<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><BRK/>
<HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA                UFGS-32 13 17 (August 2008)<BRK/>
                                              ---------------------------<BRK/>
Preparing Activity:  <PRA>USACE</PRA>                    Superseding<BRK/>
                                              UFGS-32 13 17 (January 2007)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 32 13 17</SCN><BRK/>
<BRK/>
<STL>STONE MATRIX ASPHALT (SMA) FOR AIRFIELD PAVEMENTS</STL><BRK/>
<DTE>08/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>stone matrix asphalt 
(SMA) for both heavy duty roadway and airfield pavements</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification only pertains to the stone matrix asphalt aspects 
of the project and not to any surface preparation requirements dealing with 
aggregate base courses, milling, or tack or prime coats.  Surface preparation 
requirements should be covered by either including them in this guide specification 
or by adding pertinent sections to the project documents.</NPR><BRK/>
<BRK/>
<NPR>SMA can be used as a surface course for any airfield pavement.  SMA provides 
increased durability, resistance to rutting, resistance to reflective cracking 
over HMA.  Local state highway experiences with SMA should be considered when 
developing the job specification.</NPR><BRK/>
<BRK/>
<NPR>This specification utilizes a Quality Assurance and Quality Control (QA/QC) 
construction management philosophy.  Quality Assurance refers to the actions 
performed by the Government or designated representative Engineer to assure 
the final product meets the job requirements.  Results of QA testing are the 
basis for pay.  Quality Control refers to the actions of the Contractor to monitor 
the construction and production processes and to correct these processes when 
out of control.  Results of QC testing are reported daily on the process control 
charts maintained by the Contractor.  Quality Control is covered in paragraph 
CONTRACTOR QUALITY CONTROL.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1   METHOD OF MEASUREMENT</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For unit-price contracts, include first bracketed statements and delete 
the second set.  For lump-sum contracts, delete the first bracketed statements 
and include the second set.  Lump-sum contracts should not be used when the 
job exceeds 1000 metric tons (1000 short tons).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[The amount paid for will be the number of [metric] [short] tons of SMA used in the accepted work.  Weigh the 
SMA after mixing, and no adjustment will be made for weight of asphalt cement material incorporated herein.  
The measured quantity will be divided by the mix adjustment factor (MAF) to determine the pay quantity.  The 
MAF equals the maximum theoretical specific gravity from the JMF divided by 2.500.  If the MAF calculation results 
in a value less than or equal to 1.020 and greater than or equal to 0.98, then the MAF shall be considered to 
be 1.000.  If the calculated MAF is outside the range, then the actual calculated value shall be used.][Measurement 
of the quantity of SMA, per [metric] [short] ton placed and accepted, shall be made for the purposes of assessing 
the pay factors stipulated in this section.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2   BASIS OF PAYMENT</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For unit-price contracts, include first bracketed statements and delete 
the second set.  For lump-sum contracts, delete the first bracketed statements 
and include the second set.  Include prescriptive unit price based on the Government/Engineer 
estimate for payment adjustment.  Lump-sum contracts should not be used when 
the job exceeds 1000 metric tons (1000 tons).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Quantities of SMA mixture, determined as specified above, will be paid for at respective contract unit prices 
or at reduced prices adjusted in accordance with paragraphs PERCENT PAYMENT and QUALITY ASSURANCE.  Payment will 
constitute full compensation for furnishing all materials, equipment, plant, and tools; and for all labor and 
other incidentals necessary to complete work required by this section of the specification.][The measured quantity 
of SMA will be paid for and included in the lump-sum contract price.  If less than 100 percent payment is due 
based on the pay factors stipulated in paragraph QUALITY ASSURANCE, a unit price of [_____] per ton will be used 
for purposes of calculating the payment reduction.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   PERCENT PAYMENT</TTL><BRK/>
<BRK/>
<TXT>When a lot of material fails to meet the specification requirements for 100 percent pay as outlined in the following 
paragraphs, that lot shall be removed and replaced, or accepted at a reduced price which will be computed by 
multiplying the unit price by the lot pay factor.  The lot pay factor is determined by taking the lowest computed 
pay factor based on either laboratory air voids, in place density, grade or smoothness (each discussed below).  
Pay factors based on different criteria (i.e., laboratory air voids and in place density) of the same lot will 
not be multiplied together to get a lower lot pay factor.  At the end of the project, an average of all lot pay 
factors will be calculated.  If this average lot pay factor exceeds 95.0 percent, then the percent payment for 
the entire project will be 100 percent of the unit bid price.  If the average lot pay factor is less than 95.0 
percent, then each lot will be paid for at the unit price multiplied by that lot's pay factor.  For any lots 
which are less than<MET> 2000 metric</MET><ENG> 2000 pound</ENG> tons, a weighted lot pay factor will be used to calculate the average 
lot pay factor.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Mat and Joint Densities</TTL><BRK/>
<BRK/>
<TXT>The average in place mat and joint densities are expressed as a percentage of the average maximum theoretical 
density for the lot.  The maximum theoretical density for each lot will be determined as the average maximum 
theoretical density of the two random samples per lot.  The average in place mat density and joint density for 
a lot are determined and compared with Table 1 to calculate a single pay factor per lot based on in place density, 
as described below.  First, a pay factor for both mat density and joint density are determined from Table 1.  
The area associated with the joint is then determined and will be considered to be<MET> 3 meters</MET><ENG> 10 feet</ENG> wide times 
the length of completed longitudinal construction joint in the lot.  This area will not exceed the total lot 
size.  The length of joint to be considered will be that length where a new lane has been placed against an adjacent 
lane of SMA pavement, either an adjacent freshly paved lane or one paved at any time previously.  The area associated 
with the joint is expressed as a percentage of the total lot area.  A weighted pay factor for the joint is determined 
based on this percentage (see example below).  The pay factor for mat density and the weighted pay factor for 
joint density are compared and the lowest selected.  This selected pay factor is the pay factor based on density 
for the lot.  When the maximum theoretical density on both sides of a longitudinal joint is different, the average 
of these two densities will be used as the maximum theoretical density needed to calculate the percent joint 
density.  All density results for a lot will be completed and reported within 24 hours after the construction 
of that lot.</TXT><BRK/>
<TBL><THD><BRK/>
Table 1  Pay Factor Based on In-Place Density<BRK/>
<BRK/>
Average Mat Density         Pay Factor,                 Average Joint Density<BRK/>
       (4 Cores)             Percent                           (4 Cores)<BRK/></THD>
<BRK/>
     94.0 or 96.0            100.0                        above 92.5<BRK/>
       93.9                  100.0                              92.4<BRK/>
     93.8 or 96.1             99.9                              92.3<BRK/>
       93.7                   99.8                              92.2<BRK/>
     93.6 or 96.2             99.6                              92.1<BRK/>
       93.5                   99.4                              92.0<BRK/>
     93.4 or 96.3             99.1                              91.9<BRK/>
       93.3                   98.7                              91.8<BRK/>
     93.2 or 96.4             98.3                              91.7<BRK/>
       93.1                   97.8                              91.6<BRK/>
     93.0 or 96.5             97.3                              91.5<BRK/>
       92.9                   96.3                              91.4<BRK/>
     92.8 or 96.6             94.1                              91.3<BRK/>
       92.7                   92.2                              91.2<BRK/>
     92.6 or 96.7             90.3                              91.1<BRK/>
       92.5                   87.9                              91.0<BRK/>
     92.4 or 96.8             85.7                              90.9<BRK/>
       92.3                   83.3                              90.8<BRK/>
     92.2 or 96.9             80.6                              90.7<BRK/>
       92.1                   78.0                              90.6<BRK/>
     92.0 or 97.0             75.0                              90.5<BRK/>
below 92.0, above 101.0        0.0 (reject)               below 90.5</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2   Pay Factor Based on In-Place Density</TTL><BRK/>
<BRK/>
<TXT>An example of the computation of a pay factor (in inch-pound units only) based on in place density, is as follows:  
Assume the following test results for field density made on the lot:  (1) Average mat density = 93.2 percent 
(of maximum theoretical density), (2) Average joint density = 91.0 percent (of maximum theoretical density), 
(3) Total area of lot = 30,000 square feet, (4) Length of completed longitudinal construction joint = 2000 feet.</TXT><BRK/>
<BRK/>
<LST>a.  Step 1:  Determine pay factor based on mat density and on joint density, using Table 1:</LST><BRK/>
<BRK/>
<ITM>Mat density of 93.2 percent = 98.3 pay factor</ITM><BRK/>
<ITM>Joint density of 91.5 percent = 97.3 pay factor</ITM><BRK/>
<BRK/>
<LST>b.  Step 2:  Determine ratio of joint area (length of longitudinal joint x 10 ft) to mat area (total 
paved area in the lot):  Multiply the length of completed longitudinal construction joint by the specified 
10 ft width and divide by the mat area (total paved area in the lot).</LST><BRK/>
<BRK/>
<ITM>(2000 ft. x 10 ft)/30000 sq ft = 0.6667 ratio of joint area to mat area (ratio)</ITM><BRK/>
<BRK/>
<LST>c.  Step 3:  Weighted pay factor (wpf) for joint is determined as indicated below:</LST><BRK/>
<BRK/>
<ITM>wpf = joint pay factor + (100 - joint pay factor) (1 - ratio) wpf = 97.3 + (100-97.3) (1-0.6667) 
= 98.2 percent</ITM><BRK/>
<BRK/>
<LST>d.  Step 4:  Compare weighted pay factor for joint density to pay factor for mat density and select the 
smaller:</LST><BRK/>
<BRK/>
<ITM>Pay factor for mat density:  98.3 percent.  Weighted pay factor for joint density:  98.2 percent.</ITM><BRK/>
<ITM>Select the smaller of the two values as pay factor based on density:  98.2 percent.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.3   Payment Adjustment for Smoothness</TTL><BRK/>
<BRK/>
<LST>a.  Straightedge Testing.  Location and deviation from straightedge for all measurements shall be recorded.  
When between 5.0 and 10.0 percent of all measurements made within a lot exceed the tolerance specified 
in paragraph Smoothness Requirements below, after any reduction of high spots or removal and replacement, 
the computed pay factor for that lot based on surface smoothness, will be 95 percent.  When more than 
10.0 percent of all measurements exceed the tolerance, the computed pay factor will be 90 percent.  When 
between 15.0 and 20.0 percent of all measurements exceed the tolerance, the computed pay factor will 
be 75 percent.  When 20.0 percent or more of the measurements exceed the tolerance, the lot shall be 
removed and replaced at no additional cost to the Government-Owner.  Regardless of the above, any small 
individual area with surface deviation which exceeds the tolerance given above by more than 50 percent, 
shall be corrected by diamond grinding to meet the specification requirements above or shall be removed 
and replaced at no additional cost to the Government.</LST><BRK/>
<BRK/>
<LST>b.   Profilograph Testing.  Location and data from all profilograph measurements shall be recorded.  
When the Profile Index of a lot exceeds the tolerance specified in paragraph Smoothness Requirements 
above by<MET> 16 mm/km</MET><ENG>1.0 inch/mile</ENG>, but less than<MET> 32 mm/km</MET><ENG> 2.0 inches/mile</ENG>, after any reduction of high spots 
or removal and replacement, the computed pay factor for that lot based on surface smoothness will be 
95 percent.  When the Profile Index exceeds the tolerance by<MET> 32 mm/km</MET><ENG> 2.0 inches/mile</ENG>, but less than<MET> 
47 mm/km</MET><ENG> 3.0 inches/mile</ENG>, the computed pay factor will be 90 percent.  When the Profile Index exceeds 
the tolerance by<MET> 47 mm/km</MET><ENG> 3.0 inches/mile</ENG>, but less than<MET> 63 mm/km</MET><ENG> 4.0 inches/mile</ENG>, the computed pay factor 
will be 75 percent.  When the Profile Index exceeds the tolerance by<MET> 63 mm/km</MET><ENG> 4.0 inches/mile</ENG> or more, 
the lot shall be removed and replaced at no additional cost to the Government.  Regardless of the above, 
any small individual area with surface deviation which exceeds the tolerance given above by more than<MET>
 79 mm/km</MET><ENG> 5.0 inches/mile</ENG> or more, shall be corrected by grinding to meet the specification requirements 
above or shall be removed and replaced at no additional cost to the Government.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.4   Laboratory Air Voids and Theoretical Maximum Density</TTL><BRK/>
<BRK/>
<TXT>Laboratory air voids will be calculated in accordance with <RID>ASTM D 3203</RID> by determining the density of each lab 
compacted specimen using <RID>ASTM D 2726</RID> and determining the theoretical maximum density (TMD) of every other sublot 
sample using <RID>ASTM D 2041</RID>.  Laboratory air void calculations for each sublot will use the latest theoretical maximum 
density values obtained, for either that sublot or the previous sublot.  The mean absolute deviation of the four-laboratory 
air void contents (one from each sublot) from the JMF air void content will be evaluated and a pay factor determined 
from Table 2.  All laboratory air void tests will be completed and reported within 24 hours after completion 
of construction of each lot.  The TMD is also used for computation of compaction, as required in paragraph:  
Mat and Joint Densities above.</TXT><BRK/>
<TBL><THD><BRK/>
<HL4>Table 2  Pay Factor Based on Laboratory Air Voids</HL4><BRK/>
<BRK/>
Mean Absolute Deviation of Lab Air Voids from JMF   Pay Factor, percent<BRK/></THD>
<BRK/>
                   0.60 or less                              100<BRK/>
                   0.61 - 0.80                                98<BRK/>
                   0.81 - 1.00                                95<BRK/>
                   1.01 - 1.20                                90<BRK/>
                    Above 1.20                        0 (reject)</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.5   Mean Absolute Deviation</TTL><BRK/>
<BRK/>
<TXT>An example of the computation of mean absolute deviation for laboratory air voids is as follows:  Assume that 
the laboratory air voids are determined from 4 random samples of a lot (where 3 specimens were compacted from 
each sample).  The average laboratory air voids for each sublot sample are determined to be 3.5, 3.0, 4.0, and 
3.7.  Assume that the target air voids from the JMF is 4.0.  The mean absolute deviation is then:<BRK/>
<BRK/>
Mean Absolute Deviation = ( 3.5 - 4.0  +  3.0 - 4.0  +  4.0 - 4.0  + <BRK/>
 3.7 - 4.0 )/4 = (0.5 + 1.0 + 0.0 + 0.3)/4 = (1.8)/4 = 0.45<BRK/>
<BRK/>
The mean absolute deviation for laboratory air voids is determined to be 0.45.  It can be seen from Table 2 that 
that lot's pay factor based on laboratory air voids is 100 percent.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.6   Pay Adjustment Based on Grade</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The grade and surface smoothness requirements specified below are for 
the final wearing surface only.  If there is a requirement to test and control 
the grade and smoothness for the intermediate courses, i.e., when the intermediate 
courses will be exposed to traffic, slight modifications to this specification 
will be required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Within 5 working days after completion of a particular lot incorporating the final wearing course, test the final 
wearing surface for conformance with specified plan grade requirements.  Detailed notes of the results of the 
testing shall be kept and a copy furnished to the Government immediately after each day's testing.  The final 
wearing surface of pavement shall conform to the elevations and cross sections shown and shall vary not more 
than<MET> 9 mm</MET><ENG> 0.03 foot</ENG> for runways or<MET> 15 mm</MET><ENG> 0.05 foot</ENG> for taxiways and aprons from the plan grade established and 
approved at site of work.  Finished surfaces at juncture with other pavements shall coincide with finished surfaces 
of abutting pavements.  Deviation from the plan elevation will not be permitted in areas of pavements where closer 
conformance with planned elevation is required for the proper functioning of drainage and other appurtenant structures 
involved.  The grade will be determined by running lines of levels at intervals of<MET> 7.6 meters</MET><ENG> 25 feet</ENG>, or less, 
longitudinally and transversely, to determine the elevation of the completed pavement surface.  When more than 
5 percent of all measurements made within a lot are outside the<MET> 9 or 15 mm</MET><ENG> 0.03 or 0.05 foot</ENG> tolerance, the pay 
factor based on grade for that lot will be 95 percent.  In areas where the grade exceeds the tolerance by more 
than 50 percent, remove the surface lift full depth; then replace the lift with SMA to meet specification requirements, 
at no additional cost to the Government.  Diamond grinding may be used to remove high spots to meet grade requirements.  
Skin patching for correcting low areas or planing or milling for correcting high areas will not be permitted.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification.  The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
<BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
<BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)</ORG><BRK/><BRK/><RID>AASHTO M 320</RID><RTL>(2005) Performance-Graded Asphalt Binder</RTL><BRK/><BRK/><RID>AASHTO M 325</RID><RTL>(2008) Standard Specification for Stone Matrix Asphalt (SMA)</RTL><BRK/><BRK/><RID>AASHTO R 46</RID><RTL>(2008) Standard Practice for Designing Stone Matrix Asphalt (SMA)</RTL><BRK/><BRK/><RID>AASHTO T 312</RID><RTL>(2008) Preparing and Determining the Density of Hot Mixed Asphalt (HMA) Specimens By Means of the Superpave Gyratory Compactor</RTL><BRK/><BRK/></REF><REF><ORG>ASPHALT INSTITUTE (AI)</ORG><BRK/><BRK/><RID>AI MS-02</RID><RTL>(6th Edition; 1997) Mix Design Methods for Asphalt</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM C 117</RID><RTL>(2004) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing</RTL><BRK/><BRK/><RID>ASTM C 1252</RID><RTL>(2006) Standard Test Methods for Uncompacted Void Content of Fine Aggregate (as Influenced by Particle Shape, Surface Texture, and Grading)</RTL><BRK/><BRK/><RID>ASTM C 127</RID><RTL>(2007) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate</RTL><BRK/><BRK/><RID>ASTM C 128</RID><RTL>(2007a) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Fine Aggregate</RTL><BRK/><BRK/><RID>ASTM C 131</RID><RTL>(2006)Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine</RTL><BRK/><BRK/><RID>ASTM C 136</RID><RTL>(2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates</RTL><BRK/><BRK/><RID>ASTM C 566</RID><RTL>(1997; R 2004) Standard Test Method for Total Evaporable Moisture Content of Aggregate by Drying</RTL><BRK/><BRK/><RID>ASTM C 612</RID><RTL>(2004e1) Mineral Fiber Block and Board Thermal Insulation</RTL><BRK/><BRK/><RID>ASTM C 88</RID><RTL>(2005) Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate</RTL><BRK/><BRK/><RID>ASTM D 140</RID><RTL>(2001; R 2007) Sampling Bituminous Materials</RTL><BRK/><BRK/><RID>ASTM D 2041</RID><RTL>(2003a) Theoretical Maximum Specific Gravity and Density of Bituminous Paving Mixtures</RTL><BRK/><BRK/><RID>ASTM D 2172</RID><RTL>(2005) Quantitative Extraction of Bitumen from Bituminous Paving Mixtures</RTL><BRK/><BRK/><RID>ASTM D 2419</RID><RTL>(2002) Sand Equivalent Value of Soils and Fine Aggregate</RTL><BRK/><BRK/><RID>ASTM D 242</RID><RTL>(2004) Mineral Filler for Bituminous Paving Mixtures</RTL><BRK/><BRK/><RID>ASTM D 2489/D 2489M</RID><RTL>(2008) Estimating Degree of Particle Coating of Bituminous-Aggregate Mixtures</RTL><BRK/><BRK/><RID>ASTM D 2726</RID><RTL>(2008) Bulk Specific Gravity and Density of Non-Absorptive Compacted Bituminous Mixtures</RTL><BRK/><BRK/><RID>ASTM D 2950</RID><RTL>(2005) Density of Bituminous Concrete in Place by Nuclear Methods</RTL><BRK/><BRK/><RID>ASTM D 3203</RID><RTL>(2005) Percent Air Voids in Compacted Dense and Open Bituminous Paving Mixtures</RTL><BRK/><BRK/><RID>ASTM D 3381</RID><RTL>(2005) Viscosity-Graded Asphalt Cement for Use in Pavement Construction</RTL><BRK/><BRK/><RID>ASTM D 3665</RID><RTL>(2007) Random Sampling of Construction Materials</RTL><BRK/><BRK/><RID>ASTM D 3666</RID><RTL>(2007e1) Minimum Requirements for Agencies Testing and Inspecting Road and Paving Materials</RTL><BRK/><BRK/><RID>ASTM D 4125</RID><RTL>(2005) Asphalt Content of Bituminous Mixtures by the Nuclear Method</RTL><BRK/><BRK/><RID>ASTM D 4318</RID><RTL>(2005) Liquid Limit, Plastic Limit, and Plasticity Index of Soils</RTL><BRK/><BRK/><RID>ASTM D 4791</RID><RTL>(2005e1) Flat Particles, Elongated Particles, or Flat and Elongated Particles in Coarse Aggregate</RTL><BRK/><BRK/><RID>ASTM D 4867/D 4867M</RID><RTL>(2004) Effect of Moisture on Asphalt Concrete Paving Mixtures</RTL><BRK/><BRK/><RID>ASTM D 5444</RID><RTL>(2008) Mechanical Size Analysis of Extracted Aggregate</RTL><BRK/><BRK/><RID>ASTM D 6307</RID><RTL>(2005) Asphalt Content of Hot Mix Asphalt by Ignition Method</RTL><BRK/><BRK/><RID>ASTM D 6390</RID><RTL>(2005) Determination of Draindown Characteristics in Uncompacted Asphalt Mixtures</RTL><BRK/><BRK/><RID>ASTM D 75</RID><RTL>(2003) Standard Practice for Sampling Aggregates</RTL><BRK/><BRK/><RID>ASTM D 946</RID><RTL>(1982; R 2005) Penetration-Graded Asphalt Cement for Use in Pavement Construction</RTL><BRK/><BRK/><RID>ASTM D 979</RID><RTL>(2001; R 2006e1) Sampling Bituminous Paving Mixtures</RTL><BRK/><BRK/><RID>ASTM D 995</RID><RTL>(1995b; R 2002) Mixing Plants for Hot-Mixed, Hot-Laid Bituminous Paving Mixtures</RTL><BRK/><BRK/></REF><REF><ORG>STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION (CDT)</ORG><BRK/><BRK/><RID>CDT Test 526</RID><RTL>(2002) Operation of California Profilograph and Evaluation of Profiles</RTL><BRK/><BRK/></REF><REF><ORG>U.S. ARMY CORPS OF ENGINEERS (USACE)</ORG><BRK/><BRK/><RID>COE CRD-C 171</RID><RTL>(1994) Standard Test Method for Determining Percentage of Crushed Particles in Aggregate</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.5   SYSTEM DESCRIPTION</TTL><BRK/>
<BRK/>
<TXT>Perform the work consisting of pavement courses composed of mineral aggregate, polymer-modified asphalt material, 
and a stabilizer, mixed in a central mixing plant.  The hot mixture is placed with an asphalt paver on a prepared 
course.  Stone matrix asphalt (SMA) mixtures designed and constructed in accordance with these specifications 
shall conform to the lines, grades, thicknesses, and typical cross sections shown on the drawings.  Provide plants 
used for the preparation of SMA conforming to the requirements of <RID>ASTM D 995</RID> with the changes listed below:</TXT><BRK/>
<BRK/>
<SPT><TTL>1.5.1   Truck Scales</TTL><BRK/>
<BRK/>
<TXT>Weigh the asphalt mixture on approved scales furnished by the Contractor, or on certified public scales at the 
Contractor's expense.  Scales shall be inspected and sealed at least annually by an approved calibration laboratory.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2   Testing Facilities</TTL><BRK/>
<BRK/>
<TXT>Provide laboratory facilities at the plant for the use of the Government Engineer's acceptance testing and the 
Contractor's quality control testing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.3   Inspection of Plant</TTL><BRK/>
<BRK/>
<TXT>The Contracting Officer/Engineer shall have access at all times, to all areas of the plant for checking adequacy 
of equipment; inspecting operation of the plant; verifying weights, proportions, and material properties; checking 
the temperatures maintained in the preparation of the mixtures and for taking samples.  Provide assistance, as 
requested, for the Government Engineer to procure any desired samples.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.4   Storage Bins</TTL><BRK/>
<BRK/>
<TXT>The SMA mixture may be stored in non-insulated storage bins for a period of time not to exceed 2 hours.  The 
SMA mixture may be stored in insulated storage bins for a period of time not exceeding 4 hours.  The mix drawn 
from bins shall meet the same requirements as mix loaded directly into trucks.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.5   Hauling Equipment</TTL><BRK/>
<BRK/>
<TXT>Trucks used for hauling SMA shall have tight, clean, and smooth metal beds.  To prevent the mixture from adhering 
to them, the truck beds shall be lightly coated with a minimum amount of paraffin oil, lime solution, or other 
approved material.  Petroleum based products shall not be used as a release agent.  Each truck shall have a suitable 
cover to protect the mixture from adverse weather.  When necessary to ensure that the mixture will be delivered 
to the site at the specified temperature, truck beds shall be insulated or heated, and covers (tarps) shall be 
securely fastened.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.6   Asphalt Pavers</TTL><BRK/>
<BRK/>
<TXT>Provide asphalt pavers which are self-propelled, with an activated screed, heated as necessary, and capable of 
spreading and finishing SMA which will meet the specified thickness, smoothness, and grade.  The paver shall 
have sufficient power to propel itself and the hauling equipment without adversely affecting the finished surface.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.5.6.1   Receiving Hopper</TTL><BRK/>
<BRK/>
<TXT>The paver shall have a receiving hopper of sufficient capacity to permit a uniform spreading operation.  The 
hopper shall be equipped with a distribution system to place the mixture uniformly in front of the screed without 
segregation.  The screed shall effectively produce a finished surface of the required evenness and texture without 
tearing, shoving, or gouging the mixture.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.6.2   Automatic [Grade] [Screed] Controls</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select automatic grade control when the design requires elevations for 
the SMA surface.  Most specifications require an overlay thickness and do not 
specify actual grades; therefore, select or delete the information below within 
the brackets.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[The automatic grade control device shall consist of a control system capable of automatically maintaining the 
paver screed at the specified elevation.  The control system shall be automatically actuated from either a reference 
line and/or through a system of mechanical sensors or sensor-directed mechanisms or devices which will maintain 
the paver screed at a predetermined transverse slope and at the proper elevation to obtain the required surface.  
The transverse slope controller shall be capable of maintaining the screed at the desired slope within plus or 
minus 0.1 percent.  A transverse slope controller shall not be used to control grade.  The controls shall be 
capable of working in conjunction with any of the following attachments:</TXT><BRK/>
<BRK/>
<LST>a.  Ski-type device of not less than<MET> 9.14 meters</MET><ENG> 30 feet</ENG> in length.</LST><BRK/>
<BRK/>
<LST>b.  Taut stringline set to grade.</LST><BRK/>
<BRK/>
<LST>c.  Short ski or shoe for joint matching.</LST><BRK/>
<BRK/>
<LST>d.  Laser control.]</LST><BRK/>
<BRK/>
<TXT>[The automatic screed control device shall consist of a control system capable of automatically controlling the 
elevation of the paver screed according to the inputs received.  The control system shall be automatically actuated 
from a system of mechanical sensors or sensor-directed mechanisms or devices that will maintain the paver screed 
at the proper elevation to obtain the required surface thickness and smoothness.  The controls shall be capable 
of working in conjunction with any of the following attachments:</TXT><BRK/>
<BRK/>
<LST>a.  Ski-type device of not less than<MET> 9.14 meters</MET><ENG> 30 feet</ENG> in length.</LST><BRK/>
<BRK/>
<LST>b.  Short ski or shoe for joint matching.]</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.5.7   Rollers</TTL><BRK/>
<BRK/>
<TXT>Rollers shall be in good condition and shall be operated at slow speeds to avoid displacement of the SMA mixture.  
The number, type, and weight of rollers shall be sufficient to compact the mixture to the required density.  
Rollers that cause crushing of the aggregate shall not be used.  Rubber-tired rollers shall not be used.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.6   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section <SRF>01 33 00</SRF> SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy, Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for [Contractor Quality Control approval.] [information only.  When used, a designation following the "G" 
designation identifies the office that will review the submittal for the Government.]  Submit the following in 
accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Mix Design</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Proposed JMF.</ITM><BRK/>
<BRK/>
<ITM><SUB>Contractor Quality Control</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Quality control plan.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-04 Samples</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Asphalt Cement Binder</SUB></ITM><BRK/>
<BRK/>
<ITM>  <MET>20 L</MET><ENG> 5 gallons</ENG> sample for mix design verification.</ITM><BRK/>
<BRK/>
<ITM><SUB>Aggregates</SUB></ITM><BRK/>
<BRK/>
<ITM>  Sufficient materials to produce<MET> 90 kg</MET><ENG> 200 lbs</ENG> of blended mixture for mix design verification.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Aggregates</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<ITM><SUB>QC Monitoring</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Aggregate and QC test results.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Asphalt Cement Binder</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<ITM><SUB>Fiber Stabilizer</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Copies of certified test data.</ITM><BRK/>
<BRK/>
<ITM><SUB>Testing Laboratory</SUB></ITM><BRK/>
<BRK/>
<ITM>  Certification of compliance.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7   QUALITY ASSURANCE</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  It is highly recommended to keep the Government's QA testing separate 
and distinct from the Contractor's QC testing.  However, it is recognized that 
in house testing capability to provide the QA testing required by this section 
will not always be available; in this case, it is recommended that an independent 
material testing company be hired to provide the QA testing for the project.  
The cost of this testing to assure good long-term performance is very small 
relative to the overall cost of the construction, and especially compared to 
the cost of a pavement failure.</NPR><BRK/>
<BRK/>
<NPR>Although not recommended, this guide specification may be modified to require 
the Contractor to hire an independent material-testing laboratory to perform 
the QA testing listed in this section.  The results would need to be forwarded 
daily to the Contracting Officer as the basis for acceptance and pay.  This 
should only be done if there is no way of hiring an independent testing laboratory 
to perform the QA testing.<BRK/>
<BRK/>
The QA testing program includes material tests to determine laboratory air voids 
and in place density, which are needed to determine percent payment.  The project 
engineer may choose to have additional tests conducted by the QA test agency 
to monitor aggregate gradation, asphalt content.  These tests would serve as 
a check to the Contractor's QC testing.  This additional testing, if conducted, 
is not included as part of this specification since the parameters are not used 
as a basis of pay.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The Government's quality assurance (QA) program for this project will be separate and distinct from the Contractor's 
quality control (QC) program specified in PART 3.  Testing for acceptability of work will be performed by the 
Government or by an independent laboratory hired by the Contracting Officer, except for smoothness and grade 
testing which shall be performed by the Contractor.  Acceptance of the plant produced mix and in place requirements 
will be on a lot to lot basis.  A standard lot for all requirements will be equal to<MET> 2000 metric</MET><ENG> 2000 short</ENG> tons.  
Where appropriate, adjustment in payment for individual lots of SMA will be made based on in place density, laboratory 
air voids, grade and smoothness in accordance with the following paragraphs.  Grade and surface smoothness determinations 
will be made on the lot as a whole.  Exceptions or adjustments to this will be made in situations where the mix 
within one lot is placed as part of both the intermediate and surface courses, thus grade and smoothness measurements 
for the entire lot cannot be made.  In order to evaluate laboratory air voids and in place (field) density, each 
lot will be divided into four equal sublots.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.7.1   Sublot Sampling</TTL><BRK/>
<BRK/>
<TXT>One random mixture sample for determining laboratory air voids, theoretical maximum density, and for any additional 
testing the Contracting Officer desires, will be taken from a loaded truck delivering mixture to each sublot, 
or other appropriate location for each sublot.  All samples will be selected randomly, using commonly recognized 
methods of assuring randomness conforming to <RID>ASTM D 3665</RID> and employing tables of random numbers or computer programs.  
Laboratory air voids will be determined from three laboratory compacted specimens of each sublot sample.  The 
specimens will be compacted within 2 hours of the time the mixture was loaded into trucks at the asphalt plant.  
Samples will not be reheated prior to compaction and insulated containers will be used as necessary to maintain 
the temperature.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.2   Additional Smpling and Testing</TTL><BRK/>
<BRK/>
<TXT>The Contracting Officer reserves the right to direct additional samples and tests for any area which appears 
to deviate from the specification requirements.  The cost of any additional testing will be paid for by the Government.  
Testing in these areas will be in addition to the lot testing, and the requirements for these areas will be the 
same as those for a lot.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.3   In-Place Density</TTL><BRK/>
<BRK/>
<TXT>For determining in place density, one random core (<MET>100 to 150 mm</MET><ENG> 4 to 6 inches</ENG> in diameter) will be taken by 
the Government from the mat (interior of the lane) of each sublot, and one random core will be taken from the 
joint (immediately over joint) of each sublot in accordance with <RID>ASTM D 979</RID>.  Each random core will be full thickness 
of the layer being placed.  When the random core is less than<MET> 25 mm</MET><ENG> 1 inch</ENG> thick, it will not be included in 
the analysis.  In this case, another random core will be taken.  After air-drying in accordance with <RID>ASTM D 2726</RID>
 for laboratory prepared, thoroughly dry specimens, cores obtained from the mat and from the joints will be used 
for in place density determination.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.4   Surface Smoothness</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Edit these paragraphs as appropriate to the project.  It is desired to 
restrict surface smoothness testing and evaluation to either straightedge method 
or profilograph method.  Retain the one and delete the other; otherwise, retain 
both as a Contractor's option.  Generally, designer should require use of the 
profilograph method.  If the profilograph method is allowed, and there are areas 
with dimensions less than 60 meters (200 feet) in any direction, part of the 
straightedge method must be retained for these short runs.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Use [one] [both] of the following methods to test and evaluate surface smoothness of the pavement.  Perform all 
testing in the presence of the Contracting Officer.  Keep detailed notes of the results of the testing with a 
copy furnished to the Government immediately after each day's testing.  Use the profilograph method for all longitudinal 
and transverse testing, except where the runs would be less than<MET> 60 meters</MET><ENG> 200 feet</ENG> in length and the ends where 
the straightedge shall be used.  Where drawings show required deviations from a plane surface (crowns, drainage 
inlets, etc.), the surface shall be finished to meet the approval of the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.5   Smoothness Requirements</TTL><BRK/>
<BRK/>
<LST>a.  Straightedge Testing:  The finished surfaces of the pavements shall have no abrupt change of<MET> 3 mm</MET><ENG>
 1/8 inch</ENG> or more, and all pavements shall be within the tolerances specified in Table 3 when checked 
with an approved<MET> 4-meter</MET><ENG> 12-foot</ENG> straightedge.</LST><BRK/>
<MET><TBL><THD><BRK/>
<HL4>Table 3  Straightedge Surface Smoothness-Pavements</HL4><BRK/>
<BRK/>
     Pavement Category          Direction of Testing            Tolerance, mm<BRK/></THD>
<BRK/>
Runways and taxiways                Longitudinal                       3<BRK/>
                                     Transverse                        6<BRK/>
<BRK/>
Calibration hardstands and          Longitudinal                       3<BRK/>
compass swinging bases               Transverse                        3<BRK/>
<BRK/>
All other airfield and              Longitudinal                       6<BRK/>
helicopter paved areas               Transverse                        6<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>Table 3  Straightedge Surface Smoothness-Pavements</HL4><BRK/>
<BRK/>
     Pavement Category          Direction of Testing          Tolerance, inch<BRK/></THD>
<BRK/>
Runways and taxiways                Longitudinal                      1/8<BRK/>
                                     Transverse                       1/4<BRK/>
<BRK/>
Calibration hardstands and          Longitudinal                      1/8<BRK/>
compass swinging bases               Transverse                       1/8<BRK/>
<BRK/>
All other airfield and              Longitudinal                      1/4<BRK/>
helicopter paved areas               Transverse                       1/4</TBL></ENG><BRK/>
<BRK/>
<LST>b.   Profilograph Testing:  The finished surfaces of the pavements shall have no abrupt change of<MET> 3 mm</MET><ENG>
 1/8 inch</ENG> or more, and all pavement shall have a Profile Index not greater than specified in Table 4 
when testing with an approved California-type profilograph.  If the extent of the pavement in either 
direction is less than<MET> 60 meters</MET><ENG> 200 feet</ENG>, that direction shall be tested by the straightedge method 
and shall meet requirements specified above.</LST><BRK/>
<MET><TBL><THD><BRK/>
<HL4>Table 4  Profilograph Surface Smoothness Pavements</HL4><BRK/>
<BRK/>
                                                            Maximum Specified<BRK/>
                                                              Profile Index<BRK/>
       Pavement Category         Direction of Testing            (mm/km)<BRK/></THD>
<BRK/>
Runways                            Longitudinal                    110<BRK/>
                                    Transverse                     140<BRK/>
<BRK/>
Taxiways                           Longitudinal                    140<BRK/>
                                    Transverse             (Use Straightedge)<BRK/>
<BRK/>
Calibration hardstands and                                 (Use Straightedge)<BRK/>
compass swinging bases<BRK/>
<BRK/>
All other airfield and             Longitudinal                    140<BRK/>
helicopter paved areas              Transverse                     140<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>Table 4  Profilograph Surface Smoothness Pavements</HL4><BRK/>
<BRK/>
                                                            Maximum Specified<BRK/>
                                                              Profile Index<BRK/>
       Pavement Category         Direction of Testing          (inch/mile)<BRK/></THD>
<BRK/>
Runways                            Longitudinal                    7<BRK/>
                                    Transverse                     9<BRK/>
<BRK/>
Taxiways                           Longitudinal                    9<BRK/>
                                    Transverse             (Use Straightedge)<BRK/>
<BRK/>
Calibration hardstands and                                 (Use Straightedge)<BRK/>
compass swinging bases<BRK/>
<BRK/>
All other airfield and             Longitudinal                    9<BRK/>
helicopter paved areas              Transverse                     9</TBL></ENG><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.6   Testing Method</TTL><BRK/>
<BRK/>
<TXT>After the final rolling, but not later than 24 hours after placement, the surface of the pavement in each entire 
lot shall be tested by the Contractor in such a manner as to reveal all surface irregularities exceeding the 
tolerances specified above.  Separate testing of individual sub lots is not required.  If any pavement areas 
are ground, these areas shall be retested immediately after grinding.  The entire area of the pavement shall 
be tested in both a longitudinal and a transverse direction on parallel lines.  The transverse lines shall be<MET>
 4.5 meters</MET><ENG> 15 feet</ENG> or less apart, as directed.  The longitudinal lines shall be at the centerline of each paving 
lane for lines less than<MET> 6.1 meters</MET><ENG> 20 feet</ENG> and at the third points for lanes<MET> 6.1 meters</MET><ENG> 20 feet</ENG> or greater.  
Other areas having obvious deviations shall also be tested.  Longitudinal testing lines shall be continuous across 
all joints.</TXT><BRK/>
<BRK/>
<LST>a.  Straightedge Testing.  Hold the straightedge in contact with the surface and move ahead one-half 
the length of the straightedge for each successive measurement.  Determine the amount of surface irregularity 
by placing the freestanding (unleveled) straightedge on the pavement surface and allowing it to rest 
upon the two highest spots covered by its length, and measuring the maximum gap between the straightedge 
and the pavement surface in the area between these two high points.</LST><BRK/>
<BRK/>
<LST>b.  Profilograph Testing.  Perform profilograph testing using approved equipment and procedures described 
in <RID>CDT Test 526</RID>.  The equipment shall utilize electronic recording and automatic computerized reduction 
of data to indicate "must-grind" bumps and the Profile Index for the pavement.  The "blanking band" shall 
be<MET> 5 mm</MET><ENG> 0.2 inches</ENG> wide and the "bump template" shall span<MET> 25 mm</MET><ENG> 1 inch</ENG> with an offset of<MET> 10 mm</MET><ENG> 0.4 inch</ENG>
.  The profilograph shall be operated by an approved, factory-trained operator on the alignments specified 
above.  Furnish a copy of the reduced tapes to the Government at the end of each day's testing.</LST><BRK/>
<BRK/>
<LST>c.  Bumps.  ("Must Grind" Areas).  Any bumps ("must grind" areas) shown on the profilograph trace which 
exceed<MET> 10 mm</MET><ENG> 0.4 inch</ENG> in height shall be reduced by diamond grinding until they do not exceed<MET> 7.5 mm</MET><ENG> 
0.3 inch</ENG> when retested.  Such grinding shall be tapered in all directions to provide smooth transitions 
to areas not requiring grinding.  The following will not be permitted:  (1) skin patching for correcting 
low areas, (2) planing or milling for correcting high areas.  At the Contractor's option, pavement areas, 
including ground areas, may be rechecked with the profilograph in order to record a lower Profile Index.</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.8   ENVIRONMENTAL REQUIREMENTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The temperature requirements are included to avoid problems with the 
Contractor achieving density because the mix cools too fast.  Waivers to these 
requirements, for isolated incidences during production, are applicable if the 
density requirements are still met.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Do not place the SMA upon a wet surface or when the surface temperature of the underlying course is less than<MET>
 7 degrees C</MET><ENG> 45 degrees F</ENG>.  The temperature requirements may be waived by the Contracting Officer, if requested; 
however, all other requirements, including compaction, shall be met.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   <SUB>AGGREGATES</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  One objective in the design of SMA is to produce a mixture with stone-on-stone 
aggregate contact.  This requires hard, durable, highly fractured aggregates.  
Include only sources with a satisfactory performance record under similar conditions 
of service and exposure.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Aggregates shall consist of crushed stone, [crushed gravel,] [crushed steel slag,] screenings, and mineral filler, 
as required.  The portion of material retained on the<MET> 4.75 mm</MET><ENG> No. 4</ENG> sieve is coarse aggregate.  The portion of 
material passing the<MET> 4.75 mm</MET><ENG> No. 4</ENG> sieve and retained on the<MET> 0.075 mm</MET><ENG> No. 200</ENG> sieve is fine aggregate.  The portion 
passing the<MET> 0.075 mm</MET><ENG> No. 200</ENG> sieve is defined as mineral filler.  All aggregate test results and samples shall 
be submitted to the Contracting Officer at least 14 days prior to start of construction.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.1.1   Coarse Aggregate</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The requirement for magnesium sulfate (requirement b., below) may be 
deleted in climates where freeze-thaw does not occur.  However, in these areas 
where freeze-thaw does not occur, requirement b., should remain if experience 
has shown that this test separates good performing aggregates from bad performing 
aggregates.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Coarse aggregate shall consist of sound, tough, durable particles, free from films of material that would prevent 
thorough coating and bonding with the asphalt material and free from organic matter and other deleterious substances.  
[Steel slag may be used.  ]The coarse aggregate particles shall meet the following requirements:</TXT><BRK/>
<BRK/>
<LST>a.  The percentage of loss shall not be greater than 30 percent after 500 revolutions when tested in 
accordance with <RID>ASTM C 131</RID>.</LST><BRK/>
<BRK/>
<LST>b.  The percentage of loss shall not be greater than 18 percent after five cycles when tested in accordance 
with <RID>ASTM C 88</RID> using magnesium sulfate.</LST><BRK/>
<BRK/>
<LST>c.  At least 100 percent by weight of coarse aggregate shall have at least two or more fractured faces 
when tested in accordance with <RID>COE CRD-C 171</RID>.  Fractured faces shall be produced by crushing.</LST><BRK/>
<BRK/>
<LST>d.   The particle shape shall be essentially cubical and the aggregate shall not contain more than 20 
percent, by weight, of flat and elongated particles (3:1 ratio of maximum to minimum) and no more than 
5 percent, by weight, of flat and elongated particles (5:1 ratio of maximum to minimum) when tested in 
accordance with <RID>ASTM D 4791</RID>.</LST><BRK/>
<BRK/>
<LST>e.   The maximum absorption shall not be greater than 2 percent when tested in accordance with <RID>ASTM C 127</RID>
.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.2   Fine Aggregate</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The lower limit for uncompacted void content (requirement c., below) 
should be set at 45 for fine aggregate angularity unless local experiences indicate 
that a lower value can be used.  There are some aggregates which have a good 
performance record and have an uncompacted void content less than 45.  In no 
case should the limit be set less than 43.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Fine aggregate shall consist of clean, sound, tough, durable particles.  The aggregate particles shall be free 
from coatings of clay, silt, or any objectionable material and shall contain no clay balls.  The fine aggregate 
particles shall meet the following requirements:</TXT><BRK/>
<BRK/>
<LST>a.   The fine aggregate portion of the blended aggregate shall be 100 percent crushed manufactured fines.</LST><BRK/>
<BRK/>
<LST>b.   The individual fine aggregate sources shall have a sand equivalent value greater than 45 when tested 
in accordance with <RID>ASTM D 2419</RID>.</LST><BRK/>
<BRK/>
<LST>c.   The fine aggregate portion of the blended aggregate shall have an uncompacted void content greater 
than 45.0 percent when tested in accordance with <RID>ASTM C 1252</RID> Method A.</LST><BRK/>
<BRK/>
<LST>d.   Aggregate shall be non-plastic, with a Liquid Limit of 25 percent maximum when tested in accordance 
with <RID>ASTM D 4318</RID>.</LST><BRK/>
<BRK/>
<LST>e.   The maximum absorption shall not be greater than 2 percent when tested in accordance with <RID>ASTM C 128</RID>
.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.3   Mineral Filler</TTL><BRK/>
<BRK/>
<TXT>Mineral filler shall be non-plastic material meeting the requirements of <RID>ASTM D 242</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4   Aggregate Gradation</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Generally, the layer thickness should be at least 50 mm (2 inches).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The combined aggregate gradation shall conform to gradations specified in Table 5, when tested in accordance 
with <RID>ASTM C 136</RID> and <RID>ASTM C 117</RID>, and shall not vary from the low limit on one sieve to the high limit on the adjacent 
sieve or vice versa, but grade uniformly from coarse to fine.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>Table 5 Aggregate Gradations</HL4><BRK/>
<BRK/>
                                         Percent Passing<BRK/>
                 Sieve Size, mm             by Mass<BRK/></THD>
<BRK/>
                       25.0                   ---<BRK/>
                       19.0                   100<BRK/>
                  12.5                90-100<BRK/>
                        9.5                 50-85<BRK/>
                        4.7                 20-40<BRK/>
                        2.36                16-28<BRK/>
                        1.18                  -<BRK/>
                        0.60                  -<BRK/>
                        0.30                  -<BRK/>
                        0.15                  -<BRK/>
                        0.075                8-11<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>Table 5 Aggregate Gradations</HL4><BRK/>
<BRK/>
                                         Percent Passing<BRK/>
                 Sieve Size, inch           by Mass<BRK/></THD>
<BRK/>
                       1                     ---<BRK/>
                       3/4                   100<BRK/>
                  1/2                90-100<BRK/>
                       3/8                 50-85<BRK/>
                      No. 4                20-40<BRK/>
                      No. 8                16-28<BRK/>
                      No. 16                 -<BRK/>
                      No. 30                 -<BRK/>
                      No. 50                 -<BRK/>
                      No. 100                -<BRK/>
                      No. 200               8-11</TBL></ENG><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.5   <SUB>Fiber Stabilizer</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Fibers, either cellulose or mineral, must be used in the SMA mixture.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The stabilizer can be cellulose or mineral fibers.  Requirements and test procedures are outlined in Tables 6 
and 7.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2   <SUB>ASPHALT CEMENT BINDER</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Performance Graded (PG) asphalt binders should be specified wherever 
available.  Select the same grade PG binder used by the local highway agency 
for that area (e.g., the grade typically specified in that specific location 
for dense graded mixes on highways with design ESALs less than 10 million).  
Bump (increase) the high temperature grade two grades higher and this should 
be the grade of asphalt cement used for the project.  The exception would be 
that grades with a low temperature higher than PG XX 22 should not be used (e.g. 
PG XX 16 or PG XX 10), unless the Engineer has had successful experience with 
them.  The Engineer may lower the low temperature grade to comply with the recommendations 
of the FHWA's software program "LTPPBind," if it is believed to be appropriate.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Asphalt cement binder shall conform to <RID>AASHTO M 320</RID>, Performance Grade [_____].  [As An alternate,<RID>ASTM D 3381</RID>
 Table 2, Viscosity Grade [______] or <RID>ASTM D 946</RID> Penetration Grade  [______] may be used].  Test data indicating 
grade certification shall be provided by the supplier at the time of delivery of each load to the mix plant.  
Copies of these certifications shall be submitted to the Contracting Officer.  The supplier is defined as the 
last source of any modification to the binder.  The Contracting Officer/Engineer may sample and test the binder 
at the mix plant at any time before or during mix production.  Samples for this verification testing shall be 
obtained by the Contractor in accordance with <RID>ASTM D 140</RID> and in the presence of the Contracting Officer.  These 
samples shall be furnished to the Contracting Officer for the verification testing, which shall be at no cost 
to the Contractor.</TXT><BRK/>
<TBL><THD><BRK/>
<HL4>Table 6 Cellulose Fibers Quality Requirements</HL4><BRK/>
<BRK/>
                Properties                         Requirement<BRK/></THD>
<BRK/>
Sieve Analysis<BRK/>
   Method A<BRK/>
Alpine Sieve(1) Analysis<BRK/>
Fiber length                             6 mm (0.25 inch)  (max)<BRK/>
Passing 150 micron (No. 100) sieve       70 percent (± 10%)<BRK/>
<BRK/>
   Method B<BRK/>
Mesh Screen(2) Analysis<BRK/>
Fiber length                             6 mm (0.25 inch)  (max)<BRK/>
Passing 850 micron (No. 20) sieve        85 percent (± 10%)<BRK/>
        425 micron (No. 40) sieve        65 percent (± 10%)<BRK/>
        106 micron (No. 140) sieve       30 percent (± 10%)<BRK/>
<BRK/>
Ash Content(3)                           18 percent (± 5%) non-<BRK/>
                                         volatiles<BRK/>
pH(4)                                    7.5 (± 1.0)<BRK/>
Oil Absorption(5)                        5.0 (± 1.0)(times fiber weight)<BRK/>
Moisture Content(6)                      &lt;5% (by weight)<BRK/>
<BRK/>
(1) This test is performed using an Alpine Air Jet Sieve (Type 200 LS).  A representative 5-gram sample of fiber 
is sieved for 14 minutes at a controlled vacuum of<MET> 75 kPa</MET><ENG> 11 psi</ENG>.  The portion remaining on the screen is weighed.<BRK/>
<BRK/>
(2) This test is performed using standard<MET> 850, 425, 250, 180, 150, 106 micron</MET><ENG> No. 20, 40, 60, 80, 100, 140</ENG> sieves, 
nylon brushes, and a shaker.  A representative 10-gram sample of fiber is sieved using a shaker and two nylon brushes 
on each screen.  The amount retained on each sieve is weighed and the percentage passing calculated.  The repeatability 
of this method is suspect and needs to be verified.<BRK/>
<BRK/>
(3) A representative 2-3 gram sample of fiber is placed in a tared crucible and heated between<MET> 595 and 650 degrees 
C</MET><ENG> 1100 and 1200 degrees F</ENG> for not less than 2 hours.  The crucible and ash are cooled in a desiccator and reweighed.<BRK/>
<BRK/>
(4) Five grams of fiber is added to 100 mL of distilled water, stirred, and let sit for 30 minutes.  The pH is determined 
with a probe calibrated with pH 7.0 buffer.<BRK/>
<BRK/>
(5) Five grams of fiber is accurately weighed and suspended in an excess of mineral spirits for not less than 5 minutes 
to ensure total saturation.  It is then placed in a screen mesh strainer (approximately 0.5 square millimeter hole 
size) and shaken on a wrist-action shaker for 10 minutes (approximately<MET> 31.75 mm</MET><ENG> 1 1/4 inch</ENG> motion at 240 shakes/minute).  
The shaken mass is then transferred without touching, to a tared container and weighed.  Results are reported as 
the amount (number of times its own weight) the fibers are able to absorb.<BRK/>
<BRK/>
(6) Ten grams of fiber is weighed and placed in a<MET> 121 degree C</MET><ENG> 250 degrees F</ENG> forced-air oven for 2 hours.  The sample 
is then reweighed immediately upon removal from the oven.<BRK/></TBL>
<TBL><THD><BRK/>
<HL4>Table 7 Mineral Fibers Quality Requirements</HL4><BRK/>
<BRK/>
            Properties                          Requirement<BRK/></THD>
<BRK/>
     Sieve Analysis<BRK/>
     Fiber length(1)               6 mm (0.25 inch) max mean test value<BRK/>
     Thickness(2)                  0.005 mm (0.0002 inch) max mean test value<BRK/>
     Shot content(3)<BRK/>
     250 micron (No. 60) sieve     95 percent passing (min)<BRK/>
     63 micron (No. 230) sieve     65 percent passing (min)<BRK/>
<BRK/>
(1) The fiber length is determined according to the Baur McNett fractionation.<BRK/>
<BRK/>
(2) The fiber diameter is determined by measuring at least 200 fibers in a phase contract microscope.<BRK/>
<BRK/>
(3) Shot content is a measure of non-fibrous material.  The shot content is determined on vibrating sieves.  Two 
sieves, No. 60 and No. 230, are typically utilized; for additional information see <RID>ASTM C 612</RID>.</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3   <SUB>MIX DESIGN</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select bracketed AASHTO Superpave compaction test methods for vehicle 
pavement.  Select bracketed Asphalt Institute Marshall compaction test methods 
for airfield pavement.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Develop the mix design.  The asphalt mix shall be composed of a mixture of coarse and fine aggregate, mineral 
filler, a stabilizer, and asphalt material.  The aggregate fractions shall be sized, handled in separate size 
groups, and combined in such proportions that the resulting mixture meets the grading requirements of the job 
mix formula (JMF).  No SMA for payment shall be produced until a JMF has been approved.  The SMA shall be designed 
using [<RID>AASHTO M 325</RID>, <RID>AASHTO R 46</RID>, and <RID>AASHTO T 312</RID>] [hand-held Marshall Hammer procedures contained in <RID>AI MS-02</RID>
] and meeting the criteria shown in Table 8.  The aggregate quality requirements given in this specification 
shall be used instead of those given in <RID>AASHTO M 325</RID>.  If the Tensile Strength Ratio (TSR) of the composite mixture, 
as determined by <RID>ASTM D 4867/D 4867M</RID>, is less than 75, the aggregate stripping tendencies shall be countered 
by the use of hydrated lime or by treating the bitumen with an approved antistripping agent as furnished by the 
Contractor.  The hydrated lime will be considered as mineral filler and will be considered in the gradation requirements.  
The amount of hydrated lime or antistripping agent added to the bitumen will be determined during development 
of the JMF and will be sufficient to produce a TSR greater than 75 percent.  Use of additional antistripping 
agent may be directed during the progress of work, if necessary.  Provide an anti-strip agent, if required, at 
no additional cost.  Sufficient materials to produce<MET> 90 kg</MET><ENG> 200 pounds</ENG> of blended mixture shall be provided to 
the Contracting Officer for verification of mix design at least 14 days prior to construction of test section.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.3.1   JMF Requirements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  In Table 9, use a 50 blow (compactive effort) Marshall Mix for all SMA 
pavements.  If the JMF is designed using the hand-held Marshall Hammer according 
to AI MS-02, delete element t, as given below.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Submit the job mix formula in writing, for approval, at least 14 days prior to the start of the test section 
including as a minimum:</TXT><BRK/>
<BRK/>
<LST>a.   Percent passing each sieve size.</LST><BRK/>
<LST>b.   Percent of asphalt cement.</LST><BRK/>
<LST>c.   Percent of each aggregate and mineral filler to be used.</LST><BRK/>
<LST>d.   Asphalt viscosity grade, penetration grade, or performance grade.</LST><BRK/>
<LST>e.   Type and amount of stabilizer.</LST><BRK/>
<LST>f.   Laboratory mixing temperature.</LST><BRK/>
<LST>g.   Lab compaction temperature.</LST><BRK/>
<LST>h.   Temperature-viscosity relationship of the asphalt cement.</LST><BRK/>
<LST>i.   Plot of the combined gradation on the 0.45 power gradation chart, stating the nominal maximum size.</LST><BRK/>
<LST>j.   Specific gravity and absorption of each aggregate.</LST><BRK/>
<LST>k.   Percent particles with one and two or more fractured faces (in coarse aggregate).</LST><BRK/>
<LST>l.   Fine aggregate angularity.</LST><BRK/>
<LST>m.   Percent flat or elongated particles (in coarse aggregate).</LST><BRK/>
<LST>n.   Tensile Strength Ratio (TSR).</LST><BRK/>
<LST>o.   Antistrip agent (if required) and amount.</LST><BRK/>
<LST>p.   List of all modifiers and amount.</LST><BRK/>
<LST>q.   Percent draindown of mixture.</LST><BRK/>
<LST>r.   Dry-rodded-in-the coarse aggregate (VCADRC).</LST><BRK/>
<LST>s.   Voids-in-the coarse aggregate mixture (VCAMix).</LST><BRK/>
<LST>t.   Number of revolutions of SGC compactor.</LST><BRK/>
<TBL><THD><BRK/>
<HL4>Table 8 SMA Mix Design Criteria</HL4><BRK/>
<BRK/>
               Test Property                         50 Blow Mix<BRK/></THD>
<BRK/>
Air voids, percent                                    3.0-4.0<BRK/>
Percent Voids in mineral aggregate (minimum)          17.0(1)<BRK/>
Tensile Strength Ratio (TSR), minimum percent              75<BRK/>
Draindown, percent (maximum)                          0.3 (1 hour reading)(2)<BRK/>
<BRK/>
(1) Calculate VMA in accordance with <RID>AI MS-02</RID>, based on <RID>ASTM D 2726</RID> bulk specific gravity for the aggregate.<BRK/>
<BRK/>
(2) Calculate Draindown in accordance with <RID>ASTM D 6390</RID> determination of draindown characteristics in uncompacted 
asphalt mixtures.</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.2   Adjustments to JMF</TTL><BRK/>
<BRK/>
<TXT>The JMF for each mixture shall be in effect until a new formula is approved in writing by the Contracting Officer.  
Should a change in sources of any materials be made, a new mix design shall be performed and a new JMF approved 
before the new material is used.  The Contractor will be allowed to adjust the JMF within the limits specified 
below in Table 5 to optimize mix volumetric properties.  If adjustments are needed that exceed these limits, 
a new mix design shall be developed.  Tolerances given above may permit the aggregate grading to be outside the 
limits shown in Table 1; this is acceptable.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>Table 9 Job Mix Tolerances</HL4><BRK/>
<BRK/>
                     Material                    Tolerance, Plus or Minus<BRK/></THD>
<BRK/>
Aggregate passing 4.75 mm or larger sieves             3 percent<BRK/>
Aggregate passing 2.36 mm or smaller sieves            2 percent<BRK/>
Asphalt cement                                         0.25 percent<BRK/>
Temperature of mixing                                  14 degrees C<BRK/>
<BRK/></TBL>
</MET><TBL><THD><BRK/>
<HL4>Table 9 Job Mix Tolerances</HL4><BRK/>
<BRK/>
                     Material                    Tolerance, Plus or Minus<BRK/></THD>
<BRK/>
Aggregate passing No. 4 or larger sieves               3 percent<BRK/>
Aggregate passing No. 8 or smaller sieves              2 percent<BRK/>
Asphalt cement                                         0.25 percent<BRK/>
Temperature of mixing                                  25 degrees F</TBL><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   <SUB>CONTRACTOR QUALITY CONTROL</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The Contractor may be able to meet the specified quality control requirements 
with in house capability or may have to hire a material testing firm to provide 
the required quality control testing.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.1.1   General Requirements</TTL><BRK/>
<BRK/>
<TXT>Develop an approved Quality Control Plan.  SMA for payment shall not be produced until the quality control plan 
has been approved.  Address in the plan all elements which affect the quality of the pavement including, but 
not limited to:</TXT><BRK/>
<BRK/>
<LST>a.   Mix Design and unique JMF identification code.</LST><BRK/>
<LST>b.   Aggregate Grading.</LST><BRK/>
<LST>c.   Quality of Materials.</LST><BRK/>
<LST>d.   Stockpile Management and procedures to prevent contamination.</LST><BRK/>
<LST>e.   Proportioning.</LST><BRK/>
<LST>f.   Mixing and Transportation.</LST><BRK/>
<LST>g.   Mixture Volumetric.</LST><BRK/>
<LST>h.   Moisture Content of Mixtures.</LST><BRK/>
<LST>i.   Placing and Finishing.</LST><BRK/>
<LST>j.   Joints.</LST><BRK/>
<LST>k.   Compaction.</LST><BRK/>
<LST>l.   Surface Smoothness.</LST><BRK/>
<LST>m.   Truck Bed Release Agent</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2   Testing Laboratory</TTL><BRK/>
<BRK/>
<TXT>Provide a fully equipped asphalt laboratory, located at the plant or job site, equipped with heating and air 
conditioning units to maintain a temperature of<MET> 24 degrees C ± 2.3 degrees C</MET><ENG> 75 degrees F ± 5 degrees F</ENG>.  Laboratory 
facilities shall be kept clean and all equipment shall be maintained in proper working condition.  The Contracting 
Officer shall be permitted unrestricted access to inspect the Contractor's laboratory facility, to witness quality 
control activities, and to perform any check testing desired.  The Contracting Officer will advise the Contractor 
in writing of any noted deficiencies concerning the laboratory facility, equipment, supplies, or testing personnel 
and procedures.  When the deficiencies are serious enough to adversely affect test results, the incorporation 
of the materials into the work shall be suspended immediately and will not be permitted to resume until the deficiencies 
are corrected.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3   Quality Control Testing</TTL><BRK/>
<BRK/>
<TXT>Perform all quality control tests applicable to these specifications as set forth in the Quality Control Program.  
The testing program shall include, but shall not be limited to, tests for the control of asphalt content, aggregate 
gradation, temperatures, aggregate moisture, moisture in the asphalt mixture, laboratory air voids, in-place 
density, grade and smoothness.  Develop a Quality Control Testing Plan as part of the Quality Control Program.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.3.1   Asphalt Content</TTL><BRK/>
<BRK/>
<TXT>A minimum of two tests to determine asphalt content will be performed per lot (a lot is defined in paragraph 
QUALITY ASSURANCE) by one of the following methods:  extraction method in accordance with <RID>ASTM D 2172</RID>, Method 
A or B, the ignition method in accordance with the <RID>ASTM D 6307</RID>, or the nuclear method in accordance with <RID>ASTM D 4125</RID>
, provided that each method is calibrated for the specific mix being used.  For the extraction method, the weight 
of ash, as described in <RID>ASTM D 2172</RID>, shall be determined as part of the first extraction test performed at the 
beginning of plant production; and as part of every tenth extraction test performed thereafter, for the duration 
of plant production.  The last weight of ash value obtained shall be used in the calculation of the asphalt content 
for the mixture.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.2   Gradation and Specific Gravity</TTL><BRK/>
<BRK/>
<TXT>Aggregate gradations shall be determined a minimum of twice per lot from mechanical analysis of recovered aggregate 
in accordance with <RID>ASTM D 5444</RID>.  When asphalt content is determined by the nuclear method, aggregate gradation 
shall be determined from hot bin samples on batch plants, or from the cold feed on drum mix plants.  For batch 
plants, aggregates shall be tested in accordance with <RID>ASTM C 136</RID> using actual batch weights to determine the 
combined aggregate gradation of the mixture.  The specific gravity of each aggregate size grouping shall be determined 
for each<MET> 18,000 metric tons</MET><ENG> 20,000 tons</ENG> in accordance with <RID>ASTM C 127</RID> and <RID>ASTM C 128</RID>.  All samples will be taken 
in accordance with <RID>ASTM D 75</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.3   Temperatures</TTL><BRK/>
<BRK/>
<TXT>Check temperatures at least four times per lot, at necessary locations, to determine the temperature at the dryer, 
the asphalt cement in the storage tank, the asphalt mixture at the plant, and the asphalt mixture at the job 
site.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.4   Moisture Contents</TTL><BRK/>
<BRK/>
<TXT>Determine the moisture content of aggregate used for production a minimum of once per lot in accordance with <RID>
ASTM C 566</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.5   Laboratory Air Voids</TTL><BRK/>
<BRK/>
<TXT>Take mixture samples at least four times per lot and compact them into specimens, using [50 blows per side with 
the hand-held Marshall hammer as described in <RID>AI MS-02</RID>] [the Superpave Gyratory Compactor as described in <RID>AASHTO T 312</RID>
].  After compaction, determine the laboratory air voids of each specimen.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.6   In-Place Density</TTL><BRK/>
<BRK/>
<TXT>Conduct any necessary testing to ensure the specified density is achieved.  A nuclear gauge may be used to monitor 
pavement density in accordance with <RID>ASTM D 2950</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.7   Grade and Smoothness</TTL><BRK/>
<BRK/>
<TXT>Conduct the necessary checks to ensure the grade and smoothness requirements are met in accordance with paragraphs 
PERCENT PAYMENT and QUALITY ASSURANCE.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.8   Additional Testing</TTL><BRK/>
<BRK/>
<TXT>Any additional testing, which the Contractor deems necessary to control the process, may be performed at the 
Contractor's option.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.9   <SUB>QC Monitoring</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit all QC test results to the Contracting Officer on a daily basis as the tests are performed.  The Contracting 
Officer reserves the right to monitor any of the Contractor's quality control testing and to perform duplicate 
testing as a check to the Contractor's quality control testing.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.1.4   Sampling</TTL><BRK/>
<BRK/>
<TXT>When directed by the Contracting Officer, sample and test any material which appears inconsistent with similar 
material being produced, unless such material is voluntarily removed and replaced or deficiencies corrected by 
the Contractor.  Perform all sampling in accordance with standard procedures specified.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.5   Control Charts</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If the JMF was designed according to AASHTO M 325, delete the requirements 
for plotting stability and flow.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>For process control, establish and maintain linear control charts on both individual samples and the running 
average of last four samples for the parameters listed in Table 10, as a minimum.  These control charts shall 
be posted as directed by the Contracting Officer and shall be kept current at all times.  The control charts 
shall identify the project number, the test parameter being plotted, the individual sample numbers, the Action 
and Suspension Limits listed in Table 10 applicable to the test parameter being plotted, and the Contractor's 
test results.  Target values from the JMF shall also be shown on the control charts as indicators of central 
tendency for the cumulative percent passing, asphalt content, and laboratory air voids parameters.  When the 
test results exceed either applicable Action Limit, take immediate steps to bring the process back in control.  
When the test results exceed either applicable Suspension Limit, halt production until the problem is solved.  
Use the control charts as part of the process control system for identifying trends so that potential problems 
can be corrected before they occur.  Decisions concerning mix modifications shall be made based on analysis of 
the results provided in the control charts.  The Quality Control Plan shall indicate the appropriate action, 
which shall be taken to bring the process into control when certain parameters exceed their Action Limits.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>Table 10 Action and Suspension Limits for the Parameters to be Plotted on Individual and Running Average Control 
Charts</HL4><BRK/>
<BRK/>
                                                          Running Average of<BRK/>
                                     Individual Samples   Last Four Samples<BRK/>
                                     Action  Suspension   Action  Suspension<BRK/>
   Parameter to be Plotted           Limit     Limit      Limit      Limit<BRK/></THD>
<BRK/>
4.75 mm sieve, Cumulative Percent      4         5          3          4<BRK/>
Passing, deviation from JMF target;<BRK/>
plus or minus values<BRK/>
<BRK/>
0.6 mm sieve, Cumulative Percent       3         4          2          3<BRK/>
Passing, deviation from JMF target;<BRK/>
plus or minus values<BRK/>
<BRK/>
Asphalt content, percent deviation     0.4       0.5        0.2        0.3<BRK/>
from JMF target; plus or minus values<BRK/>
<BRK/>
Laboratory Air Voids, percent          No specific action and suspension<BRK/>
deviation from JMF target value        limits set since this parameter is<BRK/>
                                       used to determine percent payment<BRK/>
<BRK/>
In-place Mat Density, percent of       No specific action and suspension<BRK/>
maximum theoretical density            limits set since this parameter is<BRK/>
                                       used to determine percent payment<BRK/>
<BRK/>
In-place Joint Density, percent of     No specific action and suspension<BRK/>
maximum theoretical density            limits set since this parameter is<BRK/>
                                       used to determine percent payment<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>Table 10 Action and Suspension Limits for the Parameters to be Plotted on Individual and Running Average Control 
Charts</HL4><BRK/>
<BRK/>
                                                          Running Average of<BRK/>
                                     Individual Samples   Last Four Samples<BRK/>
                                     Action  Suspension   Action  Suspension<BRK/>
   Parameter to be Plotted           Limit     Limit      Limit      Limit<BRK/></THD>
<BRK/>
No. 4 sieve, Cumulative Percent        4         5          3          4<BRK/>
Passing, deviation from JMF target;<BRK/>
plus or minus values<BRK/>
<BRK/>
No. 30 sieve, Cumulative Percent       3         4          2          3<BRK/>
Passing, deviation from JMF target;<BRK/>
plus or minus values<BRK/>
<BRK/>
Asphalt content, percent deviation     0.4       0.5        0.2        0.3<BRK/>
from JMF target; plus or minus values<BRK/>
<BRK/>
Laboratory Air Voids, percent          No specific action and suspension<BRK/>
deviation from JMF target value        limits set since this parameter is<BRK/>
                                       used to determine percent payment<BRK/>
<BRK/>
In-place Mat Density, percent of       No specific action and suspension<BRK/>
maximum theoretical density            limits set since this parameter is<BRK/>
                                       used to determine percent payment<BRK/>
<BRK/>
In-place Joint Density, percent of     No specific action and suspension<BRK/>
maximum theoretical density            limits set since this parameter is<BRK/>
                                       used to determine percent payment</TBL></ENG><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2   PREPARATION OF ASPHALT BINDER MATERIAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For Performance Graded (PG) asphalt cements, insert the plant temperature 
range from the Table below into the last sentence of the following paragraph.</NPR><BRK/>
<BRK/>
<TBL><THD><HL1><HL4>Performance Graded Asphalt Plant Mixing Temperatures</HL4></HL1></THD><BRK/>
<BRK/>
<HL1>Binder Grade</HL1>  <HL1> Mixing Temp Range (deg F)</HL1>   <HL1>Mixing Temp Range (deg C)</HL1><BRK/>
  PG 46-28            240 - 295                  115 - 146<BRK/>
  PG 46-34            240 - 295                  115 - 146<BRK/>
  PG 46-40            240 - 295                  115 - 146<BRK/>
  PG 52-28            240 - 300                  115 - 149<BRK/>
  PG 52-34            240 - 300                  115 - 149<BRK/>
  PG 52-40            240 - 300                  115 - 149<BRK/>
  PG 52-46            240 - 300                  115 - 149<BRK/>
  PG 58-22            260 - 310                  127 - 154<BRK/>
  PG 58-28            260 - 310                  127 - 154<BRK/>
  PG 58-34            260 - 310                  127 - 154<BRK/>
  PG 64-22            265 - 320                  129 - 160<BRK/>
  PG 64-28            265 - 320                  129 - 160<BRK/>
  PG 64-34            265 - 320                  129 - 160<BRK/>
  PG 67-22            275 - 325                  135 - 163<BRK/>
  PG 70-22            280 - 330                  138 - 166<BRK/>
  PG 70-28            275 - 325                  135 - 163<BRK/>
  PG 76-22            285 - 335                  141 - 168<BRK/>
  PG 76-28            280 - 330                  138 - 166<BRK/>
  PG 82-22            290 - 340                  143 - 171</TBL><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>A continuous supply of the asphalt cement material shall be supplied to the mixer at a uniform temperature.  
The method of heating shall avoid local overheating of the asphalt cement material.  The temperature of unmodified 
asphalts shall be no more than<MET> 160 degrees C</MET><ENG> 325 degrees F</ENG> when added to the aggregates.  Performance-Graded 
(PG) asphalts shall be within the temperature range of [_____] to [_____] degrees<MET> C</MET><ENG> F</ENG> when added to the aggregates.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3   PREPARATION OF MINERAL AGGREGATE</TTL><BRK/>
<BRK/>
<TXT>The aggregate for the mixture shall be heated and dried prior to mixing.  No damage shall occur to the aggregates 
due to the maximum temperature and rate of heating used.  The temperature of the aggregate and mineral filler 
shall not exceed<MET> 175 degrees C</MET><ENG> 350 degrees F</ENG> when the asphalt cement is added.  The temperature shall not be 
lower than is required to obtain complete coating and uniform distribution on the aggregate particles and to 
provide a mixture of satisfactory workability.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4   PREPARATION OF STONE MATRIX ASPHALT MIXTURE</TTL><BRK/>
<BRK/>
<TXT>The aggregates, stabilizer, and the asphalt cement shall be weighed or metered and introduced into the mixer 
in the amount specified by the JMF.  The combined materials shall be mixed until the aggregate and stabilizer 
obtain a uniform coating of asphalt binder and are thoroughly distributed throughout the mixture.  Wet mixing 
time shall be the shortest time that will produce a satisfactory mixture, but not less than 35 seconds for batch 
plants.  The wet mixing time for all plants shall be established by the Contractor, based on the procedure for 
determining the percentage of coated particles described in <RID>ASTM D 2489/D 2489M</RID>, for each individual plant and 
for each type of aggregate used.  The wet mixing time will be set to achieve a minimum of 95 percent coated particles.  
The moisture content of all SMA upon discharge from the plant shall not exceed 0.5 percent by total weight of 
mixture as measured by <RID>ASTM C 566</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5   PREPARATION OF THE UNDERLYING SURFACE</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  A SMA is used as a wearing or surface course overlying a conventional 
hot-mixed asphalt (HMA).  The existing HMA should be cleaned and tack-coated 
before placing the SMA.  Tack coat materials and procedures will need to be 
addressed in the contract documents.  See Section <SRF>32 12 10</SRF> BITUMINOUS TACK AND 
PRIME COATS.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Immediately before placing the SMA, the underlying course shall be cleaned of dust and debris.  A tack coat shall 
be applied in accordance with the contract specifications.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6   TEST SECTION</TTL><BRK/>
<BRK/>
<TXT>Before full production, place a test section for each JMF used.  Construct a minimum test section of<MET> [75] [150] 
meters</MET><ENG> [250] [500] feet</ENG> long and two paver passes wide placed in two lanes, with a longitudinal cold joint.  
The test section shall be of the same depth as the course which it represents.  The underlying grade or pavement 
structure, upon which the test section is to be constructed, shall be the same as the remainder of the course 
represented by the test section.  The equipment used in construction of the test section shall be the same equipment 
to be used on the remainder of the course represented by the test section.  Place the test section as part of 
the project pavement if approved by the Contracting Officer.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.6.1   Sampling and Testing for Test Section</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Table 11 applies only to the test section.  The limits in Tables 8, 9, 
and 10, apply to a number of tests run from a lot.  This is why the limits listed 
in Table 11 are different from those listed in Tables 8, 9, and 10.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>One random sample shall be taken at the plant, triplicate specimens compacted, and tested for density and laboratory 
air voids.  A portion of the same sample shall be tested for aggregate gradation and asphalt content.  Four randomly 
selected cores shall be taken from the finished pavement mat, and four from the longitudinal joint, and tested 
for density.  Random sampling shall be in accordance with procedures contained in <RID>ASTM D 3665</RID>.  The test results 
shall be within the tolerances shown in Table 11 for work to continue.  If all test results meet the specified 
requirements, the test section shall remain as part of the project pavement.  If test results exceed the tolerances 
shown, the test section shall be removed and replaced at no cost to the Government and another test section shall 
be constructed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.2   Additional Test Sections</TTL><BRK/>
<BRK/>
<TXT>If the initial test section should prove to be unacceptable, make the necessary adjustments to the JMF, plant 
operation, placing procedures, and/or rolling procedures.  A second test section shall then be placed.  Additional 
test sections, as required, shall be constructed and evaluated for conformance to the specifications.  Full production 
shall not begin until an acceptable section has been constructed and accepted.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.7   <SUB>TESTING LABORATORY</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include bracketed sentence for Corps-managed projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The laboratories used to develop the JMF, Perform CQC testing, and for Government acceptance testing shall meet 
the requirements of <RID>ASTM D 3666</RID>.  [The Government will inspect the laboratory equipment and test procedures prior 
to the start of hot-mix operations for conformance with <RID>ASTM D 3666</RID>.  The laboratory shall maintain this validation 
for the duration of the project.]  A certification stating that it meets these requirements or clearly listing 
all deficiencies shall be signed by the manager of the laboratory and submitted to the Contracting Officer prior 
to the start of construction.  The certification shall contain as a minimum:</TXT><BRK/>
<BRK/>
<LST>a.  Qualifications of personnel:  laboratory manager, supervising technician, and testing technicians.</LST><BRK/>
<BRK/>
<LST>b.  A listing of equipment to be used in developing the job mix.</LST><BRK/>
<BRK/>
<LST>c.  A copy of the laboratory's quality control system.</LST><BRK/>
<BRK/>
<LST>d.  Evidence of participation in the AASHTO Materials Reference Laboratory (AMRL) program.</LST><BRK/>
<TBL><THD><BRK/>
<HL4>Table 11 Material and Mixture Proportions for Test Section</HL4><BRK/>
<BRK/>
                    Property                        Specification Limit<BRK/></THD>
<BRK/>
Aggregate Gradation-Percent Passing <BRK/>
(Individual Test Result)<BRK/>
  4.75 mm and larger                                       JMF ± 5.0<BRK/>
  2.36 mm and smaller                                      JMF ± 3.0<BRK/>
<BRK/>
Asphalt Content, Percent (Individual Test Result)          JMF ± 0.5<BRK/>
<BRK/>
Laboratory Air Voids, Percent (Average of 3 specimens)     JMF ± 1.0<BRK/>
<BRK/>
VMA, Percent (Average of 3 specimens)                      17.0 minimum<BRK/>
<BRK/>
Mat Density, Percent of Maximum Theoretical<BRK/>
Density (Average of 4 Random Cores)                        92.0 - 96.0<BRK/>
<BRK/>
Joint Density, Percent of Maximum Theoretical<BRK/>
Density (Average of 4 Random Cores)                        90.5 - 92.5</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8   TRANSPORTING AND PLACING</TTL><BRK/>
<BRK/>
<SPT><TTL>3.8.1   Transporting</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  A material transfer vehicle has been shown to provide a pavement with 
improved smoothness and less segregation.  A material transfer vehicle is required 
when doing runway construction.  Remove last sentence if material transfer vehicle 
is not used.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Transport the SMA from the mixing plant to the site in clean, tight vehicles.  Schedule deliveries so that placing 
and compacting of mixture is uniform with minimum stopping and starting of the paver.  Provide adequate artificial 
lighting for night placements.  Hauling over freshly placed material will not be permitted until the material 
has been compacted as specified, and allowed to cool to<MET> 60 degrees C</MET><ENG> 140 degrees F</ENG>.  To deliver mix to the paver, 
use a material transfer vehicle which is operated to produce continuous forward motion of the paver.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.2   Placing</TTL><BRK/>
<BRK/>
<TXT>Place and compact the mix at a temperature suitable for obtaining density, surface smoothness, and other specified 
requirements.  Upon arrival, the mixture shall be placed to the full width by an asphalt paver; it shall be struck 
off in a uniform layer of such depth that, when the work is completed, it shall have the required thickness and 
conform to the grade and contour indicated.  The speed of the paver shall be regulated to eliminate pulling and 
tearing of the asphalt mat.  Unless otherwise permitted, placement of the mixture shall begin along the centerline 
of a crowned section or on the high side of areas with a one-way slope.  The mixture shall be placed in consecutive 
adjacent strips having a minimum width of 3 meters [10 feet].  The longitudinal joint of the SMA course shall 
be offset from the longitudinal joint in the course immediately below by at least<MET> 300 mm</MET><ENG> 1 foot</ENG>; however, the 
joint in the surface course shall be at the centerline of the pavement.  Transverse joints in the SMA course 
shall be offset by at least<MET> 3 meters</MET><ENG> 10 feet</ENG> from transverse joints in the previous course.  Transverse joints 
in adjacent lanes shall be offset a minimum of<MET> 3 meters</MET><ENG> 10 feet</ENG>.  On isolated areas where irregularities or unavoidable 
obstacles make the use of mechanical spreading and finishing equipment impractical, the mixture may be spread 
and luted by hand tools.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.9   COMPACTION OF MIXTURE</TTL><BRK/>
<BRK/>
<TXT>After placing, the mixture shall be thoroughly and uniformly compacted by rolling with steel-wheel rollers.  
The surface shall be compacted as soon as possible without causing displacement, cracking or shoving.  The sequence 
of rolling operations and the type of rollers used (with the exception noted) shall be at the discretion of the 
Contractor, with the exception that the Contractor shall not apply more than three passes with a vibratory roller 
in the vibrating mode.  The speed of the roller shall, at all times, be sufficiently slow to avoid displacement 
of the hot mixture and be effective in compaction.  Any displacement occurring as a result of reversing the direction 
of the roller, or from any other cause, shall be corrected at once.  Sufficient rollers shall be furnished to 
handle the output of the plant.  Rolling shall continue until the surface is of uniform texture, true to grade 
and cross section, and the required field density is obtained.  To prevent adhesion of the mixture to the roller, 
the wheels shall be kept properly moistened, but excessive water will not be permitted.  In areas not accessible 
to the roller, the mixture shall be thoroughly compacted with hand tampers.  Any mixture that becomes loose and 
broken, mixed with dirt, contains check-cracking, or is in any way defective shall be removed full depth, replaced 
with fresh hot mixture and immediately compacted to conform to the surrounding area.  This work shall be done 
at the Contractor's expense.  Skin patching will not be allowed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10   JOINTS</TTL><BRK/>
<BRK/>
<TXT>The formation of joints shall be made ensuring a continuous bond between the courses and to obtain the required 
density.  All joints shall have the same texture as other sections of the course and meet the requirements for 
smoothness and grade.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.10.1   Transverse Joints</TTL><BRK/>
<BRK/>
<TXT>The roller shall not pass over the unprotected end of the freshly laid mixture, except when necessary to form 
a transverse joint.  When necessary to form a transverse joint, it shall be made by means of placing a bulkhead 
or by tapering the course.  The tapered edge shall be cut back to its full depth and width on a straight line 
to expose a vertical face prior to placing the adjacent lane.  The cutback material shall be removed from the 
project.  In both methods, all contact surfaces shall be given a light tack coat of asphalt material before placing 
any fresh mixture against the joint.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2   Longitudinal Joints</TTL><BRK/>
<BRK/>
<TXT>Longitudinal joints that are irregular, damaged, uncompacted, cold (less than<MET> 80 degrees C</MET><ENG> 175 degrees F</ENG> at the 
time of placing the adjacent lane), or otherwise defective, shall be cut back a maximum of<MET> 75 mm</MET><ENG> 3 inches</ENG> from 
the edge with a cutting wheel to expose a clean, sound vertical surface for the full depth of the course.  All 
cutback material shall be removed from the project.  All contact surfaces shall be given a light tack coat of 
asphalt material prior to placing any fresh mixture against the joint.  The Contractor will be allowed to use 
an alternate method if it can be demonstrated that density, smoothness, and texture can be met.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT>   <END/><BRK/></SEC>