<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><BRK/>
<HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA                  UFGS-03 37 23 (April 2006)<BRK/>
                                                --------------------------<BRK/>
Preparing Activity:  <PRA>USACE</PRA> (CW)                 Replacing without change<BRK/>
                                                UFGS-03701 (January 2006)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 03 37 23</SCN><BRK/>
<BRK/>
<STL>ROLLER-COMPACTED CONCRETE FOR MASS CONCRETE CONSTRUCTION</STL><BRK/>
<DTE>04/06</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>furnishing, hauling, 
placing, and roller-compacting concrete for mass concrete construction</SCP>.</NPR><BRK/>
<BRK/>
<NPR>Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.</NPR><BRK/>
<BRK/>
<NPR>Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification.  The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
<BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
<BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ACI INTERNATIONAL (ACI)</ORG><BRK/><BRK/><RID>ACI 117</RID><RTL>(2006) Standard Specifications for Tolerances for Concrete Construction and Materials</RTL><BRK/><BRK/><RID>ACI 305R</RID><RTL>(1999; Errata 2006) Hot Weather Concreting</RTL><BRK/><BRK/><RID>ACI 347</RID><RTL>(2004) Guide to Formwork for Concrete</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM C 1040/C 1040M</RID><RTL>(2008) Standard Test Methods for In-Place Density of Unhardened and Hardened Concrete, Including Roller Compacted Concrete, by Nuclear Methods</RTL><BRK/><BRK/><RID>ASTM C 1064/C 1064M</RID><RTL>(2008) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete</RTL><BRK/><BRK/><RID>ASTM C 1077</RID><RTL>(2008) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation</RTL><BRK/><BRK/><RID>ASTM C 117</RID><RTL>(2004) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing</RTL><BRK/><BRK/><RID>ASTM C 123</RID><RTL>(2004) Standard Test Method for Lightweight Particles in Aggregate</RTL><BRK/><BRK/><RID>ASTM C 1260</RID><RTL>(2007) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)</RTL><BRK/><BRK/><RID>ASTM C 127</RID><RTL>(2007) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate</RTL><BRK/><BRK/><RID>ASTM C 128</RID><RTL>(2007a) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Fine Aggregate</RTL><BRK/><BRK/><RID>ASTM C 131</RID><RTL>(2006)Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine</RTL><BRK/><BRK/><RID>ASTM C 136</RID><RTL>(2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates</RTL><BRK/><BRK/><RID>ASTM C 138/C 138M</RID><RTL>(2008) Standard Test Method for Density ("Unit Weight"), Yield, and Air Content (Gravimetric) of Concrete</RTL><BRK/><BRK/><RID>ASTM C 142</RID><RTL>(1997; R 2004) Standard Test Method for Clay Lumps and Friable Particles in Aggregates</RTL><BRK/><BRK/><RID>ASTM C 143/C 143M</RID><RTL>(2008) Standard Test Method for Slump of Hydraulic-Cement Concrete</RTL><BRK/><BRK/><RID>ASTM C 150</RID><RTL>(2007) Standard Specification for Portland Cement</RTL><BRK/><BRK/><RID>ASTM C 1567</RID><RTL>(2008) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)</RTL><BRK/><BRK/><RID>ASTM C 172</RID><RTL>(2008) Standard Practice for Sampling Freshly Mixed Concrete</RTL><BRK/><BRK/><RID>ASTM C 231</RID><RTL>(2008c) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method</RTL><BRK/><BRK/><RID>ASTM C 260</RID><RTL>(2006) Standard Specification for Air-Entraining Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM C 295</RID><RTL>(2008) Petrographic Examination of Aggregates for Concrete</RTL><BRK/><BRK/><RID>ASTM C 31/C 31M</RID><RTL>(2008a) Standard Practice for Making and Curing Concrete Test Specimens in the Field</RTL><BRK/><BRK/><RID>ASTM C 33</RID><RTL>(2007) Standard Specification for Concrete Aggregates</RTL><BRK/><BRK/><RID>ASTM C 39/C 39M</RID><RTL>(2005e1e2) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens</RTL><BRK/><BRK/><RID>ASTM C 40</RID><RTL>(2004) Standard Test Method for Organic Impurities in Fine Aggregates for Concrete</RTL><BRK/><BRK/><RID>ASTM C 441</RID><RTL>(2005) Effectiveness of Pozzolansor Ground Blast-Furnace Slag in Preventing Excessive Expansion of Concrete Due to the Alkali-Silica Reaction</RTL><BRK/><BRK/><RID>ASTM C 494/C 494M</RID><RTL>(2008a) Standard Specification for Chemical Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM C 535</RID><RTL>(2003e1) Standard Test Method for Resistance to Degradation of Large-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine</RTL><BRK/><BRK/><RID>ASTM C 566</RID><RTL>(1997; R 2004) Standard Test Method for Total Evaporable Moisture Content of Aggregate by Drying</RTL><BRK/><BRK/><RID>ASTM C 618</RID><RTL>(2008a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete</RTL><BRK/><BRK/><RID>ASTM C 666/C 666M</RID><RTL>(2003; R 2008) Resistance of Concrete to Rapid Freezing and Thawing</RTL><BRK/><BRK/><RID>ASTM C 87</RID><RTL>(2005) Effect of Organic Impurities in Fine Aggregate on Strength of Mortar</RTL><BRK/><BRK/><RID>ASTM C 94/C 94M</RID><RTL>(2007) Standard Specification for Ready-Mixed Concrete</RTL><BRK/><BRK/><RID>ASTM C 989</RID><RTL>(2006) Standard Specification for Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars</RTL><BRK/><BRK/><RID>ASTM D 4318</RID><RTL>(2005) Liquid Limit, Plastic Limit, and Plasticity Index of Soils</RTL><BRK/><BRK/><RID>ASTM D 4791</RID><RTL>(2005e1) Flat Particles, Elongated Particles, or Flat and Elongated Particles in Coarse Aggregate</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)</ORG><BRK/><BRK/><RID>NIST HB 44</RID><RTL>(2007) NIST Handbook 44:  Specifications, Tolerances, and other Technical Requirements for Weighing and Measuring Devices</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA)</ORG><BRK/><BRK/><RID>NRMCA CPMB 100</RID><RTL>(2000) Concrete Plant Standards</RTL><BRK/><BRK/></REF><REF><ORG>U.S. ARMY CORPS OF ENGINEERS (USACE)</ORG><BRK/><BRK/><RID>COE CRD-C 100</RID><RTL>(1975) Method of Sampling Concrete Aggregate and Aggregate Sources, and Selection of Material for Testing</RTL><BRK/><BRK/><RID>COE CRD-C 104</RID><RTL>(1980) Method of Calculation of the Fineness Modulus of Aggregate</RTL><BRK/><BRK/><RID>COE CRD-C 114</RID><RTL>(1997) Test Method for Soundness of Aggregates by Freezing and Thawing of Concrete Specimens</RTL><BRK/><BRK/><RID>COE CRD-C 130</RID><RTL>(2001) Standard Recommended Practice for Estimating Scratch Hardness of Coarse Aggregate Particles</RTL><BRK/><BRK/><RID>COE CRD-C 143</RID><RTL>(1962) Specifications for Meters for Automatic Indication of Moisture in Fine Aggregates</RTL><BRK/><BRK/><RID>COE CRD-C 400</RID><RTL>(1963) Requirements for Water for Use in Mixing or Curing Concrete</RTL><BRK/><BRK/><RID>COE CRD-C 521</RID><RTL>(1981) Standard Test Method for Frequency and Amplitude of Vibrators for Concrete</RTL><BRK/><BRK/><RID>COE CRD-C 53</RID><RTL>(2001) Test Method for Consistency of No-Slump Concrete Using the Modified Vebe Apparatus</RTL><BRK/><BRK/><RID>COE CRD-C 55</RID><RTL>(1992) Test Method for Within-Batch Uniformity of Freshly Mixed Concrete</RTL><BRK/><BRK/><RID>EM 385-1-1</RID><RTL>(2008) Safety and Health Requirements Manual</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   UNIT PRICES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If Section 01 22 00.00 10 MEASUREMENT AND PAYMENT is included in the 
project specifications, this paragraph title (UNIT PRICES) should be deleted 
from this section and the remaining appropriately edited subparagraphs below 
should be inserted into Section 01 22 00.00 10.</NPR><BRK/>
<BRK/>
<NPR>See appropriate Design Memorandum (DM) for concrete items that are to be measured 
by the neat line, batch or lump sum.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.2.1   Roller-Compacted Concrete (RCC) in [_____]</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Repeat this bid item and its respective subparagraphs for each bid item 
of concrete, renumbering the bid items appropriately.</NPR><BRK/>
<BRK/>
<NPR>See the Design Memorandum on the use of the optional item on air entrainment.</NPR><BRK/>
<BRK/>
<NPR>If bedding concrete is to be paid for as a separate bid item, delete the optional 
words, "Bedding concrete and", below.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.2.1.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with completing the concrete work for roller-compacted concrete placed 
in the [_____], including all aggregate [, air-entraining admixture,] and the use of all equipment and tools 
to complete the concrete work.  However, these costs will not include the cost of the cement, pozzolan, [water-reducing 
admixture,] and embedded parts that are specified to be paid for separately.  [Bedding concrete and] bedding 
mortar [is] [are] incidental to the RCC and will be paid for as part of the RCC within the neat lines.  [Joint 
materials, waterstops, sealants, and bond breakers are incidental to the concrete and will be paid for as part 
of the RCC.]  No payment will be made for concrete, as such, that is placed in structures of which payment is 
made as a lump sum.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.1.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Roller-compacted concrete will be measurement for payment on the basis of the actual volume of RCC within the 
pay lines of the structures as indicated on the drawings.  Measurement of RCC placed against the sides of any 
excavation without the use of intervening forms shall be made only within the pay lines of the structure.  No 
deductions shall be made for rounded or beveled edges, space occupied by metal work, electrical conduits or reinforcing 
steel, nor for voids or embedded items that are either less than<MET> 0.14 cubic meter</MET><ENG> 5 cubic feet</ENG> in volume or<MET> 0.09 
square meter</MET><ENG> 1 square foot</ENG> in cross section.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.1.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure: cubic<MET> meter</MET><ENG> yard</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.2.2   [Dental Concrete]</TTL><BRK/>
<BRK/>
<SPT><TTL>1.2.2.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with placing dental concrete.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.2.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Dental concrete will be measurement for payment based upon the actual volume of dental concrete placed.  The 
dental concrete volume in cubic<MET> meters</MET><ENG> yards</ENG> will be computed from the<MET> mass</MET><ENG> weight</ENG> of the material batched at 
the batch plant using the theoretical<MET> mass per meter</MET><ENG> weight per yard</ENG> as determined from the design mixture.  
Any concrete which is wasted or placed in violation of the specifications will not be measured for payment.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.2.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure: cubic<MET> meter</MET><ENG> yard</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.2.3   [Bedding Concrete]</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If bedding concrete is to be paid for as a separate bid item, delete 
the optional wording "Bedding concrete and" in Bid Item "(1) Roller-Compacted 
Concrete (RCC) in [_____]", above.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.2.3.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with placing bedding concrete.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.3.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Bedding concrete will be measurement for payment based upon the actual volume of bedding concrete placed.  The 
bedding concrete volume in cubic<MET> meters</MET><ENG> yards</ENG> will be computed from the<MET> mass</MET><ENG> weight</ENG> of the material batched at 
the batch plant using the theoretical<MET> mass/meter</MET><ENG> weight/yard</ENG> as determined from the design mixture.  Any concrete 
which is wasted or placed in violation of the specifications will not be measured for payment.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.3.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure: cubic<MET> meter</MET><ENG> yard</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.2.4   Portland Cement</TTL><BRK/>
<BRK/>
<SPT><TTL>1.2.4.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with Portland cement, which includes the cost of required unloading, 
hauling, handling, and storage at the site, of all portland cement used in the work for all of the concrete bid 
items.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.4.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Portland cement will be measured for payment based upon the number of tons<MET> (metric)</MET><ENG> (2,000 pounds)</ENG> of Portland 
cement used, excluding amount specifically excepted, wasted, or used for the convenience of the Contractor.  
The quantity to be paid for will be determined by multiplying the approved batch<MET> mass in kg/cubic meter</MET><ENG> weight 
in pounds per cubic yard</ENG> of Portland cement in each type of concrete used by the number of cubic<MET> meters</MET><ENG> yards</ENG>
 of concrete types placed within the pay lines of the structure, as determined in accordance with the concrete 
bid items, and dividing by<MET> 1000</MET><ENG> 2,000</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.4.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure: tons<MET> (metric)</MET><ENG> (2,000 pounds)</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.2.5   Pozzolan</TTL><BRK/>
<BRK/>
<SPT><TTL>1.2.5.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with pozzolan, which includes the cost of required unloading, hauling, 
handling, and storage at the site, of all pozzolan used in the concrete bid items.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.5.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Pozzolan will be measured for payment based upon the number of cubic<MET> meters</MET><ENG> feet</ENG> solid volume of pozzolan used 
unless specifically excepted, wasted, or used for the convenience of the Contractor.  The quantity to be paid 
for will be determined by multiplying the approved batch<MET> mass in kg/cubic meter</MET><ENG> weight in pounds per cubic yard</ENG>
 of pozzolan in each type of concrete used by the number of cubic<MET> meters</MET><ENG> yards</ENG> of concrete of the types placed 
within the pay lines of the structure, as determined in accordance with the concrete bid items, and dividing 
by the product of the average specific gravity of the pozzolan multiplied by<MET> 1000 kg/cubic meter</MET><ENG> 62.4 pcf</ENG>.  The 
average specific gravity shall be the average of the test results for all material accepted during the period 
covered by the payment.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.5.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure: cubic<MET> meter</MET><ENG> foot</ENG> solid volume.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.2.6   Water-Reducing Admixture (WRA)</TTL><BRK/>
<BRK/>
<SPT><TTL>1.2.6.1   Payment</TTL><BRK/>
<BRK/>
<TXT>[Payment will be made for costs associated with water-reducing admixture (WRA) at the applicable contract unit 
price per cubic yard of concrete containing water-reducing admixture.]  [Payment will be made for costs associated 
with water-reducing admixture (WRA) at the applicable contract unit cost of concrete containing water-reducing 
admixture for:</TXT><BRK/>
<BRK/>
<LST>a.  "Bid Item [_____]a., first [_____] cubic<MET> meters</MET><ENG> yards</ENG>".</LST><BRK/>
<BRK/>
<LST>b.  "Bid Item [_____]b., all over [_____] cubic<MET> meters</MET><ENG> yards</ENG>".]</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.6.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Water-reducing admixture (WRA) will be measured for payment based upon the actual volume of roller-compacted 
concrete containing the admixture and within the pay lines of the structures, as determined in accordance with 
the concrete bid items.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.6.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure: cubic<MET> meter</MET><ENG> yard</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.2.7   RCC Test Section</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The Test Section may be paid for as a lump sum pay item provided test 
section requirement are clearly specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.2.7.1   Payment</TTL><BRK/>
<BRK/>
<TXT>Payment will be made for costs associated with completing the roller-compacted test section, including equipment 
and tools needed to complete the test section.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.7.2   Measurement</TTL><BRK/>
<BRK/>
<TXT>Roller-compacted concrete test section will be measurement for payment based upon the actual number of test sections 
taken.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.7.3   Unit of Measure</TTL><BRK/>
<BRK/>
<TXT>Unit of measure: each.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>1.3   GOVERNMENT TESTING AND STUDIES</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Preconstruction Testing and Mixture-Proportioning Studies</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1.1   Aggregate Testing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Contact the division laboratory for guidance in filling in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The aggregate sources listed in paragraph COMMERCIAL CONCRETE AGGREGATE SOURCES, have been tested and, at the 
time testing was performed, were capable of producing materials of the quality required for this project, provided 
suitable processing is performed.  Samples from any source selected, whether listed or not listed, consisting 
of not less than [_____]<MET> kg</MET><ENG> pounds</ENG> of each size coarse aggregate and [_____]<MET> kg</MET><ENG> pounds</ENG> of fine aggregate, and 
taken under the supervision of the Contracting Officer in accordance with <RID>COE CRD-C 100</RID>, shall be delivered to 
[_____] within 15 days after Notice to Proceed.  Sampling, shipment, and testing of samples shall be at the Contractor's 
expense.  [_____] days will be required to complete evaluation of the aggregates.  All quality assurance testing 
will be performed by the Government in accordance with the applicable COE CRD-C or ASTM test methods.  Tests 
to which aggregate may be subjected are listed in paragraph QUALITY.  The material from the proposed source shall 
meet the quality requirements of this paragraph to be used for this project.  The Government test data and other 
information on aggregate quality of those sources listed in PART 2 are included in the Design Memorandum and 
are available for review in the district office.  Quality assurance testing of aggregates by the Government does 
not relieve the Contractor of quality control requirements.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.2   Cementitious Materials and Admixtures</TTL><BRK/>
<BRK/>
<TXT>[At least [_____] days in advance of submitting samples for mixture proportioning studies,] [Not later than [_____] 
days after Notice to Proceed] the Contractor shall notify the Contracting Officer of the source, brand name, 
type, and quantity of all materials (other than aggregates) to be used in the manufacture and curing of the concrete.  
The Contractor shall assist the Contracting Officer in obtaining samples of each material.  Sampling and testing 
as determined appropriate will be performed by and at the expense of the Government.  If cement or fly ash are 
to be obtained from more than one source, the notification shall state the estimated amount of cement or fly 
ash to be obtained from each source and the proposed schedule of shipments.  When pozzolan other than fly ash 
is used, it shall be from one source.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.3   Materials for Mixture-Proportioning Studies</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Contact the Division Lab to fill in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>At least [_____] days in advance of the time when placing of concrete is expected to begin, samples of representative 
materials proposed for this project and meeting all the requirements of this specification shall be delivered 
to [_____] by the Contractor at his expense.  Samples of aggregates shall be taken under the supervision of the 
Contracting Officer in accordance with <RID>COE CRD-C 100</RID>, accompanied by test reports indicating conformance with 
grading and quality requirements hereinafter specified.  Samples of materials other than aggregates shall be 
representative of those proposed for the project and shall be submitted accompanied by manufacturer's test reports 
indicating compliance with applicable specified requirements.  Quantities of materials required shall be as follows:</TXT><BRK/>
<MET><TBL><BRK/>
<THD>                   MATERIAL                                QUANTITY<BRK/>
<BRK/></THD>
  [75 mm nominal maximum size coarse aggregate          [_____] kg]<BRK/>
  37.5 mm nominal maximum size coarse aggregate         [_____] kg<BRK/>
  19 mm nominal maximum size coarse aggregate           [_____] kg<BRK/>
  Fine aggregate                                        [_____] kg<BRK/>
  Cement                                                [_____] kg<BRK/>
  Pozzolans                                             [_____] cu meters<BRK/>
  Admixtures (each)                                     [_____] L<BRK/></TBL>
</MET><ENG><TBL><BRK/>
<THD>                   MATERIAL                                QUANTITY<BRK/>
<BRK/></THD>
  [3 in. nominal maximum size coarse aggregate          [_____] pounds]<BRK/>
  1-1/2 in. nominal maximum size coarse aggregate       [_____] pounds<BRK/>
  3/4 in. nominal maximum size coarse aggregate         [_____] pounds<BRK/>
  Fine aggregate                                        [_____] pounds<BRK/>
  Cement                                                [_____] pounds<BRK/>
  Pozzolans                                             [_____] cu feet<BRK/>
  Admixtures (each)                                     [_____] gallons<BRK/></TBL>
</ENG><BRK/>
<TXT>Mixture-proportioning studies will be made by the Government at its expense.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.3.2   Testing During Construction by the Government</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.2.1   General</TTL><BRK/>
<BRK/>
<TXT>The Government will sample and test cementitious materials, admixtures, aggregates, and concrete during construction 
as considered appropriate to determine compliance with the specifications.  The Contractor shall provide facilities 
and labor as may be necessary for procurement of representative test samples.  Samples of aggregates will be 
obtained at the point of batching in accordance with <RID>COE CRD-C 100</RID>.  Slump and air content of conventional concrete 
will be determined in accordance with <RID>ASTM C 143/C 143M</RID> and <RID>ASTM C 231</RID>, respectively, except the point of sampling 
will be as specified in paragraph TESTS AND INSPECTIONS.  Compression test specimens of conventional concrete 
will be made and laboratory cured in accordance with <RID>ASTM C 31/C 31M</RID> and will be tested in accordance with <RID>ASTM C 39/C 39M</RID>
.  Consistency of the RCC will be determined by the Government using the modified Vebe apparatus in accordance 
with paragraph CONSISTENCY OF RCC.  Compression test specimens of RCC will be made and tested by the Government.  
Density of the compacted RCC will be checked by the Government as considered appropriate.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.2   Aggregates Testing</TTL><BRK/>
<BRK/>
<TXT>Testing performed by the Government will not relieve the Contractor of his responsibility for testing under paragraph 
TESTS AND INSPECTIONS.  During construction, aggregates will be sampled for acceptance testing as delivered to 
the mixer to determine compliance with specification provisions.  The Contractor shall provide necessary facilities 
and labor for the ready procurement of representative samples under Government supervision.  The Government will 
test such samples at its expense using the specified COE CRD-C and ASTM methods.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.3   Cementitious Materials</TTL><BRK/>
<BRK/>
<TXT>Cement or pozzolan will be sampled at the mill, shipping point, or site of the work by the Government.  A list 
of prequalified cement sources and prequalified pozzolan sources is available from the Commander and Director, 
U.S. Army Engineer Waterways Experiment Station (CEWES-SC-MP), 3909 Halls Ferry Road, Vicksburg, MS  39180-6199.  
If tests prove that a material which has been delivered is unsatisfactory, it shall be promptly removed from 
the site of the work.  Cementitious materials that have not been used within 6 months after being tested will 
be retested by the Government at the expense of the Contractor when directed by the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.4   Prequalified Cement Sources</TTL><BRK/>
<BRK/>
<TXT>Cement shall be delivered and used directly from a mill of a producer designated as a prequalified source for 
the type of cement being used.  Samples of cement for quality-assurance testing will be taken at the project 
site or cement-producing plant by the Contracting Officer for testing at the expense of the Government.  A copy 
of the mill tests from the cement manufacturer shall be furnished for each lot.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.5   Prequalified Pozzolan Sources</TTL><BRK/>
<BRK/>
<TXT>Pozzolan shall be delivered and used directly from a producer designated as a prequalified source.  Samples of 
pozzolan for check testing will be taken at the project site by the Contracting Officer for testing at the expense 
of the Government.  A copy of the test results from the pozzolan manufacturer shall be furnished for each lot.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.6   Nonprequalified Cement Sources</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The Contractor's expense rate for excess testing of cement and Pozzolan 
by the government can be obtained from the Structures Laboratory, U.S. Army 
Engineer Waterways Experiment Station (CEWES-SC-MP), 3909 Halls Ferry Road, 
Vicksburg, MS 39180-6199.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Cement, if not from a prequalified source, will be sampled and tested by or under the supervision of the Government 
and at its expense.  No cement shall be used until notice has been given by the Contracting Officer that test 
results are satisfactory.  In the event of failure, the cement may be resampled and tested at the request of 
the Contractor and at the Contractor's expense.  The fill gate or gates of the sampled bin will be sealed and 
kept sealed until shipment from the bin has been completed.  Sealing of the fill gate or gates and of conveyances 
used in shipment will be done by or under the supervision of the Government.  Conveyances will not be accepted 
at the site of the work unless received with all seals intact.  If tested cement is rehandled at transfer points, 
the extra cost of inspection will be at the Contractor's expense.  The cost of testing cement excess to project 
requirements will also be at the Contractor's expense and will be deducted from payments due the Contractor at 
a rate of [_____] dollars per test.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.7   Nonprequalified Pozzolan Sources</TTL><BRK/>
<BRK/>
<TXT>Pozzolan, if not from a prequalified source, will be sampled at the source or at the site of the work and will 
be stored in sealed bins pending completion of acceptance tests.  Pozzolan may be resampled at the site when 
determined necessary.  All sampling and testing will be performed by and at the expense of the Government.  Release 
for shipment and approval for use will be based on compliance with 7-day lime-pozzolan strength requirements 
and other physical, chemical, and uniformity requirements for which tests can be completed by the time the 7-day 
lime-pozzolan strength test is completed.  Release for shipment and approval for use on this basis will be contingent 
on continuing compliance with the other requirements of the specifications.  If test results of a bin fail, the 
contents may be resampled and tested at the Contractor's expense.  The Government will supervise or perform the 
unsealing and resealing of bins and shipping conveyances.  If tested pozzolan is rehandled at transfer points, 
the extra cost of inspection will be at the Contractor's expense.  The cost of testing excess pozzolan in excess 
of project requirements will be at the Contractor's expense at a rate of [_____] dollars per test.  The amount 
will be deducted from payment to the Contractor.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.8   Admixtures</TTL><BRK/>
<BRK/>
<TXT>The Contractor shall provide satisfactory facilities for ready procurement of adequate test samples.  All sampling 
and testing of an admixture will be by and at the expense of the Government.  Tests will be conducted on the 
same materials which will be shipped to the project.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>1.4   CONSTRUCTION TOLERANCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete any of the following tables that are not applicable.  Most projects 
will require several tables to cover all parts of the structure.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The definitions of the terms used in the following tables shall be as defined in <RID>ACI 117</RID>.  Level and grade tolerance 
measurements of slabs shall be made as soon as possible after finishing.  When forms or shoring are used, the 
measurements shall be made prior to removal.  Tolerances are not cumulative.  The most restrictive tolerance 
controls.  Tolerances shall not extend the structures beyond legal boundaries.  Except as specified otherwise, 
plus tolerance increases the amount or dimension to which it applies or raises a level alignment, and minus tolerance 
decreases the amount or dimension to which it applied or lowers a level alignment.  A tolerance without sign 
means plus or minus.  Where only one signed tolerance is specified, there is no limit in the other direction.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.4.1   Conventional Concrete Surfaces</TTL><BRK/>
<BRK/>
<TXT>The definitions of the terms used in the following tables shall be as defined in <RID>ACI 117</RID>.</TXT><BRK/>
<MET><TBL><BRK/>
<THD>              TOLERANCES FOR CAST-IN-PLACE, VERTICALLY SLIPFORMED<BRK/>
                               BUILDING ELEMENTS<BRK/>
<BRK/></THD>
  (1)  Vertical alignment<BRK/>
<BRK/>
       Translation and rotation from a fixed point at the base of<BRK/>
       the structure:<BRK/>
       For heights 30 m or less ................................... 50 mm.<BRK/>
<BRK/>
       For heights greater than 30 m,<BRK/>
       1/600 times the height<BRK/>
       but not more than ......................................... 200 mm.<BRK/>
<BRK/>
  (2)  Lateral alignment<BRK/>
<BRK/>
       Between adjacent elements .................................. 50 mm.<BRK/>
<BRK/>
  (3)  Cross-sectional dimensions<BRK/>
<BRK/>
       Wall thickness ........................................ plus 19 mm.<BRK/>
                      ....................................... minus 10 mm.<BRK/>
<BRK/>
  (4)  Relative alignment<BRK/>
<BRK/>
       Formed surface slope with respect<BRK/>
       to the plane shown in the drawings .............. 18 mm in 3000 mm.<BRK/>
<BRK/></TBL>
<TBL><BRK/>
<THD>                 TOLERANCES FOR CONCRETE STRUCTURES OTHER THAN<BRK/>
                                   BUILDINGS<BRK/>
<BRK/></THD>
  (1)  Vertical alignment<BRK/>
<BRK/>
       Visible surfaces ........................................... 30 mm.<BRK/>
       Concealed surfaces ......................................... 65 mm.<BRK/>
       Side walls for radial gates and<BRK/>
       similar water-tight joints .................................. 5 mm.<BRK/>
<BRK/>
  (2)  Lateral alignment<BRK/>
<BRK/>
       Visible surfaces............................................ 30 mm.<BRK/>
       Concealed surfaces.......................................... 65 mm.<BRK/>
<BRK/>
  (3)  Level alignment<BRK/>
<BRK/>
       Visible flatwork and formed surfaces........................ 13 mm.<BRK/>
       Concealed flatwork and formed surfaces...................... 25 mm.<BRK/>
       Sills for radial gates and<BRK/>
       similar water-tight joints .................................. 5 mm.<BRK/>
<BRK/>
  (4)  Relative alignment<BRK/>
<BRK/>
       Formed surface slope with respect to the specified plane.<BRK/>
          Slopes in lateral and level alignments<BRK/>
               Visible surfaces.......................... 6 mm in 3000 mm.<BRK/>
               Concealed surfaces....................... 12 mm in 3000 mm.<BRK/>
          Slopes in vertical alignment<BRK/>
               Visible surfaces......................... 12 mm in 3000 mm.<BRK/>
               Concealed surfaces....................... 24 mm in 3000 mm.<BRK/>
<BRK/></TBL>
<TBL><BRK/>
<THD>        TOLERANCE FOR FINISHED OR FORMED CONVENTIONAL CONCRETE SURFACES<BRK/>
<BRK/></THD>
  (1)  Vertical alignment<BRK/>
<BRK/>
       Formed surfaces slope with respect to the specified plane.            Vertical alignment of outside corner<BRK/>
          of exposed corner columns and control<BRK/>
          joint grooves in concrete exposed<BRK/>
          to view........................................ 9 mm in 3000 mm.<BRK/>
          All other conditions.......................... 12 mm in 3000 mm.<BRK/>
<BRK/>
 [(2)  Abrupt variation in spillway surface<BRK/>
<BRK/>
       The offset between concrete surfaces<BRK/>
       under adjacent pieces of formwork ........................... 3 mm.]<BRK/>
<BRK/>
  (3)  Gradual variation<BRK/>
<BRK/>
       Surface finish tolerances as measured<BRK/>
       by placing a freestanding (unleveled),<BRK/>
       1500-mm straightedge for plane surface or<BRK/>
       curved template for curved surface<BRK/>
       anywhere on the surface and allowing it<BRK/>
       to rest upon two high spots within 72 hr<BRK/>
       after concrete placement.  The gap at any<BRK/>
       point between the straightedge or<BRK/>
       template and the surface shall not exceed ................... 6 mm.<BRK/>
<BRK/>
  (4)  Offsets of adjacent precast gallery<BRK/>
       segments shall not exceed .................................. 25 mm.<BRK/></TBL>
</MET><ENG><BRK/>
<TBL><BRK/>
<THD>              TOLERANCES FOR CAST-IN-PLACE, VERTICALLY SLIPFORMED<BRK/>
                               BUILDING ELEMENTS<BRK/>
<BRK/></THD>
  (1)  Vertical alignment<BRK/>
<BRK/>
       Translation and rotation from a fixed point at the base of<BRK/>
       the structure:<BRK/>
       For heights 100 ft or less .................................. 2 in.<BRK/>
       For heights greater than 100 ft,<BRK/>
       1/600 times the height<BRK/>
       but not more than ........................................... 8 in.<BRK/>
<BRK/>
  (2)  Lateral alignment<BRK/>
<BRK/>
       Between adjacent elements ................................... 2 in.<BRK/>
<BRK/>
  (3)  Cross-sectional dimensions<BRK/>
<BRK/>
       Wall thickness ....................................... plus 3/4 in.<BRK/>
                      ...................................... minus 3/8 in.<BRK/>
<BRK/>
  (4)  Relative alignment<BRK/>
       Formed surface slope with respect<BRK/>
       to the plane shown in the drawings .............. 3/4 in. in 10 ft.<BRK/>
<BRK/></TBL>
<TBL><BRK/>
<THD>                 TOLERANCES FOR CONCRETE STRUCTURES OTHER THAN<BRK/>
                                   BUILDINGS<BRK/>
<BRK/></THD>
  (1)  Vertical alignment<BRK/>
<BRK/>
       Visible surfaces ........................................ 1-1/4 in.<BRK/>
       Concealed surfaces ...................................... 2-1/2 in.<BRK/>
       Side walls for radial gates and<BRK/>
       similar water-tight joints ............................... 3/16 in.<BRK/>
<BRK/>
  (2)  Lateral alignment<BRK/>
<BRK/>
       Visible surfaces ........................................ 1-1/4 in.<BRK/>
       Concealed surfaces....................................... 2-1/2 in.<BRK/>
<BRK/>
  (3)  Level alignment<BRK/>
       Visible flatwork and formed surfaces ...................... 1/2 in.<BRK/>
       Concealed flatwork and formed surfaces ...................... 1 in.<BRK/>
       Sills for radial gates and<BRK/>
       similar water-tight joints ............................... 3/16 in.<BRK/>
<BRK/>
  (4)  Relative alignment<BRK/>
       Formed surface slope with respect to the specified plane.<BRK/>
          Slopes in lateral and level alignments<BRK/>
               Visible surfaces ......................... 1/4 in. in 10 ft<BRK/>
               Concealed surfaces ....................... 1/2 in. in 10 ft<BRK/>
          Slopes in vertical alignment<BRK/>
               Visible surfaces ......................... 1/2 in. in 10 ft<BRK/>
               Concealed surfaces ......................... 1 in. in 10 ft<BRK/>
<BRK/></TBL>
<TBL><BRK/>
<THD>        TOLERANCE FOR FINISHED OR FORMED CONVENTIONAL CONCRETE SURFACES<BRK/>
<BRK/></THD>
  (1)  Vertical alignment<BRK/>
<BRK/>
       Formed surfaces slope with respect to the specified plane<BRK/>
          Vertical alignment of outside corner<BRK/>
          of exposed corner columns and control<BRK/>
          joint grooves in concrete exposed<BRK/>
          to view ....................................... 3/8 in. in 10 ft<BRK/>
          All other conditions .......................... 1/2 in. in 10 ft<BRK/>
<BRK/>
 [(2)  Abrupt variation in spillway surface<BRK/>
<BRK/>
       The offset between concrete surfaces<BRK/>
       under adjacent pieces of formwork ......................... 1/8 in.<BRK/>
       of formwork .............................................. 1/8 in.]<BRK/>
<BRK/>
  (3)  Gradual variation<BRK/>
<BRK/>
       Surface finish tolerances as measured<BRK/>
       by placing a freestanding (unleveled),<BRK/>
       5-ft straightedge for plane surface or<BRK/>
       curved template for curved surface<BRK/>
       anywhere on the surface and allowing it<BRK/>
       to rest upon two high spots within 72 hr<BRK/>
       after concrete placement.  The gap at any<BRK/>
       point between the straightedge or template<BRK/>
       and the surface shall not exceed .......................... 1/4 in.<BRK/>
<BRK/>
  (4)  Offsets of adjacent precast gallery<BRK/>
       segments shall not exceed ................................... 1 in.<BRK/></TBL>
</ENG><BRK/></SPT>
<SPT><TTL>1.4.2   RCC Surfaces</TTL><BRK/>
<BRK/>
<LST>a.  Variations from the lines and grades of the gallery walls and ceiling from that shown in the drawings 
shall not exceed plus or minus<MET> 75 mm</MET><ENG> 3 inches</ENG> except tolerances at the gallery entrances shall be kept 
within the limits necessary for the bulkheads and doorways to fit and function as designed.</LST><BRK/>
<BRK/>
<LST>b.  Allowable variation from lines and grades of the downstream face of the dam (measured in any direction) 
shall be minus zero (-0) (no under build allowed) and plus<MET> 100 mm</MET><ENG> 4 inches</ENG>, [except that the elevation 
and shape of the spillway stilling basin training walls shall be such that the training walls match with 
the downstream face as shown in the drawings or otherwise provided for].  See additional restrictions 
in paragraph DOWNSTREAM FACE.</LST><BRK/>
<BRK/>
<LST>c.  The thickness of compacted lifts of RCC shall be within plus or minus<MET> 50 mm</MET><ENG> 2 inches</ENG> of that specified.</LST><BRK/>
<BRK/>
<LST>d.  The elevation of the surfaces of RCC lifts upon which subsequent RCC or conventional concrete is 
placed shall not vary more than<MET> 150 mm</MET><ENG> 0.5 ft</ENG> from the design elevation, except that the elevation of 
the top three lifts of the dam shall be within<MET> 60 mm</MET><ENG> 0.2 ft</ENG> of that shown.</LST><BRK/>
<BRK/>
<LST>e.  The location of anchor bars, waterstops, contraction joints, and drain holes shall be within<MET> 150 
mm</MET><ENG> 0.5 ft</ENG> of the designated locations shown.</LST><BRK/>
<BRK/>
<LST>f.  The spacing of individual reinforcing steel bars in RCC shall be within<MET> 50 mm</MET><ENG> 2 inches</ENG> of that shown.</LST><BRK/>
<BRK/>
<LST>g.  Tolerances for exposed surfaces of upstream face concrete [, the face of the spillway chute,] and 
any other conventional concrete that interfaces with the RCC shall be in accordance with paragraph CONVENTIONAL 
CONCRETE SURFACES.</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.5   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy, Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for [Contractor Quality Control approval.] [information only.  When used, a designation following the "G" 
designation identifies the office that will review the submittal for the Government.]  The following shall be 
submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Consult the materials DM or the Project Manager to select the optional 
sentences and to fill in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM><SUB>Batch Plant</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM>.<BRK/>
<BRK/>
<ITM>  Details and data on the concrete plant shall be submitted [[_____] days prior to assembly] 
[not later than 30 days after Notice to Proceed] for review by the Contracting Officer.  Final 
acceptance of any piece of plant is subject to satisfactory performance during operations.</ITM><BRK/>
<BRK/>
<ITM><SUB>Mixers</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM>.<BRK/>
<BRK/>
<ITM>  The make, type, capacity, and number of the concrete mixers proposed for use shall be submitted 
[[_____] days prior to installation] [not later than 30 days after Notice to Proceed] for review 
by the Contracting Officer.</ITM><BRK/>
<BRK/>
<ITM><SUB>Equipment</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<ITM><SUB>Transporting and Conveying Equipment</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<ITM><SUB>Spreading and Remixing Equipment</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<ITM><SUB>Compaction Equipment</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM>.<BRK/>
<BRK/>
<ITM>  A listing of the equipment proposed for transporting, handling, depositing, spreading, and 
compacting the concrete shall be submitted for review by the Contracting Officer [[_____] days 
before concrete placement begins.]  [not later than 30 days after Notice to Proceed.]  The data 
submitted shall include site drawings or sketches with locations of equipment and placement 
site.</ITM><BRK/>
<BRK/>
<ITM><SUB>Aggregate Production Schedule</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Descriptions and details for all methods and operations proposed for aggregate and concrete 
operations including daily and weekly production rates, shall be submitted [not later than [_____] 
days after Notice to Proceed] for review and approval for conformance with specifications.</ITM><BRK/>
<BRK/>
<ITM><SUB>Regular Lift-Joint Treatment</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  The method and equipment proposed for joint cleanup and waste disposal shall be submitted 
for review by the Contracting Officer [[_____] days before concrete placement begins] [not later 
than [_____] days after Notice to Proceed] for conformance with specifications.</ITM><BRK/>
<BRK/>
<ITM><SUB>Curing and Protection</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM>.<BRK/>
<BRK/>
<ITM>  The curing media and methods to be used shall be submitted for review to the Contracting Officer 
[[_____] days before concrete placement begins] for conformance with specifications.</ITM><BRK/>
<BRK/>
<ITM><SUB>Cold-Weather Protection</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  When concrete is to be placed under cold-weather conditions, a description of the materials 
and methods proposed for protection of the concrete shall be furnished to the Contracting Officer 
for review [_____] days in advance of anticipated need date.</ITM><BRK/>
<BRK/>
<ITM><SUB>Hot-Weather Protection</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  When concrete is to be placed under hot-weather conditions, a description of the materials 
and methods proposed for protection of the concrete shall be furnished to the Contracting Officer 
for review [_____] days in advance of anticipated need date.</ITM><BRK/>
<BRK/>
<ITM><SUB>Contraction Joints</SUB></ITM><BRK/>
<BRK/>
<ITM>  Details of the contraction joint material and installation procedures will be submitted within 
[_____] days after the Notice to Proceed.</ITM><BRK/>
<BRK/>
<ITM>[<SUB>Gallery</SUB></ITM><BRK/>
<BRK/>
<ITM>  Details of the Contractor's construction methods shall be submitted within [_____] days after 
the Notice to Proceed.]</ITM><BRK/>
<BRK/>
<ITM><SUB>Vertical Facings for RCC Construction</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Details of the Contractors construction methods and equipment shall be submitted for review 
within [_____] days after Notice to Proceed.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6   REGULATORY REQUIREMENTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Issue (date) of regulatory requirements included in project specifications 
need not be more current than stated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The regulatory requirements listed below form a part of this specification to the extent referenced.  The regulatory 
requirements are referred to in the text by basic designation only.</TXT><BRK/>
<BRK/>
<TBL><BRK/>
<RID>EM 385-1-1</RID>           (October 1992) Safety and Health Requirements<BRK/>
                                 Manual</TBL><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7   MATERIAL DELIVERY, STORAGE, AND HANDLING</TTL><BRK/>
<BRK/>
<SPT><TTL>1.7.1   Cementitious Materials</TTL><BRK/>
<BRK/>
<SPT><TTL>1.7.1.1   Transportation</TTL><BRK/>
<BRK/>
<TXT>When bulk cement or pozzolan is not unloaded from primary carriers directly into weather-tight hoppers at the 
batching plant, transportation from the railhead, mill, or intermediate storage to the batching plant shall be 
accomplished in adequately designed weather-tight trucks, conveyors, or other means that will protect the material 
from exposure to moisture.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.1.2   Storage</TTL><BRK/>
<BRK/>
<TXT>Cementitious materials shall be furnished in bulk.  Immediately upon receipt at the site of the work, all cementitious 
materials shall be stored in a dry, weather-tight, and properly ventilated structure.  All storage facilities 
shall permit easy access for inspection and identification.  Sufficient materials shall be in storage for at 
least two operating days of continuous placement.  In order that cement may not become unduly aged after delivery, 
the Contractor shall use any cement that has been stored at the site for 60 days or more before using cement 
of lesser age.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.7.2   Aggregate Storage</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Consult the materials engineer to select the appropriate optional phrase 
and to fill in the blank.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Fine aggregate and each size of coarse aggregate shall be stored in separate size groups adjacent to the batch 
plant and in such a manner as to prevent the intermingling of size groups or the inclusion of foreign materials 
in the aggregate.  Sufficient fine and coarse aggregate shall be maintained at the site for at least [30] [_____] 
operating days of continuous placement.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7.3   Chemical Admixtures</TTL><BRK/>
<BRK/>
<TXT>Any admixture that has been in storage at the project site for longer than recommended by the manufacturer or 
that has been subjected to freezing shall not be used in the work and shall be removed from the site.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   MATERIALS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.1   Cementitious Materials</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the appropriate concrete aggregates DM or thermal study to select 
the proper requirements for cementitious materials options.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.1.1.1   Portland Cement</TTL><BRK/>
<BRK/>
<TXT>Portland cement shall conform to <RID>ASTM C 150</RID>, Type [_____], [low alkali when it is to be used with aggregates 
listed to require it in the paragraph COMMERCIAL CONCRETE AGGREGATE SOURCES or when directed if a nonlisted source 
is permitted.]  [the heat of hydration requirement at 7 days shall be no greater than [_____] calories per gram] 
[including false-set requirement].  [In lieu of low-alkali cement, the Contractor may use a combination of portland 
cement that does not meet the low-alkali requirement with a suitable pozzolan or ground granulated blast-furnace 
slag (GGBFS) provided the following requirement is met.  The expansion of the proposed combination shall be equal 
to or less than the expansion of a low-alkali cement meeting the requirements of <RID>ASTM C 150</RID> when tested in conformance 
with <RID>ASTM C 441</RID>.  These two tests shall be performed concurrently at an independent certified laboratory at the 
Contractor's expense.  The Government reserves the right to confirm the test results and to adjust the percentage 
of pozzolan or GGBFS in the combination to suit other requirements at no additional cost to the Government.]  
Portland cement shall be furnished in bulk.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.1.2   Pozzolan</TTL><BRK/>
<BRK/>
<TXT>Pozzolan shall conform to <RID>ASTM C 618</RID>, Class [_____], and, in addition, limits in Table 2A, Uniformity Requirements 
(for air content) shall apply to all fly ash.  [Table 1A, Supplementary Optional Chemical Requirement for Maximum 
Alkalies, shall apply when it is to be used with aggregates listed to require low-alkali cement].  Pozzolan shall 
be furnished in bulk.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.1.3   Ground Granulated Blast-Furnace (GGBF) Slag</TTL><BRK/>
<BRK/>
<TXT>Ground Granulated Blast-Furnace Slag shall conform to <RID>ASTM C 989</RID>, Grade 100 or Grade 120.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.1.4   Temperature of Cementitious Materials</TTL><BRK/>
<BRK/>
<TXT>The temperature of the cementitious materials as delivered to the site shall not exceed<MET> 65 degrees C</MET><ENG> 150 degrees 
F</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.1.2   Admixtures</TTL><BRK/>
<BRK/>
<TXT>All chemical admixtures furnished as liquids shall be in a solution of suitable viscosity and dilution for field 
use as determined by the Contracting Officer.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.1.2.1   [Water-Reducing Admixture (WRA)</TTL><BRK/>
<BRK/>
<TXT>A WRA shall meet the requirements of <RID>ASTM C 494/C 494M</RID>, Type D, except that the 6-month and 1-year compressive 
strength tests are waived.  The admixture may be added to the concrete mixture only when its use is approved 
or directed and after mixture proportioning studies.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.2.2   Air-Entraining Admixture</TTL><BRK/>
<BRK/>
<TXT>Air-entraining admixture shall conform to <RID>ASTM C 260</RID>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.1.3   Water</TTL><BRK/>
<BRK/>
<TXT>Water for washing aggregates and for mixing and curing concrete shall be free from injurious amounts of oil, 
acid, salt, alkali, organic matter, or other deleterious substances and shall comply with <RID>COE CRD-C 400</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4   Aggregates</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM to select the aggregate composition options.</NPR><BRK/>
<BRK/>
<NPR>  This note may be disregarded for regions where Alkali-Silica Reactivity (ASR) 
is not a concern. Some aggregate sources may exhibit an ASR potential.  ASR 
is a potentially deleterious reaction between alkalis present in concrete and 
some siliceous aggregates, reference EM 1110-2-2000 paragraph 2-3b(6) and appendix 
D.  Use of cementitious materials meeting the low alkali requirement may be 
effective in some applications, and insufficient in others.  In regions where 
imposing the low alkali requirement has not been effective in controlling ASR, 
additional effort for evaluation and mitigation may be required.  In which case, 
the alternate procedures to proportion cementitious materials to meet the low 
alkali requirement in paragraph 2.1.1.1 Portland Cement should not be used with 
the following requirements.  Where ASR is known or suspected to pose a concern 
for concrete durability, it is recommended that aggregates proposed for use 
in concrete be evaluated to determine ASR potential and an effective mitigation.  
EM 1110-2-2000, provides recommendations for evaluating and mitigating ASR in 
concrete mixtures.  Aggregate evaluations may not be practical for projects 
requiring small quantities of concrete (less than 250 cubic yards).<BRK/>
<BRK/>
UFGS Section 32 13 11 CONCRETE PAVEMENT FOR AIRFIELDS AND OTHER HEAVY-DUTY PAVEMENTS 
MORE THAN 10,000 CUBIC YARDS, paragraph 2.2.1.2 Alkali-Silica Reactivity, provides 
a specification method for the Contractor to evaluate and mitigate ASR in concrete 
mixtures.  The expansion limits specified in Section 32 13 11 are requirements 
for pavements and exterior slab construction.  For structural concrete applications 
the measured expansion shall be less than 0.10 percent.  It may not be economical 
or practical to specify different test limit requirements for use on the same 
project.  In which case the lower limit required by the application should be used.<BRK/>
<BRK/>
The designer may use the specification method in UFGS Section 32 13 11 by incorporating 
the relevant paragraphs into this specification, or may use the following requirements 
(retain either the 0.10 or the 0.08 percent expansion limits as appropriate).included 
in the set of brackets highlighted thus "[ ]".</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.1.4.1   Composition</TTL><BRK/>
<BRK/>
<TXT>[Fine aggregate shall consist of natural sand, manufactured sand, or a combination of natural and manufactured 
sands.  Coarse aggregate shall consist of [gravel], [crushed gravel], [crushed stone], [air-cooled blast-furnace 
slag], or a combination thereof.] "[Fine and coarse aggregates proposed for use in concrete shall be tested and 
evaluated for alkali-aggregate reactivity in accordance with <RID>ASTM C 1260</RID>.  The fine and coarse aggregates shall 
be evaluated separately and in combination, which matches the Contractor's proposed mix design proportioning.  
All results of the separate and combination testing shall have a measured expansion less than 0.10 (0.08) percent 
at 16 days after casting.  Should the test data indicate an expansion of 0.10 (0.08) percent or greater, the 
aggregate(s) shall be rejected or additional testing using <RID>ASTM C 1260</RID> and <RID>ASTM C 1567</RID> shall be performed.  The 
additional testing using <RID>ASTM C 1260</RID> and <RID>ASTM C 1567</RID> shall be performed using the low alkali portland cement 
in combination with ground granulated blast furnace (GGBF) slag, or Class F fly ash.  GGBF slag shall be used 
in the range of 40 to 50 percent of the total cementitious material by mass.  Class F fly ash shall be used in 
the range of 25 to 40 percent of the total cementitious material by mass.]"</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4.2   Quality</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The tests selected should be those which are applicable to the concrete 
to be used in the project.  These tests may include those listed below in addition 
to others not listed.  See EM 1110-2-2000 for schedule of tests.</NPR><BRK/>
<BRK/>
<BRK/>
<NPR>Only a limited number of laboratories are now running ASTM C 123 due to the 
toxic chemicals required.  Recommend that ASTM C 295 be specified.</NPR><BRK/>
<BRK/>
<NPR>A list of properties and test values are unique to each project and should be 
taken from the concrete materials DM.  Delete the quality tests not required 
in the DM.</NPR><BRK/>
<BRK/>
<NPR>The petrographic examination shall be used to identify deleterious substances 
in aggregates.  Deleterious substances shall be listed individually with respective 
limits.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Aggregates delivered to the mixer shall meet the following requirements:</TXT><BRK/>
<BRK/>
<TBL><THD><HL4>TEST LIMITS</HL4><BRK/>
<BRK/>
        PROPERTY        FINE AGGREGATE     COARSE AGGREGATE       TESTS<BRK/>
<BRK/></THD>
  Specific Gravity         [_____]             [_____]        <RID>ASTM C 127</RID><BRK/>
                                                              <RID>ASTM C 128</RID><BRK/>
<BRK/>
  Absorption               [_____]             [_____]        <RID>ASTM C 127</RID><BRK/>
                                                              <RID>ASTM C 128</RID><BRK/>
<BRK/>
  Flat and Elongate        [_____]         25 percent max.   <RID>ASTM D 4791</RID><BRK/>
<BRK/>
  [Durability Factor       [_____]             [_____]     <RID>COE CRD-C 114</RID><BRK/>
  using (Procedure A)                                      <RID>ASTM C 666/C 666M</RID>]<BRK/>
<BRK/>
  [Clay Lumps and          [_____]             [_____]        <RID>ASTM C 142</RID>]<BRK/>
  Friable Particles<BRK/>
<BRK/>
  [Material Finer          [_____]             [_____]        <RID>ASTM C 117</RID>]<BRK/>
  than 75 µm (No. 200)<BRK/>
  Sieve<BRK/>
<BRK/>
  Liquid Limit and        LL 30 max.,          [_____]       <RID>ASTM D 4318</RID><BRK/>
<BRK/>
  Plastic Limit on        PI 10 max.<BRK/>
  material passing the<BRK/>
  75 µm (No. 200)<BRK/>
  sieve size<BRK/>
<BRK/>
  [Organic Impurities    Not Darker than       [_____]        <RID> ASTM C 40</RID><BRK/>
                         No. 3, Not less                      <RID> ASTM C 87</RID>]<BRK/>
                         than 95 percent<BRK/>
<BRK/>
  [L.A. Abrasion           [_____]             [_____]        <RID> ASTM C 131</RID><BRK/>
                                                              <RID> ASTM C 535</RID>]<BRK/>
<BRK/>
  [Soft Particles          [_____]             [_____]      <RID>COE CRD-C 130</RID>]<BRK/>
<BRK/>
  [Petrographic          List unwanted         [_____]         <RID>ASTM C 295</RID>]<BRK/>
  Examination            deleterious materials<BRK/>
                         and their limits<BRK/>
<BRK/>
  Percent coarse           [_____]         20 percent min.        [_____]<BRK/>
  aggregate with 2 or<BRK/>
  more fractured faces<BRK/>
<BRK/>
  [Chert, less than        [_____]             [_____]         <RID>ASTM C 123</RID><BRK/>
  2.40 specific gravity                                        <RID>ASTM C 295</RID>]<BRK/>
<BRK/>
  [Coal and Lignite,       [_____]             [_____]        <RID> ASTM C 123</RID>]<BRK/>
  less than 2.00                                            or <RID>ASTM C 295</RID><BRK/>
  specific gravity<BRK/>
<BRK/></TBL>
</SPT><SPT><TTL>2.1.4.3   Grading</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See DM for appropriate fine aggregate options.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  Fine Aggregate - The grading of the fine aggregate as delivered to the mixer for the RCC shall be 
such that the individual percent retained on any sieve shall not vary more than 3 percent from the percent 
retained on that sieve in a fixed grading selected by the Contractor after the first 30 days of concrete 
placement.  The minimum percent retained on each of the<MET> 2.36 mm</MET><ENG> No. 8</ENG> through<MET> 75 µm</MET><ENG> No. 200</ENG> sieve sizes 
shall be 5 percent.  In additional to the grading limits, the fine aggregate, as delivered to the mixer, 
shall have a fineness modulus of not less than 2.10 nor more than 2.75.  The grading of the fine aggregate 
shall also be controlled so that the fineness moduli for at least four of five consecutive test samples 
of the fine aggregate as delivered to the mixer shall not vary more than 0.10 from the fineness modulus 
of the fixed grading selected by the Contractor, and approved.  The fineness modulus shall be determined 
in accordance with <RID>COE CRD-C 104</RID>.  At the option of the Contractor, fine aggregate may be separated into 
two or more sizes or classifications, but the uniformity of the grading of the separate sizes shall be 
controlled so that they may be combined throughout the job in fixed proportions established during the 
first 30 days of RCC placement.  The grading of the fine aggregate for the bedding concrete and all other 
conventional concrete shall conform to the requirements of [<RID>ASTM C 33</RID>].  [Section [<SRF>03 31 00.00 10</SRF> CAST-IN-PLACE 
STRUCTURAL CONCRETE] [<SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE]]  The fixed grading and the results of individual 
tests during the first 30 days shall fall within the following limits:</LST><BRK/>
<BRK/>
<TBL><BRK/>
<THD>               SIEVE DESIGNATION                     PERMISSIBLE LIMITS<BRK/>
          U.S. STANDARD SQUARE MESH               PERCENT BY MASS, PASSING<BRK/>
<BRK/></THD>
               9.5 mm (3/8 in.)                                 100<BRK/>
               4.75 mm (No. 4)                                95 - 100<BRK/>
               2.36 mm (No. 8)                                75 -  95<BRK/>
               1.18 mm (No. 16)                               55 -  80<BRK/>
               600 µm (No. 30)                                35 -  60<BRK/>
               300 µm (No. 50)                                24 -  40<BRK/>
               150 µm (No. 100)                               12 -  28<BRK/>
                75 µm (No. 200)                               *8 -  18<BRK/>
      __________________________________________________________________<BRK/>
<BRK/>
Note:  *  The Contractor, at no additional cost to the Government, may substitute the required fines smaller than 
the<MET> 75 µm</MET><ENG> No. 200</ENG> sieve size with Class F fly ash.<BRK/></TBL>
<BRK/>
<LST>b.  Coarse Aggregate - The grading of the coarse aggregate within the separate size groups shall conform 
to the following requirements as delivered to the mixer.</LST><BRK/>
<TBL><BRK/>
<THD><HL4>PERCENT BY MASS PASSING INDIVIDUAL SIEVES</HL4><BRK/>
<BRK/>
                  4.75 mm (No. 4)   19.0 mm (3/4 in.)  37.5 mm (1-1/2 in.)<BRK/>
  U.S. STANDARD         to                 to                  to<BRK/>
   SIEVE SIZE     19.0 mm (3/4 in.)  37.5 mm (1-/2 in.)    75 mm (3 in.)<BRK/>
<BRK/></THD>
  100 mm (4 in.)                                                  100<BRK/>
  75 mm (3 in.)                                                 90 - 100<BRK/>
  50 mm (2 in.)                                100              20 -  55<BRK/>
  37.5 mm (1-1/2 in.)                        90 - 100            0 -  10<BRK/>
  25 mm (1 in.)             100              20 -  45            0 -   5<BRK/>
  19.0 mm (3/4 in.)       90 - 100            0 -  10<BRK/>
  9.5 mm (3/8 in.)        20 -  55            0 -   5<BRK/>
  4.75 mm (No 4)           0 -  10<BRK/>
  2.36 mm (No. 8)          0 -   5<BRK/></TBL>
<BRK/></SPT>
<SPT><TTL>2.1.4.4   Particle Shape</TTL><BRK/>
<BRK/>
<TXT>The shape of the particles of the fine aggregate and of the coarse aggregate shall be generally spherical or 
cubical.  The quantity of flat and elongated particles at a length-to-width or width-to-thickness ratio greater 
than 3 in the separated size groups of coarse aggregate, as defined and determined by <RID>ASTM D 4791</RID>, shall not 
exceed 25 percent in any size group.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4.5   Moisture Content</TTL><BRK/>
<BRK/>
<TXT>The fine aggregate shall not be placed in bins at the batch plant until it is in a stable state of moisture content.  
A stable moisture content shall be reached when the variation in the percent of total moisture tested in accordance 
with <RID>ASTM C 566</RID> and when sampled at the same location will not be more than 0.5 percent during one (1) hour of 
the two (2) hours prior to placing the material in the batch plant bins and the variation in moisture content 
when sampled at the same location shall not be more than 2.0 percent during the last 8-hour period that the aggregate 
remains in the stockpile.  The coarse aggregate shall be delivered to the mixers with the least amount of free 
moisture and the least variation in free moisture practicable under the job conditions.  Under no conditions 
shall the coarse aggregate be delivered to the mixer "dripping wet."</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4.6   [Commercial Concrete Aggregate Sources</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The list of sources and required tests will be taken from the concrete 
materials DM.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Concrete aggregates may be furnished from any source capable of meeting the quality requirements stated in paragraph 
QUALITY.  The following sources were evaluated during the design phase of the project in [19___] and were found 
at that time capable of meeting the quality requirements when suitably processed.  No guarantee is given or implied 
that any of the following listed sources are currently capable of producing aggregates that meet the required 
quality stated in paragraph QUALITY.  A DM containing the results of the Government investigation and test results 
is available for review in the [_____] District Office.  Contact [_____] at [_____] to arrange for review of 
the DM.  The test results and conclusions shall be considered valid only for the sample tested and shall not 
be taken as an indication of the quality of all material from a source nor for the amount of processing required.</TXT><BRK/>
<BRK/>
<LST>a.  List of Sources</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The concrete materials DM will list those sources requiring low-alkali 
cement, which must be noted herein.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TBL>      FINE AGGREGATE:<BRK/>
<BRK/>
      F1:  [_____] [1/]<BRK/>
      F2:  [_____]<BRK/>
      F3:  [_____]<BRK/>
<BRK/>
      [1/  Low-alkali cement must be used with these sources.]<BRK/>
<BRK/>
      COARSE AGGREGATE:<BRK/>
<BRK/>
      C1:  [_____] [1/]<BRK/>
      C2:  [_____]<BRK/>
      C3:  [_____]<BRK/>
<BRK/>
      [1/  Low-alkali cement must be used with these sources.]<BRK/></TBL>
<BRK/>
<LST>b.  Selection of Source - After the award of the contract, the Contractor shall designate in writing 
only one source or combination of sources from which he proposes to furnish aggregates.  If the Contractor 
proposes to furnish aggregates from a source or sources not listed above, he may designate only a single 
source or single combination of sources for aggregates.  Regardless of the source selected, samples for 
quality-assurance testing shall be provided as required by PART 1, paragraph PRECONSTRUCTION, TESTING, 
AND MIXTURE-PROPORTIONING STUDIES.  If a source for coarse or fine aggregate so designated by the Contractor 
does not meet the quality requirements stated in paragraph QUALITY, the Contractor may not submit for 
approval any other unlisted sources but shall furnish the coarse or fine aggregate, as the case may be, 
from sources listed, provided it meets the requirements of paragraph QUALITY, at no additional cost to 
the Government].</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4.7   [Government-Furnished Concrete Aggregate Source</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The specification writer should ascertain that restoration of the pit 
or quarry site is specified under other sections.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  Location - The deposits are [owned] [controlled] by the Government and are made available to the 
Contractor free of charge for production of aggregate required under this contract.  Within the designated 
area, an adequate supply of material is available from which concrete aggregate meeting the requirement 
of these specifications can be produced with suitable processing.  The Government guarantees that a sufficient 
amount of material of suitable quality for production of all of the concrete aggregate required is available 
within the deposit and that concrete aggregates of suitable quality can be produced with a properly designed 
and operated plant [without hand-picking or similar operations].  However, the amount of work involved 
or the amount of unsatisfactory materials required to be wasted to produce a sufficient quantity of suitable 
concrete aggregate shall be the responsibility of the Contractor, and the Government shall not be held 
liable for costs resulting from such work or waste.  The Contractor shall produce the concrete aggregate 
from the following sites as shown in the drawings:</LST><BRK/>
<BRK/>
<NED/><TBL><BRK/>
<THD>      QUARRY SITE    BAR    TERRACE   COORDINATES    DIST. and DIRECTION<BRK/>
<BRK/></THD>
  G1  ___________    ___    _______   ___________    __________________<BRK/>
  G2  ___________    ___    _______   ___________    ___________________<BRK/>
  G3  ___________    ___    _______   ___________    ___________________<BRK/></TBL>
<BRK/>
<LST>b.  Explorations - The deposits listed above have been explored by the Government to determine the character 
and extent of the materials available.  The locations of the explorations are shown in the contract drawings.  
The logs of the exploratory holes are also shown in the drawings.  Samples of materials secured are available 
for inspection at [_____].  The results of explorations are furnished for information only.  These data 
are the result of limited explorations and tests conducted by and for the Government and are accurate 
to the extent of the scope of the investigations conducted.  The Government will not be responsible for 
any deduction, interpretation, or conclusion drawn therefrom by the Contractor.]</LST><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>2.2   MIXTURE PROPORTIONING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Contact the materials engineer or the concrete materials DM for information 
on filling in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.2.1   Composition</TTL><BRK/>
<BRK/>
<TXT>All concrete mixtures will be proportioned by the Contracting Officer [except that proportions for the slipformed 
facing concrete mixture will be selected by the Contractor].  RCC shall be composed of cementitious materials, 
water, fine and coarse aggregates, and possibly admixtures.  The cementitious material shall be portland cement, 
or portland cement in combination with pozzolan.  An admixture when approved or directed will be a water-reducing/retarding 
admixture.  Air-entraining admixture will be used in the bedding concrete and other conventional concrete.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2   Proportions</TTL><BRK/>
<BRK/>
<TXT>RCC mixtures and all conventional concrete mixtures that interface with the RCC (such as facing concrete and 
bedding mixtures) will be proportioned by the Contracting Officer [except that slipformed facing concrete mixture 
will be proportioned by the Contractor].  There will be one primary RCC mixture used for the mass of the dam 
[, _____,] [and _____].  The primary mixture will contain approximately [_____] to [_____]<MET> kg</MET><ENG> pounds</ENG> water, [_____]<MET>
 kg</MET><ENG> pounds</ENG> portland cement and [_____]<MET> kg</MET><ENG> pounds</ENG> pozzolan per cubic<MET> meter</MET><ENG> yard</ENG>.  [Secondary RCC mixtures requiring 
higher portland cement and pozzolan contents (approximately [_____] to [_____]<MET> kg</MET><ENG> pounds</ENG> per cubic<MET> meter</MET><ENG> yard</ENG>
) will be used for [_____] [, _____,] [and _____].]  There also will be a "bedding mortar" and "bedding concrete."  
The bedding mortar is a broomable mixture containing approximately<MET> 280 to 355 kg</MET><ENG> 475 to 600 pounds</ENG> of portland 
cement and<MET> 135 to 180 kg</MET><ENG> 225 to 300 pounds</ENG> pozzolan per cubic<MET> meter</MET><ENG> yard</ENG>.  The bedding mortar will have<MET> 9.5 mm</MET><ENG>
 3/8-inch</ENG> nominal maximum size aggregate and a slump, when placed, of<MET> 175 to 225 mm</MET><ENG> 7 to 9 inches</ENG>.  The bedding 
concrete, <MET>75 to 100 mm</MET><ENG> 3 to 4 inch</ENG> slump conventional concrete, shall contain<MET> 19.0 mm</MET><ENG> 3/4-inch</ENG> nominal maximum 
size aggregate and approximately [_____]<MET> kg</MET><ENG> pounds</ENG> of portland cement and pozzolan per cubic<MET> meter</MET><ENG> yard</ENG>.  The 
air content of the bedding concrete as delivered to the placement site shall be between 4.5 and 7.5 percent.  
[Preliminary mixture proportioning studies are available for review in the District office.]  Concrete mixtures 
used for [the upstream face] [, and _____,] and other conventional concrete mixtures shall contain from [_____] 
to [_____]<MET> kg</MET><ENG> pounds</ENG> of cementitious materials and the slump shall be between<MET> 25 and 100 mm</MET><ENG> 1 and 4 inches</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3   Proportioning Responsibility</TTL><BRK/>
<BRK/>
<TXT>The proportions of all materials entering the RCC and the conventional concrete will be furnished.  The proportions 
will be changed as necessary by the Government.  Adjustments will be made to the batch weights, including cement, 
pozzolan, and water, to maintain the necessary consistency to prevent segregation within the RCC and allow full 
compaction as determined.  Frequent changes to the batch weights shall be considered usual and can be expected 
to occur frequently during the course of each day's placement depending on such variables as humidity, wind velocity, 
temperature, and cloud cover.  Such changes will be as directed.  The Contractor will be responsible for adjusting 
the added water to compensate for changes in aggregate moisture content and to adjust the amount of air-entraining 
admixture (if used) to keep the percent of air within the specified range.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.4   Nominal Maximum Size of Aggregate</TTL><BRK/>
<BRK/>
<TXT>The nominal maximum size of coarse aggregate to be used in the various parts of the work shall be in accordance 
with following:</TXT><BRK/>
<TBL><BRK/>
<THD>                                                     NOMINAL MAXIMUM SIZE<BRK/>
                FEATURES                                   AGGREGATE<BRK/>
<BRK/></THD>
[RCC used in the main concrete gravity dam]              75 mm (3 in.)<BRK/>
[RCC used in construction of the [_____]]<BRK/>
[Conventional concrete for the upstream face]<BRK/>
[Conventional concrete for the [_____]]<BRK/>
[RCC used in the [_____]                               37.5 mm (1-1/2 in.)]<BRK/>
[RCC used in the [_____]]<BRK/>
[Conventional concrete for [_____]]<BRK/>
[Conventional concrete bedding mixture]                19.0 mm (3/4 in.)<BRK/>
[Bedding mortar]                                       4.75 mm (No. 4)<BRK/>
<BRK/>
Note: The nominal maximum size aggregate may be changed for applications requiring a special quality of concrete 
as directed.<BRK/></TBL>
<BRK/></SPT>
<SPT><TTL>2.2.5   Consistency of RCC</TTL><BRK/>
<BRK/>
<TXT>The Contracting Officer will determine at the placement site on a continuing basis the proper consistency necessary 
for adequate hauling, spreading, and compacting and will direct all necessary changes to achieve the proper RCC 
consistency.  Changes will be directed based on visual examination of the RCC during the spreading and compaction 
process and on the Vebe time when it varies outside the range considered ideal for compaction, as determined 
by the Government using the modified Vebe apparatus, in accordance with <RID>COE CRD-C 53</RID>.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   <SUB>EQUIPMENT</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>3.1.1   Capacity</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM or EM 1110-2-2000 for the plant size requirements.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The concrete plant, conveying, placing, compaction, and cleanup systems shall have a capacity of at least [_____] 
cubic<MET> meters</MET><ENG> yards</ENG> per hour.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2   Concrete Plant</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See EM 1110-2-2000 and the concrete materials DM for selection of automatic 
or semiautomatic plant and for use of the rescreening and washing plant.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The concrete plant shall be a batch or a continuous mixing plant.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.2.1   Location</TTL><BRK/>
<BRK/>
<TXT>The concrete plant shall be located at the site of the work in the general area indicated in the drawings[, or 
shall be located offsite].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2.2   Bins and Silos</TTL><BRK/>
<BRK/>
<TXT>Separate bins, compartments, or silos shall be provided for each size or classification of aggregate and for 
each of the cementitious materials.  The compartments shall be of ample size and so constructed that the various 
materials will be maintained separately under all working conditions.  All compartments containing bulk cement 
or pozzolan shall be separated from each other by a free-draining air space.  The cement and pozzolan bins shall 
be equipped with filters which allow air passage but preclude the venting of cement or pozzolan into the atmosphere.  
All filling ports shall be clearly marked with a permanent sign stating the contents.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2.3   <SUB>Batch Plant</SUB></TTL><BRK/>
<BRK/>
<TXT>The batch plant requirements should meet the following requirements.</TXT><BRK/>
<BRK/>
<LST>a.  Batchers - Aggregate shall be weighed in separate weigh batchers with individual scales [or may be 
batched cumulatively].  Bulk cement and other cementitious materials shall each be weighed on a separate 
scale in a separate weigh batcher.  Water shall be measured by weight or by volume.  It shall not be 
weighed or measured cumulatively with another ingredient.  Ice shall be measured separately by weight.  
Admixtures shall be batched separately and shall be batched by weight or by volume in accordance with 
the manufacturers recommendations.</LST><BRK/>
<BRK/>
<LST>b.  Water Batcher - A suitable water-measuring and batching device shall be provided that will be capable 
of measuring and batching the mixing water within the specified tolerances for each batch.  The mechanism 
for delivering water to the mixers shall be free from leakage when the valves are closed.  The filling 
and discharge valves for the water batcher shall be so interlocked that the discharge valve cannot be 
opened before the filling valve is fully closed.  When a water meter is used, a suitable strainer shall 
be provided ahead of the metering device.</LST><BRK/>
<BRK/>
<LST>c.  Admixture Dispensers - A separate batcher or dispenser shall be provided for each admixture.  Each 
plant shall be equipped with the necessary calibration devices that will permit convenient checking of 
the accuracy of the dispensed volume of the particular admixture.  The batching or dispensing devices 
shall be capable of repetitively controlling the batching of the admixtures to the accuracy specified.  
Piping for liquid admixtures shall be free from leaks and properly valved to prevent backflow or siphoning.  
The dispensing system shall include a device or devices that shall detect and indicate the presence or 
absence of the admixture or provide a convenient means of visually observing the admixture in the process 
of being batched or discharged.  Each system shall be capable of ready adjustment to permit varying the 
quantity of admixture to be batched.  Each dispenser shall be interlocked with the batching and discharge 
operations so that each admixture is added separately to the batch in solution in a separate portion 
of the mixing water in a manner to ensure uniform distribution of the admixtures throughout the batch 
during the required mixing period.  Storage and handling of admixtures shall be in accordance with the 
manufacturer's recommendations.</LST><BRK/>
<BRK/>
<LST>d.  Moisture Control - The plant shall be capable of ready adjustment to compensate for the varying moisture 
content of the aggregates and to change the masses of the materials being batched.  A moisture meter 
complying with the provisions of <RID>COE CRD-C 143</RID>shall be provided for measurement of moisture in the fine 
aggregate.  The sensing element shall be arranged so that the measurement is made near the batcher charging 
gate of the sand bin or in the sand batcher.</LST><BRK/>
<BRK/>
<LST>e.  Scales - Adequate facilities shall be provided for the accurate measurement and control of each of 
the materials entering each batch of concrete.  The weighing equipment and controls shall conform to 
the applicable requirements of <RID>NIST HB 44</RID>, except that the accuracy shall be within 0.2 percent of the 
scale capacity.  The Contractor shall provide standard test weights and any other auxiliary equipment 
required for checking the operating performance of each scale or other measuring device.  Tests shall 
be made at the frequency required in paragraph TESTS AND INSPECTIONS and in the presence of a Government 
inspector.  Each weighing unit shall include a visible indicator that shall indicate the scale load at 
all stages of the weighing operation and shall show the scale in balance at zero load.  The weighing 
equipment shall be arranged so that the concrete plant operator can conveniently observe the indicators.</LST><BRK/>
<BRK/>
<LST>f.  Operation and Accuracy - [The weighing operation of each material shall start automatically when 
actuated by a single starter switch and shall end automatically when the designated amount of each material 
has been reached.  These requirements can be met by providing an automatic batching system as defined 
in the <RID>NRMCA CPMB 100</RID>.]  [The weighing operation of each material shall begin automatically when actuated 
by one or more starter switches and shall end when the designated amount of each material has been reached.  
These requirements can be met by providing a semiautomatic or automatic batching system as defined by 
the <RID>NRMCA CPMB 100</RID>.]  There shall be equipment to permit the selection of [_____] preset mixtures each 
by the movement of not more than two switches or other control devices.  The weigh batchers shall be 
so constructed and arranged that the sequence and timing of batcher discharge gates can be controlled 
to produce a ribboning and mixing of the aggregates, water, admixtures, and cementitious materials as 
the materials pass through the charging hopper into the mixer.  The plant shall include provisions to 
facilitate the inspection of all operations at all times.  Delivery of materials from the batching equipment 
shall be within the following limits of accuracy:</LST><BRK/>
<TBL><BRK/>
<THD>                                                              PERCENT OF<BRK/>
                   MATERIAL                                 REQUIRED MASS<BRK/>
<BRK/></THD>
          Cementitious materials .............................. 0 to +2<BRK/>
          Water .................................................... ±1<BRK/>
          Aggregate smaller than<BRK/>
            37.5 mm (1-1/2 in.) size ............................... ±2<BRK/>
          Aggregate larger than<BRK/>
            37.5 mm (1-1/2 in.) size ............................... ±3<BRK/>
          Chemical admixtures ................................. 0 to +6<BRK/>
<BRK/>
Note: When water or chemical admixtures are measured by volume, they shall meet the same tolerance percent as stated 
in the chart.<BRK/></TBL>
<BRK/>
<LST>g.  Interlocks - Batchers and mixers shall be interlocked so that:</LST><BRK/>
<BRK/>
<ITM>(1)  The charging device of each batcher cannot be actuated until all scales have returned to 
zero balance within plus or minus 0.2 percent of the scale capacity and each volumetric device 
has reset to start or has signaled empty.</ITM><BRK/>
<BRK/>
<ITM>(2)  The charging device of each batcher cannot be actuated if the discharge device is open.</ITM><BRK/>
<BRK/>
<ITM>(3)  The discharge device of each batcher cannot be actuated if the charging device is open.</ITM><BRK/>
<BRK/>
<ITM>(4)  The discharge device of each batcher cannot be actuated until the indicated material is 
within the allowable tolerances.</ITM><BRK/>
<BRK/>
<ITM>(5)  Admixtures are batched automatically and separately with the water.</ITM><BRK/>
<BRK/>
<ITM>(6)  The mixers cannot be discharged until the required mixing time has elapsed.</ITM><BRK/>
<BRK/>
<LST>h.  Recorder - An accurate recorder or recorders shall be provided and shall conform to the following 
detailed requirements:</LST><BRK/>
<BRK/>
<ITM>(1)  The recorder shall produce a graphical or digital record on a single visible chart or tape 
of the weight or volume of each material in the batchers at the conclusion of the batching cycle.  
The record shall be produced prior to delivery of the materials to the mixer.  After the batchers 
have been discharged, the recorder shall show the return to empty condition.</ITM><BRK/>
<BRK/>
<ITM>(2)  A graphical recording or digital printout unit shall be completely housed in a single cabinet 
that shall be capable of being locked.</ITM><BRK/>
<BRK/>
<ITM>(3)  The chart or tape shall be so marked that each batch may be permanently identified and 
so that variations in batch weights of each type of batch can be readily observed.  The chart 
or tape shall be easily interpreted in increments not exceeding 0.5 percent of each batch weight.</ITM><BRK/>
<BRK/>
<ITM>(4)  The chart or tape shall show time of day at intervals of not more than 15 minutes.</ITM><BRK/>
<BRK/>
<ITM>(5)  The recorder chart or tape shall become the property of the Government.</ITM><BRK/>
<BRK/>
<ITM>(6)  The recorder shall be placed in a position convenient for observation by the concrete plant 
operator and the Government inspector.</ITM><BRK/>
<BRK/>
<ITM>(7)  The recorded weights or volumes when compared to the weights or volumes actually batched 
shall be accurate within plus or minus 2 percent.</ITM><BRK/>
<BRK/>
<LST>i.  Batch Counters - The plant shall include devices for automatically counting the total number of batches 
of all concrete batched and the number of batches of each preset mixture.</LST><BRK/>
<BRK/>
<LST>[j.  Rescreening Plant - A rescreening plant shall be located, arranged, and operated in a manner that 
all coarse aggregate will be routed through the plant and that its operation will ensure delivery to 
the mixers of graded coarse aggregate free from variation and conforming to the size groups and grading 
of paragraph AGGREGATES and with moisture content conforming to the provisions of paragraph TESTS AND 
INSPECTION.  Coarse aggregate may be rescreened and delivered to the batch plant bins one size group 
at a time or two or more adjacent size groups at a time. Simultaneous rescreening of nonadjacent size 
groups is not permitted.  All material passing the bottom screen of the smallest size of coarse aggregate 
being screened shall be wasted.]</LST><BRK/>
<BRK/>
<LST>[k.  Washing Plant - All coarse aggregates shall be washed immediately prior to entering the rescreening 
plant.  The washing plant shall contain adequate water nozzles and vibrating screens to remove foreign 
materials and coatings from aggregate particles.  Water used for washing shall meet the requirements 
of paragraph WATER.]</LST><BRK/>
<BRK/>
<LST>l.  Batch Plant Trial Operation - Not less than 7 days prior to commencement of placing the test section, 
a test of the batching and mixing plant shall be made in the presence of a representative of the Contracting 
Officer to check operational adequacy.  The number of full-scale concrete batches required to be produced 
in trial runs shall be as directed, will not exceed 20, and shall be proportioned as directed by the 
Contracting Officer.  All concrete produced in these tests shall be wasted or used for purposes other 
than inclusion in structures covered by this specification.  All deficiencies found in plant operation 
shall be corrected to the satisfaction of the Contracting Officer prior to the start of concrete placing 
operations.  No separate payment will be made to the Contractor for labor or materials required by provisions 
of this paragraph.  Mixer uniformity testing, in accordance with paragraph TESTS AND INSPECTION, will 
be performed by the government near the end of this trial operation period.  The Contractor shall notify 
the Contracting Officer of the trial operation not less than 7 days prior to the start of the trial operation.</LST><BRK/>
<BRK/>
<LST>m.  Protection - The weighing, indicating, recording, and control equipment shall be protected against 
exposure to dust, moisture, and vibration so that there is no interference with proper operation of the 
equipment.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2.4   Continuous Mixing Plant(s)</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM or consult the materials engineer to fill 
in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>A continuous mixing plant(s) shall be capable of producing RCC of the same quality and uniformity as would be 
produced in a conventional batch plant and shall be capable of producing a uniform continuous product (at both 
maximum and minimum production rates) that is mixed so that complete intermingling of all ingredients occurs 
without balling, segregation, and wet or dry portions.</TXT><BRK/>
<BRK/>
<LST>a.  Operation and Accuracy - An electronic control system shall be provided.  The control system shall 
have the capability of changing mixtures instantaneously, producing at least [_____] different mixtures, 
producing any of the mixtures at a variable rate, and tracking a mixture change to a hopper or a conveyor 
system.  The control panel shall display for each ingredient the designed formula values and the instantaneous 
percentage values and shall record the instantaneous values at a preset time interval or on demand with 
a multiple copy printer/recorder.  The recorder shall note formula changes and shall print total quantities 
of each ingredient and total amounts produced on command.  There shall be weighing devices (belt scale 
or other) for continuous weighing of individual ingredients and total ingredients.  The plant control 
shall not require manual devices to adjust the material flow.  The plant shall be capable of total manual 
control operation for a single product at a limited production for short-time durations in the event 
of loss of electronic control.  The electronic control system shall incorporate modular replaceable components 
to reduce down time in the event of control system malfunction.  An inventory shall be maintained of 
such replaceable components.  The fine aggregate shall have a device that monitors its content immediately 
prior to dispensing into the mixing plant dispensing system.  The accuracy of the plant dispensing systems 
shall be within the following limits:</LST><BRK/>
<TBL><BRK/>
          Pozzolan ...................................... 0 to +2 percent<BRK/>
          Cement ........................................ 0 to +2 percent<BRK/>
          Water ............................................. ± 1 percent<BRK/>
          Aggregate smaller than<BRK/>
            37.5 mm (1-1/2 in.) size ........................ ± 2 percent<BRK/>
          Aggregate larger than<BRK/>
            37.5 mm (1-1/2 in.) size ........................ ± 3 percent<BRK/>
          Admixtures .................................... 0 to +6 percent<BRK/>
<BRK/>
Note: The continuous feeders for each of the ingredients shall be calibrated in accordance with the manufacturer's 
specifications.  Devices and tools shall be maintained at the plant location to check the feeder's calibration at 
the Contracting Officer's request.  A technician shall be provided that is skilled in calibration of the feed devices 
and the maintenance and repair of the plant control system.  The technician shall be available within 30 minutes 
notice during all scheduled plant operations.  The technician could be one or more of the Contractor's personnel.<BRK/></TBL>
<BRK/>
<LST>b.  Cement, Pozzolan, and Aggregate Feed - Cement, pozzolan, and aggregate shall be uniformly, continuously, 
and simultaneously fed (at the proper ratios and quantity for the mixture required) into the mixer by 
belt, auger, vane feeder, or other acceptable method.  The feed bins or silos for each ingredient shall 
be kept sufficiently full and shall be of sufficient size to ensure a uniform flow at a constant rate 
for a specific mixture.  The feed bins shall have a low-level indicator that both warns the operator 
and can shut the plant down if insufficient material is available for a uniform and continuous flow.</LST><BRK/>
<BRK/>
<LST>c.  Water and Admixture Dispensers - The liquid-dispensing devices shall be capable of metering and dispensing 
within the specified requirements.  The liquid valves shall be free from leakage in the closed position.  
The dispensers shall have attachments and/or be installed in such a manner that will permit convenient 
checking of their accuracy.  Plumbing shall be leak-free and properly valved to prevent backflow and 
siphoning.  The dispenser shall be interlocked with the electronic plant control and shall warn the operator 
and shut down the plant if insufficient liquid is available.  Separate nozzles for each liquid shall 
be properly located at the mixer to assure uniform distribution of each liquid to the materials entering 
the mixer.</LST><BRK/>
<BRK/>
<LST>d.  Continuous Mixer(s) - The continuous mixer(s) shall have proper introduction of ingredients as specified 
by the manufacturer and shall not be charged in excess of the manufacturer's recommended capacity.  Mixer(s) 
shall be capable of combining the materials into a uniform homogeneous mixture and of discharging this 
mixture without segregation.  The mixer(s) shall operate at the blade speed designated by the manufacturer 
and shall be capable of changing retention time of the ingredients in the mixer.  This should be accomplished 
by manually resetting the mixer(s) blade angles.  Mixing time (ingredient retention time in the mixer) 
shall be predicated upon the uniformity, homogeneity, and consistency of the resultant mixture.  Samples 
for uniformity testing shall be taken at 2-minute intervals and tested in accordance with <RID>COE CRD-C 55</RID>
 and paragraph REQUIREMENT.  The mixer(s) shall be maintained in satisfactory operating condition and 
mixer blades shall be kept free of hardened concrete.  Should mixer(s) at any time produce unsatisfactory 
results, its use shall be promptly discontinued until it is repaired.  Suitable facilities shall be provided 
for obtaining representative samples of concrete for testing.  All necessary platforms, shelters, tools, 
labor, and equipment shall be provided for obtaining samples.</LST><BRK/>
<BRK/>
<LST>e.  Segregation - A means shall be used to reduce and minimize segregation and waste which would otherwise 
result from the continuous stream of concrete being fed into the batch haul devices (concrete buckets, 
dump trucks, etc.).  The equipment shall retain the concrete between tracks or other means of transport 
to prevent the need for stopping the mixer.  These devices could include, but not be limited to, small-volume 
conveyor discharge hopper with a large gate that is automatically opened on a timed interval, thereby 
dumping a series of small batches into larger batch hoppers, trucks, or truck beds.</LST><BRK/>
<BRK/>
<LST>f.  Trial operation - Not less than 7 days prior to commencement of concrete placing, a test of the plant 
shall be made in the presence of a representative of the Contracting Officer to check operational adequacy.  
The number of cubic<MET> meters</MET><ENG> yards</ENG> required to be produced in trial runs shall be as directed, but will 
not exceed<MET> 40 cubic meters</MET><ENG> 50 cubic yards</ENG> and shall be proportioned as directed by the Contracting Officer.  
All concrete produced in these tests shall be wasted or used for purposes other than inclusion in structures 
covered by this specification.  All deficiencies found in plant operation shall be corrected to the satisfaction 
of the Contracting Officer prior to the start of concrete placing operations.  Mixer uniformity tests 
by the Government will be performed near the end of this trial period.  No separate payment will be made 
to the Contractor for labor or materials required by provisions of this paragraph.  The Contractor shall 
notify the Contracting Officer of the trial operation not less than 7 days prior to the start of the 
trial operation.</LST><BRK/>
<BRK/>
<LST>g.  Protection - The weighing, indicating, recording, and control equipment shall be protected against 
exposure to dust, moisture, and vibration so that there is no interference with proper operation of the 
equipment.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2.5   Laboratory Areas</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The specification writer should use the alternate sentence and fill in 
the correct section number unless a laboratory building is to be government 
furnished.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>A room shall be provided adjacent to the plant to house the moisture and grading testing equipment for aggregate 
and to provide working space for the Government representative.  Another room shall be provided for testing fresh 
concrete and for fabricating and initial curing (approximately 72 hours) of concrete test specimens in accordance 
with <RID>ASTM C 31/C 31M</RID>.  The size, arrangement, and location of these rooms will be subject to approval by the 
Contracting Officer.  The Contractor shall provide electricity, air-conditioning, heat, and water as required 
for use in these laboratory areas.  [[Section <SRF>[_____]</SRF>] [_____] of these specifications presents requirements 
for a separate building equipped for a testing laboratory.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.1.3   <SUB>Mixers</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM for information on mixer selection and 
concrete mixers.  Truck mixers shall not be allowed for mixing or transporting 
RCC or conventional concrete with less than 50 mm (2 inch) slump or greater 
than 37.5 mm (1-1/2 inch) nominal maximum size aggregate (NMSA).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Mixers shall be stationary mixers or pugmill mixers.  [Truck mixers may be used for conventional concrete].  
Mixers may be batch or continuous mixing.  Each mixer shall combine the materials into a uniform mixture and 
discharge this mixture without segregation.  Mixers shall not be charged in excess of the capacity recommended 
by the manufacturer on the nameplate.  Excessive overmixing requiring additions of water will not be permitted.  
The mixers shall be maintained in satisfactory operating condition, and mixer drums shall be kept free of hardened 
concrete.  Mixer blades or paddles shall be replaced when worn down more than 10 percent of their depth when 
compared with the manufacturer's dimension for new blades.  Should any mixer at any time produce unsatisfactory 
results, its use shall be promptly discontinued until it is repaired or replaced.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.3.1   [Truck Mixers</TTL><BRK/>
<BRK/>
<TXT>Truck mixers and the mixing of concrete therein shall conform to the requirements of <RID>ASTM C 94/C 94M</RID>.  A truck 
mixer may be used for conventional concrete complete mixing (transit-mixed) or to finish the partial mixing done 
in a stationary mixer (shrink-mixed).  Each truck shall be equipped with two counters from which it shall be 
possible to determine the number of revolutions at mixing speed and the number of revolutions at agitating speed.  
Truck mixers shall not be used to mix or agitate concrete with greater than<MET> 37.5 mm</MET><ENG> 1-1/2 inches</ENG> NMSA or concrete 
with a slump of<MET> 50 mm</MET><ENG> 2 inches</ENG> or less.  The acceptability of truck mixers for uniform mixing shall be determined 
by uniformity tests in accordance with <RID>ASTM C 94/C 94M</RID>.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.2   Pugmill Mixers</TTL><BRK/>
<BRK/>
<TXT>A batch or continuous mixing twin-shaft pugmill mixer shall be capable of producing RCC of the same quality and 
uniformity as would be produced in a conventional plant that meets all the requirements of these specification.  
All pugmill mixers shall meet the requirements of paragraph CONTINUOUS MIXING PLANT(S).</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3.3   Mixer Uniformity Requirements</TTL><BRK/>
<BRK/>
<TXT>All mixers, except for truck mixers, shall be tested by the Government in accordance with this paragraph and 
in accordance with <RID>COE CRD-C 55</RID>.  When regular testing is performed, the conventional concrete shall meet the 
limits of any five of the six applicable uniformity requirements, and the RCC shall meet the limits of any three 
of the four applicable uniformity requirements.  When abbreviated testing is performed, the concrete shall meet 
only those requirements listed for abbreviated testing.  The initial mixer evaluation test shall be a regular 
test and shall be performed prior to the start of concrete placement.  The concrete proportions used for the 
evaluation shall contain the largest size aggregate on the project and shall be as directed by the Contracting 
Officer.  Regular testing shall consist of performing all tests on three batches of concrete.  The range for 
regular testing shall be the average of the ranges of the three batches.  Abbreviated testing shall consist of 
performing the required tests on a single batch of concrete.  The range for abbreviated testing shall be the 
range for one batch.  If more than one mixer is used and all are identical in terms of make, type, capacity, 
condition, speed of rotation, etc., the results of tests on one of the mixers shall apply to the others, subject 
to the approval of the Contracting Officer.  Mixer evaluations shall be performed by the Government.  The Contractor 
shall provide labor and equipment as directed by the Contracting Officer to assist the Government in performing 
the tests.</TXT><BRK/>
<MET><TBL><THD><BRK/>
                                           REGULAR TESTS  ABBREVIATED<BRK/>
                                           ALLOWABLE      TESTS<BRK/>
                                           MAXIMUM RANGE  ALLOWABLE<BRK/>
              PARAMETER                    FOR AVERAGE    MAXIMUM RANGE<BRK/>
                                           OF 3 BATCHES   FOR 1 BATCH<BRK/>
<BRK/></THD>
  Unit weight of air-free mortar, kg/cu m1) 16          16<BRK/>
  Air content, percent1)                          1.0         --<BRK/>
  Slump, mm1)                                      25         --<BRK/>
  Coarse aggregate, percent1),2)                  6.0          6.0<BRK/>
  Compressive strength at 7 days1),2)            10.0         10.0<BRK/>
  Water content1),2), percent                     1.5          1.5<BRK/>
  Consistency, modified Vebe2), second            7.0         --<BRK/>
<BRK/>
  Note:  1) = Test for conventional concrete mixed in stationary mixer,<BRK/>
         2) = Test for RCC<BRK/></TBL>
</MET> <ENG><TBL><BRK/>
<THD>                                                                  <BRK/>
                                             REGULAR TESTS  ABBREVIATED<BRK/>
                                             ALLOWABLE      TESTS<BRK/>
                                             MAXIMUM RANGE  ALLOWABLE<BRK/>
              PARAMETER                      FOR AVERAGE    MAXIMUM RANGE<BRK/>
                                             OF 3 BATCHES   FOR 1 BATCH <BRK/>
<BRK/></THD>
  Unit weight of air-free mortar, lb/cu ft1)  2.0         2.0<BRK/>
  Air content, percent1)                           1.0          --<BRK/>
  Slump, in.1)                                     1.0          --<BRK/>
  Coarse aggregate, percent1),2)                   6.0          6.0<BRK/>
  Compressive strength at 7 days1),2)             10.0         10.0<BRK/>
  Water content1),2), percent                      1.5          1.5<BRK/>
  Consistency, modified Vebe2), second             7.0          --<BRK/>
<BRK/>
  Note:  1) = Test for conventional concrete mixed in stationary mixer,<BRK/>
         2) = Test for RCC<BRK/></TBL>
</ENG><BRK/>
<TXT>A regular test will be performed before concrete production begins and when the Contractor requests a reduced 
mixing time.  An abbreviated test shall be performed every 3 months when concrete is being placed.  If a mixer 
fails the abbreviated test, a regular test will be performed.  Cost of testing when the Contractor requests a 
reduced mixing time will be paid by the Contractor.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.1.4   Sampling Facilities</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1.4.1   Sampling Concrete</TTL><BRK/>
<BRK/>
<TXT>The Contractor shall provide suitable facilities and labor for obtaining representative samples of concrete in 
accordance with <RID>ASTM C 172</RID> for Contractor quality control and Government quality assurance testing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.4.2   Sampling Aggregates</TTL><BRK/>
<BRK/>
<TXT>Suitable facilities shall be provided for readily obtaining representative samples of aggregates for test purposes 
immediately prior to the material entering the mixer.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.1.5   <SUB>Transporting and Conveying Equipment</SUB></TTL><BRK/>
<BRK/>
<TXT>The transporting and conveying equipment shall conform to the following requirements.</TXT><BRK/>
<BRK/>
<LST>a.  The concrete mixtures (RCC, bedding mortar, concrete, and any other concrete that will interface 
with the RCC) shall be conveyed from the plant mixer(s) to placement as rapidly and as continuously as 
practical by methods which limit segregation, contamination, and surface drying.</LST><BRK/>
<BRK/>
<LST>b.  The RCC shall be conveyed from the mixing plant to the structure by means of main-line conveyor, 
end-dump truck, front-end loader, or a combination thereof.</LST><BRK/>
<BRK/>
<LST>c.  Conventional concrete may be transported by ready-mix truck, conveyor, or agitator truck, or properly 
designed nonagitating truck.</LST><BRK/>
<BRK/>
<LST>d.  Indicating and signaling devices shall be provided for the control and identification of types or 
classes of concrete as they are mixed and discharged for transfer to the placement site.</LST><BRK/>
<BRK/>
<LST>e.  Each type or class of concrete shall be visually identified by placing a colored tag or other marker 
as it leaves the mixing plant so that the concrete may be positively identified and placed in the structure 
in the desired position.</LST><BRK/>
<BRK/>
<SPT><TTL>3.1.5.1   Trucks</TTL><BRK/>
<BRK/>
<TXT>Truck mixers or agitators used for transporting central-mixed conventional concrete shall conform to the applicable 
requirements of <RID>ASTM C 94/C 94M</RID>.  Truck mixers shall not be used to transport concrete with larger than<MET> 37.5 
mm</MET><ENG> 1-1/2-inch</ENG> nominal maximum size aggregate (NMSA) or<MET> 50 mm</MET><ENG> 2 inch</ENG> slump, or less.  Nonagitating trucks may 
be used for transporting conventional central-mixed concrete over a smooth road when the hauling time is less 
than 15 minutes and the slump is less than<MET> 75 mm</MET><ENG> 3 inches</ENG>.  Bodies of nonagitating trucks shall be smooth, water-tight, 
metal containers specifically designed to transport concrete, shaped with rounded corners to minimize segregation.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.5.2   Belt Conveyors</TTL><BRK/>
<BRK/>
<TXT>Belt conveyors shall be designed and operated to assure a uniform flow of concrete from mixer or delivery truck 
to final place of deposit without segregation of ingredients or loss of mortar and shall be provided with positive 
means for preventing segregation of the concrete or loss of mortar at transfer points and the point of placing.  
The NMSA required in mixture proportions furnished by the Government will not be changed to accommodate the belt 
width.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.1.6   <SUB>Spreading and Remixing Equipment</SUB></TTL><BRK/>
<BRK/>
<TXT>The spreading and remixing equipment shall conform to the following requirements:</TXT><BRK/>
<BRK/>
<LST>a.  The primary spreading procedure shall be accomplished by dozer.  Graders or other equipment not specified 
may be used to facilitate the RCC spreading process only when approved.</LST><BRK/>
<BRK/>
<LST>b.  For open, unrestricted areas, the dozer shall be a minimum size and weight equivalent to a Caterpillar 
D-6.  For restricted placement areas, such as placement of RCC near the dam crest or next to abutments, 
the dozer shall have as a minimum a size and weight equivalent to a Caterpillar D-4.</LST><BRK/>
<BRK/>
<LST>c.  There shall be a minimum of one operating dozer for each<MET> 150 cubic meters</MET><ENG> 200 cubic yards</ENG> of RCC 
placed each hour.  The dozers shall be equipped with well maintained grousers.  A front-end loader with 
operator shall be available to assist with deposition and spreading of RCC as needed in confined areas.</LST><BRK/>
<BRK/>
<LST>d.  The equipment shall be maintained in good operating condition.  The equipment shall not leak or drip 
oil, grease, or other visible contaminants onto the RCC surface.</LST><BRK/>
<BRK/>
<LST>e.  All equipment used for spreading and remixing that leaves the surface of the structure for maintenance 
or repairs or, for any other reason, must be cleaned of all contaminants by an approved method before 
returning to the structure surface.  Under no conditions shall a dozer or other tracked vehicle be operated 
on other than fresh uncompacted RCC except to facilitate startup operations for each lift and by approved 
procedures.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.7   <SUB>Compaction Equipment</SUB></TTL><BRK/>
<BRK/>
<TXT>The compaction equipment shall conform to the following requirements.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.7.1   Primary Rollers</TTL><BRK/>
<BRK/>
<TXT>Self-propelled vibratory rollers shall be used for primary rolling and shall be double-drum.  They shall transmit 
a dynamic impact to the surface through a smooth steel drum by means of revolving weights, eccentric shafts, 
or other equivalent methods.  The compactor shall have a minimum gross mass of<MET> 9000 kg</MET><ENG> 20,000 pounds</ENG> and shall 
produce a minimum dynamic force of<MET> 60 000 N/m</MET><ENG> 350 pounds/linear inch</ENG> of drum width.  The operating frequency 
shall be variable in the approximate range of 1,700 to 3,000 cycles per minute.  The amplitude shall be adjustable 
between<MET> 0.4 and 1.0 mm</MET><ENG> 0.015 and 0.04 inches</ENG>.  The roller shall be capable of full compaction in both forward 
and reverse directions.  The roller shall be operated at speeds not exceeding<MET> 0.7 m/s</MET><ENG> 2.2 ft/s</ENG>.  Within the range 
of the operating capability of the equipment, the Contracting Officer may direct or approve variations to the 
frequency, amplitude, and speed of operation which result in the specified density at the fastest production 
rate.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.7.2   Small Vibratory Rollers</TTL><BRK/>
<BRK/>
<TXT>Small vibratory rollers shall be used to compact the RCC where the larger vibratory rollers specified above cannot 
maneuver.  The rollers shall compact the RCC to the required density and shall be so demonstrated during construction 
of the test section.  Small vibratory rollers cannot compact the RCC to the same density and thickness as the 
primary rollers; therefore, when small rollers are used, total lift thickness of the RCC layer or lift shall 
be reduced to not over<MET> 150 mm</MET><ENG> 6 inches</ENG> uncompacted thickness to permit adequate compaction.  Rollers shall have 
independent speed and vibration controls and shall be capable of a wide range of speed adjustments.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.7.3   Tampers (Rammers)</TTL><BRK/>
<BRK/>
<TXT>The tampers shall compact the RCC to the required density and shall be so demonstrated during construction of 
the test section.  Tampers cannot compact the RCC to the same density and thickness as the primary rollers; therefore, 
when tampers are used, thickness of each RCC layer that is to be compacted shall be reduced to not more than<MET> 
150 mm</MET><ENG> 6 inches</ENG> uncompacted thickness to assure adequate compaction.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.7.4   Other Requirements</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM or the materials engineer to fill in the 
blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>At least [_____] self-propelled vibratory rollers, at least [_____] small rollers, and at least [_____] tampers 
meeting these requirements shall be maintained full time at the site and ready for service at all times during 
production and placement.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.1.8   Truck-Mounted Vacuum Pickup System</TTL><BRK/>
<BRK/>
<TXT>A truck-mounted vacuum pickup system shall be provided for various cleanup operations from the beginning of foundation 
cleanup to final placement of job RCC.  The unit(s) shall be capable of pumping<MET> 125 cubic meters</MET><ENG> 4,500 cubic 
feet</ENG> of air per minute through an<MET> 200-mm</MET><ENG> 8-inch</ENG> diameter opening and capable of pumping water at a minimum rate 
of<MET> 125 L/s</MET><ENG> 2,000 gpm</ENG>.  The equipment shall be maintained in good operating condition.  The equipment shall not 
leak cleanup water and other debris during equipment operation or transit.  The equipment shall not leak or drip 
oil, grease, or other visible contamination onto the RCC.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.9   Other Motorized Equipment</TTL><BRK/>
<BRK/>
<TXT>All other equipment (backhoe with vibratory plate, backhoe with immersion vibrators, backhoe with mandrel for 
inserting contraction joint plates, wash trucks, etc.) necessary for the successful completion of RCC production, 
but not previously discussed within these specifications (or determined to be necessary during the course of 
the work), shall be approved prior to actual use.  Such equipment shall not result in any damage to the RCC, 
shall be maintained in good operating condition, and shall be operated by skilled contractor-provided personnel.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.10   Nuclear Density Gauge</TTL><BRK/>
<BRK/>
<TXT>Tests to determine the density of both the uncompacted and compacted RCC shall be made by the Contractor using 
a two-probe nuclear density gauge supplied by the Contractor.  The nuclear density gauge shall meet the applicable 
requirements of <RID>ASTM C 1040/C 1040M</RID>.  The gauge shall be capable of taking readings along a horizontal path between 
the probes at<MET> 50-mm</MET><ENG> 2-inch</ENG> increments from<MET> 50 mm</MET><ENG> 2 inches</ENG> from the surface to<MET> 600 mm</MET><ENG> 24 inches</ENG> below the surface.  
The gauge and operator shall be made available to the Government until completion of all RCC production at no 
additional cost.  The Contractor shall obtain all permits and certifications for the equipment and the operators.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.11   Calibration</TTL><BRK/>
<BRK/>
<TXT>Nuclear gauges shall have been factory calibrated within 6 months of RCC placement.  The Contractor shall construct, 
at no additional costs to the Government, three conventional concrete test blocks using RCC coarse aggregates 
and RCC fine aggregate, and with dimensions<MET> 300 mm</MET><ENG> 12 inches</ENG> larger than the gauge dimensions.  The concrete 
shall be formulated to have densities of approximately<MET> 2100, 2300, and 2600 kg/cu m</MET><ENG> 130, 145, and 160 lb/cu ft</ENG>
 using the RCC materials and so far as possible, similar relative proportions.  Completed blocks shall be weighed 
and measured to determine unit weight.  Gauge calibration constants shall be adjusted for performance on these 
blocks at least 7 days prior to the evaluation of test strips.  The Contractor shall remedy any inconsistencies 
in gauge performance prior to the start of RCC placement.  After the start of RCC placement, gauges shall be 
field recalibrated against cast blocks every 24 hours.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.12   Vibrators</TTL><BRK/>
<BRK/>
<TXT>Internal vibrators of the proper size, frequency, and amplitude for the work being performed as indicated in 
the chart below shall be used to consolidate conventional concrete and the interface between conventional concrete 
and RCC.  The vibrators for the conventional concrete/RCC interface shall consist of a minimum of four vibrators 
"gang-mounted" in a line on the boom of a backhoe or similar chassis.  The gang-mounted vibrators shall be the 
large<MET> (80 to 150 mm)</MET><ENG> (3 to 6 inch)</ENG> models of that listed below:</TXT><BRK/>
<MET><BRK/>
<TBL><THD>                              HEAD                            AMPLITUDE<BRK/>
    APPLICATION           DIAMETER (mm)   FREQUENCY (VPM)       (mm)<BRK/>
<BRK/></THD>
  RCC interface             80 to 150     7,000 to 10,500    0.75 to 1.50<BRK/>
  General construction      50 to 90      8,000 to 12,000    0.65 to 1.25<BRK/>
  Thin walls                32 to 65      9,000 to 13,500    0.50 to 1.00<BRK/></TBL>
</MET><ENG><BRK/>
<TBL><THD>                              HEAD                            AMPLITUDE<BRK/>
    APPLICATION           DIAMETER (in.)  FREQUENCY (VPM)       (in.)<BRK/>
<BRK/></THD>
  RCC interface           3 to 6          7,000 to 10,500    0.03  to 0.06<BRK/>
  General construction    2 to 3-1/2      8,000 to 12,000    0.025 to 0.05<BRK/>
  Thin walls              1-1/4 to 2-1/2  9,000 to 13,500    0.02  to 0.04<BRK/></TBL>
</ENG><BRK/>
<TXT>The frequency and amplitude shall be determined by the Contractor, in the presence of a Government representative 
in accordance with <RID>COE CRD-C 521</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.13   [Slipforming Equipment</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Consult the materials engineer or the concrete materials DM for whether 
slipforming is to be allowed or required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The slipforming equipment shall be capable of slipforming facing elements as specified at a minimum rate of<MET> 7.5 
mm/s</MET><ENG> 1.5 ft/min</ENG>.  The slip-former shall have an automated guidance system which shall guide the slip-former within 
the specified tolerances.  The slipformer shall have the capability of turning and guiding the form without damage 
to the RCC and facing element. The slipform mold shall be at least<MET> 1 m</MET><ENG> 3 feet</ENG> long to allow the slipform to track 
easily and to minimize surface tearing caused by friction between the mold and the concrete.  The mold shall 
be designed to be mortar-tight and to contain the concrete so that it can be fully consolidated.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2   PREPARATION FOR PLACING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Refer to the appropriate DM and the project coordinator for filling in 
the correct dates and to choose the optional sentences.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.2.1   Placing Schedule</TTL><BRK/>
<BRK/>
<TXT>RCC Placement for the main structure shall start no later than [_____] and no earlier than [_____].  Placement 
of all RCC shall be completed by [_____].  Before starting RCC production, a detailed schedule shall be submitted 
indicating intended daily and weekly production rates that, when followed, will meet the beginning and ending 
specified RCC production dates.  After initiation of RCC production, the Contractor's schedule shall be updated 
and adjusted on a weekly basis for the duration of the RCC placement.  If it becomes apparent for any reason 
that the Contractor is not pursuing a schedule that will meet the specified RCC production dates, actions necessary 
to increase the production rate shall be taken so that production is once again on schedule, within [_____] calendar 
days after written notice.  Also, if not back on schedule by the end of the [_____] days calendar period, the 
Government reserves the right at this time to direct the Contractor, at no additional cost to the Government, 
to increase the amount and size of crews and equipment.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.2   RCC Orientation Session</TTL><BRK/>
<BRK/>
<TXT>Prior to or in conjunction with the construction of the RCC test section, supervisors and all other Contractor 
personnel which are expected to participate in the production of RCC for this job (including laborers, equipment 
operators, foremen, and QC and inspection staff) shall participate in a 2-hour orientation session organized 
by the Contracting Officer.  The Contractor shall provide a facility suitable for slide and videotape presentation.  
The intent is to orient all individuals on the goals of the RCC placement process, provide clarification of specification 
requirements if requested, and be provided orientation as to what constitutes good construction practices.  Additional 
orientation sessions will also be made available to, and shall be attended by, all new Contractor personnel who 
are subsequently hired and that will be involved with the production of the RCC.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.3   <SUB>Aggregate Production Schedule</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the appropriate DM or the materials engineer to fill in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Aggregate production and initial stockpiling shall begin and shall be producing acceptable material by not later 
than [_____] days in advance of the time when placement of the RCC test section is expected to begin.  At least 
[_____] percent of all RCC aggregates for each size group necessary for the completed RCC construction shall 
be manufactured and stockpiled prior to start of placement of RCC for the permanent RCC structures.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.4   RCC Test Section</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the materials engineer for information for filling in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Prior to placement of any RCC, the Contractor shall construct a test section.  The purpose of the test section 
is to demonstrate the suitability of the Contractor's equipment, methods, and personnel.  The test section shall 
be at least [5] [_____] lifts in height and be at least<MET> [60] [_____] m</MET><ENG> [200] [_____] feet</ENG> long and<MET> [12] [_____] 
m</MET><ENG> [40] [_____] feet</ENG> wide at the top.  The site of the test section shall be approved.  After evaluation and assessment 
of the test section by the Contracting Officer, the Contractor shall dispose of the test section in an approved 
manner.  Under no circumstances shall the test section be incorporated into or become a part of the permanent 
RCC structure.  The test section shall demonstrate sustained plant production rates, and batching, mixing, transporting, 
spreading, and compaction procedures.  It shall also demonstrate the vertical face construction method along 
one side, the sloped face construction method along another side, procedures for foundation and concrete surface 
preparation and cleanup, procedures for placement of bedding concrete, bedding mortar, and other conventional 
concrete, and the installation of any contraction joints and waterstops.  The Contractor shall not begin RCC 
operations for the main structure until testing and evaluations by the Government have been completed, and it 
has been demonstrated to the satisfaction of the Contracting Officer that all specification requirements were 
met.  Following completion of test section construction, [10] [_____] calendar days shall be allowed for testing 
and evaluations.  If the Contractor does not meet requirements as specified, an additional test section or sections 
shall be constructed at no additional cost to the Government.  The date of the test section construction shall 
be provided at least 7 days in advance.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.5   Weather</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Make sure the climatological data is included if that optional sentence 
is included.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>If unusual adverse weather, such as heavy rain, severe cold, high winds, heavy snow, etc., occurs or is forecast 
to occur during placement, the placement operation shall be suspended until conditions improve.  *[A sample of 
available climatological data for this project based on historical information is contained herein for general 
information only.  However, it is the responsibility of the Contractor to maintain the construction schedule 
at no additional cost to the Government.]</TXT><BRK/>
<BRK/>
<SPT><TTL>3.2.5.1   Cold-Weather Placement</TTL><BRK/>
<BRK/>
<TXT>In Cold-weather placement the RCC shall not be placed when the ambient air temperature drops below<MET> 0 degrees 
C</MET><ENG> 32 degrees F</ENG>.  If the ambient air temperature does drop below<MET> 0 degrees C</MET><ENG> 32 degrees F</ENG>, the surface of any 
recently placed (within the previous 72 hours) and exposed horizontal RCC surface shall not remain exposed for 
more than 4 hours.  Surfaces that will be exposed for longer times shall be protected as specified in paragraph 
COLD-WEATHER PROTECTION as a measure to maintain RCC temperatures above<MET> 0 degrees C</MET><ENG> 32 degrees F</ENG> until after 
the ambient air temperature rises to above<MET> 0 degrees C</MET><ENG> 32 degrees F</ENG> and is expected to remain above<MET> 0 degrees 
C</MET><ENG> 32 degrees F</ENG> until the end of the curing and protection period, or until covered by another lift.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.5.2   Placing During Rain</TTL><BRK/>
<BRK/>
<TXT>RCC shall not be placed during rainfall of<MET> 2.5 mm/hr</MET><ENG> 0.1 inch/hr</ENG> or more.  During periods of lesser rainfall, 
placement of RCC may continue if, in the opinion of the Contracting Officer, no damage to the RCC is occurring.  
Work shall commence only after excess free surface water and contaminated paste or RCC have been removed and 
the surface has gained sufficient strength (no less than 4 hours after the RCC placement was suspended) to prevent 
rutting, pumping, intermixing of rainwater with the RCC, or other damage to the RCC.  When the RCC surface has 
been contaminated or damaged in any manner, the RCC surface shall be washed to break up and remove laitance and/or 
mud-like coatings from the surface.  Any undercut coarse aggregate shall be removed.  All waste shall be removed 
and disposed of in an approved manner.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.5.3   Hot-Weather Placement</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Refer to the concrete materials DM for use of the optional sentences 
and the correct placing temperature.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>In hot-weather placement the temperature of the RCC shall be controlled so that it does not exceed<MET> [25] [_____] 
degrees C</MET><ENG> [75.0] [_____] degrees F</ENG> when placed.  Placement shall be suspended as soon as the RCC temperature 
exceeds<MET> [25] [_____] degrees C</MET><ENG> [75] [_____] degrees F</ENG>.  Measures that can be taken to prevent temperatures exceeding<MET>
 [25] [_____] degrees C</MET><ENG> [75] [_____] degrees F</ENG> include, but are not limited to, chilling mixing water, sprinkling 
aggregate stockpiles, use of a canopy to shade the RCC placement areas, placing during nighttime and early morning 
hours, or restricting placements to cloudy days.  Use of any of these systems shall not be reason for extension 
of completion dates specified in these specifications.  [In addition, to prevent potential damage to the RCC 
due to hot-weather related placement conditions, all RCC operation shall be suspended between [_____] [June 15th] 
and [October 31st] [_____]].</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2.6   Surface Preparation</TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.6.1   Cleaning</TTL><BRK/>
<BRK/>
<TXT>All lift surfaces including any RCC, dental concrete, bedding concrete, bedding mortar, or other conventional 
concrete placed adjacent to and at the same time as the RCC shall be cleaned prior to placing any additional 
concrete thereon.  After cleaning, bedding concrete and bedding mortar are to be used specifically for achieving 
bond between different types of concrete and/or foundation and eliminating and preventing segregation or voids 
along margins or RCC placements.  No surfaces to receive bedding concrete or bedding mortar shall be covered 
with RCC until the prepared surfaces have been accepted in writing and that acceptance has been recorded on an 
approved checkout form.  All surfaces upon which RCC or any bedding mortar or bedding mix is placed shall be 
moist (but contain no visible free water).  Prior to placing any concrete adjacent to and at the same time as 
the RCC, all surfaces shall be clean and free of loose, unkeyed, or deteriorated rock; all mud and silt accumulations; 
vegetation; laitance; puddles or ponds of free surface water; coatings; and any other detrimental materials.  
High-pressure water jetting, and/or wet sandblasting, followed by mild high-volume, low-pressure washing, shall 
be used on all hardened concrete surfaces (cold joints) as necessary for the removal of laitance, coatings, stains, 
or other difficult-to-remove contaminants.  High-volume low-pressure water washing and/or water jetting may be 
used for removal of loose materials.  Adequate equipment with operators shall be on hand at the site to clean 
all surfaces in conformance with these specifications without disrupting in any way the RCC production as scheduled.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.6.2   High-Volume Low-Pressure Washing</TTL><BRK/>
<BRK/>
<TXT>Washing of loose materials can be accomplished with high-volume low-pressure water washing and/or air water jetting 
using equipment of similar design to that used in large-scale foundation cleanups.  The air-water jets shall 
have<MET> 40-mm</MET><ENG> 1-1/2-inch</ENG> nozzles, a water supply of at least<MET> 2 L/s</MET><ENG> 30 gpm</ENG>, and compressed air at the jet of<MET> 550 
to 850 kPa</MET><ENG> 80 to 120 psi</ENG>.  The low-pressure water jets shall have<MET> 25-mm</MET><ENG> 1-inch</ENG> nozzles available and a capacity 
of at least<MET> 13 L/s</MET><ENG> 200 gpm</ENG> for truck-mounted devices.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.6.3   High-Pressure Water Jet</TTL><BRK/>
<BRK/>
<TXT>A stream of water under a pressure of not less than<MET> 10.3 MPa</MET><ENG> 1,500 psi</ENG> for RCC and<MET> 27.6 MPa</MET><ENG> 4,000 psi</ENG> for conventional 
concrete shall be used for cleaning all cold joint surfaces, or surfaces with laitance, mortar coatings, stains, 
or other difficult-to-remove contaminants.  There shall be no undercutting of coarse-size aggregates.  Aggregate 
particles that are undercut shall be removed.  For cleaning large open areas larger than [_____] square<MET> meters</MET><ENG>
 feet</ENG>, the high-pressure water jet system shall be truck-mounted.  For cleaning small or confined areas, the 
high-pressure water jet system shall be portable.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.6.4   Wet Sandblasting</TTL><BRK/>
<BRK/>
<TXT>This method may be used when the RCC has reached sufficient strength to prevent undercutting of coarse aggregate 
particles.  Wet sandblasting shall be continued until all accumulated laitance, coatings, stain, or other difficult-to-remove 
contaminants are removed.  Wet sandblasting may be used in lieu of or in combination with the high-pressure water 
jet.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.6.5   Waste Disposal</TTL><BRK/>
<BRK/>
<TXT>Any waste water employed in cutting, washing, and rinsing of concrete surfaces, and any other surface water shall 
not stain, or affect exposed surfaces of the structure(s) or damage the environment of the project area.  Disposal 
shall comply with the provisions of Section <SRF>[_____]</SRF>.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.3   PLACING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Consult the concrete materials DM for the use of optional sentences and 
filling in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.3.1   Procedures</TTL><BRK/>
<BRK/>
<TXT>It is the intent of this contract to raise the structure at essentially the same level across the entire horizontal 
surface area.  For a dam, placement shall proceed from abutment to abutment and from downstream to upstream.  
Each lift shall be completed in its entirety across the full surface of the mass.  As the advancing edge of the 
lift progresses, the exposed leading edges shall be kept "live" by progressively placing out from the advancing 
edge in a sloping and uniform fan-like manner.  RCC shall be deposited (from the conveyor, end-dump truck, or 
front-end loader) on the uncompacted RCC of the advancing edge in a forward direction from the dump pile.  RCC 
shall not be placed in consecutive or consistent lanes.  The dump location shall be varied to avoid "lane" construction.  
[See Contract Drawing [_____] showing typical depositing, spreading, and remixing operations.]  The interval 
between batch plant mixing and final RCC compaction shall be no greater than 45 minutes for<MET> 300 mm</MET><ENG> 12 inch</ENG> lifts 
and 75 minutes for<MET> 600 mm</MET><ENG> 24 inch</ENG> lifts.  Final compaction is defined as:  Any RCC lift composed of layers that 
have been worked twice by dozer grousers, receives four passes with the vibratory roller, and meets the density 
requirements.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.2   Bedding Mortar</TTL><BRK/>
<BRK/>
<TXT>The bedding mortar shall be applied to the existing surface following any required cleanup.  The bedding mortar 
shall be applied not more than 15 minutes ahead of RCC placement, unless otherwise approved.  The bedding mortar 
shall be used between hardened conventional concrete and RCC, between different RCC placements where cold joints 
occur, and other locations as directed or as shown in the drawings.  The bedding mortar shall have an average 
thickness after application of between<MET> 6 and 13 mm</MET><ENG> 1/4 and 1/2 inch</ENG> and shall cover 100 percent of the lift area.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.3   Bedding Concrete</TTL><BRK/>
<BRK/>
<TXT>The bedding concrete, a conventional concrete mixture, shall be used at the abutment-RCC interface, and except 
for cast-in-place concrete for the upstream face, between the RCC and any formed sloping or vertical surface 
and other locations as directed or as shown in the drawings.  Placement of the bedding mixture shall occur only 
after all required surface preparations have been completed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.4   Lift Thickness</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM for the lift thickness.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The total lift thickness after final compaction by the vibratory roller shall be<MET> [300] [_____] mm</MET><ENG> [12] [_____] 
inches</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.5   Depositing, Spreading, and Remixing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the appropriate Design Memorandum for use of the alternate optional 
paragraphs below.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>After the RCC has been deposited, the RCC shall be spread by dozers into gently sloping layers, approximately<MET>
 150 mm</MET><ENG> 6 inches</ENG> thick, that will, after final compaction of the several layers by the vibratory roller, result 
in the specified lift thickness.  During the spreading process, the dozer operators shall continuously work the 
RCC surfaces with the dozer blade and grousers in a manner to remix any RCC that may contain pockets of segregated 
material and to compact the material.  All surfaces of each layer shall receive at least two passes with the 
grousers.  The dozers shall be operating continuously during the spreading process, even if this action results 
in more than two passes.  A front-end loader with operator shall be available to assist with depositing and spreading 
RCC as needed in confined areas, at the abutments, and at other locations approved or directed.  In no case shall 
the RCC, bedding mixes, or bedding mortar be allowed to dry.  Under no conditions shall a dozer or other tracked 
vehicle be operated on other than fresh uncompacted RCC except at the start of each lift placement to facilitate 
startup operations, and then only by an approved procedure.  No RCC or other concrete shall be placed on a previous 
lift which has not met specification. Unacceptable material shall be removed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.6   Compaction/Consolidation</TTL><BRK/>
<BRK/>
<TXT>After spreading and working with the dozers, the top surface of each lift shall be compacted with a minimum of 
four, plus as many additional passes with a self-propelled double-drum vibratory roller operating in the vibratory 
mode as are required to obtain a minimum of 98 percent of the theoretical density.  A round trip over the same 
material shall count as two passes (i.e., from point A to point B and return to point A by the same route is 
two passes).  Rollers shall not be operated in the vibratory mode unless they are moving.  Bedding concrete and 
any other conventional concrete that interfaces with the RCC shall be consolidated with internal vibrators.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.3.6.1   Theoretical Density (TD) Determination</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the appropriate DM to fill in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The TD is defined as the theoretical density (unit weight) of the concrete, <MET>kg</MET><ENG> pounds</ENG> per cubic<MET> meter</MET><ENG> foot</ENG>, computed 
to include an air content of [_____] percent.  The TD value to be used during construction will be determined 
using job mixture proportions and Contractor supplied materials; and, using compaction techniques suitable for 
RCC, and following the appropriate testing procedures used to determined theoretical unit weight of concrete 
as described as in <RID>ASTM C 138/C 138M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.6.2   Required Compaction Density</TTL><BRK/>
<BRK/>
<TXT>All RCC shall be compacted to a minimum of 98 percent of the TD value.  The anticipated TD, estimated from laboratory 
test data is approximately [_____]<MET> kg</MET><ENG> pounds</ENG> per cubic<MET> meter</MET><ENG> foot</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.6.3   Density Determination of Compacted RCC</TTL><BRK/>
<BRK/>
<TXT>Density shall be measured using a nuclear density meter in accordance with <RID>ASTM C 1040/C 1040M</RID>.  RCC density 
value determinations shall be made throughout the course of RCC placement to assure that the RCC is compacted 
to a minimum 98 percent of the TD and detect segregation and/or voids throughout the RCC.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.6.4   Additional Compaction</TTL><BRK/>
<BRK/>
<TXT>If more than four passes are required to achieve the required density, the additional passes shall be made at 
no additional cost to the Government.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.6.5   Consolidation of Bedding and Other Conventional Concrete</TTL><BRK/>
<BRK/>
<TXT>In no case shall vibrators be used to transport concrete.  The vibrator shall be inserted vertically at uniform 
spacing over the entire area of conventional concrete placement area.  The distance between insertions shall 
be approximately one and one-half times the radius of action of the vibrator.  The vibrator shall penetrate rapidly 
to the bottom of the layer and at least<MET> 150 mm</MET><ENG> 6 inches</ENG> into any preceding plastic layer if such exists.  The 
vibrator shall be held stationary until the entrapped air is forced to the surface (up to 6 seconds) and the 
concrete is consolidated and then withdrawn slowly.  An adequate number of vibrators shall be on hand to meet 
placing requirements, and spare vibrators shall be available to maintain production in the event of breakdown.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.3.7   Lift Joints</TTL><BRK/>
<BRK/>
<TXT>The entire RCC mass shall be placed with sufficient continuity so that it hardens and acts as one monolithic 
block without discontinuous joints or potential planes of separation.  All lift joints shall be kept clean, uncontaminated, 
free from ponded water, and continuously moist until placement of the succeeding RCC or other concrete.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.3.7.1   <SUB>Regular Lift-Joint Treatment</SUB></TTL><BRK/>
<BRK/>
<TXT>Lift joints that have not hardened or dried and are less than 72 hours old shall be given the regular lift-joint 
treatment.  Regular lift-joint treatment and maintenance shall include:</TXT><BRK/>
<BRK/>
<LST>a.  Maintaining 100 percent of each compacted lift-joint surface continuously moist,</LST><BRK/>
<BRK/>
<LST>b.  If necessary, removing all loose contaminants or deteriorated RCC by low-pressure washing and/or 
vacuuming, and</LST><BRK/>
<BRK/>
<LST>c.  Application of a<MET> 6 to 13 mm</MET><ENG> 1/4 to 1/2 inch</ENG> thick bedding mortar over the entire placement surface 
area immediately before placement of the next lift.</LST><BRK/>
<BRK/>
<TXT>For regular lift-joint treatment, no washing or vacuuming will be necessary provided damage or contamination 
of the lift surface is prevented.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.7.2   Cold Joints</TTL><BRK/>
<BRK/>
<TXT>A cold joint is any vertical or horizontal RCC surface:</TXT><BRK/>
<BRK/>
<LST>a.  That does not receive the next RCC lift within 72 hours,</LST><BRK/>
<BRK/>
<LST>b.  In which the RCC has been allowed to dry, or</LST><BRK/>
<BRK/>
<LST>c.  That has been contaminated to the extent that contaminants cannot be removed using low-pressure water.</LST><BRK/>
<BRK/>
<TXT>Cold joints shall be prepared for the next lift by the methods and procedures in paragraph SURFACE PREPARATION 
prior to resumption of RCC placement.  Following this initial preparation, the cold-joint surface shall be kept 
continuously moist until application of the bedding mortar.  Whenever a cold joint at any edge or end of any 
lift occurs, it shall be located at least<MET> 10 m</MET><ENG> 30 feet</ENG> from the location of other cold joints that may have previously 
occurred in the same direction along previous lifts.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.7.3   Vertical Joints</TTL><BRK/>
<BRK/>
<TXT>Joints for sloping, near-vertical or vertical RCC surfaces are considered to be vertical joints.  A vertical 
joint most often will occur when an RCC placement is terminated before the entire RCC placement for that lift 
has been completed.  When it does become apparent that placement of RCC will be terminated prior to completion 
of a lift, the RCC spreading procedure at the leading zone of the placement shall be adjusted to provide a gradual 
tapered slope to complete that lift.  The taper shall be no steeper than 25 horizontal on 1 vertical.  Where 
the tapered slope meets the underlying hardened lift surface, care shall be taken to prevent or remove any segregated 
or uncompacted material.  The tapered surface shall be compacted in accordance with paragraph COMPACTION/CONSOLIDATION.  
Prior to resumption of RCC placements, the tapered surface shall be prepared in accordance with paragraph SURFACE 
PREPARATION.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.3.8   Downstream Face</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM to select one of the two optional systems 
for the downstream face.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.3.8.1   [Using Sacrificial Concrete</TTL><BRK/>
<BRK/>
<TXT>The downstream sloped face of the dam and the exposed slopes of the stilling basin training walls shall be constructed 
using sacrificial RCC on [[_____] vertical to [_____] horizontal slope] [1 vertical to 0.85 horizontal slope].  
The slope shall be constructed to the tolerances specified.  Each RCC lift shall be overbuilt at least<MET> 300 mm</MET><ENG>
 12 inches</ENG>, and it shall subsequently be trimmed to the surface smoothness tolerance.  Trimming shall be performed 
before the RCC is more than 48 hours old.  The process shall be demonstrated during the test section.  Trimming 
shall be done in such a manner to prevent damage to the surface and interior RCC.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.8.2   [Using Conventional Concrete</TTL><BRK/>
<BRK/>
<TXT>The downstream face shall be constructed of conventional concrete in accordance with paragraph VERTICAL FACINGS 
FOR RCC CONSTRUCTION.]</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.4   <SUB>CURING AND PROTECTION</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>3.4.1   Curing</TTL><BRK/>
<BRK/>
<TXT>The surface of every RCC lift shall be kept continuously moist, commencing immediately after compaction, by use 
of water trucks equipped with fog sprayers for 14 days or until the surface is covered with the next lift.  The 
sloping downstream surface of the Dam, [and the [_____]] if constructed of uncompacted sacrificial RCC, need 
not be cured.  Curing and protection for all conventional concrete used in the construction of the vertical faces 
and any horizontal RCC surfaces that will not receive a subsequent concrete covering shall be moist cured.  Conventional 
concrete made with Type II portland cement, or any type of portland cement with pozzolan, and all RCC shall be 
moist cured for 14 days.  Conventional concrete made with Type I portland cement shall be moist cured for 7 days.  
Conventional concrete shall be moist cured by covering with saturated nonstaining burlap or cotton mats.  New 
burlap or cotton mats shall be rinsed to remove soluble substances before using.  Concrete that is moist cured 
shall be maintained continuously, not periodically, wet for the duration of the entire curing period.  Water 
for curing shall comply with the requirements of paragraph WATER.  If the water or mats cause staining or discoloration 
of permanently exposed concrete surfaces, the surfaces shall be cleaned by a method approved by the Contracting 
Officer.  When wood or metal forms are left in place during curing, the forms shall be kept continuously wet, 
except for sealed insulation curing in cold weather.  RCC may be cured with saturated cotton or burlap mats in 
lieu of the approved fog spraying equipment.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2   <SUB>Cold-Weather Protection</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM or thermal study for the optional numbers.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The air and forms in contact with the RCC and any conventional concrete shall be maintained at a temperature 
above<MET> 0 degrees C</MET><ENG> 32 degrees F</ENG> for [14] [_____] days.  In addition, at the time insulation or protection is removed, 
the air temperature adjacent to the RCC surfaces shall be controlled so that the concrete near the surface will 
not be subjected to a temperature differential of more than<MET> 15 degrees C</MET><ENG> 25 degrees F</ENG> (as determined by observation 
of ambient air and concrete temperatures).</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.3   Special Cold-Weather Insulation Protection</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the appropriate DM for use of this paragraph and to fill in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>In addition to the requirements specified in paragraph COLD-WEATHER PROTECTION, all RCC and any conventional 
concrete placed at the same time and in direct contact with the RCC shall receive special insulation protection 
as described for the following time periods:</TXT><BRK/>
<BRK/>
<LST>a.  [_____].</LST><BRK/>
<BRK/>
<LST>b.  [_____].</LST><BRK/>
<BRK/>
<TXT>The insulation shall provide an R value not less than [_____]<MET> square meter degree Celsius per watt</MET><ENG> hour square 
foot degree Fahrenheit per BTU</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.4   <SUB>Hot-Weather Protection</SUB></TTL><BRK/>
<BRK/>
<TXT>When ambient air temperatures exceeds<MET> 30 degrees C</MET><ENG> 90 degrees F</ENG> and as soon as the conventional concrete and 
RCC is sufficiently hard to withstand washing of surface mortar, water by fog spraying shall be applied in a 
controlled manner to provide evaporative cooling.  Water shall be applied at such a rate that it quickly evaporates 
and such that the surface remains continuously moist without ponding.  In addition, when surface materials begin 
to dry and while the RCC placement, spreading, and compaction process is still underway and until the concrete 
has sufficiently hardened to permit the above water spray, hand-held fog spraying shall be applied to the concrete 
surfaces as directed to prevent drying out of concrete materials and replace moisture lost to evaporation.  These 
hot-weather protection procedures will require additional labor(s) to assure complete coverage of the entire 
surface areas to prevent unacceptable damage to the RCC and conventional concrete.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5   <SUB>VERTICAL FACINGS FOR RCC CONSTRUCTION</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM to select the appropriate method or methods 
specified below.  It should be noted that the method used for other vertical 
conventional concrete work may be different from the method used for construction 
of the upstream face.  See paragraphs GALLERY, SPILLWAY CONSTRUCTION, etc.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The vertical faces of the RCC structure are to be constructed using [a form and cast-in-place conventional concrete 
system] [a slipform facing system] [a precast concrete panel system] as shown and specified.  The vertical facings 
system shall be demonstrated on one side of the RCC test section.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.5.1   [Form and Cast-in-Place Conventional Concrete</TTL><BRK/>
<BRK/>
<TXT>Vertical and near-vertical facings shall be as shown in the drawings.  The contract drawings are based on designs 
whereby all vertical and near-vertical faces are constructed of conventional slump concrete at the same time 
and rate as used in placement of each RCC lift.  In construction of vertical facings, a<MET> 0.75 to 1.25 meter</MET><ENG> 2.5 
to 4.0 foot</ENG> wide zone of conventional concrete shall be placed against the forms or other hard surface.  The 
design and engineering of the formwork, as well as its construction, shall be the responsibility of the Contractor.  
The formwork shall be designed for loads, lateral pressure, and allowable stresses in accordance with Chapter 
1 of <RID>ACI 347</RID>.  Forms shall have sufficient strength to withstand the pressure resulting from placement and vibration 
of the concrete and shall have sufficient rigidity to maintain specified tolerances.  The required sequence of 
construction operations after all forms and concrete surface preparations have been approved is:  place conventional 
concrete full height of each RCC lift and full width against the forms; using dozer action, spread each thin 
RCC layer into and abutting against the conventional concrete while at the same time tracking the interface between 
the two with dozer grousers; after full-lift thickness of the RCC is in place next to the conventional concrete, 
consolidate 100 percent of the conventional concrete and the interface; and finally, compact the RCC (to include 
the interface) using the vibratory roller.  The interface between the RCC and conventional concrete shall be 
consolidated and "knitted" together using the gang heavy-duty, machine-mounted, immersion vibrators.  Extreme 
care shall be taken to stage activities to assure all time restrictions are met and to prevent the occurrence 
of any openwork, honeycombing, or voids at the conventional concrete/RCC interface.  All conventional concrete 
and bedding concrete placed along the RCC and the interface shall be thoroughly consolidated and intermixed by 
use of immersion vibrators.  The Contractor's construction techniques and equipment used shall be satisfactorily 
demonstrated during construction of the test section.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2   [Slipformed Facing Elements]</TTL><BRK/>
<BRK/>
<TXT>A slipformed conventional concrete face shall be constructed on the upstream face of the dam [and [_____]].  
Concrete for the slipformed facing elements shall conform to requirements of this section.  The configuration 
for the facing elements shall be as shown.  The concrete mixture for the facing elements shall be proportioned 
by the Contractor to be formed by a slipform curbing machine and to have sufficient early strength to allow compaction 
for RCC against its surface within 4 hours.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.5.2.1   Prequalification of Equipment</TTL><BRK/>
<BRK/>
<TXT>Prior to placing any slipformed facing elements for incorporation into the dam, a demonstration of the slipform 
equipment and concrete mixture as a part of the test section shall be performed by the Contractor.  The Contractor 
shall form one side of the test section using his proposed slipforming equipment, in accordance with paragraph 
RCC TEST SECTION.  If necessary, the Contractor shall adjust the concrete mixture and make any adjustments or 
modifications to the slipforming equipment and concrete supply procedures and equipment as may be required to 
produce a satisfactory slipformed facing element.  A starting block shall be constructed to enable the first 
facing element to be formed without modification to the slipform.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2.2   Slipform Operations</TTL><BRK/>
<BRK/>
<TXT>The equipment shall be operated in such a manner as to prevent damage to the RCC surface and facing element.  
The slipformer shall carry a surge hopper of sufficient capacity to enable the slipformer to continue to extrude 
facing element between concrete deliveries.  If the slipformer is stopped, concrete shall be thoroughly consolidated, 
a joint shall be made, and unacceptable concrete shall be removed from the mold.  The slipformer shall have an 
automated guidance system which shall guide the slipformer within the specified tolerances.  A smooth, mortar-tight 
joint between successive elements shall be achieved.  Molds and vibrators shall be available in sufficient quantities 
to replace worn or damaged ones.  Vibrators shall be capable of being adjusted and relocated to achieve complete 
consolidation.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2.3   Slipforming - Preparation for Placing</TTL><BRK/>
<BRK/>
<TXT>Placement shall not begin until after all preparations are complete and the authorized representative of the 
Contracting Officer has approved in writing completion of all preparations for that placement.  No facing element 
concrete shall be placed until the surfaces to receive facing element concrete are free of deleterious substances 
including but not limited to:  uncompacted, loose, deteriorated, or improperly cured RCC or facing element concrete, 
laitance, dirt, ice, curing compounds, and visible free surface water.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2.4   Slipforming - Placing</TTL><BRK/>
<BRK/>
<TXT>All joint surfaces more than 24 hours old, or in any other way damaged or not meeting the specification requirements, 
shall be wet sandblasted, washed with air-water jets, and surface dried prior to placement of adjoining facing 
elements.  The molds for the slipform shall be kept continually full, and concrete vibrated, to prevent voids.  
The slipformed facing element shall be uniform, dense, and free of surface blemishes and tears.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2.5   Slipforming - Finishing</TTL><BRK/>
<BRK/>
<TXT>The class of finish and the requirements for finishing of slipformed facing elements shall be as specified in 
this paragraph, paragraph CONSTRUCTION TOLERANCES, and as indicated.  The finished surface shall be smooth and 
free from rock pockets and surface voids.  Light surface pitting (voids up to <MET>6 mm </MET><ENG>1/4 inch</ENG> diameter) and light 
slipforming marks are not considered objectionable.  Where the surface produced meets specified requirements, 
no further finishing operations will be required.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5.3   [Precast Reinforced Panels]</TTL><BRK/>
<BRK/>
<TXT>The precast panel systems shall be designed as specified in [Section <SRF>[_____]</SRF>] [_____].  Typical panel systems 
shall consist of interlocked panels measuring<MET> 1 m</MET><ENG> 4 ft</ENG> by as much as<MET> 5 m</MET><ENG> 16 ft, 4 inches</ENG> thick (min.), and anchored 
at four locations.  Anchor bars, straps, and connections shall be oversized or treated to compensate for deterioration 
due to exposure to moisture.  Panels shall be adequately braced with either external strongbacks or by staggering 
panel placement and connection to adjacent panels.  The Contractor, by design, shall assure the safety and immobility 
of the panel system.  The panel system shall include upstream face [, downstream face] [, spillway crest] [, 
spillway training wall] [, and stilling basin training wall panels].  Panel joints shall match with pier noses, 
spillway cap, intake structure, and transverse joints.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.5.3.1   Leveling Pad</TTL><BRK/>
<BRK/>
<TXT>No concrete leveling pad for setting panels is required unless the panel design so requires, however, the base 
of the panels shall be embedded at least<MET> 300 mm</MET><ENG> 1 foot</ENG> into concrete, RCC, or backfill material.  The initial 
row of panels shall be adequately braced, aligned, and leveled.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.3.2   Alignment</TTL><BRK/>
<BRK/>
<TXT>Panels shall be installed so that horizontal joint lines of the upstream and downstream faces and the spillway 
crest panel joints align and shall meet the tolerances in paragraph CONSTRUCTION TOLERANCES.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.6   SAFETY BARRIER</TTL><BRK/>
<BRK/>
<TXT>At all lift-surface elevations, effective and approved temporary guardrail shall be provided at the top of the 
structure to protect workers and prevent loss of tools or debris over edges.  Safety barriers shall comply with 
the requirements of <RID>EM 385-1-1</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.7   <SUB>CONTRACTION JOINTS</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the appropriate DM to fill in the blanks.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Contraction joints shall be formed by inserting plates into non-compacted full lift thickness RCC at locations 
as shown on the drawings.  The plates, when installed adjacent to each other (at the same structure stationing 
within each lift) shall form a bond breaker that serves as a contraction joint.  The plates shall be<MET> [900] [_____] 
mm</MET><ENG> [36] [_____] inches</ENG> wide, <MET>[300] [_____] mm</MET><ENG> [12] [_____] inches</ENG> deep, up to<MET> 6 mm</MET><ENG> 1/4 inch</ENG> thick, and made out 
of [_____].  The plates shall be installed vertically into the RCC by means of a vibrating plate mounted on a 
backhoe.  The exact details for the design of the contraction joints, as well as installation and methods of 
maintaining tolerances, alignment, etc., shall be submitted in accordance with paragraph SUBMITTALS.  Plate alignment 
shall be controlled by laser or other approved survey technique.  Waterstops, drains, and contraction joints 
within any conventional concrete shall be in accordance with [Section <SRF>[_____]</SRF>] [_____] and as shown.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8   [<SUB>GALLERY</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  See the concrete materials DM for use of this optional paragraph and 
to select the optional methods.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The gallery shall be constructed using one of the following schemes or combination thereof, the details which 
shall be Contractor's responsibility:</TXT><BRK/>
<BRK/>
<LST>a.  Precast gallery segments,</LST><BRK/>
<BRK/>
<LST>b.  Removable rigid forms against which conventional concrete, or RCC is placed, and</LST><BRK/>
<BRK/>
<LST>c.  A noncementing fill as a temporary filler in the gallery area and removing it to form the gallery 
after the RCC has gained sufficient strength to be self-supporting.</LST><BRK/>
<BRK/>
<TXT>Regardless of which procedure is used, the gallery shall be sloped to drain and shall include a gutter along 
the downstream gallery wall as shown in the drawings.  In no case shall the gallery floor surface be allowed 
to pond more than<MET> 25 mm</MET><ENG> 1 inch</ENG> of water.  The size and shape of the gallery shall be as shown in the drawings.]</TXT><BRK/>
<BRK/>
<SPT><TTL>3.8.1   [Precast Gallery Segments</TTL><BRK/>
<BRK/>
<TXT>If stay-in-place precast gallery units are used to form the gallery, they shall be constructed in accordance 
with [Section <SRF>[_____]</SRF>] [_____].  The design shall be submitted for review and comment.  The sections shall be 
designed to carry the full load of the vibratory roller over the first lift of fresh RCC above the ceiling section 
with a safety factor of 4 and shall be designed to carry the vibrating load of subsequent compaction without 
excessive deflection that could damage the previously placed RCC.  For each lift, a ribbon of bedding concrete, 
approximately<MET> 0.09 cubic meter per linear meter</MET><ENG> 1 cubic foot per linear foot</ENG> of precast panel, shall be placed 
between the RCC and panels.  The RCC bedding concrete interface shall be thoroughly vibrated with immersion vibrators 
to eliminate any voids or segregation within the RCC.  A permanent reinforced precast slab may be used to construct 
the gallery ceiling section in combination with other gallery construction schemes chosen by the contractor.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.2   [Temporary Forms</TTL><BRK/>
<BRK/>
<TXT>The design of any temporary gallery form system and its adequacy shall be the responsibility of the Contractor.  
Forms shall comply with the requirements of [Section <SRF>[_____]</SRF>] [_____], except that they need not be mortar-tight, 
and they shall meet the tolerances in paragraph CONSTRUCTION TOLERANCES.  The design of the ceiling form shall 
be such that it can safely carry the load of the vibratory roller with a safety factor of 4 and shall be stiff 
enough to prevent damage to the fresh RCC from elastic deflection and rebound while compaction is being accomplished.  
The forms shall not be removed until the RCC has gained sufficient strength to be self supporting (estimated 
to be 90 days) and not until at least<MET> 10 m</MET><ENG> 40 feet</ENG> of RCC has been placed above the gallery ceiling.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.3   [Noncementing Fill Method</TTL><BRK/>
<BRK/>
<TXT>The gallery section may be constructed by placing a noncementitious fill in the cross-sectional area where the 
gallery is to be located, compacting it at the same time that the adjacent RCC is compacted, and later removing 
the fill.  Details of how this procedure will be followed, what the noncementitious will consist of, how the 
fill will be removed later, and how the gallery doors will be set shall be submitted for review and comment in 
accordance with paragraph SUBMITTAL.  To form the outline of the gallery, braced partitions (or forms) shall 
be placed along the perimeter of the gallery section between the RCC and non-cementitious fill.  Separate partitions 
(or forms) shall be installed for each lift, shall be of such size and configuration, and be positioned on the 
previous lift's partitions (or forms) to ultimately form the gallery section.  The braced partitions shall be 
removed during the excavation process.  Alignment of partitions (or forms) shall not result in offsets and irregularities 
that exceed construction tolerances specified in paragraph CONSTRUCTION TOLERANCES.  The noncementitious fill 
material may be one or more of the standard RCC aggregates or any other approved fill material, without portland 
cement or pozzolan; however, nominal maximum-size aggregate shall not exceed 19.0 mm (3/4 inch).  Excavation 
of the gallery fill shall not start until the RCC has gained sufficient strength to be self supporting (a minimum 
of 30 days) and until at least<MET> 10 m</MET><ENG> 35 feet</ENG> of RCC has been placed above the gallery section.  As soon as the 
strength and cover requirements have been met, removal of the gallery shall begin.  The excavated fill material 
shall be disposed of in an approved manner.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.9   [SPILLWAY CONSTRUCTION]</TTL><BRK/>
<BRK/>
<SPT><TTL>3.9.1   [Spillway Chute and Ogee Section</TTL><BRK/>
<BRK/>
<TXT>The spillway floor shall be constructed as shown.  The drawings are based on a design whereby the spillway is 
constructed at the same time and rate as used in placement of each RCC lift.  The same technology and construction 
procedures as used in the construction of the vertical upstream face shall be used.  The major difference being, 
instead of placing conventional concrete for the floor against vertical cantilevered forms, conventional concrete 
will be placed against sloping cantilevered forms to form the spillway chute.  The design and engineering of 
the formwork, as well as its construction and methods of maintaining tolerances, etc., shall be the responsibility 
of the Contractor.  The formwork shall be designed for loads, lateral pressures, and allowable stresses in accordance 
with Chapter 1 of <RID>ACI 347</RID>.  Forms shall be of sufficient strength to withstand the pressure resulting from placement 
and vibration of the concrete and shall have sufficient rigidity to maintain specified tolerances.  Extreme care 
shall be taken to prevent the occurrence of any permanent openwork, honeycombing, or voids at the conventional 
concrete/RCC interface, or next to the forms.  The Contractor's construction techniques shall be satisfactorily 
demonstrated during placement of the test section.  The unformed portion of the spillway will be finished by 
placing concrete slightly above grade and striking off to grade by accurate screeding.  The surface shall be 
finished as specified in paragraph FLOAT FINISH.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.2   [Training Walls</TTL><BRK/>
<BRK/>
<TXT>Concrete for training walls shall be as shown in the drawings and as specified in paragraph VERTICAL FACINGS 
FOR RCC CONSTRUCTION.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.3   Finishing</TTL><BRK/>
<BRK/>
<SPT><TTL>3.9.3.1   General</TTL><BRK/>
<BRK/>
<TXT>The ambient temperature of spaces adjacent to surfaces being finished shall be not less than<MET> 10 degrees C</MET><ENG> 50 
degrees F</ENG>.  In hot weather when the rate of evaporation of surface moisture, as determined by use of Figure 2.1.5 
of <RID>ACI 305R</RID>, may reasonably be expected to exceed<MET> 1 kg/sq m</MET><ENG> 0.2 lb/sq ft</ENG> per hour, provisions for windbreaks, 
shading, fog spraying, or wet covering with a light-colored material shall be made in advance of placement, and 
such protective measures shall be taken as quickly as finishing operations will allow.  All unformed surfaces 
that are not to be covered by additional concrete or backfill shall have a float finish, unless a trowel finish 
is specified, and shall be true to the elevation shown.  Surfaces to receive additional concrete or backfill 
shall be brought to the elevation shown in the drawings and left true and regular.  Exterior surfaces shall be 
sloped for drainage unless otherwise shown or as directed.  Joints shall be carefully made with a jointing or 
edging tool.  The finished surfaces shall be protected from stains or abrasions.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.3.2   Float Finish</TTL><BRK/>
<BRK/>
<TXT>Surfaces shall be screeded and darbied or bullfloated to bring the surface to the required finish level with 
no coarse aggregate visible.  No water, cement, or mortar shall be added to the surface during the finishing 
operation.  The concrete, while still green but sufficiently hardened to bear a man's weight without deep imprint, 
shall be floated to a true and even plane.  Floating may be performed by use of suitable hand floats or power-driven 
equipment.  Hand floats shall be made of magnesium or aluminum.  Tolerance for a floated finish shall be true 
plane within<MET> 8 mm in 3000 mm</MET><ENG> 5/16 inch in 10 feet</ENG> as determined by a<MET> 3-m</MET><ENG> 10-foot</ENG> straightedge placed anywhere 
on the slab in any direction.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.10   TESTS AND INSPECTIONS</TTL><BRK/>
<BRK/>
<SPT><TTL>3.10.1   General</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The title of the certification provided by ACI that concrete inspectors/technicians 
have to have to perform concrete testing was changed from "Concrete Transportation 
Construction Inspector" to "Concrete Construction Inspector" in 2004.  Since 
the certification is good for 5 years, both titles will be kept in the specifications 
through 2006; pick the correct bracketed statement for projects prior to 2004.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The Contractor shall perform the inspection and tests as described below, and based upon the results of these 
inspections and tests, he shall take the action required and submit reports as required.  When, in the opinion 
of the Contracting Officer, the concreting operation is out of control, concrete placement shall cease.  The 
laboratory performing the tests shall be on-site and shall conform with <RID>ASTM C 1077</RID>.  The individuals who sample 
and test concrete or the constituents of concrete as required in this specification shall have demonstrated a 
knowledge and ability to perform the necessary test procedures equivalent to the ACI minimum guidelines for certification 
of Concrete Field Testing Technicians, Grade I.  The individual who performs the inspection shall have demonstrated 
a knowledge and ability equivalent to the ACI minimum guidelines for certification of [Concrete Transportation 
Construction Inspector (CTCI)] [Concrete Construction Inspector (CCI)], Level II.  The Government will inspect 
the laboratory, equipment, and test procedures prior to start of concreting operations and at least once per 
year thereafter for conformance with <RID>ASTM C 1077</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2   Testing and Inspection Requirements</TTL><BRK/>
<BRK/>
<SPT><TTL>3.10.2.1   Fine Aggregate</TTL><BRK/>
<BRK/>
<LST>a.  Grading - At least once during each shift when the concrete plant is operating, there shall be one 
sieve analysis and fineness modulus determination in accordance with <RID>ASTM C 136</RID>, <RID>ASTM C 117</RID>, and <RID>COE CRD-C 104</RID>
 for the fine aggregate or for each fine aggregate if it is batched in more than one size or classification.  
The location at which samples are taken may be selected by the Contractor as the most advantageous for 
control.  However, the Contractor is responsible for delivering fine aggregate to the mixer within specification 
limits.  The results shall be recorded on a sheet on which are also shown the specification limits applicable 
to the project.</LST><BRK/>
<BRK/>
<LST>b.  Fineness-Modulus Control Chart - Results for fineness modulus shall be grouped in sets of three consecutive 
tests, and the average and range of each group shall be plotted on a control chart.  The upper and lower 
control limits for average shall be drawn 0.10 units above and below the target fineness modulus, and 
the upper control limit for range shall be 0.20.</LST><BRK/>
<BRK/>
<LST>c.  Corrective Action for Fine Aggregate Grading - When the amount passing on any sieve is outside the 
specification limits, the fine aggregate shall be immediately resampled and retested.  If there is another 
failure on any sieve, the fact shall immediately be reported to the Contracting Officer.  Whenever a 
point on the fineness modulus control chart, either for average or range, is beyond one of the control 
limits, the frequency of testing shall be doubled.  If two consecutive points are beyond the control 
limits, the process shall be considered out of control and concreting shall be stopped.  The Contracting 
Officer shall be notified, and immediate steps shall be taken to rectify the situation.  After two consecutive 
points have fallen within the control limits, testing at the normal frequency may be resumed.</LST><BRK/>
<BRK/>
<LST>d.  Moisture Content Testing - When in the opinion of the Contracting Officer the electric moisture meter 
is not operating satisfactorily, there shall be at least four tests for moisture content in accordance 
with <RID>ASTM C 566</RID> during each 8-hour period of mixing plant operation.  The times for the tests shall be 
selected randomly within the 8-hour period.  An additional test shall be made whenever the slump is out 
of control or excessive variation in workability is reported by the placing foreman.  When an electric 
moisture meter is operating satisfactorily, at least two direct measurements of moisture content shall 
be made per week to check the calibration of the meter.  The results of tests for moisture content shall 
be used to adjust the added water in the control of the batch plant.</LST><BRK/>
<BRK/>
<LST>e.  Moisture Content Corrective Action - Whenever the moisture content of the fine aggregate changes 
by 0.5 percent or more from the previous sample, the scale settings for the fine aggregate batcher and 
water batcher shall be adjusted (directly or by means of a moisture compensation device).</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.2   Coarse Aggregate</TTL><BRK/>
<BRK/>
<LST>a.  Grading - At least once during each shift in which the concrete plant is operating, there shall be 
a sieve analysis in accordance with <RID>ASTM C 136</RID> for each size of coarse aggregate.  The location at which 
samples are taken may be selected by the Contractor as the most advantageous for production control.  
However, the Contractor shall be responsible for delivering the aggregate to the mixer within specification 
limits.  A test record of samples of aggregate taken at the same locations shall show the results of 
the current test as well as the average results of the five most recent tests including the current test.  
The Contractor may adopt limits for control coarser than the specification limits for samples taken other 
than as delivered to the mixer to allow for degradation during handling.  When facilities are available 
to test samples five times as large as those required in <RID>ASTM C 136</RID>, no averaging shall be done.</LST><BRK/>
<BRK/>
<LST>b.  Corrective Action for Grading - When the amount passing any sieve is outside the specification limits, 
the coarse aggregate shall be immediately resampled and retested.  If the second sample fails on any 
sieve, that fact shall be reported to the Contracting Officer.  Where two consecutive averages of five 
tests (or two consecutive tests where large samples are used) are outside specification limits, the operation 
shall be considered out of control, and that fact shall be reported to the Contracting Officer, concreting 
shall be stopped, and immediate steps shall be taken to correct the grading.</LST><BRK/>
<BRK/>
<LST>c.  Coarse Aggregate Moisture Content - A test for moisture content of each size group of coarse aggregate 
shall be made at least once a shift.  When two consecutive readings for smallest size coarse aggregate 
differ by more than 1.0 percent, frequency of testing shall be increased to that specified previously 
for fine aggregate.</LST><BRK/>
<BRK/>
<LST>d.  Coarse Aggregate Moisture Corrective Action - Whenever the moisture content of any size of coarse 
aggregate changes by 0.5 percent or more from the previous sample, the scale setting for the coarse aggregate 
batcher and the water batcher shall be adjusted to compensate for this.</LST><BRK/>
<BRK/>
<LST>e.  Material Finer than the<MET> 75 µm</MET><ENG> No. 200</ENG> Sieve - When in the opinion of the Contracting Officer, a problem 
exists in connection with the cleanliness of the coarse aggregate, tests shall be made in accordance 
with <RID>ASTM C 117</RID>.  Testing frequency shall be as directed.</LST><BRK/>
<BRK/>
<LST>f.  Corrective Action for material finer than the<MET> 75 µm</MET><ENG> No. 200</ENG> Sieve - When material finer than the 
No. 200 sieve exceeds 1.0 percent of the weight of the coarse aggregate finer than<MET> 37.5 mm</MET><ENG> 1-1/2 inch</ENG>
 or 0.5 percent of the weight of the aggregate coarser than<MET> 37.5 mm</MET><ENG> 1-1/2 inch</ENG>, the Contracting Officer 
shall be notified, and steps, such as washing or other corrective action, shall be initiated immediately.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.3   Quality of Aggregates</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTES:  Tests should be those listed in paragraph QUALITY.  The petrographic 
examination shall be used to identify deleterious substances in aggregates.  
Deleterious substances shall be listed individually with respective limits.</NPR><BRK/>
<BRK/>
<NPR>Only a limited number of laboratories are now running ASTM C 123 due to the 
toxic chemicals required.  Recommend that ASTM C 295 be specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>a.  Frequency of Quality Tests - Prior to submitting samples for mixture proportioning studies, the Contractor 
shall perform the tests for aggregate quality in the following list.  In addition, after the start of 
concrete placement, the Contractor shall perform tests for aggregate quality during concrete or aggregate 
production, in accordance with the following frequency schedule.  Samples tested after the start of concrete 
placement shall be taken immediately prior to entering the concrete mixer.</LST><BRK/>
<BRK/>
<TBL><BRK/>
<THD>                                    FREQUENCY<BRK/>
       PROPERTY       FINE AGGREGATE      COARSE AGGREGATE       TESTS<BRK/>
<BRK/></THD>
   Specific                                                   <RID>ASTM C 127</RID><BRK/>
   Gravity            Every 3 months      Every 3 months      <RID>ASTM C 128</RID><BRK/>
<BRK/>
   Absorption         Every 3 months      Every 3 months      <RID>ASTM C 127</RID><BRK/>
                                                            <RID>  ASTM C 128</RID><BRK/>
<BRK/>
   Flat and Elongate  Not applicable      Every 3 months      <RID>ASTM D 4791</RID><BRK/>
<BRK/>
   [Durability<BRK/>
   Factor using,                                         <RID>COE CRD-C 114</RID><BRK/>
   (Procedure A)     Every 12 months     Every 12 months  <RID>ASTM C 666/C 666M</RID>]<BRK/>
<BRK/>
   [Clay Lumps and<BRK/>
   Friable Particles Every 3 months      Every 3 months        <RID>ASTM C 142</RID>]<BRK/>
<BRK/>
   [Material Finer<BRK/>
   than the 75 µm<BRK/>
   (No. 200) Sieve   Not applicable      Every 3 months      <RID>ASTM C 117</RID>]<BRK/>
<BRK/>
   [Organic                                                    <RID>ASTM C 40</RID><BRK/>
   Impurities        Every 3 months      Not applicable        <RID>ASTM C 87</RID>]<BRK/>
<BRK/>
                                                               <RID>ASTM C 131</RID><BRK/>
   [L.A. Absorption    Not applicable      Every 6 months       <RID>ASTM C 535</RID>]<BRK/>
<BRK/>
   Liquid Limit and<BRK/>
   Plasticity Limits<BRK/>
   of -200 Sieve Size Every 3 months      Not applicable          [_____]<BRK/>
<BRK/>
   [Soft and Friable<BRK/>
   (Scratch Hardness)  Not applicable      Every 6 months  <RID>COE CRD-C 130</RID>]<BRK/>
<BRK/>
   [Petrographic<BRK/>
   Examination<BRK/>
   (including percent<BRK/>
   with fractured face)  Every 6 months    Every 6 months         [_____]]<BRK/>
<BRK/>
   [Chert, less than<BRK/>
   2.40 specific<BRK/>
   gravity               Every 6 months      Every 6 months    <RID>ASTM C 123</RID>]<BRK/>
<BRK/>
   [Coal and Lignite,<BRK/>
   less than 2.00<BRK/>
   specific gravity      Every 6 months      Every 6 months    <RID>ASTM C 123</RID>]<BRK/>
                                                            or <RID>ASTM C 295</RID><BRK/></TBL>
<BRK/>
<LST>b.  Corrective Action for Aggregate Quality - If the result of a quality test fails to meet the requirements 
for quality during submittal of samples for mixture-proportioning studies or immediately prior to start 
of concrete placement, production procedures or materials shall be changed and additional tests shall 
be performed until the material meets the quality requirements prior to proceeding with either mixture-proportioning 
studies or starting concrete placement.  After concrete placement commences, whenever the result of a 
test for quality fails the requirements, the test shall be rerun immediately.  If the second test fails 
the quality requirement, the fact shall be reported to the Contracting Officer and immediate steps taken 
to rectify the situation.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.4   Scales</TTL><BRK/>
<BRK/>
<LST>a.  Weighing Accuracy - The accuracy of the scales shall be checked by test weights at least once a month 
for conformance with the applicable requirements of paragraphs BATCH PLANT and CONTINUOUS MIXING PLANT.  
Such tests shall also be made as directed whenever there are variations in properties of the fresh concrete 
that could result from batching errors.</LST><BRK/>
<BRK/>
<LST>b.  Batching and Recording Accuracy - Once a week the accuracy of each batching and recording device 
shall be checked during a weighing operation by noting and recording the required weight, recorded weight, 
and the actual weight batched.  The Contractor shall confirm that the calibration devices described in 
paragraph BATCH PLANT for checking the accuracy of dispensed admixtures are operating properly.  If a 
continuous mixing plant is provided, the accuracy and operation of all feeding and dispensing units shall 
be checked before the start of operation each day.</LST><BRK/>
<BRK/>
<LST>c.  Scales Corrective Action - When the weighing accuracy or batching accuracy does not comply with specification 
requirements, the plant shall not be operated until necessary adjustments or repairs have been made.  
Discrepancies in recording accuracies shall be corrected immediately.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.5   Concrete Plant Control</TTL><BRK/>
<BRK/>
<TXT>The measurement of all constituent materials including cementitious materials, each size of aggregate, water, 
and admixtures shall be continuously controlled.  The aggregate weights and amount of added water shall be adjusted 
as necessary to compensate for free moisture in the aggregates.  A report shall be prepared indicating type and 
source of cement used, type and source of pozzolan or slag used, amount and source of admixtures used, aggregate 
source, the required aggregate and water weights per cubic yard, amount of water as free moisture in each size 
of aggregate, and the as-mixed aggregate and water weights per cubic<MET> meter</MET><ENG> yard</ENG> for each class of concrete placed 
during plant operation.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.6   Concrete</TTL><BRK/>
<BRK/>
<LST>a.  Conventional Concrete Slump Testing - At least two slump tests shall be made in accordance with <RID>ASTM C 143/C 143M</RID>
 on each conventional concrete mixture, including bedding mortar produced during each 8-hour period or 
less of concrete production each day.  Additional tests shall be made when excessive variation in workability 
is reported by the placing foreman or Government inspector.  The result of each test for each mixture 
shall be plotted on a control chart on which the upper and lower limits are set as specified in paragraph 
PROPORTIONS.  The range shall be plotted on a control chart on which the upper control limit is<MET> 50 mm</MET><ENG>
 2.0 inches</ENG>.  Samples for slump shall be taken at the mixer, however the Contractor is responsible for 
delivering the concrete to the placement site at the stipulated slump.  If the Contractor's materials 
or transportation methods cause slump loss between the mixer and the placement, samples shall be taken 
at the placement site as often as required by the Contracting Officer.</LST><BRK/>
<BRK/>
<LST>b.  Slump Corrective Action - Whenever points on the control chart approach the upper or lower control 
limits, an adjustment shall be made in the batch weights of water and fine aggregate.  The adjustments 
are to be made so that the total water content does not exceed that amount specified in the mixture proportions 
provided by the Contracting Officer based on the free water available with the aggregates and that amount 
of water batched.  If the adjustments to the batch weights of water and aggregates do not satisfactorily 
produce the required slump, the Contracting Officer may adjust the mixture proportions if the fine-aggregate 
moisture content is found to be stable and within the required limits.  When a single slump is outside 
the control limits, such adjustment is mandatory.  As soon as practical after each adjustment, another 
test shall be made to verify the correctness of the adjustment.  Whenever two consecutive individual 
slump tests, made during a period when there was no adjustment of batch weights, produce a point on the 
control chart for range above the upper control limits, the slump shall be considered to be out of control, 
the concreting operation halted, and the additional testing for aggregate moisture content required shall 
be undertaken, and action taken immediately to correct the problem.</LST><BRK/>
<BRK/>
<LST>c.  Air Content - At least one test for air content of conventional concrete shall be made on a randomly 
selected batch of each concrete mixture produced during each 8-hour period of concrete production.  Additional 
tests shall be made when excessive variation in workability is reported by the placing foreman or Government 
inspector.  Tests shall be made in accordance with <RID>ASTM C 231</RID>.  The average of each test for each mixture 
shall be plotted on control charts on which the average percent and upper and lower limits are set in 
accordance with paragraph PROPORTIONS.  The range between two consecutive tests for each mixture shall 
be plotted on a control chart on which the upper control limits is 3.0 percent.</LST><BRK/>
<BRK/>
<LST>d.  Air Content Corrective Action - Whenever points on the control chart approach the upper or lower 
control limits, an adjustment should be made in the amount of air-entraining admixture batched.  If a 
single test result is outside the specification limit, immediate adjustment is mandatory.  As soon as 
practical after each adjustment, another test shall be made to verify the correction of the adjustment.  
Whenever a point falls above the upper control for range, the dispenser shall be calibrated to ensure 
that it is operating correctly and with good reproducibility.  Whenever two consecutive points either 
for average or range are outside the control limits, the Contracting Officer shall be notified.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.7   Field Density</TTL><BRK/>
<BRK/>
<LST>a.  Testing and Checking - Density shall be determined for [each<MET> 450 square meters</MET><ENG> 5,000 square feet</ENG> 
of completed lift] [at least eight locations per RCC lift] with a calibrated nuclear density gauge in 
accordance with <RID>ASTM C 1040/C 1040M</RID>.  Densities shall be taken at depths of<MET> 100 and 200 mm</MET><ENG> 4 and 8 inches</ENG>
.  If the densities at<MET> 100 and 200 mm</MET><ENG> 4 and 8 inches</ENG> conflict, acceptance shall be at the<MET> 200 mm</MET><ENG> 8 inch</ENG>
 depth.</LST><BRK/>
<BRK/>
<LST>b.  Action Required - Whenever the nuclear gauge indicates density less than the specified density, a 
retest shall be made.  If the retest indicates unacceptable density, the Contracting Officer's Representative 
shall be notified, additional rolling shall be immediately provided, and a determination shall be made 
as to whether the lower density resulted from insufficient passes of the roller or a change in the mix 
properties.  If the mix properties have changed, adjustments such as increasing or decreasing the moisture 
content shall be made at the batch plant.  If the problem persists, the Contracting Officer may adjust 
the proportions of aggregates, cement, and/or pozzolan.  If the lower density is the result of incomplete 
rolling, the operator shall be notified and the Contracting Officer may require removal of the incompletely 
compacted material at no cost to the Government.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.8   Inspection Before Placing</TTL><BRK/>
<BRK/>
<TXT>Foundation or construction joints, forms, and embedded items shall be inspected by the Contractor in sufficient 
time prior to each concrete placement to certify to the Contracting Officer that they are ready to receive concrete.  
The results of each inspection shall be reported in writing.  The inspection of the lift surfaces of the RCC 
will be a continuing activity and shall be accomplished in accordance with paragraph REGULAR LIFT-JOINT TREATMENT.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.9   Placing Inspection</TTL><BRK/>
<BRK/>
<LST>a.  Inspection - The Contractor shall provide full time supervision of all placing operations to insure 
that the correct quality of RCC, conventional concrete, or grout is placed in each location and that 
all other aspects of the placing operation are performed in accordance with the contract.  During placing 
operations, the quality control staff shall measure and record concrete temperatures in accordance with <RID>
ASTM C 1064/C 1064M</RID>, ambient temperature hourly, record weather conditions, time of placement, yardage 
placed, and method of placement.</LST><BRK/>
<BRK/>
<LST>b.  Corrective Action - The placing foreman shall not permit placing to begin until he has verified that 
an adequate number of vibrators, spreaders, and compactors in working order and with competent operators 
are available.  Placing shall not be continued if any conventional concrete is inadequately consolidated 
or if any lift of RCC is not fully compacted.  Additional compaction, if necessary, shall be performed 
in accordance with paragraph ADDITIONAL COMPACTION.  If any batch of conventional concrete fails to meet 
the temperature requirements, immediate steps shall be taken to improve temperature controls.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.10   Vibrators</TTL><BRK/>
<BRK/>
<LST>a.  Vibrator Testing and Use - The frequency and amplitude of each vibrator shall be determined in accordance 
with <RID>COE CRD-C 521</RID>prior to initial use and at least once a month when concrete is being placed.  Additional 
tests shall be made as directed when a vibrator does not appear to be adequately consolidating the concrete.  
The frequency shall be determined while the vibrator is operating in concrete with the tachometer being 
held against the upper end of the vibrator head while almost submerged and just before the vibrator is 
withdrawn from the concrete.  The amplitude shall be determined with the head vibrating in air.  Two 
measurements shall be taken, one near the tip and another near the upper end of the vibrator head, and 
these results averaged.  The make, model, type, and size of the vibrator and frequency and amplitude 
results shall be reported in writing.  In addition, the self-propelled vibratory rollers, as specified 
in PART 2, paragraph PRIMARY ROLLERS, shall be checked for frequency and amplitude prior to use and once 
every 3 months when RCC is being placed.</LST><BRK/>
<BRK/>
<LST>b.  Vibrator Corrective Action - Any vibrator not meeting the requirements of paragraph VIBRATORS shall 
be immediately removed from service and repaired or replaced.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.11   Curing Inspection</TTL><BRK/>
<BRK/>
<LST>a.  Moist Curing Inspections - At least twice each shift, and twice per day on nonwork days an inspection 
shall be made of all areas subject to moist curing.  The surface moisture condition shall be noted and 
recorded.</LST><BRK/>
<BRK/>
<LST>b.  Moist Curing Corrective Action - When a daily inspection report lists an area of inadequate curing, 
immediate corrective action shall be taken, and the required curing period for those areas shall be extended 
by one day.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.12   Cold-Weather and Hot-Weather Protection</TTL><BRK/>
<BRK/>
<TXT>At least once each shift and once per day on nonwork days an inspection shall be made of all areas subject to 
cold-weather or hot-weather protection.  Any deficiencies shall be noted, corrected, and reported.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.10.2.13   Cold-Weather and Hot-Weather Protection Corrective Action</TTL><BRK/>
<BRK/>
<TXT>When a daily inspection report lists deficiencies, the deficiency shall be corrected immediately and the period 
of protection extended for one day.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.10.3   Reports</TTL><BRK/>
<BRK/>
<TXT>All results of tests or inspections conducted shall be reported informally as they are completed and in writing 
daily.  A weekly report shall be prepared for the updating of control charts covering the entire period from 
the start of the construction season through the current week.  During periods of cold-weather protection, reports 
of pertinent temperatures shall be made daily.  These requirements do not relieve the Contractor of the obligation 
to report certain failures immediately as required in preceding paragraphs.  Such reports of failures and the 
action taken shall be confirmed in writing in the routine reports.  The Contracting Officer has the right to 
examine all contractor quality control records.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT>   <END/><BRK/></SEC>