<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA      UFGS-26 42 13.00 20 (April 2006)<BRK/>
                                    ------------------------------<BRK/>
Preparing Activity:  <PRA>NAVFAC</PRA>         Replacing without change<BRK/>
                                    UFGS-13110N (September 2000)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 26 42 13.00 20</SCN><BRK/>
<BRK/>
<STL>CATHODIC PROTECTION BY GALVANIC ANODES</STL><BRK/>
<DTE>04/06</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>underground piping 
and buried or submerged structure cathodic protection systems using galvanic 
anodes systems</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The requirements for the cathodic protection systems should be determined 
by a corrosion engineer following the criteria, design, and installation recommendations 
included in the National Association of Corrosion Engineers (NACE) Standard 
SP0169 Control of External Corrosion on Underground or Submerged Metallic Piping 
Systems and others listed in the specification.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The following information should be on the drawings:</NPR><BRK/>
<BRK/>
<NPR>1. Location of all underground pipes and structures.</NPR><BRK/>
<BRK/>
<NPR>2. Locations of all anodes and test stations.</NPR><BRK/>
<BRK/>
<NPR>3. Locations of all flanges and unions.</NPR><BRK/>
<BRK/>
<NPR>4. Installation details for anodes and test stations.</NPR><BRK/>
<BRK/>
<NPR>5. Location of equipment.</NPR><BRK/>
<BRK/>
<NPR>6. Single-line diagrams elevations, limiting dimensions, and equipment ratings 
which are not covered in the specification.</NPR><BRK/>
<BRK/>
<NPR>7. Remote indicating or control requirements.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
 <BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
 <BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ASME INTERNATIONAL (ASME)</ORG><BRK/><BRK/><RID>ASME B1.1</RID><RTL>(2003; R 2008) Unified Inch Screw Threads (UN and UNR Thread Form)</RTL><BRK/><BRK/><RID>ASME B1.20.1</RID><RTL>(1983; R 2006) Pipe Threads, General Purpose (Inch)</RTL><BRK/><BRK/><RID>ASME B16.21</RID><RTL>(2005) Nonmetallic Flat Gaskets for Pipe Flanges</RTL><BRK/><BRK/><RID>ASME B16.25</RID><RTL>(2007) Standard for Buttwelding Ends</RTL><BRK/><BRK/><RID>ASME B16.39</RID><RTL>(1998; R 2006) Standard for Malleable Iron Threaded Pipe Unions; Classes 150, 250, and 300</RTL><BRK/><BRK/><RID>ASME B16.5</RID><RTL>(2003) Standard for Pipe Flanges and Flanged Fittings:  NPS 1/2 Through NPS 24</RTL><BRK/><BRK/><RID>ASME B18.2.1</RID><RTL>(1996; Addenda A 1999; Errata 2003; R 2005) Square and Hex Bolts and Screws (Inch Series)</RTL><BRK/><BRK/><RID>ASME B18.2.2</RID><RTL>(1987; R 2005) Standard for Square and Hex Nuts</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM A 194/A 194M</RID><RTL>(2008b) Standard Specification for Carbon and Alloy Steel Nuts for Bolts for High-Pressure or High-Temperature Service, or Both</RTL><BRK/><BRK/><RID>ASTM A 307</RID><RTL>(2007b) Standard Specification for Carbon Steel Bolts and Studs, 60 000 PSI Tensile Strength</RTL><BRK/><BRK/><RID>ASTM B 3</RID><RTL>(2001; R 2007) Standard Specification for Soft or Annealed Copper Wire</RTL><BRK/><BRK/><RID>ASTM B 418</RID><RTL>(2008) Standard Specification for Cast and Wrought Galvanic Zinc Anodes</RTL><BRK/><BRK/><RID>ASTM B 8</RID><RTL>(2004) Standard Specification for Concentric-Lay-Stranded Copper Conductors, Hard, Medium-Hard, or Soft</RTL><BRK/><BRK/><RID>ASTM B 843</RID><RTL>(2007) Standard Specification for Magnesium Alloy Anodes for Cathodic Protection</RTL><BRK/><BRK/><RID>ASTM C 94/C 94M</RID><RTL>(2007) Standard Specification for Ready-Mixed Concrete</RTL><BRK/><BRK/><RID>ASTM D 1248</RID><RTL>(2005) Standard Specification for Polyethylene Plastics Extrusion Materials for Wire and Cable</RTL><BRK/><BRK/><RID>ASTM D 2028</RID><RTL>(1997; R 2004) Cutback Asphalt (Rapid-Curing Type)</RTL><BRK/><BRK/><RID>ASTM D 3381</RID><RTL>(2005) Viscosity-Graded Asphalt Cement for Use in Pavement Construction</RTL><BRK/><BRK/><RID>ASTM F 1182</RID><RTL>(2007) Anodes, Sacrificial Zinc Alloy</RTL><BRK/><BRK/></REF><REF><ORG>INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)</ORG><BRK/><BRK/><RID>IEEE C2</RID><RTL>(2007; Errata 2007; INT 2008) National Electrical Safety Code</RTL><BRK/><BRK/></REF><REF><ORG>NACE INTERNATIONAL (NACE)</ORG><BRK/><BRK/><RID>NACE RP0285</RID><RTL>(2002) Corrosion Control of Underground Storage Tank Systems by Cathodic Protection</RTL><BRK/><BRK/><RID>NACE SP0169</RID><RTL>(2007) Control of External Corrosion on Underground or Submerged Metallic Piping Systems</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)</ORG><BRK/><BRK/><RID>NEMA C119.1</RID><RTL>(2006) Sealed Insulated Underground Connector Systems Rated 600 Volts</RTL><BRK/><BRK/><RID>NEMA ICS 6</RID><RTL>(1993; R 2006) Standard for Industrial Controls and Systems Enclosures</RTL><BRK/><BRK/><RID>NEMA RN 1</RID><RTL>(2005) Standard for Polyvinyl Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit</RTL><BRK/><BRK/><RID>NEMA TC 2</RID><RTL>(2003) Standard for Electrical Polyvinyl Chloride (PVC) Tubing and Conduit</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)</ORG><BRK/><BRK/><RID>NFPA 70</RID><RTL>(2007; AMD 1 2008) National Electrical Code - 2008 Edition</RTL><BRK/><BRK/></REF><REF><ORG>U.S. DEPARTMENT OF DEFENSE (DOD)</ORG><BRK/><BRK/><RID>MIL-I-1361</RID><RTL>(Rev C; Notice 1) Instrument Auxiliaries, Electrical Measuring:  Shunts, Resistors and Transformers</RTL><BRK/><BRK/></REF><REF><ORG>UNDERWRITERS LABORATORIES (UL)</ORG><BRK/><BRK/><RID>UL 44</RID><RTL>(2005; Rev thru Nov 2005) Thermoset-Insulated Wires and Cables</RTL><BRK/><BRK/><RID>UL 486A-486B</RID><RTL>(2003; Rev thru Aug 2006) Standard for Wire Connectors</RTL><BRK/><BRK/><RID>UL 510</RID><RTL>(2005; Rev thru Aug 2005) Polyvinyl Chloride, Polyethylene, and Rubber Insulating Tape</RTL><BRK/><BRK/><RID>UL 514A</RID><RTL>(2004; Rev thru Aug 2007) Standard for Metallic Outlet Boxes</RTL><BRK/><BRK/><RID>UL 514B</RID><RTL>(2004; Rev thru Aug 2007) Standard for Conduit, Tubing and Cable Fittings</RTL><BRK/><BRK/><RID>UL 6</RID><RTL>(2007) Standard for Electrical Rigid Metal Conduit-Steel</RTL><BRK/><BRK/><RID>UL 83</RID><RTL>(20086) Standard for Thermoplastic-Insulated Wires and Cables</RTL><BRK/><BRK/></REF></SPT><SPT>[<TTL>1.2   RELATED REQUIREMENTS</TTL><BRK/>
<BRK/>
<TXT>Sections <SRF>26 00 00.00 20</SRF> BASIC ELECTRICAL MATERIALS AND METHODS, [<SRF>33 71 02.00 20</SRF> UNDERGROUND UNDERGROUND TRANSMISSION 
AND DISTRIBUTION], and, [<SRF>26 20 00</SRF> INTERIOR DISTRIBUTION SYSTEM], apply to this section except as modified herein.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>1.3   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  The following shall 
be submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Insulating flange sets</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Anode junction boxes, bonding boxes and test stations</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Joint bonds</SUB></ITM><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Anodes</SUB>; <SUB>G</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Anode junction boxes, bonding boxes, and test stations</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Insulating flange sets</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Dielectric unions</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Wires</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Cable and wire</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Casings, insulation, and seals</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Shunt resistors</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Permanent reference electrodes</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Qualifications of Corrosion Engineer</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-10 Operation and Maintenance Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Cathodic Protection System</SUB>, Data Package 5[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Submit in accordance with Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE DATA.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-11, Closeout Submittals</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Initial Cathodic Protection System Field Test Report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>One Year Warranty Period Cathodic Protection System Field Test Report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Final Cathodic Protection System Field Test Report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4   Services of Corrosion Engineer</TTL><BRK/>
<BRK/>
<TXT>The Contractor shall obtain the services of a corrosion engineer to supervise, inspect and test the installation 
of the cathodic protection system(s).  Corrosion Engineer refers to a registered professional engineer with certification 
of licensing that includes education and experience in cathodic protection of buried or submerged metal structures, 
or a person accredited or certified by the National Association of Corrosion Engineers at the level of Corrosion 
Specialist or Cathodic Protection Specialist.  Such a person shall have not less than [three] [five] [_____] 
years experience in the cathodic protection of underground [storage tanks] or submerged structures.  The contractor 
shall submit evidence of the <SUB>qualifications of corrosion engineer</SUB> to the Contracting Officer for review and approval.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   <SUB>ANODES</SUB></TTL><BRK/>
<BRK/>
<SPT>[<TTL>2.1.1   Magnesium</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The chemical composition listed is for high potential anodes in accordance 
with ASTM B 843. Should standard magnesium anodes be considered suitable, provide 
appropriate chemical composition.  Specify chemical composition which will provide 
adequate and economical service.  Three different grades are generally available.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[<RID>ASTM B 843</RID>] Chemical composition as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">Aluminum          [0.01] [_____] percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Manganese         [0.5-1.3] [_____] percent</ITM><BRK/>
<ITM INDENT="-0.33">Zinc              [ -0- ] [_____] percent [maximum]</ITM><BRK/>
<ITM INDENT="-0.33">Silicon           [0.05] [_____] percent [maximum]</ITM><BRK/>
<ITM INDENT="-0.33">Copper            [0.02] [_____] percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Nickel            [0.001] [_____] percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Iron              [0.03] [_____] percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Other Impurities  0.05 percent each, 0.3 percent maximum total</ITM><BRK/>
<ITM INDENT="-0.33">Magnesium         Remainder</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Bare anode weight: <MET> [4.1] [7.72] [14.53] [_____] kg</MET><ENG> [[9] [17] [32] [_____] pounds]</ENG> [not 
including core].</ITM><BRK/>
 <BRK/>
]</SPT><SPT>[<TTL>2.1.2   [Cast] [Wrought] Zinc</TTL><BRK/>
<BRK/>
<TXT>[<RID>ASTM B 418</RID>, Type [I] [II].]  [<RID>ASTM F 1182</RID>.]  Bare anode weight: <MET> [2.2] [13.62] [_____] kg</MET><ENG> [5] [30] [_____] pounds</ENG>
 [not including core].</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.1.3   Aluminum</TTL><BRK/>
<BRK/>
<TXT>Chemical composition as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">Zinc      [4.5] [_____] percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Indium    [0.02] [_____] percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Silicon   [0.01] [_____] percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Aluminum  Remainder</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">Anode Weight<MET> [_____] kg</MET><ENG> [_____] pounds</ENG> not including core.</ITM><BRK/>
<BRK/>
]</SPT><SPT><TTL>2.1.4   Anode Wires and Core</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.4.1   Anode Lead <SUB>Wires</SUB></TTL><BRK/>
<BRK/>
<TXT>[<RID>UL 83</RID>, Type [TW] [THWN] [THHN]] [ASTM D 1248, Type HMWPE (High Molecular Weight Polyethylene)] [<RID>UL 44</RID>, Type 
RHW], [solid] [stranded] copper conductors, not less than [No. 12] [_____] AWG,<MET> [3050] [6100] [_____] mm</MET><ENG> [10] 
[20] [_____] feet</ENG> long, [of sufficient length to extend to the accompanying junction box without splicing].  
Anode lead wire shall be factory installed.  [Silver solder the lead wire to the anode core, and seal the soldered 
connection and recessed end of the anode with an [asphaltic] [epoxy] dielectric sealing compound.]  [Silver solder 
the lead wire to the protruding anode core, and completely seal the soldered connection with an [asphaltic] [epoxy] 
dielectric material.]  Dielectric material shall extend past the connection and cover the lead wire insulation 
by not less than<MET> 15 mm</MET><ENG> 1/2 inch</ENG>.  [Cover the connection with heat shrinkable tubing.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4.2   Anode Core</TTL><BRK/>
<BRK/>
<TXT>Iron [galvanized steel] rod [pipe] [strap] [_____],<MET> [3] [6.35] [12.7] mm diameter [_____] x [_____]</MET><ENG> [1/8] [1/4] 
[1/2] inch diameter [_____] x [_____]</ENG>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.1.5   Anode Backfill</TTL><BRK/>
<BRK/>
<TXT>Chemical composition as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">Hydrated gypsum -     75 percent</ITM><BRK/>
<ITM INDENT="-0.33">Bentonite clay  -     20 percent</ITM><BRK/>
<ITM INDENT="-0.33">Sodium sulfate  -      5 percent</ITM><BRK/>
<BRK/>
<TXT>Provide granular backfill with 100 percent passing through a<MET> 150 micrometers</MET><ENG> 100 mesh</ENG> screen.  Provide prepackaged 
anode in a cloth bag containing the anode and backfill.  Center the anode in the firmly packed backfill using 
spacers.  Overall dimensions of the bagged<MET> [7.72] [14.53] [_____] kg</MET><ENG> [17] [32] [_____] pound</ENG> anode shall be<MET> [165 
by 432 mm] [203 by 535 mm] [_____ by _____ mm]</MET><ENG> [6.5 by 17 inches] [8 by 21 inches] [_____ by _____ inches]</ENG> with 
a total minimum weight of<MET> [20.4] [33.6] [_____] kg</MET><ENG> [45] [74] [_____] pounds</ENG>nominal.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2   <SUB>ANODE JUNCTION BOXES, BONDING BOXES, AND TEST STATIONS</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Flush Mounted Type</TTL><BRK/>
<BRK/>
<TXT><RID>NEMA ICS 6</RID>.  Metallic or non-metallic with terminal board, [5] [8] [_____] terminal posts [and lockable lid].  
A non-metallic enclosure shall be molded of glass filled polycarbonate and urethane coated or ABS plastic [and 
mounted on a<MET> 500 mm</MET><ENG> 18 inch</ENG> length of PVC conduit].  The unit shall be of standard design, manufactured for use 
as a cathodic protection test station, complete with cover, terminal board, shunts, and brass or Type [304] [316] 
stainless steel hardware.  The terminal board shall be removable for easy access to wires.  [Provide traffic 
valve box capable of withstanding [H-20] [_____] traffic loads.]  The cover shall have a cast in legend "CP TEST."</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2   Post Top Mounted Type</TTL><BRK/>
<BRK/>
<TXT><RID>NEMA ICS 6</RID>.  Metallic or non-metallic with terminal board, [5] [8] [_____] terminal posts and lockable lid.  
A non-metallic enclosure shall be high impact strength molded plastic.  The unit shall be of standard design, 
manufactured for use as a cathodic protection test station, complete with cover, terminal board, shunts, and 
brass or Type [304] [316] stainless steel hardware.  The terminal board shall be removable for easy access to 
wires.  The test station shall be mounted atop<MET> 1830 mm</MET><ENG> 6 foot</ENG> long polyethylene conduit with anchor.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3   Wall Mounted Type</TTL><BRK/>
<BRK/>
<TXT><RID>NEMA ICS 6</RID>, Type [3R] [4X] [_____] enclosure with [clamped cover] [Type [304] [316] stainless steel hinges and 
[clamped] [latched] cover] [and padlocked hasp].  Enclosure shall be of [galvanized steel] [painted steel] [aluminum] 
[fiberglass] [non-metallic] construction with terminal board and labeled with nameplate.  Provide nameplate in 
accordance with Section <SRF>26 00 00.00 20</SRF> GENERAL ELECTRICAL MATERIALS AND METHODS.  Enclosure mounting posts shall 
be [galvanized steel pipe,schedule [40] [80] [_____]], [wood post, full length pressure treated with pentachlorophenol] 
[as indicated].  Mount enclosure<MET> 1066 mm</MET><ENG> 42 inches</ENG> above finished grade [as indicated].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.4   Terminal Boards</TTL><BRK/>
<BRK/>
<TXT>Provide terminal boards for anode junction boxes, bonding boxes, and test stations made of phenolic plastic<MET> [3] 
[6] [_____] mm</MET><ENG> [1/8] [1/4] [_____] inch</ENG> thick with dimensions as indicated.  Insulated terminal boards shall 
have the required number of terminals (one terminal required for each conductor).  Install solderless copper 
lugs and copper buss bars, shunts, and variable resistors on the terminal board as indicated.  Test station terminal 
connections shall be permanently tagged to identify each termination of conductors (e.g. identify the conductors 
connected to the protected structure, anodes, and reference electrodes).  Conductors shall be permanently identified 
by means of plastic or metal tags, or plastic sleeves to indicate termination.  [Each conductor shall be color 
coded as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">Anode lead wire - black</ITM><BRK/>
<ITM INDENT="-0.33">Structure lead wire - white</ITM><BRK/>
<ITM INDENT="-0.33">Reference electrode lead wire - red]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.5   <SUB>Shunt Resistors</SUB></TTL><BRK/>
<BRK/>
<TXT>[<RID>MIL-I-1361</RID>.]  [0.01] [______] ohm, [6] [______] ampere, accuracy plus or minus one percent, manganin wire type.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.6   Pavement Insert</TTL><BRK/>
<BRK/>
<TXT>Pavement insert shall be a non-metallic flush type test station without terminal board, and shall allow a copper-copper 
sulfate reference electrode to contact the electrolyte beneath the pavement surface.  [Provide traffic valve 
box capable of withstanding [H-20] [_____] traffic loads.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.7   Cast-In-Place Concrete</TTL><BRK/>
<BRK/>
<TXT>Flush mount type test stations, bonding boxes, and anode junction boxes shall be centered in a<MET> 460 x 460 x 102 
mm</MET><ENG> 18 x 18 x 4 inch</ENG> concrete slab.  Concrete shall be<MET> 20 Mpa</MET><ENG> 3000 psi</ENG> minimum ultimate 28-day compressive strength 
with<MET> 25 mm</MET><ENG> one inch</ENG> minimum aggregate conforming to [<RID>ASTM C 94/C 94M</RID>] [Section <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE].</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3   PERMANENT REFERENCE ELECTRODES</TTL><BRK/>
<BRK/>
<TXT><SUB>Permanent reference electrodes</SUB> shall be [copper copper-sulfate] [silver silver-chloride] [zinc] specifically 
manufactured for [underground] [marine] use,<MET> [32] [_____] mm</MET><ENG> [1 1/4] [_____] inch</ENG> diameter, by<MET> [255] [_____] 
mm</MET><ENG> [10] [_____] inches</ENG> long, [plastic [_____] tube with an ion trap to minimize contamination of the cell] [, 
and a minimum surface sensing area of <MET>[____] square centimeters</MET><ENG>[______] square inches</ENG>].  [The cell shall be prepackaged 
by the manufacturer with a backfill material as recommended by the manufacturer.]  Provide cells with No. [10] 
[12] [_____] AWG, [RHW] [THHN] [____] cable of sufficient length to extend to the [test station] [junction box] 
without splicing.  Reference electrodes shall have a minimum 15 year life, stability of plus or minus 5 millivolts 
under 3 microamp load, and an initial accuracy of plus or minus 10 millivolts referenced to a calibrated portable 
reference electrode.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4   <SUB>CABLE AND WIRE</SUB> OTHER THAN ANODE LEAD WIRES</TTL><BRK/>
<BRK/>
<TXT>[<RID>UL 83</RID>, Type [TW] [THWN] [THHN]] [<RID>ASTM D 1248</RID>, Type HMWPE (High Molecular Weight Polyethylene)], [<RID>UL 44</RID>, Type 
RHW], [solid] [stranded] copper conductor, color coded and sized (based on AWG).  Copper wires shall conform 
to <RID>ASTM B 3</RID> and <RID>ASTM B 8</RID>.  Lead wires terminating at a junction box or test station shall have a cable identification 
tag.  [Do not use bare copper wire for joint continuity bonds.]  Refer to paragraph 2.1.4 [_____] for anode lead 
wires.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5   CABLE AND WIRE IDENTIFICATION TAGS</TTL><BRK/>
<BRK/>
<TXT>[Laminated plastic material with black letters on a yellow background] [[Brass] [Stainless steel] material with 
engraved letters].  Print letters and numbers a minimum of<MET> 5 mm</MET><ENG> 3/16 inch</ENG> in size.  Provide identifier legend 
[in accordance with the drawings] [_____].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6   WIRE CONNECTORS</TTL><BRK/>
<BRK/>
<TXT><RID>UL 486A-486B</RID>.  [_____] [Solderless copper lugs]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.7   UNDERGROUND SPLICES</TTL><BRK/>
<BRK/>
<TXT>Provide splices with a compression connector on the conductors, and insulation and waterproofing using one of 
the following methods which are suitable for continuous submersion in water and comply with <RID>NEMA C119.1</RID>.</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Provide cast-type splice insulation by means of molded casting process employing a thermosetting 
epoxy resin insulating material applied by a gravity poured method or pressure injected method.  
Provide component materials of the resin insulation in a packaged form ready for convenient 
mixing without removing from the package.</ITM><BRK/>
<BRK/>
<ITM>(1) Gravity poured method shall employ materials and equipment contained in and approved commercial 
splicing kit which includes a mold suitable for the cables to be spliced.  When the mold is 
in place around the joined conductors, prepare the resin mix and pour into the mold.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Provide [heavy wall] heat shrinkable splice insulation by means of a thermoplastic adhesive 
sealant material which shall be applied by a clean burning propane gas torch.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8   CONDUIT</TTL><BRK/>
<BRK/>
<TXT>[<RID>UL 6</RID>, rigid galvanized steel], [Outlet boxes: <RID>UL 514A</RID> and fittings <RID>UL 514B</RID>, threaded hubs].  [Metallic conduit 
and fittings to be PVC coated in accordance with <RID>NEMA RN 1</RID>, Type A40], [<RID>NEMA TC 2</RID>, Type EPC-40-PVC].</TXT><BRK/>
<BRK/>
<SPT><TTL>2.8.1   Buried Cable Warning and Identification Tape</TTL><BRK/>
<BRK/>
<TXT>Polyethylene tape, manufactured for warning and identification of buried cable and conduit.  Tape shall be<MET> [75] 
[_____] mm</MET><ENG> [3] [_____] inches</ENG> wide, [Yellow] [_____] in color and read "Caution Buried Cable Below" or similar.  
Color and lettering shall be permanent and unaffected by moisture or other substances in backfill materials.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.9   INSULATING TAPE</TTL><BRK/>
<BRK/>
<TXT><RID>UL 510</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.10   <SUB>INSULATING FLANGE SETS</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  On projects having piping installed by Division 2, SITEWORK and/or Division 
15, MECHANICAL, coordinate the requirements for flanges and unions with the 
appropriate section(s).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide full-faced gaskets, insulating sleeves and washers, and steel washers.  Provide insulating flange sets 
rated for operation at the rated pressure and temperature.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.10.1   Gaskets</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Do not use asbestos materials.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASME B16.21</RID>.  [Neoprene faced phenolic] [Laminated phenolic] material for operation at<MET> [_____] KPa, [232] [_____] 
degrees C</MET><ENG> [_____] psi, [450] [_____] degrees F</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.10.2   Insulating Washers and Sleeves</TTL><BRK/>
<BRK/>
<TXT>Two sets<MET> 3 mm</MET><ENG> 1/8 inch</ENG> [laminated phenolic] [_____] for operation at<MET> [232] [_____] degrees C</MET><ENG> [450] [_____] degrees 
F</ENG>.  Insulating washers shall fit within the bolt facing on the flange over the outside of the fabric reinforced 
phenolic sleeve.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.10.3   Washers</TTL><BRK/>
<BRK/>
<TXT>Steel, cadmium plated, to fit within the bolt facing on the flange.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.11   STEEL FLANGES AND BOLTING</TTL><BRK/>
<BRK/>
<SPT><TTL>2.11.1   Steel Flanges</TTL><BRK/>
<BRK/>
<TXT><RID>ASME B16.5</RID>,<MET> [668 N] [1335 N]</MET><ENG> [150 lb.] [300 lb.]</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.11.2   Bolting</TTL><BRK/>
<BRK/>
<TXT><RID>ASTM A 307</RID>, Grade B for bolts; <RID>ASTM A 194/A 194M</RID>, Grade 2 for nuts.  Dimensions:  <RID>ASME B18.2.1</RID> for bolts, <RID>ASME B18.2.2</RID>
 for nuts.  Threads: <RID>ASME B1.1</RID>, Class 2A fit for bolts, Class 2B fit for nuts.  Bolts shall extend completely 
through the nuts and may have reduced shanks of a diameter not less than the diameter at the roof of threads.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.12   <SUB>DIELECTRIC UNIONS</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  On projects having piping installed by Division 2, SITEWORK and/or Division 
15, MECHANICAL, coordinate the requirements for flanges and unions with the 
appropriate section(s).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASME B16.39</RID>, Class [1] [2] for dimensional, strength, and pressure requirements.  Insulation barrier shall limit 
galvanic current to one percent of the short-circuit current in a corresponding metallic joint.  Provide insulating 
material impervious to [water] [oil] [gas].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.13   EXOTHERMIC WELD KITS</TTL><BRK/>
<BRK/>
<TXT>Exothermic weld kits specifically designed by the manufacturer for welding the types of materials and shapes 
provided.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.14   ELECTRICALLY INSULATING COATINGS</TTL><BRK/>
<BRK/>
<TXT>[Heat-shrinkable tape] [Conformable water tight sealant having dielectric strength not less than 15 kV for a<MET> 
3 mm</MET><ENG> 1/8 inch</ENG> thick layer].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.15   CASING INSULATORS AND SEALS</TTL><BRK/>
<BRK/>
<TXT>Casing insulators shall have a minimum<MET> [305] [_____] mm</MET><ENG> [12] [_____] inch</ENG> band width, [constructed of heat fused 
plastic coated steel] [_____] and multi-segmented to attach firmly around the pipe.  Casing end seals shall be 
S-shaped rubber seals with stainless steel straps.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   INSTALLATION</TTL><BRK/>
<BRK/>
<TXT>[<RID>NFPA 70</RID>] [<RID>IEEE C2</RID>].</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.1   Anodes and Lead Wires</TTL><BRK/>
<BRK/>
<TXT>Provide [each] anode and lead wires as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Excavate hole to a minimum<MET> 75 mm</MET><ENG> 3 inches</ENG> larger than the packaged anode diameter,<MET> [_____] 
mm</MET><ENG> [_____] feet</ENG> deep.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Excavate lead wire trench to<MET> [610] [_____] mm</MET><ENG> [24] [_____] inches</ENG> deep,<MET> [_____] mm</MET><ENG> [_____] 
inches</ENG> wide.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Do not lift or support anode by the lead wire.  Where applicable, remove manufacturer's 
plastic wrap/bag from the anode.  Exercise care to preclude damaging the cloth bag and the lead 
wire insulation.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Center the packaged anode in the hole with native soil in layers not exceeding<MET> 150 millimeters</MET><ENG>
 6 inches</ENG>.  Hand tamp each layer to remove voids taking care not to strike the anode lead wire.  
When the backfill is<MET> 150 millimeters</MET><ENG> 6 inches</ENG> above the top of the anode, pour not less than 
ten gallons of water into the hole to saturate the anode backfill and surrounding soil.  Anodes 
shall not be backfilled prior to inspection and approval by the Contracting Officer.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Cover the lead wire trench bottom with a<MET> 75 mm</MET><ENG> 3 inch</ENG> layer of sand or stone free earth.  
Center wire on the backfill layer, do not stretch or kink the conductor.  Place backfill over 
wire in layers not exceeding<MET> 150 mm</MET><ENG> six inches</ENG> deep, compact each layer thoroughly.  Do not 
place tree roots, wood scrap, vegetable matter and refuse in backfill.  Place cable warning 
tape within <MET> [450] [_____] mm</MET><ENG> [18] [_____] inches</ENG> of finished grade, above cable and conduit.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Connect anode lead wire(s) [to the test station terminal board(s)] [directly to the protected 
structure(s) by use of exothermic weld kit(s).  Clean the structure surface by scraping, filing 
or wire brushing to produce a clean, bright surface.  Weld connections using exothermic kit(s) 
in accordance with the kit manufacturer's instructions.  Check and verify adherence of the bond 
to the substrate for mechanical integrity by striking the weld with a<MET> 908 gram</MET><ENG> 2 pound</ENG> hammer.  
Cover connections with an electrically insulating coating [which is compatible with the existing 
coating on the structure]].  Allow sufficient slack in the lead wire to compensate for movement 
during backfilling operation.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Connect structure leads to structure by use of exothermic weld kit(s).  Clean the structure 
surface by scraping, filing or wire brushing to produce a clean, bright surface.  [Weld connections 
using exothermic kit(s) in accordance with the kit manufacturer's instructions.]  Conform to 
the safety precautions of paragraph 3.1.2 [_____] when welding around fuel facilities.  Check 
and verify adherence of the bond to the substrate for mechanical integrity by striking the weld 
with a<MET> 908 gram</MET><ENG> 2 pound</ENG> hammer.  Cover connections with an electrically insulating coating [which 
is compatible with the existing coating on the structure.]  Connect structure lead wires to 
the test station terminal board(s).</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2   Safety Precautions For Welding Around Fuel Facilities</TTL><BRK/>
<BRK/>
<TXT>Contractor shall take proper safety precautions prior to and during welding to live fuel pipelines [tanks].  
Contractor shall notify the activity Fuel Office via the Contracting Officer a minimum of three days before performing 
exothermic welding to live fuel lines.  Exothermic welding shall be conducted with fuel flowing through the pipeline 
to eliminate vapor spaces within the pipe and to dissipate the heat on the pipe.  Exothermic weld charges for 
connections to fuel lines shall be limited to a maximum 15 gram charge to prevent burning through the pipe wall.  
Exothermic weld connections shall be spaced a minimum of 6 inches apart.  In the event of an unsucceessful weld, 
the new weld location shall be located a minimum of 6 inches from the unsuccessful weld and any other existing 
welds.  Contractor shall obtain the services of a certified Marine Chemist or Certified Industrial Hygienist 
[to monitor the construction site during exothermic welding work and certify that the area is free of flammable 
vapors and otherwise safe for work.] [to approve the contractor's exothermic welding safety procedures.  Results 
of this consultation shall be included in the Contractor's Daily Report.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3   Anode Junction Boxes</TTL><BRK/>
<BRK/>
<TXT>Provide junction boxes and mark each of the wires terminating in each box.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.4   Bonding Boxes</TTL><BRK/>
<BRK/>
<TXT>Provide structure bonding boxes in locations [as indicated] [where the protected structure crosses or comes into 
close proximity to other metal structures that are unprotected or protected by its own electrically isolated 
cathodic protection system(s)].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.5   Test Stations [and Permanent Reference Electrodes]</TTL><BRK/>
<BRK/>
<TXT>Provide test stations [and permanent reference electrodes] [as indicated.]  as follows: </TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.   At<MET> [305] [_____] meters</MET><ENG> [1000] [_____] foot</ENG> intervals.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.   At all insulating joints.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.   At both ends of casings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.   Where the pipe crosses any other metal pipes.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.   Where the pipe connects to an existing piping system.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.   Where the pipe connects to a dissimilar metal pipe.</ITM><BRK/>
<BRK/>
<TXT>Do not fill the bottom of the test station with concrete unless otherwise specified.  Do not place rubbish, scrap 
or other debris into the test station.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.5.1   <TST>Permanent Reference Electrode Calibration</TST> and Installation</TTL><BRK/>
<BRK/>
<TXT>Provide [prepackaged] [copper copper-sulfate] [silver-silver chloride] [zinc] reference electrode(s) as inidcated 
in the drawings.  Prior to installation, soak the [prepackaged] reference electrode in a container of potable 
water for 30 minutes.  Do not use seawater [except for silver-silver chloride electrodes intended for use in 
seawater].  Calibrate the permanent reference electrode in the presence of the contracting officer or his approved 
representative by measuring the potential difference between the permanent reference electrode and an independent 
(portable) calibrated reference electrode placed in the water adjacent to the permanent reference electrode.  
[Potential differences between the two electrodes of the same generic type should not exceed [10] [15] millivolts 
when the [sensing windows of the] two electrodes being compared are not more than<MET> 2 mm</MET><ENG> 1/6 inch</ENG> apart but not 
touching.]  [Zinc permanent reference electrodes should be within the range of -1000 to -1150 millivolts when 
calibrated with an independent (portable) calibrated copper-copper sulfate reference electrode with the two electrodes 
being not more than<MET> 2 mm</MET><ENG> 1/6 inch</ENG> apart but not touching.]  Permanent reference electrodes not within these potential 
differences shall be removed from the construction site by the end of the day and replaced at the contractor's 
expense.  [Prior to completely backfilling over reference electrodes, again verify the accuracy of the reference 
electrode.]  The testing provision shall also apply to replacement reference electrodes as well.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.1.6   Insulating Flange Sets</TTL><BRK/>
<BRK/>
<TXT>[Provide insulating flange sets aboveground or within manholes as indicated].  [Locate insulating flanges on 
lines entering buildings at least<MET> 305 mm</MET><ENG> 12 inches</ENG> above grade or floor level.]  [Cut piping and provide flanges 
into place.  Carefully align flange bolt holes and weld flange to pipe in accordance with <RID>ASME B16.25</RID>.]  [Electrically 
isolate pipelines entering buildings from the structure wall either below or above ground with an electrically 
isolating wall sleeve.]  Provide insulating flange sets into place without springing or forcing.  Carefully install 
flange bolt sleeves to avoid damage to the sleeves. [Cover insulating flanges with an electrically insulating 
coating.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.7   <SUB>Dielectric Unions</SUB></TTL><BRK/>
<BRK/>
<TXT>[Cut pipe ends square, remove fins and burrs, cut taper pipe threads in accordance with <RID>ASME B1.20.1</RID>.]  Provide 
insulating unions as indicated.  Work piping into place without springing or forcing.  Apply joint compound or 
thread tape to male threads only.  Backing off to permit alignment of threaded joints shall not be permitted.  
Engage threads so that not more than three threads remain exposed.  [Cover unions with an electrically insulating 
coating.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.8   <SUB>Joint Bonds</SUB></TTL><BRK/>
<BRK/>
<TXT>Provide joint bonds on metallic pipe to and across buried flexible couplings, mechanical joints, flanged joints 
[except at places where insulating joints are specified] and joints not welded or threaded to provide electrical 
continuity.  Connect bond wire(s) to the structure(s) by use of exothermic weld kit(s).  Clean the structure 
surface by scraping, filing or wire brushing to produce a clean, bright surface.  [Weld connections using exothermic 
kits in accordance with the kit manufacturer's instructions.]  Check and verify adherence of the bond to the 
substrate for mechanical integrity by striking the weld with a<MET> 908 gram</MET><ENG> 2 pound</ENG> hammer.  Cover connections with 
an electrically insulating coating [which is compatible with the existing coating on the structure].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.9   <SUB>Casings, Insulation, and Seals</SUB></TTL><BRK/>
<BRK/>
<TXT>Where the pipeline is installed in a casing under a roadway or railway, insulate the pipeline from the casing, 
and seal the annular space against intrusion of water.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.10   Concrete</TTL><BRK/>
<BRK/>
<TXT>Concrete shall be<MET> 20 Mpa</MET><ENG> 3000 psi</ENG> minimum ultimate 28-day compressive strength with<MET> 25 mm</MET><ENG> one inch</ENG> minimum aggregate 
conforming to [<RID>ASTM C 94/C 94M</RID>] [Section <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.11   Reconditioning of Surfaces</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1.11.1   Restoration of Sod</TTL><BRK/>
<BRK/>
<TXT>Restore unpaved surfaces disturbed during the installation of anodes and wires to their original elevation and 
condition.  Preserve sod and topsoil carefully and replace after the backfilling is completed.  Where the surface 
is disturbed in a newly seeded area, re-seed the area with the same quality and formula of seed as that used 
in the original seeding.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.11.2   Restoration of Pavement</TTL><BRK/>
<BRK/>
<TXT>Repair pavement, sidewalks, curbs, and gutters where existing surfaces are removed or disturbed for construction.  
Saw cut pavement edges.  Graded aggregate base course shall have a maximum aggregate size of<MET> 40 millimeters</MET><ENG> 1 
1/2 inches</ENG>.  Prime base course with [liquid asphalt, <RID>ASTM D 2028</RID>, Grade RC-70] [_____] prior to paving.  Match 
base course thickness to existing but shall not be less than<MET> 150 millimeters</MET><ENG> 6 inches</ENG>.  Asphalt aggregate size 
shall be<MET> 15 mm</MET><ENG> 1/2 inch</ENG> [_____], asphalt cement shall [conform to <RID>ASTM D 3381</RID>, Grade AR-2000] [_____].  Match 
asphalt concrete thickness to existing but shall not be less than<MET> 50 millimeters</MET><ENG> 2 inches</ENG>.  Repair portland cement 
concrete pavement, sidewalks, curbs, and gutters using<MET> 20.67 MPa</MET><ENG> 3,000 psi</ENG> concrete conforming to [<RID>ASTM C 94/C 94M</RID>
] [Section <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE.]  Match existing pavement, sidewalk, curb, and gutter thicknesses.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.2   FIELD QUALITY CONTROL</TTL><BRK/>
<BRK/>
<TXT>Field tests shall be witnessed by the Contracting Officer or his designated representative.  Advise the Contracting 
Officer [5] [_____] days prior to performing each field test.  Quality control for the <SUB>cathodic protection system</SUB>
 shall consist of the following:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Initial field testing by the contractor upon construction</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Government Field Testing after Contractor initial field test report submission.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Warranty period field testing by the Contractor.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Final field testing by the contractor after one year of service.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Additional testing may be required based upon the specific project or 
design.  All tests listed below may not be required.  Designer should consider 
the project requirements for selection of test procedures.  Specify 30 days 
notice for large systems to allow the Government corrosion engineer to be on-site 
during the initial and final field testing of the cathodic protection systems. </NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.2.1   Testing</TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.1.1   <TST>Non-Destructive Testing of Anodes</TST></TTL><BRK/>
<BRK/>
<TXT>Contractor shall perform the tests in the presence of the Contracting Officer.  One anode of each type shall 
be chosen at random for non-destructive testing and shall be submerged in a container of fresh water for about 
30 minutes.  Contractor shall then measure the anode-to-water potential difference between a calibrated copper-copper 
sulfate reference electrode.  Potential differences should generally be within the following ranges:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">High potential Magnesium     -1.65 to -1.75 Volts</ITM><BRK/>
<ITM INDENT="-0.33">Standard Magnesium           -1.4 to -1.5 Volts</ITM><BRK/>
<ITM INDENT="-0.33">Zinc                         -1.0 to -1.15 Volts</ITM><BRK/>
<BRK/>
<TXT>[Failure of the test anode to conform to this specification can be cause for rejecting all anodes from the same 
lot as the test anode.  The contractor shall mark all rejected anodes on the ends with a 6" high "X" using yellow 
spray paint.  Failed anodes shall be removed from the job site by the end of the day.  The contractor shall replace 
any rejected anodes at his expense.  The destructive testing provision shall also apply to replacement anodes 
as well.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.1.2   <TST>Destructive Testing of Anodes</TST></TTL><BRK/>
<BRK/>
<TXT>Contractor shall perform the tests in the presence of the Contracting Officer.  Contractor shall include the 
cost of an additional anode [of each different type] with the longest lead wire for the destructive test in his 
bid.  One completed [prepackaged] anode of each type with lead wires shall be chosen at random for destructive 
testing and shall be submitted to a static pull test.  Anode wire connections shall have sufficient strength 
to withstand a minimum tensile load of<MET> [136] [_____] kg</MET><ENG> [300] [_____] pounds</ENG>.  [The anode shall also be cut into 
sections and/or broken with a sledge hammer to verify conformance with this specification.  Such items as anode-to-wire 
connection, complete encapsulation of the wire connector, and wire to anode electrical resistance shall be checked.]  
[Failure of the test anode to conform to this specification can be cause for rejecting all anodes from the same 
lot as the test anode.  The contractor shall mark all rejected anodes on the ends with a 6" high "X" using yellow 
spray paint.  Failed anodes shall be removed from the job site by the end of the day.  The contractor shall replace 
any rejected anodes at his expense.  The destructive testing provision shall also apply to replacement anodes 
as well.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.1.3   <TST>Initial Cathodic Protection System Field Testing</TST></TTL><BRK/>
<BRK/>
<TXT>Systems shall be tested and inspected by the Contractor's corrosion engineer in the presence of the Contracting 
Officer's corrosion protection engineer or an approved representative.  Record test data, including date, time, 
and locations of testing and submit report to the Contracting Officer.  Contractor shall correct and retest, 
at his expense, deficiencies in the materials and installation observed by these tests and inspections.  Testing 
shall include the following measurements.</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  <TST>Base potential tests</TST>:  At least [one week] [24 hours] [_____]  after [backfilling of the 
pipe] [installation of structure to be protected] [initial operation of structures containing 
fluids] and installation of the anodes, but before connection of anodes to the structure, measure 
base (native) structure-to-electrolyte potentials of the [pipe [and casings]] [structure].  
Perform measurements at anode junction boxes, test stations and other locations suitable for 
test purposes (such as service risers or valves), at intervals not exceeding<MET> [30] [120] [_____] 
meters</MET><ENG> [100] [400] [_____] feet</ENG> [with readings at each end point and the midpoints as a minimum]. 
The locations of these measurements shall be identical to the locations specified for potential 
measurements with anodes connected.  Use the same measuring equipment that is specified for 
measuring protected potential measurements.  </ITM><ITM>[For underground storage tanks, take a minimum 
of three measurements with the reference electrode located as follows:</ITM><BRK/>
<BRK/>
<ITM>(1)  Directly over the longitudinal and transverse centerlines of the tank at intervals not 
exceeding the diameter of the tank and to a distance from the tank of two times the tank diameter.</ITM><BRK/>
<BRK/>
<ITM>(2)  At points directly around the circumference of the tank.]</ITM><BRK/>
<BRK/>
<ITM>b.  <TST>Permanent reference electrode calibration</TST>:  Verify calibration of the reference electrode 
by measuring the potential difference between the permanent reference electrode and an independent 
(portable) calibrated reference electrode placed in the soil or water adjacent to or as close 
as practicable to the permanent reference electrode.  [Potential differences between the two 
electrodes of the same generic type should not exceed [10] [15] millivolts.]  [Zinc permanent 
reference electrodes should be within the range of -1000 to -1150 millivolts when calibrated 
with a copper-copper sulfate reference electrode.]  Permanent reference electrodes not within 
these potential differences shall be removed from the construction site by the end of the day 
and replaced at the contractor's expense.  The testing provision shall also apply to replacement 
reference electrodes as well.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  <TST>Insulation joint testing</TST>:  Perform insulation testing at each insulating joint or fitting 
[prior to burying the joint or fitting] before and after the connection of anodes to the pipe 
at [anode junction box] [test station].  Before connection, test using an insulation checker.  
After connection, test by measuring the potential shift on both sides of the insulating joint.  
These tests shall demonstrate that no metallic contact or short circuit exists between the two 
insulated sections of the pipe.  Report and repair defective insulating flanges at the Contractor's 
expense.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  <TST>Electrical continuity testing</TST>:  <TST>Perform electrical continuity testing for joint bonded pipe 
prior to backfilling of the pipe. [Circulate current through the pipe and compare the measured 
resistance to the theoretical resistance of the pipe and bond cables.</TST>  The resistance measured 
shall not exceed 150 percent of the theoretical resistance.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  <TST>Pipe casing testing</TST>:  Before final acceptance of the installation, test the electrical insulation 
of the carrier pipe from casings and correct any short circuits.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  <TST>Anode-to-soil potential and anode output testing</TST>:  Measure anode-to-soil potential of each 
anode with the anode disconnected [through the anode junction box].  After connecting the anodes 
to the pipe, measure current output of each anode [across the shunt installed].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  <TST>Protected potential measurement tests</TST>:  With the entire galvanic protection system put into 
operation for at least [one week] [24 hours] [_____], measure potentials along the [pipeline 
[and at all casings]] [structure] using a portable [copper-copper sulfate] [silver-silver chloride] 
[and all permanent] reference electrodes and a voltmeter having an input impedance of not less 
than 10 megohm.  The locations of these measurements shall be identical to the locations used 
for the base potential measurements.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  <TST>Interference testing</TST>:  Perform interference testing with respect to any crossing and nearby 
foreign pipes in cooperation with the owner of the foreign pipes.  The testing shall verify 
that the cathodic protection system does not have a deleterious effect on the foreign pipelines, 
and vice versa.  Prepare a full report of the tests giving all details including remedial actions 
taken or recommendations to correct noted interference problems.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.1.4   <SUB>Initial Cathodic Protection System Field Test Report</SUB></TTL><BRK/>
<BRK/>
<TXT>The contractor shall submit a field test report of the cathodic protection system.  All structure-to-electrolyte 
measurements, including initial potentials and anode outputs, shall be recorded on applicable forms.  Identification 
of test locations, test station and anode test stations shall coordinate with the as-built drawings and be provided 
on system drawings included in the report.  The contractor shall locate, correct, and report to the Contracting 
Officer any short circuits encountered during the checkout of the installed cathodic protection system.</TXT><BRK/></SPT>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The requirements of paragraph entitled "Government Field Testing" are 
required for cathodic protection projects in the LANTNAVFACENGCOM area.  The 
designer should verify their applicability to projects outside the LANTNAVFACENGCOM 
area with the appropriate EFD corrosion program manager.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.2.1.5   Government Field Testing</TTL><BRK/>
<BRK/>
<TXT>The government corrosion [engineer, LANTNAVFACENGCOM Code 404] [program manager, LANTNAVFACENGCOM Code 1614C] 
shall review the Contractor's initial field testing report.  Approximately four weeks after receipt of the Contractor's 
initial test report, the system will be tested and inspected in the Contractor's presence by the government corrosion 
[engineer, LANTNAVFACENGCOM Code 404] [program manager, LANTNAVFACENGCOM Code 1614C].  The Contractor shall correct, 
at his expense, materials and installations observed by these tests and inspections to not be in conformance 
with the plans and specifications.  The Contractor shall pay for all retesting done by the government engineer 
made necessary by the correction of deficiencies.</TXT><BRK/></SPT>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For cathodic protection projects in the LANTNAVFACENGCOM area, select 
the appropriate LANTNAVFACENGCOM options for paragraphs entitled "One Year Warranty 
Period Testing" and "Final Field Testing."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.2.1.6   One Year Warranty Period Testing</TTL><BRK/>
<BRK/>
<TXT><TST>The Contractor shall inspect, test, and adjust the cathodic protection system [quarterly] [semi-annually] [_____] 
for one year, [4] [2] [  ] interim inspections total, to ensure its continued conformance with the criteria outlined 
below.</TST>  The performance period for these tests shall commence upon the completion of all cathodic protection 
work, including changes required to correct deficiencies identified during initial testing, and preliminary acceptance 
of the cathodic protection system by the Contracting Officer.  Copies of the <SUB>One Year Warranty Period Cathodic 
Protection System Field Test Report</SUB>, including field data, and certified by the Contractor's corrosion engineer 
shall be submitted to the Contracting Officer, the activity, and the geographic Engineering Field Division corrosion 
[protection program manager] [engineer, LANTNAVFACENGCOM Code 404] [protection program manager, LANTNAVFACENGCOM 
Code 1614C].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.1.7   Final Field Testing</TTL><BRK/>
<BRK/>
<TXT><TST>Conduct final field testing of the cathodic protection system utilizing the same procedures specified under, 
"Initial Field Testing of the Galvanic Cathodic Protection Systems".  The Contractor shall inspect, test, and 
adjust the cathodic protection system after one year of operation to ensure its continued conformance with the 
criteria outlined below.</TST>  The performance period for these tests shall commence upon preliminary acceptance for 
the cathodic protection system by the Contracting Officer.  Copies of the <SUB>Final Cathodic Protection System Field 
Test Report</SUB>, certified by the Contractor's corrosion engineer shall be submitted to the Contracting Officer and 
the geographic Engineering Field Division corrosion [protection program manager] [engineer, LANTNAVFACENGCOM 
Code 404] [protection program manager, LANTNAVFACENGCOM Code 1614C] for approval, and as an attachment to the 
operation and maintenance manual in accordance with Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE DATA.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2.2   Criteria for Cathodic Protection</TTL><BRK/>
<BRK/>
<TXT>Conduct in accordance with [<RID>NACE SP0169</RID>] [<RID>NACE RP0285</RID>].  Criteria for determining the adequacy of protection 
shall be selected by the corrosion engineer as applicable:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The following criteria are applicable only to iron and steel structures.  
Refer to NACE SP0169 for appropriate criteria for other metal structures.  Not 
all criteria may be readily applicable to the type of CP system(s) being designed, 
and the designer should select only the applicable criteria.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM INDENT="-0.33">a.  A negative voltage of at least 0.85 volt (850 millivolts) as measured between the structure 
surface and a saturated copper- copper sulfate reference electrode contacting the earth [electrolyte].  
Determination of this voltage is to be made with the protective current applied to the [structure] 
[tank] [pipeline] for a minimum of [24] [_____] hours.  Voltage drops must be considered for 
valid interpretation of this voltage measurement.  The method of voltage drop consideration 
shall be identified by the Contractor's corrosion engineer and approved by the Government corrosion 
engineer.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  A negative polarized potential of at least 0.85 volt (850 millivolts) as measured between 
the structure surface and a saturated copper-copper sulfate reference electrode contacting the 
earth [electrolyte].  Determination of this voltage is to be made after the protective current 
has been applied to the [structure] [tank] [pipeline] for a minimum of [24] [_____] hours.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  A minimum polarization voltage shift of 100 mV measured between the structure surface and 
a saturated copper-copper sulfate reference electrode contacting the earth [electrolyte].  This 
voltage shift shall be determined by interrupting the protective current and measuring the polarization 
decay.  At the instant the protective current is interrupted ("instant off"), an immediate voltage 
shift will occur.  The voltage reading just after the immediate shift shall be used as the base 
reading from which to measure the polarization decay.  The polarization decay shall be the difference 
between the base reading and a voltage measurement made [24] [48] [_____] hours after the interruption 
of protective current.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.3   DEMONSTRATION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Instructing Government Personnel</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  There are restrictions on the type and extent of training.  Training 
is usually on-site, 2 days or less.  Factory representatives or others provide 
basic instructions to facility maintenance and operation personnel.  If more 
extensive training is required, i.e., student travel, special consultants, etc., 
consult the Contract Division Director and the head of the Comptroller Department 
for assistance.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><TST>During the warranty testing and at a time designated by the Contracting Officer, make available the services 
of a technician regularly employed or authorized by the manufacturer of the Cathodic Protection System for instructing 
Government personnel in the proper operation, maintenance, safety, and emergency procedures of the Cathodic Protection 
System.  The period of instruction shall be not less than [one] [_____] but not more than [two] [_____] 8-hour 
working day[s].  Conduct the training at the jobsite or at another location mutually satisfactory to the Government 
and the Contractor.</TST>  The field instructions shall cover all of the items contained in the operation and maintenance 
manual.</TXT><BRK/>
<BRK/></SPT>
</SPT><MET><SPT><TTL>3.4   SCHEDULE</TTL><BRK/>
<BRK/>
<TXT>Some metric measurements in this section is based on a mathematical conversion of an English unit measurement, 
and not on metric measurement commonly agreed upon by the manufacturers or other parties.  The English and metric 
units for the measurements shown are as follows:</TXT><BRK/>
<TBL><THD><BRK/>
         <HL1>Products</HL1>                      <HL1>English Units</HL1>       <HL1>Metric Units</HL1><BRK/></THD>
<BRK/>
         a.  Reference Electrodes<BRK/>
             - Diameter                1 1/4 inches         32 mm<BRK/>
             - Length                  10 inches           255 mm<BRK/>
<BRK/>
         b.  Warning Tape<BRK/>
             - width                   3 inches             75 mm<BRK/></TBL>
<BRK/></SPT>
</MET></PRT>    <END/><BRK/></SEC>