<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><BRK/>
<HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA            UFGS-01 22 00.00 10 (April 2006)<BRK/>
                                          --------------------------------<BRK/>
Preparing Activity:  <PRA>USACE</PRA>  (CW)          Replacing without change<BRK/>
                                          UFGS-01270A (February 1994)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 01 22 00.00 10</SCN><BRK/>
<BRK/>
<STL>MEASUREMENT AND PAYMENT</STL><BRK/>
<DTE>04/06</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification provides an example of the appropriate form 
to be used in developing a project specification covering <SCP>lump sum schedule 
payment items and unit price schedule payment items</SCP>.  This section is recommended 
to be included in all Civil Works projects.  Parts of this section are shown 
for illustration purposes only and the section must be extensively edited to 
fit the job.</NPR><BRK/>
<BRK/>
<NPR>Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.</NPR><BRK/>
<BRK/>
<NPR>Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification.  The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
<BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
<BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM A 615/A 615M</RID><RTL>(2008b) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement</RTL><BRK/><BRK/><RID>ASTM C 127</RID><RTL>(2007) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate</RTL><BRK/><BRK/><RID>ASTM C 128</RID><RTL>(2007a) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Fine Aggregate</RTL><BRK/><BRK/><RID>ASTM D 1250</RID><RTL>(2007) Standard Guide for Use of the Petroleum Measurement Tables</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy, Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for [Contractor Quality Control approval.][information only.  When used, a designation following the "G" 
designation identifies the office that will review the submittal for the Government.]  The following shall be 
submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Weight Certificates</SUB></ITM><BRK/>
<BRK/>
<ITM>  Submit certified weight certificates for<MET> M 90</MET><ENG> R 200</ENG> Riprap.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   LUMP SUM PAYMENT ITEMS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The number and identification of lump sum payment items is primarily 
a Construction Division concern.  Generally, it is better to keep the number 
of lump sum payment items to a minimum.  The description of the work included 
in a payment item is unique for each job and must be developed for each construction 
contract.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Payment items for the work of this contract for which contract lump sum payments will be made are listed in the 
BIDDING SCHEDULE and described below.  All costs for items of work, which are not specifically mentioned to be 
included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most 
closely associated with the work involved.  The lump sum price and payment made for each item listed shall constitute 
full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor 
quality control, environmental protection, meeting safety requirements, tests and reports, and for performing 
all work required for which separate payment is not otherwise provided.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Mobilization and Demobilization</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If mobilization and demobilization costs are expected to be a minor cost 
under the contract, this clause and payment item should be deleted.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.3.1.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with mobilization and demobilization, as defined in Special Clause 
PAYMENT FOR MOBILIZATION AND DEMOBILIZATION.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.2   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure:  lump sum.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.3.2   Structure No. 1</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.2.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with operations necessary for construction of the structure at Station 
XX+XX.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.2   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure:  lump sum.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.3.3   Structure No. 2</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.3.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with operations necessary for construction of the structure at Station 
YY+YY.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.3.2   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure:  lump sum.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>1.4   UNIT PRICE PAYMENT ITEMS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Unit price payment items should be used only where appropriate under 
the guidance of Federal Acquisition Regulation (FAR) Part 36 - Construction 
and Architect-Engineer Contracts paragraph 36.207.</NPR><BRK/>
<BRK/>
<NPR>The Unit Price payment items shown below are for illustration purposes only.  
Unit price payment item language must be written specifically for each job.   
Unit price payment item language appropriate for inclusion below is contained 
in guide specification sections and must be moved to this section to develop 
the pay items for the project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Payment items for the work of this contract on which the contract unit price payments will be made are listed 
in the BIDDING SCHEDULE and described below.  The unit price and payment made for each item listed shall constitute 
full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor 
quality control, environmental protection, meeting safety requirements, tests and reports, and for performing 
all work required for each of the unit price items.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.4.1   Excavation</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Since there is no UFGS Guide Specification for Civil Works "Excavation", 
this example was taken from a job specification.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.4.1.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with excavation for the channel and for the structure, which includes 
performing required excavation and other operations incidental thereto, Contractor-furnished disposal area(s) 
and disposition of excess excavated material and unsuitable and frozen materials.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.1.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>The total quantity of excavated material for which payment will be made will be the theoretical quantity between 
the ground surface as determined by a survey and the grade and slope of the theoretical cross sections indicated.  
No allowance will be made for overdepth excavation or for the removal of any material outside the required slope 
lines unless authorized.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.1.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure:  cubic<MET> meter</MET><ENG> yard</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4.2   <MET>M 90</MET><ENG>R 200</ENG> Riprap</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This example was taken from Section 35 31 19 STONE, CHANNEL, SHORELINE/COASTAL 
PROTECTION FOR STRUCTURES.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.4.2.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with furnishing, transporting, stockpiling (if applicable), placing, 
and constructing the stone protection as specified.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.2.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Riprap will be measured for payment by the ton<MET> (metric)</MET><ENG> (2,000 pounds)</ENG> by weighing each truckload to the nearest 
0.1 ton, and the final quantity of [each truckload] [the whole sum] will be rounded to the nearest whole ton.  
The riprap will be measured for payment by being weighed on approved scales before being placed in the work.  
Quarry weights will not be accepted.  Scales shall be of sufficient length to permit simultaneous weighing all 
axle loads and shall be inspected, tested and sealed as directed to assure accuracy with 0.5 percent throughout 
the range of the scales.  The scales, located at the site of the work, shall be certified as to accuracy by an 
acceptable scales company representative prior to weighing any riprap.  Scales will be checked and certified 
before riprap hauling and rechecked and recertified whenever a variance is suspected.  The Contractor shall furnish 
the scales.  If commercial scales are readily available in close proximity<MET> 15 kilometers</MET><ENG> 10 miles</ENG> of site of 
work, the Contracting Officer may approve the use of the scales.  The riprap shall be weighed in the presence 
of the  Government representative.  The Contracting Officer may elect to accept certified <SUB>weight certificates</SUB>
 furnished by a public weighmaster in lieu of scale weights at the jobsite.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.2.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure:  ton<MET> (metric)</MET><ENG> (2,000 pounds)</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4.3   Deformed Steel Bars for Concrete Reinforcement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This example was taken from Section 03 20 02 STEEL BARS AND WELDED WIRE 
FABRIC FOR CONCRETE.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.4.3.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with furnishing, transporting, delivering, and placing deformed steel 
bars for concrete reinforcement, which includes steel in laps as indicated or as required.  No payment will be 
made for the additional steel in laps which are authorized for the convenience of the Contractor.  No separate 
payment will be made for accessories and payment shall be included in the contract unit price for the items of 
work to which the accessories are incidental.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.3.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>The measured lengths of deformed steel bars for concrete reinforcement will be converted to weights for the size 
of bars listed by the use of the nominal weights per lineal<MET> meter</MET><ENG> foot</ENG> specified in <RID>ASTM A 615/A 615M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.3.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure:  per<MET> kilogram</MET><ENG> pound</ENG> in place.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4.4   Bituminous Base Course</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Paragraph UNIT PRICES of Section 32 11 26 BITUMINOUS BASE COURSE was 
edited to develop this example.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.4.4.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with bituminous base course, which includes preparing and reconditioning 
the underlying layer, and other incidentals necessary to complete the work required by Section <SRF>32 11 26</SRF> BITUMINOUS 
BASE COURSE.  No payment will be made for defective areas until corrected.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.4.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Bituminous Base Course will be measured for payment based upon the number of tons<MET> (metric)</MET><ENG> (2,000 pounds)</ENG> of 
bituminous mixture used in the accepted work.  Bituminous mixture shall be weighed after mixing, and no deductions 
will be made for the weight of bituminous material incorporated in the mix.  Quantities of paving mixtures called 
for in bid schedule are based on aggregates having a specific gravity of 2.65 as determined according to apparent 
specific gravity paragraphs in <RID>ASTM C 127</RID> and <RID>ASTM C 128</RID>.  Correction in the tonnage of bituminous base course 
mixtures shall be made to compensate for the difference in the tonnage of mixtures used in the project, when 
specific gravities of aggregates used are more than 2.70 and less than 2.60.  The tonnage paid for shall be the 
number of tons used, proportionately corrected for specific gravities using 2.65 as the base correctional factor.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.4.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure:  ton<MET> (metric)</MET><ENG> (2,000 pounds)</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4.5   Bituminous Materials</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Paragraph UNIT PRICES of Section 32 11 26 BITUMINOUS BASE COURSE was 
edited to develop this example.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.4.5.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with bituminous materials.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.5.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Bituminous materials will be measured for payment based upon the number of [<MET>liters</MET><ENG> gallons</ENG> of the material used 
in the accepted work, corrected to [_____]<MET> liters</MET><ENG> gallons</ENG> at<MET> 15 degrees C</MET><ENG> 60 degrees F</ENG> in accordance with <RID>ASTM D 1250</RID>
.][tons<MET> (metric)</MET><ENG> 2,000 pounds</ENG> of the material used in the accepted work.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.5.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure: [<MET>liters</MET><ENG> gallons</ENG>][ tons<MET> (metric)</MET><ENG> (2,000 pounds)</ENG>].</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT></PRT><PRT><TTL>PART 2   PRODUCTS  (Not Applicable)</TTL><BRK/>
<BRK/></PRT>
<PRT><TTL>PART 3   EXECUTION (Not Applicable)</TTL><BRK/>
<BRK/></PRT>
    <END/><BRK/></SEC>