<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><BRK/>
<HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA                UFGS-01 57 23 (April 2008)<BRK/>
                                              --------------------------<BRK/>
Preparing Activity:  <PRA>USACE</PRA> (CW)               Superseding<BRK/>
                                              UFGS-01 57 23 (January 2008)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 01 57 23</SCN><BRK/>
<BRK/>
<STL>TEMPORARY STORM WATER POLLUTION CONTROL</STL><BRK/>
<DTE>04/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTES:  This specification covers the requirements for <SCP>temporary construction 
measures most used in complying with the Best Management Practices of the storm 
water pollution prevention plan as required by a NPDES Permit</SCP>.</NPR><BRK/>
<BRK/>
<NPR>Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.</NPR><BRK/>
<BRK/>
<NPR>Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.<BRK/>
<BRK/>
This guide specification includes tailoring options for LANTDIV.  Selection 
or deselection of a tailoring option will include or exclude that option in 
the section, but editing the resulting section to fit the project is still required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification must be tailored to meet the requirements of 
the job and of the permitting authority.  Individual states may require prevention 
measures that differ from the ones specified in this section and, in that case, 
this guide specification will be tailored to meet those State requirements.  
This guide specification is required for all construction projects that include 
disturbing over 2 hectares (5 acres) of land surface area that could be a source 
for erosion and sediment pollution due to storm water runoff.</NPR><BRK/>
<BRK/>
<NPR>(1)  A Notice of Intent (NOI) will be prepared and sent to the appropriate state 
licensing office or USEPA Regional Office.  At this time, it has not been determined 
when to send in the NOI, but it will be done after preparation of a storm water 
pollution prevention plan, and perhaps after award of the contract because the 
names of the Contractors must be give on the NOI.</NPR><BRK/>
<BRK/>
<NPR>(2)  After construction is completed, a Notice of Termination (NOT) will be 
sent to the state office or Regional USEPA Regional Office.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification.  The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.</NPR><BRK/>
<BRK/>
<NPR>Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.</NPR><BRK/>
<BRK/>
<NPR>References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM D 4439</RID><RTL>(2004) Geosynthetics</RTL><BRK/><BRK/><RID>ASTM D 4491</RID><RTL>(1999a; R 2004e1) Water Permeability of Geotextiles by Permittivity</RTL><BRK/><BRK/><RID>ASTM D 4533</RID><RTL>(2004) Trapezoid Tearing Strength of Geotextiles</RTL><BRK/><BRK/><RID>ASTM D 4632</RID><RTL>(2008) Grab Breaking Load and Elongation of Geotextiles</RTL><BRK/><BRK/><RID>ASTM D 4751</RID><RTL>(2004) Determining Apparent Opening Size of a Geotextile</RTL><BRK/><BRK/><RID>ASTM D 4873</RID><RTL>(2002) Identification, Storage, and Handling of Geosynthetic Rolls and Samples</RTL><BRK/><BRK/></REF><REF><ORG>U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)</ORG><BRK/><BRK/><RID>EPA 832-R-92-005</RID><RTL>(1992) Storm Water Management for Construction Activities Developing Pollution Preventions and Plans and Best Management Practices</RTL><BRK/><BRK/></REF><REF><ORG>U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)</ORG><BRK/><BRK/><RID>40 CFR 122.26</RID><RTL>Storm Water Discharges (Applicable to State NPDES Programs, see section 123.25)</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   SYSTEM DESCRIPTION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Current studies indicate contaminants bind to soil particles and can 
be carried with the eroded soils into streams.  The intent of this specification 
is to prevent sediment from entering streams or water bodies adjacent to construction 
sites.  The Contracting Officer, when necessary, should provide information 
to the Contractor emphasizing the need for source and sediment controls.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The work consists of implementing the storm water pollution prevention measures to prevent sediment from entering 
streams or water bodies as specified in this Section in conformance with the requirements of Section 
<SRF>01 57 20.00 10</SRF> ENVIRONMENTAL PROTECTION, and the requirements of the National Pollution Discharge Elimination 
System (NPDES) permit attached to that Section.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   <SUB>EROSION AND SEDIMENT CONTROLS</SUB></TTL><BRK/>
<BRK/>
<TXT>The controls and measures required of the Contractor are described below.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Stabilization Practices</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Describe interim stabilization practices, including site-specific scheduling 
of the implementation of the practices.  Plans should ensure that existing vegetation 
is preserved where attainable and disturbed areas are stabilized.  Show locations 
for stabilization practices on the drawings.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The stabilization practices to be implemented include [temporary seeding,] [mulching,] [geotextiles,] [sod stabilization,] 
[vegetative buffer strips,] [erosion control matts,] [protection of trees,] [preservation of mature vegetation,] 
[etc].  On the daily CQC Report, record the dates when the major grading activities occur, (e.g., [clearing] 
[and grubbing,] [excavation,] [embankment,] [and] [grading]); when construction activities temporarily or permanently 
cease on a portion of the site; and when stabilization practices are initiated.  Except as provided in paragraphs 
UNSUITABLE CONDITIONS and NO ACTIVITY FOR LESS THAN 21 DAYS, initiate stabilization practices as soon as practicable, 
but no more than 14 days, in any portion of the site where construction activities have [temporarily or] permanently 
ceased.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.3.1.1   Unsuitable Conditions</TTL><BRK/>
<BRK/>
<TXT>Where the initiation of stabilization measures by the fourteenth day after construction activity [temporarily 
or] permanently ceases or is precluded by unsuitable conditions caused by the weather, initiate stabilization 
practices as soon as practicable after conditions become suitable.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.2   No Activity for Less Than 21 Days</TTL><BRK/>
<BRK/>
<TXT>When the total time period in which construction activity is temporarily ceased on a portion of the site is [21] 
[_____] days minimum, stabilization practices do not have to be initiated on that portion of the site until 14 
days have elapsed after construction activity temporarily ceased.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.3   Burnoff</TTL><BRK/>
<BRK/>
<TXT>Burnoff of the ground cover is not permitted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.4   Protection of Erodible Soils</TTL><BRK/>
<BRK/>
<TXT>Immediately finish the earthwork brought to a final grade, as indicated or specified, and protect the side slopes 
and back slopes upon completion of rough grading.  Plan and conduct earthwork to minimize the duration of exposure 
of unprotected soils.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.3.2   Erosion, Sediment and Stormwater Control</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For projects located in Virginia where 10,000 or more square feet of 
land area are disturbed, choose the paragraph below.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  [Submit "Erosion and Sediment Controls" (E&amp;S) (form provided at the pre-construction conference) 
[and <SUB>Storm Water Inspection Reports for General Permit</SUB>] to the Contracting Officer once every 7 calendar 
days and within 24 hours of a storm event that produces<MET> 12 mm</MET><ENG> 0.5 inch</ENG> or more of rain.]</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For projects located in North Carolina where 1 or more acres (0.4 hectares) 
of land area are disturbed, choose the paragraph below and delete paragraph, 
Storm Water Notice of Intent for Construction Activities.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>b.  [Submit "Erosion and Sediment Control Reports" (E&amp;S) (form provided at the pre-construction conference) 
and "Stormwater Inspections for General Permit NCG010000 - Land Disturbing Activities" (form provided 
at <URL HREF="http://h2o.enr.state.nc.us/su/PDF_Files/SW_General_Permits/NCG01_Inspect_log.pdf">http://h2o.enr.state.nc.us/su/PDF_Files/SW_General_Permits/NCG01_Inspect_log.pdf)</URL> to the Contracting 
Officer once every 7 days and within 24 hours of a storm event that produces 0.5 inch or more of rain.]</LST><BRK/>
<BRK/>
<LST>c.  [Comply with NCG010000, North Carolina Permit to Discharge Storm Water under the National Pollutant 
Discharge Elimination System.  The existing permit may be obtained from:  <URL HREF="http://h2o.enr.state.nc.us/su/PDF_Files/SW_General_Permits/NCG01_Inspect_log.pdf">http://h20.enr.state.nc.us/su/PDF_Files/SW_General_Permits/NCG01_Inspect_log.pdf</URL>
.]</LST><BRK/>
<BRK/>
<LST>d.  Storm Water Notice of Intent for Construction Activities</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use paragraph "e" when 0.4 or more hectares (1 or more acres) of total 
land area are to be disturbed during the construction.  This requirement is 
the Federal EPA standard.  Some States are more stringent; e.g., South Carolina 
EPA standards invoke these requirements for construction sites disturbing any 
land area within 0.8 kilometer (1/2 mile) of a receiving water body in the Coastal 
Zone.  Verify if the requirements of this paragraph are applicable for land 
area less than the Federal EPA standard by checking with the EPA of the State 
where the project is located.  Edit the text accordingly. </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>e.  Submit a <SUB>Storm Water Notice of Intent</SUB> for NPDES coverage under the general permit for construction 
activities and a <SUB>Storm Water Pollution Prevention Plan</SUB> (SWPPP) for the project to the Contracting Officer 
prior to the commencement of work.  The SWPPP shall meet the requirements of the [EPA][State of [_____]] 
general permit for storm water discharges from construction sites.  Submit the SWPPP along with any required 
Notice of Intents, Notice of Termination, and appropriate permit fees, via the Contracting Officer, to 
the appropriate [Federal][State] agency for approval, a minimum of 14 calendar days prior to the start 
of any land disturbing activities.  Maintain an approved copy of the SWPPP at the construction on-site 
office, and continually update as regulations require, to reflect current site conditions.  Include within 
the SWPPP:</LST><BRK/>
<BRK/>
<ITM>(1)  Identify potential sources of pollution which may be reasonably expected to affect the 
quality of storm water discharge from the site.</ITM><BRK/>
<BRK/>
<ITM>(2)  Describe and ensure implementation of practices which will be used to reduce the pollutants 
in storm water discharge from the site.</ITM><BRK/>
<BRK/>
<ITM>(3)  Ensure compliance with terms of the [EPA][State of [_____]] general permit for storm water 
discharge.</ITM><BRK/>
<BRK/>
<ITM>(4)  Select applicable best management practices from EPA 832-R-92-005.</ITM><BRK/>
<BRK/>
<ITM>(5)  Include a completed copy of the Registration Statement, BMP Inspection Report Template 
and Notice of Termination except for the effective date.</ITM><BRK/>
<BRK/>
<ITM>[(6)  Storm Water Pollution Prevention Measures and Notice of Intent <RID>40 CFR 122.26</RID>, <RID>EPA 832-R-92-005</RID>
.  Provide a "Storm Water Pollution Prevention Plan" (SWPPP) for the project.  The SWPPP will 
meet the requirements of the [EPA][State of [_____]] general permit for storm water discharges 
from construction sites.  Submit the SWPPP along with any required Notice of Intents, Notice 
of Termination, and appropriate permit fees, via the Contracting Officer, to the appropriate 
[Federal][State] agency for approval, a minimum of 14 calendar days prior to the start of construction.  
A copy of the approved SWPPP will be kept at the construction on-site office, and continually 
updated as regulations require to reflect current site conditions.]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For projects located in Virginia where 1 or more acres (0.4 hectares) 
of land area are disturbed during construction, use the following paragraph 
instead of the above item in addition to items (a) thorough (e).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[(7)  Storm Water Pollution Prevention Measures and Notice of Intent 40 CFR 122.26, EPA 832-R-92-005.  
Provide a "Storm Water Pollution Prevention Plan" (SWPPP) for the project.  The SWPPP will meet 
the requirements of the State of Virginia general permit for storm water discharges from construction 
activities.  Submit the SWPPP to the Contracting Officer for review, approval and signature 
a minimum of 15 days prior to the start of any land disturbing activities.  Maintain an approved 
copy of the SWPPP at the construction on-site office, and continually update as regulations 
require, to reflect current site conditions.]</ITM><BRK/>
<BRK/>
<ITM>(8)  Following SWPPP approval, submit Registration Statement and appropriate permit fees to 
the Virginia Department of Conservation and Recreation (DCR) before any land disturbing activities 
begin.  Coverage under the permit begins on the day the Registration Statement and fee are: 
(1) post marked by mail, (2) registered online at the DCR's website, or (3) hand delivered to 
the DCR office.  The Contractor is responsible for all associated fees; contact DCR to determine 
applicable fees.</ITM><BRK/>
<BRK/>
<ITM>(9)  Install, inspect, and maintain best management practices (BMPs) as required by the general 
permit.  Prepare and submit to DCR, BMP Inspection Reports as required by the general permit.</ITM><BRK/>
<BRK/>
<ITM>(10)  Once construction is complete and the site has been stabilized with a final, sustainable 
cover, submit the Notice of Termination to DCR within 30 days after all land disturbing activities 
end.</ITM><BRK/>
<BRK/>
<TAI OPT="LANTDIV"><ITM>(11)  At the time of submittal to DCR, concurrently forward copies of the SWPPP, Registration 
Statement, BMP Inspection Reports, and Notice of Termination to the Contracting Officer, and 
to Mid-Atlantic Environmental at:  Commander, Naval Facilities Engineering Command, MIDLANT, 
Code: EV2, 9742 Maryland Avenue, Norfolk, VA 23511-3095.</ITM></TAI><BRK/>
<BRK/>
<ITM>(12)  Information on the permit application, SWPPP requirements, Registration Statement, BMP 
Inspection Reports, and Notice of Termination can be found in the Virginia Permit Regulation 
9 VAC 25-180.  The Registration Statement, Notice of Termination, and permit fee forms can be 
found on the DCR website <URL HREF="http://www.dcr.state.va.us/sw/vsmp.htm">http://www.dcr.state.va.us/sw/vsmp.htm</URL>.  This website also contains 
the permit regulations and information on how to obtain coverage online.</ITM><BRK/>
<BRK/>
<ITM>(13)  Once construction is complete and the site has been stabilized with a final, sustainable 
cover, submit the Notice of Termination to DCR within 30 days after all land disturbing activities 
end.</ITM><BRK/>
<BRK/></SPT>
<TAI OPT="LANTDIV"><SPT><TTL>1.3.3   Stormwater Drainage</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use this paragraph for Norfolk Naval Shipyard projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>There will be no discharge of excavation ground water to the sanitary sewer, storm drains, or to the river without 
prior specific authorization of the Environmental Programs Division in writing.  Discharge of hazardous substances 
will not be permitted under any circumstances.  Construction site runoff will be prevented from entering any 
storm drain or the river directly by the use of straw bales or other method suitable to the Environmental Programs 
Division of the Shipyard.  Provide erosion protection of the surrounding soils.</TXT><BRK/>
<BRK/></SPT>
</TAI><SPT><TTL>1.3.4   Structural Practices</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTES:  Describe structural practices to divert flows from exposed soils, store 
flows, or otherwise limit runoff and the discharge of pollutants from exposed 
areas of the site to the degree attainable.  A permit under Section 404 of the 
Clean Water Act may be required for certain structural practices.  Check with 
Permits Branch.</NPR><BRK/>
<BRK/>
<NPR>For common drainage locations that serve a disturbed area of 4 or more hectares 
(10 or more acres) at one time, provide a temporary or permanent detention basin 
providing 252 cubic meters of storage per hectare (3,600 cubic feet of storage 
per acre) drained, or equivalent control measures, where attainable until stabilization 
of the site.  The 252 cubic meters of storage per hectare (3,600 cubic feet 
of storage per acre) drained does not apply to flows from offsite areas and 
flows from onsite areas that are either undisturbed or have undergone final 
stabilization where such flows are diverted around the sediment basin.  For 
drainage locations which serve a disturbed area of 4 or more hectares (10 or 
more acres) at one time and where a temporary sediment basin providing 252 cubic 
meters of storage per hectare (3,600 cubic feet of storage per acre) drained, 
or equivalent sediment controls, is not attainable, sediment controls are required 
for all sideslope and downslope boundaries of the construction area.</NPR><BRK/>
<BRK/>
<NPR>For drainage locations serving less than 4 hectares (10 acres), sediment traps, 
silt fences, or equivalent sediment controls are required for all sideslope 
and downslope boundaries of the construction area unless a sediment basin providing 
storage for 252 cubic meters of storage per hectare (3,600 cubic feet of storage 
per acre) drained is provided.</NPR><BRK/>
<BRK/>
<NPR>Listed are examples of typical structural devices.  Requirements for Silt Fences, 
Straw Bales, and Diversion Dikes are contained within this Guide Specification.  
Add specifications for other structural practices used in the project to this 
section.</NPR><BRK/>
<BRK/>
<NPR>a.  Silt fences.</NPR> <BRK/>
<NPR>b.  Straw bales.</NPR><BRK/>
<NPR>c.  Diversion dikes.</NPR><BRK/>
<NPR>d.  Drainage swales.</NPR><BRK/>
<NPR>e.  Check dams.</NPR><BRK/>
<NPR>f.  Subsurface drains.</NPR><BRK/>
<NPR>g.  Pipe Slope drains.</NPR><BRK/>
<NPR>h.  Level spreaders.</NPR><BRK/>
<NPR>i.  Storm drain inlet protection.</NPR><BRK/>
<NPR>j.  Rock outlet protection.</NPR><BRK/>
<NPR>k.  Sediment traps.</NPR><BRK/>
<NPR>l.  Reinforced soil retaining systems.</NPR><BRK/>
<NPR>m.  Gabions.</NPR><BRK/>
<NPR>n.  Sediment basins.</NPR><BRK/>
<BRK/>
<NPR>The permanent stabilization practices which are to be installed under the contract 
should be specified in other section of the specifications.  These are measures 
that will be installed during the construction process to control pollutants 
in storm water discharges that will occur after construction operations have 
been completed.  Structural measures should be placed on upland soils to the 
degree attainable.  The installation of these devices may be subject to Section 
404 of the Clean Water Act.</NPR><BRK/>
<BRK/>
<NPR>A goal of 80 percent removal of total suspended solids from these flows which 
exceed predevelopment levels should be used in designing and installing storm 
water management controls (where practicable).  Where this goal is not met, 
the permittee must provide justification for rejecting each practice listed 
above based on site conditions.</NPR><BRK/>
<BRK/>
<NPR>Place velocity dissipation devices at discharge locations and along the length 
of any outfall channel as necessary to provide a non-erosive velocity flow from 
the structure to a water course so that the natural physical and biological 
characteristics and functions are maintained and protected.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Implement structural practices to divert flows from exposed soils, temporarily store flows, or otherwise limit 
runoff and the discharge of pollutants from exposed areas of the site.  Implement structural practices in a timely 
manner, during the construction process, to minimize erosion and sediment runoff.  Include the following devices;  
[Location and details of installation and construction are shown on the drawings.]</TXT><BRK/>
<BRK/>
<SPT>[<TTL>1.3.4.1   Silt Fences</TTL><BRK/>
<BRK/>
<TXT>Provide silt fences as a temporary structural practice to minimize erosion and sediment runoff.  Properly install 
silt fences to effectively retain sediment immediately after completing each phase of work where erosion would 
occur in the form of sheet and rill erosion (e.g. clearing and grubbing, excavation, embankment, and grading).  
Install silt fences in the locations indicated on the drawings.  Obtain approval from the Contracting Officer 
prior to final removal of silt fence barriers.</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>1.3.4.2   Straw Bales</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  EPA may not recommend the use of straw bales in certain rugged locations 
because bales do not easily conform to the ground contours.  Other materials 
like fiber or coier rolls should be investigated.</NPR><BRK/>
<BRK/>
<NPR>For item d. below, space rows a maximum of 60 meters (200 feet) apart in drains 
with slopes equal to or less than 5 percent and 30 meters (100 feet) apart in 
drains with slopes steeper than 5 percent.  If drainage ditches have slopes 
above and below the 5 percent limit the spacing should be shown on the drawings.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide [bales of straw] [_____] as a temporary structural practice to minimize erosion and sediment runoff.  
If bales are used, properly place the bales to effectively retain sediment immediately after completing each 
phase of work (e.g., clearing and grubbing, excavation, embankment, and grading) in each independent runoff area 
(e.g., after clearing and grubbing in a area between a ridge and drain, place the bales as work progresses, remove/replace/relocate 
the bales as needed for work to progress in the drainage area).  Show on the drawings areas where straw bales 
are to be used.  The Contracting Officer will approve the final removal of straw bale barriers.  Provide rows 
of bales of straw as follows:</TXT><BRK/>
<BRK/>
<LST>a.  Along the downhill perimeter edge of all areas disturbed.</LST><BRK/>
<BRK/>
<LST>b.  Along the top of the slope or top bank of drainage ditches, channels, swales, etc. that traverse 
disturbed areas.</LST><BRK/>
<BRK/>
<LST>c.  Along the toe of all cut slopes and fill slopes of the construction areas.</LST><BRK/>
<BRK/>
<LST>d.  Perpendicular to the flow in the bottom of existing drainage ditches, channels, swales, etc. that 
traverse disturbed areas or carry runoff from disturbed areas.  Space the rows [a maximum of [_____]<MET> 
meters</MET><ENG> feet</ENG> apart] [as shown on the drawings].</LST><BRK/>
<BRK/>
<LST>e.  Perpendicular to the flow in the bottom of new drainage ditches, channels, and swales.  Space the 
rows [a maximum of [_____]<MET> m</MET><ENG> feet</ENG> apart] [as shown on the drawings].</LST><BRK/>
<BRK/>
<LST>f.  At the entrance to culverts that receive runoff from disturbed areas.</LST><BRK/>
<BRK/>
<LST>g.  [_____].</LST><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>1.3.4.3   Diversion Dikes</TTL><BRK/>
<BRK/>
<TXT>Build diversion dikes with a maximum channel slope of 2 percent and adequately compacted to prevent failure.  
The minimum height measured from the top of the dike to the bottom of the channel shall be<MET> 0.5 m</MET><ENG> 18 inches</ENG>.  
The minimum base width shall be<MET> 1.8 m</MET><ENG> 6 feet</ENG> and the minimum top width shall be<MET> 0.6 m</MET><ENG> 2 feet</ENG>.  Ensure that the 
diversion dikes are not damaged by construction operations or traffic.  Locate diversion dikes where shown on 
the drawings.</TXT><BRK/>
<BRK/>
]</SPT></SPT><SPT><TTL>1.3.5   Sediment Basins</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The appropriate design-year storm is determined by the downstream environment 
to be protected.  In the event permanent sediment basins are necessary for the 
particular project, these permanent facilities will be included in the project 
design and included as part of the contract documents.  If permanent basins 
are not required, delete reference thereto.  For natural environments, the following 
general guidelines should be followed:</NPR><BRK/>
<TBL><THD><BRK/>
               <HL1>Downstream Environment</HL1>             <HL1>Design-Year Storm</HL1><BRK/></THD>
<BRK/>
               Dry wash or areas without<BRK/>
               significant vegetation                     0-1<BRK/>
<BRK/>
               Seasonal creek or highly<BRK/>
               vegetative areas                           10<BRK/>
<BRK/>
               Stream, river, estuary, or<BRK/>
               other open waters                          25<BRK/>
<BRK/>
               Lake, reservoir, harbor, bay,<BRK/>
               or other closed waters                     50</TBL><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Trap sediment in [temporary] [permanent] sediment basins.  Select a basin size to accommodate the runoff of a 
local [_____]-year storm.  Pump dry and remove the accumulated sediment, after each storm.  Use a paved weir 
or vertical overflow pipe for overflow.  Remove collected sediment from the site.  Institute effluent quality 
monitoring programs.  Install, inspect, and maintain best management practices (BMPs) as required by the general 
permit.  Prepare BMP Inspection Reports as required by the general permit.  If required by the permit, include 
those inspection reports.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.6   Vegetation and Mulch</TTL><BRK/>
<BRK/>
<LST>a.  Provide temporary protection on sides and back slopes as soon as rough grading is completed or sufficient 
soil is exposed to require erosion protection.  Protect slopes by accelerated growth of permanent vegetation, 
temporary vegetation, mulching, or netting.  Stabilize slopes by hydroseeding, anchoring mulch in place, 
covering with anchored netting, sodding, or such combination of these and other methods necessary for 
effective erosion control.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Indicate section number and title in blank below using proper format 
per UFC 1-300-02.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>b.  Seeding:  Provide new seeding where ground is disturbed.  Include topsoil or nutriment during the 
seeding operation necessary to [establish] [reestablish] a suitable stand of grass.  [The seeding operation 
will be as specified in Section <SRF>32 92 19</SRF> SEEDING.]</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section <SRF>01 33 00</SRF> SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.</NPR><BRK/>
<BRK/>
<NPR>A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.</NPR><BRK/>
<BRK/>
<NPR>For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy, Air Force, 
and NASA projects.</NPR><BRK/>
<BRK/>
<NPR>Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for [Contractor Quality Control approval.] [information only.  When used, a designation following the "G" 
designation identifies the office that will review the submittal for the Government.]  Submit the following in 
accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-01 Preconstruction Submittals</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Storm Water Pollution Prevention Plan</SUB></ITM><BRK/>
<ITM><SUB>Storm Water Notice of Intent</SUB></ITM><BRK/>
<BRK/>
<ITM>  Pollution prevention plan and Notice of intent for NPDES coverage under the general permit 
for construction activities</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Storm Water Inspection Reports for General Permit</SUB></ITM><BRK/>
<ITM><SUB>Erosion and Sediment Controls</SUB></ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Mill Certificate or Affidavit</SUB></ITM><BRK/>
<BRK/>
<ITM>  Certificate attesting that the Contractor has met all specified requirements.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5   DELIVERY, STORAGE, AND HANDLING</TTL><BRK/>
<BRK/>
<TXT>Identify, store and handle filter fabric in accordance with <RID>ASTM D 4873</RID>.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   COMPONENTS FOR SILT FENCES</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.1   Filter Fabric</TTL><BRK/>
<BRK/>
<TXT>Provide geotextile that complies with the requirements of  <RID>ASTM D 4439</RID>, and consists of polymeric filaments which 
are formed into a stable network such that filaments retain their relative positions.  The filament shall consist 
of a long-chain synthetic polymer composed of at least 85 percent by weight of ester, propylene, or amide, and 
contains stabilizers and/or inhibitors added to the base plastic to make the filaments resistent to deterioration 
due to ultraviolet and heat exposure.  Provide synthetic filter fabric that contains ultraviolet ray inhibitors 
and stabilizers to assure a minimum of six months of expected usable construction life at a temperature range 
of<MET> -18 to plus 49 degrees C</MET><ENG> 0 to 120 degrees F</ENG>.  The filter fabric shall meet the following requirements:</TXT><BRK/>
<MET><BRK/>
<TBL>                        FILTER FABRIC FOR SILT SCREEN FENCE<BRK/>
<BRK/>
PHYSICAL PROPERTY           TEST PROCEDURE         STRENGTH REQUIREMENT<BRK/>
<BRK/>
Grab Tensile                 <RID>ASTM D 4632</RID>               445 N min.<BRK/>
Elongation (percent)                                         30 percent max.<BRK/>
<BRK/>
Trapezoid Tear               <RID>ASTM D 4533</RID>               245 N min.<BRK/>
<BRK/>
Permittivity                 <RID>ASTM D 4491</RID>                 0.2 sec-1<BRK/>
<BRK/>
AOS (U.S. Std Sieve)         <RID>ASTM D 4751</RID>                 20-100<BRK/></TBL>
</MET><ENG><BRK/>
<TBL>                        FILTER FABRIC FOR SILT SCREEN FENCE<BRK/>
<BRK/>
PHYSICAL PROPERTY           TEST PROCEDURE         STRENGTH REQUIREMENT<BRK/>
<BRK/>
Grab Tensile                 <RID>ASTM D 4632</RID>             100 lbs. min.<BRK/>
Elongation (percent)                                          30 percent max.<BRK/>
<BRK/>
Trapezoid Tear               <RID>ASTM D 4533</RID>              55 lbs. min.<BRK/>
<BRK/>
Permittivity                 <RID>ASTM D 4491</RID>                  0.2 sec-1<BRK/>
<BRK/>
AOS (U.S. Std Sieve)         <RID>ASTM D 4751</RID>                  20-100</TBL></ENG><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.2   Silt Fence Stakes and Posts</TTL><BRK/>
<BRK/>
<TXT>Use either wooden stakes or steel posts for fence construction.  Wooden stakes utilized for silt fence construction, 
shall have a minimum cross section of<MET> 50 by 50 mm</MET><ENG> 2 by 2 inches</ENG> when oak is used and<MET> 100 by 100 mm</MET><ENG> 4 by 4 inches</ENG>
 when pine is used, and have a minimum length of<MET> 1.5 m</MET><ENG> 5 feet</ENG>.  Steel posts (standard "U" or "T" section) utilized 
for silt fence construction, shall have a minimum<MET> mass of 1.98 kg/linear meter</MET><ENG> weight of 1.33 pounds/linear foot</ENG>
 and a minimum length of<MET> 1.5 m</MET><ENG> 5 feet</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.3   <SUB>Mill Certificate or Affidavit</SUB></TTL><BRK/>
<BRK/>
<TXT>Provide a mill certificate or affidavit attesting that the fabric and factory seams meet chemical, physical, 
and manufacturing requirements specified above.  Specify in the mill certificate or affidavit the actual Minimum 
Average Roll Values and identify the fabric supplied by roll identification numbers.  Submit a mill certificate 
or affidavit signed by a legally authorized official from the company manufacturing the filter fabric.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2   COMPONENTS FOR STRAW BALES</TTL><BRK/>
<BRK/>
<TXT>The straw in the bales shall be stalks from oats, wheat, rye, barley, rice, or from grasses such as byhalia, 
bermuda, etc., furnished in air dry condition.  Provide bales with a standard cross section of<MET> 350 by 450 mm</MET><ENG> 
14 by 18 inches</ENG>.  Wire-bound or string-tie all bales.  Use either wooden stakes or steel posts to secure the 
straw bales to the ground.  Wooden stakes utilized for this purpose, shall have a minimum dimensions of<MET> 50 by 
50 mm</MET><ENG> 2 by 2 inches</ENG> in cross section and have a minimum length of<MET> 1 m</MET><ENG> 3 feet</ENG>.  Steel posts (standard "U" or "T" 
section) utilized for securing straw bales, shall have a minimum<MET> mass of 1.98 kg/linear meter</MET><ENG> weight of 1.33 
pounds/linear foot</ENG> and a minimum length of<MET> 1 m</MET><ENG> 3 feet</ENG>.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Additional execution topics such as the requirements for a contractor 
to take rain gage measurements; detail record keeping on the contractors inspection 
of its BMPs and repairs; the ability to allow the DPW to get the COE to assess 
fines using liquidated damages, etc. may be added when necessary.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.1   INSTALLATION OF SILT FENCES</TTL><BRK/>
<BRK/>
<TXT>Extend silt fences a minimum of<MET> 400 mm</MET><ENG> 16 inches</ENG> above the ground surface without exceeding<MET> 860 mm</MET><ENG> 34 inches</ENG> 
above the ground surface.  Provide filter fabric from a continuous roll cut to the length of the barrier to avoid 
the use of joints.  When joints are unavoidable, splice together filter fabric at a support post, with a minimum<MET>
 150 mm</MET><ENG> 6 inch</ENG> overlap, and securely sealed.  Excavate trench approximately<MET> 100 mm</MET><ENG> 4 inches</ENG> wide and<MET> 100 mm</MET><ENG> 4 
inches</ENG> deep on the upslope side of the location of the silt fence.  The<MET> 100 by 100 mm</MET><ENG> 4 by 4 inch</ENG> trench shall 
be backfilled and the soil compacted over the filter fabric.  Remove silt fences upon approval by the Contracting 
Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2   INSTALLATION OF STRAW BALES</TTL><BRK/>
<BRK/>
<TXT>Place the straw bales in a single row, lengthwise on the contour, with ends of adjacent bales tightly abutting 
one another.  Install straw bales so that bindings are oriented around the sides rather than along the tops and 
bottoms of the bales in order to prevent deterioration of the bindings.  Entrench and backfill the barrier.  
Excavate a trench the width of a bale and the length of the proposed barrier to a minimum depth of<MET> 100 mm</MET><ENG> 4 inches</ENG>
.  After the bales are staked and chinked (gaps filled by wedging with straw), backfill the excavated soil against 
the barrier.  Conform the backfill soil with the ground level on the downhill side and build up to<MET> 100 mm</MET><ENG> 4 inches</ENG>
 against the uphill side of the barrier.  Scatter loose straw over the area immediately uphill from a straw bale 
barrier to increase barrier efficiency.  Securely anchor each bale by at least two stakes driven through the 
bale.  Drive the first stake or steel post in each bale toward the previously laid bale to force the bales together.  
Drive stakes or steel pickets a minimum<MET> 450 mm</MET><ENG> 18 inches</ENG> deep into the ground to securely anchor the bales.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3   FIELD QUALITY CONTROL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Describe the procedures to be followed during construction to maintain 
the vegetation, erosion and sediment control measures, and other protective 
measures in good and effective operating condition.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Maintain the temporary and permanent vegetation, erosion and sediment control measures, and other protective 
measures in good and effective operating condition by performing routine inspections to determine condition and 
effectiveness, by restoration of destroyed vegetative cover, and by repair of erosion and sediment control measures 
and other protective measures.  Use the following procedures to maintain the protective measures.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Silt Fence Maintenance</TTL><BRK/>
<BRK/>
<TXT>Inspect the silt fences in accordance with paragraph, titled "Inspections," of this section.  Any required repairs 
shall be made promptly.  Pay close attention to the repair of damaged silt fence resulting from end runs and 
undercutting.  Should the fabric on a silt fence decompose or become ineffective, and the barrier is still necessary, 
replace the fabric promptly.  Remove sediment deposits when deposits reach one-third of the height of the barrier.  
Remove a silt fence when it is no longer required.  The immediate area occupied by the fence and any sediment 
deposits shall be shaped to an acceptable grade.  The areas disturbed by this shaping shall [receive erosion 
control] [be seeded in accordance with Section <SRF>32 05 33</SRF> LANDSCAPE ESTABLISHMENT, except that the coverage requirements 
in paragraph, titled "Establishment" of this section do not apply].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.2   Straw Bale Maintenance</TTL><BRK/>
<BRK/>
<TXT>Inspect straw bale barriers in accordance with paragraph, titled "Inspections".  Pay close attention to the repair 
of damaged bales, end runs and undercutting beneath bales.  Accomplish necessary repairs to barriers or replacement 
of bales in a promptly manner.  Remove sediment deposits when deposits reach one-half of the height of the barrier.  
At the each end of each row turn bales uphill when used to retain sediment.  Remove a straw bale barrier when 
it is no longer required.  The immediate area occupied by the bales and any sediment deposits shall be shaped 
to an acceptable grade.  Seed the areas disturbed by this shaping in accordance with Section <SRF>32 92 19</SRF> SEEDING.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.3   Diversion Dike Maintenance</TTL><BRK/>
<BRK/>
<TXT>Inspect diversion dikes in accordance with paragraph, titled "Inspections," of this section.  Pay close attention 
to the repair of damaged diversion dikes and accomplish necessary repairs promptly.  When diversion dikes are 
no longer required, shape to an acceptable grade.  Seed the areas disturbed by this shaping in accordance with 
Section <SRF>32 92 19</SRF> SEEDING.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.4   INSPECTIONS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Currently some of the installations are assigned small MS4 permits which 
require them to develop, implement and enforce construction site inspections 
allowing enforcement on the Contractor for CWA violations.</NPR><BRK/>
<BRK/>
<NPR>In some cases it may be desirable to require the Contractor to inspect the BMPs 
before, during, and after a storm event.  By inspecting during a storm event, 
the Contractor can determine if the BMPs are actually working or whether they 
are being breached.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.4.1   General</TTL><BRK/>
<BRK/>
<TXT>Inspect disturbed areas of the construction site, areas that have not been finally stabilized used for storage 
of materials exposed to precipitation, stabilization practices, structural practices, other controls, and area 
where vehicles exit the site at least once every seven (7) calendar days and within 24 hours of the end of any 
storm that produces<MET> 13 mm</MET><ENG> 0.5 inches</ENG> or more rainfall at the site.  Conduct inspections at least once every month 
where sites have been finally stabilized.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2   Inspections Details</TTL><BRK/>
<BRK/>
<TXT>Inspect disturbed areas [and areas used for material storage that are exposed to precipitation] for evidence 
of, or the potential for, pollutants entering the drainage system.  Observe erosion and sediment control measures 
identified in the Storm Water Pollution Prevention Plan to ensure that they are operating correctly.  Inspect 
discharge locations or points to ascertain whether erosion control measures are effective in preventing significant 
impacts to receiving waters.  Inspect locations where vehicles exit the site for evidence of offsite sediment 
tracking.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.3   Inspection Reports</TTL><BRK/>
<BRK/>
<TXT>For each inspection conducted, prepare a report summarizing the scope of the inspection, name(s) and qualifications 
of personnel making the inspection, the date(s) of the inspection, major observations relating to the implementation 
of the Storm Water Pollution Prevention Plan, maintenance performed, and actions taken.  Furnish the report to 
the Contracting Officer within 24 hours of the inspection as a part of the Contractor's daily CQC REPORT.  A 
copy of the inspection report shall be maintained on the job site.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.4   [Monthly Inspection Report and Certification Form</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Some States require submittal of inspection reports to their respective 
agency.  If this is required in the state where the proposed project is located, 
the following example should be appropriately edited and included in the project 
specifications.  The designer should attach the appropriate state forms at the 
end of this section.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Complete, sign, and submit the original form, on the first working day of each month, to the State of [_____], 
[Office of Pollution Control (OPC)] at the following address:</TXT><BRK/>
<BRK/>
<LST>Chief, [_____]</LST><BRK/>
<BRK/>
<LST>[_____]</LST><BRK/>
<BRK/>
<LST>[_____]</LST><BRK/>
<BRK/>
<LST>[_____]</LST><BRK/>
<BRK/>
<TXT>A copy of the State of [_____]'s [Monthly Inspection Report and Certification Form for Erosion and Sediment Controls] 
is attached to the end of this section.  Also furnish, on the first working day of each month, one copy of the 
form submitted to the [OPC] to the Contracting Officer as part of the Contractor's daily CQC Report and attach 
a copy of the completed form to the Plan.  Unless otherwise notified by the <NED/>[OPC], submit the [Monthly Inspection 
Report and Certification Forms] for an additional two months after the final completion of all storm water pollution 
prevention measures required in this contract have been implemented.]</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT>    <END/><BRK/></SEC>