Requirements].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2   Pozzolan</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The supplemental requirements for limit on alkalies and limit on reactivity 
in brackets should be specified any time low alkali cement is specified or if 
class C pozzolan is permitted.  Class C pozzolan should not be used if there 
is potential for sulfate attack.  The supplemental requirements a-c should be 
used if there is potential for sulfate attack.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Fly ash shall conform to the requirements of <RID>ASTM C 618</RID>, Class [F][C], including the optional requirements for 
drying shrinkage, uniformity, and effectiveness in controlling Alkali-Silica reaction and shall have a loss on 
ignition not exceeding [3][6] percent.  Class F fly ash for use in mitigating Alkali-Silica Reactivity shall 
have a Calcium Oxide (CaO) content of less than 8 percent.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3   Portland-Pozzolan Cement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The optional requirement for mortar expansion should be specified when 
the Portland-pozzolan cement will be used with alkali-reactive aggregate.<BRK/>
<BRK/>
If portland-pozzolan cement is not locally and readily available, remove this 
paragraph and all other references to the material in this specification.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Portland-pozzolan cement shall conform to the requirements of <RID>ASTM C 595</RID>, Type IP or Type I(PM), including requirement 
for [mortar expansion][sulfate resistance] contained in Table III.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.4   Ground Granulated Blast Furnace Slag</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If ground granulated blast furnace slag is not locally and readily available, 
remove this paragraph and all other references to the material in this specification.  
Select the appropriate grade of GGBFS.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ground granulated blast furnace slag shall conform to the requirements of <RID>ASTM C 989</RID>, grade [80][100][120].</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3   WATER</TTL><BRK/>
<BRK/>
<TXT>Provide water conforming to the requirements of <RID>COE CRD-C 400</RID> that is clean, fresh, and free from injurious amounts 
of oil, acid, salt, alkali, organic matter, and other substances deleterious to the hardening of concrete, subject 
to approval.  Water that meets local drinking water satndards and has no pronounced taste or odor may be used 
without testing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4   CURING MATERIALS</TTL><BRK/>
<BRK/>
<LST>a. Impervious-Sheet materials shall conform to <RID>ASTM C 171</RID>.  The type is potional.</LST><BRK/>
<BRK/>
<LST>b. Membrane-Forming curing compund shall conform to [<RID>ASTM C 309</RID>, Type 1-D or 2][<RID>COE CRD-C 300</RID>]  Nonpigmented 
compound shall contain a fugitive dye, and shall have the reflective requirements in <RID>ASTM C 309</RID> waived.</LST><BRK/>
<BRK/>
<LST>c. Burlap and cotton mat used for curing shall conform to <RID>AASHTO M 182</RID>.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5   AGGREGATES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Modify the 90 percent limits if local information indicates that available 
aggregates cannot comply with this requirement and it is in the government's 
best interest to allow such a variation.<BRK/>
<BRK/>
If the desire is to use State approved aggregates sources, revise the table 
values to match the state requirements and add supplemental line items as necessary.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Furnish, separately, both fine and coarse aggregates that meet requirements of these specifications.  The coarse 
aggregate may consist of one or more nominal size groups each consisting of at least [90][_____] percent by weight 
of aggregate retained on the<MET> 4.75 mm</MET><ENG> No. 4</ENG> sieve, and the fine aggregate and blending material, if used, shall 
have at least [90][_____] percent by weight of aggregate passing the<MET> 4.75 mm</MET><ENG> No. 4</ENG> sieve.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.5.1   Coarse Aggregate</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Crushing the gravel tends to improve quality and bond characteristics 
and generally results in higher flexural strength of concrete and a more stable 
mixture under compaction.  When mixture proportioning studies or local experience 
indicates that low flexural strength will be attained by using an uncrushed 
gravel, the possibility of attaining higher strength by crushing the gravel 
should be investigated.  When desirable to require all the coarse aggregate 
to be crushed, modify the paragraph by deleting uncrushed gravel and adding 
the sentence in brackets.<BRK/>
<BRK/>
If history of aggregate sources in the project area indicates lower concrete 
strengths are caused if dust and other coatings are not washed from the aggregate, 
then the option in brackets for washing aggregate should be considered if economically 
justified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Coarse aggregate shall consist of crushed or uncrushed gravel, crushed stone, air cooled blast furnace slag, 
or a combination thereof.[  Crushed gravel shall contain not less than 60 percent by weight of crushed particles 
size having at least one freshly fractured face, in each sieve.]  Coarse aggregates shall consist of clean, hard, 
uncoated particles meeting the specified requirements.[  Dust and other coatings shall be removed from the coarse 
aggregate by washing.]  Particles of the coarse aggregate shall be generally spherical or cubical in shape.  
Coarse aggregate shall meet the test limits and requirements of TABLE VI - QUALITY LIMITS FOR AGGREGATE</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.2   Fine Aggregate</TTL><BRK/>
<BRK/>
<SPT><TTL>2.5.2.1   General Requirements</TTL><BRK/>
<BRK/>
<TXT>Fine aggregate shall consist of natural sand, manufactured sand, or a combination of the two meeting the requirements 
of TABLE VI - QUALITY LIMITS FOR AGGREGATE.  Where necessary to meet grading requirements, a fine blending material 
may also be used.  Particles of the fine aggregate shall be generally spherical or cubical in shape.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.2.2   Blending Material</TTL><BRK/>
<BRK/>
<TXT>To meet the specified gradation, additional fines (minus<MET> 0.150 and 0.075 mm</MET><ENG> No. 100 and No. 200</ENG> sieve size material), 
if necessary, shall be provided by adding to the aggregates a fine blending sand or pozzolan (fly ash).  If pozzolan 
is used, it shall be the same material as furnished for cementitious material as required by paragraph CEMENTITIOUS 
MATERIALS.  Pozzolan, if used for this purpose, shall be batched or fed together with pozzolan used as cementitious 
material and shall be furnished at the Contractor's expense.  Blending sand, if used, shall be a clean, hard, 
siliceous material meeting all quality requirements specified herein for fine aggregate and shall be furnished 
to the mixer as a separate material.</TXT><BRK/>
<TBL><BRK/>
<THD>         TABLE VI - QUALITY LIMITS FOR AGGREGATE<BRK/>
<BRK/>
            Parameters                       Test Method         Coarse  Fine<BRK/>
                                                                 Aggr    Aggr<BRK/>
                                                                   E       F <BRK/></THD>
<BRK/>
Characterization Tests:<BRK/>
a Sieve Analysis                           <RID>ASTM C 136</RID>  (a)     (a)<BRK/>
b Specific Gravity &amp; Absorption, BSSD      <RID>ASTM C 127</RID>  (b)     (b)<BRK/>
                                         &amp; <RID>ASTM C 128</RID><BRK/>
Tests for Deleterious Materials (c) (d)<BRK/>
c Materials finer than 0.075 mm (No. 200)  <RID>ASTM C 117</RID>  1.0     3.0<BRK/>
  sieve, max % by wt. (e)<BRK/>
d Clay lumps, max % by wt.                 <RID>ASTM C 142</RID>  2.0     1.0<BRK/>
e Lightweight particles, max % by wt.      <RID>ASTM C 123</RID>  1.0     0.5<BRK/>
  (BSSD Sp. Gr.2.00) (f)<BRK/>
f Chert and cherty stone, max % by wt.     <RID>ASTM C 295</RID>   --      --<BRK/>
  (BSSD Sp. Gr. &lt;2.40)<BRK/>
g Shale, max % by wt.                      <RID>ASTM C 295</RID>   --      --<BRK/>
h Clay ironstone, max by wt.               <RID>ASTM C 295</RID>   --      --<BRK/>
i Claystone, mudstone, and siltstone,      <RID>ASTM C 295</RID>   --      --<BRK/>
  max % by wt.<BRK/>
j Shaly and argillaceous limestone,        <RID>ASTM C 295</RID>   --      --<BRK/>
  max % by wt.<BRK/>
k Other soft particles, max % by wt.    <RID>COE CRD-C 130</RID>  2.0      --<BRK/>
K Total of all deleterious substances,                            5.0      --<BRK/>
  exclusive of material finer than<BRK/>
  0.075 mm (No. 200) sieve, c through<BRK/>
  k, max % by wt.<BRK/>
<BRK/>
Other Quality Tests:<BRK/>
l Flat and elongated particles, max %      <RID>ASTM D 4791</RID>  20      --<BRK/>
  by wt.<BRK/>
m Resistance to Freezing and Thawing     <RID>COE CRD-C 130</RID>  50      50<BRK/>
  using conventional concrete specimens<BRK/>
  if no service record of performance,<BRK/>
  min DFE<BRK/>
n Los Angeles Abrasion, max % loss by wt.   <RID>ASTM C 131</RID>  40      NA<BRK/>
o Organic Impurities, max color number       <RID>ASTM C 40</RID>  NA       3<BRK/>
p Effect of Organic Impurities, % of std.    <RID>ASTM C 87</RID>  NA    pass<BRK/>
q Petrographic examination to assess        <RID>ASTM C 295</RID>  yes    yes<BRK/>
  potentially alkali-silica reactive<BRK/>
  constituents (f) (g)<BRK/>
r Alkali Reactivity, max expansion at      <RID>ASTM C 1260</RID>  0.08  0.08<BRK/>
  16 days (f)</TBL><BRK/>
<BRK/>
<TXT>The following notes correspond to bracketed references (x) in Table VI:</TXT><BRK/>
<BRK/>
<LST>a. The combined aggregate grading must meet the requirements of Table VI.  Reference paragraph Aggregate 
Gradation.</LST><BRK/>
<BRK/>
<LST>b. Specific gravity and absorption are required for each aggregate size group for use in trial mixture 
proportioning.</LST><BRK/>
<BRK/>
<LST>c. Tests for deleterious materials require a petrographic analysis in accordance with <RID>ASTM C 295</RID> for 
determining the presence of shale, clay ironstone, chert, cherry stone, claystone, mudstone, siltstone 
and shaly and argillaceous limestone.</LST><BRK/>
<BRK/>
<LST>d. The test sample size of coarse aggregate shall be at least<MET> 100 kg</MET><ENG> 220 lbs</ENG> for nominal size groups 
greater than<MET> 19 to 38 mm</MET><ENG> 3/4 to 1-1/2 inch</ENG> and<MET> 11.5 kg</MET><ENG> 26 lbs</ENG> for the<MET> 5 to 19 mm</MET><ENG> No. 4 to 3/4 inch</ENG> coarse 
aggregate.  The minimum test sample for fine aggregate shall be<MET> 5 kg</MET><ENG> ll lbs</ENG>.  The testing procedure on 
each sample of coarse aggregate for compliance with limits on deleterious materials shall be as follows:</LST><BRK/>
<BRK/>
<ITM>1). Step 1:  Test approximately one-fifth of sample for material finer than the<MET> 0.075 mm</MET><ENG> No. 
200</ENG> sieve.</ITM><BRK/>
<BRK/>
<ITM>2). Step 2:  Wash off material finer than the<MET> 0.075 mm</MET><ENG> No. 200</ENG> sieve from the remainder of the 
sample and recombine the remainder with material retained on the<MET> 0.075 mm</MET><ENG> No. 200</ENG> sieve from 
Step 1.</ITM><BRK/>
<BRK/>
<ITM>3). Step 3:  Test remaining full sample for clay lumps and friable particles and remove.</ITM><BRK/>
<BRK/>
<ITM>4). Step 4:  Test remaining full sample for lightweight particles and remove, and then for chert 
and/or cherty stone with SSD density of less than Sp. Gr. 2.40 and remove.</ITM><BRK/>
<BRK/>
<ITM>5). Step 5:  Test remaining sample for clay-ironstone, shale, claystone, mudstone, siltstone, 
shaly and/or argillaceous limestone, and remove.  This work shall be done by a licensed petrographer.</ITM><BRK/>
<BRK/>
<ITM>6). Step 6:  Test approximately one-fifth of remaining full sample for other soft particles.</ITM><BRK/>
<BRK/>
<LST>e. The limit for material finer than<MET> 0.075 mm</MET><ENG> No. 200</ENG> sieve will be increased to 1.5 percent for crushed 
coarse aggregates and 5.0 percent for fine aggregates if the fine material consists of crusher dust and 
supplemental tests confirm that the material is essentially free from clay or shale.  The separation 
medium shall have a specific gravity of 2.0.  This limit does not apply to coarse aggregate manufactured 
from blast-furnace slag unless contamination is evident.</LST><BRK/>
<BRK/>
<LST>f. Determination of potential alkali reactivity of aggregates is a complex process that may involve additional 
testing if results of petrographic examination and <RID>ASTM C 1260</RID> tests indicate potential deleterious reactivity.  
See paragraph: Alkali-Silica Reactivity for requirements.</LST><BRK/>
<BRK/>
<LST>g. The petrographer meeting the requirements of <RID>ASTM C 856</RID> shall be subject to approval and at least 
10 days before any individual is proposed to commence this type of work, submit a written resume of the 
individual's training and experience for approval by the Government.  The Contractor will not be entitled 
to any extension of time or additional payment due to any delays caused by the testing, evaluation or 
personnel requirements specified herein.</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.5.3   Alkali-Silica Reactivity</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use these paragraphs for regions where aggregates have a history of high 
alkali-silica reactivity.  This requirement is more restrictive than the procedure 
required in Table III.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Evaluate and test fine and coarse aggregates to be used in all concrete for alkali-aggregate reactivity in accordance 
with <RID>ASTM C 1260</RID>.  Test both coarse aggregate size groups if from different sources.  Evaluate the fine and coarse 
aggregates separately and in combination matching the proposed mix design proportioning.  Test results of each 
individual group and combination must have a measured expansion less than 0.08 percent at 16 days after casting.  
Should the test data indicate an expansion equal to or greater than 0.08 percent, reject the aggregate(s) or 
perform additional testing in accordance with <RID>ASTM C 1567</RID> using one of the following options.  If any of the 
above options does not lower the expansion to less than 0.08 percent at 16 days after casting, reject the aggregate(s) 
and submit new aggregate sources for retesting.  Submit the results of testing to the Contracting Officer for 
evaluation and acceptance</TXT><BRK/>
<BRK/>
<SPT><TTL>2.5.3.1   Class F Flyash Option</TTL><BRK/>
<BRK/>
<TXT>Utilize the Contractor's proposed low alkali portland cement and Class F fly ash pozzolan in combination with 
the proposed aggregate percentage for the test proportioning.  Use Class F fly ash pozzolan in the range of 25 
percent to 40 percent of the total cementitious material by mass.  Determine the quantity that will meet all 
the requirements of these specifications and that will lower the expansion to less than 0.08 percent at 16 days 
after casting.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.3.2   GGBF Option</TTL><BRK/>
<BRK/>
<TXT>Utilize the Contractor's proposed low alkali portland cement and ground granulated blast furnace (GGBF) slag 
in combination with the proposed aggregate percentage for the test proportioning.  Use GGBF slag in the range 
of 40 percent to 50 percent of the total cementitious material by mass.  Determine the quantity that will meet 
all the requirements of these specifications and that will lower the expansion to less than 0.08 percent at 16 
days.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.5.4   Aggregate Gradation</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The combined aggregate grading is the property that must be evaluated 
and controlled.  However, aggregates are stockpiled and handled in size groups 
that are typically fine aggregate (5 to 0 mm (No. 4 to 0), 19 to 5 mm (3/4-inch 
to No. 4), and 38 to 19 mm (1.5 to 3/4 inch)).  This section requires that the 
Contractor designate the size groups, the gradings of each size group, and the 
proportion of each size group such that the combined grading is met.  Typically 
the grading of each size group is monitored and controlled with little regard 
for the combined grading.  This specification requires that the combined grading 
also be monitored and controlled.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The combined aggregate shall consist of a minimum of at least two nominal size groups consisting of coarse and 
fine aggregate with blending material, if necessary, as previously described.  Each nominal aggregate size group 
shall have a gradation such that the two or more materials can be combined in proportions that will produce a 
combined gradation within the specified limits. Each size group of aggregate and blending material shall be batched 
separately or otherwise fed separately to the mixer.  The specified grading limits are determined in a 2 part 
process: 1) determining the initial combined aggregate grading and 2) determining the base grading limit.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.5.4.1   Initial Combined Aggregate Grading Limits</TTL><BRK/>
<BRK/>
<TXT>Nominal aggregate size groups shall be combined to produce a uniform distribution of aggregate particles forming 
a smooth, well-graded curve.  The Contractor's selected aggregate blend shall fall within the limits specified 
in the Table VII - Initial Combined Aggregate Grading Limits.  Sieve analysis of fine and coarse aggregates (<RID>
ASTM C 136</RID>, <RID>ASTM C 117</RID>) shall be performed to develop the Contractor's selected aggregate blend and initial grading.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>TABLE VII - Initial Combined Aggregate Grading Limits</HL4><BRK/>
<BRK/>
                                             Cumulative Percent<BRK/>
            Sieve Size                       by Weight Passing<BRK/>
            __________                       __________________<BRK/></THD>
<BRK/>
             25 mm                                    100<BRK/>
             19 mm                                 85-100<BRK/>
             12.5 mm                               70-95<BRK/>
              9.5 mm                               55-85<BRK/>
              4.75 mm                              40-65<BRK/>
              2.36 mm                              30-55<BRK/>
              1.18 mm                              20-45<BRK/>
              0.600 mm                             15-35<BRK/>
              0.300 mm                             10-25<BRK/>
              0.150 mm                              5-15<BRK/>
              0.075 mm                              2-10<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>TABLE VII - Initial Combined Aggregate Grading Limits</HL4><BRK/>
<BRK/>
                                             Cumulative Percent<BRK/>
            Sieve Size                       by Weight Passing<BRK/>
            __________                       __________________<BRK/></THD>
<BRK/>
             1 inch                                   100<BRK/>
             3/4 inch                              85-100<BRK/>
             1/2 inch                              70-95<BRK/>
             3/8 inch                              55-85<BRK/>
             No. 4                                 40-65<BRK/>
             No. 8                                 30-55<BRK/>
             No. 16                                20-45<BRK/>
             No. 30                                15-35<BRK/>
             No. 50                                10-25<BRK/>
             No. 100                                5-15<BRK/>
             No. 200                                2-10</TBL></ENG><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.4.2   Base Aggregate Grading Limits</TTL><BRK/>
<BRK/>
<TXT>After testing is completed and the aggregate blend meeting the initial combined aggregate grading shown in Table 
VII is selected, and after mix proportions and properties are determined using the selected blend, the base grading 
limits of each nominal size group of aggregate to be used during production shall be established.  The base grading 
limit for each nominal aggregate size group, including any necessary blending material, shall be the grading 
used in the mix proportioning study with tolerances shown in Table VIII applied to each individual sieve size.  
The base grading limit for each aggregate size group will then be used for acceptance of aggregates entering 
the mixer.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>TABLE VIII - Grading Limits for Each Aggregate Sieve Size</HL4><BRK/>
<BRK/>
                                         Tolerance, plus or minus<BRK/>
               Sieves                        Percentage points<BRK/>
               ______                    ________________________<BRK/></THD>
<BRK/>
        12.5 mm, 9.5 mm                              5<BRK/>
        2.36 mm, 1.18 mm, 0.600 mm                   4<BRK/>
        25 mm, 19 mm, 4.75 mm, 0.300 mm              3<BRK/>
        0.150 mm, 0.075 mm                           2<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>TABLE VIII - Grading Limits for Each Aggregate Sieve Size</HL4><BRK/>
<BRK/>
                                         Tolerance, plus or minus<BRK/>
               Sieves                        Percentage points<BRK/>
               ______                    ________________________<BRK/></THD>
<BRK/>
        1/2 inch, 3/8 inch,                          5<BRK/>
        No. 8, No. 16, No. 30                        4<BRK/>
        1 inch, 3/4 inch, No. 50, No. 4              3<BRK/>
        No. 100, No. 200                             2</TBL></ENG><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>2.6   ADMIXTURES</TTL><BRK/>
<BRK/>
<TXT>Water-reducing and retarding admixtures, if used, shall conform to <RID>ASTM C 494/C 494M</RID>, Type B or D.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7   EQUIPMENT</TTL><BRK/>
<BRK/>
<SPT><TTL>2.7.1   Paver Requirements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This specification prohibits the use of traditional asphalt concrete 
pavers.  Those are pavers that consolidate the material using a vibrating screed 
plate.  The specified paver, also used for asphalt concrete, utilizes one or 
more tamping bars that compacts the material before exiting the machine.  Much 
higher degree of compaction is attained by this type of machine.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Pavers shall be heavy-duty, track-equipped machines of the self-propelled type, similar to laydown machines (pavers) 
used for asphalt concrete or soil-cement construction.  The pavers shall:</TXT><BRK/>
<BRK/>
<LST>a.  Be equipped with hoppers, distributing screws, vibrating screen and/or at least one tamping bar, 
adjustable screeds capable of being operated both manually and automatically, and equalizing devices.</LST><BRK/>
<BRK/>
<LST>b.  Be of suitable weight and stability to spread and finish the concrete to the indicated thickness, 
smoothness, and surface texture requirements.</LST><BRK/>
<BRK/>
<LST>c.  Confine edges of lanes to true lines without use of stationary side forms and shall place the concrete 
to the required thickness, free from segregation.</LST><BRK/>
<BRK/>
<LST>d.  Shall be equipped with interchangeable side forms (shoes) which will form the edge of the pavement 
lane either vertically or 15 degrees from vertical.</LST><BRK/>
<BRK/>
<LST>e.  Be designed to operate forward at variable speeds and in reverse.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.2   Paver Control</TTL><BRK/>
<BRK/>
<TXT>The pavers shall automatically control both line and grade by means of electronic controls operating from stationary 
stringlines on both sides of the paver.  However, as appropriate, a short ski riding on an adjacent paved lane 
may be used in lieu of one of the stringlines.  Laser control devices may be used in lieu of a stringline provided 
the entire process is approved.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.3   Compaction Equipment</TTL><BRK/>
<BRK/>
<SPT><TTL>2.7.3.1   Vibratory Rollers</TTL><BRK/>
<BRK/>
<TXT>Vibratory rollers shall be self-propelled, double-drum, steel-wheeled.  Within the range of the operational capability 
of the equipment, the Contracting Officer may direct or allow variations within the specified range to the frequency, 
amplitude, and speed of operation which result in the required density and satisfactory surface texture at the 
fastest production rate.  At least one self-propelled vibratory roller, in good operating condition and meeting 
these requirements, shall be used full time for each paver used full time.  Any rollers that pick up material 
from the surface of the pavement shall be adjusted, modified, or replaced.  The vibratory roller shall have the 
following features:</TXT><BRK/>
<BRK/>
<LST>a. An average operating weight per drum of at least<MET> 2.7 kg/mm</MET><ENG> 150 pounds/lineal inch</ENG> of drum.</LST><BRK/>
<BRK/>
<LST>b. A dynamic impact to the surface through the drums by means of revolving weights, eccentric shafts, 
or other equivalent methods.</LST><BRK/>
<BRK/>
<LST>c. A vibrating frequency of at least 1,500 cycles per minute.</LST><BRK/>
<BRK/>
<LST>d. An amplitude between<MET> 0.38 and 1.02 mm</MET><ENG> 0.015 and 0.040 inch</ENG> at the operating frequency used.</LST><BRK/>
<BRK/>
<LST>e. Controls that permit ready variation of the amplitude at a minimum of two settings over at least 50 
percent of the above range.</LST><BRK/>
<BRK/>
<LST>f. Drum diameter  between<MET> 1219 and 1676 mm</MET><ENG> 48 and 66 inches</ENG> and between<MET> 1676 to 2438 mm</MET><ENG> 66 to 96 inches</ENG>
 in width.</LST><BRK/>
<BRK/>
<LST>g. Each drum equipped with an operating scraper and pad.</LST><BRK/>
<BRK/>
<LST>h. Equipped with a means of keeping the drums damp during operation.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.3.2   Rubber-Tired Roller</TTL><BRK/>
<BRK/>
<TXT>The rubber-tired roller shall have the following features:</TXT><BRK/>
<BRK/>
<LST>a. Smooth tires, nonoscillating wheels and a tire pressure adjustable between a minimum of<MET> 345 and a 
maximum of 620 kPa</MET><ENG> 50 and a maximum of 90 psi</ENG> and with a total load between<MET> 1400 and 2000 kg</MET><ENG> 3,000 and 
4,500 pounds</ENG> per wheel.</LST><BRK/>
<BRK/>
<LST>b. 2 axles with at least 3 wheels per axle, offset so the front and back tires do not track in the same 
path.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.3.3   Finish Roller</TTL><BRK/>
<BRK/>
<TXT>The smooth-wheeled tandem roller shall weigh<MET> 5 to 9 metric tons</MET><ENG> 5 to 10 tons</ENG>.  The vibratory roller may be used 
without vibration as a finish roller to remove surface blemishes.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.3.4   Other Compaction Equipment</TTL><BRK/>
<BRK/>
<TXT>Light, walk-behind, or similar sized vibratory rollers and mechanical plate vibrators shall be furnished for 
use in compacting areas inaccessible to the large rollers.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.7.4   Straightedge</TTL><BRK/>
<BRK/>
<TXT>Furnish one<MET> 3.6 meter</MET><ENG> 12 foot</ENG> straightedge for each paving spreader for testing the finished surface.  Straightedges 
shall be made available for Government use upon request.  Straightedges shall be constructed of aluminum or other 
lightweight metal and shall have blades of box or box-girder cross section with flat bottom reinforced to ensure 
rigidity and accuracy.  Straightedges shall have handles to facilitate movement on the pavement.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.5   Nuclear Density Gauge</TTL><BRK/>
<BRK/>
<TXT>One operable and properly calibrated nuclear density gauge shall be furnished for each paver.  The nuclear density 
gauge shall be made available for Government use upon request.  The nuclear density apparatus shall conform to <RID>
ASTM C 1040/C 1040M</RID>, Method A, and shall be of a single-probe type.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.6   Curing Equipment</TTL><BRK/>
<BRK/>
<TXT>Equipment for applying membrane-forming curing compound shall have the following features and configuration:</TXT><BRK/>
<BRK/>
<LST>a. Mounted on a self-propelled frame that spans the paving lane.</LST><BRK/>
<BRK/>
<LST>b. The reservoir for curing compound shall be constantly mechanically (not air) agitated during operation 
and shall contain means for completely draining the reservoir.</LST><BRK/>
<BRK/>
<LST>c. A spraying system consisting of a mechanically powered pump which will maintain constant pressure 
during operation and an operable pressure gauge.</LST><BRK/>
<BRK/>
<LST>d. Either a series of spray nozzles evenly spaced across the lane to give uniformly overlapping coverage 
or a single spray nozzle which is mounted on a carriage which automatically traverses the lane width 
at a speed correlated with the forward movement of the overall frame</LST><BRK/>
<BRK/>
<LST>e. All spray nozzles protected with wind screens.</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.8   <SUB>MIXTURE PROPORTIONING</SUB></TTL><BRK/>
<BRK/>
<TXT>The Contractor is responsible for all activities leading to development of a viable RCC pavement mix design.  
The work includes sampling aggregates, collecting materials, and laboratory testing and evaluations.  The Contractor 
will be responsible for initial mixture proportions by the laboratory mixture proportioning trials.  With approval 
of the Contracting Officer, the Contractor may make minor adjustments to the mixture proportions during construction 
as necessary to achieve the desired properties.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.8.1   Laboratory and Staff Qualifications</TTL><BRK/>
<BRK/>
<TXT>The laboratory and testing staff determining the RCC mixture proportions shall meet the same requirements specified 
in paragraph: CONTRACTOR QUALITY CONTROL.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.2   Composition</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  A typical range for most applications is 250 (min) to 350 (max) kg/cubic 
meter (400 (min) to 600 (max) lbs/cubic yard) of cementitious material and 15 
to 25 percent pozzolan by absolute volume replacement of cementitious material.  
Add sentence in last set of brackets on ground slag only if it will be used.  
Actual proportions will be determined by the testing laboratory.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>RCC shall be composed of cementitious material, water, and fine and coarse aggregates, including any necessary 
fine blending material.  The cementitious materials shall be portland cement in combination with pozzolan or, 
at the Contractor's option, cementitious material may be [portland-pozzolan cement] [portland cement in combination 
with ground granulated blast furnace slag].  A retarding admixture may be used, if ambient temperatures above<MET>
 [27][_____]degrees C</MET><ENG> [80][_____] degrees F</ENG> are anticipated during placement.  Other admixtures shall not be 
used unless demonstrated to be beneficial, approved in writing, and used in the mixture proportioning studies.  
Samples of all materials used in the mixture proportioning studies shall be representative of those proposed 
for use on the project.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.3   Criteria for Mixture Proportions</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Pavement design is mostly based on the flexural strength of the mixture.  
Field control of mixtures is most easily done by evaluating compressive strength.  
One purpose of the mix design program is to correlate flexural strength and 
compressive strength of the mixture.  It is important to not overspecify strength 
because that will result in mixtures that generate higher heat and may result 
in more cracking than would otherwise occur.  Consequently overdesign strength 
values should be added to the extent required but not be excessive.  It should 
be added to the specified strength and no separate provision made for computing 
overdesign strength.  Suggest that 10 percent should be added to design compressive 
and flexural strengths.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The RCC mixture shall be proportioned based on the following cirteria:</TXT><BRK/>
<BRK/>
<LST>a. Workability of the mixture shall be appropriate for the paving machine to achieve the required density, 
thickness, grade, and finish texture.</LST><BRK/>
<BRK/>
<LST>b. The mixture shall attain a [28-day][56-day][90-day] [flexural][compressive strength] of [_____] psi.</LST><BRK/>
<BRK/>
<LST>c. The mixture shall be proportioned to minimize the volume of Portland cement.</LST><BRK/>
<BRK/>
<LST>d. The mixture [may][shall] contain pozzolan at a minimum replacement of [15%] of the volume of cementitious 
materials.</LST><BRK/>
<BRK/>
<LST>e. The mixture [may][shall] contain granulated ground blast furnace slag at a minimum replacement of 
[_____] percent of the volume of cementitious materials.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8.4   Mix Design Procedure</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  There is no stardard guide for RCC pavement mixture.  A previous guide, 
CRD C 161 in the Handbook of Cement and Concrete, is based on optimum moisture 
content and not considered as appropriate as the procedure outlined in Appendix 
C "RCC Pavement Mixture Proportioning Method" at the end of this Section.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Total mixture proportions shall be selected generally using the procedure detailed in Appendix C at the end of 
this Section.  [Compressive][ and ][flexural] strength performance shall be determined for each trial mixture 
by testing [3 nominal<MET> 150 by 300 mm</MET><ENG> 6 by 12-inch</ENG> cylinders][ and ][4 nominal<MET> 150 by 500 mm</MET><ENG> 6 by 6 by 20-inch</ENG> 
beams] each at 7, 14, 28,[ 56,][ and ][90] days.</TXT><BRK/>
<BRK/>
<LST>a. Strength.  A minimum of three trial mixes shall be prepared at approximately 2 percent above and below 
the cementitious material content initially selected to meet the target project design [flexural][compressive] 
strength.</LST><BRK/>
<BRK/>
<LST>b. Workability.  For each of the trial mixes, the paste volume shall be adjusted to produce workability 
approximately 10 seconds higher and 10 seconds lower than the target workability level.  Subsequent moisture 
variations shall be based on observed performance during compaction of specimens.</LST><BRK/>
<BRK/>
<LST>c. Pozzolan.  An additional 2 trial mixes shall be designed during the trial mix design study to establish 
the effect of pozzolan.  Using the cementitious material content selected to meet the target project 
design, proportion two additional mixes using 15 and 25 percent pozzolan replacement by volume of cementitious 
material.[  If ground granulated blast furnace slag is used the proportions will vary between 25 and 
50 percent by absolute volume of the cementitious material, depending on the temperature during placing.  
No pozzolan or portland-pozzolan cement will be used if ground granulated blast furnace slag is used.]</LST><BRK/>
<BRK/>
<LST>d. Aggregate Fines.  Using the cementitious material content selected to meet the target project design, 
proportion two additional mixes with fines content (materials passing<MET> 0.075 mm</MET><ENG> No. 200</ENG> sieve) at 2 percent 
above and below the target blend.</LST><BRK/>
<BRK/>
<LST>e. Select the final mixture proportions from the performance data of the trial mixtures that best meets 
the mix performance criteria.  The Contracting Officer may direct further adjustments to the mix proportions 
before and during placement.</LST><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   PRE-PLACEMENT ACTIONS</TTL><BRK/>
<BRK/>
<TXT>Complete the following activities prior to the commencement of pavement placement.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.1   Calibration Block for the Nuclear Density Gauge</TTL><BRK/>
<BRK/>
<LST>a. General.  A calibration block shall be fabricated with concrete materials and proportions representative 
of those to be used during construction.  The calibration block shall be available for use by the Government 
as needed.  The calibration may be either a fabricated block or a test section area.</LST><BRK/>
<BRK/>
<LST>b. Fabricated Block.  The block shall be fabricated before the test section construction begins.  The 
block size shall be<MET> 456 by 456 mm</MET><ENG> 18 by 18 inches</ENG> by the maximum thickness of one lift, plus<MET> 25 mm</MET><ENG> 1 
inch</ENG>.  The block shall be compacted to between 98 and 100 percent of the maximum wet density, which will 
have been determined during mixture design trials.  The moisture content of the concrete used to fabricate 
the block may be increased just enough to facilitate compaction of the mixture (normally 0.1 to 0.5 percent), 
as long as the proportions of the dry materials remain constant and the required density is achieved.  
Drill a hole in the block to accommodate the nuclear density gauge probe.  The block shall be measured 
and weighed to determine the actual density (unit weight) and shall be used to check the calibration 
of the nuclear density gauge.</LST><BRK/>
<BRK/>
<LST>c. Test Section.  In lieu of a fabricated block, designate a portion of the test section or test strip 
to be the calibration area.  The gage location shall be identified and a probe hole maintained for repeated 
testing.  Six<MET> 100 mm</MET><ENG> 4-inch</ENG> diameter full depth cores shall be removed from the perimeter of a<MET> 1219 mm</MET><ENG>
 4-foot</ENG> diameter circle around the probe hole.  The cores shall be trimmed<MET> 25 mm</MET><ENG> 1 inch</ENG> on each end and 
density of each core determined.  The average of the 6 cores shall be used provided that the density 
range is not more than<MET> 32 kg/cubic m</MET><ENG> 2 lbs/cf</ENG>.  The calibration area shall not be disturbed or damaged 
during the construction of any RCC.</LST><BRK/>
<BRK/>
<LST>d. Daily Calibration.  The block shall be used each day before paving begins to calibrate the full-depth 
readings of the nuclear density gauges used by the Contractor and the Government.  Three sets of full 
depth nuclear density gauge tests shall be performed in the direct transmission mode and the results 
for each depth averaged.  This average nuclear density gauge reading shall be compared with the measured 
unit weight of the block and the difference used as a correction factor for all readings taken that day.</LST><BRK/>
<BRK/>
<LST>e. Verification.  All measuring and weighing of the test block and all calibration checking of the density 
gauge shall be performed in the presence of the Contracting Officer.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2   Test Strips</TTL><BRK/>
<BRK/>
<TXT>Place at least [4][_____] test strips in the vicinity of the plant.  These strips shall be one paver width wide 
and<MET> 9-12 m</MET><ENG> 30-40 feet</ENG> in length.  The test strips allow evaluation of the placing characteristics of the mixture 
and to make necessary adjustments prior to placing the test section.  The strips may be demolished within 3 hours 
after placing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3   <SUB>Test Section</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For noncritical pavement areas, the test section may be included into 
the actual pavement area.  For critical areas, the test section should be constructed 
in a separate area near the jobsite, with similar conditions and pavement section 
to the actual construction site.</NPR><BRK/>
<BRK/>
<NPR>The requirement of building the test section 10 days before the main construction 
begins may be lengthened or shortened in the project specifications, depending 
on the confidence of the designer in the ability to obtain the design flexural 
strength in the test section.</NPR><BRK/>
<BRK/>
<NPR>If the test section will be included into the actual pavement area, this paragraph 
should be modified to state that the test section will be removed if it is unacceptable.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>At least 10 days but not more than 60 days prior to construction of the pavement, construct a test section near 
the job site at the location designated on the contract plans.  The Contracting Officer shall be notified at 
least 5 days in advance of the date of test section construction.  The test section shall be placed in portions 
as directed by the Government.  Test sections unacceptable to the Contracting Officer shall be removed at the 
Contractor's expense.</TXT><BRK/>
<BRK/>
<LST>a. Timing.  Two separate days shall be used for construction of the test section.  The test section will 
provide the Contractor the opportunity to develop and demonstrate that the proposed techniques of mixing, 
hauling, placing, compacting, finishing and curing, and the preparation of the construction joints meet 
the contract requirements.  The mixing plant shall be fully operational and calibrated, and uniformity 
testing completed prior to placing the test section.</LST><BRK/>
<BRK/>
<LST>b. Features.  Use the same equipment, materials, and construction techniques on the test section as will 
be used in all subsequent work.  Base course preparation, concrete production, placing, compacting, curing, 
construction of joints, and all testing shall be in accordance with applicable provisions of this specification.  
The test section shall:</LST><BRK/>
<BRK/>
<ITM>1). Be no less than two adjacent paving lanes each<MET> 30 m</MET><ENG> 100 feet</ENG> long.</ITM><BRK/>
<ITM>2). Be constructed to the designated thickness and number of lifts.</ITM><BRK/>
<ITM>3). Use the same lane width proposed for use in the project.</ITM><BRK/>
<ITM>4). Include at least one fresh longitudinal construction joint</ITM><BRK/>
<ITM>5). Include at least one cold transverse joint.</ITM><BRK/>
<ITM>6). Include one longitudinal cold construction joint that is at least 12 hours old before placing 
the adjacent lane.</ITM><BRK/>
<BRK/>
<LST>c. Operational Demonstration.  Demonstrate the ability to meet the specified requirements for:</LST><BRK/>
<BRK/>
<ITM>1). Plant operations and paving start-up procedures.</ITM><BRK/>
<ITM>2). The RCC laydown method and production rate.</ITM><BRK/>
<ITM>3). The rolling pattern and method for the mat, and fresh and cold construction joints.</ITM><BRK/>
<ITM>4). Cold joint preparation.</ITM><BRK/>
<ITM>5). Saw-cutting and joint sealant installation.</ITM><BRK/>
<ITM>6). RCC testing and evaluation methods.</ITM><BRK/>
<BRK/>
<LST>d. Adjustments During Test Placement.  Be prepared to make adjustments to various aspects of the test 
section placement as directed by the Contracting Officer.  Adjustments include:</LST><BRK/>
<BRK/>
<ITM>1). Varying the amplitude and frequency of the roller to identify the optimums.</ITM><BRK/>
<ITM>2). Varying the rolling pattern of the all rollers to determine the best pattern</ITM><BRK/>
<ITM>3). Varying the mixture proportions other than water.</ITM><BRK/>
<ITM>4). Varying the water content, as necessary, to arrive at the appropriate content.</ITM><BRK/>
<BRK/>
<LST>e. Testing.  Remove twelve<MET> [150][100] mm</MET><ENG> [6][4]-inch</ENG> diameter cores and six beams<MET> 150 by 810 mm</MET><ENG> 6 by 
32 inches</ENG>, by full depth, from points selected in the test section by the Contracting Officer 5 days 
after completion of the test section.  Trim the beams to dimensions directed by the Contracting Officer 
and test the cores and beams in accordance with <RID>ASTM C 42/C 42M</RID>.  Perform testing at 7, 28, and 90 days 
of age.</LST><BRK/>
<BRK/>
<LST>f. Acceptance.  The test section shall meet all specified performance factors, density, thickness, strength, 
surface smoothness, and surface texture.  Failure to construct an acceptable test section will necessitate 
construction of additional test sections at no additional cost to the Government.  Remove test sections 
after completion of the test section evaluations.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.4   Subgrade Preparation</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Designer will include the title of the applicable specification section 
used for base course or subgrade, and delete inappropriate sections.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Previously constructed material underlying the RCC pavement shall be conditioned as specified in Section [
<SRF>32 11 27</SRF> BITUMINOUS-STABILIZED BASE COURSE, SUBBASE, OR SUBGRADE][<SRF>32 11 26.16</SRF> PORTLAND CEMENT-STABILIZED BASE 
OR SUBBASE COURSE][<SRF>32 11 36.13</SRF> LIME-STABILIZED BASE COURSE, SUBBASE, OR SUBGRADE][<SRF>32 11 33</SRF> BITUMINOUS BASE COURSE][
<SRF>32 11 16.16</SRF> SUBBASE COURSES][<SRF>32 11 24</SRF> GRADED, CRUSHED AGGREGATE BASE COURSE].  In all cases prior to placing 
concrete, deficiencies in the underlying material shall be corrected, and the surface shall be cleaned and moistened, 
as directed.  The Contracting Officer will inspect and approve the surface of the underlying material prior to 
placing RCC pavement.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.5   Grade Control</TTL><BRK/>
<BRK/>
<TXT>Establish and maintain lines and grades shown on contract drawings for each pavement category of the contract 
by means of line and grade stakes.  Finished pavement gradelines and elevations shown shall be established and 
controlled at the site of work in accordance with bench mark elevations shown on the contract drawings.  The 
surface of the underlying material shall be finished to the necessary grade such that when the required thickness 
of RCC is placed, the pavement surface will meet the indicated grade.  Finished and completed RCC pavement shall 
conform to the lines, grades, cross section, and dimensions indicated.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2   <SUB>TRANSPORTING AND PLACING METHODS</SUB></TTL><BRK/>
<BRK/>
<TXT>Haul concrete from the mixer to the placing site in dump trucks [equipped with protective covers].  The trucks 
shall dump directly into the hopper of the paver or into an approved secondary material distribution system which 
deposits material into the paver hopper.  RCC shall not be dumped onto the prepared subgrade or adjacent areas.  
Schedule deliveries so that concrete will be spread and rolled within the time limit specified in paragraph COMPACTION 
and spreading and rolling of all mixture prepared for 1 day's run can be completed during daylight unless artificial 
lighting is provided.  Loads that have become visibly contaminated or have become wet by rain will be rejected.  
Hauling over freshly placed concrete will not be permitted[, except as approved by the Contracting Officer on 
the lower compacted lift of multilift-pavements].  RCC not meeting these specifications shall be removed from 
the plant or placement area and disposed of [as specified in Section [_____]][at a location designated by the 
Contracting Officer].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3   BATCHING AND MIXING</TTL><BRK/>
<BRK/>
<TXT>Operate the plant to produce a uniform and homogeneous mixture.  The proportions shall be as developed during 
the mixture proportioning process and otherwise approved.  All materials used in the mixture shall be batched 
or fed separately, except that fly ash used as aggregate fines shall be batched or fed with fly ash used as cementitious 
material.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Mixing</TTL><BRK/>
<BRK/>
<TXT>The aggregates, cementitious materials, water, and admixtures shall be conveyed to the mixer in proportions, 
as required.  In batch mixing, aggregates and cementitious materials shall be charged into the mixer and dry-mixed 
at least 15 seconds.  Water shall be added, and mixing shall be continued as required to obtain a homogeneous 
mixture.  The paddles of the pug mill shall be adjusted, as necessary, to provide the required mixing time and 
to provide a thorough  mixing.  Shaft speed of the pug mill shall be maintained at the speed recommended by the 
manufacturer.  RCC shall not extend above the tips of the paddles of the pug mill mixer when paddles are in vertical 
position.  Mixer and mixer paddle surfaces shall be kept free of hardened concrete and other contamination.  
The dimensions of mixer paddles worn down more than 10 percent from new paddles of the same type and manufacture 
shall be replaced.  New paddles shall be available onsite for comparison.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.2   Water Content</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Mixture workability is a major factor in achieving the required density 
and the most desirable surface texture.  Periodic water content adjustments 
are necessary to compensate for stockpile moisture variations or variable aggregate 
properties.  Typically these adjustments are minor and it is normal that the 
Contractor have the latitude to make the adjustments as required.  Otherwise 
a timely response to an observed condition cannot be made.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The initial or start-up water content will be approved by the Contracting Officer based on results of the mixture 
proportioning trials.  After startup, the total water content of the mix shall be controlled as necessary to 
meet all requirements stated herein.  The water content shall be varied at frequent intervals, as necessary and 
as considered appropriate, because of placing and compacting operations and shall in general be based on: 1) 
the action of the vibratory roller on the freshly placed concrete; 2) the field density test results attained 
in the pavement; and 3)the texture of the RCC surface being produced.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.3   Mixture Uniformity Testing</TTL><BRK/>
<BRK/>
<TXT>Evaluation of mixture uniformity consists of 2 separate test series and each shall be performed to evaluate: 
1) the performance of the drum mixer and 2) the uniformity of the batching and mixing process.  Mixture uniformity 
testing shall be done prior to the production and placement of any RCC.  The RCC proportions used for testing 
shall be as that proposed for use on the project.  All mixture uniformity testing shall be performed in accordance 
with <RID>COE CRD-C 55</RID> as modified herein and paragraph CONTRACTOR QUALITY CONTROL.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.3.3.1   Mixer Performance Test</TTL><BRK/>
<BRK/>
<LST>a. Perform mixer performance tests when a reduced mixing time is proposed.  The test is performed on 
three separate samples representing each of the three thirds of a single full-production batch of concrete.  
For continuous mix plants, take samples during full plant production at 1 minute intervals.</LST><BRK/>
<BRK/>
<LST>b. Before uniformity data are available, the mixing time for each batch after all solid materials are 
in the mixer, and provided that all of the mixing water is introduced before one-fourth of the mixing 
time has elapsed, shall be at least 75 seconds.</LST><BRK/>
<BRK/>
<LST>c. The RCC shall meet the limits of the five mixer performance requirements listed in Table IX below.  
The testing shall consist of performing all five tests on a single batch of concrete.  The range for 
determining acceptability shall be the range of test results for each of the three samples representing 
the single batch.  If more than one mixer is used and all are identical in terms of make, type, capacity, 
condition, speed of rotation, etc., the results of tests on one of the mixers shall apply to the others, 
subject to the approval of the Contracting Officer.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.3.2   Process Uniformity Test</TTL><BRK/>
<BRK/>
<TXT>Process uniformity testing shall consist of performing all five tests on three separate batches of concrete.  
The range for determining acceptability shall be the range of test results for each of the three samples representing 
the three full-production batches.  For continuous mix plants, samples shall be taken at approximately 3 hour 
intervals during full plant production.</TXT><BRK/>
<TBL><BRK/>
<THD>         TABLE IX - UNIFORMITY REQUIREMENTS--STATIONARY MIXERS<BRK/>
<BRK/>
                           Process Uniformity Test     Mixer Performance Test<BRK/>
                                Allowable                     Allowable<BRK/>
                            Maximum Range for               Maximum Range<BRK/>
       Parameter           Average of 3 Batches             for 1 Batch</THD><BRK/>
<BRK/>
  Unit weight of            32 kg/cubic m                  24 kg/cubic m<BRK/>
  (Air-free) mortar         (2.0 lbs/cubic ft)             (1.5 lbs/cubic ft)<BRK/>
  Coarse aggregate          6.0 percent                    6.0 percent<BRK/>
  Compressive strength     10.0 percent                   10.0 percent<BRK/>
  at 7 days<BRK/>
  Water Content             1.5 percent                    1.0 percent<BRK/>
  Unit Weight of Concrete   24 kg/cubic m                 16 kg/cubic m<BRK/>
  (full mix including air)  (1.5 lbs/ft)                  (1.0 lbs/ft)</TBL><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.4   <SUB>PLACING AND SPREADING</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>3.4.1   Placing</TTL><BRK/>
<BRK/>
<LST>a. Timing.  Place mixture in accordance with the <SUB>Placement Schedule</SUB> and as nearly continuous as possible, 
with an absolute minimum of stops and starts; control speed of placing to permit proper rolling.  The 
timing of placement shall be controlled so that all RCC mixture shall be placed and rolled within the 
time limit specified in paragraph COMPACTION.  Except as specified below, for certain extremely small 
odd-shaped isolated areas, all concrete shall be placed and spread with the paver.</LST><BRK/>
<BRK/>
<LST>b. Charging.  The level of concrete in the paver hopper shall not be allowed to approach empty between 
loads, and concrete shall be maintained above the auger shaft during paving.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If the total pavement thickness is greater than 250 mm (10 inches), use 
the first statement in brackets regarding lift thickness; otherwise, the second 
statement should be used.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>c. Setup.  The paver shall be adjusted and the speed regulated to prevent segregation, meet the surface 
requirements, and of such depth that, when compacted, the surface will conform to cross section, grade, 
and contour indicated.  [No layer shall be in excess of<MET> 250 mm</MET><ENG> 10 inches</ENG> or less than<MET> 100 mm</MET><ENG> 4 inches</ENG>
 in compacted thickness.][The entire depth of pavement shall be placed as one layer.]</LST><BRK/>
<BRK/>
<LST>d. Edges.  Each edge of each lane shall be constructed with a sloped face of 15 degrees from vertical 
configuration, as directed.  The edge shoe shall be constructed so that it is within<MET> 19 mm</MET><ENG> 3/4 inch</ENG> of 
the compacted base surface.</LST><BRK/>
<BRK/>
<LST>e. Lanes.  Mixture shall be placed in consecutive adjacent lanes having a minimum width of<MET> 3 m</MET><ENG> 10 feet</ENG>
 and a maximum width of<MET>6 m</MET><ENG> 20 feet</ENG>.  A wider lane may be approved to prevent edge lanes less than<MET> 3 m</MET><ENG>
 10 feet</ENG> in width.  If more than 60 minutes should elapse between placements in adjacent lanes, the construction 
joint shall be considered a "cold joint" and treatment as specified herein for cold joints shall be provided.  
Not more than 60 minutes shall elapse between placement of lifts on multilift construction.  During extremely 
hot weather, both of these limits will be decreased by the Contracting Officer as specified in paragraph: 
Placing During Hot Weather or as otherwise considered appropriate.  Each lane placed before a succeeding 
lane shall be of such length that, where practical, the succeeding lane can be placed without the use 
of a cold joint.</LST><BRK/>
<BRK/>
<LST>f. Joints.  Pavers shall be used in sufficient numbers and operated in staggered formation to assist 
in achieving the above requirement and to produce multilane construction in one construction operation 
to minimize cold construction joints.  Otherwise, the joint shall be constructed as a cold joint.  In 
multilift construction, a separate paver shall be required for placement of each lift of pavement.  The 
length of a lane that is to be followed by another lane shall be approved and shall be decreased or increased 
as required by air temperatures, wind, and other climatic conditions existing at the time of placement.  
Longitudinal joints and edges shall be constructed to true line markings.  Lines parallel to the centerline 
of an area to be paved shall be established, and stringlines shall be placed coinciding with established 
lines for the spreading machine to follow.</LST><BRK/>
<BRK/>
<LST>g. Control of Water.  Placing shall be discontinued during rain except for light mists that do not cause 
intermixing of cement and water slurry on the surface.  Placing shall be done in a pattern so that curing 
water from previous placements will not pose a runoff problem on the fresh surface or base course.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2   Placing Adjacent Lanes</TTL><BRK/>
<BRK/>
<TXT>Fresh longitudinal construction joints between separate lanes of concrete pavement shall be completed within 
the time limitations in the paragraph PLACING AND SPREADING.  Other longitudinal joints shall be treated as "cold 
joints."  Joints shall be made to assure continuous bond between old and new sections of pavement.  Extra passes 
of the vibratory roller and other compaction and hand finishing shall be used as necessary to assure specified 
full depth compaction and surface finish.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.3   Special Requirements for Placing Lanes Succeeding Initial Lanes</TTL><BRK/>
<BRK/>
<TXT>For longitudinal construction joints the screed of the paver shall overlap the previously placed lane<MET> 25 to 50 
mm</MET><ENG> 1 to 2 inches</ENG> and shall be sufficiently high so that compaction will produce a smooth, dense joint, without 
offset.  The concrete placed on the edge of the previously placed lane by the paver shall be carefully pushed 
back by hand by using a lute to the edge of the lane being placed, so none will remain on the surface of the 
previously placed lane.  If necessary, when the quantity of concrete on the edge of the previously placed lane 
plus uncompacted material in the lane being placed exceeds that required to produce a smooth, dense joint, the 
excess concrete shall be removed by approved methods and wasted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.4   Handwork</TTL><BRK/>
<BRK/>
<TXT>Any paving operations that require significant handwork, other than as specified above, shall be stopped and 
the problems corrected before restarting.  Broadcasting or fanning of concrete mixture over areas being compacted 
will not be permitted.  When segregation occurs in the concrete during placement, the spreading operation shall 
be suspended until the cause is determined and corrected.  Segregated coarse aggregate shall be removed from 
the surface prior to compaction.  Irregularities in alignment of the pavement left by the mechanical spreader 
shall be corrected by hand trimming directly behind the spreader before rolling.  Distortion of pavement during 
edge trimming will not be permitted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.5   Placing Odd-Shaped Areas</TTL><BRK/>
<BRK/>
<TXT>In isolated instances involving very small, odd-shaped areas where use of machine spreading is impractical, concrete 
shall be spread by hand.  Spreading shall be in a manner to prevent segregation.  Mixture shall be spread uniformly 
with shovels in a loose layer of thickness that, when compacted, will conform to density, grade, thickness, and 
surface texture requirements.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.6   Placing During Cold Weather</TTL><BRK/>
<BRK/>
<TXT>Placement shall be discontinued when the air temperature reaches<MET> 5 degrees C</MET><ENG> 40 degrees F</ENG> and is falling and 
shall not be resumed until the air temperature reaches<MET> 2 degrees C</MET><ENG> 35 degrees F</ENG> and is rising.  No RCC shall 
be placed on any surface containing frost or frozen material.  Provision shall be made to protect the concrete 
from freezing during the specified curing period.  Mixing water and/or aggregates shall be heated, as necessary, 
to produce concrete having a temperature between<MET> 10 and 30 degrees C</MET><ENG> 50 and 85 degrees F</ENG> as placed.  Methods 
and equipment for heating shall be as approved.  The aggregates shall be free of ice, snow, and frozen lumps 
before entering the mixer.  Covering and other means shall be provided for maintaining the RCC at a temperature 
of at least<MET> 10 degrees C</MET><ENG> 50 degrees F</ENG> for not less than 72 hours after placing and at a temperature above freezing 
for the remainder of the curing period.  Concrete damaged by freezing shall be removed and replaced as directed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.7   Placing During Hot Weather</TTL><BRK/>
<BRK/>
<TXT>During periods of hot weather when the maximum daily air temperature is likely to exceed<MET> 30 degrees C</MET><ENG> 85 degrees 
F</ENG>, the following precautions shall be taken:</TXT><BRK/>
<BRK/>
<LST>a.  The maximum period between placing succeeding lifts or lanes shall be 45 minutes.</LST><BRK/>
<BRK/>
<LST>b.  The underlying material shall be sprinkled with water immediately before placing the concrete.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The maximum placing temperature at which concrete should be placed is 
dependent on the minimum temperatures that can occur in the region.  For simplicity 
3 regions have been established based on average ambient air temperatures (AAAT).  
When air temperatures during RCC placement in these regions exceeds 30 degrees 
C (85 degrees F), one of the following maximum concrete temperatures should 
be required:<BRK/>
<BRK/>
AAAT.&lt;40 degrees, concrete temperat. &lt;70 degrees F<BRK/>
AAAT &lt;50 degrees, concrete temperat. &lt;80 degrees F<BRK/>
AAAT &lt;60 degrees, concrete temperat. &lt;90 degrees F</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>c.  Place the concrete at the coolest temperature practicable, and the temperature of the concrete when 
placed shall not exceed [_____] degrees <MET>C</MET><ENG>F</ENG>.</LST><BRK/>
<BRK/>
<LST>d.  The finished surfaces of the newly laid pavement shall be kept damp by applying a waterfog or mist, 
not streams of water, with approved spraying equipment until the pavement is covered by the curing medium.</LST><BRK/>
<BRK/>
<TXT>When the Contracting Officer determines heat or wind  excessive, immediately take additional measures, as necessary, 
to protect the concrete surface.  Such measures shall consist of wind screens, more effective fog sprays, and 
similar measures commencing immediately behind the paver.  If these measures are not effective, paving operations 
shall be immediately stopped until satisfactory placement conditions exist.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5   COMPACTION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Do not, under any conditions, reduce the requirements for use of vibratory 
rollers operating in the vibratory mode or for use of electronic controls and 
stringlines or lasers.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Accomplish compaction by self-propelled, vibratory, steel-wheeled rollers and rubber-tired rollers.  Rollers 
shall not be operated in the vibratory mode when not moving.  The frequency and amplitude of vibration shall 
be varied, as needed or directed, within the range specified.  Surfaces of roller drums and wheels shall be kept 
clean at all times.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.5.1   Timing</TTL><BRK/>
<BRK/>
<TXT>Rolling shall begin within 10 minutes of spreading and, except for fresh joints, rolling shall be completed within 
45 minutes of start of mixing, except during hot or dry weather conditions.  In hot or dry weather, rolling shall 
begin within 5 minutes of spreading and, except for joints, rolling shall be completed within 30 minutes of start 
of mixing.  Delays in rolling freshly laid mixture will not be permitted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2   Initial Rolling</TTL><BRK/>
<BRK/>
<TXT>Initial rolling shall consist of a minimum of 4 complete vibratory passes of the vibratory roller.  In no case 
shall this requirement for vibratory rolling be relaxed.  Initial static passes may be necessary before the vibratory 
rolling to "set" the pavement surface before vibratory compaction is started.  A round trip over the same material 
shall count as 2 complete passes (i.e., from point A to point B and return to point A by the same route are 2 
complete passes).</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.3   Deficiency Evaluation</TTL><BRK/>
<BRK/>
<TXT>After initial vibratory rolling, preliminary tests and examination of density, crown, grade, smoothness, and 
surface texture shall be made under the supervision of the Contracting Officer.  Before rolling is continued, 
deficiencies shall be corrected so that the finished surface will conform to requirements for grade, surface 
texture, and smoothness specified herein.  Further smoothness checks shall be as directed by the Contracting 
Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.4   Vibratory Rolling and Testing</TTL><BRK/>
<BRK/>
<TXT>Rolling shall be continued with the vibratory roller in vibratory mode, if necessary, until the specified wet 
field density as a percentage of the "Target Density," maximum wet density is attained in the lane interior, 
at fresh joints, and at cold joint.  Nuclear density testing shall be performed in accordance with paragraph 
CONTRACTOR QUALITY CONTROL.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.5   Final Rolling</TTL><BRK/>
<BRK/>
<TXT>Once at least 4 passes of the vibratory roller, operating in the vibratory mode, have been made and the specified 
density is attained, rolling with the steel wheeled vibratory roller shall stop.  Vibratory rolling beyond that 
specified above will not be permitted.  All additional rolling beyond 4 vibratory passes required to produce 
the specified field density shall be at the Contractor's expense.  As soon as rolling with the vibratory roller 
is complete, the pavement surface shall receive at least 2 complete passes of the rubber-tired roller with tire 
pressure and loading per wheel at the midpoint of the range previously specified, unless otherwise directed.  
These passes shall be followed by 2 complete passes of the finish roller.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.6   Operation of Rollers and Tampers</TTL><BRK/>
<BRK/>
<TXT>Speed of rollers shall be slow enough at all times to avoid displacement of the concrete but not more than<MET> 2.5 
km/hr</MET><ENG> 1.5 mph</ENG>.  Displacement of concrete resulting from reversing direction of roller or from any other cause 
shall be immediately corrected.  Alternate passes of roller shall be varied slightly in length and shall overlap 
sufficiently to provide full coverage over the surface.  Additional rollers shall be furnished if pavement density 
specified is not attained and/or if paving operations are getting ahead of rolling.  Paving operations shall 
not be altered to accommodate a lack of rollers.  Places inaccessible to large vibratory rollers shall be thoroughly 
compacted with walk-behind rollers and hand-tampers to the required density, using multiple thin lifts, as necessary.  
Additional field density tests shall be made for those areas by the Contractor and may also be made by the Government.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.7   Rolling Pattern</TTL><BRK/>
<BRK/>
<LST>a.  Rolling shall commence at the outer edge of the lane, followed by the other edge, and then the center.  
On subsequent adjacent lanes, rolling shall begin at the outer edge.  The first pass along each edge 
shall extend to within approximately<MET> 450 mm</MET><ENG> 18 inches</ENG> of the edge except as otherwise approved or directed.</LST><BRK/>
<BRK/>
<LST>b.  If there will be a subsequent lane placed along an edge and the joint will be constructed as a "fresh" 
joint, the roller shall go no closer to the outer edge until the subsequent lane is placed.</LST><BRK/>
<BRK/>
<LST>c.  If there will be a subsequent lane and the joint will be treated as a "cold" construction joint, 
or if the edge will be the final edge of the pavement, the outer<MET> 450 mm</MET><ENG> 18 inches</ENG> shall be rolled after 
rolling of the center of the lane.</LST><BRK/>
<BRK/>
<LST>d.  If the edge abuts a previously placed strip, either as a "fresh" joint or as a "cold" joint, the 
uncompacted joint area shall be rolled after the center of the lane.  This joint area shall be given 
additional passes of the vibratory roller and rubber-tired roller, as necessary, to produce the specified 
compaction in the joint area.</LST><BRK/>
<BRK/>
<LST>e.  Approved hand-finishing operations shall be used as necessary to produce a tight surface at the joint, 
meeting the specified surface tolerances in Table III.  The rolling pattern shall be used consistently 
throughout production.</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.6   <SUB>JOINTS</SUB></TTL><BRK/>
<BRK/>
<TXT>Joints shall conform to the details indicated and shall be perpendicular to the finished grade of the pavement.  
The joint area is considered the RCC material within 12 inches of the joint.  Joints shall:</TXT><BRK/>
<BRK/>
<LST>a.  Be straight and continuous from edge to edge of the pavement.</LST><BRK/>
<BRK/>
<LST>b.  Be made to ensure continuity in smoothness and grade between old and new sections of pavement, as 
specified hereinafter.</LST><BRK/>
<BRK/>
<LST>c.  Have the same texture, full-depth density, and smoothness as specified for other sections of pavement 
or as specified for joints.</LST><BRK/>
<BRK/>
<LST>d.  Be cleaned by brushing or cut back with approved power saw, as directed, regardless of age, contact 
surfaces of previously constructed strips that have become coated with dust, sand, or other objectionable 
material.</LST><BRK/>
<BRK/>
<SPT><TTL>3.6.1   Longitudinal Construction Joints</TTL><BRK/>
<BRK/>
<TXT>Any construction joints in which the density fails to meet the specified limits shall be trimmed by sawing the 
edge of the hardened concrete with a power concrete saw, not earlier than 12 hours age.</TXT><BRK/>
<BRK/>
<LST>a.  The sawcut shall be at least<MET> 150 mm</MET><ENG> 6 inches</ENG> from the original edge, and more if necessary to produce 
an acceptable joint.</LST><BRK/>
<BRK/>
<LST>b.  The sawcut shall be full depth of the pavement and shall produce a face within 15 degrees of vertical, 
free of all loose or uncompacted material.</LST><BRK/>
<BRK/>
<LST>c.  The outer portion shall be removed carefully to prevent any damage to the sawed face.  If damage 
occurs, the edge shall be resawed.</LST><BRK/>
<BRK/>
<LST>d.  If necessary, additional rolling shall be used to assure that full depth density and surface texture 
is attained.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.2   Transverse Construction Joints</TTL><BRK/>
<BRK/>
<LST>a.  When a transverse construction joint is required, the roller shall pass over the end of the freshly 
placed concrete.</LST><BRK/>
<BRK/>
<LST>b.  The tapered end of the strip and adjacent unacceptable material shall be cut with a power concrete 
saw to full depth of the lift, as specified above, and the excess material removed.</LST><BRK/>
<BRK/>
<LST>c.  In continuing placement of the strip, the paver shall be positioned on the transverse joint so that 
sufficient fresh concrete will be spread to obtain a joint, after rolling, which will conform to required 
full-depth density and smoothness specified.  When necessary, the fresh mixture shall be hand finished 
at the joints.  Additional rolling shall be used to assure that specified full-depth density and surface 
finish is attained.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.3   Joints in Multilift Construction</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete this paragraph if only one course construction is to be used in 
the project.  Delete bracketed statement if all lift joints are to receive bedding 
mortar.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  The top layer shall be placed so that longitudinal joints in that layer will coincide with joints 
in the lower layers of the pavement.</LST> <BRK/>
<BRK/>
<LST>b.  Transverse joints in the top layer shall coincide with transverse joints in the lower layers of the 
pavement.</LST><BRK/>
<BRK/>
<LST>c.  All portions of the lower layer that are to be covered by the upper layer shall be covered with a 
bedding mortar layer<MET> 6 to 10 mm</MET><ENG> 1/4 to 3/8 inch</ENG> thick immediately before placing the upper layer[ if 
the time between successive layers exceeds 30 minutes].</LST><BRK/>
<BRK/>
<LST>d.  Bedding mortar shall be a mixture of cement, fine aggregate and water of the proportions directed 
and shall be spread evenly over the lower layer.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.4   Slip Joints</TTL><BRK/>
<BRK/>
<TXT>Slip joints shall be constructed between roller-compacted and conventional concrete where no expansion joint 
is required and as shown on the contract drawings.  The edge of the initial placement, either RCC or PCC, shall 
be coated with a bituminous product a minimum of<MET> 3 mm</MET><ENG> 1/8 inch</ENG> thick prior to placing the next material.  If 
RCC is placed prior to conventional concrete, the RCC shall be sawcut full depth at the joint line and excess 
RCC removed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.5   Sawing of Contraction Joints</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Sawing of transverse contraction joints is recommended because of appearance 
and ease of sealing.  However, in the past much RCC pavement has been allowed 
to crack naturally without benefit of sawing.  These natural cracks normally 
occur at 12 to 20 m (40 to 70 ft) spacing.  Delete this paragraph if sawed joints 
are not being used and modify paragraph Sealing Joints and Cracks accordingly.  
The bracketed statement should be included if longitudinal construction joints 
are to be sawed and sealed.  In the past, longitudinal construction joints have 
had no treatment except for routing and sealing if they open up to form a crack 
3 mm (1/8 inch) or more in width.  In general this has been a satisfactory approach.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  Transverse contraction joints shall be sawed at<MET> 12 m</MET><ENG> 40 ft</ENG> spacing or as otherwise indicated.  [Longitudinal 
construction joints between lanes shall be sawed to form a reservoir for joint sealant in the same manner 
as specified above.]</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Very early age sawing is commonly done for conventional concrete pavements.  
It is also appropriate for RCC pavements where sawn joints is desired.  Specialized 
equipment is necessary for sawcutting to be done at very early ages so that 
damage to the joint and pavement is prevented.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>b.  Timing for Sawing.  Initial joint sawing shall be accomplished where indicated by using a<MET> 3 mm</MET><ENG> 1/8 
inch</ENG> blade to the depth indicated.  The time of sawing shall vary depending on existing and anticipated 
weather conditions and shall be such as to prevent uncontrolled cracking of the pavement.  Sawing of 
the joints shall commence as soon as the concrete has hardened sufficiently to permit sawing the concrete 
without chipping, spalling, or tearing.  The sawing operation shall be carried on, as required, during 
both day and night regardless of weather conditions.  Water-curing, if required, shall be discontinued 
only in small areas to facilitate sawing.</LST><BRK/>
<BRK/>
<LST>c.  Cracking.  Before sawing a joint, the concrete shall be examined closely for cracks, and the joint 
shall not be sawed if a crack has occurred within<MET> 3 m</MET><ENG> 10 feet</ENG> from the planned joint location.  Sawing 
shall be discontinued when a crack develops ahead of the saw cut.</LST><BRK/>
<BRK/>
<LST>d.  Spacing and Alignment.  The joints shall be sawed at the required spacing consecutively in the sequence 
of the concrete placement.  A chalkline or other suitable guide shall be used to mark the alignment of 
the joint.  The saw cut shall not vary more than<MET> 13 mm</MET><ENG> 1/2 inch</ENG> from the true joint alignment from edge 
to edge of the pavement area, and shall have no abrupt offsets.</LST><BRK/>
<BRK/>
<LST>e.  Undercutting.  The sawed faces of joints will be inspected for undercutting or washing of the concrete 
due to the early sawing, and sawing shall be delayed if undercutting is sufficiently deep to cause structural 
weakness or excessive roughness in the joint.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Installation of the final joint seal or sealant, if required, should 
be done after completion of the curing period.  To minimize costs, it is always 
preferable that the sealing subcontractor be able to install all the seals or 
sealant at one time rather than to mobilize several times.  Sealing as soon 
as practical is desirable so that continued construction operations don't damage 
or contaminate joints.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>f.  Joint Widening.  After expiration of the curing period and no later than [_____] days, the upper 
portion of the groove shall be widened by sawing to the width and depth indicated to form a reservoir 
for the joint sealer.</LST><BRK/>
<BRK/>
<LST>g.  Cleaning Joint.  Immediately after initial and final sawing of the joint, the saw cut and adjacent 
concrete surface shall be thoroughly flushed with water until all waste from sawing is removed from the 
joint.</LST><BRK/>
<BRK/>
<LST>h.  Equipment.  The sawing equipment shall be adequate in the number of units and the power to complete 
the sawing at the required rate.  An ample supply of saw blades shall be available on the job before 
concrete placement is started, and at least one standby sawing unit in good working order shall be available 
at the jobsite at all times during the sawing operation.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.6   Routing Cracks</TTL><BRK/>
<BRK/>
<TXT>Thirty to 45 days after placement of concrete, all cracks which have been opened to<MET> 3 mm</MET><ENG> 1/8 inch</ENG> or more shall 
be routed to the dimensions shown.  Routing shall be done minimizing spalling, using a vertical spindle type 
rotary router mounted on a rigid chassis so that the spindle will caster.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.7   Sealing Joints and Cracks</TTL><BRK/>
<BRK/>
<TXT>Joints and cracks shall be sealed immediately following routing of cracks or sawing of joint reservoir or as 
soon thereafter as weather conditions permit.  Joints and cracks shall be sealed as specified in Section 
<SRF>32 01 19</SRF> FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.7   CURING AND PROTECTION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Curing of RCC surfaces is difficult.  It is not practical to moist cure 
surfaces where water runoff may effect adjacent construction operations.  In 
most cases it is preferable that RCC surfaces be cured by a membrane curing 
compound.  The relatively rough surface texture of RCC would requires a high 
dosage of curing compound (often double) to minimize voids in the membrane.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.7.1   General</TTL><BRK/>
<BRK/>
<LST>a.  Concrete shall be continuously protected against loss of moisture and rapid temperature changes for 
at least 7 days from the completion of finishing operations.  All equipment needed for adequate curing 
and protection of the concrete shall be on hand and ready for use before actual concrete placement begins.  
If any selected method of curing does not afford the proper curing and protection against concrete cracking, 
the damaged pavement shall be removed and replaced, and another method of curing shall be employed as 
directed.</LST><BRK/>
<BRK/>
<LST>b.  Calibrate the spraying system in accordance with <RID>ASTM D 2995</RID>, Method A, for the rate of application 
required in paragraph: Membrane Curing.  Any hand-operated sprayers allowed by paragraph: Membrane Curing 
shall be compressed air supplied by a mechanical air compressor.  If the curing equipment fails to apply 
an even coating of compound at the specified rate, it shall immediately be replaced.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.2   Membrane Curing</TTL><BRK/>
<BRK/>
<LST>a.  Timing.  A uniform coating of white-pigmented, membrane-forming, curing compound shall be applied 
to the entire exposed surface of the concrete and the edge surfaces as soon as the free water has disappeared 
from the surface.  Concrete shall not be allowed to dry before the application of the membrane.  If any 
drying has occurred, the surface of the concrete shall be moistened with a fine spray of water, and the 
curing compound applied as soon as the free water disappears.</LST><BRK/>
<BRK/>
<LST>b.  Coverage.  The curing compound shall be applied to the finished surfaces by means of an approved 
automatic self-propelled spraying machine.  The curing compound shall be applied with an overlapping 
coverage that will give two-coat application coverage of<MET> 93 square m/L</MET><ENG> 400 square feet/gallon</ENG> per coat, 
plus or minus 5.0 percent for each coat.  A one-coat application may be applied provided a uniform overlapping 
application and coverage of<MET> 47 squarem/L</MET><ENG> 200 square feet/gallon</ENG>, plus or minus 5.0 percent is obtained.</LST><BRK/>
<BRK/>
<LST>c.  Manual Application.  The application of curing compound by hand-operated, mechanical powered pressure 
sprayers will be permitted only on odd widths or shapes of slabs and on concrete surfaces exposed by 
the removal of forms.  When the application is made by hand-operated sprayers, a second coat shall be 
applied in a direction approximately at right angles to the direction of the first coat.  If pinholes, 
abrasions, or other discontinuities exist, an additional coat shall be applied to the affected areas 
within 30 minutes.</LST><BRK/>
<BRK/>
<LST>d.  Protection.  Concrete surfaces to which membrane-curing compounds have been applied shall be adequately 
protected during the entire curing period from pedestrian and vehicular traffic, except as required for 
joint-sawing operations and surface tests, and from any other possible damage to the continuity of the 
membrane.</LST><BRK/>
<BRK/>
<LST>e.  Membrane Damage.  Concrete surfaces that are subjected to heavy rainfall within 3 hours after the 
curing compound has been applied shall be resprayed by the method and at the coverage specified above.  
Areas where the curing compound is damaged by subsequent construction operations within the curing period 
shall be immediately resprayed.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.3   Burlap</TTL><BRK/>
<BRK/>
<TXT>Burlap covers shall consist of 2 or more layers of burlap having a combined weight of<MET> 4746 gm or more/sq m</MET><ENG> 14 
ounces or more/square yard</ENG> in a dry condition.  Burlap shall be either new or shall have been used only for curing 
concrete.  Burlap strips shall have a length after shrinkage of at least<MET> 305 mm</MET><ENG> 1 foot</ENG> greater than necessary 
to cover the entire width and edges of the pavement.  Mats shall overlap each other at least<MET> 150 mm</MET><ENG> 6 inches</ENG>.  
Mats shall be thoroughly wetted before placing and shall be kept continuously wet and in intimate contact with 
the surface and edges of the pavement area for the entire curing period.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7.4   Protection of Pavement</TTL><BRK/>
<BRK/>
<TXT>After final rolling of the pavement, no vehicular traffic, except for approved curing equipment having wheel 
loads not exceeding<MET> 2000 kg</MET><ENG> 4,500 pounds</ENG>, shall be permitted on the RCC pavement until the end of the curing 
period.  No traffic or equipment shall be allowed on the surface that will cause any damage to the surface.  
Plastic sheeting meeting the requirements of <RID>ASTM C 171</RID> shall be provided and kept readily available to cover 
pavement less than 12 hours old if rainfall occurs.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.8   TREATMENT OF DEFECTIVE PAVEMENT</TTL><BRK/>
<BRK/>
<TXT>Defective pavements shall be removed and replaced unless the deficiency is subject to payment adjustments.  RCC 
mixtures that are improperly proportioned or become contaminated are considered defective and shall be removed.  
Skin patching of an area that has been rolled will not be permitted.  No additional payment will be made for 
the repair or removal and replacement of defective pavement.  Except as noted below, the following defects will 
require complete removal and replacement[ or pay adjustment.  A defect greater than allowed for pay adjustment 
shall be removed and replaced].</TXT><BRK/>
<BRK/>
<LST>a.  Reduced thickness of pavement.</LST><BRK/>
<LST>b.  Surface texture.</LST><BRK/>
<LST>c.  Smoothness.</LST><BRK/>
<LST>d.  Density.</LST><BRK/>
<LST>e.  Horizontal Alignment.</LST><BRK/>
<BRK/>
<SPT><TTL>3.8.1   Pavement Removal and Replacement</TTL><BRK/>
<BRK/>
<TXT>Defective areas to be replaced shall be delineated by sawing full depth of the pavement around the perimeter 
of the defective area.  The delineated area shall be removed for the full pavement depth of the course without 
damaging the adjacent pavement.  Delineated areas shall have a length or width no less than<MET> 3 m</MET><ENG> 10 feet</ENG>, and 
no adjacent slab or portion of a slab that remains in the pavement abutting the replacement area shall have a 
length or width less than<MET> 2.5 m</MET><ENG> 8 feet</ENG> when measured from a joint or edge.  The edge of the existing concrete 
shall form a clean, vertical face to pave against.  Conventional concrete or RCC may be used at the Contractor's 
option to fill the void.  The new slab shall conform to all requirements of smoothness, surface texture, density, 
thickness, and concrete quality, as stated herein.  Longitudinal and transverse joints shall be established in 
the new slab in accordance with the original plans and shall be sealed, if required for the adjacent slab.</TXT><BRK/>
<BRK/></SPT>
[<SPT><TTL>3.8.2   Cracks in Pavement</TTL><BRK/>
<BRK/>
<TXT>Joint sawcutting shall be modified to prevent the repeated occurence of cracks.  Pavement sections shall be removed 
and replaced when cracks exceed [_____]<MET> mm</MET><ENG> inch</ENG> in width or when spaced closer than [_____]<MET> m</MET><ENG> feet</ENG>.[  Cracks 
determined to be repairable shall be repaired as specified.]</TXT><BRK/>
<BRK/></SPT>
]<SPT><TTL>3.8.3   Mix Proportion Variations</TTL><BRK/>
<BRK/>
<TXT>Variation in aggregate grading of pavement shall be subject to pay adjustment.  Grading variations greater than 
allowed for pay adjustment shall be removed and replaced.  Pavement sections shall be removed and replaced for 
variations in other mixture constituents beyond the specified tolerances.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.4   Voids</TTL><BRK/>
<BRK/>
<TXT>Holes the full thickness of course shall be cut so that the sides are perpendicular and parallel to the jointing 
pattern and the edges are vertical.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.5   Grade Variations</TTL><BRK/>
<BRK/>
<TXT>High spots indicated by the testing edge in excess of applicable tolerance shall be marked plainly and removed 
or reduced by rubbing with a Carborundum brick and water.  Rubbing shall be discontinued as soon as contact with 
the coarse aggregate is made.  If high spots cannot be removed in the above manner because of disturbing the 
coarse aggregate, the high portion of the pavement shall be corrected by an approved surface-grinding machine 
after the RCC is 14 days old or the defective pavement shall be removed and replaced.  When grinding of<MET> 13 mm</MET><ENG>
 1/2 inch</ENG> or more would be required, the pavement shall be removed and replaced.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.9   <SUB>CONTRACTOR QUALITY CONTROL</SUB></TTL><BRK/>
<BRK/>
<TXT>The Contractor is responsible for sampling and testing aggregates, cementitious materials, and RCC to determine 
compliance with the specifications.  Provide facilities and labor as may be necessary for procurement of representative 
test samples.  Furnish sampling platforms and belt templates to obtain representative samples of aggregates from 
charging belts at the concrete plant.  Obtain samples of RCC at the point of delivery to the paver.  Perform 
the inspection and tests described below, and based upon the results of these inspections and tests, take the 
action required and submit reports as required.  Perform this testing regardless of any other testing performed 
by the Government, [either for pay adjustment purposes or for any other reason].</TXT><BRK/>
<BRK/>
<SPT><TTL>3.9.1   Contractor Quality Control Staff</TTL><BRK/>
<BRK/>
<TXT>All Contractor Quality Control personnel assigned to concrete construction shall be American Concrete Institute 
(ACI) certified in the following grade (or shall have written evidence acceptable to the Contracting Officer 
of having completed similar qualification programs):</TXT><BRK/>
<BRK/>
<LST>a.  CQC personnel responsible for inspection of concrete paving operations: ACI Concrete Transportation 
Inspector.</LST><BRK/>
<BRK/>
<LST>b.  Field Testing Technicians: ACI Concrete Field Testing Technician, Grade I.</LST><BRK/>
<BRK/>
<LST>c.  Laboratory Testing Technicians: ACI Concrete Strength Testing Technician and Laboratory Testing Technician, 
Grade I or II.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.2   Laboratory Accreditation</TTL><BRK/>
<BRK/>
<TXT>Laboratory and testing facilities shall be provided by and at the expense of the Contractor.  The laboratories 
performing the tests shall be accredited in accordance with <RID>ASTM C 1077</RID>, including <RID>ASTM C 78</RID> and <RID>ASTM C 1260</RID>.  
The accreditation shall be current and shall include the required and optional test methods, as specified throughout 
this Section.</TXT><BRK/>
<BRK/>
<LST>a.  Aggregate Testing and Mix Proportioning:  Aggregate testing and mixture proportioning studies shall 
be performed by a commercial laboratory.</LST><BRK/>
<BRK/>
<LST>b.  Contractor Quality Control:  All sampling and testing shall be performed by an approved, onsite, 
independent, commercial laboratory, or for cementitious materials and admixtures, the manufacturer's 
laboratory.</LST><BRK/>
<BRK/>
<LST>c.  Laboratory Inspection:  The Government will inspect the laboratory equipment and test procedures 
prior to the start of concreting operations for conformance to <RID>ASTM C 1077</RID>.  The laboratory shall maintain 
these certifications for the duration of the project.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.3   Reports</TTL><BRK/>
<BRK/>
<TXT>All results of tests conducted at the project site shall be reported on the same day tested and shall be delivered 
to the Contracting Officer.  These requirements do not relieve the Contractor of the obligation to report certain 
failures immediately as required in preceding paragraphs.  Such reports of failure and the action taken shall 
be confirmed in writing in the routine reports.  The Contracting Officer has the right to examine all Contractor 
quality control records at any time.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.4   Lots and Sublots</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The lot size can be specified on the basis of time (i.e., 4 hours, 1 
shift, etc.) or amount of production (i.e, 500 cu m (665 cu yd), 1000 cu m (1333 
cu yd), etc.).  If the lot size is based on the amount of production, it normally 
should be selected to be approximately equal to the amount of RCC expected to 
be produced in 1 shift of operation.  The lot size should not exceed 1500 cu 
m (2000 cu yd) of RCC.  When a lump sum contract is used, the lot size becomes 
the total job; thus, the percent payment is applied to the contract price.  
The following paragraphs will be edited accordingly.<BRK/>
<BRK/>
Delete this paragraph if the project is small or control based on lots is not 
appropriate.  Revise QC table where lots and sublots are identified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Areas to be tested[ and quantities for which payment is to be adjusted] will be based on pavement areas subdivided 
into lots and lots subdivided into sublots.  A lot will be that quantity of construction that will be evaluated 
for compliance with specification requirements.  A lot will be equal to [<MET>[375][_____] cu m</MET><ENG> [500][_____] cu yd</ENG>
] [[8][_____] hours production] [1 shift production].  Sublots are designated and defined for the specific parameter 
to be tested.  Thickness, surface smoothness, and surface texture determinations will be made on the lot as a 
whole.  In order to evaluate field density, each lot will be divided into 4 equal sublots.  All samples and test 
locations will be selected randomly, using commonly recognized methods of assuring randomness conforming to <RID>ASTM D 3665</RID>
 and employing tables of random numbers or computer programs.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.5   Additional Sampling and Testing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Add bid items for requirements that may need additional testing.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The Contracting Officer will request additional samples and tests for any area that appears to deviate from the 
specification requirements.  The Contractor will pay for the cost of any additional testing if tests verify deficient 
material.  If tests verify that materials conform to the specifications, payment will be made under the appropriate 
bid item.  Testing in these areas will be in addition to the lot testing, and the requirements for these areas 
will be the same as those for a lot.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.6   Testing and Evaluation</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  In Table X modify testing items and frequency of testing to fit project 
specific conditions.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Based upon the results of these tests, take the action and submit reports as required in Table X, and any additional 
tests to ensure that the requirements of these specifications are met.</TXT><BRK/>
<TBL><BRK/>
<THD>TABLE X - CONTRACTOR TESTING AND INSPECTION REQUIREMENTS<BRK/>
<BRK/>
Frequency      Test Method           Control Limit/Corrective Action </THD><BRK/>
<BRK/>
CEMENTITIOUS MATERIALS SAMPLING<BRK/>
1 Sample         none               2.2 kg (5 lb) samples to be collected,<BRK/>
per 500 tons                        labeled, stored and delivered to the <BRK/>
                                    CO after completion of the project.<BRK/>
<BRK/>
FINE AGGREGATE GRADATION AND FINENESS MODULUS<BRK/>
1 500 tons   <RID>ASTM C 136</RID>  Outside limits on any sieve: retest<BRK/>
of aggregate  Sample at stock-      2nd failure: stop, repair, retest<BRK/>
during        pile.                 <BRK/>
production<BRK/>
<BRK/>
1 per sublot <RID>ASTM C 136</RID>  Outside limits on any sieve: retest<BRK/>
during RCC    Sample at discharge   2nd failure: stop, repair, retest<BRK/>
placement     belt from plant<BRK/>
<BRK/>
COARSE AGGREGATE GRADATION<BRK/>
1 500 tons   <RID>ASTM C 136</RID>  Outside limits on any sieve: retest<BRK/>
of aggregate  Sample at stock-      2nd failure: stop, repair, retest<BRK/>
during        pile.<BRK/>
production<BRK/>
<BRK/>
1 per sublot <RID>ASTM C 136</RID>  Outside limits on any sieve: retest<BRK/>
during RCC    Sample at discharge   2nd failure: stop, repair, retest<BRK/>
placement     belt from plant<BRK/>
<BRK/>
AGGREGATE DELETERIOUS MATERIALS<BRK/>
Initially    See paragraph:         Stop production, retest, replace<BRK/>
and when     AGGREGATES             aggregate. 2nd faikure: stop, evaluate<BRK/>
visual                              problem, notify CO for corrective action<BRK/>
change<BRK/>
<BRK/>
AGGREGATE MOISTURE<BRK/>
Daily        <RID>ASTM C 566</RID>  Adjust plant settings accordingly<BRK/>
<BRK/>
PLANT - SCALES, WEIGHING ACCURACY<BRK/>
Initially  <RID>NRMCA CPMB 100</RID> Stop plant operations, repair, recalibrate<BRK/>
then                                 standard test weights accurate to plus <BRK/>
monthly                              or minus 0.1% and provide for checking <BRK/>
                                     plant scales<BRK/>
<BRK/>
PLANT - CALIBRATION OF BATCHING AND RECORDING EQUIPMENT<BRK/>
Initially    Record/Report          Record required/recorded/actual batch <BRK/>
then every                          mass,. Stop plant operations, repair<BRK/>
10 shifts                           recalibrate. See paragraph 3.11.1<BRK/>
<BRK/>
PLANT - RECORD OF BATCH PLANT CONTROLS<BRK/>
Every lot    Record/Report          Record type/amt of each material per lot<BRK/>
<BRK/>
PLANT - MIXTURE UNIFORMITY - STATIONARY MIXER<BRK/>
Every 4  <RID>COE CRD-C 55</RID> After initial approval, use abbreviated<BRK/>
months       as modified            method. Increase mixing time, change<BRK/>
during                              batching sequence, reduce batch size to<BRK/>
paving                              bring into compliance. Retest<BRK/>
<BRK/>
NUCLEAR DENSITY GAGE RCC CALIBRATION<BRK/>
Daily        Test block             Calculate calibration factor for placing<BRK/>
                                    period. Report change of more than 5% of<BRK/>
                                    previous value to CO and initiate gage<BRK/>
                                    evaluation<BRK/>
<BRK/>
RCC MOISTURE DENSITY RELATIONSHIP<BRK/>
Start of     <RID>ASTM D 1557</RID>  See paragraph 3.9.8<BRK/>
each lot      Sample taken at        <BRK/>
              plant discharge<BRK/>
<BRK/>
FIELD DENSITY AND FIELD MOISTURE<BRK/>
Per 100 ft   <RID>ASTM C 1040/C 1040M</RID>, See paragraph 3.9.8<BRK/>
of paving     method A and <BRK/>
lane and 100 <RID>ASTM D 6938</RID><BRK/>
of joint      at the placement within<BRK/>
              30 minutes of mixing RCC<BRK/>
<BRK/>
CONCRETE MIXTURE - TEMPERATURE<BRK/>
When test    <RID>ASTM C 1064/C 1064M</RID>  See par. 3.4<BRK/>
specimens     Sample at paving site<BRK/>
prepared<BRK/>
<BRK/>
CONCRETE MIXTURE - STRENGTH<BRK/>
8 per lot    <RID>ASTM C 31/C 31M</RID> See par. CONCRETE STRENGTH<BRK/>
              Sample at paving site     See par. 3.9.9<BRK/>
<BRK/>
SURFACE SMOOTHNESS<BRK/>
Continuous                          Exceed tolerances: notify CO and modify<BRK/>
and within 1 hour                   operation.<BRK/>
of placement                        See paragraph 3.10.4<BRK/>
<BRK/>
PAVEMENT TEXTURE<BRK/>
1 core per   3 point direct         See paragraph 3.10.6<BRK/>
sublot       measurement            <BRK/>
<BRK/>
PAVEMENT THICKNESS<BRK/>
1 core per   3 point direct         See paragraph 3.10.5<BRK/>
sublot       measurement<BRK/>
<BRK/>
PAVING - INSPECTION BEFORE PAVING<BRK/>
Prior to     Report                 Inspect underlying material, construction<BRK/>
each paving                         joint faces, forms, reinforcing, dowels,<BRK/>
operation                           and embedded items<BRK/>
<BRK/>
PAVING - INSPECTION DURING PAVING<BRK/>
During each                         Monitor and control paving operation,<BRK/>
paving                              including placement, consolidation, <BRK/>
operation                           finishing, texturing, curing, and joint<BRK/>
                                    sawing.  See paragraph 3.9.13<BRK/>
<BRK/>
PAVING - ROLLER VIBRATION<BRK/>
Weekly,      Vibration meter        Test frequency and amplitude of each <BRK/>
during                              roller. Repair or replace defective <BRK/>
paving                              rollers<BRK/>
<BRK/>
MEMBRANE COMPOUND CURING<BRK/>
Daily        Visual                 Compute coverage based on quantity/area.<BRK/>
                                    Re-spray areas with defective coverage <BRK/>
                                    Re-calibrate equipment<BRK/>
<BRK/>
INSPECTION OF HOT WEATHER MEASURES<BRK/>
Once per     Visual                 Repair defects, report conditions to CO<BRK/>
<BRK/>
INSPECTION OF COLD WEATHER PROTECTION<BRK/>
Once per     Visual                 Repair defects, report conditions to CO</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.7   Calibration of Mixing Plant</TTL><BRK/>
<BRK/>
<TXT>The accuracy of proportioning for continuous plants shall be checked by simultaneously securing timed samples 
of the cementitious materials and the combined aggregate as they are fed to the mixer and weighing each as appropriate.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.8   Field Density Testing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For record, nuclear density gauge readings of moisture content and density 
should be taken at 50 mm (2 inch) intervals to the thickness of the pavement 
minus 50 mm (2 inches), although the deepest reading only will be the basis 
for acceptance.  The deepest readings of the nuclear density gauges of the Contractor 
and Government should be checked for agreement.  The deepest reading should 
be approximately 50 mm (2 inches) less than the depth of the pavement slab.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a. Furnish one operable and properly calibrated single probe nuclear density gauge for each paver.  Submit 
a copy of the State license authorizing the use of a nuclear gage, and manufacturer certification that 
operators have completed an approved safety and gage operation training session.  For each gage to be 
used on site, provide the date of calibration, the calibrating organization, list of calibration standards, 
and the calibration curve.  The submittal shall include a description of the nuclear density gauge apparatus 
proposed for use, the manufacturer's literature and the latest manufacturer's calibration results of 
the nuclear density gauge.</LST><BRK/>
<BRK/>
<LST>b. The maximum wet density or "target density" shall be determined by <RID>ASTM D 1557</RID> using a<MET> 150 mm</MET><ENG> 6-inch</ENG>
 mold.</LST><BRK/>
<BRK/>
<LST>c. The test shall be performed using a single probe nuclear density gauge operating in the direct transmission 
mode so density of the full depth of the pavement can be measured.  Each test shall include readings 
at depths of [_____], [_____] and [_____]<MET> mm</MET><ENG> inches</ENG>; however, only the deepest reading shall be used 
to evaluate the density.  Both wet and dry densities shall be reported, and all individual readings shall 
be reported.  The moisture content shall be determined at the same depths.  The wet field density shall 
also be reported as a percentage of the "Target Density," maximum laboratory wet density as determined 
for that lot.  All holes left in the concrete as a result of nuclear density testing shall be filled 
with a cement grout.</LST><BRK/>
<BRK/>
<LST>d. Additional tests shall be made as directed, particularly during start-up and when problems with attaining 
required density occur.  The nuclear density gauge shall be made available for Government use upon request.</LST><BRK/>
<BRK/>
<LST>e. See Appendix A, at the end of this Section for sample density computations.  If any nuclear density 
gauge reading is below 97.8 percent for interior or fresh joint or below 95.8 percent for a cold joint, 
another test shall be performed within a<MET> 1.5 to 2.4 m</MET><ENG> 5 to 8 foot</ENG> radius of the previous testing location.  
If this adjacent reading is also below the density requirements, the Contracting Officer shall be notified 
immediately, and additional vibratory roller passes shall be made across the full lane width between 
the last testing location that produced an acceptable reading and the paver.  If additional vibratory 
roller passes cause the density to decrease or cause the surface texture and appearance to deteriorate 
in the opinion of the Contracting Officer, the paving operation shall be discontinued until appropriate 
adjustments are made to the moisture content of the mixture, to the operation of the paver, to rolling 
procedures, or other operations to assure that the specified density and surface requirements can be 
achieved.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.9   Concrete Strength</TTL><BRK/>
<BRK/>
<TXT>Contractor Quality Control operations for concrete strength shall consist of the following steps:  [Note:  two 
methods specified: a) cylinders/beams correlated during mix design and only cylinders cast during production, 
and b) beams correlated during mix design for ages and beams cast during production.]</TXT><BRK/>
<BRK/>
<LST>a. [Correlation of Beams and Cyliders in Laboratory, Cylinders in Field</LST><BRK/>
<BRK/>
<ITM>1). Take samples for strength tests at the paving site.  Fabricate and cure test cylinders in 
accordance with <RID>ASTM C 31/C 31M</RID>; test them in accordance with <RID>ASTM C 39/C 39M</RID>.</ITM><BRK/>
<BRK/>
<ITM>2). Fabricate and cure 2 test cylinders per sublot from the same batch or truckload and at the 
same time acceptance cylinders are fabricated and test them for compressive strength at 7-day 
age.</ITM><BRK/>
<BRK/>
<ITM>3). Average all 8 compressive tests per lot.  Convert this average 7-day compressive strength 
per lot to equivalent [28][90]-day flexural strength using the Correlation Ratio determined 
during mixture proportioning studies.  See Appendix B at the end of this Section.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Adjust ages to match design requirement.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>4). Compare the equivalent [28][90]-day flexural strength from the conversion to the Average 
Flexural Strength Required for Mixtures from paragraph of same title.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Adjust ages to match design requirement.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>5). If the equivalent average [28][90]-day strength for the lot is below the Average Flexural 
Strength Required for Mixtures by<MET> 138 Pa</MET><ENG> 20 psi</ENG> flexural strength or more, at any time, adjust 
the mixture to increase the strength, as approved.</ITM><BRK/>
<BRK/>
<ITM>6). Fabricate and cure two beams for every<MET> 1528 cubic m</MET><ENG> 2000 cubic yards</ENG> of concrete placed.  
Fabricate and cure in accordance with <RID>ASTM C 31/C 31M</RID>; test at 14-days of age in accordance 
with <RID>ASTM C 78</RID>.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Adjust ages to match design requirement.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>7) The Contractor's CQC testing agency shall maintain up-to-date control charts for strength, 
showing the 7-day CQC compressive strength, the 14-day compressive strength (from acceptance 
tests) and the [28][90]-day equivalent flexural strength of each of these for each lot.]</ITM><BRK/>
<BRK/>
<LST>b. [Beams Only in Laboratory, Beams Only in Field</LST><BRK/>
<BRK/>
<ITM>1). Take samples for strength tests at the paving site.  Fabricate and cure test beams in accordance 
with <RID>ASTM C 31/C 31M</RID>; test them in accordance with <RID>ASTM C 78</RID>.</ITM><BRK/>
<BRK/>
<ITM>2). Fabricate and cure 2 test beams per sublot from the same batch or truckload and at the same 
time acceptance beams are fabricated and test them for flexural strength at 7-day age.</ITM><BRK/>
<BRK/>
<ITM>3). Average all 8 flexural tests per lot.  Convert this average 7-day flexural strength per 
lot to equivalent [28][90]-day flexural strength using the Correlation Ratio determined during 
mixture proportioning studies.</ITM><BRK/>
<BRK/>
<ITM>4). Compare the equivalent [28][90]-day flexural strength from the conversion to the Average 
Flexural Strength Required for Mixtures from paragraph of same title.</ITM><BRK/>
<BRK/>
<ITM>5). If the equivalent average [28][90]-day strength for the lot is below the Average Flexural 
Strength Required for Mixtures by 69 psi flexural strength or more, at any time, adjust the 
mixture to increase the strength, as approved.</ITM><BRK/>
<BRK/>
<ITM>6). The Contractor's CQC testing agency shall maintain up-to-date control charts for strength, 
showing the 7-day CQC flexural strength and the [28][90]-day flexural strength (from acceptance 
tests) of each of these for each lot.]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.10   Surface-Smoothness Determination (Straightedge Testing)</TTL><BRK/>
<BRK/>
<LST>a. Furnish one<MET> 3.7 m</MET><ENG> 12 ft</ENG> straightedge for each paving spreader for testing the finished surface.  Straightedges 
shall be made available for Government use upon request.  Straightedges shall be constructed of aluminum 
or other lightweight metal and shall have blades of box or box-girder cross section with flat bottom 
reinforced to ensure rigidity and accuracy.  Straightedges shall have handles to facilitate movement 
on the pavement.</LST><BRK/>
<BRK/>
<LST>b. Immediately after rolling is complete in each area, but not later than 1 hour after the concrete has 
been placed, the surface of the pavement shall be tested with an approved straightedge or other approved 
device that will reveal all surface irregularities varying from the testing edge exceeding tolerances 
specified in Table V-LIMITS AND ALLOWABLE VARIATIONS.  The entire area of the pavement involved shall 
be tested in both a longitudinal and a transverse direction on parallel lines<MET> 3 m</MET><ENG> 10 feet</ENG> or less apart.  
The straightedge shall be held in contact with the surface and moved ahead one-half the length of the 
straightedge for each successive measurement.  Straightedge lines shall be carried continuously across 
joints.  Perform the testing in the presence of the Contracting Officer.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.11   Surface Texture</TTL><BRK/>
<BRK/>
<TXT>The final surface texture of the pavement, after all rolling and curing, shall be smooth and uniform over the 
whole area of the pavement and shall be totally free of any surface pitting, voids or indentations, pockmarks, 
surface tears, check cracking, segregation or rock pockets, pumped areas, aggregate drag marks, areas loosened 
by construction operations, and areas where fines have been washed away during the curing process.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.12   Determine Pavement Thickness</TTL><BRK/>
<BRK/>
<TXT>Cores shall be drilled from points in the pavement within 7 days after placement of the pavement.  A minimum 
of one core per sublot will be taken from locations selected in a random fashion by the Contracting Officer.  
Cores shall be<MET> 150 mm</MET><ENG> 6 inch</ENG> diameter.  Refilling of core holes shall be performed with portland cement mortar, 
using materials and procedures directed.  Cores will become the property of the Government and may be tested 
for strength determination or other properties as considered appropriate.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.13   Inspection During Placing</TTL><BRK/>
<BRK/>
<TXT>The placing foremen shall supervise all placing operations and shall be responsible for measuring and recording 
concrete temperatures, ambient temperature, weather conditions, time of placement, yardage placed, and method 
and location of placement.</TXT><BRK/>
<BRK/>
<LST>a. Cold-Weather Placing.  At least once during each shift, an inspection shall be made of all areas subject 
to cold-weather protection.  Deficiencies shall be noted.  During removal of protection, the concrete 
and ambient temperature shall be measured at least hourly.</LST><BRK/>
<BRK/>
<LST>b. Hot-Weather Placing and Initial Curing at All Times.  When the maximum daily air is likely to exceed<MET>
 30 degrees C</MET><ENG> 85 degrees F</ENG>, take and record the temperature of the concrete mixture at 30-minute intervals 
during hot-weather placement.  The surface of the base course shall be inspected to ensure that it is 
sprinkled with water immediately before the concrete is placed and any deficiencies noted.  Regardless 
of ambient temperature, the finished concrete shall be inspected to ensure that it is kept damp until 
the curing medium is applied and any deficiencies noted and immediately brought to the attention of the 
Contracting Officer.  Immediate steps shall be taken to correct any deficiencies.</LST><BRK/>
<BRK/>
<LST>c. Temperature Protection.  The Contracting Officer shall be notified whenever the concrete temperature 
during the period of protection or protection removal fails to comply with the specifications, and immediate 
steps shall be taken to correct the situation.  Regardless of the ambient temperature, when the temperature 
of the concrete mixture exceeds<MET> 32 degrees C</MET><ENG> 90 degrees F</ENG>, mixing and placing shall be stopped and the 
Contracting Officer notified.</LST><BRK/>
<BRK/>
<LST>d. Curing Operation.  The curing operation shall be inspected to assure that the surface of the pavement 
is kept very moist (or wet) continuously until the end of the curing period.  The Contracting Officer 
shall be notified when any pavement surface is allowed to dry before the end of the curing period, and 
immediate steps shall be taken to correct the situation.</LST><BRK/>
<BRK/></SPT>
</SPT><BRK/>
<PGE/><SPT><TTL>3.10   APPENDIX A</TTL><BRK/>
<TBL><BRK/>
<THD>                    <HL3>APPENDIX A</HL3><BRK/>
                    <HL3>Example of Computations</HL3></THD><BRK/>
<BRK/>
1.0  Field Density.<BRK/>
The calculation of computed percent payment based on field density is illustrated below for a typical set of field 
tests on the lane interior and on the fresh and cold joints in a typical lot.  Assume the following test results 
for field density made on the lot:<BRK/>
<BRK/>
     a.  Average lane interior density:  98.0 percent (of target density)<BRK/>
<BRK/>
     b.  Average fresh joint density:  97.7 percent (of target density)<BRK/>
<BRK/>
     c.  Average cold joint density:  95.4 percent (of target density)<BRK/>
<BRK/>
     d.  Total area of lot:  <MET>2,790 sq m</MET><ENG> 30,000 sq ft (3,333 sq yd)</ENG><BRK/>
<BRK/>
     e.  Length of completed fresh longitudinal construction joint:  610 m (2000 ft) (Paving lane on each side of 
joint complete)<BRK/>
<BRK/>
     f.  Length of cold longitudinal construction joint:  228 m (750 ft) (Paving lane on one side of joint constructed 
with this lot)<BRK/>
<BRK/>
Step 1:  Determine percent payment based on lane interior density and on fresh joint and on cold joint density, using 
Table I.<BRK/>
<BRK/>
     a.  Lane interior density of 98.0 percent:  95.0 percent payment<BRK/>
<BRK/>
     b.  Fresh joint density of 97.7 percent:  72.0 percent payment<BRK/>
<BRK/>
     c.  Cold joint density of 95.4 percent:  52.0 percent payment<BRK/>
<BRK/>
Step 2:  Determine percent payment deduction based on lane interior density and on both fresh and cold joint density 
by subtracting each percent payment from 100.<BRK/>
<BRK/>
     a.  Lane interior:  100 percent - 95.0 percent = 5.0 percent deduction<BRK/>
<BRK/>
     b.  Fresh joint:  100 percent - 72.0 percent = 28.0 percent deduction<BRK/>
<BRK/>
     c.  Cold joint:  100 percent - 52.0 percent = 48.0 percent deduction<BRK/>
<BRK/>
Step 3:  Determine ratio of fresh joint strip area to lane interior area (total paved area in the lot).<BRK/>
<BRK/>
Multiply the length of completed fresh longitudinal construction joint by the specified<MET> 3 m</MET><ENG> 10 ft</ENG> width and divide 
by the lane interior area (total paved area in the lot):<BRK/>
<BRK/>
<MET>610 m x 3m /2790 sq m</MET><ENG> 2000 ft. x 10 ft./30000 sq ft</ENG> = 0.6667 ratio of fresh joint strip area to lane interior area<BRK/>
<BRK/>
Step 4:  Determine the weighted percent payment deduction for fresh joint density:<BRK/>
<BRK/>
Multiply percent payment deduction for fresh joint density by ratio of fresh joint strip area to lane interior area:<BRK/>
<BRK/>
28.0 percent x 0.6667 = 18.7 percent weighted percent payment deduction for fresh joint density<BRK/>
<BRK/>
Step 5:  Determine ratio of cold joint strip area to lane interior area (total paved area in the lot):<BRK/>
<BRK/>
Multiply the length of completed cold longitudinal construction joint (one side) by the specified<MET> 1.5 m</MET><ENG> 5 ft</ENG> width 
and divide by the lane interior area (total paved area in the lot):<BRK/>
<BRK/>
<MET>228 m x 1.5 m/2790 sq ft</MET><ENG> 750 ft x 5 ft/30000 sq ft</ENG> = 0.125 ratio of cold joint strip area to lane interior area<BRK/>
<BRK/>
Step 6:  Determine the weighted percent deduction for cold joint density:<BRK/>
<BRK/>
Multiply percent payment deduction for cold joint density by ratio of cold joint strip area to lane interior area:<BRK/>
<BRK/>
48.0 percent x 0.125 = 6.0 percent payment deduction for cold joint density<BRK/>
<BRK/>
Step 7:  Compare weighted percent payment deduction for fresh joint area, for cold joint area, and for lane interior 
density, and select the larger:<BRK/>
<BRK/>
     a.  Percent payment deduction for lane interior density:  5.0 percent<BRK/>
<BRK/>
     b.  Weighted percent payment deduction for fresh joint density:  18.7 percent<BRK/>
<BRK/>
     c.  Weighted percent payment deduction for cold joint density:  6.0 percent<BRK/>
<BRK/>
     d.  Select the larger =  18.7 percent<BRK/>
<BRK/>
Step 8:  Determine computed percent payment based on field density by subtracting the larger value from Step 7 from 100:<BRK/>
<BRK/>
100 - 18.7 percent = 81.3 percent computed percent payment based on field density.<BRK/>
<BRK/>
2.0  Thickness<BRK/>
A lot in which 18 percent of the area is deficient in thickness by an average of<MET> 10 mm</MET><ENG> 3/8 inch</ENG> (Category II) will 
have a computed percent payment for thickness of:<BRK/>
<BRK/>
               Proportion            Percent Payment     Weighted<BRK/>
                of Total                  From           Percent<BRK/>
  Category      Lot Area                Table II         Payment<BRK/>
__________     __________            _______________     ________<BRK/>
<BRK/>
     I     (1.0-0.18) = 0.82     x         100             82.0<BRK/>
<BRK/>
     II           0.18           x          65             11.7<BRK/>
                                                          ______<BRK/>
<BRK/>
              Computed Percent Payment for Total Lot =     93.7<BRK/></TBL>
</SPT><BRK/>
<PGE/><BRK/>
<SPT><TTL>3.11   Appendix B</TTL><BRK/>
<TBL><BRK/>
<THD>                 <HL3>APPENDIX B</HL3><BRK/>
<BRK/>
            <HL3>Procedure for Molding RCC Test Specimen for</HL3><BRK/>
         <HL3>Flexural Strength Testing Using a Vibrating Hammer:</HL3></THD><BRK/>
<BRK/>
A-1   Field of Application<BRK/>
<BRK/>
The procedure is for molding RCC test specimens using a vibrating hammer for third-point flexural-strength testing.  
Maximum aggregate size shall not exceed<MET> 25 mm</MET><ENG> 1 inch</ENG>.<BRK/>
<BRK/>
A-2   Equipment<BRK/>
<BRK/>
1.   Rectangular steel molds with inside measurements of<MET> 100 x 100 x 400 mm</MET><ENG> 4-inch x 4-inch x 16-inch</ENG>.<BRK/>
<BRK/>
2.   Vibrating hammer, conforming to <RID>ASTM C 1435/C 1435M</RID>, shall weigh<MET> 10 ± 2 kg</MET>, have a minimum power input of 900W 
and be capable of providing 2000 impacts/minute.<BRK/>
<BRK/>
3.   Removable steel collar to contain the last layer of RCC.<BRK/>
4.   Steel compaction plate with a minimum thickness of<MET> 15 mm</MET><ENG> 0.6-inch</ENG> that can fit into the rectangular mold.<BRK/>
5.   Steel finishing plate with a minimum thickness of<MET> 15 mm</MET><ENG> 0.6-inch</ENG> that can fit into the rectangular mold.<BRK/>
<BRK/>
A-3   Molding Specimens for Flexural-Strength Testing<BRK/>
<BRK/>
1.   The specimens must be produced within 20 min of collecting the sample.<BRK/>
2.   Using the wet density of the RCC, weigh a quantity of fresh concrete corresponding to the volume of the test 
specimen to be produced.<BRK/>
3.   Use a flat shovel to fill the mold to the halfway point, moving the shovel along the rim of the mold to distribute 
the concrete evenly and keeping segregation to a minimum.  A tamping rod can be used to spread the concrete evenly 
within the mold prior to consolidation.<BRK/>
4.   Compact the concrete until the mold is half full.  Install the collar.  Put in the remaining concrete and compact it.<BRK/>
5.   Remove the collar, place the steel plate on top of the mold, and complete consolidation by applying the compactor 
to the steel plate.<BRK/>
6.   Spray all concrete surfaces with an evaporation retarder.  Immediately cover the specimens with a nonabsorbent, 
nonreactive plate to retard evaporation.<BRK/>
7.   Store the specimens on a rigid, level surface protected from sunlight, vibration, and other disturbances in 
an environment maintained at a temperature of<MET> 15 to 25°C</MET><ENG> 60 to 77°F</ENG>.  The specimens should be removed from the molds 
24 ± 4 h after fabrication and moist-cured at a temperature of<MET> 21 to 25°C</MET><ENG> 70 to 77°F</ENG> so that they are constantly 
covered with a thin coating of moisture until time of testing.  The specimens shall not be exposed to running water.<BRK/>
<BRK/>
A-4   Flexural-Strength Testing<BRK/>
<BRK/>
Perform flexural testing in accordance with <RID>ASTM C 78</RID>.<BRK/>
<BRK/></TBL>
</SPT><PGE/><SPT><TTL>3.12   APPENDIX C</TTL><BRK/>
<TBL><BRK/>
<THD><HL4><HL3>APPENDIX C</HL3><BRK/>
<HL3> RCC Pavement Mixture Proportioning Method</HL3></HL4></THD></TBL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  TO DOWNLOAD UFGS GRAPHICS OF APPENDIX C<BRK/>
<BRK/>
Go to <URL HREF="http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf">http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf</URL>.<BRK/>
<BRK/>
Appendix C exists as a PDF file to be inserted here after the project specification 
has been printed to pdf.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/></SPT>
</PRT>     <END/><BRK/></SEC>