<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA         UFGS-26 12 19.00 40 (November 2008)<BRK/>
                                       -----------------------------------<BRK/>
Preparing Activity:  <PRA>NASA</PRA>              Superseding<BRK/>
                                       UFGS-26 12 00.00 40 (July 2007)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 26 12 19.00 40</SCN><BRK/>
<BRK/>
<STL>PAD-MOUNTED, LIQUID-FILLED, MEDIUM-VOLTAGE TRANSFORMERS</STL><BRK/>
<DTE>11/08</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers <SCP>three-phase pad-mounted transformers 
of the dead-front and live-front types for exterior applications</SCP>.<BRK/>
<BRK/>
Use pad-mounted transformers (properly protected with bayonet type, oil-immersed, 
expulsion fuses in series with oil-immersed, partial-range, current-limiting 
fuses) for kVA ratings up to and including 750 kVA on 5 kV systems and for kVA 
ratings up to and including 1500 kVA on 15 and 25 kV systems.<BRK/>
<BRK/>
For voltages above 25 kV and in ratings above those previously indicated, this 
specification requires significant modifications and additional specification 
sections may need to be added on the project.<BRK/>
<BRK/>
The use of pad-mounted transformers with secondary currents exceeding 2000 amperes 
is discouraged due to the size and quantity of secondary conductors.  Therefore, 
transformers above 750 kVA serving 208Y/120 volt loads and transformers above 
1500 kVA serving 480Y/277 volt loads should be in a secondary unit substation configuration.<BRK/>
<BRK/>
Contact the cognizant EFD or PWC for direction.<BRK/>
<BRK/>
For SOUTHNAVFACENGCOM projects, determine the use of secondary unit substations 
on a case by case basis.<BRK/>
<BRK/>
Use the following related guide specifications for power distribution equipment:<BRK/>
Section <SRF>26 08 00</SRF> APPARATUS INSPECTION AND TESTING<BRK/>
Section <SRF>26 12 19.20</SRF> SINGLE-PHASE PAD-MOUNTED TRANSFORMERS<BRK/>
Section <SRF>33 71 01</SRF> OVERHEAD TRANSMISSION AND DISTRIBUTION<BRK/>
Section <SRF>26 11 14.00 10</SRF> MAIN ELECTRIC SUPPLY STATION AND SUBSTATION<BRK/>
Section <SRF>26 11 13.00 20</SRF> PRIMARY UNIT SUBSTATION<BRK/>
Section <SRF>26 11 16</SRF> SECONDARY UNIT SUBSTATIONS<BRK/>
Section <SRF>26 28 00.00 10</SRF> MOTOR CONTROL CENTERS, SWITCHBOARDS AND PANELBOARDS<BRK/>
Section <SRF>26 22 00.00 10</SRF> 480-VOLT STATION SERVICE SWITCHGEAR AND TRANSFORMERS<BRK/>
Section <SRF>26 23 00</SRF> SWITCHBOARDS AND SWITCHGEAR<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestion on this specification are welcome and should be directed 
to the technical proponent of the specification.  A listing of the <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE: TO DOWNLOAD UFGS GRAPHICS<BRK/>
<BRK/>
Go to <URL HREF="http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf">http://www.wbdg.org/ccb/NAVGRAPH/graphtoc.pdf</URL>.</NPR><BRK/>
<BRK/>
<NPR>Do not include list of tables, or tables themselves, in project specifications.  
Use tables to obtain values required in Part 2 of the specification.</NPR><BRK/>
<BRK/>
<NPR>For SOUTHNAVFACENGCOM facilities use Table PM-2.</NPR><BRK/>
<BRK/>
<TBL><THD>  <HL1>TABLE NUMBER</HL1>                           <HL1>TITLE</HL1><BRK/>
<BRK/></THD>
     PM-1            Transformer Loss &amp; Impedance Data - for Energy<BRK/>
                           Cost (EC) Less Than or Equal to<BRK/>
                           $0.04  (2 pages)<BRK/>
<BRK/>
     PM-2            Transformer Loss &amp; Impedance Data - for Energy<BRK/>
                           Cost (EC) Greater Than $0.04 and Less Than<BRK/>
                           or Equal to $0.08  (2 pages)<BRK/>
<BRK/>
     PM-3            Transformer Loss &amp; Impedance Data - for Energy<BRK/>
                           Cost (EC) Greater Than $0.08 and Less Than<BRK/>
                           or Equal to $0.12 (2 pages)<BRK/>
<BRK/>
     EC-1            Energy costs at LANTNAVFACENGCOM Activities<BRK/>
                           (2 pages)</TBL><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Show the following information on the project drawings:</NPR><BRK/>
<BRK/>
<NPR>1.  Single-line diagram showing pad-mounted transformer connectors, inserts, 
surge arresters, switches, fuses, current transformers with ratings, and meters 
as applicable.</NPR><BRK/>
<BRK/>
<NPR>2.  Grounding plan.</NPR><BRK/>
<BRK/>
<NPR>3.  Type and number of cables, and size of conductors for each power circuit.</NPR><BRK/>
<BRK/>
<NPR>4.  Transformer primary and secondary voltages.  (Use IEEE C57.12.00, Table 
11(b), "Designation of voltage ratings of three-phase windings".)  State the 
primary voltage (nominal) actually in service and not the voltage class.</NPR><BRK/>
<BRK/>
<NPR>5.  Special conditions, such as altitude, temperature and humidity; exposure 
to fumes, vapors, dust, and gases; and seismic requirements.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to in the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ACI INTERNATIONAL (ACI)</ORG><BRK/><BRK/><RID>ACI 318M</RID><RTL>(2008) Metric Building Code Requirements for Structural Concrete and Commentary</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)</ORG><BRK/><BRK/><RID>ANSI C12.7</RID><RTL>(2005) Requirements for Watthour Meter Sockets</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM A 167</RID><RTL>(1999; R 2004) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip</RTL><BRK/><BRK/><RID>ASTM C 260</RID><RTL>(2006) Standard Specification for Air-Entraining Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM D 117</RID><RTL>(2002) Standard Guide for Sampling, Test Methods, Specifications and Guide for Electrical Insulating Oils of Petroleum Origin</RTL><BRK/><BRK/><RID>ASTM D 1535</RID><RTL>(2008) Specifying Color by the Munsell System</RTL><BRK/><BRK/><RID>ASTM D 3487</RID><RTL>(2008) Standard Specification for Mineral Insulating Oil Used in Electrical Apparatus</RTL><BRK/><BRK/><RID>ASTM D 877</RID><RTL>(2002; R 2007) Standard Test Method for Dielectric Breakdown Voltage of Insulating Liquids Using Disk Electrodes</RTL><BRK/><BRK/><RID>ASTM D 92</RID><RTL>(2005a) Standard Test Method for Flash and Fire Points by Cleveland Open Cup Tester</RTL><BRK/><BRK/><RID>ASTM D 97</RID><RTL>(2008) Pour Point of Petroleum Products</RTL><BRK/><BRK/></REF><REF><ORG>FM GLOBAL (FM)</ORG><BRK/><BRK/><RID>FM P7825</RID><RTL>(2005) Approval Guide</RTL><BRK/><BRK/></REF><REF><ORG>INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)</ORG><BRK/><BRK/><RID>IEEE C2</RID><RTL>(2007; Errata 2007; INT 2008) National Electrical Safety Code</RTL><BRK/><BRK/><RID>IEEE C37.47</RID><RTL>(1981) Distribution Fuse Disconnecting Switches, Fuse Supports, and Current-Limiting Fuses**</RTL><BRK/><BRK/><RID>IEEE C57.12.00</RID><RTL>(2006) Standard General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers</RTL><BRK/><BRK/><RID>IEEE C57.12.25</RID><RTL>(1990) Standard for Transformers - Pad-Mounted, Compartmental-Type, Self-Cooled, Single-Phase Distribution Transformers with Separable Insulated High-Voltage Connectors; High Voltage (34 500-Grd Y/19 920 Volts and Below; Low Voltage, 240/120 Volts; 167 kVA and Smaller - Requirements)</RTL><BRK/><BRK/><RID>IEEE C57.12.28</RID><RTL>(2005) Standard for Pad-Mounted Equipment - Enclosure Integrity</RTL><BRK/><BRK/><RID>IEEE C57.12.34</RID><RTL>(2004; Errata 2005) Pad-Mounted, Compartmental-Type, Self-Cooled, Three-Phase Distribution Transformers, 2500 kVA and Smaller—High-Voltage: 34 500 GrdY/19 920 Volts and Below; Low Voltage: 480 Volts and Below</RTL><BRK/><BRK/><RID>IEEE C57.12.80</RID><RTL>(2002) Standard Terminology for Power and Distribution Transformers</RTL><BRK/><BRK/><RID>IEEE C57.12.90</RID><RTL>(2006) Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers</RTL><BRK/><BRK/><RID>IEEE C57.13</RID><RTL>(2008) Standard Requirements for Instrument Transformers</RTL><BRK/><BRK/><RID>IEEE C57.98</RID><RTL>(1993; R 1999) Guide for Transformer Impulse Tests</RTL><BRK/><BRK/><RID>IEEE C62.11</RID><RTL>(2005; Amendment A 2008) Standard for Metal-Oxide Surge Arresters for Alternating Current Power Circuits (&gt;1kV)</RTL><BRK/><BRK/><RID>IEEE Std 100</RID><RTL>(2000) The Authoritative Dictionary of IEEE Standards Terms</RTL><BRK/><BRK/><RID>IEEE Std 386</RID><RTL>(2006) Standard for Separable Insulated Connector Systems for Power Distribution Systems Above 600V</RTL><BRK/><BRK/></REF><REF><ORG>INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)</ORG><BRK/><BRK/><RID>NETA ATS</RID><RTL>(2003) Acceptance Testing Specifications</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)</ORG><BRK/><BRK/><RID>NEMA C12.1</RID><RTL>(2008) Electric Meters; Code for Electricity Metering</RTL><BRK/><BRK/><RID>NEMA C12.10</RID><RTL>(2004) Physical Aspects of Watthour Meters</RTL><BRK/><BRK/><RID>NEMA LI 1</RID><RTL>(1998) Industrial Laminated Thermosetting Products</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)</ORG><BRK/><BRK/><RID>NFPA 70</RID><RTL>(2007; AMD 1 2008) National Electrical Code - 2008 Edition</RTL><BRK/><BRK/></REF><REF><ORG>ORGANISATION FOR ECONOMIC CO-OPERATION AND DEVELOPMENT (OECD)</ORG><BRK/><BRK/><RID>OECD Test 203</RID><RTL>(1992) Fish Acute Toxicity Test</RTL><BRK/><BRK/></REF><REF><ORG>U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)</ORG><BRK/><BRK/><RID>EPA 600/4-90/027F</RID><RTL>(1993) Methods for Measuring the Acute Toxicity of Effluents and Receiving Waters to Freshwater and Marine Organisms</RTL><BRK/><BRK/><RID>EPA 712-C-98-075</RID><RTL>(1996) Fate, Transport and Transformation Test Guidelines - OPPTS 835.3100- "Aerobic Aquatic Biodegradation"</RTL><BRK/><BRK/></REF><REF><ORG>UNDERWRITERS LABORATORIES (UL)</ORG><BRK/><BRK/><RID>UL 467</RID><RTL>(2007) Standard for Grounding and Bonding Equipment</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   RELATED REQUIREMENTS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include Section 26 08 00 APPARATUS INSPECTION AND TESTING on all projects 
involving medium voltage and specialized power distribution equipment.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Section <SRF>26 08 00</SRF> APPARATUS INSPECTION AND TESTING applies to this section, with the additions and modifications 
specified herein.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   DEFINITIONS</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, 
and on the drawings, shall be as defined in <RID>IEEE Std 100</RID>.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Submittals shall be limited to those necessary for adequate quality control.  
The importance of an item in the project should be one of the primary factors 
in determining if a submittal for the item should be required.<BRK/>
<BRK/>
A  “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”. Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Recommended codes for Army 
projects are "RE" for Resident Engineer approval, "ED" for Engineering approval, 
and "AE" for Architect-Engineer approval.  Codes following the "G" typically 
are not used for Navy projects.<BRK/>
<BRK/>
Submittal items not designated with a "G" are considered as being for information 
only for Army projects and for Contractor Quality Control approval for Navy 
projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are for information only or as otherwise designated.  When used, a designation following the "G" designation 
identifies the office that will review the submittal for the Government.  Submit the following in accordance 
with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include the bracketed option on "CIEE and 074 review" for NAVFAC Atlantic 
and SOUTHNAVFACENGCOM projects respectively.  For other projects, submittal 
review shall be performed by the designer of record.  If submittal review by 
NAVFAC Atlantic or SOUTHNAVFACENGCOM is specifically desired, the responsible 
Government agency must coordinate with the respective Code CIEE or 074 during 
the design process.  Add appropriate information in section entitled "Submittal 
Procedures" to coordinate with the special requirements.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[[Code CIEE, NAVFAC Atlantic][Code 074, Southern Division, Naval Facilities Engineering Command] will review 
and approve all submittals in this section requiring Government approval.]  As an exception to this paragraph, 
transformers manufactured by ABB in Jefferson City, MO; by Cooper Power Systems in Waukesha, WI; by ERMCO in 
Dyersburg, TN; or by Howard Industries in Laurel, MS need not submit the entire submittal package requirements 
of this contract.  Instead, submit the following items:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  A certification, from the manufacturer, that the technical requirements of this specification shall 
be met.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  An outline drawing of the transformer with devices identified (paragraph entitled "Pad-Mounted Transformer 
Drawings", item a).</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  ANSI nameplate data of the transformer (paragraph entitled "Pad-Mounted Transformer Drawings", item 
b).</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The designer is responsible for providing proper settings for any secondary 
over-current device(s) to ensure proper protection of equipment and coordination 
with transformer high side fuses.  Include the following option for transformers 
serving secondary over-current devices containing adjustable trips.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[d.  Manufacturer's published time-current curves (on full size logarithmic paper) of the transformer 
high side fuses (paragraph entitled "Pad-Mounted Transformer Drawings", item e).]</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use "will" on all SOUTHNAVFACENGCOM projects.  Coordinate with paragraph 
entitled "Source Quality Control."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">e.  Routine and other tests (in PART 2, see paragraph entitled "Routine and Other Tests"), shall be conducted 
by the manufacturer and [may][will] be witnessed by the government (in Part 2, see paragraph entitled 
"Source Quality Control").  Provide transformer test schedule required by submittal item "SD-11 Closeout 
Submittals".  Provide certified copies of the tests.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Provide acceptance test reports required by submittal item "SD-06 Test Reports".</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Provide operation and maintenance manuals required by submittal item "SD-10 Operation and Maintenance 
Data".</LST><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Pad-mounted transformer drawings</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Pad-mounted transformers</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Submittal shall include manufacturer's information for each component, device, and accessory 
provided with the transformer.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Acceptance checks and tests</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Transformer losses</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Submit certification from the manufacturer indicating conformance with the paragraph entitled 
"Specified Transformer Losses."</ITM><BRK/>
<BRK/>
<LST><SUB>SD-09 Manufacturer's Field Reports</SUB></LST><BRK/>
<BRK/>
<ITM>Pad-mounted transformer <SUB>design tests</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Pad-mounted transformer <SUB>routine and other tests</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-10 Operation and Maintenance Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Transformer(s)</SUB>, Data Package 5[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Submit operation and maintenance data in accordance with Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE 
DATA and as specified herein.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-11 Closeout Submittals</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Transformer test schedule</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>Submit report of test results as specified by paragraph entitled "Field Quality Control."</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5   QUALITY ASSURANCE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.5.1   <SUB>Pad-Mounted Transformer Drawings</SUB></TTL><BRK/>
<BRK/>
<TXT>Drawings shall indicate, but not be limited to the following:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  An outline drawing, with front, top, and side views.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  ANSI nameplate data.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Navy policy requires that all facilities be metered.  If exception is 
taken, coordinate with paragraphs entitled "Additions to Operation and Maintenance 
Manuals" and "Metering."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">c.  Elementary diagrams and wiring diagrams with terminals identified of watthour meter and current transformers.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  One-line diagram, including switch(es), current transformers, meters, and fuses.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Manufacturer's published time-current curves (on full size logarithmic paper) of the transformer 
high side fuses.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.2   Regulatory Requirements</TTL><BRK/>
<BRK/>
<TXT>In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the 
word, "shall" had been substituted for "should" wherever it appears.  Interpret references in these publications 
to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer.  Equipment, 
materials, installation, and workmanship shall be in accordance with the mandatory and advisory provisions of <RID>
NFPA 70</RID> unless more stringent requirements are specified or indicated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.3   Standard Products</TTL><BRK/>
<BRK/>
<TXT>Provide materials and equipment that are products of manufacturers regularly engaged in the production of such 
products which are of equal material, design and workmanship.  Products shall have been in satisfactory commercial 
or industrial use for 2 years prior to bid opening.  The 2-year period shall include applications of equipment 
and materials under similar circumstances and of similar size.  The product shall have been on sale on the commercial 
market through advertisements, manufacturers' catalogs, or brochures during the 2-year period.  Where two or 
more items of the same class of equipment are required, these items shall be products of a single manufacturer; 
however, the component parts of the item need not be the products of the same manufacturer unless stated in this 
section.</TXT><BRK/>
<BRK/>
<SPT><TTL>1.5.3.1   Alternative Qualifications</TTL><BRK/>
<BRK/>
<TXT>Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory 
field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is 
furnished.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.5.3.2   Material and Equipment Manufacturing Date</TTL><BRK/>
<BRK/>
<TXT>Do not use products manufactured more than 3 years prior to date of delivery to site, unless specified otherwise.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>1.6   MAINTENANCE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.6.1   Additions to Operation and Maintenance Data</TTL><BRK/>
<BRK/>
<TXT>In addition to requirements of Data Package 5, include the following on the actual <SUB>transformer(s)</SUB> provided:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  An instruction manual with pertinent items and information highlighted</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  An outline drawing, front, top, and side views</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Prices for spare parts and supply list</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Routine and field acceptance test reports</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Fuse curves for primary fuses</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Information on watthour demand meter, CT's, and fuse block</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Actual nameplate diagram</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">h.  Date of purchase</LST><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.7   WARRANTY</TTL><BRK/>
<BRK/>
<TXT>The equipment items shall be supported by service organizations which are reasonably convenient to the equipment 
installation in order to render satisfactory service to the equipment on a regular and emergency basis during 
the warranty period of the contract.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   PRODUCT COORDINATION</TTL><BRK/>
<BRK/>
<TXT>Products and materials not considered to be pad-mounted transformers and related accessories are specified in[ 
Section <SRF>33 71 01</SRF> OVERHEAD TRANSMISSION AND DISTRIBUTION,][ Section <SRF>33 71 02.00 20</SRF> UNDERGROUND ELECTRICAL DISTRIBUTION,][ 
and][ Section <SRF>26 20 00</SRF> INTERIOR DISTRIBUTION SYSTEM][ Section <SRF>33 70 02.00 10</SRF> ELECTRICAL DISTRIBUTION SYSTEM, 
UNDERGROUND].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2   THREE-PHASE <SUB>PAD-MOUNTED TRANSFORMERS</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use dead-front transformers unless available system fault current exceeds 
equipment ratings.  If live-front transformers are required, their use shall 
be approved by the cognizant EFD.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>IEEE C57.12.34</RID>, <RID>IEEE C57.12.28</RID> and as specified herein.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Compartments</TTL><BRK/>
<BRK/>
<TXT>Separate the high- and low-voltage compartments with steel isolating barriers extending the full height and depth 
of the compartments. Compartment doors:  hinged lift-off type with stop in open position and three-point latching.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Current policy is to use oil-immersed fuses in series with current limiting 
fuses to achieve better protection and obtain life cycle cost benefits.  Use 
dry-well canister fuses only when specifically required by the activity.</NPR><BRK/>
<BRK/>
<NPR>Do not provide standoff bushings unless this transformer is the only dead-front 
transformer on the base.  Public works normally carries standoff bushings in 
their vehicles.  Provide protective caps when providing standoff bushings and 
to cover unused bushing well inserts when not providing surge arresters.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.2.1.1   High Voltage, Dead-Front</TTL><BRK/>
<BRK/>
<TXT>High-voltage compartment shall contain the incoming line, insulated high-voltage load-break connectors, bushing 
well inserts,[ feed-thru inserts,] six high-voltage bushing wells configured for loop feed application, load-break 
switch handle(s), access to [oil-immersed fuses][dry-well fuse canisters],[ dead-front surge arresters,] tap 
changer handle, connector parking stands[ with insulated standoff bushings],[ protective caps,] and ground pad.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The following paragraph is based on 200-ampere connectors.  If transformer 
primary load current is greater than 200 amperes or if primary cable size is 
greater than No. 4/0 AWG, designer shall determine the appropriate connector system.<BRK/>
<BRK/>
Portions of the 4.16 kV system at Dam Neck, VA and all of the 11.5 kV system 
at Norfolk Naval Shipyard, VA have a fault capability in excess of 10,000 amps.  
Locating the current-limiting fuses ahead of the load-break switch as specified 
in this paragraph will limit the available fault current to less than 10,000 
amps.  Therefore, 600 amp separable insulated connectors with a short time rating 
of 25,000 rms symmetrical amperes and load-break switches can be used on pad-mounted 
transformers in these locations.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">a.  Insulated high-voltage load-break connectors:  <RID>IEEE Std 386</RID>, rated [15][_____] kV, [95][_____] kV 
BIL.  Current rating:  200 amperes rms continuous.  Short time rating:  10,000 amperes rms symmetrical 
for a time duration of 0.17 seconds.  Connector shall have a steel reinforced hook-stick eye, grounding 
eye, test point, and arc-quenching contact material.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Bushing well inserts[ and feed-thru inserts]:  <RID>IEEE Std 386</RID>, 200 amperes, [15][_____] kV Class.  
Provide a bushing well insert for each bushing well unless indicated otherwise.[  Provide feed-thru inserts 
as indicated.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Load-break switch</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>[Radial-feed oil-immersed type rated at [15][_____] kV, [95][_____] kV BIL, with a continuous current 
rating and load-break rating of [200][_____] amperes, and a make-and-latch rating of 10,000 rms amperes 
symmetrical.  Locate the switch handle in the high-voltage compartment.]</LST><BRK/>
<BRK/>
<LST>[Loop feed sectionalizer switches:  Provide three, two-position, oil-immersed type switches to permit 
closed transition loop feed and sectionalizing.  Each switch shall be rated at [15][_____] kV, [95][_____] 
kV BIL, with a continuous current rating and load-break rating of [200][_____] amperes, and a make-and-latch 
rating of 10,000 rms amperes symmetrical.  Locate the switch handles in the high-voltage compartment.  
Operation of switches shall be as follows:</LST><BRK/>
<BRK/>
<TBL><THD>            |  DESCRIPTION         |  SWITCH POSITION<BRK/>
  ARRANGE-  |  OF SWITCH           |  LINE A SW. | LINE B SW |  XFMR. SW<BRK/>
  MENT NO.  |  ARRANGEMENT         |  OPEN|CLOSE | OPEN|CLOSE|  OPEN|CLOSE<BRK/>
--------------------------------------------------------------------------<BRK/>
<BRK/></THD>
      1     |  Line A              |      |  X   |     |  X  |      |  X<BRK/>
            |  connected           |      |      |     |     |      |<BRK/>
            |  to Line B           |      |      |     |     |      |<BRK/>
            |  and both lines      |      |      |     |     |      |<BRK/>
            |  connected to        |      |      |     |     |      |<BRK/>
            |  transformer         |      |      |     |     |      |<BRK/>
--------------------------------------------------------------------------<BRK/>
      2     |  Transformer         |      |  X   |  X  |     |      |  X<BRK/>
            |  connected to        |      |      |     |     |      |<BRK/>
            |  Line A only         |      |      |     |     |      |<BRK/>
--------------------------------------------------------------------------<BRK/>
      3     |  Transformer         |  X   |      |     |  X  |      |  X<BRK/>
            |  connected to        |      |      |     |     |      |<BRK/>
            |  Line B only         |      |      |     |     |      |<BRK/>
--------------------------------------------------------------------------<BRK/>
      4     |  Transformer         |      |  X   |     |  X  |  X   |<BRK/>
            |  open and            |      |      |     |     |      |<BRK/>
            |  loop closed         |      |      |     |     |      |<BRK/>
--------------------------------------------------------------------------<BRK/>
      5     |  Transformer         |  X   |      |  X  |     |  X   |<BRK/>
            |  open and            |      |      |     |     |      |<BRK/>
            |  loop open           |      |      |     |     |      |<BRK/>
-------------------------------------------------------------------------]</TBL><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Provide bayonet type, oil-immersed, expulsion fuses in series with oil-immersed, partial-range, current-limiting 
fuses.  Bayonet fuse links shall sense both high currents and high oil temperature in order to provide 
thermal protection to the transformer.  Coordinate transformer protection with expulsion fuse clearing 
low-current faults and current-limiting fuse clearing high-current faults beyond the interrupting rating 
of the expulsion fuse.  In order to eliminate or minimize oil spills, the bayonet fuse assembly shall 
include an oil retention valve inside the housing which closes when the fuse holder is removed and an 
external drip shield.  Conspicuously display warning within the high-voltage compartment cautioning against 
removing or inserting fuses unless the load-break switch is in the open position and the tank pressure 
has been released.</LST><BRK/>
<BRK/>
<LST>Bayonet fuse assembly:  150 kV BIL.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For transformers with loop-feed sectionalizer switching, delete the bracketed 
option regarding placement of current-limiting fuses.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>Oil-immersed current-limiting fuses:  <RID>IEEE C37.47</RID>; 50,000 rms amperes symmetrical interrupting rating 
at the system voltage specified.[  Connect current-limiting fuses ahead of the radial-feed load-break 
switch.]</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  When dry-well canisters are selected, delete the above paragraphs on 
oil-immersed fuses.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[e.  Current-limiting fuses, dry-well mount:  <RID>IEEE C37.47</RID>.  Provide fuses in air-insulated, oil-sealed, 
dead-front, non-load-break dry-well fuse canisters, on the load side of the load-break switch serving 
the transformer.  Interlock fuse canisters with the load-break switch so that the fuses may be removed 
and inserted only when the switch is in the "Off" position.  Fuses shall remove the transformer from 
service in case of an internal fault.  Size fuses to approximately 150 percent of the transformer primary 
full load current rating and in accordance with fuse manufacturer's recommendations for dry-well mounting.  
Fuses shall have an interrupting rating of 50,000 rms amperes symmetrical at the system voltage specified.  
Furnish a spare fuse for each fuse provided.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[f.  Surge arresters:  <RID>IEEE C62.11</RID>, rated [3][6][9][10][12][15][_____] kV, fully shielded, dead-front, 
metal-oxide-varistor, elbow type with resistance-graded gap, suitable for plugging into inserts.[  Provide 
three arresters for radial feed circuits.][  Provide [three][six] arresters for loop feed circuits.]]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Parking stands:  Provide a parking stand near each bushing well.[  Provide insulated standoff bushings 
for parking of energized load-break connectors on parking stands.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[h.  Protective caps:  <RID>IEEE Std 386</RID>, 200 amperes, [15][25][_____] kV Class.  Provide insulated protective 
caps (not shipping caps) for insulating and sealing out moisture from unused bushing well inserts[ and 
insulated standoff bushings].]</LST><BRK/>
<BRK/></SPT>
<SPT>[<TTL>2.2.1.2   High Voltage, Live-Front</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  When live-front is selected, delete the above paragraphs on dead-front.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>High-voltage compartment shall contain the incoming line, transformer high-voltage bushings, load-break switch 
handle(s), access to [oil-immersed fuses][dry-well fuse canisters],[ surge arresters,] tap changer handle, insulated 
phase barriers, and ground pad.</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Cable terminators:  Provide as specified in Section[ <SRF>33 71 02.00 20</SRF> UNDERGROUND ELECTRICAL DISTRIBUTION][ 
<SRF>33 70 02.00 10</SRF> ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND].</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Load-break switch</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>[Radial-feed oil-immersed type rated at [15][_____] kV, [95][_____] kV BIL, with a continuous current 
rating and load-break rating of [200][_____] amperes, and a make-and-latch rating of 10,000 rms amperes 
symmetrical.  Locate the switch handle in the high-voltage compartment.]</LST><BRK/>
<BRK/>
<LST>[Loop feed sectionalizer switches:  Provide three, two-position, oil-immersed type switches to permit 
closed transition loop feed and sectionalizing.  Rate each switch at [15][_____] kV, [95][_____] kV BIL, 
with a continuous current rating and load-break rating of [200][_____] amperes, and a make-and-latch 
rating of 10,000 rms amperes symmetrical.  Locate the switch handles in the high-voltage compartment.  
Operation of switches shall be as follows:</LST><BRK/>
<BRK/>
<TBL><THD>            |  DESCRIPTION      |  SWITCH POSITION<BRK/>
  ARRANGE-  |  OF SWITCH        |  LINE A SW. | LINE B SW |  XFMR. SW<BRK/>
  MENT NO.  |  ARRANGEMENT      |  OPEN|CLOSE | OPEN|CLOSE|  OPEN|CLOSE<BRK/>
--------------------------------------------------------------------------<BRK/>
<BRK/></THD>
      1     |  Line A           |      |  X   |     |  X  |      |  X<BRK/>
            |  connected        |      |      |     |     |      |<BRK/>
            |  to Line B and    |      |      |     |     |      |<BRK/>
            |  both lines       |      |      |     |     |      |<BRK/>
            |  connected to     |      |      |     |     |      |<BRK/>
            |  transformer      |      |      |     |     |      |<BRK/>
--------------------------------------------------------------------------<BRK/>
      2     |  Transformer      |      |  X   |  X  |     |      |  X<BRK/>
            |  connected to     |      |      |     |     |      |<BRK/>
            |  Line A only      |      |      |     |     |      |<BRK/>
--------------------------------------------------------------------------<BRK/>
      3     |  Transformer      |  X   |      |     |  X  |      |  X<BRK/>
               connected to     |      |      |     |     |      |<BRK/>
            |  Line B only      |      |      |     |     |      |<BRK/>
--------------------------------------------------------------------------<BRK/>
      4     |  Transformer      |      |  X   |     |  X  |  X   |<BRK/>
               open and         |      |      |     |     |      |<BRK/>
            |  loop closed      |      |      |     |     |      |<BRK/>
--------------------------------------------------------------------------<BRK/>
      5     |  Transformer      |  X   |      |  X  |     |  X   |<BRK/>
               open and         |      |      |     |     |      |<BRK/>
            |  loop open        |      |      |     |     |      |<BRK/>
-------------------------------------------------------------------------]</TBL><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Provide bayonet type, oil-immersed, expulsion fuses in series with oil-immersed, partial-range, current-limiting 
fuses.  Bayonet fuse links shall sense both high currents and high oil temperature in order to provide 
thermal protection to the transformer.  Coordinate transformer protection with expulsion fuse clearing 
low-current faults and current-limiting fuse clearing high-current faults beyond the interrupting rating 
of the expulsion fuse.  In order to eliminate or minimize oil spills, the bayonet fuse assembly shall 
include an oil retention valve inside the housing which closes when the fuse holder is removed and an 
external drip shield.  Conspicuously display warning within the high-voltage compartment cautioning against 
removing or inserting fuses unless the load-break switch is in the open position and the tank pressure 
has been released.</LST><BRK/>
<BRK/>
<LST>Bayonet fuse assembly:  150 kV BIL.</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For transformers with loop-feed sectionalizer switching, delete the bracketed 
option regarding placement of current-limiting fuses.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST>Oil-immersed current-limiting fuses:  <RID>IEEE C37.47</RID>; 50,000 rms amperes symmetrical interrupting rating 
at the system voltage specified.[  Connect current-limiting fuses ahead of the radial-feed load-break 
switch.]</LST><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  When dry-well canisters are selected, delete the above paragraphs on 
oil-immersed fuses.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[d.  Current-limiting fuses, dry-well mount:  <RID>IEEE C37.47</RID>.  Provide fuses in air-insulated, oil-sealed, 
dead-front, non-load-break dry-well fuse canisters, on the load side of the load-break switch serving 
the transformer.  Interlock fuse canisters with the load-break switch so that the fuses may be removed 
and inserted only when the switch is in the "Off" position.  Fuses shall remove the transformer from 
service in case of an internal fault.  Size fuses to approximately 150 percent of the transformer primary 
full load current rating and in accordance with fuse manufacturer's recommendations for dry-well mounting.  
Fuses shall have an interrupting rating of 50,000 rms amperes symmetrical at the system voltage specified.  
Furnish a spare fuse for each fuse provided.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[e.  Surge arresters:  <RID>IEEE C62.11</RID>, rated [3][6][9][10][12][15][_____] kV.[  Provide three arresters 
for radial feed circuits.][  Provide [three][six] arresters for loop feed circuits.]]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Insulated phase barriers:  <RID>NEMA LI 1</RID>, Type GPO-3,<MET> 6.35 mm</MET><ENG> 0.25 inch</ENG> minimum thickness.  Provide vertical 
barriers between the high-voltage bushings and a single horizontal barrier above the high-voltage bushings.</LST><BRK/>
<BRK/>
]</SPT><SPT><TTL>2.2.1.3   Low Voltage</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Installation of circuit breakers in the secondary compartment is not 
recognized by ANSI standards, and limits accessibility by covering lugs, gages, 
and accessories.  Do not use.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Low-voltage compartment shall contain low-voltage bushings with NEMA spade terminals, accessories,[ metering,] 
stainless steel or laser-etched anodized aluminum diagrammatic transformer nameplate, and ground pad.</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Accessories shall include drain valve with sampler device, fill plug, pressure relief device, liquid 
level gage, pressure-vacuum gage, and dial type thermometer with maximum temperature indicator.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.1.4   Three-Phase Metering</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  When Section 23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR 
HVAC or Section 23 09 23 DIRECT DIGITAL CONTROL FOR HVAC AND OTHER LOCAL BUILDING 
SYSTEMS is used, coordinate meter requirements.  Form 9S, in text below, is 
for three-phase, four-wire wye systems, for other system configurations, designer 
shall determine the appropriate form designation.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM INDENT="-0.33">1.  Design:  Provide meter designed for use on a 3-phase, 4-wire, [208Y/120][480Y/277] volt 
system with 3 current transformers.  Include necessary KYZ pulse initiation hardware for Energy 
Monitoring and Control System (EMCS)[ as specified in Section[ <SRF>23 09 23</SRF> DIRECT DIGITAL CONTROL 
HVAC AND OTHER LOCAL BUILDING SYSTEMS]].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Coordination:  Provide meter coordinated with ratios of current transformers and transformer 
secondary voltage.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Class:  20; Form:  [9S][___]; Accuracy: +/- 1.0 percent; Finish: Class II</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Cover:  Polycarbonate and lockable to prevent tampering and unauthorized removal.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Kilowatt-hour Register:  5 digit electronic programmable type</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Demand Register:</ITM><BRK/>
<BRK/>
<ITM>(a)  Provide solid state</ITM><BRK/>
<BRK/>
<ITM>(b)  Meter reading multiplier:</ITM><BRK/>
<BRK/>
<ITM INDENT="0.33">(1)  Indicate multiplier on the meter face.</ITM><BRK/>
<BRK/>
<ITM>(c)  Demand interval length: shall be programmed for [15][30][60] minutes with rolling demand 
up to six subintervals per interval.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">7.  Meter fusing:  Provide a fuse block mounted in the secondary compartment containing one 
fuse per phase to protect the voltage input to the watthour meter.  Size fuses as recommended 
by the meter manufacturer.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">8.  Socket:  <RID>ANSI C12.7</RID>.  Provide NEMA Type 3R, box-mounted socket having automatic circuit-closing 
bypass and having jaws compatible with requirements of the meter.  Cover unused hub openings 
with blank hub plates.  Paint box Munsell 7GY3.29/1.5 green to match the pad-mounted transformer 
to which the box-mounted socket is attached.  The Munsell color notation is specified in <RID>ASTM D 1535</RID>
.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">9.  Current transformers:  <RID>IEEE C57.13</RID>.  Provide butyl-molded window type current transformers 
with 600-volt insulation, 10 kV BIL and mount on the low-voltage bushings.  Route current transformer 
leads in a location as remote as possible from the power transformer secondary cables to permit 
current measurements to be taken with hook-on-ammeters.  Provide three current transformers 
per power transformer with characteristics listed in the following table.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[1.  <RID>NEMA C12.10</RID>.  Metering for two-compartment transformers:  Provide a socket-mounted electronic 
programmable outdoor watthour meter, surface mounted flush against the side of the low-voltage 
compartment as indicated.  Meter shall either be programmed at the factory or programmed in 
the field.  When field programming is performed, turn field programming device over to the Contracting 
Officer at completion of project.  Coordinate meter to system requirements.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  When Section 23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR 
HVAC is used, coordinate meter requirements.  Form 4S, in text below, is for 
single-phase, three-wire systems, for other system configurations, designer 
shall determine the appropriate form designation.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>(a)  Design:  Provide meter designed for use on a single-phase, three-wire, [240/120][480/240] 
volt system with two current transformers.  Include necessary KYZ pulse initiation hardware 
for energy monitoring and control system (EMCS)[ as specified in Section <SRF>23 09 23</SRF> DIRECT DIGITAL 
CONTROL FOR HVAC AND OTHER BUILDING SYSTEMS].</ITM><BRK/>
<BRK/>
<ITM>(b)  Coordination:  Provide meter coordinated with ratios of current transformers and transformer 
secondary voltage.</ITM><BRK/>
<BRK/>
<ITM>(c)  Class:  20<BRK/>
Form:  4S, accuracy:  plus or minus 1.0 percent<BRK/>
Finish:  Class II</ITM><BRK/>
<BRK/>
<ITM>(d)  Cover:  Polycarbonate and lockable to prevent tampering and unauthorized removal.</ITM><BRK/>
<BRK/>
<ITM>(e)  Kilowatt-hour register:  Five digit electronic programmable type</ITM><BRK/>
<BRK/>
<ITM>(f)  Demand register</ITM><BRK/>
<BRK/>
<ITM>    (1)  Provide solid state</ITM><BRK/>
<BRK/>
<ITM>    (2)  Meter reading multiplier:  Indicate multiplier on the meter face.</ITM><BRK/>
<BRK/>
<ITM>    (3)  Demand interval length:  Program for [15][30][60] minutes with rolling demand up to 
six subintervals per interval.</ITM><BRK/>
<BRK/>
<ITM>(g)  Meter fusing:  Provide a fuse block mounted in the secondary side containing one fuse per 
phase to protect the voltage input to the meter.  Size fuses as recommended by the meter manufacturer.</ITM><BRK/>
<BRK/>
<ITM>(h)  Socket:  <RID>ANSI C12.7</RID>.  Provide NEMA Type 3R, box-mounted socket having automatic circuit-closing 
bypass and having jaws compatible with requirements of the meter.  Cover unused hub openings 
with blank hub plates.  Paint box Munsell 7GY3.29/1.5 green to match the pad-mounted transformer 
to which the box-mounted socket is attached.  The Munsell color notation is specified in <RID>ASTM D 1535</RID>
.]</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The following guidelines for specifying current transformers are based 
on the standard current transformer primary rating which is just below the full 
load current of the power transformer.</NPR><BRK/>
<BRK/>
<NPR>1.  Select the appropriate current transformer (CT) ratio, continuous-thermal-current 
rating factor (RF) at 30 degrees C and ANSI Metering Accuracy Class values based 
on transformer kVA size and secondary voltage.  Example:  for a 500 kVA transformer 
at 208 volts - select 1200/5, 1.5, 0.3 - B-0.5.</NPR><BRK/>
<BRK/>
<TBL><THD>       |---------------------------(VOLTS)---------------------------|<BRK/>
       |             208              |              240             |<BRK/>
       |------------------------------|------------------------------|<BRK/>
       |   CT  |    |      Meter      |   CT  |    |      Meter      |<BRK/>
  kVA  | Ratio | RF |      Class      | Ratio | RF |      Class      |<BRK/>
|------|------------------------------|------------------------------|<BRK/>
<BRK/></THD>
|   75 |  200/5, 4.0,  0.3 thru B-0.1 |  200/5, 4.0,  0.3 thru B-0.1 |<BRK/>
|112.5 |  300/5, 3.0,  0.3 thru B-0.2 |  200/5, 4.0,  0.3 thru B-0.1 |<BRK/>
|  150 |  400/5, 4.0,  0.3 thru B-0.2 |  300/5, 3.0,  0.3 thru B-0.2 |<BRK/>
|  225 |  600/5, 3.0,  0.3 thru B-0.5 |  400/5, 4.0,  0.3 thru B-0.2 |<BRK/>
|  300 |  800/5, 2.0,  0.3 thru B-0.5 |  600/5, 3.0,  0.3 thru B-0.5 |<BRK/>
|  500 | 1200/5, 1.5,  0.3 thru B-0.5 | 1200/5, 1.5,  0.3 thru B-0.5 |<BRK/>
|  750 | 2000/5, 1.5,  0.3 thru B-1.8 | 1500/5, 1.5,  0.3 thru B-0.9 |<BRK/>
 --------------------------------------------------------------------</TBL><BRK/>
<BRK/>
<TBL><THD>       |---------------------------(VOLTS)--------------------------|<BRK/>
       |             480              |              600            |<BRK/>
       |------------------------------|-----------------------------|<BRK/>
       |   CT  |    |    Meter        |   CT  |    |     Meter      |<BRK/>
  kVA  | Ratio | RF |    Class        | Ratio | RF |     Class      |<BRK/>
|------|------------------------------|-----------------------------|<BRK/>
<BRK/></THD>
|   75 |  200/5, 4.0,  0.3 thru B-0.1 |  200/5, 4.0, 0.3 thru B-0.1 |<BRK/>
|112.5 |  200/5, 4.0,  0.3 thru B-0.1 |  200/5, 4.0, 0.3 thru B-0.1 |<BRK/>
|  150 |  200/5, 4.0,  0.3 thru B-0.1 |  200/5, 4.0, 0.3 thru B-0.1 |<BRK/>
|  225 |  200/5, 4.0,  0.3 thru B-0.1 |  200/5, 4.0, 0.3 thru B-0.1 |<BRK/>
|  300 |  300/5, 3.0,  0.3 thru B-0.2 |  200/5, 4.0, 0.3 thru B-0.1 |<BRK/>
|  500 |  600/5, 3.0,  0.3 thru B-0.5 |  400/5, 4.0, 0.3 thru B-0.2 |<BRK/>
|  750 |  800/5, 2.0,  0.3 thru B-0.5 |  600/5, 3.0, 0.3 thru B-0.5 |<BRK/>
| 1000 | 1200/5, 1.5,  0.3 thru B-0.5 |  800/5, 2.0, 0.3 thru B-0.5 |<BRK/>
| 1500 | 1500/5, 1.5,  0.3 thru B-0.9 | 1200/5, 1.5, 0.3 thru B-0.5 |<BRK/>
| 2000 | 2000/5, 1.5,  0.3 thru B-1.8 | 1500/5, 1.5, 0.3 thru B-0.9 |<BRK/>
| 2500 | 3000/5, 1.33, 0.3 thru B-1.8 | 2000/5, 1.5, 0.3 thru B-1.8 |<BRK/>
 -------------------------------------------------------------------</TBL><BRK/>
<BRK/>
<NPR>2.  Incorporate the appropriate values in table below.</NPR><BRK/>
<AST/></NTE><BRK/></SPT>
</SPT><SPT><TTL>2.2.2   Compartment Construction</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">[a.  Single compartment:  Shall be Type 1 as defined by <RID>IEEE C57.12.25</RID> with combination high- and low-voltage 
compartment.  Compartment shall be of the clam shell type with lockable (having pad-locking provisions) 
hinged cover and single-point latching.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[b.  Two compartment:  Separate the high- and low-voltage compartments with steel isolating barriers 
extending the full height and depth of the compartments.  Compartment doors:  hinged lift-off type with 
stop in open position and three-point latching.]</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3   Transformer</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the following guidelines for specifying transformers.</NPR><BRK/>
<BRK/>
<NPR>1.  Previously the use of mineral oil filled transformers were recommended wherever 
possible.  The recent availability of biodegradable less-flammable transformer 
liquids may have altered that recommendation.  For NAVFAC Atlantic , choose 
less-flammable transformer liquids as specified below for all projects unless 
there is a specific requirement to do otherwise.  Where adequate distance from 
structures cannot be attained, consult NAVFAC design manuals and UFC 3-600-01, 
"Design: Fire Protection Engineering For Facilities."  Do not use Silicon-filled 
and R-temp filled transformers for less-flammable requirements.</NPR><BRK/>
<BRK/>
<NPR>2.  Use IEEE C57.12.00, Table 11(b), voltage designations, such as "4160 V - 
480Y / 277 V".</NPR><BRK/>
<BRK/>
<NPR>3.  Select impedance value in accordance with technical note under paragraph 
entitled "Specified Transformer Losses."</NPR><BRK/>
<BRK/>
<NPR>4.  Delete inapplicable sound levels.</NPR><BRK/>
<BRK/>
<NPR>5.  Delete last sentence if transformer secondary winding is delta type.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">a.  [Oil-insulated][Less-flammable liquid-insulated], two winding, 60 hertz, 65 degrees C rise above 
a 30 degrees C average ambient, self-cooled type.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Transformer shall be rated [_____] kVA, [95][60][_____] kV BIL.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Transformer voltage ratings:  [_____] V - [_____] V.[  For GrdY - GrdY transformers, provide transformer 
with five-legged core design for third harmonic suppression.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Tap changer shall be externally operated, manual type for changing tap setting when the transformer 
is de-energized.  Provide four 2.5 percent full capacity taps, two above and two below rated primary 
voltage.  Tap changers shall clearly indicate which tap setting is in use.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Minimum tested impedance shall not be less than [_____] percent at 85 degrees C on Three-Phase tranformers 
[and [_____] at 85 degrees C on Single-Phase traformers].</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Audible sound levels shall comply with the following:</LST><BRK/>
<BRK/>
<TBL><THD>                   <HL1>kVA</HL1>          <HL1>DECIBELS (MAX)</HL1><BRK/>
<BRK/></THD>
                   75                  51<BRK/>
                   112.5               55<BRK/>
                   150                 55<BRK/>
                   225                 55<BRK/>
                   300                 55<BRK/>
                   500                 56<BRK/>
                   750                 57<BRK/>
                   1000                58<BRK/>
                   1500                60</TBL><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Transformer shall include lifting lugs and provisions for jacking under base.  The transformer base 
construction shall be suitable for using rollers or skidding in any direction.  Provide transformer top 
with an access handhole.[  Transformer shall have its kVA rating conspicuously displayed on its enclosure.]  
The transformer shall have an insulated low-voltage neutral bushing with NEMA spade terminal, and with 
removable ground strap.</LST><BRK/>
<BRK/>
<SPT><TTL>2.2.3.1   Specified <SUB>Transformer Losses</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Steps to specifying transformer losses.</NPR><BRK/>
<BRK/>
<NPR>1.  Print Tables PM-1, PM-2, PM-3, and EC-1 as applicable (directions included 
at the front of this specification).</NPR><BRK/>
<BRK/>
<NPR>2.  Obtain energy cost for the specific activity from the cognizant EFD or PWC.  
Energy costs should be based on the cost of energy without the demand charge 
factors scaled in.  Use Table EC-1 for energy costs at the NAVFAC Atlantic activities 
indicated.  Use Table PM-2 for energy costs at all SOUTHNAVFACENGCOM activities.  
(Additional tables will be added for other EFD's as the information becomes 
available.)</NPR><BRK/>
<BRK/>
<NPR>3.  Use Tables PM-1, PM-2, and PM-3 to specify losses and impedances for transformers 
based on energy cost range, and transformer primary and secondary voltages.</NPR><BRK/>
<BRK/>
<NPR>4.  Perform fault current calculations to verify that distribution equipment 
is coordinated with impedance specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[No-load losses (NLL) shall be [_____] watts at 20 degrees C and load losses (LL) shall be [_____] watts at 85 
degrees C.  Use the values for the specified losses for comparison with the losses determined during the routine 
tests.  If the routine test values for no-load losses exceed the specified no-load losses by more than 10 percent, 
or the total losses exceed the specified total losses (sum of no-load and load losses) by more than 6 percent, 
the transformer is unacceptable.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2.4   Insulating Liquid</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options.  For NAVFAC Atlantic , choose less-flammable 
transformer liquids for all projects unless there is a specific requirement 
to do otherwise.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">[a.  Mineral oil:  <RID>ASTM D 3487</RID>, Type II, tested in accordance with <RID>ASTM D 117</RID>.  Provide identification 
of transformer as "non-PCB" and "Type II mineral oil" on the nameplate.]</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">[b.  Less-flammable transformer liquids:  <RID>NFPA 70</RID> and <RID>FM P7825</RID> for less-flammable liquids having a fire 
point not less than 300 degrees C tested per <RID>ASTM D 92</RID> and a dielectric strength not less than 33 kV 
tested per <RID>ASTM D 877</RID>.  Provide identification of transformer as "non-PCB" and "manufacturer's name and 
type of fluid" on the nameplate.</LST><BRK/>
<BRK/>
<LST>The fluid shall be a biodegradable electrical insulating and cooling liquid classified by UL and approved 
by FM as "less flammable" fluids.  The fluid shall meet the following fluid properties:</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Pour point:  <RID>ASTM D 97</RID>, less than -15 degree C</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Aquatic biodegradation:  <RID>EPA 712-C-98-075</RID>, 100%</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Trout toxicity:  <RID>OECD Test 203</RID>, zero mortality of <RID>EPA 600/4-90/027F</RID>, pass]</ITM><BRK/>
<BRK/>
<SPT><TTL>2.2.4.1   Liquid-Filled Transformer Nameplates</TTL><BRK/>
<BRK/>
<TXT>Provide distribution transformers with nameplate information in accordance with <RID>IEEE C57.12.00</RID> and as modified 
or supplemented by this section.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2.5   Corrosion Protection</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use stainless steel bases and cabinets for most applications.  In hostile 
environments, the additional cost of totally stainless steel tanks and metering 
may be justified.  Manufacturer's standard construction material is acceptable 
only in noncoastal and noncorrosive environments.  Choose the second bracketed 
option for hostile environments.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Bases and cabinets of transformers shall be corrosion resistant and shall be fabricated of stainless steel conforming 
to <RID>ASTM A 167</RID>, Type 304 or 304L.  Base shall include any part of pad-mounted transformer that is within<MET>75 mm</MET><ENG> 
3 inches</ENG> of concrete pad.  Paint bases, cabinets, and tanks Munsell 7GY3.29/1.5 green.  Paint coating system 
shall comply with <RID>IEEE C57.12.28</RID>.  The Munsell color notation is specified in <RID>ASTM D 1535</RID>.][Entire transformer 
assembly, including tank and radiator, base, enclosure, and metering enclosure shall be fabricated of stainless 
steel conforming to <RID>ASTM A 167</RID>, Type 304 or 304L.  Form enclosure of stainless steel sheets.  Paint entire transformer 
assembly Munsell 7GY3.29/1.5 green.  Paint coating system shall comply with <RID>IEEE C57.12.28</RID>.  The Munsell color 
notation is specified in <RID>ASTM D 1535</RID>.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3   WARNING SIGNS</TTL><BRK/>
<BRK/>
<TXT>Provide warning signs for the enclosures of pad-mounted transformers having a nominal rating exceeding 600 volts.</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  When the enclosure integrity of such equipment is specified to be in accordance with <RID>IEEE C57.12.28</RID>
, such as for pad-mounted transformers, provide self-adhesive warning signs on the outside of 
the high voltage compartment door(s).  Sign shall be a decal and have nominal dimensions of<MET> 
178 by 255 mm</MET><ENG> 7 by 10 inches</ENG> with the legend "DANGER HIGH VOLTAGE" printed in two lines of nominal<MET>
 50 mm</MET><ENG> 2 inch</ENG> high letters.  The word "DANGER" shall be in white letters on a red background 
and the words "HIGH VOLTAGE" shall be in black letters on a white background.  Decal shall be 
Panduit No. PPSO710D72 or approved equal.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[b.  When such equipment is guarded by a fence, mount signs on the fence.  Provide metal signs 
having nominal dimensions of<MET> 355 by 255 mm</MET><ENG> 14 by 10 inches</ENG> with the legend "DANGER HIGH VOLTAGE 
KEEP OUT" printed in three lines of nominal<MET> 75 mm</MET><ENG> 3 inch</ENG> high white letters on a red and black 
field.]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4   GROUNDING AND BONDING</TTL><BRK/>
<BRK/>
<TXT><RID>UL 467</RID>.  Provide grounding and bonding as specified in Section[ <SRF>33 71 02.00 20</SRF> UNDERGROUND ELECTRICAL DISTRIBUTION][ 
<SRF>33 70 02.00 10</SRF> ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND].</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>2.5   PADLOCKS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Designer must assure that Section 08 71 00 DOOR HARDWARE is included 
and is edited to include padlocks.<BRK/>
<BRK/>
Do not use this paragraph for NAVFAC Atlantic projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide padlocks for pad-mounted equipment [and for each fence gate].  Padlocks shall be keyed [alike] [as directed 
by the Contracting Officer].  Padlocks shall comply with Section <SRF>08 71 00</SRF> DOOR HARDWARE .</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>2.6   CAST-IN-PLACE CONCRETE</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the first bracketed paragraph when project includes a concrete section 
in Division 3; otherwise, the second bracketed paragraph may be used.  Coordinate 
requirements with Section <SRF>03 31 00.00 10</SRF> CAST-IN-PLACE STRUCTURAL CONCRETE or 
Section <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE.  Use Section <SRF>03 30 00</SRF> CAST-IN-PLACE 
for Navy projects and Section <SRF>03 31 00.00 10</SRF> CAST-IN-PLACE STRUCTURAL CONCRETE 
for other projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Concrete associated with electrical work for other than encasement of underground ducts shall be<MET> 30 MPa</MET><ENG> 4000 
psi</ENG> minimum 28-day compressive strength unless specified otherwise.  All concrete shall conform to the requirements 
of Section[ <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE][ <SRF>03 31 00.00 10</SRF> CAST-IN-PLACE STRUCTURAL CONCRETE].]</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If concrete requirements are detailed and no cast-in-place section is 
to be included in the project specification, refer to Section 03 30 00 CAST-IN-PLACE 
CONCRETE or Section 03 31 00.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE and select 
such portions as needed to provide complete requirements in addition to the 
requirements below.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Shall be composed of fine aggregate, coarse aggregate, portland cement, and water so proportioned and mixed 
as to produce a plastic, workable mixture.  Fine aggregate shall be of hard, dense, durable, clean, and uncoated 
sand.  The coarse aggregate shall be reasonably well graded from<MET> 4.75 mm to 25 mm</MET><ENG> 3/16 inch to 1 inch</ENG>.  The fine 
and coarse aggregates shall be free from injurious amounts of dirt, vegetable matter, soft fragments or other 
deleterious substances.  Water shall be fresh, clean, and free from salts, alkali, organic matter, and other 
impurities.  Concrete associated with electrical work for other than encasement of underground ducts shall be<MET>
30 MPa</MET><ENG> 4000 psi</ENG> minimum 28-day compressive strength unless specified otherwise.  Slump shall not exceed<MET> 100 mm</MET><ENG>
 4 inches</ENG>.  Retempering of concrete will not be permitted.  Exposed, unformed concrete surfaces shall be given 
a smooth, wood float finish.  Concrete shall be cured for a period of not less than 7 days, and concrete made 
with high early strength portland cement shall be repaired by patching honeycombed or otherwise defective areas 
with cement mortar as directed by the Contracting Officer.  Air entrain concrete exposed to weather using an 
air-entraining admixture conforming to <RID>ASTM C 260</RID>.  Air content shall be between 4 and 6 percent.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7   SOURCE QUALITY CONTROL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use "reserves the right to" on all projects, except those for SOUTHNAVFACENGCOM.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.7.1   <SUB>Transformer Test Schedule</SUB></TTL><BRK/>
<BRK/>
<TXT>The Government [reserves the right to][will] witness tests.  Provide transformer test schedule for tests to be 
performed at the manufacturer's test facility.  Submit required test schedule and location, and notify the Contracting 
Officer 30 calendar days before scheduled test date.  Notify Contracting Officer 15 calendar days in advance 
of changes to scheduled date.</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Test Instrument Calibration</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  The manufacturer shall have a calibration program which assures that all applicable test 
instruments are maintained within rated accuracy.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  The accuracy shall be directly traceable to the National Institute of Standards and Technology.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Instrument calibration frequency schedule shall not exceed 12 months for both test floor 
instruments and leased specialty equipment.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Dated calibration labels shall be visible on all test equipment.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Calibrating standard shall be of higher accuracy than that of the instrument tested.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Keep up-to-date records that indicate dates and test results of instruments calibrated or 
tested.  For instruments calibrated by the manufacturer on a routine basis, in lieu of third 
party calibration, include the following:</ITM><BRK/>
<BRK/>
<ITM>(a) Maintain up-to-date instrument calibration instructions and procedures for each test instrument.</ITM><BRK/>
<BRK/>
<ITM>(b) Identify the third party/laboratory calibrated instrument to verify that calibrating standard 
is met.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.2   <SUB>Design Tests</SUB></TTL><BRK/>
<BRK/>
<TXT><RID>IEEE C57.12.00</RID>, and <RID>IEEE C57.12.90</RID>.  Section 5.1.2 in <RID>IEEE C57.12.80</RID> states that "design tests are made only 
on representative apparatus of basically the same design."  Submit design test reports (complete with test data, 
explanations, formulas, and results), in the same submittal package as the catalog data and drawings for[ each 
of] the specified transformer(s).  Perform design tests prior to the award of this contract.</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Tests shall be certified and signed by a registered professional engineer.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Temperature rise:  "Basically the same design" for the temperature rise test means a pad-mounted 
transformer with the same coil construction (such as wire wound primary and sheet wound secondary), the 
same kVA, the same cooling type (ONAN), the same temperature rise rating, and the same insulating liquid 
as the transformer specified.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Lightning impulse:  "Basically the same design" for the lightning impulse dielectric test means a 
pad-mounted transformer with the same BIL, the same coil construction (such as wire wound primary and 
sheet wound secondary), and a tap changer, if specified.  Design lightning impulse tests shall include 
the primary windings only of that transformer.</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  <RID>IEEE C57.12.90</RID>, paragraph 10.3 entitled "Lightning Impulse Test Procedures," and <RID>IEEE C57.98</RID>
.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  State test voltage levels.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Provide photographs of oscilloscope display waveforms or plots of digitized waveforms with 
test report.</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  Lifting and moving devices:  "Basically the same design" requirement for the lifting and moving devices 
test means a test report confirming that the lifting device being used is capable of handling the weight 
of the specified transformer in accordance with <RID>IEEE C57.12.34</RID>.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Pressure:  "Basically the same design" for the pressure test means a pad-mounted transformer with 
a tank volume within 30 percent of the tank volume of the transformer specified.</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Short circuit:  "Basically the same design" for the short circuit test means a pad-mounted transformer 
with the same kVA as the transformer specified.</LST><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7.3   <SUB>Routine and Other Tests</SUB></TTL><BRK/>
<BRK/>
<TXT><RID>IEEE C57.12.00</RID>.  Routine and other tests shall be performed by the manufacturer on[ each of] the actual transformer(s) 
prepared for this project to ensure that the design performance is maintained in production.  Submit test reports, 
by serial number and receive approval before delivery of equipment to the project site.  Required tests and testing 
sequence shall be as follows:</TXT><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Cold resistance measurements (provide reference temperature)</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Phase relation</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">c.  Ratio</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">d.  No-load losses (NLL) and excitation current</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">e.  Load losses (LL) and impedance voltage</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">f.  Dielectric</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Impulse</ITM><BRK/>
 <BRK/>
<ITM INDENT="-0.33">2.  Applied voltage</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Induced voltage</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">g.  Leak</LST><BRK/>
<BRK/>
<LST INDENT="-0.33">h.  Dissolved gas analysis (DGA)</LST><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   INSTALLATION</TTL><BRK/>
<BRK/>
<TXT>Electrical installations shall conform to <RID>IEEE C2</RID>, <RID>NFPA 70</RID>, and to the requirements specified herein.  Provide 
new equipment and materials unless indicated or specified otherwise.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2   GROUNDING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For SOUTHNAVFACENGCOM projects, delete this paragraph and its subparagraphs, 
and use optional paragraph entitled "Transformer Grounding" instead.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Where rock or other soil conditions prevent obtaining a specified ground 
value, other methods of grounding should be specified.  Where it is impractical 
to obtain the indicated ground resistance values, make every effort within reason 
to obtain ground resistance values as near as possible to the indicated values.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>NFPA 70</RID> and <RID>IEEE C2</RID>, except that grounding systems shall have a resistance to solid earth ground not exceeding 
5 ohms.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.2.1   Grounding Electrodes</TTL><BRK/>
<BRK/>
<TXT>Provide driven ground rods as specified in Section[ <SRF>33 71 02.00 20</SRF> UNDERGROUND ELECTRICAL DISTRIBUTION][ 
<SRF>33 70 02.00 10</SRF> ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND].  Connect ground conductors to the upper end of ground 
rods by exothermic weld or compression connector.  Provide compression connectors at equipment end of ground 
conductors.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.2   Pad-Mounted Transformer Grounding</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Ensure plans show the secondary neutral grounding conductor sized in 
accordance with NFPA 70 and the primary neutral grounding conductor when required.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide separate copper grounding conductors and connect them to the ground loop as indicated.  When work in 
addition to that indicated or specified is required to obtain the specified ground resistance, the provision 
of the contract covering "Changes" shall apply.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.3   Connections</TTL><BRK/>
<BRK/>
<TXT>Make joints in grounding conductors and loops by exothermic weld or compression connector.  Install exothermic 
welds and compression connectors as specified in Section[ <SRF>33 71 02.00 20</SRF> UNDERGROUND ELECTRICAL DISTRIBUTION][ 
<SRF>33 70 02.00 10</SRF> ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.4   Grounding and Bonding Equipment</TTL><BRK/>
<BRK/>
<TXT><RID>UL 467</RID>, except as indicated or specified otherwise.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT>[<TTL>3.3   TRANSFORMER GROUNDING</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For SOUTHNAVFACENGCOM projects, use this paragraph in lieu of the previous 
paragraph entitled "GROUNDING."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide a 1/0 bare copper-ground girdle around transformer.  Girdle shall be buried<MET> 305 mm</MET><ENG> one foot</ENG> deep and 
placed<MET> 915 mm</MET><ENG> 3 feet</ENG> laterally from the transformer enclosure.  Connect girdle to enclosure at two opposite places 
using 1/0 copper.  Exothermically weld joints.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.4   INSTALLATION OF EQUIPMENT AND ASSEMBLIES</TTL><BRK/>
<BRK/>
<TXT>Install and connect pad-mounted transformers furnished under this section as indicated on project drawings, the 
approved shop drawings, and as specified herein.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.4.1   Meters and Current Transformers</TTL><BRK/>
<BRK/>
<TXT><RID>NEMA C12.1</RID>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5   FIELD APPLIED PAINTING</TTL><BRK/>
<BRK/>
<TXT>Where field painting of enclosures is required to correct damage to the manufacturer's factory applied coatings, 
provide manufacturer's recommended coatings and apply in accordance with manufacturer's instructions.</TXT><BRK/>
<BRK/></SPT>
[<SPT><TTL>3.6   WARNING SIGN MOUNTING</TTL><BRK/>
<BRK/>
<TXT>Provide the number of signs required to be readable from each accessible side, but space the signs a maximum 
of<MET> 9 meters</MET><ENG> 30 feet</ENG> apart.</TXT><BRK/>
<BRK/></SPT>
]<SPT><TTL>3.7   FOUNDATION FOR EQUIPMENT AND ASSEMBLIES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Mounting slab connections may have to be given in detail depending on 
the requirements for the seismic zone in which the requirement is located.  
Include construction requirements for concrete slab only if slab is not detailed 
in drawings.  At some activities, curbs or raised edges may also be required 
around liquid filled transformer.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Mount transformer on concrete slab.  Unless otherwise indicated, the slab shall be at least<MET> 200 mm</MET><ENG> 8 inches</ENG> thick, 
reinforced with a<MET> 152 mm x 152 mm - MW19 by MW19 (6 by 6 - W2.9 by W2.9)</MET><ENG> 6 by 6 - W2.9 by W2.9</ENG> mesh, placed uniformly<MET>
 100 mm</MET><ENG> 4 inches</ENG> from the top of the slab.  Place the slab on a<MET> 150 mm</MET><ENG> 6 inch</ENG> thick, well-compacted gravel base.  
Top of concrete slab shall be approximately<MET> 100 mm</MET><ENG> 4 inches</ENG> above finished grade with gradual slope for drainage.  
Edges above grade shall have<MET> 15 mm</MET><ENG> 1/2 inch</ENG> chamfer.  Slab shall be of adequate size to project at least<MET> 200 
mm</MET><ENG> 8 inches</ENG> beyond the equipment.</TXT><BRK/>
<BRK/>
<TXT>Stub up conduits, with bushings,<MET> 50 mm</MET><ENG> 2 inches</ENG> into cable wells in the concrete pad.  Coordinate dimensions 
of cable wells with transformer cable training areas.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.7.1   Cast-In-Place Concrete</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use the first bracketed option when project includes a concrete section 
in Division 3; otherwise, the second bracketed option may be used.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Cast-in-place concrete work shall conform to the requirements of[ Section[ <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE][ 
<SRF>03 31 00.00 10</SRF> CAST-IN-PLACE STRUCTURAL CONCRETE]][ <RID>ACI 318M</RID>].</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>3.7.2   Sealing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Require sealing of holes (windows) in the concrete pad if rodent intrusion 
is a problem.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>When the installation is complete, the Contractor shall seal all conduit and other entries into the equipment 
enclosure with an approved sealing compound.  Seals shall be of sufficient strength and durability to protect 
all energized live parts of the equipment from rodents, insects, or other foreign matter.</TXT><BRK/>
<BRK/>
]</SPT></SPT><SPT><TTL>3.8   FIELD QUALITY CONTROL</TTL><BRK/>
<BRK/>
<SPT><TTL>3.8.1   Performance of <SUB>Acceptance Checks and Tests</SUB></TTL><BRK/>
<BRK/>
<TXT><TST>Perform in accordance with the manufacturer's recommendations</TST> and include the following visual and mechanical 
inspections and electrical tests, performed in accordance with <RID>NETA ATS</RID>.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.8.1.1   Pad-Mounted Transformers</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Visual and mechanical inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Compare equipment nameplate information with specifications and approved shop drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Inspect physical and mechanical condition.  Check for damaged or cracked insulators and 
leaks.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, 
verifying tightness of accessible bolted electrical connections by calibrated torque-wrench 
method, or performing thermographic survey.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Verify correct liquid level in tanks.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Perform specific inspections and mechanical tests as recommended by manufacturer.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Verify correct equipment grounding.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">[7.  Verify the presence of transformer surge arresters.]</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Electrical tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Perform resistance measurements through all bolted connections with low-resistance ohmmeter.</ITM><BRK/>
              <BRK/>
<ITM INDENT="-0.33">2.  Verify that the tap-changer is set at specified ratio.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Verify proper secondary voltage phase-to-phase and phase-to-neutral after energization and 
prior to loading.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.1.2   Current Transformers</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Visual and mechanical inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Compare equipment nameplate data with specifications and approved shop drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Inspect physical and mechanical condition.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Verify correct connection.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Verify that adequate clearances exist between primary and secondary circuit.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">5.  Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, 
verifying tightness of accessible bolted electrical connections by calibrated torque-wrench 
method, or performing thermographic survey.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">6.  Verify that required grounding and shorting connections provide good contact.</ITM><BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Electrical tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Perform resistance measurements through all bolted connections with low-resistance ohmmeter, 
if applicable.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Perform insulation-resistance test.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Perform a polarity test.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">4.  Perform a ratio-verification test.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.1.3   Watthour Meter</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">[a.  Visual and mechanical inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Compare equipment nameplate data with specifications and approved shop drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Inspect physical and mechanical condition.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Verify tightness of electrical connections.</ITM>]<BRK/>
<BRK/>
<LST INDENT="-0.33">b.  Electrical tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Calibrate watthour meters according to manufacturer's published data.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Verify that correct multiplier has been placed on face of meter, where applicable</ITM>.<BRK/>
<BRK/>
<ITM INDENT="-0.33">3.  Verify that current transformer secondary circuits are intact.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.1.4   Grounding System</TTL><BRK/>
<BRK/>
<LST INDENT="-0.33">a.  Visual and mechanical inspection</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Inspect ground system for compliance with contract plans and specifications.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For SOUTHNAVFACENGCOM projects, delete "Electrical tests" below.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<LST INDENT="-0.33">b.  Electrical tests</LST><BRK/>
<BRK/>
<ITM INDENT="-0.33">1.  Perform ground-impedance measurements utilizing the fall-of-potential method.  On systems 
consisting of interconnected ground rods, perform tests after interconnections are complete.  
On systems consisting of a single ground rod perform tests before any wire is connected.  Take 
measurements in normally dry weather, not less than 48 hours after rainfall.  Use a portable 
ground testing megger in accordance with manufacturer's instructions to test each ground or 
group of grounds.  Equip the instrument with a meter reading directly in ohms or fractions thereof 
to indicate the ground value of the ground rod or grounding systems under test.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">2.  Submit the measured ground resistance of each ground rod and grounding system, indicating 
the location of the rod and grounding system.  Include the test method and test setup (i.e., 
pin location) used to determine ground resistance and soil conditions at the time the measurements 
were made.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.8.2   Follow-Up Verification</TTL><BRK/>
<BRK/>
<TXT><TST>Upon completion of acceptance checks and tests, the Contractor shall show by demonstration in service that circuits 
and devices are in good operating condition and properly performing the intended function.</TST>  As an exception to 
requirements stated elsewhere in the contract, the Contracting Officer <NED/>shall be given 5 working days advance 
notice of the dates and times of checking and testing.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT>    <END/><BRK/></SEC>