<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA      UFGS-09 67 23.16 (August 2008)<BRK/>
                                    -------------------------------<BRK/>
Preparing Activity:  <PRA>NAVFAC</PRA>         Superseding<BRK/>
                                    UFGS-09 62 50.12 (April 2006)  <BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 09 67 23.16</SCN><BRK/>
<BRK/>
<STL>FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM</STL><BRK/>
<DTE>08/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>a five-coat, epoxy 
mortar flooring system with reflective urethane topcoats, slip resistance, and 
joint work</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The epoxy mortar flooring system is appropriate for use in: aircraft 
maintenance hangars, equipment maintenance shops, jet engine test cells, and 
all other industrial floors where resistance to impact, abrasion, and fuel is 
required.  Installation costs: $5.00 - $10.00 per<MET> 0.1 square meters</MET><ENG> square foot</ENG>
.  Nominal thickness:<MET> 6.25 mm</MET><ENG> 1/4 inch</ENG>.  Benefits: Tolerates high Moisture Vapor 
Emission (MVE) rates, produces a level surface over coarse concrete, high impact 
resistance, good chemical resistance, and may provide a suitable topcoat base 
for more than 10 years service.  Can be rejuvenated by replacing urethane topcoats, 
and non-skid, only.  Approximate service life: Urethane topcoating with non-skid 
grit at three or more years.  The flooring system is neither conductive nor 
Electro-Static Dissipative (ESD), however, either formulation is easily designed 
upon request.  This specification is not for use in overcoating existing sound 
coating systems.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Prior to the flooring systems installation, a concrete condition assessment 
in accordance with the Naval Facilities Engineering Service Center's (NFESC) 
Users Guide (UG)-2036-SHR is highly recommended.  The condition assessment is 
designed to identify problem floors and eliminate premature flooring failures 
produced by: 1) Coating concrete with low surface strength, 2) coating concrete 
with high surface contamination levels (oils, fuels, fats, waxes, etc.), and 
3) coating concrete with a  high Moisture Vapor Emission (MVE) rate.  The thin 
film flooring system is suitable for application to: A) "Smooth" or "Coarse" 
concrete surface textures, B) concrete with a MVE rate no more than <MET>254 micrograms 
moisture per second, square meter </MET><ENG>4.5 pounds moisture per 24 hours, 1000 square 
feet </ENG>(ASTM F 1869), C) concrete with surface strength greater than <MET>1.34 MPa </MET><ENG>
200 psi </ENG>(ASTM D 4541), and D) concrete with fuel/oil contamination to a depth 
no more than<MET> 6.25 mm</MET><ENG> 1/4 inch</ENG>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: If a concrete floor has a Moisture Vapor Emission (MVE) rate more than <MET>
254 micrograms moisture per second, square meter </MET><ENG>4.5 pounds moisture per 24 
hours, 1000 square feet </ENG>(ASTM F 1869), apply a layered Moisture Reducing System 
(MRS) prior to the epoxy mortar flooring system application.  Use MRS compatible 
with the submitted flooring system and approved / warranted by the epoxy mortar 
flooring system manufacturer.  Apply the MRS to shot blasted concrete and reduce 
the MVE rate to less than<MET> 254 micrograms moisture per second, square meter</MET><ENG> 4.5 
pounds moisture per 24 hours, 1000 square feet</ENG>.  MRSs can employ combinations 
of concrete sealers, specific epoxies, and moisture insensitive grouts, with 
or without mesh.  MRSs are available from the following partial list of epoxy 
mortar flooring system vendors: Tennant (800) 553-8033, Stonhard (856) 779-7500, 
General Polymers (800) 543-7694, Crawford Labs (800) 356-7625, Floor Seal (800) 
295-0221.  Moisture Vapor Emission Test Kits (MVETK) are available from the 
following partial list of vendors: Crawford Labs (800) 356-7625, Floor Seal 
(800) 295-0221, Sinak (619)231-1771, General Polymers (800)534-7694. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include Section 03 01 30.71 CONCRETE REHABILITATION for minor spalls and 
surface deterioration repair to depths less than three inches.  Specify epoxy 
mortar for repairs to depths no more than<MET> 50 mm</MET><ENG> 2 inches</ENG>.  Specify epoxy concrete 
for repairs to depths from<MET> 25 to 75 mm</MET><ENG> 1 to 3 inches</ENG>.  Saw cut repairs to depths 
greater than <MET>25 mm </MET><ENG>1 inch </ENG>to a rectangular geometry.  Finish repairs to resemble 
surrounding concrete using a stainless steel trowel.  <BRK/>
<BRK/>
Include Section 32 01 19.61 RESEALING OF JOINTDS IN RIGID PAVEMENT for large 
spalls and severe deterioration repair to depths from<MET> 75 to 150 mm</MET><ENG> 3 to 6 inches</ENG>
.  Specify Portland Cement Concrete (PCC) with less than 0.45 water-cement ratio, 
light steel trowel finish, and cure using plastic coated burlap. Use rectangular 
geometry for repairs with saw cut edges to a nominal repair depth of<MET> 150 mm</MET><ENG> 
6 inches</ENG>.  Cure PCC repair for approximately 30 days prior to the application 
of the flooring system.  Do not cure repairs using liquid membrane-forming compounds.<BRK/>
<BRK/>
For repairs to spalls and severely distressed concrete to depths greater than<MET>
 150 mm</MET><ENG> 6 inches</ENG>, seek material guidance from Section 03300N CAST-IN-PLACE CONCRETE 
and procedural guidance from the American Concrete and Pavement Association 
(ACPA) Guideline TB-002.02P "Concrete Paving Technology - Guidelines for Full 
Depth Repair."  Fill repair base with a minimum of <MET>50 mm </MET><ENG>2 inches </ENG>of clean, 
non-reactive concrete sand over a suitable vapor retarder (<MET>0.25 mm </MET><ENG>10 mils </ENG>polyethylene 
sheeting).  Finish repairs by light steel trowel and cured using plastic coated 
burlap.  Cure repairs for approximately 30 days, or more, prior to the the flooring 
system application.  Do not cure repairs using liquid membrane-forming compounds.<BRK/>
 <BRK/>
Scarify level any curled and/or settled slab ends with joint surfaces displaying 
more than <MET>3.2 mm </MET><ENG>1/8 inch </ENG>difference in vertical height.  Resulting surfaces 
shall contain a height difference no more than <MET>1.5 mm </MET><ENG>1/16 inch </ENG>and a surface 
texture equal to ICRI-CSP 4.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include Section 03300N CAST-IN-PLACE CONCRETE for new concrete slab construction.  
Emply measures to control the base, subbase, and subgrade moisture Moisture 
Vapor Emission (MVE) rates to total no more than <MET>169.0 micrograms moisture per 
second, square meter </MET><ENG>3.0 pounds moisture per 24 hours, 1000 square feet </ENG>when 
measured on the slab's surface (ASTM F 1869).  Improper MVE controls have produced 
numerous premature coating failures.  In addition to appropriate subbase drainage, 
specify a minimum of <MET>50 mm </MET><ENG>2 inches </ENG>of clean, non-reactive concrete sand over 
no less than <MET>0.25 mm </MET><ENG>10 mils </ENG>of polyethylene sheeting (ASTM D 4397) with sealed 
lap joints.  Specify concrete mix to be free of accelerators containing calcium 
chloride and other sources of chloride ion contamination.  Specify two passes 
of a light power troweled finish and cure using plastic coated burlap or equal 
method.  Do not cure concrete using liquid membrane-forming compounds.  Do not 
specify surface hardeners or dry shake finish (Section 09 97 23).  Approximately 
60 days following the concrete pour and prior to the flooring system installation, 
test concrete for the MVE rate and confirm rate is no more than <MET>254 micrograms 
moisture per second, square meter </MET><ENG>4.5 pounds moisture per 24 hours, 1000 square 
feet </ENG>(ASTM F 1869).  Consult ACI 224.3R "Joints in Concrete Construction," ACI 
302.1R "Guide for Concrete Floor and Slab Construction," ACI 360R "Design of 
Slabs on Grade," and other appropriate construction guidance. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Where tile is to be removed prior to the flooring system application, 
test both tile and mastic for the presence of asbestos.  If asbestos is detected, 
include Section 02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS 
for removal and disposal. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: If flooring system is to be applied to warehouse floors with heavy forklift 
traffic, a semi-flexible joint sealant is required in lieu of the specified 
flexible sealant.  Use a semi-flexible epoxy sealant with approximately 90 percent 
elongation.  Do not use semi-flexible sealants in areas exposed to exterior 
temperatures. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Include Section 01 45 02 NAVFAC QUALITY CONTROL. </NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include Section 01 57 19.00 20 TEMPORARY ENVIRONMENTAL CONTROLS.  This 
section defines fugitive dust, generated waste, hazardous materials, hazardous 
substance, hazardous waste, solid waste, construction and demolition (CD) debris, 
and liquid waste, and contains documentation for dangerous waste profile, waste 
information sheet, waste identification document, waste generation record, landfill 
disposal form, and hazardous material reporting.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
 <BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
 <BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM C 307</RID><RTL>(2003; R 2008) Tensile Strength of Chemical-Resistant Mortar, Grouts, and Monolithic Surfacings</RTL><BRK/><BRK/><RID>ASTM C 531</RID><RTL>(2000; R 2005) Linear Shrinkage and Coefficient of Thermal Expansion of Chemical-Resistant Mortars, Grouts, and Monolithic Surfacings, and Polymer Concretes</RTL><BRK/><BRK/><RID>ASTM C 579</RID><RTL>(2001; R 2006) Compressive Strength of Chemical-Resistant Mortars, Grouts, Monolithic Surfacings, and Polymer Concretes</RTL><BRK/><BRK/><RID>ASTM C 679</RID><RTL>(2003) Tack-Free Time of Elastomeric Sealants</RTL><BRK/><BRK/><RID>ASTM C 884/C 884M</RID><RTL>(1998; R 2005) Thermal Compatibility between Concrete and Epoxy-Resin Overlay</RTL><BRK/><BRK/><RID>ASTM D 1308</RID><RTL>(2002; R 2007) Effect of Household Chemicals on Clear and Pigmented Organic Finishes</RTL><BRK/><BRK/><RID>ASTM D 2240</RID><RTL>(2005) Standard Test Method for Rubber Property - Durometer Hardness</RTL><BRK/><BRK/><RID>ASTM D 2621</RID><RTL>(1987; R 2005) Infrared Identification of Vehicle Solids from Solvent-Reducible Paints</RTL><BRK/><BRK/><RID>ASTM D 2697</RID><RTL>(2003; R 2008) Volume Nonvolatile Matter in Clear or Pigmented Coatings</RTL><BRK/><BRK/><RID>ASTM D 3335</RID><RTL>(1985a; R 2005) Low Concentrations of Lead, Cadmium, and Cobalt in Paint by Atomic Absorption Spectroscopy</RTL><BRK/><BRK/><RID>ASTM D 3718</RID><RTL>(1985a; R 2005) Low Concentrations of Chromium in Paint by Atomic Absorption Spectroscopy</RTL><BRK/><BRK/><RID>ASTM D 3925</RID><RTL>(2002) Sampling Liquid Paints and Related Pigmented Coatings</RTL><BRK/><BRK/><RID>ASTM D 412</RID><RTL>(2006ae1e2) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension</RTL><BRK/><BRK/><RID>ASTM D 4541</RID><RTL>(2002) Pull-Off Strength of Coatings Using Portable Adhesion Testers</RTL><BRK/><BRK/><RID>ASTM D 6237</RID><RTL>(2003) Painting Inspectors (Concrete and Masonry Substrates)</RTL><BRK/><BRK/><RID>ASTM D 638</RID><RTL>(2008) Standard Test Method for Tensile Properties of Plastics</RTL><BRK/><BRK/><RID>ASTM E 11</RID><RTL>(2004) Wire Cloth and Sieves for Testing Purposes</RTL><BRK/><BRK/><RID>ASTM F 1869</RID><RTL>(2004) Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride</RTL><BRK/><BRK/></REF><REF><ORG>INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI)</ORG><BRK/><BRK/><RID>ICRI 03732</RID><RTL>(1997) Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays</RTL><BRK/><BRK/></REF><REF><ORG>THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)</ORG><BRK/><BRK/><RID>SSPC-TU 2</RID><RTL>(1997) Design, Installation, and Maintenance of Coating Systems for Concrete Used in Secondary Containment</RTL><BRK/><BRK/></REF><REF><ORG>U.S. GENERAL SERVICES ADMINISTRATION (GSA)</ORG><BRK/><BRK/><RID>FED-STD-595</RID><RTL>(Rev B; Am 1) Colors Used in Government Procurement</RTL><BRK/><BRK/></REF><REF><ORG>U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)</ORG><BRK/><BRK/><RID>29 CFR 1910.1000</RID><RTL>Air Contaminants</RTL><BRK/><BRK/><RID>29 CFR 1910.134</RID><RTL>Respiratory Protection</RTL><BRK/><BRK/><RID>29 CFR 1926.59</RID><RTL>Hazard Communication</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  Submit the following 
in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-04 Samples</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Joint Sealant</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
 <ITM><SUB>Epoxy Mortar Flooring System</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>White Aluminum Oxide Non-Skid Grit</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Joint Sealant</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Epoxy Mortar Flooring System</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Primer</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Grout Coat</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Urethane Topcoat</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>White Aluminum Oxide Non-Skid Grit</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Patch Test Demonstration</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Daily Inspection Report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Adhesion Testing</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Work Plan</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Flooring System Applicator Qualifications</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Joint Sealant</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Epoxy Mortar Flooring System</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Warranty</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-08 Manufacturer's Instructions</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Joint Sealant</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Epoxy Mortar Flooring System</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Water-Based Alkaline Degreaser</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-11 Closeout Submittals</SUB></LST><BRK/>
<BRK/>
  <ITM><SUB>Inspection Logbook</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   QUALITY ASSURANCE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Test Reports</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1.1   <SUB>Joint Sealant</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test results that confirm sealant complies with Table Ia requirements.  Samples must have been tested 
within the last three years.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.2   <SUB>Epoxy Mortar Flooring System</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test results that confirm the epoxy mortar flooring system complies with Table Ib requirements.  Samples 
must have been tested within the last three years.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.3   <SUB>Primer</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test results that confirm the primer complies with Table Ic requirements.  Samples must have been tested 
within the last three years.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.4   <SUB>Grout Coat</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test results that confirm grout coat complies with Table Id requirements.  Samples must have been tested 
within the last three years.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.5   <SUB>Urethane Topcoat</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit test results that confirm urethane topcoat complies with Table Ie requirements.  Samples must have been 
tested within the last three years.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.1.6   <SUB>Daily Inspection Report</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit one copy of the daily inspection report to the Contracting Officer within 24 hours of the date recorded.</TXT><BRK/></SPT>
<BRK/></SPT>
<SPT><TTL>1.3.2   Certificates</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.2.1   <SUB>Work Plan</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit schedule to complete work within approximately twelve (12) consecutive calendar days.  Submit a written 
plan describing in detail all phases of coating operations.  Address work sequencing, surface preparation, flooring 
system application, recoat and cure time projections, as well as how each step will be controlled, tested, and 
evaluated.  Address safety measures, work scheduling around weather, and record keeping.  Assign one supervisor 
to the job who is to remain on site throughout all phases of work and who is to act as the contractor's primary 
point of contact.  Identify this person in the submitted schedule.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.2   <SUB>Flooring System Applicator Qualifications</SUB></TTL><BRK/>
<BRK/>
<TXT>Minimum requirements for the installation contractor are as follows:  Completed three or more jobs within the 
past two years applying the specified materials to concrete surfaces in which the total area exceeds <MET>18 587 square 
meters</MET> <ENG>200,000 square feet</ENG>.  Submit documentation listing location of work, point of contact at job site, total 
square footage of applied materials, listing of both materials and equipment used, and validation from coating 
manufacturer documenting quality of materials purchased per job for work totalling <MET>18 587 square meters</MET> <ENG>200,000 
square feet</ENG> within the past two years.  In addition to the above requirements, installation contractor shall 
be certified by the material manufacturer(s) to install the submitted coatings and sealant.  Submit copy of certificates.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.3   <SUB>Joint Sealant</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit literature documenting the sealant's past performance in automotive and/or aircraft maintenance shops.  
Minimum requirements are two or more maintenance shops with joint work totaling<MET> 3048 linear meters</MET><ENG> 10,000 linear 
feet</ENG> whereby the sealant has performed for two years with less than one percent combined sealant failures and 
defects.  Include from sealant manufacturer a list of shop locations, total linear feet of sealant applied per 
shop, shop point of contact, date sealant was applied, and the name of the installed sealant material.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.4   <SUB>Epoxy Mortar Flooring System</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit literature documenting the coating system's past performance in aircraft maintenance shops and over floors 
with high Moisture Vapor Emission (MVE) rates.  Minimum requirements are two or more aircraft maintenance shops 
totaling<MET> 3160 square meters</MET><ENG> 34,000 square feet</ENG> where the coating system has performed for two years with less 
than 0.05 percent combined premature coating failures, material defects and surface discoloration; no more than 
0.03 percent discoloration from aviation chemicals, tire plasticizers, and UV exposure.  Provide a minimum of 
two additional case histories where successful installation occurred on floor slabs with no less than<MET> 254 micrograms 
moisture per second, square meter</MET><ENG> 4.5 pounds moisture per 24 hours, 1000 square feet</ENG>.  Include from flooring 
manufacturer a list of shop locations, total coated area per shop, shop point of contact, date coating system 
was applied, successful installation to concrete with high MVE, and the names of the installed coating materials.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2.5   <SUB>Warranty</SUB></TTL><BRK/>
<BRK/>
<TXT>Warrantee materials and workmanship for a minimum of one year following completion of flooring and sealant application.  
The following terms and conditions form a part of the warranty:  If the applied coating system develops blisters 
(chemical), checks, softening, or lifting within one year following application, rework each area by installation 
contractor at contractor's expense.  The following conditions are excluded from the warranty: A) Concrete cracking, 
flooring system mirrors cracks in concrete, B) cosmetic imperfections due to scratching and gouging, C) application 
to metallic concrete finishes (Section <SRF>09 97 23</SRF>), and D) application to concrete with a MVE rate greater than<MET>
 282 micrograms moisture per second, square meter</MET><ENG> 5.0 pounds moisture per 24 hours, 1000 square feet</ENG>.  If the 
coating system's adhesion is in question, perform one adhesion test per<MET> 9.3 square meters</MET><ENG> 100 square feet</ENG> as 
described in the Article entitled "ADHESION TESTING."  To satisfy the warranty, adhesion testing shall produce 
cohesive failures within the concrete, concrete removal over 95 percent of each pull-off coupon, and/or adhesion 
no less than<MET> 2.8 MPa</MET><ENG> 400 psi</ENG>.  Each area failing to meet adhesion requirements shall require two additional adhesion 
tests to confirm results.  Within the warranty period, remove to sound material and rework all areas unable to 
meet adhesion requirements.  Zero percent sealant failures within one year is required.  Within the warranty 
period, remove and rework all sealant material with chemically attacked surfaces and/or lifting from joint walls.  
Topcoat cracking over sealant is excluded from warranty.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.3.3   Manufacturer's Instructions</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.3.1   Joint Sealant</TTL><BRK/>
<BRK/>
<TXT>Submit manufacturer's printed instructions to include detailed application procedures, minimum and maximum application 
temperatures, and curing procedures.  In accordance with <RID>29 CFR 1926.59</RID>, include Material Safety Data Sheets 
(MSDS) for the sealant to be used at the job site.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.3.2   <SUB>Epoxy Mortar Flooring System</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit manufacturer's printed instructions to include detailed mixing, minimum and maximum application temperatures, 
acceptable atmospheric and/or interior climatic conditions, application procedures, curing procedures, and procedures 
for flooring system maintenance cleaning.  Provide explicit instructions detailing surface preparation, recoat 
windows and remedial actions in case recoat windows are missed, and, if applicable, solvent-wiping between coats 
with acceptable types and grades of solvents.  In accordance with <RID>29 CFR 1926.59</RID>, include MSDSs for the coatings 
to be used at the job site.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.3.3   <SUB>Water-Based Alkaline Degreaser</SUB></TTL><BRK/>
<BRK/>
<TXT>Submit manufacturer's printed instructions to include detailed mixing, dilution rate, application procedures, 
and rinsing procedures.  In accordance with <RID>29 CFR 1926.59</RID>, include MSDSs for the water-based alkaline degreaser 
to be used at the job site.</TXT><BRK/></SPT>
</SPT><BRK/></SPT>
<SPT><TTL>1.4   DELIVERY, STORAGE, AND HANDLING</TTL><BRK/>
<BRK/>
<TXT>Store coatings and sealant in spaces with temperatures from<MET> 5 - 24 degrees C</MET><BRK/>
<ENG>40 - 75 degrees F</ENG>.  Inspect materials on site for damage prior to use.  Return to manufacturer any packaged materials 
in dented, rusty, or leaking containers.  Return to manufacturer materials with an expired shelf life for testing, 
and if compliant, reissuing of shelf life extension.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5   COATING HAZARDS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include either Section 01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS 
or prepare instructions detailing each safety element for use with this section.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Ensure that employees are trained in all safety plan aspects. Follow the coating manufacturer's written safety 
precautions throughout mixing, application, and curing of coatings.  Comply with respiratory protection requirements 
in <RID>29 CFR 1910.134</RID> and safe levels of airborne contaminants in <RID>29 CFR 1910.1000</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6   JOB SITE REFERENCES</TTL><BRK/>
<BRK/>
<TXT>Make available to the Contracting Officer at least one copy each of <RID>ASTM D 4541</RID>, <RID>ASTM D 6237</RID>, <RID>SSPC-TU 2</RID>, and <RID>
ICRI 03732</RID>, including replica standards ICRI-CSP 1 through ICRI-CSP 9, at the job site.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7   <SUB>PATCH TEST DEMONSTRATION</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This is a very important part of the submittal process.  While it is 
unusual to require a test patch prior to the submitted materials' approval, 
this flooring system is unusual in that it is required to perform significant 
tasks for a long time.  Proof of contractor claims, especially under conditions 
to be encountered in the specific project, is considered necessary.<BRK/>
<BRK/>
If customer dislikes non-skid grit level, adjustments to the specification can 
be made.  Grit coarser than #60 aluminum oxide is not recommended.  On architectural 
floors, non-skid grit broadcast rates can range from none to approximately half 
the specified level.  To confirm grit broadcast is acceptable, walk on cured 
patch test under both dry and wet conditions.  Water can be used to simulate 
the wet condition.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Prior to the submitted flooring system's approval, apply the complete flooring system to a <MET>3 meter by 3 meter </MET><ENG>
10 foot by 10 foot </ENG>square concrete section as prepared in accordance with Part 3 "EXECUTION."  Within this area, 
perform three adhesion tests using procedures as detailed in the Article entitled "ADHESION TESTING."  If adhesion 
testing produces cohesive failures within the concrete, no less than <MET>1 mm </MET><ENG>40 mils </ENG>concrete removed over 95 percent 
of each pull-off coupon, and/or adhesion more than <MET>2.75 MPa, </MET><ENG>400 psi, </ENG>patch test adhesion is acceptable. If concrete 
surface preparation was insufficient, apply an additional coating system patch to properly prepared concrete 
followed by the above adhesion testing.  If adhesion results are unacceptable for both the topcoat and the coatings 
below the grout coat, submit a new coating system manufactured by a different coating vendor.  Apply new coating 
system to a patch and subject this patch to the above requirements for adhesion prior to approval.  If customer 
dislikes non-skid grit application, adjustments to the specifications can be made.  Grit coarser than #60 aluminum 
oxide is not recommended.  Immediately following "passing" adhesion results, remove urethane topcoats and grout 
coat by sanding, repair patch test holes using epoxy mortar, and place a "Key-In Termination" adjacent patch 
test perimeter.  Coarse scarification and/or pneumatic scabbling can be required to remove patch tests failing 
to meet adhesion requirements.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The specified materials are not appropriate for use in primary chemical 
containment, secondary chemical containment, or on floors subjected to spills 
from concentrated acids, bases, and organic solvents.  Consult with the Naval 
Facilities Engineering Service Center's (NFESC) Paints and Coatings Center of 
Expertise for alternative coating systems to suit specific Navy needs.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: Tables Ia, Ib, Ic, Id, Ie, and II, are presented at the end of Part 3 
"EXECUTION." </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.1   JOINT SEALANT</TTL><BRK/>
<BRK/>
<TXT>Formulate the joint sealant to exhibit the properties as listed in Table Ia.<BRK/></TXT>
<BRK/>
<BRK/></SPT>
<SPT><TTL>2.2   EPOXY MORTAR FLOORING SYSTEM</TTL><BRK/>
<BRK/>
<TXT>A five-coat flooring system consisting of primer, epoxy mortar, grout coat, and two urethane topcoats.  Apply 
the system at a nominal thickness of <MET>6.25 mm </MET><ENG>1/4 inch </ENG>and contain an aluminum oxide non-skid grit broadcast.  
Formulate the complete flooring system to exhibit the properties listed in Table Ib.  Additional requirements 
for primer coat, grout coat, and urethane top coat are contained in the following sub-paragraphs.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Primer Coat</TTL><BRK/>
<BRK/>
<TXT>In addition to the epoxy mortar flooring system requirements, formulate the primer coat to exhibit the properties 
as listed in Table Ic.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2   Grout Coat</TTL><BRK/>
<BRK/>
<TXT>In addition to the epoxy mortar flooring system requirements, formulate the grout coat to exhibit the properties 
as listed in Table Id.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3   Urethane Topcoat</TTL><BRK/>
<BRK/>
<TXT>In addition to the epoxy mortar flooring system requirements, formulate the urethane topcoat to exhibit the properties 
as listed in Table Ie.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3   <SUB>WHITE ALUMINUM OXIDE NON-SKID GRIT</SUB></TTL><BRK/>
<BRK/>
<TXT>Size #60, dust-free (washed and dry), minimum 99 percent pure, having the following sieve analysis when tested 
using a <MET>1000 gram </MET><ENG>2.2 pound </ENG>sample<BRK/>
(<RID>ASTM E 11</RID>):<BRK/>
<BRK/>
   Sieve No. 40      100% passing<BRK/>
   Sieve No. 50      15-30% retained<BRK/>
   Sieve No. 60      70-85% retained<BRK/>
   Sieve No. 70      0 -15% retained</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4   PREAPPROVED MATERIALS</TTL><BRK/>
<BRK/>
<TXT>Table II is a list of vendors with "preapproved materials."</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   COATING SAMPLE COLLECTION</TTL><BRK/>
<BRK/>
<TXT>The Contracting Officer and QC Manager shall witness all material sampling. Notify the Contracting Officer a 
minimum of three days in advance of sampling.  Obtain liquid samples of each component (eg., primer, intermediate, 
grout coat, topcoat) by random selection from sealed containers and in accordance with <RID>ASTM D 3925</RID>.  Samples 
may be either individual cans of liquid material or <MET>1.0 liter </MET><ENG>1.0 quart </ENG>quantities of properly mixed, extracted, 
and sealed liquid material.  Label samples by designated name, specification number, batch number, project contract 
number, sample date, intended use, and quantity involved.  When the applied epoxy mortar system has met the requirements 
defined in the Article entitled "ADHESION TESTING," return coating samples to the installation contractor for 
proper disposal.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>3.2   TILE AND TILE ADHESIVE REMOVAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete "Tile and Tile Adhesive Removal" if concrete is not tiled.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Remove tile 100 percent, employing one or more of the following techniques: chipping, scraping, sanding, scarification, 
high-pressure water, and various hand tools.  Remove tile adhesive 100 percent, using solvents and power scrubbing.  
Remove residual contamination using hot potable water under a minimum of<MET> 27.6 MPa</MET><ENG> 4,000 psi</ENG>.  Resulting surfaces 
shall appear clean and display the gray color of concrete.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.3   JOINT MATERIAL REMOVAL, RE-SAW CUTTING, CRACK CHASING</TTL><BRK/>
<BRK/>
<TXT>Remove existing material 100 percent in all joints including material bonded to joint walls and base.  Rigid 
material may require saw cutting equipment to remove.  Joints may be widened up to <MET>3.2 mm </MET><ENG>1/8 inch </ENG>when re-saw 
cutting.  Chase concrete cracks identified for repair and open to a minimum depth of <MET>12.5 mm </MET><ENG>1/2 inch </ENG>below crack 
surface, resulting in crack(s) with smooth vertical walls.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4   DEGREASING</TTL><BRK/>
<BRK/>
<TXT>On both previously coated and uncoated concrete, degrease entire floor by scrubbing using a hot potable water 
solution,<MET> 49 to 77 degrees C</MET><ENG> 120 to 170 degrees F</ENG>, and a concentrated water-based alkaline degreaser.  Perform 
two complete degreasing cycles on the entire floor surface.  Allow solution to soak into surfaces prior to scrubbing 
and remove using hot potable water under a minimum of<MET> 27.6 MPa</MET><ENG> 4,000 psi</ENG>.  Rinsing shall be complete when the 
rinse water appears clear.  If the industrial detergent is not biodegradable, collect all rinse water and dispose 
of as hazardous waste.  Squeegees and shop vacuums may be used to collect pooling rinse water.  Fans may be used 
to aid drying of floor surfaces.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>3.5   COATING SYSTEM REMOVAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete "Coating System Removal" if concrete is uncoated.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Remove existing coating system 100 percent employing one or more of the following techniques: shot blasting, 
chipping, scraping, sanding, scarification, high pressure water blasting, and various hand tools.  Impact tools 
such as scabblers may be used to remove unsound epoxy mortar flooring systems.  In general, a coating system 
cannot be completely removed by shot blasting and, to attain 100 percent coating removal, requires a combination 
of the above techniques.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.6   SURFACE PREPARATION</TTL><BRK/>
<BRK/>
<TXT>Shot blast entire floor to produce a level of coarseness equal to <RID>ICRI 03732</RID> CSP 3. Overlap each shot blasting 
pass by<MET> 6.25 to 12.5 mm</MET><ENG> 1/4 to 1/2 inch</ENG>.  Add new shot to shot blasting equipment prior to blasting.  Prepare 
concrete surfaces inaccessible to shot blasting, perimeter wall bases and under secured equipment, using a diamond 
disk grinding and/or light scarification to produce a level of coarseness equal to <RID>ICRI 03732</RID>CSP 2, <RID>ICRI 03732</RID>
 CSP 4, respectively.  Resulting surfaces shall appear clean and contain the appropriate surface coarseness level.  
If the resulting cleanliness level cannot be determined, place numerous drops of water on surfaces that appear 
contaminated.  If the water drops soak into concrete, the surfaces are hydrocarbon contamination free (oils, 
grease, skydrol).  If the water drops bead up and do not flatten out, surfaces require additional degreasing 
as detailed in the Article entitled "DEGREASING."  Shot blasting coarse concrete and/or broom finished concrete 
can produce a coarseness level equal to <RID>ICRI 03732</RID> CSP 5: employ a best effort attempt to minimize excessive 
removal of coarse concrete material.  If coarse concrete is encountered, shot blasting to a level of coarseness 
equal to <RID>ICRI 03732</RID> CSP 5 is acceptable: however, extremely coarse concrete can require resurfacing prior to 
the flooring system's installation.  Sweep, vacuum, and run a high powered magnet over all surfaces to be coated, 
including joints.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.6.1   CMU Surface Preparation</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph if epoxy mortar is not to be applied to the CMU wall 
bases.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>A minimum remove 100 percent of coatings <MET>100 mm </MET><ENG>4 inches </ENG>up the base of CMU walls adjacent the flooring space, 
and prepare surface by power grinding to a resulting level of coarseness equal to <RID>ICRI 03732</RID> CSP 2.  If oils/grease 
are present, degrease in accordance with the Article entitled "DEGREASING."</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.7   COVE STRIP INSTALLATION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph if epoxy mortar is not to be applied to the CMU wall 
bases.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Install a continuous cove strip at a nominal height of <MET>100 mm </MET><ENG>4 inches </ENG>up each CMU perimeter wall base.  Install 
a solvent resistant cove strip using a solvent resistant adhesive.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8   KEY-IN TERMINATIONS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If the epoxy mortar flooring system is to be applied up the CMU wall 
bases, a Key-In termination is not required adjacent these walls.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Place the "Key-In" termination as detailed in <RID>SSPC-TU 2</RID> Figure 8 at transition surfaces, directly below doorways, 
and adjacent walls, floor drains, drain grates (interior side), and all other obstructions embedded into the 
floor slab.  The Key-In termination shall contain one vertical wall at a depth from <MET>9.4 to 15.6 mm </MET><ENG>3/8 to 5/8 
inch </ENG>and, leading down to the resulting vertical depth, a sloped surface from<MET> 37.5 to 50 mm</MET><ENG> 1-1/2 to 2 inches</ENG>
.  A hand held concrete saw can be used to cut the correct vertical depth followed by power tool grinding to 
create a sloped surface.  Remove concrete dust by vacuuming.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9   CRACK REPAIRS</TTL><BRK/>
<BRK/>
<TXT>Use the "Elastomeric Underlayer Crack-Bridging Design" as detailed in <RID>SSPC-TU 2</RID> Figure 7 over the surface of 
epoxy mortar filled cracks.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.9.1   Install Bondbreaker</TTL><BRK/>
<BRK/>
<TXT>Install bondbreaker, either solvent resistant bondbreaker tape or a <MET>3.2 to 6.25 mm </MET><ENG>1/8 to 1/4 inch </ENG>#20-#40 mesh 
silica sand layer, to the base of previously chased cracks identified for repair.  For cracks without a rigid 
base, install suitably sized fiberboard to a depth of <MET>12.5 mm </MET><ENG>1/2 inch </ENG>below floor level and with bondbreaker 
over exposed fiberboard.  Install bondbreaker to cover the crack's horizontal base and continuously span the 
entire crack length.  Bondbreaker application prevents epoxy mortar from penetrating deep into cracks.  Use bondbreaker 
tape no more than <MET>150 microns </MET><ENG>6 mils </ENG>thick.  In this application, the use of backer rod is prohibited.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.2   Repair Cracks</TTL><BRK/>
<BRK/>
<TXT>Using the specified materials, prime interior crack walls and apply epoxy mortar directly into wet primer.  Finish 
epoxy mortar level with floor and without feathered edges.  When cured, remove mortar imperfections by sanding 
flush with adjacent concrete.  Apply solvent resistant tape parallel to each side of the mortar filled crack(s) 
at a minimum inner width of <MET>100 mm </MET><ENG>4 inches </ENG>between tape.  A <MET>100 mm </MET><ENG>4 inch </ENG>inner tape width is generally suitable 
for cracks less than <MET>12.5 mm </MET><ENG>1/2 inch </ENG>wide whereas cracks more than <MET>12.5 mm </MET><ENG>1/2 inch </ENG>wide can require an inner 
tape width of<BRK/>
<MET>150 mm</MET><ENG>6 inches</ENG>.  Apply <MET>1 mm </MET><ENG>1/24 inch </ENG>of the specified sealant, in one coat, directly over filled crack(s) and 
spread flush with inner tape edges: a stiff bristled paintbrush can be used to spread the sealant.  Use a Wet 
Film Thickness (WTF) gage to confirm sealant application is between <MET>875 to 1125 microns </MET><ENG>35 to 40 mils </ENG>wet.  Remove 
tape and allow sealant to cure a minimum of 24 hours prior to the epoxy mortar flooring system application.  
Sealant application above <MET>1250 microns </MET><ENG>50 mils </ENG>dry will require removal and reapplication.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.10   PRE-APPLICATION TESTING FOR CONTAMINATION</TTL><BRK/>
<BRK/>
<TXT>Spot check surfaces for oil/grease contamination using the water break test.  At a rate of 5 tests per<MET> 95 square 
meters</MET><ENG> 1000 square feet</ENG> place one to two water drops onto surfaces and observe for beading.  Test all other surfaces 
that show visible signs of potential contamination.  Perform additional degreasing to surfaces displaying water 
beading in accordance with the Article entitled "DEGREASING."</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  At this point in the installation sequence, minor spalls and surface 
deterioration to depths less than <MET>75 mm </MET><ENG>3 inches </ENG>can be repaired.  Use epoxy 
mortar for repairs to depths no more than <MET>50 mm. </MET><ENG>2 inches. </ENG> Use epoxy concrete 
for repairs to depths from <MET>25 to 75 mm. </MET><ENG>1 to 3 inches. </ENG> Contain repairs to depths 
greater than <MET>25 mm </MET><ENG>1 inch </ENG>in a rectangular geometry with saw cut edges.  Finish 
repairs to resemble surrounding concrete using a stainless steel trowel.  Include 
Section 03 01 30.71 CONCRETE REHABILITATION if concrete repairs if this nature 
are required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/></SPT>
<SPT><TTL>3.11   COATING APPLICATION</TTL><BRK/>
<BRK/>
<TXT>Prior to the flooring system application, vacuum flooring space and mark all joints.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.11.1   Isolation (Expansion) and Construction Joint Treatment</TTL><BRK/>
<BRK/>
<TXT>Install into each isolation (expansion) and construction joint, a continuous length of round polyethylene backer 
rod flush with the floor's surface and under 30 percent compression.  Backer rod placement prevents epoxy mortar 
from penetrating into isolation and construction joints.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.2   Contraction Joint Treatment</TTL><BRK/>
<BRK/>
<TXT>Apply primer and epoxy mortar directly into all contraction joints.  This quantity is in addition to the specified <MET>
6.25 mm </MET><ENG>1/4 inch </ENG>epoxy mortar thickness.  This step may be performed either prior to, or during, the full epoxy 
mortar application.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.3   Primer Application</TTL><BRK/>
<BRK/>
<TXT>Apply primer to flooring space at a minimum of <MET>250 microns </MET><ENG>10.0 mils </ENG>wet.  Do not prime previously installed 
patch test.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.4   Epoxy Mortar Application</TTL><BRK/>
<BRK/>
<TXT>Apply epoxy mortar at <MET>6.25 mm </MET><ENG>1/4 inch </ENG>directly into wet primer using a screed box or equal equipment.  Finish 
open areas using a power trowel with stainless steel blades.  Perimeter edges and adjacent equipment footings 
may require  finishing by stainless steel hand trowel.  Directly above areas with Key-In terminations and at 
a distance from <MET>25 to 37.5 mm </MET><ENG>1 to 1-1/2 inches </ENG>away from the mortar's outer edge, slope the mortar down and 
flush with the concrete's surface.  Terminate the resulting angle flush with the each Key-In termination vertical 
cut.  Apply epoxy mortar flush with previously installed patch test.  Do not apply epoxy mortar onto patch test 
surface.  When sufficiently cured, sand entire mortar surface.  Resulting surface shall appear level, contain 
uniform thickness, and be free of surface imperfections including trowel marks.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.5   Primer Application to CMU Walls</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph if epoxy mortar is not to be applied to CMU wall bases.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>When the epoxy mortar has sufficiently cured, prime approximately <MET>100 mm </MET><ENG>4 inches </ENG>up base of CMU walls to cove 
strip and <MET>50 mm </MET><ENG>2 inches </ENG>adjacent the wall's base using the specified primer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.6   Epoxy Mortar Application to CMU Walls</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete paragraph if epoxy mortar is not to be applied to CMU wall bases.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Apply epoxy mortar directly into wet primer at<MET> 4.5 mm to 6.25 mm</MET><ENG> 3/16 to 1/4 inch</ENG>.  Use a cove trowel to create 
a rounded transition between floor surfaces and perimeter wall bases.  When sufficiently cured, sand the base 
and <MET>100 mm </MET><ENG>4 inches </ENG>up perimeter walls.  Resulting finish shall contain a rounded transition of uniform thickness 
between flooring surfaces and CMU walls.  When sufficiently cured, sand mortar surfaces.  Resulting surface shall 
be free of surface imperfections including trowel marks.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.7   Grout Coat Application</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Selecta grout coat color identical to the selected topcoat color, either 
white or ultra-light gray.  Ultra-light gray is preferred to white.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Sweep and vacuum up residual dust from epoxy mortar sanding.  Apply grout coat to epoxy mortar at a minimum of <MET>
250 microns </MET><ENG>10 mils </ENG>wet. Apply grout coat to previously install patch test.  If applicable, up CMU wall bases.  
If the cured grout coat feels oily/greasy, an amine blush has occurred which requires removal.  Consult the coating 
manufacturer to recommend an appropriate blush removal procedure.  Epoxy amines can blush during cool temperatures 
with high humidity.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.8   Grout Coat Sanding</TTL><BRK/>
<BRK/>
<TXT>Sand grout coat using 100 grit or finer sandpaper to a dull appearance with visible scratches.  Resulting surface 
shall appear 100 percent absent of gloss with zero shiny spots.  Lightly sand perimeter edges and around equipment 
footings.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.9   Saw Cutting and Sealing Joints</TTL><BRK/>
<BRK/>
<TXT>Use the "Conventional Sealed Joint" as detailed in Figure 1 of <RID>SSPC-TU 2</RID> to seal each contraction and expansion 
joint.  Take care to reduce contamination from saw cutting equipment and foot traffic.  Limit floor access to 
essential contractor personnel.  When performing joint work, including saw cutting, suggest placing clean rolled 
cardboard adjacent joint surfaces to reduce coating system contamination.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.11.9.1   Saw Cut Contraction Joints</TTL><BRK/>
<BRK/>
<TXT>Place saw cuts directly in the middle of each contraction joint <MET>6.25 mm </MET><ENG>1/4 inch </ENG>wide, placed to a minimum depth 
of <MET>31.2 mm</MET> <ENG>1-1/4 inches</ENG>, and span the joint's entire length.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.9.2   Saw Cut Isolation (Expansion) and Construction Joints</TTL><BRK/>
<BRK/>
<TXT>Place saw cuts to the isolation (expansion) and construction joint's original width and to a minimum depth of<MET>
 31.2 mm</MET><ENG> 1-1/4 inches</ENG>.  Completely remove the epoxy mortar across the joint's width and further remove the previously 
installed backer rod.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.9.3   Install Backer Rod</TTL><BRK/>
<BRK/>
<TXT>Install a continuous length of round, closed-cell polyethylene backer rod into each saw cut.  For <MET>12.5, 9.4 and 
6.25 mm </MET><ENG>1/2, 3/8 and 1/4 inch </ENG>wide saw cuts, place backer rod to a depth of <MET>9.4 mm </MET><ENG>3/8 inch </ENG>below the grout coat's 
surface the highest point on the backer rod.  For expansion joint saw cuts greater than or equal to <MET>18.8 mm </MET><ENG>3/4 
inch </ENG>wide, place backer rod to a depth of <MET>15.6 mm </MET><ENG>5/8 inch </ENG>below the grout coat's surface.  Fit backer rod tight 
between joint walls under 30 percent compression and place using a backer rod tool.  Remove and reinstall all 
backer rod that is the incorrect size or at the incorrect depth.  Following backer rod installation, apply painter's 
tape to surfaces adjacent joints to protect from sealant.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.9.4   Joint Sealant Application</TTL><BRK/>
<BRK/>
<TXT>Apply sealant directly into joints using a bulk-caulking gun.  At room temperature, the resulting sealant application 
shall exhibit a concave recess between <MET>3.2 to 1.0 mm </MET><ENG>1/8 to 1/24 inch </ENG>below the grout coat's surface.  Remove 
and reapply cured sealant remaining either flush or greater.  Following sealant application, remove painter's 
tape and sealant drips on grout coat.  Prior to topcoating, cure sealant a minimum of 24 hours.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.11.10   Application of Topcoats</TTL><BRK/>
<BRK/>
<TXT>Apply two coats of urethane topcoat.  Broadcast #60, white, aluminum oxide non-skid grit into the second urethane 
topcoat.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.11.10.1   Non-Skid Grit Broadcast</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
NOTE:  Aircraft hangars servicing light aircraft with weight less than <MET>18 140 kg </MET><ENG>40,000 pounds </ENG>may require a 
higher non-skid grit loading.  The additional grit will assist in towing aircraft under wet conditions; however, 
the additional grit will decrease coating aesthetics.  Up to <MET>450 grams </MET><ENG>1.0 pounds </ENG>per <MET>9.3 square meters </MET><ENG>100 
square feet </ENG>of additional non-skid grit can be required.<BRK/>
<BRK/>
On either warehouse or architectural floors, considerably less non-skid grit may be appropriate.  Broadcast 
rates can range from none to less than <MET>450 grams </MET><ENG>1.0 pound </ENG>per<MET> 93 square meters</MET><ENG> 1000 square feet</ENG>.<BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Broadcast non-skid grit at a rate of <MET>680 grams </MET><ENG>1.0 pound </ENG>per <MET>9.3 square meters </MET><ENG>100 square feet </ENG>into the second 
urethane topcoat and backroll.  Map floor into <MET>55.8 square meters </MET><ENG>600 square foot </ENG>sections where <MET>4080 grams </MET><ENG>9.0 
pounds </ENG>of non-skid grit is pre-weighed, placed into clean buckets and used in its entirety per marked <MET>55.8 square 
meter </MET><ENG>600 square foot </ENG>section.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.10.2   Grout Coat Cleaning</TTL><BRK/>
<BRK/>
<TXT>Inspect floor for shiny grease spots and, if detected, spot degrease using manufacturer approved solvent(s) with 
clean, lint-free rags.  Sweep and vacuum up all residual dirt and dust.  Solvent wipe all surfaces using solvent(s) 
and procedures as recommended by manufacturer of epoxy mortar flooring system.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.10.3   First Topcoat</TTL><BRK/>
<BRK/>
<TXT>Apply a full coat of urethane topcoat at a spreading rate from <MET>62.5 to 80 microns </MET><ENG>2.5 to 3.2 mils </ENG>Dry Film Thickness 
(DFT).  Stripe  coat perimeter edges and around equipment footings.  Monitor and record a minimum of one Wet 
Film Thickness (WFT) reading per <MET>55.8 square meters </MET><ENG>600 square foot </ENG>section of floor surface.  Sealant is to 
be lightly coated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.10.4   Second topcoat</TTL><BRK/>
<BRK/>
<TXT>Apply a second coat of urethane topcoat at a spreading rate from <MET>62.5 to 80 microns </MET><ENG>2.5 to 3.2 mils </ENG>DFT.  Stripe  
coat perimeter edges and around equipment footings.  Monitor and record a minimum of one WFT reading per <MET>55.8 
square meters </MET><ENG>600 square foot </ENG>section of floor surface prior to broadcasting non-skid grit.  When the correct 
WFT has been applied per <MET>55.8 square meters </MET><ENG>600 square feet </ENG>of area, immediately and evenly broadcast non-skid 
grit into the second urethane topcoat and backroll in two directions.  Test the adhesion of the epoxy mortar 
flooring system in accordance with the Article entitled "ADHESION TESTING."</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.11.10.5   Walkway Stripes</TTL><BRK/>
<BRK/>
<TXT>Place the walkway stripe and grounding rod marker, if applicable, according to Government drawings.  When the 
second topcoat is within its recoat window, apply a walkway stripe of the red/orange urethane topcoat at <MET>75 microns </MET><ENG>
3.0 mils </ENG>DFT.  Lightly broadcast non-skid grit into the wet walkway stripe.  Use solvent resistant tape to protect 
the floor coating against stripe coat bleed.  A thin clear coat of either epoxy or urethane may be required to 
prevent stripe coat bleed prior to the full application of the colored stripe coat.  Completely hide the topcoat 
color with the red/orange stripe, in one coat.  If insufficient hiding occurs, apply one additional walkway stripe 
coat.  Apply grounding rod markings using similar procedures, urethane topcoat, and colors and size according 
to Government drawings.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.12   CURING</TTL><BRK/>
<BRK/>
<TXT>Installed materials shall cure and display performance equal to manufacturer's product literature.  Remove and 
reapply improperly cured material.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.13   FIELD TESTS AND INSPECTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.13.1   Coating Inspector</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Insert directly into Section 01 45 02 NAVFAC <BRK/>
QUALITY CONTROL requirement for NACE Coating Inspector.  See Appendix A for 
instructions on modifying Section 01 45 02 NAVFAC <BRK/>
QUALITY CONTROL.  The NACE Coating Inspector will act as QC Specialist.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Consider the Coating Inspector a QC Specialist, working for the QC Manager, and be qualified in accordance with 
Section <SRF>01 45 02</SRF> NAVFAC <BRK/>
QUALITY CONTROL.  The Coating Inspector will be present during all field tests, surface preparation, flooring 
application, initial cure of the flooring system, and during all flooring repair work.  The Coating Inspector 
will provide all tools/equipment necessary to perform field tests and inspection.  The Coating Inspector will 
be responsible for field tests and specified level of inspection.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.13.2   Inspection</TTL><BRK/>
<BRK/>
<TXT>Document weather conditions, job site occurrences, and report conditions and occurrences potentially detrimental 
to the flooring system.  The listed inspection requirements are in addition to the QC inspection and reporting 
requirements defined in Section <SRF>01 45 02</SRF>NAVFAC QUALITY CONTROL CONTROL.  The Coating Prepare a project reference 
sheet outlining all requirements, tests, test methods, and evaluation criteria, and hold regular meetings with 
contractor personnel, including shot blasting operators and applicators, to review requirements/evaluation criteria 
for upcoming work prior to execution.  At the start of coating operations and every 1.0 hour following until 
daily work is complete, record air temperature, substrate temperature, and relative humidity.  Following each 
coat application, inspect surfaces for improperly cured material, blisters, inadequate and/or excessive coating 
thickness, and other defects. Document each inspection, test, non-compliant area, and location of each non-compliant 
area.  List evaluation method, evaluation criteria, areas requiring rework, and all other pertinent observations.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.13.2.1   Daily Inspection Report</TTL><BRK/>
<BRK/>
<TXT>Submit to the Contracting Officer one copy of the daily inspection report completed each day when performing 
work under this Section.  Use Appendix X1 "Inspection Checklist" of <RID>ASTM D 6237</RID> to monitor daily activity and 
to assist in preparing the daily inspection report.  Note each non-compliant issue and each issue identified 
for rework in accordance with the QC documentation procedures in Section <SRF>01 45 02</SRF> NAVFAC QUALITY CONTROL.  <BRK/>
Use of forms containing entry blocks for all required data is encouraged.  Present the data in a legible and 
professional format.  Submit report within 24 hours of the report date.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.13.2.2   <SUB>Inspection Logbook</SUB></TTL><BRK/>
<BRK/>
<TXT>Record all daily activity related to this Section in the Inspection Logbook.  Record the daily inspection reports, 
as well as all other pertinent observations and information, in the logbook.  Use a hard or spiral bound book 
with consecutively numbered pages.  Prior to final payment, submit original Inspection Logbook to the Contracting 
Officer upon completion of project.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.13.2.3   Inspection Equipment</TTL><BRK/>
<BRK/>
<TXT>Use equipment in good condition, operational within its design range, and calibrated as required by the specified 
standard for each device.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.13.3   <SUB>Adhesion Testing</SUB></TTL><BRK/>
<BRK/>
<TXT>Perform a minimum of three modified adhesion tests (<RID>ASTM D 4541</RID>) on the topcoat no less than forty-eight hours 
following application.  Select three random flooring locations spaced a minimum of <MET>6 meters</MET> <ENG>20 feet</ENG> between each 
location.  Vertically core completely through the epoxy mortar flooring system and a minimum of <MET>9.4 mm </MET><ENG>3/8 inch </ENG>
into concrete using a suitable drill fitted with a <MET>25 mm </MET><ENG>1 inch </ENG>diameter core bit.  Throughout coring, a employ 
a best effort attempt to avoid fracturing and/or overheating both the mortar system and concrete: improper coring 
can affect adhesion results.  Adhere directly to each cored surface's center a <MET>18.75 mm </MET><ENG>3/4 inch </ENG>diameter pull-off 
coupon.  Lightly sand test area flooring surface prior to attaching pull-off coupons containing a grit-blasted 
anchor profile.  When pull-off coupon adhesive has sufficiently cured, test adhesion and evaluate results.  If 
testing produces cohesive failures within the concrete, no less than <MET>1 mm </MET><ENG>40 mils </ENG>concrete removal over 95 percent 
of each pull-off coupon, and/or adhesion more than <MET>2.75 MPa </MET><ENG>400 psi </ENG>mortar system's adhesion is acceptable.  
If the above requirements are not satisfied, then perform one adhesion test per <MET>9.3 square meters </MET><ENG>100 square 
feet </ENG>using the above procedures.  Two additional tests will confirm results for each non-compliant area.  Remove 
and rework all areas unable to meet adhesion requirements to sound material.  Fill core holes using primer, sand-filled 
epoxy mortar, grout coat, and urethane topcoats.  Finish resulting repairs flush with adjacent coatings, displaying 
an equivalent appearance.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.14   Final Cleanup</TTL><BRK/>
<BRK/>
<TXT>Following work completion, remove debris, equipment, and materials from site.  Remove temporary connections to 
Government or contractor furnished water and electrical services.  Restore existing facilities in and around 
the work areas to their original condition.</TXT><BRK/>
<BRK/>
<MET><BRK/>
<PGE/><BRK/>
<TXT><HL4>TABLE I</HL4><BRK/>
<HL4>MATERIAL REQUIREMENTS</HL4></TXT><BRK/>
<BRK/>
<TXT>Table Ia - Sealant</TXT><BRK/>
<BRK/>
<TBL><BRK/>
<THD>Test                                 Minimum Requirement<BRK/>
                                    (maximum where indicated)<BRK/>
<BRK/>
---------------------------------------------------------------</THD><BRK/>
<BRK/>
Sealant System                      Polysulfide (Manganese Cure; MnO2)<BRK/>
(two-pack: self-leveling)           or Urethane<BRK/>
<BRK/>
Percent Volume Solids               100 %<BRK/>
<BRK/>
Chemical Resistance to JP-8+100     48 hours immersion:)<BRK/>
Fuel @ 21<SPS>0</SPS>C                         2.0% (max) weight increase, <BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase, <BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor        48 hours immersion:<BRK/>
Oils @ 21<SPS>0</SPS>C                         2.0% (max) weight increase<BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase<BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols     48 hours immersion:<BRK/>
@ 21<SPS>0</SPS>C                              2.0% (max) weight increase<BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase<BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Hardness (<RID>ASTM D 2240</RID>: Shore A)     20<BRK/>
<BRK/>
Tensile Strength (<RID>ASTM D 412</RID>)       1.0 MPa <BRK/>
(or <RID>ASTM D 638</RID>)<BRK/>
<BRK/>
Percent Elongation (<RID>ASTM D 412</RID>)     500%<BRK/>
(or <RID>ASTM D 638</RID>)<BRK/>
<BRK/>
Tack Free @ 18.3<SPS>0</SPS>C                  12 hours maximum<BRK/>
(<RID>ASTM C 679</RID>)<BRK/>
<BRK/>
Adhesion to Sand Filled Epoxy       0.96 MPa <BRK/>
Polyamine<BRK/>
<BRK/>
Adhesion to Urethane Topcoats       0.96 MPa <BRK/>
(paintable sealant)<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immerse and test a minimum of three - 50 by 12.5 by 12.5 mm section of cured sealant.</TBL></MET><BRK/>
<ENG><BRK/>
<PGE/><TXT><HL4>TABLE I</HL4><BRK/>
<HL4>MATERIAL REQUIREMENTS</HL4></TXT><BRK/>
<BRK/>
<TXT>Table Ia - Sealant</TXT><BRK/>
<BRK/>
<TBL><BRK/>
<THD>Test                                 Minimum Requirement<BRK/>
                                    (maximum where indicated)<BRK/>
<BRK/>
---------------------------------------------------------------</THD><BRK/>
<BRK/>
Sealant System                      Polysulfide (Manganese Cure; MnO2)<BRK/>
(two-pack: self-leveling)           or Urethane<BRK/>
<BRK/>
Percent Volume Solids               100 %<BRK/>
<BRK/>
Chemical Resistance to JP-8+100     48 hours immersion:)<BRK/>
Fuel @ 70<SPS>0</SPS>F                         2.0% (max) weight increase, <BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase, <BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor        48 hours immersion:<BRK/>
Oils @ 70<SPS>0</SPS>    F                     2.0% (max) weight increase<BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase<BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols     48 hours immersion:<BRK/>
@ 70<SPS>0</SPS>F                              2.0% (max) weight increase<BRK/>
(<RID>ASTM D 1308</RID>) (see note 1)          5.0% (max) volume increase<BRK/>
                                    2.0% (max) weight loss<BRK/>
<BRK/>
Hardness (<RID>ASTM D 2240</RID>: Shore A)     20<BRK/>
<BRK/>
Tensile Strength (<RID>ASTM D 412</RID>)       150 psi<BRK/>
(or <RID>ASTM D 638</RID>)<BRK/>
<BRK/>
Percent Elongation (<RID>ASTM D 412</RID>)     500%<BRK/>
(or <RID>ASTM D 638</RID>)<BRK/>
<BRK/>
Tack Free @ 65<SPS>0</SPS>F                    12 hours maximum<BRK/>
(<RID>ASTM C 679</RID>)<BRK/>
<BRK/>
Adhesion to Sand Filled Epoxy       140 psi<BRK/>
Polyamine<BRK/>
<BRK/>
Adhesion to Urethane Topcoats       140 psi<BRK/>
(paintable sealant)<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immerse and test a minimum three -2 by 1/2 by 1/2 inch section of cured sealant.</TBL></ENG><BRK/>
<BRK/>
<MET><BRK/>
<PGE/><BRK/>
<TXT>Table Ib - Epoxy Mortar Flooring System</TXT><BRK/>
<TBL><BRK/>
<THD>Test                                         Minimum Requirement<BRK/>
                                            (maximum where indicated)<BRK/>
----------------------------------------------------------------</THD><BRK/>
<BRK/>
Compression Strength )<RID>ASTM C 579</RID>)           51.7 MPa <BRK/>
<BRK/>
Tensile Strength (<RID>ASTM C 307</RID>)               9.0 MPa <BRK/>
<BRK/>
Adhesion to Concrete (<RID>ASTM D 4541</RID>)          2.75 MPa or <BRK/>
(see note 1)                                100 % failure in concrete<BRK/>
<BRK/>
Heat Resistance, continuous exposure        60<SPS>0</SPS>C <BRK/>
<BRK/>
Heat Resistance, intermittent exposure      93.3<SPS>0</SPS>C <BRK/>
<BRK/>
Coefficient of Thermal Expansion            9.0 - 59.4 x 10<SPS>-6</SPS>mm/mm<SPS>0</SPS>C<BRK/>
-17.7 - 99<SPS>0</SPS>C (<RID>ASTM C 531</RID>)           <BRK/>
<BRK/>
Thermal Compatibility between Concrete      "pass"<BRK/>
(<RID>ASTM C 884/C 884M</RID>)<BRK/>
<BRK/>
Chemical Resistance to JP-8+100 Fuel        48 hours immersion:<BRK/>
@21<SPS>0</SPS>C (<RID>ASTM D 1308</RID>)                         2.0% (max) weight increase<BRK/>
(see note 2)                                2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor Oils           49 hours immersion:<BRK/>
@21<SPS>0</SPS>C (<RID>ASTM D 1308</RID>)                         2.0% (max) weight increase<BRK/>
(see note 2)                                2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols             48 hours immersion:<BRK/>
@21<SPS>0</SPS>C (<RID>ASTM D 1308</RID>)                         2.0% (max) weight increase<BRK/>
(see note 2)                                2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Lead (<RID>ASTM D 3335</RID>)                          0.06% (max)<BRK/>
<BRK/>
Cadmium (<RID>ASTM D 3335</RID>)                       0.06% (max)<BRK/>
<BRK/>
Chromium (<RID>ASTM D 3718</RID>)                      0.00%<BRK/>
<BRK/>
NOTES:<BRK/>
<BRK/>
(1)  When tested for adhesion, mortar system shall display 2.75 MPa adhesion and/or remove no less than 1.0 mm of 
concrete over 95% of each pull-off coupon throughout service.<BRK/>
<BRK/>
(2)  Immediately following immersion, in addition to the listed requirements, mortar system shall be evaluated for 
blisters, checks, discoloration, softening, and lifting.  Mortar system shall be visually free of blisters, checks, 
and discoloration, and display both substrate and intercoat adhesion no less than 2.4 MPa (<RID>ASTM D 4541</RID>).</TBL></MET><BRK/>
<BRK/>
<ENG><TXT>Table Ib - Epoxy Mortar Flooring System</TXT><BRK/>
<TBL><BRK/>
<THD>Test                                         Minimum Requirement<BRK/>
                                            (maximum where indicated)<BRK/>
----------------------------------------------------------------</THD><BRK/>
<BRK/>
Compression Strength )<RID>ASTM C 579</RID>)           7,500 psi<BRK/>
<BRK/>
Tensile Strength (<RID>ASTM C 307</RID>)               1,300 psi<BRK/>
<BRK/>
Adhesion to Concrete (<RID>ASTM D 4541</RID>)          400 psi or <BRK/>
(see note 1)                                100 % failure in concrete<BRK/>
<BRK/>
Heat Resistance, continuous exposure        140<SPS>0</SPS>F<BRK/>
<BRK/>
Heat Resistance, intermittent exposure      200<SPS>0</SPS>F<BRK/>
<BRK/>
Coefficient of Thermal Expansion            5.0 - 33.0 x 10<SPS>-6</SPS>in/in <SPS>0 </SPS>F<BRK/>
0 - 210<SPS>0</SPS>F (<RID>ASTM C 531</RID>)           <BRK/>
<BRK/>
Thermal Compatibility between Concrete      "pass"<BRK/>
(<RID>ASTM C 884/C 884M</RID>)<BRK/>
<BRK/>
Chemical Resistance to JP-8+100 Fuel        48 hours immersion:<BRK/>
@ 70<SPS>0</SPS>F(<RID>ASTM D 1308</RID>)                         2.0% (max) weight increase<BRK/>
(see note 2)                                2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor Oils           49 hours immersion:<BRK/>
@ 70<SPS>0</SPS>F(<RID>ASTM D 1308</RID>)                         2.0% (max) weight increase<BRK/>
(see note 2)                                2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols             48 hours immersion:<BRK/>
@ 70<SPS>0</SPS>F(<RID>ASTM D 1308</RID>)                         2.0% (max) weight increase<BRK/>
(see note 2)                                2.0% (max) volume increase<BRK/>
                                            2.0% (max) weight loss<BRK/>
<BRK/>
Lead (<RID>ASTM D 3335</RID>)                          0.06% (max)<BRK/>
<BRK/>
Cadmium (<RID>ASTM D 3335</RID>)                       0.06% (max)<BRK/>
<BRK/>
Chromium (<RID>ASTM D 3718</RID>)                      0.00%<BRK/>
<BRK/>
NOTES:<BRK/>
<BRK/>
(1)  When tested for adhesion, mortar system shall display 400 psi adhesion and/or remove no less than 40 mils of 
concrete over 95% of each pull-off coupon throughout service.<BRK/>
<BRK/>
(2)  Immediately following immersion, in addition to the listed requirements, mortar system shall be evaluated for 
blisters, checks, discoloration, softening, and lifting.  Mortar system shall be visually free of blisters, checks, 
and discoloration, and display both substrate and intercoat adhesion no less than 350 psi (<RID>ASTM D 4541</RID>).</TBL><BRK/></ENG>
<BRK/>
<BRK/>
<MET><TXT>Table Ic - Primer </TXT><BRK/>
<TBL><BRK/>
<THD>Test                                       Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
--------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                 Epoxy Polyamine (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)        100%<BRK/>
<BRK/>
Color                                      Clear to Amber<BRK/>
<BRK/>
Hydrolytic Stability                       No effect: 30 days immersion in <BRK/>
(see note 1)                               Sodium Hydroxide solution with pH <BRK/>
                                           no less than 13.5<BRK/>
<BRK/>
Moisture Insensitivity Throughout          No effect: Insensitive to<BRK/>
Service (<RID>ASTM F 1869</RID>, <RID>ASTM D 4541</RID>)         moisture vapor emission at rates<BRK/>
(see note 2)                               no more than 254 micrograms <BRK/>
                                           moisture per second, square meter <BRK/>
                                           <BRK/>
Adhesion to Concrete Throughout            2.75 MPa or <BRK/>
Service (<RID>ASTM D 4541</RID>)                      100% failure in concrete<BRK/>
(see note 3)<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immediately following immersion, evaluate primer for blisters, checks, discoloration, softening, and substrate 
lifting.  Primer shall be visually free of blisters, checks and moderate discoloration, and display wet adhesion 
no less than 2.4 MPa (<RID>ASTM D 4541</RID>).<BRK/>
<BRK/>
(2)  During and following application, primer shall remain unaffected by Moisture Vapor Emmsion (MVE) at rates no 
more than 254 micrograms moisture per second, square meter: primer shall meet the requirements of note 3.  Signs 
of moisture sensitivity include blisters, softening, lifting, and discoloration (whitening).<BRK/>
<BRK/>
(3)  When tested for in-situ adhesion, primer shall display 400 psi adhesion and/or remove no less than 1.0 mm of 
concrete over 95% off each pull-off coupon.<BRK/></TBL>
</MET><BRK/>
<BRK/>
<ENG><BRK/>
<PGE/><TXT>Table Ic - Primer </TXT><BRK/>
<TBL><BRK/>
<THD>Test                                       Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
--------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                 Epoxy Polyamine (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)        100%<BRK/>
 <BRK/>
Color                                      Clear to Amber<BRK/>
<BRK/>
Hydrolytic Stability                       No effect: 30 days immersion in <BRK/>
(see note 1)                               Sodium Hydroxide solution with pH <BRK/>
                                           no less than 13.5<BRK/>
<BRK/>
Moisture Insensitivity Throughout          No effect: Insensitive to<BRK/>
Service (<RID>ASTM F 1869</RID>, <RID>ASTM D 4541</RID>)         moisture vapor emission at rates<BRK/>
(see note 2)                               no more than 4.5 pounds<BRK/>
                                           moisture/24 hours, 1000<BRK/>
                                           square feet<BRK/>
<BRK/>
Adhesion to Concrete Throughout            400 psi or <BRK/>
Service (<RID>ASTM D 4541</RID>)                      100% failure in concrete<BRK/>
(see note 3)<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immediately following immersion, evaluate primer for blisters, checks, discoloration, softening, and substrate 
lifting.  Primer shall be visually free of blisters, checks and moderate discoloration, and display wet adhesion 
no less than 350 psi (<RID>ASTM D 4541</RID>).<BRK/>
<BRK/>
(2)  During and following application, primer shall remain unaffected by Moisture Vapor Emmsion (MVE) at rates no 
more than 4.5 pounds moisture per 24 hours, 1000 square feet: primer shall meet the requirements of note 3.  Signs 
of moisture sensitivity include blisters, softening, lifting, and discoloration (whitening).<BRK/>
<BRK/>
(3)  When tested for in-situ adhesion, primer shall display 400 psi adhesion and/or remove no less than 40 mils of 
concrete over 95% off each pull-off coupon.<BRK/></TBL>
</ENG><BRK/>
<PGE/><BRK/>
<BRK/>
<MET><TXT>Table Id - Grout Coat</TXT><TBL><BRK/>
<BRK/>
<THD>Test                                      Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
<BRK/>
-------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                Epoxy Polyamine (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)       100%<BRK/>
<BRK/>
Color                                     17925 (white),<BRK/>
                                          or 17875 (ultra-light gray)<BRK/>
<BRK/>
Hardness (<RID>ASTM D 2240</RID>: Shore D)           80<BRK/>
<BRK/>
Adhesion to Epoxy Mortar (<RID>ASTM D 4541</RID>)    2.75 MPa <BRK/></TBL>
<BRK/>
<BRK/>
<BRK/></MET>
<BRK/>
<BRK/>
<ENG><TXT>Table Id - Grout Coat</TXT><TBL><BRK/>
<BRK/>
<THD>Test                                      Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
<BRK/>
-------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                Epoxy Polyamine (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)       100%<BRK/>
<BRK/>
Color                                     17925 (white),<BRK/>
                                          or 17875 (ultra-light gray)<BRK/>
<BRK/>
Hardness (<RID>ASTM D 2240</RID>: Shore D)           80<BRK/>
<BRK/>
Adhesion to Epoxy Mortar (<RID>ASTM D 4541</RID>)    400 psi<BRK/></TBL>
</ENG><BRK/>
<BRK/>
<MET><BRK/>
<PGE/><BRK/>
<TXT>Table Ie - Urethane Topcoat</TXT><BRK/>
<TBL><BRK/>
<THD>Test                                       Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
<BRK/>
-------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                 Aliphatic Urethane (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)        51%<BRK/>
<BRK/>
Topcoat Color (<RID>FED-STD-595</RID>)                17925 (white)<BRK/>
                                           or 17875 (ultra-light gray)<BRK/>
<BRK/>
Walkway Strip Color: Red/Orange,           22197 (red/orange)<BRK/>
semi-gloss (<RID>FED-STD-595</RID>)<BRK/>
<BRK/>
Application Thickness per Coat             62.5 - 80 microns <BRK/>
                                           Dry Film Thickness(DFT)<BRK/>
<BRK/>
Hiding Power: Red/Orange                   Complete hiding of white coatings<BRK/>
                                           at 80 microns DFT<BRK/>
                                           (one coat)<BRK/>
<BRK/>
Sunlight Resistance                        Non-yellowing<BRK/>
<BRK/>
Heat Resistance, continuous exposure       60<SPS>0</SPS>C <BRK/>
<BRK/>
Heat Resistance, intermittent exposure     93.3<SPS>0</SPS>C <BRK/>
<BRK/>
Chemical Resistance to JP-8+100 Fuel       48 hours immersion:<BRK/>
@21<SPS>0</SPS>C (<RID>ASTM D 1308</RID>)                        1.0% (max) weight increase<BRK/>
(see note 1)                               1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor Oils          48 hour immersion:<BRK/>
@21<SPS>0</SPS>C (<RID>ASTM D 1308</RID>)                        1.0% (max) weight increase<BRK/>
(see note 1)                               1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols            48 hours immersion:<BRK/>
@21<SPS>0</SPS>C (<RID>ASTM D 1308</RID>)                        1.0% (max) weight increase<BRK/>
(see note 1)                               1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immediately following immersion, in addition to the listed requirements, evaluate urethane topcoat for blisters, 
checks, discoloration, softening, and lifting.  Urethane topcoat shall be visually free of blisters, checks, and 
discoloration, and display adhesion no less than 2.4 MPa (<RID>ASTM D 4541</RID>).<BRK/></TBL>
</MET><BRK/>
<BRK/>
<ENG><BRK/>
<PGE/><TXT>Table Ie - Urethane Topcoat</TXT><BRK/>
<BRK/>
<TBL><BRK/>
<THD>Test                                       Minimum Requirement<BRK/>
                                          (maximum where indicated)<BRK/>
<BRK/>
-------------------------------------------------------------------</THD><BRK/>
<BRK/>
Resin System (<RID>ASTM D 2621</RID>)                 Aliphatic Urethane (two-pack)<BRK/>
<BRK/>
Percent Volume Solids (<RID>ASTM D 2697</RID>)        51%<BRK/>
<BRK/>
Topcoat Color (<RID>FED-STD-595</RID>)                17925 (white)<BRK/>
                                           or 17875 (ultra-light gray)<BRK/>
<BRK/>
Walkway Strip Color: Red/Orange,           22197 (red/orange)<BRK/>
semi-gloss (<RID>FED-STD-595</RID>)<BRK/>
<BRK/>
Application Thickness per Coat             2.5 - 3.5 mils<BRK/>
                                           Dry Film Thickness(DFT)<BRK/>
<BRK/>
Hiding Power: Red/Orange                   Complete hiding of white coatings<BRK/>
                                           at 3.2 mils DFT<BRK/>
                                           (one coat)<BRK/>
<BRK/>
Sunlight Resistance                        Non-yellowing<BRK/>
<BRK/>
Heat Resistance, continuous exposure       140<SPS>0</SPS>F<BRK/>
<BRK/>
Heat Resistance, intermittent exposure     200<SPS>0</SPS>F<BRK/>
<BRK/>
Chemical Resistance to JP-8+100 Fuel       48 hours immersion:<BRK/>
@ 70<SPS>0</SPS>F (<RID>ASTM D 1308</RID>)                       1.0% (max) weight increase<BRK/>
(see note 1)                               1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Motor Oils          48 hour immersion:<BRK/>
@ 70<SPS>0</SPS>F (<RID>ASTM D 1308</RID>)                       1.0% (max) weight increase<BRK/>
(see note 1)                               1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
Chemical Resistance to Skydrols            48 hours immersion:<BRK/>
@ 70<SPS>0</SPS>F (<RID>ASTM D 1308</RID>)                       1.0% (max) weight increase<BRK/>
(see note 1)                               1.0% (max) volume increase<BRK/>
                                           1.0% (max) weight loss<BRK/>
<BRK/>
NOTES:<BRK/>
(1)  Immediately following immersion, in addition to the listed requirements, evaluate urethane topcoat for blisters, 
checks, discoloration, softening, and lifting.  Urethane topcoat shall be visually free of blisters, checks, and 
discoloration, and display adhesion no less than 350 psi <BRK/>
(<RID>ASTM D 4541</RID>).<BRK/></TBL>
</ENG><BRK/>
<PGE/><BRK/>
<BRK/>
<TXT><HL4>TABLE II</HL4><BRK/>
<HL4>PREAPPOROVED MATERIALS*</HL4></TXT><BRK/>
<BRK/>
<TBL><BRK/>
<THD>Vendors                               Materials<BRK/>
------------------------------------------------------------------------------</THD><BRK/>
<BRK/>
Stonhard                        Primer:         Standard Primer<BRK/>
(856) 779-7500                  Epoxy Mortar:   Stonclad GS<BRK/>
                                Grout Coat:     Stonkote GS4<BRK/>
                                Topcoat:        Stonseal GS6<BRK/>
                                Sealant:        Vulkem 245<BRK/>
<BRK/>
Polyspec                        Primer:         300EX<BRK/>
(281) 397-0033                  Epoxy Mortar:   Tuffrez 200<BRK/>
                                Grout Coat:     Tuffrez 203<BRK/>
                                Topcoat:        Tuffrez 235<BRK/>
                                Sealant:        T-2235SL<BRK/>
<BRK/>
Tennant                         Primer:         Eco-MPE )<BRK/>
(800) 553-8033                  Mortar Coat:    Eco-PT 250<BRK/>
                                Grout Coat:     Eco-PT<BRK/>
                                Topcoat:        VOC-CRU<BRK/>
                                Sealant:        N/A **<BRK/>
<BRK/>
<BRK/>
Crawford Labs                   Primer:         Florock 4700<BRK/>
(800) 356-7625                  Epoxy Mortar:   Florock 4700<BRK/>
                                Grout Coat:     Florock 4700<BRK/>
                                Topcoat:        Florock Super CRU<BRK/>
                                Sealant:        N/A **<BRK/>
<BRK/>
General Polymers                Primer:         #3578, Universal Primer<BRK/>
(800) 543-7694                  Epoxy Coat:     #3562, Mortar Binder Resin<BRK/>
                                Grout Coat:     #3744GP, Novo-Flo<BRK/>
                                Topcoat:        #4618, Polyurethane Enamel<BRK/>
                                Sealant:        Cor-Seal PS<BRK/>
<BRK/>
NOTES:<BRK/>
* Other products may meet specification requirements.  Up to specification's date of issue, preapproved materials 
met specification requirements.  It is the users' responsibility to confirm preapproved material formulations have 
not changed and specification requirements will be met.  **Polyspec T-2235SL sealant may be used.<BRK/></TBL>
</SPT><BRK/>
<PGE/><NTE><BRK/>
<AST/><BRK/>
<NPR>        APPENDIX A<BRK/>
<BRK/>
INSTRUCTIONS FOR MODIFYING SECTION 01 45 02 NAVFAC <BRK/>
QUALITY CONTROL to add NACE INSPECTOR.<BRK/>
<BRK/>
Modify Section 01 45 02 NAVFAC <BRK/>
QUALITY CONTROL to include NACE Coating Inspector as follows:<BRK/>
<BRK/>
1.  In the Article entitled "Submittals," add submittal requirement "SD-07 Certificates,"  
add "NACE Coating Inspector; G" and add the following paragraph below the addition 
of "NACE Coating Inspector; G."<BRK/>
<BRK/>
Submit documentation confirming each coating inspector is classified no less 
than "Intermediate" Coating Inspector under the National Association of Corrosion 
Engineers (NACE) Coating Inspector Program (NACE CIP).  Include successfully 
completed, as a minimum, "Session III" of NACE CIP.  Include NACE Coating Inspector 
identification number, date of qualification, expiration date, and copy of "Session 
III" certificate or copy of "NACE Certified" certificate.  The NACE Coating 
Inspector shall work directly for the prime construction contractor as part 
of the prime's Quality Control (QC) Organization.  Automatically disqualify 
NACE Coating Inspectors with prior and/or current business relations to job 
site subcontractors, material suppliers, and equipment suppliers.  Submit documentation 
confirming NACE Coating Inspectors have met the aforementioned requirements 
over the past two years.<BRK/>
<BRK/>
2.  Add the following to the table in the Article entitled "QC Specialists Duties 
and Qualification:"<BRK/>
under the heading "Qualification/Experience in Area of Responsibility, add "NACE 
Coating Inspector;" under the heading "Area of Responsibility," add "Surface 
preparation, flooring system installation, field tests, and field inspection;" 
and under the heading "Frequency" add "Full-time during surface preparation, 
flooring system installation, field tests, and field inspection."<BRK/>
<BRK/>
3.  Use NACE Coating Inspector on all flooring projects or, as a minimum, on 
flooring projects with greater than<MET> 232.25 square meters</MET><ENG> 2,500 square feet</ENG>.<BRK/></NPR>
<BRK/>
<AST/><BRK/></NTE>
</PRT>    <END/><BRK/></SEC>