<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA      UFGS-26 42 19.00 20 (August 2001)<BRK/>
                                    ------------------------------<BRK/>
Preparing Activity:  <PRA>NAVFAC</PRA>         Replacing without change <BRK/>
                                    UFGS-13111N (August 2001)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 26 42 19.00 20</SCN><BRK/>
<BRK/>
<STL>CATHODIC PROTECTION BY IMPRESSED CURRENT</STL><BRK/>
<DTE>04/06</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>underground piping 
and buried or submerged structure cathodic protection systems using impressed 
current systems</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The requirements for the cathodic protection systems should be determined 
by a corrosion engineer following the criteria, design, and installation recommendations 
included in the National Association of Corrosion Engineers (NACE) Standard 
SP0169, Control of External Corrosion on Underground or Submerged Metallic Piping 
Systems and others listed in the specification.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The following information should be on the drawings:</NPR><BRK/>
<BRK/>
<NPR>1.  Locations of the subject pipe or structure and all crossing and nearby underground 
pipes and structures.</NPR><BRK/>
<BRK/>
<NPR>2.  Locations of all anodes, rectifiers, power sources and test stations.</NPR><BRK/>
<BRK/>
<NPR>3.  Locations of all insulating flanges and unions.</NPR><BRK/>
<BRK/>
<NPR>4.  Installation details of anodes, rectifiers and bond cables.</NPR><BRK/>
<BRK/>
<NPR>5.  Locations of nearby cathodic protection systems.</NPR><BRK/>
<BRK/>
<NPR>6.  Electrical single-line diagrams, elevations, limiting dimensions, and equipment 
ratings which are not covered in the specification.</NPR><BRK/>
<BRK/>
<NPR>7.  Remote indicating or control requirements.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
 <BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
 <BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ASME INTERNATIONAL (ASME)</ORG><BRK/><BRK/><RID>ASME B1.1</RID><RTL>(2003; R 2008) Unified Inch Screw Threads (UN and UNR Thread Form)</RTL><BRK/><BRK/><RID>ASME B1.20.1</RID><RTL>(1983; R 2006) Pipe Threads, General Purpose (Inch)</RTL><BRK/><BRK/><RID>ASME B16.21</RID><RTL>(2005) Nonmetallic Flat Gaskets for Pipe Flanges</RTL><BRK/><BRK/><RID>ASME B16.25</RID><RTL>(2007) Standard for Buttwelding Ends</RTL><BRK/><BRK/><RID>ASME B16.39</RID><RTL>(1998; R 2006) Standard for Malleable Iron Threaded Pipe Unions; Classes 150, 250, and 300</RTL><BRK/><BRK/><RID>ASME B16.5</RID><RTL>(2003) Standard for Pipe Flanges and Flanged Fittings:  NPS 1/2 Through NPS 24</RTL><BRK/><BRK/><RID>ASME B18.2.1</RID><RTL>(1996; Addenda A 1999; Errata 2003; R 2005) Square and Hex Bolts and Screws (Inch Series)</RTL><BRK/><BRK/><RID>ASME B18.2.2</RID><RTL>(1987; R 2005) Standard for Square and Hex Nuts</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM A 194/A 194M</RID><RTL>(2008b) Standard Specification for Carbon and Alloy Steel Nuts for Bolts for High-Pressure or High-Temperature Service, or Both</RTL><BRK/><BRK/><RID>ASTM A 307</RID><RTL>(2007b) Standard Specification for Carbon Steel Bolts and Studs, 60 000 PSI Tensile Strength</RTL><BRK/><BRK/><RID>ASTM A 518/A 518M</RID><RTL>(1999; R 2008) Standard Specification for Corrosion-Resistant High-Silicon Iron Castings</RTL><BRK/><BRK/><RID>ASTM A 53/A 53M</RID><RTL>(2007) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless</RTL><BRK/><BRK/><RID>ASTM B 3</RID><RTL>(2001; R 2007) Standard Specification for Soft or Annealed Copper Wire</RTL><BRK/><BRK/><RID>ASTM B 8</RID><RTL>(2004) Standard Specification for Concentric-Lay-Stranded Copper Conductors, Hard, Medium-Hard, or Soft</RTL><BRK/><BRK/><RID>ASTM C 94/C 94M</RID><RTL>(2007) Standard Specification for Ready-Mixed Concrete</RTL><BRK/><BRK/><RID>ASTM D 1248</RID><RTL>(2005) Standard Specification for Polyethylene Plastics Extrusion Materials for Wire and Cable</RTL><BRK/><BRK/><RID>ASTM D 2028</RID><RTL>(1997; R 2004) Cutback Asphalt (Rapid-Curing Type)</RTL><BRK/><BRK/><RID>ASTM D 3381</RID><RTL>(2005) Viscosity-Graded Asphalt Cement for Use in Pavement Construction</RTL><BRK/><BRK/></REF><REF><ORG>INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)</ORG><BRK/><BRK/><RID>IEEE C2</RID><RTL>(2007; Errata 2007; INT 2008) National Electrical Safety Code</RTL><BRK/><BRK/></REF><REF><ORG>NACE INTERNATIONAL (NACE)</ORG><BRK/><BRK/><RID>NACE RP0285</RID><RTL>(2002) Corrosion Control of Underground Storage Tank Systems by Cathodic Protection</RTL><BRK/><BRK/><RID>NACE SP0169</RID><RTL>(2007) Control of External Corrosion on Underground or Submerged Metallic Piping Systems</RTL><BRK/><BRK/><RID>NACE SP0572</RID><RTL>(2007) Design, Installation, Operation and Maintenance of Impressed Current Deep Groundbeds</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)</ORG><BRK/><BRK/><RID>NEMA C119.1</RID><RTL>(2006) Sealed Insulated Underground Connector Systems Rated 600 Volts</RTL><BRK/><BRK/><RID>NEMA ICS 6</RID><RTL>(1993; R 2006) Standard for Industrial Controls and Systems Enclosures</RTL><BRK/><BRK/><RID>NEMA RN 1</RID><RTL>(2005) Standard for Polyvinyl Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit</RTL><BRK/><BRK/><RID>NEMA ST 1</RID><RTL>(1988; R 1997) Standard for Specialty Transformers (Except General Purpose Type)</RTL><BRK/><BRK/><RID>NEMA TC 2</RID><RTL>(2003) Standard for Electrical Polyvinyl Chloride (PVC) Tubing and Conduit</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)</ORG><BRK/><BRK/><RID>NFPA 70</RID><RTL>(2007; AMD 1 2008) National Electrical Code - 2008 Edition</RTL><BRK/><BRK/></REF><REF><ORG>U.S. DEPARTMENT OF DEFENSE (DOD)</ORG><BRK/><BRK/><RID>MIL-I-1361</RID><RTL>(Rev C; Notice 1) Instrument Auxiliaries, Electrical Measuring:  Shunts, Resistors and Transformers</RTL><BRK/><BRK/></REF><REF><ORG>UNDERWRITERS LABORATORIES (UL)</ORG><BRK/><BRK/><RID>UL 44</RID><RTL>(2005; Rev thru Nov 2005) Thermoset-Insulated Wires and Cables</RTL><BRK/><BRK/><RID>UL 467</RID><RTL>(2007) Standard for Grounding and Bonding Equipment</RTL><BRK/><BRK/><RID>UL 486A-486B</RID><RTL>(2003; Rev thru Aug 2006) Standard for Wire Connectors</RTL><BRK/><BRK/><RID>UL 489</RID><RTL>(2002; Rev thru Jun 2006) Standard for Molded-Case Circuit Breakers, Molded-Case Switches and Circuit-Breaker Enclosures</RTL><BRK/><BRK/><RID>UL 506</RID><RTL>(2000; Rev thru May 2006) Standard for Specialty Transformers</RTL><BRK/><BRK/><RID>UL 510</RID><RTL>(2005; Rev thru Aug 2005) Polyvinyl Chloride, Polyethylene, and Rubber Insulating Tape</RTL><BRK/><BRK/><RID>UL 514A</RID><RTL>(2004; Rev thru Aug 2007) Standard for Metallic Outlet Boxes</RTL><BRK/><BRK/><RID>UL 514B</RID><RTL>(2004; Rev thru Aug 2007) Standard for Conduit, Tubing and Cable Fittings</RTL><BRK/><BRK/><RID>UL 6</RID><RTL>(2007) Standard for Electrical Rigid Metal Conduit-Steel</RTL><BRK/><BRK/><RID>UL 83</RID><RTL>(20086) Standard for Thermoplastic-Insulated Wires and Cables</RTL><BRK/><BRK/><RID>UL 854</RID><RTL>(2004; Rev thru Oct 2007) Service-Entrance Cables</RTL><BRK/><BRK/></REF></SPT><SPT>[<TTL>1.2   Related Requirements</TTL><BRK/>
<BRK/>
<TXT>Sections <SRF>26 00 00.00 20</SRF> BASIC ELECTRICAL MATERIALS NAD METHODS, [<SRF>33 71 02.00 20</SRF> UNDERGROUND UNDERGROUND TRANSMISSION 
AND DISTRIBUTION], and, [<SRF>26 20 00</SRF> INTERIOR DISTRIBUTION SYSTEM], apply to this section except as modified herein.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>1.3   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  The following shall 
be submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Rectifiers</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Insulating flange sets</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Anode installation</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Test stations </SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Bonding boxes</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Anode junction boxes</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Anode vent pipe</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Joint bonds</SUB></ITM><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Rectifiers</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Cable and wire</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Insulating flange sets</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Dielectric unions</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Anodes</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Test stations</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Anode junction boxes</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Anode vent pipe</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Casing insulators and seals</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Reference electrodes</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Shunt resistors</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Anode backfill</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Bonding boxes</SUB></ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Qualifications of Corrosion Engineer</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-10 Operation and Maintenance Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Cathodic protection system</SUB>, Data Package 5[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Rectifier replacement/spare parts list</SUB>, Data Package 5[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Submit in accordance with Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE DATA.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-11 Closeout Submittals</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Initial Cathodic Protection System Field Test Report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>One Year Warranty Period Cathodic Protection System Field Test Report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Final Cathodic Protection System Field Test Report</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4   SERVICES OF CORROSION ENGINEER</TTL><BRK/>
<BRK/>
<TXT>The Contractor shall obtain the services of a Corrosion Engineer to supervise, inspect and test the installation 
of the cathodic protection system(s).  Corrosion Engineer refers to a registered professional engineer with certification 
or licensing that includes education and experience in cathodic protection of buried or submerged metal structures, 
or a person certified by the National Association or Corrosion Engineers at the level of Corrosion Specialist 
or Cathodic Protection Specialist.  Such a person shall have not less than [three] [five] [_____] years experience 
in the cathodic protection of underground [storage tanks] or submerged structures.  The contractor shall submit 
evidence of the <SUB>qualifications of corrosion engineer</SUB> to the Contracting Officer for review and approval.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   <SUB>ANODES</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The chemical compositions listed are examples only.  The actual compositions 
required shall be determined to provide adequate and economical service.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/>*<BRK/>
<NPR>NOTE:  Options for anode materials include "High-Silicon Chromium Bearing Cast 
Iron,"  "Graphite," and "Mixed Metal Oxide Coated" anodes.  Selection of material 
should be based upon the conditions and operating parameters for the intended 
use.  Precious metal or other anode materials, packaging or connections may 
also be appropriate for use, as determined by the engineer.  These materials, 
packaging, or connections must also be submitted for approval in accordance 
with "Submittals Procedures."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT>[<TTL>2.1.1   High-Silicon Chromium Bearing Cast Iron</TTL><BRK/>
<BRK/>
<TXT>[<RID>ASTM A 518/A 518M</RID>], Grade 3.  [Chemical composition as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">Carbon                  0.70 - 1.10 percent</ITM><BRK/>
<ITM INDENT="-0.33">Manganese               1.5 percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Silicon                 14.20 - 14.75 percent</ITM><BRK/>
<ITM INDENT="-0.33">Chromium                3.25 - 5.00 percent</ITM><BRK/>
<ITM INDENT="-0.33">Copper                  0.50 percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Molybdenum              0.20 percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Iron                    Remainder</ITM><BRK/>
<BRK/>
<TXT>Anode dimensions:  [_____] by [_____]<MET> mm.</MET><ENG> inches.</ENG>  [Centrifugally cast tubular anodes with uniform wall thickness, 
[_____]<MET> mm</MET><ENG> inches</ENG> long, [_____]<MET> mm</MET><ENG> inches</ENG> outer diameter, [_____] square<MET> meter</MET><ENG> feet</ENG> surface area, and [_____]<MET>
 kg</MET><ENG> lb</ENG> bare anode weight.]]</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.1.2   Graphite</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Maximum allowable current densities for anode surface area are as follows; 
Seawater: <MET> 40.37 amps per square meter</MET><ENG> 3.75 amps per square foot</ENG>, Fresh water: <MET>
 2.69 amps per square meter</MET><ENG> 0.25 amps per square foot</ENG>, and Soil (anode placed 
in backfill): <MET> 10.76 amps per square meter</MET><ENG> 1.0 amps per square foot</ENG>.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Chemical composition as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">Impregnant                            6.5 percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Ash                                   1.5 percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Moisture &amp; Volatiles                  0.5 percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Water Soluble Matter                  1.0 percent maximum</ITM><BRK/>
<ITM INDENT="-0.33">Graphite                              Remainder</ITM><BRK/>
<BRK/>
<TXT>Anode dimensions:  [_____] by [_____]<MET> mm</MET><ENG> inches</ENG>.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>2.1.3   Mixed Metal Oxide Anodes</TTL><BRK/>
<BRK/>
<TXT>Mixed metal oxide anodes shall be provided by a firm that is regularly engaged in and has a minimum 5 years experience 
in manufacturing and applying mixed metal oxide coatings to titanium anode substrates.  The mixed metal oxide 
anodes shall be of the size indicated and shall conform to the following requirements.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.1.3.1   Conductive Material</TTL><BRK/>
<BRK/>
<TXT>Titanium substrate coated with an inert, dimensionally stable, electrically conductive coating [with average 
composition of a 50/50 atomic percent] mixture of iridium and titanium oxides with a small amount of tantalum 
and ruthenium, 0.002 ohm-centimeter maximum resistivity, 50 MPa minimum adhesion or bond strength, and capable 
of sustaining a current density of 100 ampere per square meter in an oxygen generating electrolyte at<MET> 66 degrees 
C</MET><ENG> 150 degrees F</ENG> for 20 years.  Sinter the mixed metal oxide coating to the titanium surface as to remain tightly 
bound to the surface when bent 180 degrees onto itself.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.3.2   Anode Life Test</TTL><BRK/>
<BRK/>
<TXT>Perform an accelerated current capacity life test on every lot of anode wire used to construct the anode as described.  
The anode wire material shall sustain current densities of 100 ampere per square meter in an oxygen generating 
electrolyte for 20 years.  The manufacturer shall certify that a representative sample taken from the same lot 
used to construct the anode, has been tested and meets the following criteria.</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  The representative sample shall be<MET> 125 mm</MET><ENG> 5 inch</ENG> in length and be taken from the lot of 
wire that is to be used for the anode.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  The cell containing the anode shall be powered with a constant current power supply for 
the 30 day test period.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  The test cell sustains a current density of 10,000 ampere per square meter in a 15 weight 
percent sulfuric acid electrolyte at<MET> 66 degrees C</MET><ENG> 150 degrees F</ENG> without an increase in anode 
to cathode potential of more than 1 volt.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.3.3   Adhesion or Bond Strength Test</TTL><BRK/>
<BRK/>
<TXT>Determine the adhesion or bond strength by epoxy bonding a<MET> 2.54 mm</MET><ENG> 100 mils</ENG> diameter stud to the ceramic coating 
and measuring the load to failure of either the epoxy or the interface between the coating and the substrate.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.1.4   Anode Lead Wires</TTL><BRK/>
<BRK/>
<TXT>Not less than [No. 8] [No. 6] [_____] AWG stranded copper conductor with [<MET>2.8 mm</MET><ENG>110 mils</ENG> [_____] thick <RID>ASTM D 1248</RID>
, high molecular weight polyethylene (HMWPE) insulation] [an inner jacket of<MET> one mm</MET><ENG> 40 mils</ENG> [_____] of ethylene 
chlorotrifuoroethylene insulation covered by an outer jacket of<MET> 1.6 m</MET><ENG> 65 mils</ENG> [_____] of <RID>ASTM D 1248</RID>, high molecular 
weight polyethylene (HMWPE)] [a primary insulation of ethylene propylene rubber and an outer jacket of chloro 
sulphonated polyethylene],<MET> [3050] [6100] [_____] mm</MET><ENG> [10] [20] [_____] feet</ENG> in length [of sufficient length to 
extend to junction box without splicing].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.5   Attachment of Anode Lead Wire</TTL><BRK/>
<BRK/>
<TXT>Anode lead wires shall be factory installed.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.1.5.1   End Connected Anode</TTL><BRK/>
<BRK/>
<TXT>[Drill] [Cast] a recess<MET> [150] [_____] mm</MET><ENG> [6] [_____] inches</ENG> deep in one end of the anode.  Attach the lead wire 
to the anode with an anchor device.  Not more than<MET> 10 mm</MET><ENG> 1/2 inch</ENG> of bare wire shall protrude from the anchor 
device.  Attachment shall withstand a<MET> 1446 Newton</MET><ENG> 325 pound</ENG> pull without loosening the wire or anchor device.  
Fill the recess with an [asphalt] [epoxy] sealing compound [, leaving sufficient space for a plug].  [Provide 
non-metallic plug flush with the anode end surface.]  [Install a heat shrinkable anode cap over the attachment, 
cap shall extend not less than<MET> 65 mm</MET><ENG> 2 1/2 inches</ENG> on the lead wire and<MET> 75 mm</MET><ENG> 3 inches</ENG> on the anode.]  Cable to 
anode contact resistance shall be 0.02 ohms maximum.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.5.2   Center Connected Anode</TTL><BRK/>
<BRK/>
<TXT>Attach the lead wire to the center of the anode with an anchor device suitably fastened to the wire.  Not more 
than<MET> 20 mm</MET><ENG> one inch</ENG> of bare wire shall protrude from the anchor device.  Encapsulate [each side of] the connection 
point with a minimum of<MET> 152 mm</MET><ENG> 6 inches</ENG> [_____] of high voltage insulating compound mastic [and<MET> 102 mm</MET><ENG> 4 inches</ENG>
 [_____] of epoxy resin].  Attachment shall withstand <MET>[4000] [6675] [_____] N</MET> <ENG>[900] [1500] [_____] pounds</ENG> pull 
without loosening the wire or anchor device.  Provide a non-metallic [plug flush with the anode end] [end cap] 
to prevent chaffing of the anode lead wire.  Cable to anode contact resistance shall be 0.02 ohms maximum.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.5.3   Mixed Metal Oxide Anode Lead Wires</TTL><BRK/>
<BRK/>
<TXT>[[Solidly crimp] [and solder] the connection between the anode rod or ribbon and the lead wire.  Seal the connection 
[with two layers of half lapped mastic tape covered with a heat shrinkable sleeve] [in cast epoxy].] [Tin and 
anneal the copper wire and hydraulically swage the tubular anode onto copper bushings in contact with the wire.  
Place a<MET> 28 mm</MET><ENG> 1 1/8 inch</ENG> long copper sleeve, inner diameter slightly larger than the tubular anode outer diameter, 
over the tube prior to swaging.]  Cable to anode contact resistance shall be 0.02 ohms maximum.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.1.6   <SUB>Anode Backfill</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The chemical composition listed is for example only.  The actual type 
and composition required shall be determined by the design engineer to provide 
adequate and economical service.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Calcined petroleum [metallurgical] coal coke breeze having the following analysis:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Chemical composition -</ITM><BRK/>
<BRK/>
<ITM>Fixed carbon               - [99.0] [_____] percent minimum</ITM><BRK/>
<ITM>Ash                        - [0.10] [_____] percent</ITM><BRK/>
<ITM>Moisture content           - [0.02] [_____] percent</ITM><BRK/>
<ITM>Sulphur                    - [4.29] [_____] percent (maximum)</ITM><BRK/>
<ITM>Volatile matter            - [0.22] [_____] percent</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Weight: <MET> [1045] [768] [1184] [_____] kg per cubic meter</MET><ENG> [65] [48] [74] lbs per cubic foot</ENG></ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Size: <MET> 6 mm</MET><ENG> 1/4 inch</ENG> maximum diameter [85 percent to pass a<MET> 9.5 mm</MET><ENG> 3/8 inch</ENG> mesh,] [100 
percent to pass<MET> 12.5 mm</MET><ENG> 1/2 inch</ENG> mesh.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Electrical resistivity:  [1] [10] [20] [50] [_____] ohm-cm [maximum] [loose] [tightly compacted]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.7   Gravel</TTL><BRK/>
<BRK/>
<TXT>100 percent to pass a<MET> 25 mm</MET><ENG> one inch</ENG> mesh.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>2.1.8   Anode Centering Device for Deep Anode Ground Beds</TTL><BRK/>
<BRK/>
<TXT>Centering device shall be [non-metallic] and capable of maintaining centering in the hole without interfering 
with other anode lead wiring until completion of backfilling operations.</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.1.9   Deep Anode Ground Bed Casing</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  A metal casing should not be used except for a maximum of<MET> 1.5 meter</MET><ENG> 5 
feet</ENG> at the top for a well cap which also serves as a support for the suspension 
ropes.  The drilling mud on the sides of the hole will usually keep the hole 
open until the anodes and coke breeze are installed.  If a casing must be used, 
it should be fiberglass reinforced plastic (non-metallic), should be located 
above the anode string and must be perforated to allow contact between the coke 
breeze and the surrounding electrolyte.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Casing shall be [_____]<MET> mm</MET><ENG> inch</ENG> outside diameter,<MET> 3.2 mm</MET><ENG> 1/8 inch</ENG> minimum wall thickness black steel pipe, conforming 
to <RID>ASTM A 53/A 53M</RID>, Type E or S, Grade B.  The top casing shall be [_____]<MET> mm</MET><ENG> inch</ENG>outside diameter,<MET> 3.2 mm</MET><ENG> 1/8 
inch</ENG> minimum wall thickness black steel pipe, conforming to <RID>ASTM A 53/A 53M</RID>, Type E or S, Grade B.  The metal 
casing shall extend no more than<MET> 1.5 meters</MET><ENG> 5 feet</ENG> below the top of a well cap.</TXT><BRK/>
<BRK/>
]</SPT></SPT><SPT><TTL>2.2   <SUB>ANODE VENT PIPE</SUB></TTL><BRK/>
<BRK/>
<TXT><RID>NEMA TC 2</RID>, Type [EPC-80-PE] [EPC-80-PVC],<MET> [38] [_____] mm</MET><ENG> [1 1/2] [_____] inches</ENG> in diameter and having [<ENG>3/16 
inch</ENG><MET>5 mm</MET> diameter holes located<MET> 150 mm</MET><ENG> 6 inch</ENG> apart and at<MET> 1.57 rad</MET><ENG> 90 degrees</ENG> around the vent pipe] [vertical 
slits parallel to the pipe longitudinal centerline,<MET> 38 mm</MET><ENG> 1.5 inches</ENG> long,<MET> 0.15 mm</MET><ENG> 0.006 inch</ENG> wide, spaced<MET> 152 
mm</MET><ENG> 6 inches</ENG> apart longitudinally and<MET> 25 mm</MET><ENG> one inch</ENG> apart circumferentially around the vent pipe] along the length 
of vent tube which is in the coke breeze backfill.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3   <SUB>RECTIFIERS</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Air-cooled rectifiers will be used for most applications in non-corrosive 
atmospheres.  Where highly corrosive atmosphere exist, the equipment will be 
oil-immersed in a tank type housing.  For hazardous area applications, oil-immersed 
equipment will be provided with an explosion-proof or dust-ignition-proof housing, 
as appropriate.  Transformer tap adjusters will be provided in cases where an 
automatic system is not provided.  Variacs should not be used where subjected 
to corrosive or marine air atmospheres.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>2.3.1   Transformer</TTL><BRK/>
<BRK/>
<TXT><RID>UL 506</RID> and <RID>NEMA ST 1</RID>, as applicable.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.2   Electrical Ratings</TTL><BRK/>
<BRK/>
<TXT>Electrical ratings as follows:  input voltage at 60 Hz: [[115] [208] [230] volts single phase] [[208] [230] [460] 
volts three phase].</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Output voltage, dc:  [9] [12] [18] [24] [_____] volts [As indicated].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Output current, dc:  [8] [16] [24] [32] [_____] amperes [As indicated]</ITM><BRK/>
<BRK/>
<TXT>The rectifier shall be capable of supplying continuous full rated output at an ambient temperature of<MET> 44 degrees 
C</MET><ENG> 112 degrees F</ENG> in full sunlight with expected life of 10 years minimum.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.3   Rectifier Stacks</TTL><BRK/>
<BRK/>
<TXT>[Silicon] [_____] connected in such a manner as to provide full wave rectification.  [Silicon diodes shall be 
protected by selenium cells or varistors against overvoltage surges and by current limiting devices against overcurrent 
surges.]</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>2.3.4   Enclosure</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose this paragraph for air-cooled rectifier enclosures or the paragraph 
below entitled "Oil Immersed Enclosures."  Oil immersed enclosures shall be 
used where highly corrosive atmosphere exist.  When locating oil immersed rectifiers 
near buildings, consult with paragraph 3.2.3 of MILHDBK 1008C for fire safety 
requirements.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>NEMA ICS 6</RID>, Type [3] [3X] [4] [4X] [7] [_____], suitable for [wall] [post] [pad] mounting.  Enclosure shall include 
hinged door with [padlock hasp] [key lock, provide [three] [_____] keys].  [Enclosure locks shall be keyed alike.]  
Fit enclosure with screened openings to provide for cooling by natural convection.  Provide holes, conduit knockouts 
and threaded hubs of sufficient size and location.  The cabinet and mounting support shall be [painted] [hot-dipped 
galvanized] [stainless] steel [according to the manufacturer's standards].</TXT><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>2.3.5   Oil Immersed Enclosures</TTL><BRK/>
<BRK/>
<TXT>Provide enclosures of 11-gage steel or heavier, with an accessible drain plug.  The oil level shall be clearly 
marked.  Provide a hinged lid with quick release clamps to secure it in a closed position.  Provide a compressive, 
oil resistant, positive sealing gasket.  Base mounting shall have<MET> 100 mm</MET><ENG> 4 inch</ENG> high channels.  Provide an internal 
terminal board and connections above oil level for monitoring and adjustment.  The cabinet and mounting support 
shall be [painted] [hot-dipped galvanized] [stainless] steel [according to the manufacturer's standards].</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>2.3.6   Overload and Short Circuit Protection</TTL><BRK/>
<BRK/>
<TXT><RID>UL 489</RID>, Molded case circuit breaker, [magnetic] [thermal-magnetic] type.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.7   D.C. Output Control</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  A minimum of five coarse and five fine taps is recommended to provide 
sufficient voltage adjustment.  Variacs should not be used where subjected to 
corrosive or marine air atmospheres.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>D.C. output voltage shall be adjustable.  Transformer taps, [5] [_____] coarse, [[5] [_____] fine.]  [Variac.] 
[_____].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.8   Output Voltage and Current Metering</TTL><BRK/>
<BRK/>
<TXT>Provide separate panel voltmeter and ammeter, not less than<MET> 63.5 mm</MET><ENG> 2 1/2 inch</ENG> [rectangular] [round], two percent 
full scale accuracy [at<MET> 30 degrees C</MET><ENG> 80 degrees F</ENG>, temperature stability above and below<MET> 30 degrees C</MET><ENG> 80 degrees 
F</ENG> of at least one percent per<MET> 5 degrees C</MET><ENG> 10 degrees F</ENG>]. Provide an "ON-OFF" toggle switch for each meter.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.9   Surge Protection</TTL><BRK/>
<BRK/>
<TXT>Protect silicon diodes by use of AC and DC lightning arresters or metal oxide varistors against overvoltage surges 
and by current-limiting device against overcurrent surges.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.10   Efficiency</TTL><BRK/>
<BRK/>
<TXT>Overall efficiency of [65 percent] [90 percent] [_____] minimum when operated at full output.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.11   Grounding Provisions</TTL><BRK/>
<BRK/>
<TXT><RID>NFPA 70</RID> and <RID>UL 467</RID> including a grounding terminal in the cabinet. Grounding conductor from terminal to earth 
grounding system shall be solid or stranded copper not smaller than No. 6 AWG.  Earth grounding system shall 
consist of one or more [copper] [copper clad steel] rods.  Ground rods shall be a minimum of<MET> 2435 mm</MET><ENG> 8 feet</ENG> long.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.12   <SUB>Shunt Resistors</SUB></TTL><BRK/>
<BRK/>
<TXT><RID>MIL-I-1361</RID>.  Resistors shall be located on the rectifier front panel and clearly marked with current and voltage 
for verification of panel ammeter.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.13   Wiring Diagram</TTL><BRK/>
<BRK/>
<TXT>Provide complete wiring diagram of the power unit showing both A.C. supply and D.C. connections to anodes on 
the inside of the cabinet door.  Show and label components.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.14   <SUB>Rectifier Replacement/Spare Parts List</SUB></TTL><BRK/>
<BRK/>
<TXT>Provide identification and coverage for all parts of each component, assembly, and accessory of the items subject 
to replacement in accordance with Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE DATA.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.4   CONDUIT AND CABLE FOR POWER SERVICE AT 600 VOLTS OR LESS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.4.1   Conduit</TTL><BRK/>
<BRK/>
<TXT>[<RID>UL 6</RID>, rigid galvanized steel] [Outlet boxes:  <RID>UL 514A</RID> and, Fittings: <RID>UL 514B</RID>, threaded hubs.]  [Metallic conduit 
and fittings to be polyvinylchloride coated in accordance with <RID>NEMA RN 1</RID>, Type A40.] [<RID>NEMA TC 2</RID>, Type EPC-40-PVC.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.2   <SUB>Cable and Wire</SUB> Other Than Anode Lead Wires</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Type THW insulation can only be obtained in large quantity.  Use of this 
type insulation is not recommended for small project.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Copper conductors conforming to <RID>ASTM B 3</RID> and <RID>ASTM B 8</RID>.  Wires terminating at a rectifier, junction box, or test 
station shall have cable identification tags.  Refer to paragraph 2.1.4 [_____] for anode lead wires.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.4.2.1   AC Power Supply Wiring</TTL><BRK/>
<BRK/>
<TXT>[<RID>UL 83</RID>, Type [THW] [THWN] [TW]] [<RID>UL 44</RID>, Type RHW,] [<RID>UL 854</RID>, Type USE], stranded [solid] copper conductors, gage 
(AWG) as indicated. </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.2.2   Rectifier DC Negative (Structure) Cable(s)</TTL><BRK/>
<BRK/>
<TXT><RID>ASTM D 1248</RID>, High Molecular Weight Polyethylene (HMWPE) insulation, stranded copper conductors, gage (AWG) as 
indicated.</TXT><BRK/>
<BRK/></SPT>
[<SPT><TTL>2.4.2.3   Rectifier DC Positive (Anode) Header Cable(s)</TTL><BRK/>
<BRK/>
<TXT><RID>ASTM D 1248</RID>, High Molecular Weight Polyethylene (HMWPE) insulation, stranded copper conductors, gage (AWG) as 
indicated.  Refer to paragraph 2.1.4 [_____] for anode lead wires.</TXT><BRK/>
<BRK/></SPT>
]<SPT><TTL>2.4.2.4   Continuity Bond Cables</TTL><BRK/>
<BRK/>
<TXT><RID>ASTM D 1248</RID>, High Molecular Weight Polyethylene (HMWPE) insulation, stranded copper conductors, gage (AWG) as 
indicated.  Do not use bare copper wire for joint continuity bonds.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.4.3   Cable and Wire Identification Tags</TTL><BRK/>
<BRK/>
<TXT>[Laminated plastic material with black letters on a yellow background] [[Brass] [Stainless steel] material with 
stamped or engraved letters].  Print letters and numbers a minimum of<MET> 5 mm</MET><ENG> 3/16 inch</ENG> in size.  Provide identifier 
legend [in accordance with the drawings] [_____].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.4   Wire Connectors</TTL><BRK/>
<BRK/>
<TXT>[<RID>UL 486A-486B</RID>.] [Solderless copper crimp connections.] [Exothermic weld.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.5   Insulating Tape</TTL><BRK/>
<BRK/>
<TXT><RID>UL 510</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.6   Underground Splices</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Splices and damaged anode lead wire insulation are a common cause of 
premature failure.  Splices are not normally allowed except under certain circumstances.  
If splices are allowed, select the appropriate option.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[Splices are not permitted in buried sections of anode header cable.]  Provide splices with a compression connector 
on the conductors, and insulation and waterproofing using one of the following methods which are suitable for 
continuous  submersion in water and comply with <RID>NEMA C119.1</RID>.</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Provide cast-type splice insulation by means of molded casting process employing a thermosetting 
epoxy resin insulating material applied by a gravity poured method or pressure injected method.  
Provide component materials of the resin insulation in a packaged form ready for  convenient 
mixing without removing from the package.</ITM><BRK/>
<BRK/>
<ITM>(1) Gravity poured method shall employ materials and equipment contained in and approved commercial 
splicing kit which includes a mold suitable for the cables to be spliced.  When the mold is 
in place around the joined conductors, prepare the resin mix and pour into the mold.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Provide [heavy wall] heat shrinkable splice insulation by means of a thermoplastic adhesive 
sealant material which shall be applied by a clean burning propane gas torch.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.7   Buried Cable Warning and Identification Tape</TTL><BRK/>
<BRK/>
<TXT>Polyethylene tape, manufactured for warning and identification of buried cable and conduit.  Tape shall be<MET> [75] 
[_____] mm</MET><ENG> [3] [_____] inches</ENG> wide, [Yellow] [_____] in color and read "Caution Buried Cable Below" or similar.  
Color and lettering shall be permanent and unaffected by moisture or other substances in backfilling.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.5   <SUB>ANODE JUNCTION BOXES</SUB> AND <SUB>TEST STATIONS</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>2.5.1   Flush Mounted Type</TTL><BRK/>
<BRK/>
<TXT><RID>NEMA ICS 6</RID>.  Metallic or non-metallic with terminal board, [5] [8] [_____] terminal posts [and lockable lid].  
A non-metallic enclosure shall be molded of glass filled polycarbonate and urethane coated or ABS plastic [and 
mounted on a<MET> 500 mm</MET><ENG> 18 inch</ENG> length of PVC conduit].  The unit shall be of standard design, manufactured for use 
as a cathodic protection test station, complete with cover, terminal board, shunts, and brass or Type [304] [316] 
stainless steel hardware.  The terminal board shall be removable for easy access to wires.  [Provide traffic 
valve box capable of withstanding [H-20] [_____] traffic loads.]  The cover shall have a cast in legend "CP TEST."</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.2   Post Top Mounted Type</TTL><BRK/>
<BRK/>
<TXT><RID>NEMA ICS 6</RID>.  Metallic or non-metallic with terminal board, [5] [8] [_____] terminal posts and lockable lid.  
A non-metallic enclosure shall be high impact strength molded plastic.  The unit shall be of standard design, 
manufactured for use as a cathodic protection test station, complete with cover, terminal board, shunts, and 
brass or Type [304] [316] stainless steel hardware.  The terminal board shall be removable for easy access to 
wires.  The test station shall be mounted atop<MET> 1830 mm</MET><ENG> 6 foot</ENG> long polyethylene conduit with anchor.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.3   Wall Mounted Type</TTL><BRK/>
<BRK/>
<TXT><RID>NEMA ICS 6</RID>, Type [3R] [4X] [_____] enclosure with [clamped cover] [Type [304] [316] stainless steel hinges and 
[clamped] [latched] cover] [and padlocked hasp].  Enclosure shall be of [galvanized steel] [painted steel] [aluminum] 
[fiberglass] [non-metallic] construction with terminal board and labeled with nameplate.  Provide nameplate in 
accordance with Section <SRF>26 00 00.00 20</SRF> GENERAL ELECTRICAL MATERIALS AND METHODS.  Enclosure mounting posts shall 
be [galvanized steel pipe,schedule [40] [80] [_____]], [wood post, full length pressure treated with pentachlorophenol] 
[as indicated].  Mount enclosure<MET> 1066 mm</MET><ENG> 42 inches</ENG> above finished grade [as indicated].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.4   Terminal Boards</TTL><BRK/>
<BRK/>
<TXT>Provide terminal boards for anode junction boxes, bonding boxes, and test stations made of phenolic plastic<MET> [3] 
[6] [_____] mm</MET><ENG> [1/8] [1/4] [_____] inch</ENG> thick with dimensions as indicated.  Insulated terminal boards shall 
have the required number of terminals (one terminal required for each conductor).  Install solderless copper 
lugs and copper buss bars, shunts, and variable resistors on the terminal board as indicated.  Test station terminal 
connections shall be permanently tagged to identify each termination of conductors (e.g. identify the conductors 
connected to the protected structure, anodes, and reference electrodes).  Conductors shall be permanently identified 
by means of plastic or metal tags, or plastic sleeves to indicate termination.  [Each conductor shall be color 
coded as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">Anode lead wire - black</ITM><BRK/>
<ITM INDENT="-0.33">Structure lead wire - white</ITM><BRK/>
<ITM INDENT="-0.33">Reference electrode lead wire - red]</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.5   <SUB>Shunt Resistors</SUB></TTL><BRK/>
<BRK/>
<TXT>[<RID>MIL-I-1361</RID>.]  [0.01] [______] ohm, [6] [______] ampere, accuracy plus or minus one percent, [manganin wire] 
[______] type.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.6   Pavement Insert</TTL><BRK/>
<BRK/>
<TXT>Pavement insert shall be a non-metallic flush type test station without terminal board, and shall allow a copper-copper 
sulfate reference electrode to contact the electrolyte beneath the pavement surface.  [Provide traffic valve 
box capable of withstanding [H-20] [_____] traffic loads.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.5.7   Cast-In-Place Concrete</TTL><BRK/>
<BRK/>
<TXT>Flush mount type test stations, bonding boxes, and anode junction boxes shall be centered in a<MET> 460 x 460 x 102 
mm</MET><ENG> 18 x 18 x 4 inch</ENG> concrete slab.  Concrete shall be<MET> 20 Mpa</MET><ENG> 3000 psi</ENG> minimum ultimate 28-day compressive strength 
with <MET>25 mm</MET> <ENG>1-inch</ENG> minimum aggregate conforming to [<RID>ASTM C 94/C 94M</RID>] [Section <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE].</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.6   <SUB>INSULATING FLANGE SETS</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  On projects having piping installed by DIVISION 2, SITE WORK and/or DIVISION 
15, MECHANICAL, coordinate the requirements for flanges and unions with the 
appropriate section(s).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide full-faced gaskets, insulating sleeves and washers, and steel washers.  Provide flange sets rated for 
operation at the rated pressure and temperature of the flanges.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.6.1   Gaskets</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Do not use asbestos materials.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASME B16.21</RID>. [Neoprene faced phenolic] [Laminated phenolic] material for operations at<MET> [862] [_____] kPa</MET><ENG> [125] 
[_____] psi</ENG> and<MET> [232] [_____] degrees C</MET><ENG> [450] [_____] degrees F</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6.2   Insulating Washers and Sleeves</TTL><BRK/>
<BRK/>
<TXT>Two sets<MET> 3 mm</MET><ENG> 1/8 inch</ENG> [laminated phenolic] [_____] for operation at<MET> [232] [_____] degrees C</MET><ENG> [450] [_____] degrees 
F</ENG>.  Insulating washers shall fit within the bolt facing on the flange over the outside of the fabric reinforced 
sleeves.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.6.3   Washers</TTL><BRK/>
<BRK/>
<TXT>Steel, cadmium plated, to fit within the bolt facing on the flange.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.7   <SUB>DIELECTRIC UNIONS</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  On projects having piping installed by DIVISION 2, SITE WORK and/or DIVISION 
15, MECHANICAL, coordinate the requirements for flanges and unions with the 
appropriate section(s).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASME B16.39</RID>, Class [1] [2] for dimensional, strength, and pressure requirements.  Insulation barrier shall limit 
galvanic current to one percent of the short-circuit current in a corresponding metallic joint. Provide insulating 
material impervious to [water] [oil] [gas].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.8   BONDING AND GROUNDING EQUIPMENT</TTL><BRK/>
<BRK/>
<TXT><RID>UL 467</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.9   ELECTRICAL INSULATING COATINGS</TTL><BRK/>
<BRK/>
<TXT>[Heat-shrinkable tape] [Conformable water tight sealant having dielectric strength not less than 15 kV for a<MET> 
3 mm</MET><ENG> 1/8 inch</ENG> thick layer].</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Rectifiers shall be pad or post mounted.  Select the appropriate paragraph.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/></SPT>
<SPT>[<TTL>2.10   CONCRETE RECTIFIER PAD</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Provide detail on the drawings.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Dimensions, conduit locations, and anchor bolt location [as indicated] [in accordance with] the manufacturer's 
drawings for the equipment furnished.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.10.1   Concrete</TTL><BRK/>
<BRK/>
<TXT><MET>20.67 MPa</MET><ENG>3000 psi</ENG> concrete conforming to [<RID>ASTM C 94/C 94M</RID>] [Section <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE.]</TXT><BRK/>
<BRK/></SPT>
]</SPT><SPT>[<TTL>2.11   RECTIFIER MOUNTING POST</TTL><BRK/>
<BRK/>
<TXT>[Galvanized steel pipe, Schedule [40] [80]], [wood post, full length pressure treated with pentachlorophenol].</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>2.12   <SUB>CASING INSULATORS AND SEALS</SUB></TTL><BRK/>
<BRK/>
<TXT>Casing insulators shall have a minimum<MET> [305] [_____] mm</MET><ENG> [12] [_____] inch</ENG> band width, [constructed of heat fused 
plastic coated steel] [_____] and multi-segmented to attach firmly around the pipe.  Casing end seals shall be 
S-shaped rubber seals with stainless steel straps.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.13   PERMANENT <SUB>REFERENCE ELECTRODES</SUB></TTL><BRK/>
<BRK/>
<TXT>Permanent reference electrodes shall be [copper copper-sulfate] [silver silver-chloride] [zinc] specifically 
manufactured for [underground] [marine] use,<MET> [31.75] [_____] mm</MET><ENG> [1 1/4] [_____] inch</ENG> diameter, by<MET> [255] [_____] 
mm</MET><ENG> [10] [_____] inches</ENG> long, [plastic [_____] tube with an ion trap to minimize contamination of the cell] [, 
and a minimum surface sensing area of <MET>[______] square centimeters</MET><ENG>[______] square inches</ENG>].  [The cell shall be 
prepackaged by the manufacturer with a backfill material as recommended by the manufacturer.] Provide cells with 
No. [10] [12] [_____] AWG, [THHN] [_____] cable of sufficient length to extend to the [test station] [junction 
box] without splicing.  Reference electrodes shall have a minimum 15 year life, stability of plus or minus 5 
millivolts under 3 microamp load, and an initial accuracy of plus or minus 10 millivolts referenced to a calibrated 
portable reference electrode.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.14   STEEL FLANGES AND BOLTING</TTL><BRK/>
<BRK/>
<SPT><TTL>2.14.1   Steel Flanges</TTL><BRK/>
<BRK/>
<TXT><RID>ASME B16.5</RID><MET> [667.5] [1335] [_____] N</MET><ENG> [150] [300] [_____] lb</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.14.2   Bolting</TTL><BRK/>
<BRK/>
<TXT><RID>ASTM A 307</RID>, Grade B for bolts: <RID>ASTM A 194/A 194M</RID>, Grade 2 for nuts.  Dimensions <RID>ASME B18.2.1</RID> for bolts, <RID>ASME B18.2.2</RID>
 for nuts.  Threads: <RID>ASME B1.1</RID>, Class 2A fit for bolts, Class 2B fit for nuts.  Bolts shall extend completely 
through the nuts and may have reduced shanks of a diameter not less than the diameter at the roof of the threads.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.15   EXOTHERMIC WELD KITS</TTL><BRK/>
<BRK/>
<TXT>Exothermic weld kits specifically designed by the manufacturer for welding the types of materials and shapes 
provided.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   <SUB>ANODE INSTALLATION</SUB></TTL><BRK/>
<BRK/>
<TXT>[<RID>IEEE C2</RID>] [<RID>NFPA 70</RID>].</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.1   Anodes and Lead Wires</TTL><BRK/>
<BRK/>
<TXT>Provide anodes and lead wires as follows [and in accordance with <RID>NACE SP0572</RID>].</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select the applicable paragraph(s) from the following dependent upon 
selection of vertical or horizontal anodes.  Deep well anode beds may also be 
used.  Designer shall select anode and installation procedures for specific 
site.  Provide detail on the drawings.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT>[<TTL>3.1.1.1   Vertical Anodes</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Excavation for anodes:  Excavate hole to [a minimum<MET> 75 mm</MET><ENG> 3 inches</ENG> larger than the packaged 
anode diameter.] [the diameter indicated.]  [<MET>1220 mm</MET><ENG>4 feet</ENG> deeper than the anode length.] [the 
depth indicated.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Excavation for wire trench:  Excavate lead [and main feeder] wire trenches to [the depth 
indicated] [not less than<MET> [455] [610] mm</MET><ENG>[18] [24] inches</ENG> deep], [<MET>[150] [_____] mm</MET><ENG>[6] [_____] 
inches</ENG> wide] [width as indicated].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Lifting anodes:  Do not lift or support anode by the lead wire.  Exercise care to preclude 
damaging the anode and the lead wire insulation.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Installing anodes:  [Place<MET> 305 mm</MET><ENG> 12 inches</ENG> of coke breeze in the hole and tamp well.  Center 
the anode in the hole and place<MET> 305 mm</MET><ENG> 12 inches</ENG> of additional coke breeze and tamp well taking 
care not to strike and damage the anode lead wire.  Repeat sequence until coke breeze is<MET> 305 
mm</MET><ENG> 12 inches</ENG> above the anode.]  [Center the canister anode in the hole.  Completely fill the 
annular space between the canister and the wall of the hole with a slurry of stone free earth.]  
[Place a vent pipe vertically above the anode.  Cut the pipe to sufficient length to extend 
from<MET> 75 mm</MET><ENG> 3 inches</ENG> within the coke breeze to<MET> 75 mm</MET><ENG> 3 inches</ENG> below finish grade.  Place gravel 
around the vent pipe to a level<MET> 150 mm</MET><ENG> 6 inches</ENG> below finish grade.]  Fill the remaining excavation 
with soil and tamp.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Installing lead wires:  Provide anodes with lead wires of sufficient length to extend to 
the anode junction box without splicing.  Cover the lead [and main feeder] wire trench bottom 
with a<MET> 75 mm</MET><ENG> 3 inch</ENG> layer of sand or stone free earth.  Center wire on the backfill layer.  
Handle to eliminate damage to the cable and insulation, do not stretch or kink the conductor.  
Place backfill over wire in layers not exceeding<MET> 150 mm</MET><ENG> 6 inches</ENG> deep, compact each layer thoroughly.  
Do not place tree roots, wood scrap, vegetable matter and refuse in the backfill.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Splices and damaged anode lead wire insulation are a common cause of 
premature failure.  Splices are not normally allowed except under certain circumstances.  
If splices are allowed, select the "Anode lead to main feeder connections" option.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM INDENT="-0.33">f.  Splices not allowed:  Splices, or repairs to damaged anode lead wire insulation are not 
allowed.  Install anode lead wires back to the anode junction box as indicated in the drawings.  
[Anode lead to main feeder connections:  Make connections as follows:</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[(1)  Remove insulation to expose approximately<MET> 50 mm</MET><ENG> 2 inches</ENG> of each conductor.</ITM><BRK/>
<BRK/>
<ITM>(2)  Make connection between conductors using solderless crimp connector or exothermic weld.</ITM><BRK/>
<BRK/>
<ITM>(3)  Cover connection with uncured butyl rubber tape to provide filler wrap.</ITM><BRK/>
<BRK/>
<ITM>(4)  Apply four layers of half-lapped neoprene tape, extend the tape over the cable insulation.</ITM><BRK/>
<BRK/>
<ITM>(5)  Apply two layers of half-lapped pressure sensitive polyethylene or polyvinyl chloride tape.]</ITM><BRK/>
<BRK/>
<ITM>[(1) Remove insulation to expose approximately<MET> 50 mm</MET><ENG> 2 inches</ENG> of each conductor.</ITM><BRK/>
<BRK/>
<ITM>(2)  Make connection between conductors using solderless crimp connector or exothermic weld.</ITM><BRK/>
<BRK/>
<ITM>(3)  Cover connection with pre-manufactured splice kit.]]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g. Anode junction box.  Mark each of the wires terminating in the junction box.  Install anode 
junction box as shown in the drawings [prior to pouring the concrete slab].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Installing lead wires.  Connect anode lead wires to the appropriate terminals in the anode 
junction box.</ITM><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>3.1.1.2   Horizontal Anodes</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Excavation for anodes:  Excavate anode trenches to [the depth indicated,<MET> 610 mm</MET><ENG> two feet</ENG>
 longer than the anode,<MET> 305 mm</MET><ENG> one foot</ENG> wide] [the depth, length, and width indicated].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Excavation for wire trench:  Excavate lead [and main feeder] wire trenches to [the depth 
indicated] [not less than<MET> [455] [610] mm</MET><ENG> [18] [24] inches</ENG> deep], [<MET>[150] [_____] mm</MET><ENG>[6] [_____] 
inches</ENG> wide] [width as indicated].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Lifting anodes:  Do not lift or support anode by the lead wire.  Exercise care to preclude 
damaging the anode and the lead wire insulation.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Installing anodes:  Place<MET> [100] [_____] mm</MET><ENG> [4] [_____] inches</ENG> of coke breeze in the anode 
trench and tamp well.  Center the anode in the trench and cover with coke breeze to provide 
a minimum<MET> [100] [_____] mm</MET><ENG> [4] [_____] inch</ENG> cover over the anode.  Tamp the coke breeze firm 
taking care not to strike and damage the anode lead wire.  [Place a vent pipe vertically above 
the anode.  Cut the pipe to sufficient length to extend from<MET> 75 mm</MET><ENG> 3 inches</ENG> within the coke 
breeze to<MET> 75 mm</MET><ENG> 3 inches</ENG>below finish grade.  Place gravel around the vent pipe to a level<MET> 150 
mm</MET><ENG> 6 inches</ENG> below finish grade.]  Fill the remaining excavation with soil and tamp.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Installing lead wires:  Provide anodes with lead wires of sufficient length to extend to 
the anode junction box without splicing.  Cover the lead [and main feeder] wire trench bottom 
with a<MET> 75 mm</MET><ENG> 3 inch</ENG> layer of sand or stone free earth.  Center wire on the backfill layer.  
Handle to prevent damage to the cable and insulation, do not stretch or kink the conductor.  
Place backfill over wire in layers not exceeding<MET> 150 mm</MET><ENG> 6 inches</ENG> deep, compacting each layer 
thoroughly.  Do not place tree roots, wood scrap, vegetable matter, and refuse in the backfill.  
Place cable warning tape, within<MET> [455] [_____] mm</MET><ENG> [18] [_____] inches</ENG> of finished grade, above 
buried cable and conduit.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Splices and damaged anode lead wire insulation are a common cause of 
premature failure.  Splices are not normally allowed except under certain circumstances.  
If splices are allowed, select the "Anode lead to main feeder connections" option.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM INDENT="-0.33">f.  Splices not allowed:  Splices, or repairs to damaged anode lead wire insulation are not 
allowed.  Install anode lead wires back to the anode junction box as indicated in the drawings.  
[Anode lead to main feeder connections:  Make connectors as follows:</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Choose one of the following options.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM>[(1) Remove insulation to expose approximately<MET> 50 mm</MET><ENG> 2 inches</ENG> of each conductor.</ITM><BRK/>
<BRK/>
<ITM>(2)  Make connection between conductors using solderless crimp connector or exothermic weld.</ITM><BRK/>
<BRK/>
<ITM>(3)  Cover connection with uncured butyl rubber type to provide filler wrap.</ITM><BRK/>
<BRK/>
<ITM>(4)  Apply four layers of half-lapped neoprene tape, extend the tape over the cable insulation.</ITM><BRK/>
<BRK/>
<ITM>(5)  Apply two layers of half-lapped pressure sensitive polyethylene or polyvinyl chloride tape.]</ITM><BRK/>
<BRK/>
<ITM>[(1) Remove insulation to expose approximately<MET> 50 mm</MET><ENG> 2 inches</ENG> of each conductor.</ITM><BRK/>
<BRK/>
<ITM>(2)  Make connection between conductors using solderless crimp connector or exothermic weld.</ITM><BRK/>
<BRK/>
<ITM>(3)  Cover connection with pre-manufactured splice kit.]</ITM>]<BRK/>
<BRK/>
<ITM INDENT="-0.33">g. Anode junction box.  Mark each of the wires terminating in the junction box.  Install anode 
junction box as shown in the drawings [prior to pouring the concrete slab].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Installing lead wires.  Connect anode lead wires to the appropriate terminals in the anode 
junction box.</ITM><BRK/>
<BRK/>
]</SPT><SPT>[<TTL>3.1.1.3   Deep Well Anode Ground beds</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Drilling of anode well.  Drilling of the anode well shall be accomplished by a qualified 
well driller.  Submit documentation of experience to the Contracting Officer.  Drill a hole<MET> 
[254] [305] [_____] mm</MET><ENG> [10] [12] [_____] inches</ENG> in diameter to the depth indicated using rotary 
bit equipment designed specifically for this purpose.  Select the type and consistency of drilling 
fluids to be consistent with soil characteristics.  The use of temporary well casings may be 
necessary.  Remove all temporary casings upon completion of the installation.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Excavation for wire trench.  Excavate anode header cable [_____] wire trenches to [the depth 
indicated] [not less than<MET> [455] [610] mm</MET><ENG> [18] [24] inches</ENG> deep], [<MET>[150] [_____] mm</MET><ENG>[16] [_____] 
inches</ENG> wide] [width as indicated].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Installing anodes.  Do not lift or support anode by the lead wire.  Exercise care to preclude 
damaging the anode and the lead wire insulation.  Attach the anode centralizers to the anodes.  
[Place the vent pipe in the hole as indicated prior to installing the anodes.  Install the anodes 
in the hole at the depths indicated and supported in place using a method that does not suspend 
the anodes by the lead wire.]  [Strap the [anodes] [anode assembly] to the vent pipe spaced 
as indicated on the drawings.  Lower the anode/vent pipe assembly into the hole.]  [Label and 
coil the excess anode lead wire at the top of the casing].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Coke backfill.  Pump the coke back fill into the hole through a separate removable tube 
with the tip at the bottom of the hole.  Pumping operations shall be continuous.  Maintain a 
continuous supply of fluidized coke at the pump suction until coke is filled to the top of the 
hole.   Allow the coke to settle for [24] [_____] hours.  Verify the level of coke and provide 
additional as necessary until the level of coke is not lower than that indicated in the drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  [Casing.  Install well head casing as indicated.  Seal the annular space between the casing 
and earth with cement grout.  Seal the top of the anode well as shown on the drawings.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Anode well access box.  Place the anode well access box around the top of the casing, and 
pour the concrete slab around the box as indicated.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Anode junction box.  Install anode junction box as shown in the drawings [prior to pouring 
the concrete slab].</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Installing lead wires.  Provide anodes with lead wires of sufficient length to extend to 
the anode junction box without splicing.  Splices, or repairs to damaged anode lead wire insulation 
are not allowed.  Mark each of the wires terminating in the junction box.  Connect anode lead 
wires to the appropriate terminals in the anode junction box.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">i.  Anode header cable.  Provide anodes header cable of sufficient length to extend to the anode 
junction box without splicing.  Splices, or repairs to damaged anode header cable wire insulation 
are not allowed.  Cover the anode header cable trench bottom with a<MET> 75 mm</MET><ENG> 3 inch</ENG> layer of sand 
or stone free earth.  Center wire on the backfill layer.  Handle cable to prevent damage to 
the cable and insulation, do not stretch or kink the conductor.  Place backfill over wire in 
layers not exceeding<MET> 150 mm</MET><ENG> 6 inches</ENG> deep, compact each layer thoroughly.  Do not place tree 
roots, wood scrap, vegetable matter and refuse in the backfill.  Connect the anode header cable 
to the appropriate terminal in the anode junction box.</ITM><BRK/>
<BRK/>
]</SPT></SPT><SPT><TTL>3.1.2   Wire-To-Structure Connections</TTL><BRK/>
<BRK/>
<TXT>Connect wire to [pipe] [tank] structure [_____] [by use of a exothermic weld kit] [by brazing].  Clean the structure 
surface by scraping, filing or wire brushing to produce a clean, bright surface. [Weld connections using the 
exothermic weld kits in accordance with the kit manufacturer's instructions.]   Test the integrity of the weld, 
prior to coating, by striking with a<MET> 908 gram</MET><ENG> two pound hammer</ENG>.  Cover connections and exposed structures with 
an electrically insulating coating, compatible with existing coating.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.2.1   Safety Precautions Around Fuel Facilities</TTL><BRK/>
<BRK/>
<TXT>Contractor shall take proper safety precautions prior to and during welding to live fuel pipelines [tanks].  
Contractor shall notify the activity Fuel Office via the Contracting Officer a minimum of three days before performing 
exothermic welding to live fuel lines.  Exothermic welding shall be conducted with fuel flowing through the pipeline 
to eliminate vapor spaces within the pipe and to dissipate the heat on the pipe.  Exothermic weld charges for 
connections to fuel lines shall be limited to a maximum 15 gram charge to prevent burning through the pipe wall.  
Exothermic weld connections shall be spaced a minimum of<MET>150 mm</MET><ENG> 6 inches</ENG> apart.  In the event of an unsuccessful 
weld, the new weld location shall be located a minimum of 6 inches from the unsuccessful weld and any other existing 
welds.  Contractor shall obtain the services of a certified Marine Chemist or Certified Industrial Hygienist 
[to monitor the construction site during exothermic welding work and certify that the area is free of flammable 
vapors and otherwise safe for work.] [to approve the contractor's exothermic welding safety procedures.  Results 
of this consultation shall be included in the Contractor's Daily Report.]</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.1.3   Rectifiers</TTL><BRK/>
<BRK/>
<TXT>Location and mounting as indicated.  Assemble and attach equipment enclosures to [wall] [post] [pad] in accordance 
with the manufacturer's instructions.  Handle wires to prevent stretching or kinking the conductors or damaging 
the insulation.  Use lubricants when pulling wires into conduits.  Bond the equipment enclosures to a grounding 
electrode.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.4   Test Stations [and Permanent Reference Electrodes]</TTL><BRK/>
<BRK/>
<TXT>Locate test stations [and permanent reference electrodes] [as indicated.] as follows: </TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  At<MET> [305] [_____] meters</MET><ENG> [1000] [_____] foot</ENG> intervals.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  At insulating joints.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  At both ends of casings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Where the pipe crosses any other metal pipes.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Where the pipe connects to an existing old piping system not under cathodic protection.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Where the pipe connects to a dissimilar metal pipe.</ITM><BRK/>
<BRK/>
<TXT>Do not fill the bottom of the test station with concrete unless otherwise specified.  Do not place rubbish, scrap 
or other debris into the test station.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.1.4.1   <TST>Permanent Reference Electrode Calibration</TST> and Installation</TTL><BRK/>
<BRK/>
<TXT>Provide [prepackaged] [copper copper-sulfate] [silver-silver chloride] [zinc] reference electrode(s) as indicated 
in the drawings.  Prior to installation, soak the [prepackaged] reference electrode in a container of potable 
water for 30 minutes.  Do not use seawater [except for silver-silver chloride electrodes intended for use in 
seawater].  Calibrate the permanent reference electrode in the presence of the contracting officer or his approved 
representative by measuring the potential difference between the permanent reference electrode and an independent 
(portable) calibrated reference electrode placed in the water adjacent to the permanent reference electrode.  
[Potential differences between the two electrodes of the same generic type should not exceed [10] [15] millivolts 
when the [sensing windows of the] two electrodes being compared are not more than<MET> 2 mm</MET><ENG> 1/6 inch</ENG> apart but not 
touching.]  [Zinc permanent reference electrodes should be within the range of -1000 to -1150 millivolts when 
calibrated with an independent (portable) calibrated copper-copper sulfate reference electrode with the two electrodes 
being not more than<MET> 2 mm</MET><ENG> 1/6 inch</ENG> apart but not touching.]  Permanent reference electrodes not within these potential 
differences shall be removed from the construction site by the end of the day and replaced at the contractor's 
expense.  [Prior to completely backfilling over reference electrodes, again verify the accuracy of the reference 
electrode.]  The testing provision shall also apply to replacement reference electrodes as well.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.1.5   <SUB>Bonding Boxes</SUB></TTL><BRK/>
<BRK/>
<TXT>Provide structure bonding boxes in locations [as indicated] [where the protected structure crosses or comes into 
close proximity to other metal structures that are unprotected or protected by its own electrically isolated 
cathodic protection system(s)].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.6   Insulating Flange Sets</TTL><BRK/>
<BRK/>
<TXT>[Provide insulating flange sets aboveground or within manholes as indicated.]  [Locate insulating flanges on 
lines entering buildings at least<MET> 305 mm</MET><ENG> 12 inches</ENG> above grade or floor level.]  [Cut piping and provide flanges 
into place.  Carefully align flange bolt holes and weld flange to pipe in accordance with <RID>ASME B16.25</RID>.]  [Electrically 
isolate pipelines entering buildings from the structure wall either below or above ground with an electrically 
isolating wall sleeve.]  Provide insulating  flange sets into place without springing or forcing.  Carefully 
install flange bolt sleeves to avoid damage to the sleeves.  [Cover insulating flanges with an electrically insulating 
coating.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.7   Dielectric Unions</TTL><BRK/>
<BRK/>
<TXT>Provide insulating unions aboveground or within manholes as indicated.  [Cut pipe ends square, remove fins and 
burrs, cut taper pipe threads in accordance with <RID>ASME B1.20.1</RID>.]  Work piping into place without springing or 
forcing.  Apply joint compound or thread tape to male threads only.  Backing off to permit alignment of threaded 
joints shall not be permitted.  Engage threads so that not more than three threads remain exposed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.8   <SUB>Joint Bonds</SUB></TTL><BRK/>
<BRK/>
<TXT>Provide joint bonds on metallic pipe to and across buried flexible couplings, mechanical joints, flanged joints 
[except at places where insulating joints are specified] and at joints not welded or threaded to provide electrical 
continuity.  Conform to the safety precautions of paragraph [_____] when welding around fuel facilities.  Check 
and verify adherence of the bond to the substrate for mechanical integrity by striking the weld with a<MET> 908 gram</MET><ENG>
 2 pound</ENG> hammer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.9   Casings, Insulation, and Seals</TTL><BRK/>
<BRK/>
<TXT>Where the pipeline is installed in a casing under a roadway or railway, insulate the pipeline from the casing, 
and seal the annular space against intrusion of water.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.10   Reconditioning of Surfaces</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  On projects having site work provided by DIVISION 2, coordinate the requirements 
for reconditioning of surfaces with the appropriate section(s).</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.1.10.1   Restoration of Sod</TTL><BRK/>
<BRK/>
<TXT>Restore unpaved surfaces disturbed during the installation of anodes and wires to their original elevation and 
condition.  Preserve sod and topsoil carefully and replace after the backfilling is completed.  Where the surface 
is disturbed in a newly seeded area, re-seed the area with the same quality and formula of seed as that used 
in the original seeding.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.10.2   Restoration of Pavement</TTL><BRK/>
<BRK/>
<TXT>Patch pavement, sidewalks, curbs and gutters where existing surfaces are removed for construction.  Saw cut pavement 
edges.  Graded aggregate base course shall have a maximum aggregate size of<MET> 35 mm</MET><ENG> 1 1/2 inches</ENG>. Prime base course 
with [liquid asphalt, <RID>ASTM D 2028</RID>, Grade RC-70] [_____] prior to paving.  Match base course thickness to existing 
but shall not be less than<MET> 150 mm</MET><ENG> 6 inches</ENG>.  Asphalt aggregate size shall be<MET> 12.7 mm</MET><ENG> 1/2 inch</ENG>, asphalt cement 
shall [conform to <RID>ASTM D 3381</RID>, Grade AR-2000] [_____].  Match asphalt concrete thickness to existing but shall 
not be less than<MET> 50 mm</MET><ENG> 2 inches</ENG>.  Repair portland cement concrete pavement, sidewalks, curbs, and gutters using<MET>
 20.67 MPa</MET><ENG> 3,000 psi</ENG> concrete conforming to [<RID>ASTM C 94/C 94M</RID>] [Section <SRF>03 30 00</SRF> CAST-IN-PLACE CONCRETE].  Match 
existing pavement, sidewalk, curb, and gutter thicknesses.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.2   FIELD QUALITY CONTROL</TTL><BRK/>
<BRK/>
<TXT>Field tests shall be witnessed by the Contracting Officer or his designated representative.  Advise the Contracting 
Officer [5] [_____] days prior to performing each field test.  Quality control for the <SUB>cathodic protection system</SUB>
 shall consist of the following:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Initial field testing by the contractor upon construction</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Government Field Testing after Contractor initial field test report submission.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Warranty period field testing by the Contractor.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Final field testing by the contractor after one year of service.</ITM><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Additional testing may be required, based upon the specific project or 
design.  All tests listed below may not be required.  Designer should consider 
the project requirements for selection of test procedures.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.2.1   Testing</TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.1.1   Destructive Testing</TTL><BRK/>
<BRK/>
<TXT>Contractor shall perform the tests in the presence of the Contracting Officer.  Contractor shall include the 
cost of an additional anode [of each different type] with the longest lead wire for the destructive test in his 
bid.  <TST>One completed [prepackaged] anode of each type with lead wires shall be chosen at random for destructive 
testing and shall be submitted to a static pull test.  Anode lead wire connections of anodes shall have sufficient 
strength to withstand a minimum tensile load of<MET> [1335] [_____] N</MET><ENG> [300] [_____] pounds</ENG>.</TST>  <TST>[The anode shall also 
be cut into sections and/or broken with a sledge hammer to verify conformance with this specification.  Such 
items as anode-to-wire connection, complete encapsulation of the wire connector, and wire to anode electrical 
resistance shall be checked.]</TST>  [Failure of the test anode to conform to this specification can be cause for rejecting 
all anodes from the same lot as the test anode.  The contractor shall mark all rejected anodes on the ends with 
a<MET> 150 mm</MET><ENG> 6 inches</ENG> high "X" using yellow spray paint.  Failed anodes shall be removed from the job site by the 
end of the day.  The contractor shall replace any rejected anodes at his expense.  The destructive testing provision 
shall also apply to replacement anodes as well.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.1.2   Wire for Power Service</TTL><BRK/>
<BRK/>
<TXT><TST>Test wire for power service at 600 volts or less to determine that the wiring system and equipment are free from 
short circuits and grounds [by a minimum of two megohms].  Perform the test with a megohm meter having a 500-volt 
rating.</TST></TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.1.3   <TST>Initial Cathodic Protection System Field Testing</TST></TTL><BRK/>
<BRK/>
<TXT>The systems shall be tested and inspected by the Contractor's corrosion engineer in the presence of the Contracting 
Officer's corrosion protection engineer or an approved representative.  Record test data, including date, time, 
and locations of testing and submit report to the Contracting Officer.  Contractor shall correct, at his expense, 
all deficiencies in the materials and installation observed by these tests and inspections.  Contractor shall 
pay for retests made necessary by the corrections.  Testing shall include the following measurements:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  <TST>Base potential tests</TST>:  At least [one week] [24 hours] [_____] after [backfilling of the 
pipe] [installation of the structure to be protected] [initial operation of structures containing 
fluids] [_____] , but before energizing of the cathodic protection system, measure the base 
(native) [structure-to-electrolyte] [pipe-to-soil] potentials of the [pipe [and the casings]] 
[structure].  Perform measurements at anode junction boxes, test stations and other locations 
suitable for test purposes (such as service risers or valves) at intervals not exceeding<MET> [30] 
[122] [_____] meters</MET><ENG> [100] [400] [_____] feet</ENG> with readings at each end point and the midpoint 
as a minimum.  The locations of these measurements shall be identical to the locations specified 
for measuring energized [structure-to-electrolyte] potentials.  Use the same measuring equipment 
that is specified for measuring protected potential measurements.</ITM><TST><ITM>  [For underground storage 
tanks, take a minimum of three measurements with the reference electrode located as follows:</ITM><BRK/>
<BRK/>
<ITM>(1)  Directly over the longitudinal and transverse centerlines of the tank at intervals not 
exceeding the diameter of the tank and to a distance from the tank of two times the tank diameter.</ITM><BRK/>
<BRK/>
<ITM>(2)  At points directly around the circumference of the tank.]</ITM></TST><BRK/>
<BRK/>
<ITM>b.  <TST>Permanent reference electrode calibration</TST>:  Verify calibration of the reference electrode 
by measuring the potential difference between the permanent reference electrode and an independent 
(portable) calibrated reference electrode placed in the soil or water adjacent to or as close 
as practicable to the permanent reference electrode.  [Potential differences between the two 
electrodes of the same generic type should not exceed [10] [15] millivolts.]  [Zinc permanent 
reference electrodes should be within the range of -1000 to -1150 millivolts when calibrated 
with a copper-copper sulfate reference electrode.]  Permanent reference electrodes not within 
these potential differences shall be removed from the construction site by the end of the day 
and replaced at the contractor's expense.  The testing provision shall also apply to replacement 
reference electrodes as well.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  <TST>Insulation joint testing</TST>:  Perform insulation testing at each insulating joint or fitting 
[prior to burying the joint or fitting] before and after the cathodic protection system is energized.  
Before energizing, test using an insulation checker.  After energizing, test the insulation 
by measuring the potential shift on both sides of the insulating joint.  This testing shall 
demonstrate that no metallic contact or short circuit exists between the two insulated sections 
of the pipe.  Report and repair defective insulating fitting at the Contractor's expense.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  <TST>Electrical continuity testing</TST>:  Perform electrical continuity testing for joint bonded pipe 
prior to backfilling of the pipe.  [Circulate current through the pipe and compare the measured 
resistance to the theoretical resistance of the pipe and bond cables.  The resistance measured 
shall not exceed 150 percent of the theoretical resistance.]</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  <TST>Rectifier system testing</TST>:  Upon completion of the installation, "Baseline Potential Tests", 
"Insulation Joint Tests", and "Electrical Continuity Tests", energize and adjust each rectifier.  
Measure D.C. outputs of the rectifier and current outputs [of each anode] [of associated ground 
bed] at different rectifier settings.  Measure the current outputs across the installed shunts.  
Verify these readings using portable, calibrated meters and shunts.  This testing shall demonstrate 
if the rectifier system is capable of functioning properly as required to provide effective 
cathodic protection.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  <TST>Pipe casing testing</TST>:  Before final acceptance of the installation, test the electrical insulation 
of the carrier pipe from casings and correct any short circuits.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  <TST>Energized potential tests</TST>:  With the entire cathodic protection system put into operation 
for at least [one week] [24 hours] [_____], measure pipe-to-soil potentials along the [pipeline 
[and at all casings]] [structure] using a portable [copper/copper sulfate] [silver silver-chloride] 
[and all permanent] reference electrode(s) and a voltmeter having an input impedance of not 
less than 10 megohms.  The locations of these measurements shall be identical to the locations 
used for the base potential measurements.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  <TST>Interference testing</TST>:  Perform interference testing with respect to any crossing and nearby 
foreign pipelines in cooperation with the owner of the related pipelines.  The testing shall 
verify that the subject cathodic protection system does not have a deleterious effect on the 
foreign pipelines, and vice versa.  Prepare a full report of the tests, giving all details including 
remedial actions taken or recommendations to correct noted interference problems.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.1.4   <SUB>Initial Cathodic Protection System Field Test Report</SUB></TTL><BRK/>
<BRK/>
<TXT>The contractor shall submit a field test report of the cathodic protection system.  All structure-to-electrolyte 
measurements, including initial potentials and anode outputs, shall be recorded on applicable forms.  Identification 
of test locations, test station and anode test stations shall coordinate with the as-built drawings and be provided 
on system drawings included in the report.  The contractor shall locate, correct, and report to the Contracting 
Officer any short circuits encountered during the checkout of the installed cathodic protection system.</TXT><BRK/></SPT>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The requirements of paragraph entitled "Government Field Testing" are 
required for cathodic protection projects in the LANTNAVFACENGCOM area.  The 
designer should verify their applicability to projects outside the LANTNAVFACENGCOM 
area with the appropriate EFD corrosion program manager.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.2.1.5   Government Field Testing</TTL><BRK/>
<BRK/>
<TXT>The government corrosion [engineer, LANTNAVFACENGCOM Code 404] [program manager, LANTNAVFACENGCOM Code 1614C] 
shall review the Contractor's initial field testing report.  Approximately four weeks after receipt of the Contractor's 
initial test report, the system will be tested and inspected in the Contractor's presence by the government corrosion 
[engineer, LANTNAVFACENGCOM Code 404] [program manager, LANTNAVFACENGCOM Code 1614C].  The Contractor shall correct, 
at his expense, materials and installations observed by these tests and inspections to not be in conformance 
with the plans and specifications.  The Contractor shall pay for all retesting done by the government engineer 
made necessary by the correction of deficiencies.</TXT><BRK/></SPT>
<BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For cathodic protection projects in the LANTNAVFACENGCOM area, select 
the appropriate LANTNAVFACENGCOM options for paragraphs entitled "One Year Warranty 
Period Testing" and "Final Field Testing."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>3.2.1.6   One Year Warranty Period Testing</TTL><BRK/>
<BRK/>
<TXT><TST>The Contractor shall inspect, test, and adjust the cathodic protection system [quarterly] [semi-annually] [_____] 
for one year, [4] [2] [  ] interim inspections total, to ensure its continued conformance with the criteria outlined 
below.</TST>  The performance period for these tests shall commence upon the completion of all cathodic protection 
work, including changes required to correct deficiencies identified during initial testing, and preliminary acceptance 
of the cathodic protection system by the Contracting Officer.  Copies of the <SUB>One Year Warranty Period Cathodic 
Protection System Field Test Report</SUB>, including field data, and certified by the Contractor's corrosion engineer 
shall be submitted to the Contracting Officer, the activity, and the geographic Engineering Field Division corrosion 
[protection program manager] [engineer, LANTNAVFACENGCOM Code 404] [protection program manager, LANTNAVFACENGCOM 
Code 1614C].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.1.7   Final Field Testing</TTL><BRK/>
<BRK/>
<TXT><TST>Conduct final field testing of the cathodic protection system utilizing the same procedures specified under, 
"Initial Field Testing of the Galvanic Cathodic Protection Systems".  The Contractor shall inspect, test, and 
adjust the cathodic protection system after one year of operation to ensure its continued conformance with the 
criteria outlined below.</TST>  The performance period for these tests shall commence upon the completion of all cathodic 
protection work, including changes required to correct deficiencies identified during initial testing, and preliminary 
acceptance of the cathodic protection system by the Contracting Officer.  Copies of the <SUB>Final Cathodic Protection 
System Field Test Report</SUB>, certified by the Contractor's corrosion engineer shall be submitted to the Contracting 
Officer and the geographic Engineering Field Division corrosion [protection program manager] [engineer, LANTNAVFACENGCOM 
Code 404] [protection program manager, LANTNAVFACENGCOM Code 1614C] for approval, and as an attachment to the 
operation and maintenance manual in accordance with Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE DATA.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2.2   Criteria for Cathodic Protection</TTL><BRK/>
<BRK/>
<TXT>Conduct in accordance with [<RID>NACE SP0169</RID>] [<RID>NACE RP0285</RID>]. Criteria for determining the adequacy of protection shall 
be selected by the corrosion engineer as applicable:</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The following criteria are applicable only to iron and steel structures.  
Refer to NACE SP0169 for appropriate criteria for other metal structures.  Not 
all criteria may be readily applicable to the type of CP system(s) being designed, 
and the designer should select only the applicable criteria.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<ITM INDENT="-0.33">a.  A negative voltage of at least 0.85 volt (850 millivolts) as measured between the structure 
surface and a saturated copper-copper sulfate reference electrode contacting the earth [electrolyte].  
Determination of this voltage is to be made with the protective current applied to the [structure] 
[tank] [pipeline] for a minimum of [24] [____] hours.  Voltage drops must be considered for 
valid interpretation of this voltage measurement.  The method of voltage drop consideration 
shall be identified by the Contractor's corrosion engineer and approved by the Government corrosion 
engineer.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  A negative polarized potential of at least 0.85 volt (850 millivolts) as measured between 
the structure surface and a saturated copper-copper sulfate reference electrode contacting the 
earth [electrolyte].  Determination of this voltage is to be made after the protective current 
has been applied to the [structure] [tank] [pipeline] for a minimum of [24] [____] hours.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  A minimum polarization voltage shift of 100 mV measured between the structure surface and 
a saturated copper-copper sulfate reference electrode contacting the earth [electrolyte].  This 
voltage shift shall be determined by interrupting the protective current and measuring the polarization 
decay.  At the instant the protective current is interrupted ("instant off"), an immediate voltage 
shift will occur.  The voltage reading just after the immediate shift shall be used as the base 
reading from which to measure the polarization decay.  The polarization decay shall be the difference 
between the base reading and a voltage measurement made [24] [48] [_____] hours after the interruption 
of protective current.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.3   DEMONSTRATION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Instructing Government Personnel</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  There are restrictions on the type and extent of training.  Training 
is usually on-site, 2 days or less.  Factory representatives or others provide 
basic instructions to facility maintenance and operation personnel.  If more 
extensive training is required, i.e. student travel, special consultants, etc., 
consult the Contract Division Director and the head of the Comptroller Department 
for assistance.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><TST>During the warranty testing and at a time designated by the Contracting Officer, make available the services 
of a technician regularly employed or authorized by the manufacturer of the Cathodic Protection System for instructing 
Government personnel in the proper operation, maintenance, safety, and emergency procedures of the Cathodic Protection 
System.  The period of instruction shall be not less than [one] [_____] but not more than [two] [_____] 8-hour 
working day[s].  Conduct the training at the jobsite or at another location mutually satisfactory to the Government 
and the Contractor.</TST>  The field instructions shall cover all of the items contained in the operation and maintenance 
manual.</TXT><BRK/>
<BRK/></SPT>
</SPT><MET><SPT><TTL>3.4   SCHEDULE</TTL><BRK/>
<BRK/>
<TXT>Some metric measurements in this section are based on mathematical conversion of English unit measurements, and 
not on metric measurement commonly agreed to by the manufacturers or other parties.  The English and metric units 
for the measurements shown are as follows:</TXT><BRK/>
<TBL><THD><BRK/>
       <HL1>PRODUCTS</HL1>                   <HL1>ENGLISH UNITS</HL1>        <HL1>METRIC UNITS</HL1><BRK/></THD>
<BRK/>
  a.  Reference Electrodes<BRK/>
      - Diameter                  1 1/4 inches         31.75 mm<BRK/>
      - Length                    10 inches            255 mm<BRK/>
<BRK/>
  b.  Terminal Board<BRK/>
      (phenolic plastic)          1/8 inch             3 mm<BRK/>
       thickness                  1/4 inch             6 mm<BRK/></TBL>
<BRK/></SPT>
</MET></PRT>    <END/><BRK/></SEC>