<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA      UFGS-09 67 23.15 (August 2008)<BRK/>
                                    -------------------------------<BRK/>
Preparing Activity:  <PRA>NAVFAC</PRA>         Superseding<BRK/>
                                    UFGS-09 62 50.10 (April 2006)  <BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 09 67 23.15</SCN><BRK/>
<BRK/>
<STL>FUEL RESISTIVE RESINOUS FLOORING, 3-COAT SYSTEM</STL><BRK/>
<BRK/>
<DTE>08/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>a three-coat, liquid 
flooring system with reflective urethane topcoats, slip resistance, and joint 
work</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The thin film flooring system is appropriate for use in: aircraft maintenance 
hangars, equipment maintenance shops, and all other industrial floors where 
resistance to abrasion and fuel is required.  Installation costs: $2.00 - $4.50 
per<MET> 0.1 square meters</MET><ENG> square foot</ENG>. Nominal thickness:<MET> 0.375 mm</MET><ENG> 15.0 mils</ENG>.  Can 
be rejuvenated by replacing urethane topcoats, and non-skid, only.  Approximate 
service life: Urethane top coating with non-skid grit at three or more years.  
The flooring system is neither conductive nor Electro-Static Dissipative (ESD), 
however, either formulation is easily designed upon request.  This specification 
is not for use in overcoating existing sound floor coatings.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Prior to the flooring systems installation, a concrete condition assessment 
in accordance with the Naval Facilities Engineering Service Center's (NFESC) 
Users Guide (UG)-2036-SHR is highly recommended.  The condition assessment is 
designed to identify problem floors and eliminate premature flooring failures 
produced by: 1) coating concrete with low surface strength, 2) coating concrete 
with high levels of surface contamination (oils, fuels, fats, waxes, etc.), 
and 3) coating concrete with a  high rate of Moisture Vapor Emission (MVE).  
The thin film flooring system is suitable for application to: A) "smooth" concrete 
surface texture, B) concrete with a rate of MVE no more than<MET> 169.0 micrograms 
moisture per second, square meter</MET><ENG>3.0 pounds moisture per 24 hours, 1000 square 
feet </ENG> (ASTM F 1869), C) concrete with surface strength greater than<MET> 1.34 MPa</MET><ENG>
 200 psi</ENG> (ASTM D 4541), and D) concrete with fuel/oil contamination to a depth 
no more than<MET> 6.25 mm</MET><ENG> 1/4 inch</ENG>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: If a concrete floor has a rate of Moisture Vapor Emission (MVE) more than<MET>
 197.0 micrograms moisture per second, square meter</MET><ENG> 3.5 pounds moisture per 
24 hours, 1000 square feet</ENG> (ASTM F 1869), apply a layered Moisture Reducing 
System (MRS) prior to the application of the thin film flooring system.  The 
MRS shall be compatible with the submitted flooring system and approved / warranted 
by the manufacturer of the thin film flooring system.  Apply the MRS to shot 
blasted concrete and reduce the rate of MVE to less than<MET> 169.0 micrograms moisture 
per second, square meter</MET><ENG> 3.0 pounds moisture per 24 hours, 1000 square feet</ENG>.  
MRSs can employ combinations of concrete sealers, specific epoxies, and moisture 
insensitive grouts, with or without mesh.  MRSs are available from the following 
partial list of vendors: Tennant (800) 553-8033, Stonhard (856) 779-7500, General 
Polymers (800) 543-7694, Crawford Labs (800) 356-7625, Floor Seal (800) 295-0221.  
Moisture Vapor Emission Test Kits (MVETK) are available from the following partial 
list of vendors: Floor Seal (800) 295-0221, Sinak (619)231-1771, General Polymers 
(800)534-7694, Crawford Labs (800) 356-7625. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include Section 03 01 30.71 CONCRETE REHABILITATION for repair of minor 
spalls and surface deterioration to depths less than<MET> 75 mm</MET><ENG> 3 inches</ENG>.  Specify 
epoxy mortar for repairs to depths no more than<MET> 50 mm</MET><ENG> 2 inches</ENG>.  Specify epoxy 
concrete for repairs to depths from<MET> 25 mm</MET><ENG> 1 inch</ENG> to<MET> 75 mm</MET><ENG> 3 inches</ENG>.  Contain 
repairs to depths greater than<MET> 25 mm</MET><ENG> 1 inch</ENG> in a rectangular geometry with saw 
cut edges.  Finish repairs to resemble surrounding concrete using a stainless 
steel trowel.  <BRK/>
<BRK/>
Include Section 32 01 29.61 PARTIAL DEPTH PATCHING FOR RIGID PAVEMENTS for repair 
of large spalls and severe deterioration to depths from <MET>75 mm </MET><ENG>3 inches </ENG>to<MET>150 
mm</MET><ENG>6 inches</ENG>.  Specify Portland Cement Concrete (PCC) with less than 0.45 water-cement 
ratio, light steel trowel finish, and cure using plastic coated burlap. Provide 
rectangular geometry for repairs with saw cut edges to a nominal repair depth 
of<MET> 150 mm</MET><ENG> 6 inches</ENG>.  Cure PCC repair for approximately 30 days prior to the 
application of the flooring system.  Do not cure repairs using liquid membrane-forming compounds.<BRK/>
<BRK/>
For repair of spalls and severely distressed concrete to depths greater than<MET>
 150 mm</MET><ENG> 6 inches</ENG>, seek material guidance from Section 03 31 00.00 10, CAST-IN-PLACE 
STRUCTURAL CONCRETE, Section 03 30 00 and procedural guidance from the American 
Concrete Pavement Association (ACPA) Guideline TB-002.02P "Concrete Paving Technology 
- Guidelines for Full Depth Repair."  Contain within repair base a minimum of <MET>
50 mm </MET><ENG>2 inches </ENG>of clean, non-reactive concrete sand over a suitable vapor retarder 
(<MET>0.25 mm </MET><ENG>10 mils </ENG> polyethylene sheeting).  Finish repairs by light steel trowel 
and cured using plastic coated burlap.  Cure repairs for approximately 30 days, 
or more, prior to the application of the flooring system.  Do not cure repairs 
using liquid membrane-forming compounds.<BRK/>
 <BRK/>
Scarify to level any curled and/or settled slab ends with joint surfaces displaying 
more than<MET> 3.2 mm</MET><ENG> 1/8 inch</ENG> difference in vertical height.  Contain within resulting 
surfaces a height difference no more than<MET> 1.5 mm</MET><ENG> 1/16 inch</ENG> and a surface texture 
equal ICRI 03732 CSP 4.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include Section 03 31 00.00 10, CAST-IN-PLACE STRUCTURAL CONCRETE, Section 
03 30 00 CAST-IN-PLACE CONCRETE for new concrete slab construction.  Employ 
measures to control the rate of base, subbase, and subgrade Moisture Vapor Emission 
(MVE) to total no more than <MET>169.0 micrograms moisture per second, square meter </MET><ENG>
3.0 pounds moisture per 24 hours, 1000 square feet </ENG>when measured on the slab's 
surface (ASTM F 1869).  Improper MVE controls have produced numerous premature 
coating failures.  In addition to appropriate subbase drainage, specify a minimum 
of<MET> 25 mm</MET><ENG> 2 inches </ENG> of clean, non-reactive concrete sand over no less than<MET> 0.25 
mm</MET><ENG> 10 mils</ENG> of polyethylene sheeting (ASTM F 4397) with sealed lap joints.  Specify 
concrete mix to be free of both accelerators containing calcium chloride and 
other sources of chloride ion contamination.  Specify two passes of a light 
power troweled finish and cure using plastic coated burlap or equal method.  
Do not cure concrete using liquid membrane-forming compounds.  Do not specify 
surface hardeners or dry shake finish (Section 09 97 23).  Approximately 60 
days following the concrete pour and prior to the installation of the flooring 
system, test concrete for the rate of MVE and confirm rate is no more than<MET> 169.0 
micrograms moisture per second, square meter</MET><ENG> 3.0 pounds moisture per 24 hours, 
1000 square feet</ENG> (ASTM D 1869).  Consult ACI 224.3R "Joints in Concrete Construction," 
ACI 302.1R "Guide for Concrete Floor and Slab Construction," ACI 360R "Design 
of Slabs on Grade," and other appropriate construction guidance. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Where tile is to be removed prior to the application of flooring system, 
test both tile and mastic for the presence of asbestos.  If asbestos is detected, 
include Section 02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS 
for removal and disposal. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: If flooring system is to be applied to warehouse floors with heavy forklift 
traffic, a semi-flexible joint sealant is required in lieu of the specified 
flexible sealant.  Use a semi-flexible epoxy sealant with approximately 90 percent 
elongation.  Do not use semi-flexible sealants in areas exposed to exterior 
temperatures. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include Section 01 45 02 NAVFAC QUALITY CONTROL. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include Section 01 57 19.00 20 TEMPORARY ENVIRONMENTAL CONTROLS.  This 
section defines fugitive dust, generated waste, hazardous materials, hazardous 
substance, hazardous waste, solid waste, construction and demolition (CD) debris, 
and liquid waste, and contains documentation for dangerous waste profile, waste 
information sheet, waste identification document, waste generation record, landfill 
disposal form, and hazardous material reporting.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
 <BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
 <BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM C 679</RID><RTL>(2003) Tack-Free Time of Elastomeric Sealants</RTL><BRK/><BRK/><RID>ASTM C 884/C 884M</RID><RTL>(1998; R 2005) Thermal Compatibility between Concrete and Epoxy-Resin Overlay</RTL><BRK/><BRK/><RID>ASTM D 1308</RID><RTL>(2002; R 2007) Effect of Household Chemicals on Clear and Pigmented Organic Finishes</RTL><BRK/><BRK/><RID>ASTM D 2240</RID><RTL>(2005) Standard Test Method for Rubber Property - Durometer Hardness</RTL><BRK/><BRK/><RID>ASTM D 2370</RID><RTL>(1998; R 2002) Tensile Properties of Organic Coatings</RTL><BRK/><BRK/><RID>ASTM D 2621</RID><RTL>(1987; R 2005) Infrared Identification of Vehicle Solids from Solvent-Reducible Paints</RTL><BRK/><BRK/><RID>ASTM D 2697</RID><RTL>(2003; R 2008) Volume Nonvolatile Matter in Clear or Pigmented Coatings</RTL><BRK/><BRK/><RID>ASTM D 3335</RID><RTL>(1985a; R 2005) Low Concentrations of Lead, Cadmium, and Cobalt in Paint by Atomic Absorption Spectroscopy</RTL><BRK/><BRK/><RID>ASTM D 3718</RID><RTL>(1985a; R 2005) Low Concentrations of Chromium in Paint by Atomic Absorption Spectroscopy</RTL><BRK/><BRK/><RID>ASTM D 3925</RID><RTL>(2002) Sampling Liquid Paints and Related Pigmented Coatings</RTL><BRK/><BRK/><RID>ASTM D 412</RID><RTL>(2006ae1e2) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension</RTL><BRK/><BRK/><RID>ASTM D 4541</RID><RTL>(2002) Pull-Off Strength of Coatings Using Portable Adhesion Testers</RTL><BRK/><BRK/><RID>ASTM D 6237</RID><RTL>(2003) Painting Inspectors (Concrete and Masonry Substrates)</RTL><BRK/><BRK/><RID>ASTM D 638</RID><RTL>(2008) Standard Test Method for Tensile Properties of Plastics</RTL><BRK/><BRK/><RID>ASTM E 11</RID><RTL>(2004) Wire Cloth and Sieves for Testing Purposes</RTL><BRK/><BRK/><RID>ASTM F 1869</RID><RTL>(2004) Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride</RTL><BRK/><BRK/></REF><REF><ORG>INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI)</ORG><BRK/><BRK/><RID>ICRI 03732</RID><RTL>(1997) Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays</RTL><BRK/><BRK/></REF><REF><ORG>THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)</ORG><BRK/><BRK/><RID>SSPC-TU 2</RID><RTL>(1997) Design, Installation, and Maintenance of Coating Systems for Concrete Used in Secondary Containment</RTL><BRK/><BRK/></REF><REF><ORG>U.S. GENERAL SERVICES ADMINISTRATION (GSA)</ORG><BRK/><BRK/><RID>FED-STD-595</RID><RTL>(Rev B; Am 1) Colors Used in Government Procurement</RTL><BRK/><BRK/></REF><REF><ORG>U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)</ORG><BRK/><BRK/><RID>29 CFR 1910.1000</RID><RTL>Air Contaminants</RTL><BRK/><BRK/><RID>29 CFR 1910.134</RID><RTL>Respiratory Protection</RTL><BRK/><BRK/><RID>29 CFR 1926.59</RID><RTL>Hazard Communication</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  Submit the following 
in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-04 Samples</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Joint Sealant</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
 <ITM><SUB>Thin Film Flooring System</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>White Aluminum Oxide Non-Skid Grit</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Joint Sealant</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Thin Film Flooring System</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Primer</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Urethane Topcoat</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>White Aluminum Oxide Non-Skid Grit</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Patch Test Demonstration</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Daily Inspection Report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Adhesion Testing</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Work Plan</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Flooring System Applicator Qualifications</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Joint Sealant</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Thin Film Flooring System</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Warranty</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-08 Manufacturer's Instructions</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Joint Sealant</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Thin Film Flooring System</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Water-Based Alkaline Degreaser</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-11 Closeout Submittals</SUB></LST><BRK/>
<BRK/>
  <ITM><SUB>Inspection Logbook</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   QUALITY ASSURANCE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Test Reports</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1.1   <SUB>Joint Sealant</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test results that confirm sealant complies with the requirements of Table 1a.  Samples must have been 
tested within the last three years.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.2   <SUB>Thin Film Flooring System</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test results that confirm the thin film flooring system complies with the requirements of Table Ib.  Samples 
must have been tested within the last three years.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.3   <SUB>Primer</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test results that confirm the primer complies with the requirements of Table 1c.  Samples must have been 
tested within the last three years.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.4   <SUB>Urethane Topcoat</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test results that confirm the urethane topcoat complies with the requirements of Table 1d.  Samples must 
have been tested within the last three years.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.5   <SUB>Daily Inspection Report</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit one copy of the daily inspection report to the Contracting Officer within 24 hours of the date recorded.</TXT><BRK/></SPT>
<BRK/></SPT>
<SPT><TTL>1.3.2   Certificates</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.2.1   <SUB>Work Plan</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit schedule to complete work within approximately twelve (12) consecutive days.  Submit a written plan describing 
in detail all phases of coating operations.  Address work sequencing, surface preparation, flooring system application, 
recoat and cure time projections, as well as how each step will be controlled, tested, and evaluated.  Address 
safety measures, work scheduling around weather, and record keeping.  Assign one supervisor to the job who is 
to remain at the site throughout all phases of work and who is to act as the contractor's primary point of contact.  
Identify this person in the submitted schedule.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.2   <SUB>Flooring System Applicator Qualifications</SUB></TTL><BRK/>
<BRK/>
<TXT>Minimum requirements for the installation contractor are as follows:  Completed three or more jobs within the 
past two years applying the specified materials to concrete surfaces in which the total area exceeds<MET> 18,587 square 
meters</MET><ENG> 200,000 square feet</ENG>.  Submit documentation listing location of work, point of contact at job site, total 
square footage of applied materials, listing of both materials and equipment used, and validation from coating 
manufacturer documenting quality of materials purchased per job for work totalling<MET> 18,587 square meters</MET><ENG> 200,000 
square feet</ENG> within the past two years.  In addition to the above requirements, be certified by the material manufacturer(s) 
to install the submitted coatings and sealant.  Submit copy of certificates.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.3   <SUB>Joint Sealant</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit literature documenting the past performance of the sealant's use in automotive and/or aircraft maintenance 
shops.  Minimum requirements are two or more maintenance shops with joint work totaling<MET> 3,048 linear meters</MET><ENG> 10,000 
linear feet</ENG>where the sealant has performed for two years with less than 1 percent combined sealant failures and 
defects.  List location of shops, total linear feet of sealant applied per shop, shop point of contact, date 
sealant was applied, and the name of the installed sealant material.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.4   <SUB>Thin Film Flooring System</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit literature documenting the past performance of the coating system's use in aircraft maintenance shops 
and over floors with high rates of Moisture Vapor Emission (MVE).  Minimum requirements are two or more aircraft 
maintenance shops totaling<MET> 3,160 square meters</MET><ENG> 34,000 square feet</ENG> where the coating system has performed for 
two years with less than 0.05 percent combined premature coating failures, material defects and surface discoloration; 
no more than 0.03 percent discoloration from aviation chemicals, tire plasticizers, and UV exposure.  Provide 
a minimum of two additional case histories where successful installation occurred on floor slabs with no less 
than<MET> 197.0 micrograms moisture per second, square meter</MET><ENG> 3.5 pounds moisture per 24 hours, 1000 square feet</ENG>.  
List location of shops, total coated area per shop, shop point of contact, date coating system was applied, successful 
installation to concrete with high MVE, and the names of the installed coating materials.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.5   <SUB>Warranty</SUB></TTL><BRK/>
<BRK/>
<TXT>Warrantee materials and workmanship for a minimum period of one year following coating and sealant application.  
The following terms and conditions form a part of the warranty: If the applied coating system develops either 
blisters (chemical), checks, softening, or lifting within one year following application, rework each area at 
contractor's expense.  The following conditions are excluded from the warranty: A) concrete cracking, flooring 
system mirrors cracks in concrete; B) cosmetic imperfections due to scratching and gouging; C) application to 
metallic concrete finishes ; and D) application to concrete with a rate of Moisture Vapor Emission (MVE)greater 
than<MET> 197.0 micrograms moisture per second, square meter</MET><ENG> 3.5 pounds moisture per 24 hours, 1000 square feet</ENG>.  
If the coating system's adhesion is in question, perform one adhesion test per<MET> 9.3 square meters</MET><ENG> 100 square feet</ENG>
 as described in the Article entitled "ADHESION TESTING."  To satisfy the warranty, each adhesion test shall 
produce cohesive failures, concrete removal over 95 percent of each pull-off coupon, and/or adhesion no less 
than<MET> 2.8 MPa</MET><ENG> 400 psi</ENG>.  Require two additional adhesion tests to confirm results for each area failing to meet 
adhesion requirements.  Within the warranty period, remove to sound material and rework all areas unable to meet 
adhesion requirements.  There shall be zero percent sealant failures within one year.  Within the warranty period, 
remove and rework all sealant material with chemically attacked surfaces and/or lifting from joint walls. Topcoat 
cracking over sealant is excluded from warranty.</TXT><BRK/></SPT>
<BRK/></SPT>
<SPT><TTL>1.3.3   Product Data</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.3.1   <SUB>Joint Sealant</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit manufacturer's printed instructions to include detailed application procedures, minimum and maximum application 
temperatures, and curing procedures.  In accordance with <RID>29 CFR 1926.59</RID>, include Material Safety Data Sheets 
(MSDS) for the sealant to be used at the job site.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.3.2   <SUB>Thin Film Flooring System</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit manufacturer's printed instructions to include detailed mixing, minimum and maximum application temperatures, 
acceptable atmospheric and/or interior climatic conditions, application procedures, curing procedures, and procedures 
for maintenance cleaning of flooring system.  Provide explicit instructions detailing surface preparation, recoat 
windows and remedial actions in case recoat windows are missed, and, if applicable, solvent-wiping between coats 
with acceptable types and grades of solvents.  In accordance with <RID>29 CFR 1926.59</RID>, include MSDSs for the coatings 
to be used at the job site.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.3.3   <SUB>Water-Based Alkaline Degreaser</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit manufacturer's printed instructions to include detailed mixing, rate of dilution, application procedures, 
and rinsing procedures.  In accordance with <RID>29 CFR 1926.59</RID>, include MSDSs for the water-based alkaline degreaser 
to be used at this job site.</TXT><BRK/></SPT>
</SPT><BRK/></SPT>
<SPT><TTL>1.4   DELIVERY, STORAGE, AND HANDLING</TTL><BRK/>
<BRK/>
<TXT>Store coatings and sealant in spaces with temperatures from<MET> 5 degrees C</MET><ENG> 40 degrees F</ENG> to<MET> 24 degrees C</MET><ENG> 75 degrees 
F</ENG>.  Inspect materials on site for damage prior to use.  Return to manufacturer packaged materials in dented, 
rusty, or leaking containers.  Conduct testing by manufacture of returned materials with an expired shelf life 
and if compliant, reissue a shelf life extension.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5   COATING HAZARDS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include either Section 01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIRMENTS 
or prepare instructions detailing each element of safety for use with this section.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure that employees are trained in all aspects of the safety plan.  Follow the coating manufacturer's written 
safety precautions throughout mixing, application, and curing of coatings.  Comply with respiratory protection 
requirements in <RID>29 CFR 1910.134</RID> and safe levels of airborne contaminants in <RID>29 CFR 1910.1000</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6   JOB SITE REFERENCES</TTL><BRK/>
<BRK/>
<TXT>Make available to the Contracting Officer at least one copy each of <RID>ASTM D 4541</RID>, <RID>ASTM D 6237</RID>, <RID>SSPC-TU 2</RID>, and <RID>
ICRI 03732</RID>, including replica standards ICRI 03732 CSP 1 through CSP 9, at the job site.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7   <SUB>PATCH TEST DEMONSTRATION</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This is a very important part of the submittal process.  While it is 
unusual to require a test patch prior to the submitted coating system's approval, 
this flooring system is unusual in that it is required to provide extended, 
uninterrupted performance.  A demonstration of contractor claims, especially 
under conditions to be encountered in the specific project, is considered necessary.<BRK/>
<BRK/>
If customer dislikes level of non-skid grit, adjustments to the specification 
can be made.  Grit coarser than #60 aluminum oxide is not recommended.  On architectural 
floors, non-skid grit broadcast rates can range from none to approximately half 
the specified level.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Prior to the submitted flooring system's approval, apply the complete coating system to a<MET> 3 meter by 3 meter</MET><ENG> 
10 foot by 10 foot</ENG> square section of concrete as prepared in accordance with Part 3 "EXECUTION."  Within this 
area, perform three adhesion tests as described in the Article entitled "ADHESION TESTING."  If adhesion testing 
produces cohesive failures within the concrete, no less than<MET> 1 mm</MET><ENG> 40 mils</ENG> concrete removed over 95 percent of 
each pull-off coupon, and/or adhesion more than<MET> 2.75 MPa</MET> <ENG>400 psi</ENG>, patch test adhesion is acceptable.  If concrete 
surface preparation was insufficient, apply an additional coating system patch to properly prepared concrete 
followed by the above adhesion testing. If adhesion results are unacceptable for both the topcoats and the primer, 
submit a new coating system manufactured by a different coating vendor.  Apply a patch of the new coating system 
and subject patch to the above requirements for adhesion prior to approval.  If customer dislikes non-skid grit 
application, adjustments to the specifications can be made.  Grit coarser than #60 aluminum oxide is not recommended.  </TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The specified materials are not appropriate for use in primary chemical 
containment, secondary chemical containment, or on floors subjected to spills 
from concentrated acids, bases, and organic solvents.  Consult with the Naval 
Facilities Engineering Service Center's (NFESC) Paints and Coatings Center of 
Expertise for alternative coating systems to suit specific Navy needs.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.1   JOINT SEALANT</TTL><BRK/>
<BRK/>
<TXT>Formulate the joint sealant to exhibit the properties as listed in Table Ia.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2   THIN FILM FLOORING SYSTEM</TTL><BRK/>
<BRK/>
<TXT>A three-coat industrial flooring system consisting of primer and two urethane topcoats.  Apply the coating system 
at a Dry Film Thickness (DFT) ranging from<MET> 325 to 500 microns</MET><ENG> 13 to 20 mils</ENG> and contain a broadcast of aluminum 
oxide non-skid grit.  Formulate the complete flooring system to exhibit the properties as listed in Table Ib. 
Additional requirements for primer coat and urethane topcoat are listed in the following sub-paragraphs.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Primer Coat</TTL><BRK/>
<BRK/>
<TXT>In addition to the requirements of the thin film flooring system, formulate the primer coat to exhibit the properties 
as listed in Table Ic.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2   Urethane Topcoat</TTL><BRK/>
<BRK/>
<TXT>In addition to the requirements of the thin film flooring system, formulate the urethane top coat to exhibit 
the properties as listed in Table Id.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3   <SUB>WHITE ALUMINUM OXIDE NON-SKID GRIT</SUB></TTL><BRK/>
<BRK/>
<TXT>Size #60, dust free (washed and dry), minimum 99 percent pure, having the following sieve analysis when tested 
using a<MET> 1000 gram</MET><ENG> 2.2 pound</ENG> sample <BRK/>
(<RID>ASTM E 11</RID>):<BRK/>
<BRK/>
      Sieve No. 40         100% passing<BRK/>
      Sieve No. 50         15-30% retained<BRK/>
      Sieve No. 60         70-85% retained<BRK/>
      Sieve No. 70         0-15% retained</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4   PREAPPROVED MATERIALS</TTL><BRK/>
<BRK/>
<TXT>Table II contains a listing of vendors with "preapproved materials."</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   COATING SAMPLE COLLECTION</TTL><BRK/>
<BRK/>
<TXT>The Contracting Officer and QC Manager shall witness all material sampling. Notify the Contracting Officer a 
minimum of three days in advance of sampling.  Obtain liquid samples of each component of primer and topcoat 
by random selection from sealed containers and in accordance with <RID>ASTM D 3925</RID>. Samples may be either individual 
cans of liquid material or <MET>1.0 liter</MET> <ENG>1.0 quart </ENG>quantities of properly mixed, extracted, and sealed liquid material.  
Identify samples by designated name, specification number, batch number, project contract number, sample date, 
intended use, and quantity involved.  When the applied coating system has met the requirements defined in the 
Article entitled "ADHESION TESTING," return coating to the installation contractor for proper disposal.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>3.2   TILE AND TILE ADHESIVE REMOVAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Delete "Tile and Tile Adhesive Removal" if concrete is not tiled.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Remove 100 percent of tile employing one or more of the following techniques: chipping, scraping, sanding, scarification, 
high-pressure water, and various hand tools.  Remove 100 percent of the tile adhesive using solvents and power 
scrubbing.  Remove residual contamination using hot potable water under a minimum of<MET> 27.6 MPa</MET><ENG> 4,000 psi</ENG>.  Resulting 
surfaces shall appear clean and display the gray color of concrete.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.3   JOINT MATERIAL REMOVAL, RE-SAW CUTTING, CRACK CHASING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Hairline cracks having no more than<MET> 3.2 mm</MET><ENG> 1/8 inch</ENG> width are typically 
not repaired.  However, cracks greater than<MET> 3.2 mm</MET><ENG> 1/8 inch</ENG> width can be chased 
to a minimum depth of<MET> 12.5 mm</MET><ENG> 1/2 inch</ENG> and sealed using the procedures and materials 
specified for joints.  Cracks more than <MET>18.75 mm </MET><ENG>3/4 inch </ENG>width can be repaired 
using either epoxy mortar and/or epoxy concrete.  Sealed cracks will assist 
in protecting the subbase against chemical migration.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Remove 100 percent of the existing material in all joints including material bonded to joint walls and base.  
Rigid material may require the use of saw cutting equipment to remove.  Joints may be widened up to<MET> 3.2 mm</MET><ENG> 1/8 
inch</ENG> when re-saw cutting.  Chase concrete cracks identified for repair  and open to a minimum depth of<MET> 12.5 mm</MET><ENG>
 1/2 inch</ENG> below crack surface with smooth vertical walls.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4   DEGREASING</TTL><BRK/>
<BRK/>
<TXT>On both coated and uncoated concrete, degrease entire floor by scrubbing using a solution of hot potable water,<MET>
 49 degrees C</MET><ENG> 120 degrees F</ENG> to<MET> 77 degrees C</MET><ENG> 170 degrees F</ENG>, and a concentrated water-based alkaline degreaser. 
Perform two complete degreasing cycles on the entire floor surface.  Allow solution to soak into surfaces prior 
to scrubbing and remove using hot potable water under a minimum of<MET> 27.6 MPa</MET><ENG> 4,000 psi</ENG>.  Rinsing is complete when 
the rinse water appears clear.  If the industrial detergent is not biodegradable, collect all rinse water and 
dispose as hazardous waste.  Squeegees and shop vacuums may be used to collect pooling rinse water.  Fans may 
be used to aid drying of floor surfaces.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>3.5   COATING SYSTEM REMOVAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Delete "Coating System Removal" if concrete is uncoated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Remove 100 percent of the existing coating system employing one or more of the following techniques: shot blasting, 
chipping, scraping, sanding, scarification, high pressure water blasting, and various hand tools.  The use of 
impact tools such as scabblers may be used to remove unsound epoxy mortar flooring systems.  In general, a coating 
system cannot be completely removed by shot blasting and, to attain 100 percent coating removal, and requires 
a combination of the above techniques.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.6   SURFACE PREPARATION</TTL><BRK/>
<BRK/>
<TXT>Shot blast entire floor to produce a level of coarseness equal to <RID>ICRI 03732</RID> CSP 3. Overlap each pass of shot 
blasting by<MET> 6.25 mm</MET><ENG> 1/4 inches</ENG> to<MET> 12.5 mm</MET><ENG> 1/2 inches</ENG>.  Add new shot to shot blasting equipment prior to blasting.  
Prepare surfaces inaccessible to shot blasting, base of perimeter walls and under secured equipment, using diamond 
disk grinding and/or light scarification to produce a level of coarseness equal to <RID>ICRI 03732</RID> CSP 2 and/or <RID>ICRI 03732</RID>
 CSP 4, respectively.  Resulting surfaces shall appear clean and contain the appropriate level of surface coarseness.  
If the resulting level of cleanliness cannot be determined, place numerous drops of water on surfaces that appear 
contaminated.  If the water drops soak into concrete, the surfaces are free of hydrocarbon contamination (oils, 
grease, skydrol). If the water drops bead up and do not flatten out, surfaces require additional degreasing as 
detailed in the Article entitled "DEGREASING."  Shot blasting coarse concrete and/or broom finished concrete 
can produce a level of coarseness equal to <RID>ICRI 03732</RID>CSP 5: employ a best effort attempt to minimize over shot 
blasting of coarse concrete.  If coarse concrete is encountered, shot blasting to a level of coarseness equal 
to <RID>ICRI 03732</RID> CSP 5 is acceptable: however, extremely coarse concrete can require resurfacing prior to the flooring 
system's installation.  Sweep, vacuum, and run a high powered magnet over all surfaces to be coated, including 
joints.  </TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: At this point in the installation sequence, minor spalls and surface deterioration 
to depths less than<MET> 75 mm</MET><ENG> 3 inches</ENG> can be repaired.  Use epoxy mortar for repairs 
to depths no more than<MET> 50 mm</MET><ENG> 2 inches</ENG>.  Use epoxy concrete for repairs to depths 
from<MET> 25 mm to 75 mm</MET><ENG> 1 inch to 3 inches</ENG>.  Finish repairs to depths greater than<MET>
 25 mm</MET><ENG> 1 inch</ENG> with a rectangular geometry with saw cut edges.  Repairs shall 
be finished to resemble surrounding concrete using a stainless steel trowel.  
Include Section 03 01 30.71 CONCRETE REHABILITATION if concrete repairs of this 
nature are required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<BRK/></SPT>
<SPT><TTL>3.7   JOINT TREATMENT</TTL><BRK/>
<BRK/>
<TXT>Use the "Conventional Sealed Joint" as detailed in Figure 1 of <RID>SSPC-TU 2</RID>  to seal joints.  Employ measures to 
reduce contamination from equipment and foot traffic.  Limit floor access to essential contractor personnel.  
Confirm joint surfaces are sufficiently clean.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.7.1   Install Backer Rod</TTL><BRK/>
<BRK/>
<TXT>Install a continuous length of round, closed-cell polyethylene backer rod into each joint using a backer rod 
tool.  For<MET> 12.5 mm</MET><ENG> 1/2 inch</ENG>,<MET> 9.4 mm</MET><ENG> 3/8 inch</ENG>, and<MET> 6.25 mm</MET><ENG> 1/4 inch</ENG> wide joints, place backer rod to a depth of<MET>
 9.4 mm</MET><ENG> 3/8 inch</ENG> (depth equals the distance from the concrete's surface to the highest point on the backer rod).  
For joints greater than or equal to<MET> 18.75 mm</MET><ENG> 3/4 inch</ENG> width, place backer to a depth of<MET> 15.6 mm</MET><ENG> 5/8 inch</ENG> below 
the concrete's surface.  Fit backer rod tight between joint walls (30 percent compression).  Remove and reinstall 
all backer rod that is installed using either the incorrect size (loose fit) or at the incorrect depth.  Following 
backer rod installation, apply painter's tape to surfaces adjacent joints to protect from sealant.</TXT><BRK/>
<BRK/></SPT>
<BRK/>
<SPT><TTL>3.7.2   Sealant Application</TTL><BRK/>
<BRK/>
<TXT>Apply sealant directly into joints using a bulk-calking gun.  At room temperature, the resulting sealant application 
shall exhibit a concave recess between<MET> 3.2 mm</MET><ENG> 1/8 inch</ENG> to<MET> 1.6 mm</MET><ENG> 1/16 inch</ENG> below the concrete's surface.  Remove 
and reapply cured sealant remaining either flush or greater.  Following sealant application, remove painter's 
tape and sealant drips on concrete surfaces.  Cure sealant a minimum of 24 hours, prior to the application of 
coatings.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.8   PRE-APPLICATION TESTING FOR CONTAMINATION</TTL><BRK/>
<BRK/>
<TXT>Spot check surfaces for oil/grease contamination using the water break test.  At a rate of 5 tests per<MET> 95 square 
meters</MET><ENG> 1000 square feet</ENG>, place one to two drops of water onto surfaces and observe for beading.  Test all other 
surfaces that show visible signs of potential contamination.  Apply additional degreasing techniques to surfaces 
displaying water beading in accordance with the Article entitled "DEGREASING."</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9   COATING APPLICATION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Use epoxy primer the same color, either white or ultra-light gray, as 
the selected topcoats.  Ultra-light gray is preferred to white.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Vacuum flooring space one additional time prior to coating application.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.9.1   Primer Application</TTL><BRK/>
<BRK/>
<TXT>Apply primer to flooring space at<MET> 175 microns</MET><ENG> 7.0 mils</ENG> to<MET> 375 microns</MET><ENG> 15.0 mils</ENG> Dry Film Thickness (DFT).  If 
the prepared concrete resembles an <RID>ICRI 03732</RID> CSP 3 surface, apply the primer at a minimum of<MET> 175 microns</MET><ENG> 7.0 
mils</ENG> DFT.  If the prepared concrete resembles an <RID>ICRI 03732</RID> CSP 5 surface, apply the primer at a maximum of<MET> 375 
microns</MET><ENG> 15.0 mils</ENG> DFT.  The previously applied sealant may be lightly coated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.2   Non-Skid Grit Broadcast</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Aircraft hangars servicing light aircraft with weight less that<MET> 18,140 
kg</MET><ENG> 40,000 pounds</ENG> may require a higher loading of non-skid grit.  The additional 
grit will assist in towing aircraft under wet conditions; however, the additional 
grit will decrease coating aesthetics.  Up to <MET>450 grams </MET><ENG>1 pound </ENG>per<MET> 93 square 
meters</MET><ENG> 100 square feet</ENG> of additional non-skid grit can be required<BRK/>
<BRK/>
On either warehouse or architectural floors, considerably less non-skid grit 
may be appropriate.  Broadcast rates can range from none to less than<MET> 450 grams</MET><ENG>
 1.0 pound</ENG> per<MET> 93 square meters</MET><ENG> 1000 square feet</ENG>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Broadcast non-skid grit at a rate of<MET> 680 grams</MET><ENG> 1.5 pounds</ENG> per<MET> 9.3 square meters</MET><ENG> 100 square feet</ENG> into the second 
urethane top coat and backroll.  Map floor into<MET> 55.8 square meter</MET><ENG> 600 square foot</ENG> sections where<MET> 4080 grams</MET><ENG> 9.0 
pounds</ENG> of non-skid grit is pre-weighed, placed into clean buckets and used in its entirety per marked<MET> 55.8 square 
meter</MET><ENG> 600 square foot</ENG> section.  </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.3   Application of Topcoats</TTL><BRK/>
<BRK/>
<TXT>Apply two coats of urethane topcoat to the epoxy primer and broadcast white aluminum oxide non-skid grit directly 
into the second urethane topcoat.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.9.3.1   First Topcoat</TTL><BRK/>
<BRK/>
<TXT>Apply a full coat of the urethane topcoat at a spreading rate from<MET> 62.5 to 80 microns</MET><ENG> 2.5 to 3.2 mils</ENG> Dry Film 
Thickness (DFT).  Stripe coat perimeter edges and around equipment footings.  Monitor and record a minimum of 
one Wet Film Thickness (WFT) reading per<MET> 55.8 square meter</MET><ENG> 600 square feet</ENG> of floor surface.  Sealant is to be 
lightly coated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.3.2   Second Topcoat</TTL><BRK/>
<BRK/>
<TXT>Apply a second coat of the urethane topcoat at a spreading rate of<MET> 62.5 to 80 microns</MET><ENG> 2.5 to 3.2 mils</ENG> DFT. Stripe 
coat perimeter edges and around equipment footings.  Monitor and record a minimum of one WFT reading per<MET> 55.8 
square meters</MET><ENG> 600 square feet</ENG> of floor surface prior to broadcasting non-skid grit. When the correct WFT has 
been applied per<MET> 55.8 square meters</MET><ENG> 600 square feet</ENG> of area, immediately and evenly broadcast non-skid grit directly 
into the second topcoat of urethane and backroll in two directions.  Test the adhesion of the thin film flooring 
system in accordance with the Article entitled "ADHESION TESTING."</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.3.3   Walkway Stripe and Grounding Rod Markings</TTL><BRK/>
<BRK/>
<BRK/>
<TXT>Place the walkway stripe and grounding rod markings according to Government drawings, if applicable.  When the 
second topcoat is within its recoat window, apply a walkway stripe of the red/orange urethane topcoat at<MET> 75 microns</MET><ENG>
 3.0 mils</ENG> DFT, completely hiding the top coat, in one coat.  If insufficient hiding occurs, apply one additional 
coat of the walkway stripe.  Lightly broadcast non-skid grit into the wet walkway stripe.  Use solvent resistant 
tape to protect the floor coating against stripe coat bleed.  A thin clear coat of either epoxy or urethane may 
be required to prevent stripe coat bleed prior to the full application of the colored stripe coat.  Apply grounding 
rod markings using similar procedures, urethane top coat, and colors and size according to Government drawings.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.10   CURING</TTL><BRK/>
<BRK/>
<TXT>Cure installed materials to display performance equal to manufacturer's product literature.  Remove and reapply 
improperly cured material.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11   FIELD TESTS AND INSPECTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.11.1   Coating Inspector</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Insert directly into Section 01 45 02 NAVFAC <BRK/>
QUALITY CONTROL requirement for NACE Coating Inspector.  See Appendix A for 
instructions on modifying Section 01 45 02 NAVFAC <BRK/>
QUALITY CONTROL.  The NACE Coating Inspector will act as QC Specialist.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Consider the Coating Inspector as a QC Specialist, who works for the QC Manager, and be qualified in accordance 
with Section <SRF>01 45 02</SRF> NAVFAC <BRK/>
QUALITY CONTROL.  The Coating Inspector will be present during all field tests, surface preparation, flooring 
application, initial cure of the flooring system, and during all flooring repair work.  The Coating Inspector 
will provide all tools/equipment necessary to perform field tests and inspection.  The Coating Inspector will 
be responsible for field tests and specified level of inspection.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.2   Inspection</TTL><BRK/>
<BRK/>
<TXT>Document weather conditions, job site occurrences, and report conditions and occurrences potentially detrimental 
to the flooring system.  The listed inspection requirements are in addition to the QC inspection and reporting 
requirements defined in Section <SRF>01 45 02</SRF>NAVFAC QUALITY CONTROL.  <BRK/>
Prepare a project reference sheet outlining all requirements, tests, test methods, and evaluation criteria, and 
hold regular meetings with contractor personnel, including shot blasting operators and applicators, to review 
requirements/evaluation criteria for upcoming work prior to execution.  At the start of coating operations and 
every 1.0 hour following until daily work is complete, record air temperature, substrate temperature, and relative 
humidity.  Following the application of each coat, inspect surfaces for improperly cured material, blisters, 
inadequate and/or excessive coating thickness, and other defects. Document each inspection, test, non-compliant 
area, and location of each non-compliant area.  List method of evaluation, evaluation criteria, areas requiring 
rework, and all other pertinent observations.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.11.2.1   Daily Inspection Report</TTL><BRK/>
<BRK/>
<TXT>Submit to the Contracting Officer one copy of the daily inspection report completed each day when performing 
work under this Section.  Use Appendix X1 "Inspection Checklist" of <RID>ASTM D 6237</RID> to monitor daily activity and 
to assist in preparing the daily inspection report.  Note each non-compliant issue and each issue identified 
for rework in accordance with the QC documentation procedures of Section <SRF>01 45 02</SRF> NAVFAC <BRK/>
QUALITY CONTROL.  Use of forms containing entry blocks for all required data is encouraged.  The data shall be 
legible and presented in a professional format.  Submit report within 24 hours of the report date.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.2.2   <SUB>Inspection Logbook</SUB></TTL><BRK/>
<BRK/>
<TXT>Record all daily activity related to this section in the Inspection Logbook, including the daily inspection reports, 
as well as all other pertinent observations and information.  Use  hard or spiral bound book with consecutively 
numbered pages.  Prior to final payment, submit original Inspection Logbook to the Contracting Officer upon completion 
of project.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.2.3   Inspection Equipment</TTL><BRK/>
<BRK/>
<TXT>Use equipment in good condition, operational within its design range, and calibrated as required by the specified 
standard for use with each device.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.11.3   <SUB>Adhesion Testing</SUB></TTL><BRK/>
<BRK/>
<TXT>Perform a minimum of three adhesion tests in accordance with <RID>ASTM D 4541</RID> to the thin film flooring system.  Select 
three random flooring locations spaced a minimum of<MET> 6 meters</MET><ENG> 20 feet</ENG> between each location.  Prior to attaching 
pull-off coupons, lightly sand flooring surface and attach pull-off coupons containing a grit-blasted anchor 
profile.  Adhere directly to the center of each sanded surface a<MET> 18.75 mm</MET><ENG> 3/4 inch</ENG> diameter pull-off coupon.  
When pull-off coupon adhesive has sufficiently cured, score circumference of each pull-off coupon to concrete 
substrate.  Test adhesion and evaluate results. If testing produces cohesive failures within the concrete, no 
less than <MET>1 mm </MET><ENG>40 mils </ENG>concrete removed over 95 percent of each pull-off coupon, and/or adhesion more than<MET> 2.75 
MPa</MET><ENG> 400 psi</ENG> coating system's adhesion is acceptable.  If the above requirements are not satisfied, then perform 
one adhesion test per<MET> 9.3 square meters</MET><ENG> 100 square feet</ENG> using the above procedures.  Perform two additional tests 
per non-compliant area to confirm results.  Remove to sound material and rework all areas unable to meet adhesion 
requirements.  Repair each adhesion test using a combination of primer, sand-filled epoxy mortar (for deep cohesive 
failures, if applicable), and two urethane topcoats.  Make repairs flush with adjacent coatings and display an 
equivalent appearance.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.12   FINAL CLEANUP</TTL><BRK/>
<BRK/>
<TXT>Following completion of the work, remove debris, equipment,and materials from the site.  Remove temporary connections 
to Government or contractor furnished water and electrical services.  Restore existing facilities in and around 
the work areas to their original condition.</TXT><BRK/>
<BRK/>
<MET><BRK/>
<PGE/><TBL><BRK/>
<THD><HL4>TABLE I - MATERIALS REQUIREMENTS</HL4><BRK/>
<HL4>TABLE Ia</HL4><BRK/>
<BRK/>
Test                                 Minimum Requirement<BRK/>
                                    (maximum where indicated)<BRK/>
---------------------------------------------------------------</THD><BRK/>
<BRK/>
Sealant System                      Polysulfide (Manganese Cure; MnO2)<BRK/>
(two-pack: self-leveling)           or Urethane<BRK/>
<BRK/>
Percent Volume Solids               100 %<BRK/>
<BRK/>
Chemical Resistance to JP-8+100     48 hours immersion:<BRK/>
Fuel @ 21<SPS>0</SPS> C                        2.0% (max) weight increase, <BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase, <BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor        48 hours immersion:<BRK/>
Oils @ 21<SPS>0</SPS> C                        2.0% (max) weight increase<BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase<BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols     48 hours immersion:<BRK/>
@ 21<SPS>0</SPS> C (<RID>ASTM D 1308</RID>) (see note 1)  2.0% (max) weight increase<BRK/>
                                    5.0% (max) volume increase<BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Hardness (<RID>ASTM D 2240</RID>:Shore A)      20<BRK/>
<BRK/>
Tensile Strength (<RID>ASTM D 412</RID>)       1.0 MPa <BRK/>
(or <RID>ASTM D 638</RID>)<BRK/>
<BRK/>
Percent Elongation (<RID>ASTM D 412</RID>)     500%<BRK/>
(or <RID>ASTM D 638</RID>)<BRK/>
<BRK/>
Tack Free                           12 hours maximum<BRK/>
@ 18.3<SPS>0</SPS> C (<RID>ASTM C 679</RID>)       <BRK/>
<BRK/>
Adhesion to Concrete                0.96 MPa <BRK/>
<BRK/>
Adhesion to Urethane Topcoats       0.96 MPa <BRK/>
(paintable sealant)<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immerse and test a minimum of three 50 mm by 12.5 mm by 12.5 mm sections of cured sealant.<BRK/></TBL>
</MET><BRK/>
<ENG><BRK/>
<PGE/><TBL><BRK/>
<THD><HL4>TABLE I - MATERIALS REQUIREMENTS</HL4><BRK/>
<HL4>TABLE Ia</HL4><BRK/>
<BRK/>
Test                                 Minimum Requirement<BRK/>
                                    (maximum where indicated)<BRK/>
---------------------------------------------------------------</THD><BRK/>
<BRK/>
Sealant System                      Polysulfide (Manganese Cure; MnO2)<BRK/>
(two-pack: self-leveling)           or Urethane<BRK/>
<BRK/>
Percent Volume Solids               100 %<BRK/>
<BRK/>
Chemical Resistance to JP-8+100     48 hours immersion:<BRK/>
Fuel @ 70<SPS>0</SPS> F                        2.0% (max) weight increase, <BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase, <BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor        48 hours immersion:<BRK/>
Oils @ 70<SPS>0</SPS> F                        2.0% (max) weight increase<BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase<BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols     48 hours immersion:<BRK/>
@ 70<SPS>0</SPS> F (<RID>ASTM D 1308</RID>) (see note 1)  2.0% (max) weight increase<BRK/>
                                    5.0% (max) volume increase<BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Hardness (<RID>ASTM D 2240</RID>:Shore A)      20<BRK/>
<BRK/>
Tensile Strength (<RID>ASTM D 412</RID>)       150 psi<BRK/>
(or <RID>ASTM D 638</RID>)<BRK/>
<BRK/>
Percent Elongation (<RID>ASTM D 412</RID>)     500%<BRK/>
(or <RID>ASTM D 638</RID>)<BRK/>
<BRK/>
Tack Free                           12 hours maximum<BRK/>
@ 65<SPS>0</SPS> F(<RID>ASTM C 679</RID>)     <BRK/>
<BRK/>
Adhesion to Concrete                140 psi<BRK/>
<BRK/>
Adhesion to Urethane Topcoats       140 psi<BRK/>
(paintable sealant)<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immerse and test a minimum of three 2 inch by 1/2 inch by 1/2 inch section of cured sealant.<BRK/></TBL>
</ENG><BRK/>
<BRK/>
<BRK/>
<MET><BRK/>
<PGE/><TBL><BRK/>
<THD><HL4>TABLE Ib</HL4><BRK/>
<BRK/>
Test                                        Minimum Requirement<BRK/>
                                           (maximum where indicated)<BRK/>
----------------------------------------------------------------</THD><BRK/>
<BRK/>
Tensile Strength (<RID>ASTM D 2370</RID>)              4.83 MPa <BRK/>
<BRK/>
Percent Elongation (<RID>ASTM D 2370</RID>)            5.0%<BRK/>
<BRK/>
Adhesion to Concrete (<RID>ASTM D 4541</RID>)          2.75 MPa  or <BRK/>
(see note 1)                                100 % failure in concrete<BRK/>
<BRK/>
Thermal Compatibility between Concrete      60<SPS>0</SPS> C <BRK/>
(<RID>ASTM C 884/C 884M</RID>)<BRK/>
<BRK/>
Heat Resistance, continuous exposure        "pass"<BRK/>
<BRK/>
Chemical Resistance to JP-8+100 Fuel        48 hours immersion:<BRK/>
@ 21<SPS>0</SPS> C (<RID>ASTM D 1308</RID>) (see note 2)          2.0% (max) weight increase<BRK/>
                                            2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor Oils           48 hours immersion:<BRK/>
@ 21<SPS>0</SPS> C (<RID>ASTM D 1308</RID>)(see note 2)           2.0% (max) weight increase<BRK/>
                                            2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols             48 hours immersion:<BRK/>
@ 21<SPS>0</SPS> C(<RID>ASTM D 1308</RID>)(see note 2)            2.0% (max) weight increase<BRK/>
                                            2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Lead (<RID>ASTM D 3335</RID>)                          0.06% (max)<BRK/>
<BRK/>
Cadmium (<RID>ASTM D 3335</RID>)                       0.06% (max)<BRK/>
<BRK/>
Chromium (<RID>ASTM D 3718</RID>)                      0.00%<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  When tested for adhesion, coating system shall display 2.75 MPa adhesion and/or remove no less than 1.0 mm of 
concrete over 95 percent of each pull-off coupon throughout service.<BRK/>
<BRK/>
(2)  Immediately following immersion, in addition to the listed requirements, coating system shall be evaluated for 
blisters, checks, discoloration, softening, and lifting.  Coating system shall be visually free of blisters, checks, 
discoloration, and display both substrate and intercoat adhesion no less than 2.4 MPa (<RID>ASTM D 4541</RID>).<BRK/></TBL>
</MET><BRK/>
<ENG><BRK/>
<PGE/><TBL><BRK/>
<THD><HL4>TABLE Ib</HL4><BRK/>
<BRK/>
Test                                        Minimum Requirement<BRK/>
                                           (maximum where indicated)<BRK/>
----------------------------------------------------------------</THD><BRK/>
<BRK/>
Tensile Strength (<RID>ASTM D 2370</RID>)              700 psi<BRK/>
<BRK/>
Percent Elongation (<RID>ASTM D 2370</RID>)            5.0%<BRK/>
<BRK/>
Adhesion to Concrete (<RID>ASTM D 4541</RID>)          400 psi or <BRK/>
(see note 1)                                100 % failure in concrete<BRK/>
<BRK/>
Thermal Compatibility between Concrete      140<SPS>0</SPS> F<BRK/>
(<RID>ASTM C 884/C 884M</RID>)<BRK/>
<BRK/>
Heat Resistance, continuous exposure        "pass"<BRK/>
<BRK/>
Chemical Resistance to JP-8+100 Fuel        48 hours immersion:<BRK/>
@ 70<SPS>0</SPS> F (<RID>ASTM D 1308</RID>)(see note 2)           2.0% (max) weight increase<BRK/>
                                            2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor Oils           48 hours immersion:<BRK/>
@ 70<SPS>0</SPS> F (<RID>ASTM D 1308</RID>)(see note 2)           2.0% (max) weight increase<BRK/>
                                            2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols             48 hours immersion:<BRK/>
@ 70<SPS>0</SPS> F (<RID>ASTM D 1308</RID>)(see note 2)           2.0% (max) weight increase<BRK/>
                                            2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Lead (<RID>ASTM D 3335</RID>)                          0.06% (max)<BRK/>
<BRK/>
Cadmium (<RID>ASTM D 3335</RID>)                       0.06% (max)<BRK/>
<BRK/>
Chromium (<RID>ASTM D 3718</RID>)                      0.00%<BRK/>
 <BRK/>
NOTES:<BRK/>
(1)  When tested for adhesion, coating system shall display 400 psi adhesion and/or remove no less than 40 mils of 
concrete over 95 percent of each pull-off coupon throughout service.<BRK/>
<BRK/>
(2)  Immediately following immersion, in addition to the listed requirements, coating system shall be evaluated for 
blisters, checks, discoloration, softening, and lifting.  Coating system shall be visually free of blisters, checks, 
discoloration, and display both substrate and intercoat adhesion no less than 350 psi (<RID>ASTM D 4541</RID>).<BRK/></TBL>
</ENG><BRK/>
<MET><BRK/>
<PGE/><TBL><BRK/>
<THD><HL4>TABLE Ic</HL4><BRK/>
<BRK/>
Test                                       Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
--------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                 Epoxy (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)        85%<BRK/>
<BRK/>
Color                                      17925 (white)<BRK/>
                                           or 17875 (ultra-light gray)<BRK/>
<BRK/>
Hydrolytic Stability                       No effect: 30 days immersion in <BRK/>
(see note 1)                               Sodium Hydroxide solution with pH <BRK/>
                                           no less than 13.5<BRK/>
<BRK/>
Moisture Insensitivity Throughout          No effect: Insensitive to<BRK/>
Service (<RID>ASTM F 1869</RID>, <RID>ASTM D 4541</RID>)         moisture vapor emission at rates<BRK/>
(see note 2)                               no more than 197.0 micrograms <BRK/>
                                           moisture/second, square meter <BRK/>
<BRK/>
Adhesion to Concrete Throughout            2.75 MPa or <BRK/>
Service (<RID>ASTM D 4541</RID>)                      100% failure in concrete<BRK/>
(see note 3)<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immediately following immersion, primer shall be evaluated for blisters, checks, discoloration, softening, and 
substrate lifting.  Primer shall appear free of blisters, checks and moderate discoloration, and display wet adhesion 
no less than 2.4 MPa (<RID>ASTM D 4541</RID>).<BRK/>
<BRK/>
(2)  During and following application, primer shall remain unaffected by Moisture Vapor Emission (MVE) at rates no 
more than 197.0 micrograms moisture per second, square meter: primer shall meet the requirements of Note (3).  Signs 
of moisture sensitivity include blisters, softening, lifting, and discoloration (whitening).<BRK/>
<BRK/>
(3)  When tested for in-situ adhesion, primer shall display 2.75 MPa adhesion and/or remove no less than 1.0 mm of 
concrete over 95 percent off each pull-off coupon.<BRK/></TBL>
</MET><BRK/>
<ENG><BRK/>
<PGE/><TBL><BRK/>
<THD><HL4>TABLE Ic</HL4><BRK/>
<BRK/>
Test                                       Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
--------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                 Epoxy (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)        85%<BRK/>
<BRK/>
Color                                      17925 (white)<BRK/>
                                           or 17875 (ultra-light gray)<BRK/>
<BRK/>
Hydrolytic Stability                       No effect: 30 days immersion in <BRK/>
(see note 1)                               Sodium Hydroxide solution with pH <BRK/>
                                           no less than 13.5<BRK/>
<BRK/>
Moisture Insensitivity Throughout          No effect: Insensitive to<BRK/>
Service (<RID>ASTM F 1869</RID>, <RID>ASTM D 4541</RID>)         moisture vapor emission at rates<BRK/>
(see note 2)                               no more than 3.5 pounds  <BRK/>
                                           moisture/24 hrs, 1000 square feet<BRK/>
<BRK/>
Adhesion to Concrete Throughout            400 psi or <BRK/>
Service (<RID>ASTM D 4541</RID>)                      100% failure in concrete<BRK/>
(see note 3)<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immediately following immersion, primer shall be evaluated for blisters, checks, discoloration, softening, and 
substrate lifting.  Primer shall appear free of blisters, checks and moderate discoloration, and display wet adhesion 
no less than 350 psi (<RID>ASTM D 4541</RID>).<BRK/>
<BRK/>
(2)  During and following application, primer shall remain unaffected by Moisture Vapor Emission (MVE) at rates no 
more than 3.5 pounds moisture per 24 hours, 1000 square feet: primer shall meet the requirements of Note (3).  Signs 
of moisture sensitivity include blisters, softening, lifting, and discoloration (whitening).<BRK/>
<BRK/>
(3)  When tested for in-situ adhesion, primer shall display 400 psi adhesion and/or remove no less than 40 mils of 
concrete over 95 percent off each pull-off coupon.<BRK/></TBL>
</ENG><BRK/>
<BRK/>
<MET><BRK/>
<PGE/><TBL><BRK/>
<THD><HL4>TABLE Id </HL4><BRK/>
<BRK/>
Test                                      Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
-------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                 Aliphatic Urethane (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)        51%<BRK/>
<BRK/>
Topcoat Color (<RID>FED-STD-595</RID>)                17925 (white)<BRK/>
                                           or 17875 (ultra-light gray)<BRK/>
<BRK/>
Walkway Stripe Color: Red/Orange,          22197 (red/orange)<BRK/>
semi-gloss (<RID>FED-STD-595</RID>)<BRK/>
<BRK/>
Application Thickness per Coat             62.5 microns to 80 microns<BRK/>
                                           Dry Film Thickness(DFT)<BRK/>
<BRK/>
Hiding Power: Red/Orange                   Complete hiding of white coatings <BRK/>
                                           at 80 microns DFT(one coat)<BRK/>
<BRK/>
Sunlight Resistance                        Non-yellowing<BRK/>
 <BRK/>
Heat Resistance, continuous exposure       60<SPS>0</SPS> C  <BRK/>
<BRK/>
Heat Resistance, intermittent exposure     93.3<SPS>0</SPS> C <BRK/>
<BRK/>
Chemical Resistance to JP-8+100 Fuel       48 hours immersion:<BRK/>
@ 21<SPS>0</SPS> C (<RID>ASTM D 1308</RID>)(see note 1)          1.0% (max) weight increase<BRK/>
                                           1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor Oils          48 hour immersion:<BRK/>
@ 21<SPS>0</SPS> C (<RID>ASTM D 1308</RID>)(see note 1)          1.0% (max) weight increase<BRK/>
                                           1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols            48 hours immersion:<BRK/>
@ 21<SPS>0</SPS> C (<RID>ASTM D 1308</RID>)(see note 1)          1.0% (max) weight increase<BRK/>
                                           1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immediately following immersion, in addition to the listed requirements, urethane topcoat shall be evaluated 
for blisters, checks, discoloration, softening, and lifting.  Urethane topcoat shall be visually free of blisters, 
checks, and discoloration, and display adhesion no less than 2.4 MPa (<RID>ASTM D 4541</RID>).<BRK/></TBL>
</MET><BRK/>
<ENG><BRK/>
<PGE/><TBL><BRK/>
<THD><HL4>TABLE Id </HL4><BRK/>
<BRK/>
Test                                      Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
-------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                 Aliphatic Urethane (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)        51%<BRK/>
<BRK/>
Topcoat Color (<RID>FED-STD-595</RID>)                17925 (white)<BRK/>
                                           or 17875 (ultra-light gray)<BRK/>
<BRK/>
Walkway Stripe Color: Red/Orange,          22197 (red/orange)<BRK/>
semi-gloss (<RID>FED-STD-595</RID>)<BRK/>
<BRK/>
Application Thickness per Coat             2.5 mils to 3.2 Dry Film <BRK/>
                                           Thickness(DFT)<BRK/>
<BRK/>
Hiding Power: Red/Orange                   Complete hiding of white coatings <BRK/>
                                           at 3.2 mils mils DFT(one coat)<BRK/>
   <BRK/>
Sunlight Resistance                        Non-yellowing<BRK/>
 <BRK/>
Heat Resistance, continuous exposure       140<SPS>0</SPS> F<BRK/>
<BRK/>
Heat Resistance, intermittent exposure     200<SPS>0</SPS> F<BRK/>
<BRK/>
Chemical Resistance to JP-8+100 Fuel       48 hours immersion:<BRK/>
@ 70<SPS>0</SPS> F (<RID>ASTM D 1308</RID>)(see note 1)          1.0% (max) weight increase<BRK/>
                                           1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor Oils          48 hour immersion:<BRK/>
@ 70<SPS>0</SPS> F (<RID>ASTM D 1308</RID>)(see note 1)          1.0% (max) weight increase<BRK/>
                                           1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols            48 hours immersion:<BRK/>
@ 70<SPS>0</SPS> F (<RID>ASTM D 1308</RID>)(see note 1)          1.0% (max) weight increase<BRK/>
                                           1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immediately following immersion, in addition to the listed requirements, urethane topcoat shall be evaluated 
for blisters, checks, discoloration, softening, and lifting.  Urethane topcoat shall be visually free of blisters, 
checks, and discoloration, and display adhesion no less than 350 psi (<RID>ASTM D 4541</RID>).<BRK/></TBL>
</ENG><BRK/>
<BRK/>
<PGE/><TBL><BRK/>
<THD><HL4>TABLE II</HL4><BRK/>
<HL4>PREAPPROVED MATERIALS*</HL4><BRK/>
<BRK/>
Vendors                               Materials<BRK/>
------------------------------------------------------------------------------</THD><BRK/>
<BRK/>
Polyspec                        Primer:      300EX<BRK/>
(281) 397-0033                  Topcoat:     Tuffrez 235<BRK/>
                                Sealant:     T-2235SL<BRK/>
<BRK/>
Tennant                         Primer:      Eco-MPE (see note 1)<BRK/>
(800) 553-8033                  Topcoat:     VOC-CRU<BRK/>
                                Sealant:     N/A (see note 2)<BRK/>
<BRK/>
Stonhard                        Primer:      Standard Primer<BRK/>
(856) 779-7500                  Topcoat:     Stonseal GS6<BRK/>
                                Sealant:     Vulkem 245<BRK/>
<BRK/>
Crawford Labs                   Primer:      Florock 4700<BRK/>
(800) 356-7625                  Topcoat:     Florock Super CRU<BRK/>
                                Sealant:     N/A (see note 2)<BRK/>
<BRK/>
General Polymers                Primer:      #3578, Universal Primer<BRK/>
(800) 543-7694                  Topcoat:     #4618, Polyurethane Enamel<BRK/>
                                Sealant:     Cor-Seal PS<BRK/>
<BRK/>
NOTES:<BRK/>
(*)  Other products may meet specification requirements,  Up to specification's date of issue, preapproved materials 
met specification requirements.  It is the user's responsibility to confirm preapproved material formulations have 
not changed and specification requirements will be met.<BRK/>
<BRK/>
(1)  ECO-CRE primer is to be used on floors with heavy Skydrol use.<BRK/>
<BRK/>
(2)  Polyspec T-2235SL sealant may be used.<BRK/></TBL>
</SPT><BRK/>
<PGE/><NTE><BRK/>
<AST/><BRK/>
<NPR>APPENDIX A  INSTRUCTIONS FOR MODIFYING SECTION 01 45 02 NAVFAC <BRK/>
QUALITY CONTROL TO ADD NACE INSPECTOR.<BRK/>
<BRK/>
Modify Section 01 45 02 NAVFAC <BRK/>
QUALITY CONTROL to include NACE Coating Inspector as follows:<BRK/>
<BRK/>
1.  In the Article entitled "SUBMITTALS," add submittal requirement "SD-07 Certificates,"  
add "NACE Coating Inspector; G" and add the following paragraph below the addition 
of "NACE Coating Inspector; G."<BRK/>
<BRK/>
   Submit documentation confirming each coating inspector is classified no less 
than "Intermediate" Coating Inspector under the National Association of Corrosion 
Engineers (NACE) Coating Inspector Program (NACE CIP)and has successfully completed, 
as a minimum, "Session III" of NACE CIP.  Include NACE Coating Inspector identification 
number, date of qualification, expiration date, and copy of "Session III" certificate 
or copy of "NACE Certified" certificate.  The NACE Coating Inspector shall work 
directly for the prime construction contractor and work as part of the prime's 
Quality Control (QC) Organization.  Automatically disqualify any NACE Coating 
Inspector with prior and/or current business relations to job site subcontractors, 
material suppliers, and equipment suppliers.  Submit documentation confirming 
NACE Coating Inspectors have met the aforementioned requirements over the past 
two years.<BRK/>
<BRK/>
2.  Add the following to  the Article entitled "QC Specialists Duties and Qualification:"<BRK/>
under the heading "Qualification/Experience in Area of Responsibility, add "NACE 
Coating Inspector;" under the heading "Area of Responsibility," add "Surface 
preparation, flooring system installation, field tests, and field inspection;" 
and under the heading "Frequency" add "Full-time during surface preparation, 
flooring system installation, field tests, and field inspection."<BRK/>
<BRK/>
3.  Use NACE Coating Inspector on all flooring projects or, as a minimum, on 
flooring projects with greater than<MET> 278.7 square meters</MET><ENG> 3000 square feet</ENG>.</NPR> <BRK/>
<AST/><BRK/></NTE>
<BRK/></PRT>
    <END/><BRK/></SEC>