<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA      UFGS-33 63 13 (April 2006)<BRK/>
                                    ------------------------------<BRK/>
Preparing Activity: <PRA>NAVFAC</PRA>          Replacing without change <BRK/>
                                    UFGS-02553 (August 2004)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 33 63 13</SCN><BRK/>
<BRK/>
<STL>EXTERIOR UNDERGROUND STEAM DISTRIBUTION SYSTEM</STL><BRK/>
<DTE>04/06</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>an insulated underground 
heat distribution system (UHDS) and/or condensate return system of the pre-engineered 
type</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Additional information can be found in Unified Facilities Criteria (UFC) 
3-430-09N, "Exterior Mechanical Utility Distribution."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Remember all design notes are to the government designer or design Architect/Engineer 
firm and will not be seen by the contractor or their subcontractors.  The designer 
should realize that this specification requires coordination with other design 
disciplines (examples:  cathodic protection, trenching and backfill, structural 
for coordinating manhole structures).  This guide specification covers the designing, 
furnishing, installing and testing of a direct buried, insulated UHDS and/or 
condensate return system of the pre-engineered type.  These systems are capable 
of transporting steam, condensate, or high temperature hot water.  This specification 
is for systems operating above<MET> 120 degrees C</MET><ENG> 250 degrees F</ENG> to a maximum acceptable 
pressure and temperature of approximately<MET> 4.551 Mpa (gage)</MET><ENG> 660 psig</ENG> and<MET> 260 
degrees C</MET><ENG> 500 degrees F</ENG>.  It should be noted that not all UHDS are acceptable 
for all site classifications, temperatures, and pressure ratings.</NPR><BRK/>
<BRK/>
<NPR>This guide specification provides the requirements necessary for a complete 
operable system (except for design of the valve manhole and associated piping 
and equipment in the valve manhole which are covered elsewhere).  The manufacturer 
of the "pre-engineered UHD" (UHDS system manufacturer) will provide a detailed 
design for the pre-engineered system up to and including the interface with 
the valve manhole or building wall, terminating their UHDS at least<MET> 150 mm</MET><ENG> six 
inches</ENG> inside the valve manhole or building.  This includes all designs for 
pipe anchors and expansion loops, offsets and bends. Valve manholes are not 
the responsibility of the UHDS manufacturer and will be detailed on the contract 
drawings.</NPR><BRK/>
<BRK/>
<NPR>The UHDS manufacturer shall be responsible for the design, fabrication, and 
witnessing of the installation and testing of the system within the design parameters 
established by the contract drawings and specifications.  The government designer 
will establish the site, soil and groundwater conditions.  The contract drawings 
will show the size, proposed routing (including construction limits) and estimated 
length of the system.  The contract drawings will establish the elevations and 
show the profiles of the pipe and the existing and finished earth surfaces.  
Indicate and identify all obstructions within<MET> 8 m</MET><ENG> 25 feet</ENG> of the system centerline, 
including adjacent or crossing utilities.</NPR><BRK/>
<BRK/>
<NPR>This guide specification is not for the design of the valve manhole and associated 
piping and equipment in the valve manhole.  Valve manholes and the piping and 
equipment inside the valve manholes will be designed and detailed on the contract 
drawings.  Section 02559, "Valve Manholes and Piping and Equipment in Valve 
Manholes," will be included as part of this project.</NPR><BRK/>
<BRK/>
<NPR>Designer will include a log of soil conditions along the pipe line right-of-way 
at pipe depth on the drawings which gives, as a minimum, soil classification, 
moisture content, soil resistivity and pH, bearing strength and unstable conditions.</NPR><BRK/>
<BRK/>
<NPR>Designer will provide details at building entries on the contract drawings to 
show pipe elevation, floor and grade elevation, building wall construction and 
existing equipment.  Include location of valve manhole and/or valve boxes, branch 
runouts, and isolation valves on the contract drawings.  Provide details at 
manhole entries on the contract drawings to show pipe elevations; floor, top, 
entrance, and grade elevations; manhole wall construction; anchor location and 
construction; and existing equipment and piping.</NPR><BRK/>
<BRK/>
<NPR>REMEMBER:  All connections to the UHDS piping will occur only in manholes.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
 <BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
 <BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)</ORG><BRK/><BRK/><RID>AASHTO M 300</RID><RTL>(2003; R 2007) Inorganic Zinc-Rich Primer</RTL><BRK/><BRK/></REF><REF><ORG>ASME INTERNATIONAL (ASME)</ORG><BRK/><BRK/><RID>ASME B16.11</RID><RTL>(2005) Forged Fittings, Socket-Welding and Threaded</RTL><BRK/><BRK/><RID>ASME B16.9</RID><RTL>(2007) Standard for Factory-Made Wrought Steel Buttwelding Fittings</RTL><BRK/><BRK/><RID>ASME B31.1</RID><RTL>(2007; Addenda 2008) Power Piping</RTL><BRK/><BRK/><RID>ASME B40.100</RID><RTL>(2005) Pressure Gauges and Gauge Attachments</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM A 106/A 106M</RID><RTL>(2008) Standard Specification for Seamless Carbon Steel Pipe for High-Temperature Service</RTL><BRK/><BRK/><RID>ASTM A 134</RID><RTL>(1996; R 2005) Standard Specification for Pipe, Steel, Electric-Fusion (Arc)-Welded (Sizes NPS 16 and Over)</RTL><BRK/><BRK/><RID>ASTM A 135/A 135M</RID><RTL>(2006) Standard Specification for Electric-Resistance-Welded Steel Pipe</RTL><BRK/><BRK/><RID>ASTM A 139/A 139M</RID><RTL>(2004) Standard Specification for Electric-Fusion (ARC)-Welded Steel Pipe (NPS 4 and over)</RTL><BRK/><BRK/><RID>ASTM A 167</RID><RTL>(1999; R 2004) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip</RTL><BRK/><BRK/><RID>ASTM A 234/A 234M</RID><RTL>(2007) Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service</RTL><BRK/><BRK/><RID>ASTM A 36/A 36M</RID><RTL>(2008) Standard Specification for Carbon Structural Steel</RTL><BRK/><BRK/><RID>ASTM A 53/A 53M</RID><RTL>(2007) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless</RTL><BRK/><BRK/><RID>ASTM C 518</RID><RTL>(2004) Steady-State Thermal Transmission Properties by Means of the Heat Flow Meter Apparatus</RTL><BRK/><BRK/><RID>ASTM C 533</RID><RTL>(2007) Standard Specification for Calcium Silicate Block and Pipe Thermal Insulation</RTL><BRK/><BRK/><RID>ASTM C 591</RID><RTL>(2008) Standard Specification for Unfaced Preformed Rigid Cellular Polyisocyanurate Thermal Insulation</RTL><BRK/><BRK/><RID>ASTM D 2310</RID><RTL>(2006) Machine-Made "Fiberglass" (Glass-Fiber-Reinforced Thermosetting-Resin) Pipe</RTL><BRK/><BRK/><RID>ASTM D 2487</RID><RTL>(2006e1) Soils for Engineering Purposes (Unified Soil Classification System)</RTL><BRK/><BRK/><RID>ASTM D 2996</RID><RTL>(2001; R 2007e1) Filament-Wound "Fiberglass" (Glass-Fiber-Reinforced Thermosetting-Resin) Pipe</RTL><BRK/><BRK/></REF><REF><ORG>ISA - INTERNATIONAL SOCIETY OF AUTOMATION (ISA)</ORG><BRK/><BRK/><RID>ISA MC96.1</RID><RTL>(1982) Temperature Measurement Thermocouples</RTL><BRK/><BRK/></REF><REF><ORG>NACE INTERNATIONAL (NACE)</ORG><BRK/><BRK/><RID>NACE SP0169</RID><RTL>(2007) Control of External Corrosion on Underground or Submerged Metallic Piping Systems</RTL><BRK/><BRK/></REF><REF><ORG>NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)</ORG><BRK/><BRK/><RID>NEMA ICS 4</RID><RTL>(2005) Industrial Control and Systems: Terminal Blocks</RTL><BRK/><BRK/></REF><REF><ORG>U.S. GENERAL SERVICES ADMINISTRATION (GSA)</ORG><BRK/><BRK/><RID>FS L-S-125</RID><RTL>(Rev B) Screening, Insect, Nonmetallic</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   DEFINITIONS</TTL><BRK/>
<BRK/>
<TXT>The following definitions are applicable:</TXT><BRK/>
<BRK/>
<SPT><TTL>1.2.1   Pre-engineered System</TTL><BRK/>
<BRK/>
<TXT>A complete underground [heat distribution] [and] [condensate return] system including all required components 
such as carrier pipes, [steam pipe], [high temperature hot water supply pipe], [condensate return pipe], and 
[high temperature hot water return pipe], fittings, anchors, pipe supports, insulation, protective casing, and 
cathodic protection, for the system supplied.  The pre-engineered system does not include valve manholes and 
the piping and equipment inside the valve manholes; see Section <SRF>33 60 01</SRF> VALVE MANHOLES AND PIPING AND EQUIPMENT 
IN VALVE MANHOLES.  The pre-engineered system shall include all piping and components to a point at least<MET> 150 
mm</MET><ENG> six inches</ENG> inside the building and valve manhole.  The UHDS shall not use any part of the building or valve 
manhole structure as an anchor point.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.2   Direct-Buried</TTL><BRK/>
<BRK/>
<TXT>A system which is buried without the need for a field-fabricated protective enclosure such as a concrete trench 
or tunnel.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select from the following two paragraphs as applicable to the type of 
system to be allowed.  See paragraph Site Classification for assistance in selecting 
system types.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/></SPT>
<SPT><TTL>1.2.3   UHDS Types</TTL><BRK/>
<BRK/>
<SPT><TTL>1.2.3.1   Drainable-Dryable-Testable (DDT) Direct-Buried System</TTL><BRK/>
<BRK/>
<TXT>A factory-fabricated system including an air and water-tight outer protective casing, air space and an insulated 
carrier pipe.  Drains and vents are provided at the end plates of the system (in manholes or buildings).  The 
drains are normally plugged but the plugs can be removed to drain water which may leak into the air space if 
there is a failure in the casing or the carrier pipe.  The vents allow water vapor to escape and provide a tell-tale 
sign of leakage.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>1.2.3.2   Water Spread Limiting (WSL) Direct-Buried System</TTL><BRK/>
<BRK/>
<TXT>A factory-fabricated system including an outer protective casing and an insulated carrier pipe.  The system is 
fabricated in sections which are independent from each other; ground water or condensate which leaks from or 
into one section cannot travel into the next section.  Field-assembly of the sections requires no welding as 
the sections push together and are sealed with a system of couplings and seals.</TXT><BRK/>
<BRK/>
]</SPT></SPT><SPT><TTL>1.2.4   <SUB>UHDS Manufacturer Certification</SUB></TTL><BRK/>
<BRK/>
<TXT>The UHDS manufacturer is the company responsible for the design and manufacture of the pre-engineered system.  
The UHDS manufacturer directs the installation of their system and has a representative on the job site.Certification 
includes that the UHDS manufacturer regularly and currently manufactures direct-buried systems, and that the 
designs of the system and equipment to be provided for this project conform to specification requirements.  This 
certification shall be an original signed by a principal officer of the UHDS manufacturer and shall be submitted 
at minimum of [2] [_____] weeks prior to start of work.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.5   UHDS Manufacturer's Representative</TTL><BRK/>
<BRK/>
<TXT>The UHDS manufacturer's representative shall be a person who regularly performs the duties specified herein, 
is certified in writing by the UHDS manufacturer to be technically qualified and experienced in the installation 
of the system, and shall be authorized by the manufacturer to make and sign the daily reports specified herein.  
The UHDS manufacturer's representative shall be under the direct employ and supervision of the UHDS manufacturer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.6   Corrosion Engineer</TTL><BRK/>
<BRK/>
<TXT>Corrosion engineer refers to a person who by knowledge of the physical sciences and the principles of engineering 
and mathematics, acquired by professional education and related practical experience, is qualified to engage 
in the practice of corrosion control.  Such person may be a licensed professional corrosion engineer or certified 
as being qualified by the National Association of Corrosion Engineers (NACE), if such licensing or certification 
includes 3 years experience in corrosion control on underground metallic surfaces of the type under this contract.  
NACE certification shall be technologist, corrosion specialist, or cathodic protection specialist.  The corrosion 
engineer shall make at least 3 visits to the project site.  The first of these visits shall include obtaining 
soil resistivity data, acknowledging the type of pipeline coatings to be used and reporting to the Contractor 
the type of cathodic protection required.  Once the submittals are approved and the materials delivered, the 
corrosion engineer shall revisit the site to ensure the Contractor understands installation practices and laying 
out the components.  The third visit shall involve testing the installed cathodic protection systems and training 
applicable personnel on proper maintenance techniques.  The corrosion engineer shall supervise, inspect, and 
test the installation and performance of the cathodic protection system.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.7   <SUB>Pipe-Stress and System Expansion Calculations</SUB></TTL><BRK/>
<BRK/>
<TXT>Pipe-stress and system-expansion calculations for each expansion compensation elbow using a finite element computer 
generated three-dimensional analysis, not later than [7 days] [_____] after notice to proceed.</TXT><BRK/>
<BRK/>
<TXT>Calculations (including heat loss calculations) shall demonstrate that pipe stresses from temperature changes 
are within the allowable requirements in <RID>ASME B31.1</RID> and the anchors and the guides will withstand the resultant 
forces.  Submitted detailed design layout drawings including the location of all anchors and guides.  Layout 
shall also include all analysis node points.  As a minimum, the computer analysis results include node stresses, 
forces, moments and displacements.  Calculations shall be approved, certified, stamped and signed by a registered 
Professional Engineer in the employ of the UHDS manufacturer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.8   <SUB>Cathodic Protection System Calculations</SUB></TTL><BRK/>
<BRK/>
<TXT>Design life calculations for cathodic protection system in accordance with <RID>NACE SP0169</RID>, not later than [7 days] 
[_____] after notice to proceed.  Calculations shall be stamped and signed by a NACE qualified corrosion engineer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.9   <SUB>Manufacturer's Data Sheets</SUB></TTL><BRK/>
<BRK/>
<TXT>Manufacturer's data sheets on all components of the UHDS and the instrumentation required for thermal performance 
testing.</TXT><BRK/>
<BRK/>
<TXT>Manufacturer's data sheets for all <SUB>coatings</SUB> and for carrier pipe insulation, indicate thicknesses not later than 
[7 days] [_____] after notice to proceed.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.10   <SUB>Work Plan</SUB></TTL><BRK/>
<BRK/>
<TXT>A proposed schedule of activities indicating when various items of work and tests are to be carried out and when 
the representative of the UHDS manufacturer shall be present at job site.  The UHDS manufacturer shall submit 
a list of what characteristics shall be considered damaged or defective materials that must be replaced.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.11   Quality Assurance Plan</TTL><BRK/>
<BRK/>
<TXT>Manufacturer's <SUB>quality assurance</SUB> plan for fabrication, delivery, storage, installation and testing of system.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.12   <SUB>Thermal Performance Testing</SUB></TTL><BRK/>
<BRK/>
<TXT>A proposed test procedure and proposed samples of test data sheets for each required test, 30 days prior to the 
proposed test date.  The procedure shall contain a complete description of the proposed test with calibration 
curves or test results furnished by an independent testing laboratory of each instrument, meter, gauge, and thermometer 
to be used in the tests.  The test shall not commence until the procedure has been approved.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.13   <SUB>Certificate of Compliance</SUB></TTL><BRK/>
<BRK/>
<TXT>Upon completion of the work, and before final acceptance, a notarized statement signed by a principal officer 
of both the UHDS manufacturer and the contractor, certifying that the system has been installed satisfactorily 
and in accordance with the contract drawings, specifications, UHDS  manufacturer's detailed design layout drawings 
and with the UHDS manufacturer's recommendations.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.14   <SUB>Testing Firm Qualification</SUB></TTL><BRK/>
<BRK/>
<TXT>A Certificate of the Testing Firm Qualification from the independent testing firm or firms, not later than [_____] 
days after notice to proceed, certifying that:  weld examination methods and procedures, and the interpretation 
of radiographic films will be performed in accordance with <RID>ASME B31.1</RID>; the firm intends to utilize the proper 
film exposure, techniques, and penetrameter to produce density and geometric sharpness in sufficient clarity 
to determine presence of defects; and that all radiographic films will be reviewed and interpreted, and reading 
reports signed, by not less than a Certified American Society for Nondestructive Testing Level III Radiographer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.15   <SUB>Welds</SUB></TTL><BRK/>
<BRK/>
<TXT>A Certification of Acceptability of all welds made in the field, upon completion of the project.  This certification 
shall consist of a letter signed by an official of the independent testing firm or firms examining welds, stating 
that all provisions of this specification have been complied with, and that all welds inspected radiographically 
have met the acceptability standards specified.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.16   <SUB>Daily Written Report</SUB></TTL><BRK/>
<BRK/>
<TXT>A daily written report from the representative of the UHDS manufacturer whenever the representative is required 
to be on the jobsite.  The report shall be checked for accuracy and the original shall be submitted no later 
than the next working day after the date of the report.  One copy shall be forwarded to the UHDS manufacturer's 
main office.  The report shall be signed by the representative.  The report shall state whether or not the condition 
and quality of the materials and methods used and the installation of the system are in accordance with the contract 
drawings, specifications, and the UHDS manufacturers detailed design layout drawings and requirements.  If anything 
connected with the installation is unsatisfactory, the report shall state what corrective action has been taken 
or shall contain the UHDS manufacturer's recommendations for corrective action and when the unsatisfactory condition 
is to be corrected.  The daily report will track and report all unsatisfactory conditions and corrective measured 
being taken.  The report shall identify any conditions that could result in an unsatisfactory installation, including 
such items as open conduit ends left in the trench overnight and improper valve manhole entries and changes required 
to the UHDS design due to interferences or conflicts, upon realization of interferences or conflicts.  On a weekly 
basis the daily reports shall be reviewed, approved, signed and sealed by the registered Professional Engineer 
responsible for the system design and shall be submitted to the Contracting Officer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.2.17   <SUB>Heat Distribution System,</SUB> Data Package 2</TTL><BRK/>
<BRK/>
<TXT>The operation and maintenance manual for the heat distribution system shall list routine maintenance procedures, 
possible breakdowns and repairs, procedures for recording conduit temperatures biannually, and troubleshooting 
guides.  Manual shall include as-built piping layout of the system including final elevations.  Submit in accordance 
with Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE DATA.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.3   DESCRIPTION</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Scope</TTL><BRK/>
<BRK/>
<TXT>The work includes the design and fabrication; furnishing; installing, and testing of a direct buried underground 
[insulated heat-distribution system] [and] [insulated steam pipe], [insulated high temperature hot water supply 
pipe], [insulated steel condensate return pipe], [insulated high temperature hot water return pipe] consisting 
of piping as indicated, cathodic protection system(where required by this specification), together with all fittings 
and appurtenances necessary for a complete and operable system.  Gland type end seals shall not be permitted.  
Drainable, dryable, testable (DDT) systems with fiberglass casings shall not be provided.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2   <SUB>UHDS Design</SUB></TTL><BRK/>
<BRK/>
<TXT>The UHDS manufacturer shall be responsible for the complete design of the UHDS, the product to be supplied, fabrication, 
witnessing installation and testing of the system within the design parameters established by the contract drawings 
and specifications, and in compliance with the detailed design.  The complete design of the UHDS shall be sealed 
by a Professional Engineer in the employ of the UHDS manufacturer.A Certificate of Satisfactory Operation shall 
be submitted certifying that at least 3 systems installed by the UHDS manufacturer within the previous 10 years 
have and are operating satisfactorily for not less than 5 years, not later than [_____] days after notice to 
proceed.  The certificate shall indicate the location, type of system, size of system, point of contact (POC) 
including phone number, for information verification.  This certificate of satisfactory operation shall be an 
original signed by a principal officer of the UHDS manufacturer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.3   Contract Drawings</TTL><BRK/>
<BRK/>
<TXT>The contract drawings accompanying this specification provide information on:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  The size of carrier pipes, approximate length, and site location of the system.</ITM> <BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  The routing and elevation of the piping along the route.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Location and design of manholes. </ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  The obstacles that must be avoided along the path.</ITM> <BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Location of piping <SUB>anchors</SUB> (anchors will be no closer than<MET> one m</MET><ENG> 3 feet</ENG> nor further than<MET>
 1.5 m</MET><ENG> 5 feet</ENG> from entrance to manholes and buildings) at manholes and/or buildings.  The UHDS 
manufacturer shall incorporate any additional anchors as needed for their system.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Operating pressure and temperature of system.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4   SYSTEM REQUIREMENTS</TTL><BRK/>
<BRK/>
<SPT><TTL>1.4.1   <SUB>Cathodic Protection</SUB></TTL><BRK/>
<BRK/>
<TXT>Cathodic protection shall be provided for systems with coated steel casings.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.2   Operating Characteristics</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The operating and the rated characteristics must be supplied.  Operating 
characteristics should be based on the capabilities of the system.  The operating 
characteristics shall not exceed the values for the "Rated Characteristics" 
of the system.  Rated characteristics are to be used for calculations for the 
system design and represent a "worst case".  For rated characteristics for DDT 
systems insert<MET> 260 degrees C and 4.585 MPa (gage)</MET><ENG> 500 degrees F and 665 psig</ENG>
.  For rated characteristics for WSL systems which are only allowed for steam 
and condensate return systems, insert<MET> 208 degrees C and 1.723 MPa (gage)</MET><ENG> 406 
degrees F and 250 psig</ENG>.  The design conditions for the condensate and hot water 
return piping shall be the same as for the steam and hot water supply.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The [steam] [high temperature hot water] supply system shall have an operating temperature of<MET> [_____] degrees 
C</MET><ENG> [_____] degrees F </ENG>  and an operating pressure of<MET> [_____] kPa</MET><ENG> [_____] psig</ENG>. [[Condensate] [High Temperature 
hot water] return system shall have an operating temperature of<MET> [_____] degrees C</MET><ENG> [_____] degrees F</ENG> and an operating 
pressure of<MET> [_____] kPa</MET><ENG> [_____] psig</ENG>.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.3   Rated Characteristics</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The rated characteristics are to be used in the calculations for the 
system design and represent a "worst case".  The rated conditions for the high 
temperature hot water return piping will be the same as for the supply.  For 
"Installation Temperature" use the 99 Percent Dry Bulb Temperature Winter Design 
Heating Data from the weather tables in AFM 88-29, TM-S-785, NAVFAC P-89, Engineering 
Weather Data.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>All thermal expansion calculations shall be computed for the supply and return piping using the following design 
characteristics and installation temperature.  The system design conditions for [steam], [condensate], [high 
temperature hot water] supply and/or return at a temperature of [<MET>260 degrees C</MET><ENG>500 degrees F</ENG>] and a pressure of 
[<MET>4.585 kPa</MET><ENG>665 psig</ENG>.] For calculation purposes the installation temperature (the ambient temperature at the site) 
shall be no higher than a temperature of [<MET>[_____] degrees C</MET><ENG>[_____] degrees F</ENG>].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.4   Heat Distribution System design</TTL><BRK/>
<BRK/>
<TXT>A complete description of the <SUB>Heat Distribution System design</SUB> and assembly of the system, materials of construction 
and field installation instructions minimum of [2] [_____] days prior to the start of field measurements.  Also 
submittal shall include sufficient system details required to show that the specified minimum insulation thickness 
has been met.  A detailed design layout of the system (plan and elevation views) showing size, type, elevations 
and location of each component to be used in the system, the design and location of anchors, pipe guides, pipe 
supports, expansion loops, Z-bends, L-bends, end seals, leak plates, joint locations, pipe and insulation thickness 
and sizes, types, and movements, connection to manhole and building wall penetrations, and including, if applicable, 
transition point design to aboveground or other type systems.  Also, if applicable, type and details of  the 
cathodic protection system to be used.  Detailed design layout drawings shall be prepared and approved by a registered 
Professional Engineer as certified by their stamp.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.5   STANDARD PRODUCTS</TTL><BRK/>
<BRK/>
<TXT>Approval by Contracting Officer is required for products or services of the UHDS manufacturer.  The design of 
the system and equipment provided for this project shall conform to specification requirements, shall be of current 
production and shall essentially duplicate systems that have been in satisfactory use for at least 5 years, prior 
to bid opening, at three locations.  The systems must have been  operated under pressure, temperature and site 
characteristics that are equal to or more severe than the operating conditions in this specification and must 
have distributed the same medium.  The system shall be supported by a service organization that is, in the opinion 
of the Contracting Officer, reasonably convenient to the site.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.6   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  The following shall 
be submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Heat Distribution System design</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-03 Product Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Pipe</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Insulation</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Fittings</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Cathodic protection</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Anchors</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Expansion joints</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Coatings</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Conduit</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Field Connection of Casing Sections</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-05 Design Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Pipe-stress and system expansion calculations</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Cathodic protection system calculations</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Manufacturer's data sheets</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>WSL system tests</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Work plan</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Quality assurance</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Thermal performance testing</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>UHDS manufacturer certification</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>UHDS design</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Certificate of compliance</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Testing firm qualification</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM><SUB>Welds</SUB>[; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<LST><SUB>SD-10 Operation and Maintenance Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Heat distribution system</SUB>, Data Package 2; [; <SUB>G</SUB>][; <SUB>G, [_____]</SUB>]</ITM><BRK/>
<BRK/>
<ITM>  Submit operation and maintenance data in accordance with Section <SRF>01 78 23</SRF> OPERATION AND MAINTENANCE 
DATA.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-11 Closeout Submittals</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Daily written report</SUB></ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.7   SITE CLASSIFICATION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  A site survey must be made of the proposed routing of the UHDS.  It is 
important that the site survey report include the identification, location, 
and depth of all existing underground utilities and structures as well as all 
aboveground utilities, roadways, structures, etc.  Classification of the site 
conditions will be used to determine the type of system to be used: a drainable, 
dryable, testable (DDT) system should be allowed in severe, bad, and moderate 
site conditions; a water-spread-limiting (WSL) system should be allowed in bad 
and moderate site conditions for steam and condensate return systems only.  
Remove these paragraphs if the survey will be done by the Government.</NPR><BRK/>
<BRK/>
<NPR>A soils engineer, familiar with the underground water conditions onsite, should 
be employed to establish the site classification.  Site parameters are defined 
in TABLE A.  If underground water conditions at the site are not available, 
a detailed site classification survey will be made and TABLE B will be utilized 
to establish the site classification.  This survey should be conducted within 
the framework of the following guidelines:</NPR><BRK/>
<BRK/>
<NPR>1.  The survey will be made after the general layout of the system has been 
determined and should cover the entire length of the proposed system.</NPR><BRK/>
<BRK/>
<NPR>2.  The survey should be conducted during the time of the year when the water 
table is at its highest point.  If this is not possible, water table measurements 
should be corrected to indicate conditions likely to exist at the time of year 
when the water table is at its highest point.</NPR><BRK/>
<BRK/>
<NPR>3.  Information on groundwater conditions, soil types, terrain, and soil moisture 
content in the area of the system will be collected.  Information on terrain, 
precipitation rates and irrigation practices will be obtained if not available 
from records at the installation.</NPR><BRK/>
<BRK/>
<NPR>4.  Required information will be obtained through boring, test pits, or other 
suitable exploratory means.  Generally, a boring or test pit should be made 
at least every 30 m (100 feet) along the line of the proposed system, and each 
exploratory hole should extend to a level at least 1.5 m (5 feet) below the 
anticipated elevation of the bottom of the system.</NPR><BRK/>
<BRK/>
<NPR>5.  Underground and aboveground utilities and obstructions will be located.</NPR><BRK/>
<BRK/>
<NPR>The load-bearing qualities of the soil in which the system will be installed 
will be investigated by an experienced soils engineer (preferably the same engineer 
responsible for other soils engineering work), and the location and nature of 
potential soil problems will be identified.</NPR><BRK/>
<BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Classification of the site conditions for the UHDS was based on <RID>ASTM D 2487</RID> and the following criteria:  [_____].</TXT><BRK/>
<TBL><THD><BRK/>
<HL4>TABLE A</HL4><BRK/>
<HL4>SITE CLASSIFICATION DEFINITION</HL4><BRK/>
<HL4>BASED ON KNOWN UNDERGROUND WATER CONDITIONS</HL4><BRK/>
<BRK/>
  Site Classification          General Conditions for Classification<BRK/>
  -----------------------------------------------------------------------<BRK/></THD>
<BRK/>
  Severe           The water table is expected to be frequently above the<BRK/>
                   bottom of the system and surface water is expected to<BRK/>
                   accumulate and remain for long periods in the soil<BRK/>
                   surrounding the system.<BRK/>
<BRK/>
                   OR<BRK/>
<BRK/>
                   The water table is expected to be occasionally above<BRK/>
                   the bottom of the system and surface water is expected<BRK/>
                   to accumulate and remain for long periods in the soil<BRK/>
                   surrounding the system.<BRK/>
  -----------------------------------------------------------------------<BRK/>
  Bad              The water table is expected to be occasionally above<BRK/>
                   the bottom of the system and surface water is expected<BRK/>
                   to accumulate and remain for short periods (or not at<BRK/>
                   all) in the soil surrounding the system<BRK/>
<BRK/>
                   OR<BRK/>
<BRK/>
                   The water table is expected never to be above the<BRK/>
                   bottom of the system but surface water is expected to<BRK/>
                   accumulate and remain for short periods in the soil<BRK/>
                   surrounding the system.<BRK/>
  -----------------------------------------------------------------------<BRK/>
  Moderate         The water table is expected never to be above the<BRK/>
                   bottom of the system but surface water is expected to<BRK/>
                   accumulate and remain for short periods (or not at<BRK/>
                   all) in the soil surrounding the system.<BRK/>
<BRK/>
                   OR<BRK/>
<BRK/>
                   The water table is expected never to be above the<BRK/>
                   bottom of the system but surface water is expected to<BRK/>
                   accumulate and remain for brief or occasional periods<BRK/>
                   in the soil surrounding the system.<BRK/>
<BRK/>
                   OR<BRK/>
<BRK/>
                   The water table is expected never to be above the<BRK/>
                   bottom of the system and surface water is not expected<BRK/>
                   to accumulate or remain in the soil surrounding the<BRK/>
                   system.<BRK/></TBL>
<MET><TBL><THD><BRK/>
<HL4>TABLE B</HL4><BRK/>
<HL4>SITE CLASSIFICATION CRITERIA</HL4><BRK/>
<HL4>BASED ON SUBSURFACE SOIL INVESTIGATION</HL4><BRK/>
<BRK/>
                                                      Precipitation<BRK/>
 Site         Water              Soil                 Rates or<BRK/>
 Classif-     Table              Types                Irrigation<BRK/>
 ication      Level                        Terrain    Practices in Area<BRK/>
 -----------------------------------------------------------------------<BRK/></THD>
<BRK/>
 SEVERE      Water table         Any        Any         Any<BRK/>
             Within 300 mm<BRK/>
             of bottom<BRK/>
             of system<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             Water table         GC, SC     Any         Any<BRK/>
             Within 1500 mm      CL, CH<BRK/>
             of bottom           OH<BRK/>
             of system<BRK/>
 ------------------------------------------------------------------------<BRK/>
 BAD         Water table         GW, GP,    Any         Any<BRK/>
             Within 1500 mm      SW, SP<BRK/>
             of bottom<BRK/>
             of system<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             No                  GC, SC,    Any         Equivalent to<BRK/>
             groundwater         SW, CH,                75 mm or more<BRK/>
             encountered         OH                     in any one<BRK/>
                                                        month or 500 mm<BRK/>
                                                        or more in one<BRK/>
                                                        year.<BRK/>
 ------------------------------------------------------------------------<BRK/>
 MODERATE    No                  GM, SM,    Any         Equivalent to<BRK/>
             groundwater         ML, OL,                75 mm or more in<BRK/>
             encountered         MH                     any one month or<BRK/>
                                                        500 mm or more<BRK/>
                                                        in one year.<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             No                  GC, SC,    Any         Equivalent to<BRK/>
             groundwater         CL, CH,    except      less than 75 mm<BRK/>
             encountered         OH         low         in any one month<BRK/>
                                            areas       or less than<BRK/>
                                                        500 mm in one year.<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             No                  GW, GP,    Any         Any<BRK/>
             groundwater         SW, SP<BRK/>
             encountered<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             No                  GM, SM,    Any         Equivalent to<BRK/>
             groundwater         ML, SM,                less than 75 mm<BRK/>
             encountered                                in any one month<BRK/>
                                                        or less than<BRK/>
                                                        500 mm in one year.<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>TABLE B</HL4><BRK/>
<HL4>SITE CLASSIFICATION CRITERIA</HL4><BRK/>
<HL4>BASED ON SUBSURFACE SOIL INVESTIGATION</HL4><BRK/>
<BRK/>
                                                      Precipitation<BRK/>
 Site         Water              Soil                 Rates or<BRK/>
 Classif-     Table              Types                Irrigation<BRK/>
 ication      Level                        Terrain    Practices in Area<BRK/>
 -----------------------------------------------------------------------<BRK/></THD>
<BRK/>
 SEVERE      Water table         Any        Any         Any<BRK/>
             Within 1 foot<BRK/>
             of bottom<BRK/>
             of system<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             Water table         GC, SC     Any         Any<BRK/>
             Within 5 feet       CL, CH<BRK/>
             of bottom           OH<BRK/>
             of system<BRK/>
 ------------------------------------------------------------------------<BRK/>
 BAD         Water table         GW, GP,    Any         Any<BRK/>
             Within 5 feet       SW, SP<BRK/>
             of bottom<BRK/>
             of system<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             No                  GC, SC,    Any         Equivalent to<BRK/>
             groundwater         SW, CH,                3 in. or more<BRK/>
             encountered         OH                     in any one<BRK/>
                                                        month or 20 in.<BRK/>
                                                        or more in one<BRK/>
                                                        year.<BRK/>
 ------------------------------------------------------------------------<BRK/>
 MODERATE    No                  GM, SM,    Any         Equivalent to<BRK/>
             groundwater         ML, OL,                3 in. or more<BRK/>
             encountered         MH                     in any one<BRK/>
                                                        month or 20 in,<BRK/>
                                                        or more in<BRK/>
                                                        one year.<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             No                  GC, SC,    Any         Equivalent to<BRK/>
             groundwater         CL, CH,    except      less than 3 in.<BRK/>
             encountered         OH         low         in any one month<BRK/>
                                            areas       or less than<BRK/>
                                                        20 in. in one year.<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             No                  GW, GP,    Any         Any<BRK/>
             groundwater         SW, SP<BRK/>
             encountered<BRK/>
<BRK/>
             OR<BRK/>
<BRK/>
             No                  GM, SM,    Any         Equivalent to<BRK/>
             groundwater         ML, SM,                less than 3 in.<BRK/>
             encountered                                in any one month<BRK/>
                                                        or less than 20 in.<BRK/>
                                                        in one year.<BRK/></TBL>
</ENG><BRK/></SPT>
</PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   FACTORY FABRICATED, DIRECT-BURIED, DRAINABLE, DRYABLE, TESTABLE (DDT) SYSTEMS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.1   DDT Steam and High Temperature Hot Water Carrier Pipes</TTL><BRK/>
<BRK/>
<TXT>Requirements shall be in accordance with the "Heat Distribution Piping" paragraph.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.2   DDT Condensate Carrier Pipes</TTL><BRK/>
<BRK/>
<TXT>Carrier piping for condensate return systems shall be steel, schedule 80.  Pipe requirements shall be in accordance 
with the "Heat Distribution Piping" paragraph.</TXT><BRK/>
<BRK/>
<TXT>Do not locate condensate pipes in conduit casings which contain steam pipes or any other piping.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.3   DDT Carrier Pipe Insulation</TTL><BRK/>
<BRK/>
<TXT>Carrier pipe insulation shall conform to minimum thicknesses and type listed in Tables 1 and 2 as required for 
temperature in carrier pipe specified under the "Rated Conditions" paragraph.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4   Insulation Banding and Scrim</TTL><BRK/>
<BRK/>
<TXT>Stainless steel bands and clips, at least<MET> 13 mm</MET><ENG> 0.5 inches</ENG> wide, <RID>ASTM A 167</RID> (304 stainless steel), maximum spacing<MET>
 460 mm</MET><ENG> 18 inches</ENG> shall be used over the scrim to secure the insulation onto the carrier pipe.  A minimum of 
two bands are required for each<MET> 1300 mm</MET><ENG> 4 foot</ENG> section of insulation.  Vinyl-coated fiberglass scrim, <RID>FS L-S-125</RID>
, Type II, Class 2, with 18 x 16 mesh (number of filaments per<MET> mm</MET><ENG> inch</ENG>) and made of<MET> 0.335 mm</MET><ENG> 0.013 inch</ENG> diameter 
vinyl-coated fibrous glass yarn.  Bands are used over the scrim to secure the insulation onto the carrier pipe.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.5   Casing</TTL><BRK/>
<BRK/>
<TXT>Smooth-wall steel, electric resistance spiral welded, conforming to <RID>ASTM A 134</RID>, <RID>ASTM A 135/A 135M</RID>, or <RID>ASTM A 139/A 139M</RID>
 and the values tabulated below.  Provide eccentric connectors as necessary between casing sections to provide 
drainage of casing section between manholes and between manholes and buildings.</TXT><BRK/>
<MET><TBL><THD><BRK/>
Casing Diameter (mm)   Minimum Thickness (mm)<BRK/></THD>
<BRK/>
     150 - 660               6.35<BRK/>
     675 - 900               6.35<BRK/>
     940 - 1050              6.35<BRK/>
     1170                    6.35<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
   Casing Diameter (in.)   Minimum Thickness (in.)<BRK/></THD>
<BRK/>
       6 - 26                 0.250<BRK/>
      27 - 36                0.250<BRK/>
      37 - 42                0.250<BRK/>
      46                     0.250<BRK/></TBL>
</ENG><BRK/></SPT>
<SPT><TTL>2.1.6   Casing End Plates, Vents, and Drains</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Designer must accommodate<MET> 25 mm</MET><ENG> one inch</ENG> vent pipe in the design of the 
manhole.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>End plates shall be made of <RID>ASTM A 36/A 36M</RID> steel, minimum thickness<MET> 13 mm</MET><ENG> 0.5 inches</ENG> for <SUB>conduit</SUB> pipe sizes 
above<MET> 300 mm</MET><ENG> 12 inches</ENG> and<MET> 9.5 mm</MET><ENG> 0.375 inches</ENG> for conduit pipe sizes<MET> 300 mm</MET><ENG> 12 inches</ENG> and less.  Provide<MET> 25 
mm</MET><ENG> 1 inch</ENG> <RID>ASTM A 53/A 53M</RID>, Schedule 40, galvanized vent riser pipe on end plate vent opening.  Vent pipe shall 
extend to top of manhole and terminate<MET> 300 mm</MET><ENG> 12 inches</ENG> above grade with a 180 degree bend.  Provide<MET> 25 mm</MET><ENG> one 
inch</ENG> drain at the bottom and vent at the top.  Construct with welded steel half coupling welded to the end plate, 
and brass plugs.  Plug drains, do not plug vents.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.7   Air Space</TTL><BRK/>
<BRK/>
<TXT>Provide continuous<MET> 25 mm</MET><ENG> one inch</ENG> minimum air space between carrier pipe insulation and casing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.8   Casing Coating</TTL><BRK/>
<BRK/>
<TXT>Fusion-bonded epoxy, minimum thickness<MET> 1.0 mm</MET><ENG> 0.040 inches</ENG>.  Rated by coating manufacturer for continuous service 
for at least 25 years at temperatures of<MET> 110 degrees C</MET><ENG> 230 degrees F</ENG> and having a coefficient of expansion similar 
to that of steel.  Coating shall be applied in accordance with the coating manufacturer's instructions.  Factory-inspect 
for holidays and make repairs as necessary.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.9   Coating of End Plates and conduit Sections Extending in Manholes</TTL><BRK/>
<BRK/>
<TXT>Zinc-rich coating that conforms to <RID>AASHTO M 300</RID>, Type IA except that volatile organic compounds shall not exceed<MET>
 0.34 kg per liter</MET><ENG> 2.8 pounds per gallon</ENG>.  The zinc rich coating shall be applied in accordance with the coating 
manufacturer's requirements including surface preparation.  No additional top coat shall be applied.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.10   Carrier Pipe Guides</TTL><BRK/>
<BRK/>
<TXT>Maximum spacing<MET> 3 m</MET><ENG> 10 feet</ENG> on centers, no more than<MET> 1500 mm</MET><ENG> 5 feet</ENG> from pipe ends, minimum of three guides per 
elbow section.  Guides shall be designed to allow thermal expansion without damage, provide proper pipe guiding, 
and to allow horizontal movement in two directions as required at expansion loops and bends.  Design of supports 
shall permit flow of water and air vapor through the support.  Pipe insulation shall extend thru the pipe guides 
and be protected by steel sleeves.  Design of guides shall be such that no metal to metal contact exists between 
the casing and the carrier pipe.  Insulation or non-metallic material used to ensure no metal to metal contact 
shall be designed to not be compressed by the weight of the carrier pipe when full of water.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.11   Anchor Plates</TTL><BRK/>
<BRK/>
<TXT>Anchor plate shall be <RID>ASTM A 36/A 36M</RID> steel, welded to carrier pipe and casing,<MET> 13 mm</MET><ENG> 0.5 inches</ENG> minimum thickness 
and shall include, passages for air flow and water drainage through the annular air space in the system.  Exterior 
surface of the anchor plate shall be coated with the same coating material as the casing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.12   <SUB>Field Connection of Casing Sections</SUB></TTL><BRK/>
<BRK/>
<TXT>Steel section conforming to casing specification, welded to casing sections, coated on all surfaces with UHDS 
manufacturer's coating field repair compound, and covered with a<MET> 1.3 mm</MET><ENG> 0.05 inch</ENG> minimum thickness polyethylene 
shrink sleeve designed for a service temperature exceeding<MET> 260 degrees C</MET><ENG> 500 degrees F</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.13   Manufacturer's Identification</TTL><BRK/>
<BRK/>
<TXT>Provide embossed brass or stainless steel tag hung by brass or stainless steel chain at each end of each conduit 
or insulated piping in the manholes and buildings.  The tag shall identify UHDS manufacturer's name, date of 
installation, Government contract, and manufacturer's project number.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2   FACTORY FABRICATED, DIRECT-BURIED, WATER-SPREAD-LIMITING (WSL) SYSTEM</TTL><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Steam/High Temperature Hot Water Carrier Pipes</TTL><BRK/>
<BRK/>
<TXT>Refer to Paragraph, HEAT DISTRIBUTION PIPING for pipe material requirements.  The pipe shall be steel with the 
ends machined and metallized to provide a satisfactory sealing surface for the sealing rings. The metallizing 
shall be a high nickel alloy applied to an excess thickness and then machined to the required OD.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2   Condensate Carrier Pipes</TTL><BRK/>
<BRK/>
<TXT>Carrier piping for condensate return systems shall be steel, Schedule 80.  Refer to paragraph entitled "HEAT 
DISTRIBUTION PIPING" for pipe requirements.  Condensate piping shall not be located in casings which contain 
steam piping or any other piping.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3   Casing for Steam and Condensate</TTL><BRK/>
<BRK/>
<TXT>The casing shall be reinforced thermosetting resin plastic pipe (RTRP) manufactured by the filament winding process.  
The casing pipe shall be wound to meet <RID>ASTM D 2310</RID> classification RTRP and <RID>ASTM D 2996</RID>.  The resin shall be a 
polyester isothalic resin.  The outer surface shall be coated with a pigmented, protected resin containing a 
parafinated wax and ultraviolet inhibitors.  Casing thickness shall be as follows:</TXT><BRK/>
<MET><TBL><THD><BRK/>
   Carrier Pipe                  Casing<BRK/>
      Size                     Thickness<BRK/>
       mm                         mm<BRK/></THD>
<BRK/>
       50                         5<BRK/>
       80                         5<BRK/>
      100                         5<BRK/>
      150                         6.5<BRK/>
      200                         6.5<BRK/>
      250                         6.5<BRK/>
      300                         6.5<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
   Carrier Pipe                  Casing<BRK/>
      Size                     Thickness<BRK/>
     Inches                     Inches<BRK/></THD>
<BRK/>
       2                        0.185<BRK/>
       3                        0.185<BRK/>
       4                        0.185<BRK/>
       6                        0.250<BRK/>
       8                        0.250<BRK/>
      10                        0.250<BRK/>
      12                        0.250<BRK/></TBL>
</ENG><BRK/></SPT>
<SPT><TTL>2.2.4   Pipe Coupling, Steam</TTL><BRK/>
<BRK/>
<TXT>Coupling shall be of a multi-stage seal designed to accommodate the expansion and contraction of the system in 
the coupling.  Couplings shall be of corrosion resistant materials capable of handling the design characteristics 
of the system listed in paragraph entitled "Rated Characteristics".  The annular seals and carrier pipe ends 
shall be specifically designed to protect the seals and resist abrasion due to lateral loads in the system.</TXT><BRK/>
 <BRK/></SPT>
<SPT><TTL>2.2.5   Pipe Coupling, Condensate</TTL><BRK/>
<BRK/>
<TXT>Coupling shall be a single stage seal design to accommodate the expansion and contraction of the adjacent pipes.  
Coupling shall be of corrosion resistance materials capable of handling the design characteristics of the system 
listed in paragraph entitled "Rated Characteristics."  The annular seals and carrier pipe ends shall be specifically 
designed to protect the seals and resist abrasion due to lateral loads in the system.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.6   Carrier Pipe Insulation</TTL><BRK/>
<BRK/>
<TXT>Conform to minimum thicknesses and type of insulation listed for WSL systems in Tables 1 and 2 as required for 
temperature in carrier pipe.  Insulation shall consist of an inner layer of high temperature calcium silicate 
and an outer layer of polyurethane foam.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.6.1   Calcium Silicate Insulation for Steam Systems</TTL><BRK/>
<BRK/>
<TXT>The calcium silicate insulation shall be a hydrous material satisfactory for temperatures to<MET> 650 degrees C</MET><ENG> 1200 
degrees F</ENG>.  Calcium Silicate insulation shall conform to <RID>ASTM C 533</RID>.  The physical properties shall be as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">Density (dry)<MET> 208 kg/cubic meter</MET><ENG> 13 lbs./cu. ft.</ENG> (minimum)<BRK/>
Compressive Strength to produce 5 percent compression: <MET> 1723 kPa</MET><ENG> 250 psi</ENG>  (For<MET> 37 mm</MET><ENG> 1.5 inch</ENG>
 thick sample)</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">Maximum Linear shrinkage after 24 hour soaking period at <MET> 650 degrees C</MET><ENG> 1200 degrees F</ENG>: 1.1 
percent</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">Maximum Thermal Conductivity k<MET> k(metric) = W/(meter*K)</MET><ENG> k = BTU-IN/HR-FT2-DEG.F)</ENG>.  Where k varies 
with temperature as shown:</ITM><BRK/>
<BRK/>
<ITM>Mean Temp   100    200     300      400<BRK/>
     k      0.38   0.41    0.44     0.48<BRK/>
k(metric)   0.04   0.04    0.04     0.04</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.6.2   Polyurethane Foam Insulation for Steam and Condensate Systems</TTL><BRK/>
<BRK/>
<TXT>Polyurethane foam shall be in accordance with <RID>ASTM C 591</RID>.  The polyurethane foam shall completely fill the annular 
space between the calcium silicate insulation and the casing for the steam pipe and between the carrier pipe 
and the casing for condensate return system.</TXT><BRK/>
<BRK/>
<TXT>Polyurethane foam insulation shall also meet the following requirements:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Type: Two component urethane.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Compressive Strength: <MET> 172 kPa</MET><ENG> 25 psi</ENG> parallel to rise (minimum at 50 percent compression).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Shrinkage: None at<MET> one to 21 degrees C</MET><ENG> 30 to 70 degrees F</ENG>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Free Rise Density: <MET> 32 kg/cubic meter</MET><ENG> 2 lbs/cubic foot</ENG>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Maximum aged k (<MET>32 degrees C</MET><ENG>90 degrees F</ENG>/90 percent RH for 72 hours):</ITM><BRK/>
<BRK/>
<ITM><MET>.02 W/mK</MET><ENG>0.14 (BTU-IN/HR FT-2-DEG. F)</ENG> at<MET> 24 degrees C</MET><ENG> 75 degrees F</ENG>, when tested in accordance 
with <RID>ASTM C 518</RID>.</ITM> <BRK/>
<BRK/>
<ITM INDENT="-0.33">f.   Minimum Closed Cell Content:  90 percent</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.6.3   Insulation Concentricity</TTL><BRK/>
<BRK/>
<TXT>Carrier pipe shall be concentric in relation to the casing pipe.  The allowable maximum deviation from center 
line of the carrier pipe shall be plus or minus<MET> 6 mm</MET><ENG> 0.25 inch</ENG> at the casing center point and plus or minus<MET> 1.5 
mm</MET><ENG> 0.06 inch</ENG> at the end seals.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.6.4   Insulated Fittings</TTL><BRK/>
<BRK/>
<TXT>Fittings shall be pre-insulated by manufacturer using the same insulation thickness and casing as the straight 
sections.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.6.5   Coupling Insulation for Steam Systems</TTL><BRK/>
<BRK/>
<TXT>The material which locks the bronze coupling in the casing shall be composed of refractory composite.  The approximate 
minimum  conductivity of this material shall be<MET> .2 W/(meter*K)</MET><ENG> 1.6 (BTU/HR/F/IN DEG.F)</ENG> at a mean temperature 
of<MET> 1260 degrees C</MET><ENG> 2300degrees F</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.6.6   Coupling Insulation for Condensate Systems</TTL><BRK/>
<BRK/>
<TXT>The coupling shall be insulated with polyurethane foam per requirements herein.  The insulation thickness shall 
be equal to the carrier pipe insulation.  The coupling shall be encased in the same casing as the pipe.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2.7   Manufacturer's Identification</TTL><BRK/>
<BRK/>
<TXT>Provide an embossed brass or stainless steel tag hung by a brass or stainless steel chain at each end of each 
casing or insulated piping in the manholes and buildings.  The tags shall identify UHDS manufacturer's name and 
date of installation.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.8   End Seals</TTL><BRK/>
<BRK/>
<SPT><TTL>2.2.8.1   General</TTL><BRK/>
<BRK/>
<TXT>Each preinsulated section of piping shall completely seal the insulation providing a permanent water and vapor 
seal at each end of the preinsulated section of piping.  Preinsulated factory fabricated sections of piping modified 
in the field shall be provided with an end seal which is equivalent to the end seals furnished with the preinsulated 
section of piping.  Tests shall be conducted by the UHDS manufacturer to demonstrate that casings, couplings 
and end seals are capable of resisting penetration of water into the casing and insulation under rated conditions.  
The <SUB>WSL System Tests</SUB> shall be performed on each type of pre-fabricated system to be furnished, and the test results 
shall be verified by an independent testing laboratory.  The steam system shall be tested and certified in accordance 
with paragraph entitled Assembly Testing of WSL systems for Steam Service.  The Condensate Return system shall 
be tested and certified in accordance with paragraph entitled "Assembly ASSM Testing of WSL systems for Condensate 
Return Service".  Test reports in booklet form showing all field tests performed to prove compliance with the 
specified performance criteria, upon completion and testing of the installed system.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.8.2   End Seals for Steam Service</TTL><BRK/>
<BRK/>
<TXT>End seals shall be elastomer-ring type designed and dimensioned to fit in the annular space between the casing 
and the carrier pipe.  Tape used for covering field repair joints shall be multi polymer alloy film type and 
shall be compatible with synthetic elastomeric tape, suitable for cold application.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.8.3   End Seals for Condensate Return Service Types</TTL><BRK/>
<BRK/>
<TXT>End seals provided shall be one of the following types:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Carrying the outer casing over tapered pipe insulation ends and extending it to the carrier 
pipe.  Sufficient surface bonding area shall be provided between the casing and the carrier 
pipe.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Using specially designed molded caps made of polyethylene or rubber of standard manufactured 
thickness.  A minimum<MET> 40 mm</MET><ENG> 1 1/2 inch</ENG> surface bonding area shall be provided between the cap 
and both the casing and carrier pipe.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Using elastomer-ring end seals designed and dimensioned to fit in the annular space between 
the casing and the carrier pipe.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Using a waterproof mastic seal vapor barrier over the exposed insulation ends.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Shrink sleeves.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2.9   Assembly Testing of WSL Systems for Steam Service</TTL><BRK/>
<BRK/>
<TXT>The tests shall demonstrate that the WSL system will operate successfully for 25 years under typical operating 
conditions.  The tests shall be conducted in both a dry and wet environment.  The WSL system shall be as described 
in the manufacturer's brochure.  The testing program described below shall be conducted at the expense of the 
WSL system manufacturer.  Tests shall be witnessed and verified by an independent testing laboratory.  The entire 
pre-insulated test section shall be hydrostatically tested, with water, to<MET> 2600 kPa</MET> <ENG>375 psig</ENG> (1/5 times the rated 
pressure) before and after temperature cycling.  The tests shall be conducted in a dry environment which followed 
by a test in a wet environment for 60 cycles which demonstrates resistance to ground water infiltration.  All 
tests shall be conducted on one test section and all testing shall be completed in 1 time period (approximately 
6 weeks) and the 120 testing cycles shall be continuous except for weekend time periods.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.2.9.1   Apparatus</TTL><BRK/>
<BRK/>
<TXT>A curved bottom test tank at least<MET> 3.7 m</MET><ENG> 12 feet</ENG> long,<MET> 0.8 m</MET><ENG> 32 inches</ENG> wide,<MET> 0.8 m</MET><ENG> 32 inches</ENG> deep shall be used.  
The tank shall be fitted with a gasketed and bolted cover to pressurize the tank to<MET> 60 kPa</MET><ENG> 8.67 psig</ENG>.  The tank 
shall have a drain at the lowest point and a vent at the highest point.  Manhole entrance sleeves (i.e. wall 
sleeves through the ends of the tank to simulate manhole entries in actual field conditions) shall be centrally 
located on each end of the tank.  Auxiliary equipment shall include:  Steam supply with sufficient capacity to 
satisfy testing requirements, makeup water tank and pump, and a means for continuously recording temperatures 
and pressures at needed locations.  Thermocouples shall be used to record temperatures at the following points:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Carrier pipe at tank inlet (in thermowell).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Casing at mid-point in pipe length (on casing).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Casing at anchor point (above FRRP overwrap on plate).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Casing at field joint (repair, on casing).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Casing at coupling mid-point (on casing).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  End seal flange at coupling (on elastomer).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Outer edge of new end plate (at steel plate and FRP wrap).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Carrier pipe at specimen outlet end (in thermowell).</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">i.  Interface of calcium-silicate and polyurethane insulations.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">j.  Carrier pipe internal pressure, at inlet to test specimen.</ITM><BRK/>
<BRK/>
<TXT>Surface thermocouples shall be epoxied to the surface of the casing.  The calibration of the thermocouples shall 
be checked and recorded prior to  installation and the recorder shall record within<MET> 0.06 degrees C</MET><ENG> 0.1 degrees 
F</ENG> resolution.  A pressure transmitter shall be used to record pressure in the test tank.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.9.2   Test Section</TTL><BRK/>
<BRK/>
<TXT>A<MET> 100 mm</MET><ENG> 4 inch</ENG> steel carrier pipe test section consisting of<MET> 8 m</MET><ENG> 27 feet</ENG> of pre-insulated pipe meeting specified 
materials and design requirements shall be provided.  Approximately<MET> 3.7 m</MET><ENG> 12 feet</ENG> of the test section shall be 
encased within the tank as described below.  The test section within the tank shall consist of an expansion coupling, 
field repair joint, anchor plate, anchor block and end seals.  The test section shall be installed (as directed) 
on at least<MET> 280 mm</MET><ENG> 11 inches</ENG> of firmly tamped sand.  Sand shall not be any lower than<MET> 100 mm</MET><ENG> 4 inches</ENG> from the 
top of the tank.  The test section shall be anchored to the tank wall at one end and the building floor at the 
other end on the portion of the pipe external to the tank.  The expansion coupling shall be misaligned by 1.5 
degrees in the horizontal plane.  Sand (<MET>118 mL</MET><ENG>4 fluid oz.</ENG>) shall be introduced into the carrier pipe and disbursed 
throughout the test loop at startup.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.9.3   Resistance to Water Damage and Joint Leakage</TTL><BRK/>
<BRK/>
<TXT>This test shall simulate the operation of the WSL system to assure the system will provide successful service 
life through its expected life span.  The system shall be tested in steam service by cycling for an extended 
period of time, as described below.  System performance shall be deemed successful if there is no joint leakage, 
deformation of the casing, deterioration of the end seals, or any other deleterious effects.</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  The piping system shall be subjected to 60 cycles of admitting steam into the system while 
at an ambient temperature of less than<MET> 38 degrees C</MET><ENG> 100 degrees F</ENG>, heating the system up to 
a temperature of<MET> 207 degrees C</MET><ENG> 406 degrees F</ENG> (as measured at the core pipe at the tank inlet 
and tank outlet), stopping the steam admission and allowing the system to cool back to ambient 
termperature.  The system shall be held at<MET> 207 degrees C</MET><ENG> 406 degrees F</ENG> minimum for a minimum 
of 30 minutes, each cycle.  This cycling shall continue for 60 cycles in dry sand followed by 
60 cycles in a saturated environment.  The reduction in temperature to less than<MET> 38 degrees 
C</MET><ENG> 100 degrees F</ENG> shall occur naturally with no artificial means of cooling used.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Results shall conform to paragraph Criteria for Satisfactory Results and Reporting.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.9.4   Resistance to Mechanical or Structural Damage</TTL><BRK/>
<BRK/>
<TXT>This test shall simulate loads induced by truck traffic over pipe, which may occur under actual operating conditions.  
This test shall be conducted commencing with the 18th cycle of the Resistance to Water Damage and Joint Leakage 
test and continue through the 60th cycle.  Other aspects of the Resistance to Water Damage and Joint Leakage 
test shall continue simultaneously with this test.</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Apparatus:  Same as for apparatus used in Resistance to water damage and joint leakage test 
loading device, with the addition of a<MET> 96 kPa</MET><ENG> 2000 psf</ENG>.  A hydraulic jack shall be used to apply 
the test pressure against a<MET> 500 x 500 mm</MET><ENG> 18 x 18 inch </ENG> plate bearing on the sand directly over 
the coupling in the tank.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Procedure:  A steady and constant vertical load of<MET> 96 kPa</MET><ENG> 2000 psf</ENG> shall be applied to the 
plate for 14 days during the test.  The test section shall be installed as in the Resistance 
to water damage and joint leakage test.  During the 14 day loading period, steam shall be circulated 
through the carrier pipe alternately at ambient and<MET> 207 degrees C</MET><ENG> 406 degrees F</ENG> as in earlier 
test.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Results:  Requirements shall be in accordance with paragraph Criteria for Satisfactory Results 
and Reporting.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.9.5   Resistance to Ground Water Infiltration</TTL><BRK/>
<BRK/>
<TXT>This test shall be the wet environment test conducted during the second 3 weeks (61st to 120th cycles) of the 
test period to show that the WSL system will resist the penetration of ground water into the system.</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Apparatus:  Same as for basic apparatus used in Resistance to Water Damage and Joint Leakage 
phase test, plus the following:</ITM><BRK/>
<BRK/>
<ITM>(1)  One<MET> 200 L</MET><ENG> 50 gallon</ENG> water reservoir with a<MET> 0 to 206 kPa</MET><ENG> 0 to 30 psig</ENG> pressure gauge and 
compressed air connection.</ITM><BRK/>
<BRK/>
<ITM>(2)  Provisions to introduce pressurized red dye into the curved bottom test tank.  The water/dye 
solution shall be mixed to a concentration in accordance with the dye manufacturer's recommendation 
for maximum detectability.</ITM><BRK/>
<BRK/>
<ITM>(3)  One pressure tank with<MET> 0 to 206 kPa</MET><ENG> 0 to 30 psig</ENG> static pressure gauge.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Procedure:  This phase shall start on the 61st cycle and continue until the 120th cycle.  
The test section of pipe shall be the same test segment used in the previous tests.  The tank 
cover shall be bolted in place and the Resistance to Ground Water Infiltration test shall begin.  
The water/dye source shall be attached to the fill fitting and a surge tank shall be attached 
to the vent with a tee fitting.  The pressure tank shall have<MET> 0 to 206 kPa</MET><ENG> 0 to 30 psig</ENG> static 
pressure gauge attached.  The other branch of the tee fitting shall employ a shut-off valve.  
With the shut-off valve open, the water/dye mixture shall be admitted into the tank through 
the fill fitting until the tank is full and water/dye runs freely from the open valve.  The 
valve shall be closed and the filling shall continue until the pressure reaches<MET> 60 kPa</MET><ENG> 8.67 
psig</ENG>.  The tank pressure shall be maintained throughout the test period.  Steam shall be circulated 
through the carrier pipe and cycled from ambient to<MET> 207 degrees C</MET><ENG> 406 degrees F</ENG> as in the previous 
test.  At the end of the test, the pressure shall be relieved by opening the vent valve and 
the water/dye shall be drained from the tank through the drain fitting.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Results:  Requirements shall be in accordance with paragraph criteria for Satisfactory Results 
and Reporting.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.9.6   Criteria for Satisfactory Results and Reporting</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Reporting:  Logs of times and temperature shall be recorded to assure compliance with test 
requirements and procedures.  Complete photographic documentation of the construction and operation 
of the test facility, as well as the piping system components before and after testing, shall 
be produced.  Data shall be analyzed to assure complete compliance with test objectives.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Drawing:  A drawing showing details of the test apparatus and test specimen shall be provided.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  For the Resistance to Water Damage and Joint Leakage test:  Joints and end seals shall be 
removed for examination, immediately upon completion of all test cycles.  Successful results 
shall show that steam has not leaked out of the carrier pipe and that the components show no 
signs of deterioration.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  For the Resistance to Mechanical or Structural Damage test:  The loading shall not have 
been sufficient to cause the casing to be damaged or deformed enough to impair functioning of 
the system.  The casing shall not be ruptured or deformed more than<MET> 25 mm</MET><ENG> one inch</ENG> in any direction.  
Casing sections with pipe anchors shall not fail.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  For the Resistance to Ground Water Infiltration test:  Determine whether or not the water/dye 
solution has entered the insulation.  This shall be observed by removing and inspecting all 
joints and seals for dye penetration at the end of the test.  Results will be deemed successful 
if no dye solution is evident in the insulation.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Evidence of Test Results:  After completion of all tests, the test apparatus shall be dismantled 
for visual inspection of all critical components subjected to the heat cycling, water infiltration 
and loading tests.  All parts will be examined thoroughly for any detrimental affects.  Examinations 
specified shall be conducted.  Log sheets, test data and color photographs shall be kept on 
file and made available as required to document and substantiate compliance to the test requirements.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Report:  A report from the independent testing agency shall be submitted.  The report shall 
include the laboratory analysis of the condition of the test section and shall attest that the 
testing conditions were followed.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.2.10   Assembly Test of WSL Systems for Condensate Return Service</TTL><BRK/>
<BRK/>
<TXT>Testing and certification procedures by an independent testing laboratory shall demonstrate that casings and 
end seals are capable of resisting penetration of ground water or condensate into the casing and insulation.  
The test shall be performed on the type of prefabricated system to be furnished.  If more than 1 type of prefabricated 
system is to be used, the tests shall be performed on each type.  The test shall consist of hot and cold cycle 
testing followed by immersion in a water filled chamber with a head pressure.  The hot and cold cycle testing 
shall consist of a minimum of 120 cycles, of temperature cycling.  A fluid with a temperature of<MET> 5 degrees C</MET><ENG> 
40 degrees F</ENG> shall circulate through the carrier pipe alternating every 3 hours with a fluid with a temperature 
of<MET> 120 degrees C</MET><ENG> 250 degrees F</ENG> circulating through the carrier pipe.  While the hot and cold cycle test is being 
performed, the test sample shall be either buried or encased in dry bedding sand with a minimum of<MET> 300 mm</MET><ENG> 12 
inches</ENG> of sand all around the test sample.  The carrier pipe size of the test sample shall be<MET> 75 mm</MET><ENG> 3 inches</ENG> 
in diameter and shall be restrained during the test period.  The insulation thickness shall not exceed the maximum 
thickness provided for the piping in the project.  Transition time for temperature cycle testing shall not exceed 
15 minutes in going from cold to hot and 30 minutes in going from hot to cold.  The fluid in the carrier pipe 
shall be water, or steam.  Following the hot and cold cycling test, the test sample shall be immersed in a water 
filled chamber.  The pressure on the highest point of the test sample shall not be less than<MET> 60 kPa</MET><ENG> 20 feet</ENG> of 
water head pressure subjected over the entire length of the<MET> 2.4 m</MET><ENG> 8 foot</ENG> test sample of prefabricated pipe.  
The water shall contain a dye penetrant, which shall be used to check for end seal leakage.  The pressure in 
the chamber shall be held for not less than 48 hours.  Upon completion of this pressure test, the test sample 
shall be cut open.  With the use of a light that will readily show the presence of the dye that was in the water, 
the test sample shall be inspected.  Evidence of the dye inside the test sample shall indicate that the end seal 
is not acceptable and cannot be certified.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3   PIPE <SUB>INSULATION</SUB> FOR DIRECT BURIED HEAT DISTRIBUTION SYSTEMS</TTL><BRK/>
<BRK/>
<TXT>Materials containing asbestos are not permitted.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.3.1   Insulation Thickness</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Delete inapplicable columns in Tables 1 and 2.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The minimum thickness of insulation for the heat distribution system shall be in accordance with Tables 1 and 
2 in which the insulations listed have passed the 96 hour boiling water test.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>TABLE 1</HL4><BRK/>
<HL4>MINIMUM PIPE INSULATION THICKNESS (mm)</HL4><BRK/>
<BRK/>
<HL4>For Steam (100 to 2.800 kPa (gage)) and High Temperature</HL4><BRK/>
<HL4>Hot Water Supply and Return (120 to 230 degrees C).</HL4><BRK/>
<BRK/>
              INSULATIONS                             INSULATIONS<BRK/>
      For Drainable/Dryable Systems      For other Pre-Engineered Systems<BRK/>
<BRK/>
  Nominal Pipe                Kaylo-10                    WSL<BRK/>
  Diameter          Epitherm  Thermo-12         Calcium      Polyurethane<BRK/>
  (mm)        Paroc Delta     Super Caltemp      Silicate<BRK/>
 -------------------------------------------------------------------------<BRK/></THD>
<BRK/>
     25       50      63         100                 N/A             N/A<BRK/>
     40       50      63         100                 N/A             N/A<BRK/>
     50       63      85         110                 N/A             N/A<BRK/>
     65       63      85         110                 N/A             N/A<BRK/>
     80       75     100         125                  25             +31<BRK/>
    100       75     100         125                  25             +31<BRK/>
    125       75     100         125                 N/A             N/A<BRK/>
    150       85     110         135                  35             +34<BRK/>
    200       85     110         135                  50             +30<BRK/>
    250      100     125         150                  63             +33<BRK/>
    300      100     125         150                  50             +32<BRK/>
    350      100     125         150                 N/A             N/A<BRK/>
    400      100     125         150                 N/A             N/A<BRK/>
    450      100     125         150                 N/A             N/A<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>TABLE 1</HL4><BRK/>
<HL4>MINIMUM PIPE INSULATION THICKNESS (inches)</HL4><BRK/>
<BRK/>
<HL4>For Steam (16 to 408 psig) and High Temperature</HL4><BRK/>
<HL4>Hot Water Supply and Return (250 to 450 degrees F).</HL4><BRK/>
<BRK/>
              INSULATIONS                             INSULATIONS<BRK/>
     For Drainable/Dryable Systems      For other Pre-Engineered Systems<BRK/>
<BRK/>
  Nominal Pipe                Kaylo-10                    WSL<BRK/>
  Diameter          Epitherm  Thermo-12         Calcium      Polyurethane<BRK/>
  (inches)    Paroc Delta     Super Caltemp      Silicate<BRK/>
 -------------------------------------------------------------------------<BRK/></THD>
<BRK/>
    1.0       2.0     2.5         4.0                 N/A             N/A<BRK/>
    1.5       2.0     2.5         4.0                 N/A             N/A<BRK/>
    2.0       2.5     3.5         4.5                 N/A             N/A<BRK/>
    2.5       2.5     3.5         4.5                 N/A             N/A<BRK/>
    3.0       3.0     4.0         5.0                 1.0           +1.23<BRK/>
    4.0       3.0     4.0         5.0                 1.0           +1.22<BRK/>
    5.0       3.0     4.0         5.0                 N/A             N/A<BRK/>
    6.0       3.5     4.5         5.5                 1.5           +1.34<BRK/>
    8.0       3.5     4.5         5.5                 2.0           +1.21<BRK/>
   10.0       4.0     5.0         6.0                 2.5           +1.31<BRK/>
   12.0       4.0     5.0         6.0                 2.0           +1.29<BRK/>
   14.0       4.0     5.0         6.0                 N/A             N/A<BRK/>
   16.0       4.0     5.0         6.0                 N/A             N/A<BRK/>
   18.0       4.0     5.0         6.0                 N/A             N/A<BRK/></TBL>
</ENG><MET><TBL><THD><BRK/>
<HL4>TABLE 2</HL4><BRK/>
<HL4>MINIMUM PIPE INSULATION THICKNESS (mm)</HL4><BRK/>
<HL4>CONDENSATE RETURN</HL4><BRK/>
<HL4>HIGH TEMPERATURE HOT WATER RETURN SYSTEM</HL4><BRK/>
<BRK/>
  Nominal Pipe                      Kaylo-10<BRK/>
  Diameter                          Thermo-12<BRK/>
  (mm)         Paroc    Epitherm    Super Caltemp     Polyurethane<BRK/>
 ------------------------------------------------------------------<BRK/></THD>
<BRK/>
      25        35        50            75                  N/A<BRK/>
      40        35        50            75                  N/A<BRK/>
      50        35        50            75                   19<BRK/>
      65        35        50            75                  N/A<BRK/>
      80        50        63            85                   26<BRK/>
      100       50        63            85                   26<BRK/>
      125       50        63            85                  N/A<BRK/>
      150       63        76            110                  30<BRK/>
      200       63        76            110                 N/A<BRK/>
      250       76        100           125                 N/A<BRK/>
      300       76        100           125                 N/A<BRK/>
      350       76        100           125                 N/A<BRK/>
      400       76        100           125                 N/A<BRK/>
      450       76        100           125                 N/A<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>TABLE 2</HL4><BRK/>
<HL4>MINIMUM PIPE INSULATION THICKNESS (inches)</HL4><BRK/>
<HL4>CONDENSATE RETURN</HL4><BRK/>
<HL4>HIGH TEMPERATURE HOT WATER RETURN SYSTEM</HL4><BRK/>
<BRK/>
  Nominal Pipe                      Kaylo-10<BRK/>
  Diameter                          Thermo-12<BRK/>
  (inches)     Paroc    Epitherm    Super Caltemp     Polyurethane<BRK/>
 ------------------------------------------------------------------<BRK/></THD>
<BRK/>
      1.0       1.5       2.0           3.0                  N/A<BRK/>
      1.5       1.5       2.0           3.0                  N/A<BRK/>
      2.0       1.5       2.0           3.0                 0.77<BRK/>
      2.5       1.5       2.0           3.0                  N/A<BRK/>
      3.0       2.0       2.5           3.5                 1.05<BRK/>
      4.0       2.0       2.5           3.5                 1.05<BRK/>
      5.0       2.0       2.5           3.5                  N/A<BRK/>
      6.0       2.5       3.0           4.5                 1.32<BRK/>
      8.0       2.5       3.0           4.5                  N/A<BRK/>
     10.0       3.0       4.0           5.0                  N/A<BRK/>
     12.0       3.0       4.0           5.0                  N/A<BRK/>
     14.0       3.0       4.0           5.0                  N/A<BRK/>
     16.0       3.0       4.0           5.0                  N/A<BRK/>
     18.0       3.0       4.0           5.0                  N/A<BRK/></TBL>
</ENG><BRK/></SPT>
</SPT><SPT><TTL>2.4   HEAT DISTRIBUTION PIPING</TTL><BRK/>
<BRK/>
<SPT><TTL>2.4.1   Steam and High Temperature Hot Water <SUB>Pipe</SUB></TTL><BRK/>
<BRK/>
<TXT>Pipe material shall be steel; seamless, <RID>ASTM A 53/A 53M</RID>, Grade B or <RID>ASTM A 106/A 106M</RID>, Grade B; or electric resistance 
welded <RID>ASTM A 53/A 53M</RID>, Grade B; Schedule 40.  Standard weight permitted for pipe sizes<MET> 300 mm</MET><ENG> 12 inches</ENG> and 
above.  <RID>ASTM A 53/A 53M</RID>, Type F furnace butt welded pipe is not allowed.  No joints shall be allowed in the factory 
fabricated straight section of the carrier pipe.  Factory fabricated piping sections as part of an expansion 
loop or bend shall have all welded joints 100 percent radiographed inspected in accordance with <RID>ASME B31.1</RID>.  
Radiographs shall be reviewed and interpreted by a Certified American Society for Nondestructive Testing (ASNT) 
Level III radiographer, employed by the testing firm, who shall sign the reading report.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.4.1.1   Condensate Pipe</TTL><BRK/>
<BRK/>
<TXT>Steel; seamless, <RID>ASTM A 53/A 53M</RID>, Grade B or <RID>ASTM A 106/A 106M</RID>, Grade B, schedule 80; electric resistance welded <RID>
ASTM A 53/A 53M</RID>, Grade B; Schedule 80. <RID>ASTM A 53/A 53M</RID>, Type F furnace butt welded pipe is not allowed.  No joints 
shall be allowed in the factory fabricated straight section of the carrier pipe.  Factory fabricated piping sections 
as part of an expansion loop or bend shall have all welded joints 100 percent radiographed inspected in accordance 
with <RID>ASME B31.1</RID>.  Radiographs shall be reviewed and interpreted by an ASNT Certified Level II radiographer, employed 
by the testing firm, who shall sign the reading report.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.1.2   Joints</TTL><BRK/>
<BRK/>
<TXT>Joints shall be butt-weld except socket-weld joints are permitted for pipe sizes<MET> 50 mm</MET><ENG> 2 inches</ENG> and smaller.  
Dye penetrant inspection may be used in place of 100 percent radiographic inspection for pipe sizes<MET> 50 mm</MET><ENG> 2 inches</ENG>
 and below. Indicate location and elevation of all field joints on detailed design layout drawings.  Split-ring 
welding rings may be used.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.4.2   <SUB>Fittings</SUB></TTL><BRK/>
<BRK/>
<TXT>All welds in factory fittings shall be 100 percent radiographic inspected.  All radiographs shall be reviewed 
and interpreted by a Certified ASNT Level III radiographer, employed by the testing firm, who shall sign the 
reading report.  The Contracting Officer reserves the right to review all inspection records, and if any welds 
inspected are found unacceptable in accordance with <RID>ASME B31.1</RID>, the fitting shall be removed, replaced, and radiographically 
reexamined at no cost to the government.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.4.2.1   Butt-Welded</TTL><BRK/>
<BRK/>
<TXT>Steel, <RID>ASTM A 234/A 234M</RID>, Grade B, <RID>ASME B16.9</RID>, same schedule as adjoining pipe.  All elbows shall be long radius 
unless otherwise indicated.  Tees shall be full size or reducing as required, having interior surfaces smoothly 
contoured.  Split-ring welding rings may be used.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.2.2   Socket-Welded</TTL><BRK/>
<BRK/>
<TXT>Forged steel, <RID>ASME B16.11</RID>,<MET> 13,800 kPa</MET><ENG> 2000 pound</ENG> class will be used for pipe sizes<MET> 50 mm</MET><ENG> 2 inch</ENG> and below.  Dye 
penetrant inspection may be used in place of 100 percent radiographic inspection of welded fittings for pipe 
sizes<MET> 50 mm</MET><ENG> 2 inch</ENG> and below.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>2.5   <SUB>EXPANSION JOINTS</SUB>, LOOPS AND BENDS</TTL><BRK/>
<BRK/>
<TXT>Stresses shall be less than the maximum allowable stress from the Power Piping Code (<RID>ASME B31.1</RID>).  Submit detailed 
design layout drawings and stress and anchor force calculations for all loops and bends.  Show locations of all 
anchors, guides and supports.  Base the calculations on rated characteristics (pressures and temperatures), specified 
herein, for both the supply and return lines.</TXT><BRK/>
<BRK/></SPT>
</PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1.1   UHDS Design</TTL><BRK/>
<BRK/>
<TXT>The UHDS manufacturer is responsible for the complete design of the UHDS, the product to be supplied, fabrication, 
witnessing installation and testing of the system within the design parameters established by the contract drawings 
and specifications and in compliance with the detailed design.  The complete design of the UHDS shall be prepared, 
signed, and sealed by a Professional Engineer in the employ of the UHDS manufacturer.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2   Installation, Inspection, and Testing</TTL><BRK/>
<BRK/>
<TXT>The pre-engineered system shall be installed, inspected, and tested in accordance with the contract drawings 
and specifications, the UHDS manufacturer's standard procedures, detailed design layout drawings and any directions 
given by the UHDS manufacturer's  representative.  All work described in paragraph "UHDS Manufacturer's Representative's 
Responsibilities" shall be performed in the presence of the UHDS manufacturer's representative.</TXT><BRK/>
<BRK/></SPT>
<SPT>[<TTL>3.1.3   Job Conditions</TTL><BRK/>
<BRK/>
<TXT>Phasing of [demolition and construction] [construction] shall be in accordance with the provisions of Section 
<SRF>01 11 00</SRF> SUMMARY OF WORK, and as shown on contract drawings.</TXT><BRK/>
<BRK/>
]</SPT><SPT><TTL>3.1.4   Interruption of Existing Service</TTL><BRK/>
<BRK/>
<TXT>The contractor shall arrange, phase and perform work and provide temporary facilities, materials, equipment, 
and connections to utilities, to assure adequate heat distribution service for existing installations at all 
times.  Only such absolutely necessary interruptions as may be required for making connections shall be permitted, 
and only at such times when approval is obtained from the Contracting Officer.  Interruptions to heat distribution 
service shall be only with prior approval, and be the minimum possible duration.  All interruptions shall be 
[between the hours of _____ thru _____] [as scheduled under paragraph "PHASING" of Section <SRF>01 11 00</SRF> SUMMARY OF 
WORK] [as approved by the Contracting Officer].</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.5   Connecting to Existing Work</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Any connections to the UHDS distribution will only occur in manholes.  
Designer must ensure that a thorough survey of the aboveground and underground 
conditions is performed.  The contract drawings must identify all potential 
interferences or conflicts.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Connect new work to existing work in a neat and workmanlike manner.  Connection shall be made only in manholes.  
Where an existing structure must be cut or existing utilities interfere, such obstruction shall be bypassed, 
removed, replaced or relocated, restored and repaired.  Any changes required to the UHDS design as a result of 
interferences or conflicts must be approve by the UHDS designer and the Contracting Officer.  Work disturbed 
or damaged shall be replaced to its prior condition, as required by Section <SRF>01 11 00</SRF> SUMMARY OF WORK.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.6   Coordination</TTL><BRK/>
<BRK/>
<TXT>Coordinate the location of all items of equipment and work of all trades.  Maintain operability and maintainability 
of the equipment and systems.  Any relocation of equipment or systems to comply with the requirement of operability 
and maintainability shall be performed by the contractor at his cost.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.7   Grading</TTL><BRK/>
<BRK/>
<TXT>Unless otherwise shown on the contract drawings or the detailed design layout drawings, steam/condensate and 
high temperature hot water supply/return lines shall be graded uniformly downward not less than<MET> 40 mm in 10 meters</MET><ENG>
 5.0 inches in 100 feet</ENG> to the lower point of entry between manholes and/or building entries.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.8   Variations</TTL><BRK/>
<BRK/>
<TXT>Any variations from the approved detailed design layout drawings must be submitted to the Contracting Officer 
for approval.  Variations must be signed and sealed by the UHDS manufacturers' professional engineer responsible 
for the complete design of the UHDS.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.9   Storage and Handling</TTL><BRK/>
<BRK/>
<TXT>Equipment and material placed on the job shall remain in the custody of the Contractor until final acceptance 
whether or not the Contractor has been reimbursed for the equipment and material by the Government.</TXT><BRK/>
<BRK/>
<TXT>The Contractor is solely responsible for the protection of the equipment and material against damage from any 
source.  Protect all materials against entry of water and mud by installing watertight protection on open ends 
at all times.  Sections of the casing or carrier piping found to have been subjected to full or partial submergence 
in water (which would allow the insulation to become wet) shall be immediately replaced.  Protect materials at 
all times while stored or during installation from damage from UV light.  Materials awaiting installation shall 
be completely covered to protect from UV degradation.</TXT>  <BRK/>
<BRK/>
<TXT>Place all damaged items in new operating condition or replace damaged items as determined and directed by the 
Contracting Officer, at no additional cost to the Government</TXT>.<BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2   DEMOLITION</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Ensure that Demolition specification is included in project specifications.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Perform work in accordance with requirements for phasing.  Completely remove all pipe, valves, fittings, insulation, 
and all hangers including the connection to the structure and any fastenings.  Seal all openings in manhole or 
building walls after removal of piping.  All material and equipment removed shall become the property of the 
Contractor and shall be removed from Government property within one week and shall not be stored in operating 
areas.  All flame cutting shall be performed with adequate fire protection facilities available as required by 
safety codes and Contracting Officer.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.2.1   Asbestos Removal</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Existing systems may contain asbestos containing materials.  Provisions 
must be made for an asbestos survey to be performed and abatement measures to 
be included in project specification if necessary.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Conform to Section <SRF>02 82 16.00 20</SRF> ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.3   PIPE, PIPING JOINTS AND FITTINGS</TTL><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Welded Joints</TTL><BRK/>
<BRK/>
<TXT>Clean pipe and fittings inside and outside before and after assembly.  Remove all dirt, scale, and other foreign 
matter from inside the piping by use of a pipe swab or pipe pig before connecting pipe sections, valves, equipment 
or fittings.  Use eccentric connectors as necessary between casing sections to provide drainage of casing section 
between manholes and between manholes and buildings.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.3.2   Fittings</TTL><BRK/>
<BRK/>
<TXT>All changes in direction shall be made with factory-built reinforced fittings.  Field-fabricated fittings and 
miters are not permitted.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.4   WELDING</TTL><BRK/>
<BRK/>
<TXT>The Contractor is entirely responsible for the quality of the welding and shall:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Conduct tests of the welding procedures used by his organization, determine the suitability 
of the procedures used, determine that the welds made shall meet the required tests, and also 
determine that the welding operators have the ability to make sound welds under standard conditions.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Comply with <RID>ASME B31.1</RID>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Perform all welding operations required for construction and installation of the heat distribution 
system.</ITM><BRK/>
<BRK/>
<SPT><TTL>3.4.1   Qualification of Welders</TTL><BRK/>
<BRK/>
<TXT>Rules of procedure for qualification of all welders and general requirements for fusion welding shall conform 
with the applicable portions of <RID>ASME B31.1</RID> and also as outlined below.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.2   Examining Welders</TTL><BRK/>
<BRK/>
<TXT>The contractor shall examine each welder to determine the ability of the welder to meet the qualifications required.  
Test welders for piping for all positions, including welds with the axis horizontal (not rolled) and with the 
axis vertical.  Each welder shall:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Weld only in positions in which he/she has  qualified.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Identify welds with the specific code marking signifying name and number assigned.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.3   Examination Results</TTL><BRK/>
<BRK/>
<TXT>Provide the Contracting Officer with a list of names and corresponding code markings.  Retest welders which fail 
to meet the prescribed welding qualifications.  Disqualify welders who fail the second test, for work on the 
project.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.4   Beveling</TTL><BRK/>
<BRK/>
<TXT>Field bevels and shop bevels shall be done by mechanical means or by flame cutting.  Where beveling is done by 
flame cutting, surfaces shall be thoroughly cleaned of scale and oxidation just prior to welding.  Conform to 
specified standards.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.5   Alignment</TTL><BRK/>
<BRK/>
<TXT>Utilize split welding rings for field joints on all carrier pipes above<MET> 50 mm</MET><ENG> two inches</ENG> to assure proper alignment, 
complete weld penetration, and prevention of weld spatter reaching the interior of the pipe.  Make field joints<MET>
 50 mm</MET><ENG> two inches</ENG> and smaller with welding sockets. </TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.6   Erection</TTL><BRK/>
<BRK/>
<TXT>Piping shall not be split, bent, flattened, or otherwise damaged either before, during, or after installation.  
Where the pipe temperature falls to<MET> 0 degrees C</MET><ENG> 32 degrees F</ENG> or lower, the pipe shall be heated to approximately<MET>
 38 degrees C</MET><ENG> 100 degrees F</ENG> for a distance of<MET> 300 mm</MET><ENG> one foot</ENG> on each side of the weld before welding, and the 
weld shall be finished before the pipe cools to<MET> 0 degrees C</MET><ENG> 32 degrees F</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.7   Defective Welds</TTL><BRK/>
<BRK/>
<TXT>Replace and reinspect defective welds in accordance with <RID>ASME B31.1</RID>.  Repairing defective welds by adding weld 
material over the defect or by peening shall not be permitted.  Welders responsible for defective welds must 
be requalified.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.8   Electrodes</TTL><BRK/>
<BRK/>
<TXT>Electrodes shall be stored in a dry heated area, and be kept free of moisture and dampness during fabrication 
operations.  Discard electrodes that have lost part of their coating.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.4.9   Radiographic Testing</TTL><BRK/>
<BRK/>
<TXT>An approved independent testing firm regularly engaged in radiographic testing shall perform radiographic examination 
of 100 percent of the field welds in the carrier piping of direct-buried systems in accordance with <RID>ASME B31.1</RID>
.  Furnish a set of films showing each weld inspected, a reading report evaluating the quality of each weld, 
and a location plan showing the physical location where each weld is to be found in the completed project, prior 
to installing casing field joints, backfilling and hydrostatic testing.  All radiographs shall be reviewed and 
interpreted by a Certified American Society for Nondestructive Testing Level III radiographer, employed by the 
testing firm, who shall sign the reading report.  The Contracting Officer reserves the right to review all inspection 
records, and if any welds inspected are found unacceptable they shall be removed, rewelded, and radiographically 
reexamined at no cost to the Government.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.5   HEAT DISTRIBUTION SYSTEM INSTALLATION</TTL><BRK/>
<BRK/>
<TXT>The UHDS manufacturer's representative shall oversee the delivery, storage, and witness the installation and 
testing of the system.  All work shall be in strict accordance with the requirements specified herein and with 
the printed instructions of the manufacturer.  These specifications shall take precedence over the printed instructions, 
if conflicts arise.  Printed instructions shall be submitted to the Contracting Officer prior to system installation.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.5.1   Verification of Final Elevations</TTL><BRK/>
<BRK/>
<TXT>Prior to covering the top of the casing with backfill material, but after all temporary supports have been removed 
and initial backfilling of the conduit system has been accomplished, the Contractor shall measure and record 
the elevation of the top of the casing in the trench.  Elevations shall be taken at every completed field joint, 
1/3 points along each pipe section and top of elbows.  This measurement shall be checked against the contract 
drawings.  These measurements shall confirm that the conduit system has been installed to the elevations shown 
on the contract drawings.  Slope shall be uniform to within 0.1 percent.  These measurements shall be recorded 
by the Contractor, included in the UHDS manufacturer's representative daily report, and given to the Contracting 
Officer prior to covering the casing with backfill material.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.2   Excavation, Trenching, and Backfilling</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The designer must coordinate the type of sand to be used with Section 
31 00 00.  Do not allow beach sand or any sand with large amounts of chlorides 
to be specified.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Perform all excavation, trenching, and backfilling as required by the UHDS manufacturer's design and as specified 
in Section <SRF>31 00 00</SRF> EXCAVATION.  Pipe shall lay on a<MET> 305 mm</MET><ENG> 12 inch</ENG> minimum sand bed and backfilled with sand 
on all sides to a minimum of<MET> 150 mm</MET><ENG> 6 inches</ENG> as measured from outside of casing.  Foundation for system must 
be firm and stable.  Foundation and backfill must be free from rocks or substances which could damage the system 
coating.  Concrete anchor and thrust blocks must be installed in undisturbed earth.  Backfilling must not commence 
until system has been satisfactorily pressure tested (both hydrostatic test of carrier and, for DDT systems, 
pneumatic test of casing.  Minimum depth of burial to the top of the casing is<MET>600 mm</MET><ENG> 24 inches</ENG>. Maximum depth 
of burial to the top of the casing is<MET> 3 meters</MET><ENG> 10 feet</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.3   UHDS Manufacturer's Representative Responsibilities</TTL><BRK/>
<BRK/>
<TXT>This shall be a person who regularly performs the duties listed below, is certified in writing by the UHDS manufacturer 
to be technically qualified and experienced in the installation of the system, and shall be authorized by the 
manufacturer to make and sign the daily reports specified herein.  The UHDS Manufacturer's representative shall 
be present at the job site and witness when the following types of work are being performed:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Inspection and unloading.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Inspection of trench prior to commencing installation of system.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Inspection of concrete anchors and thrust blocks.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Hydrostatic testing of carrier piping.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Field joint closure work.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Pneumatic testing of DDT system casing.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Holiday test of conduit coating.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Repair of any coating.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">i.  Installation of cathodic protection system.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">j.  Initial backfill up to<MET> 250 mm</MET><ENG> 10 inches</ENG> above the top of the casing.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">k.  Verification of final elevations.  Elevation readings shall be witnessed and recorded.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">l.  Testing of cathodic protection system.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">m.  Operational tests</ITM><BRK/>
<BRK/>
<TXT>The UHDS manufacturer's representative is to notify the contractor immediately of any problems.  If necessary, 
the UHDS manufacturer's representative will notify the Contracting Officer of problems requiring immediate action, 
otherwise the daily reports will note any problems encountered and indicate the corrective actions taken.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.4   UHDS Manufacturer Representative's Reports</TTL><BRK/>
<BRK/>
<TXT>The UHDS manufacturer representative shall prepare and sign a written daily report.  Present the original daily 
report to the Contracting Officer no later than one working day after it is prepared, and forward one copy to 
the manufacturer's main office.  The report shall state whether or not the condition and quality of the materials 
used and the delivery, storage, installation and testing of the system are in accordance with the plans, specifications, 
and manufacturer's printed instructions and is satisfactory in all respects.  When any work connected with the 
installation is unsatisfactory, the report shall state what corrective action has been taken or shall contain 
the UHDS manufacturer's recommendations for corrective action.  The report shall identify any conditions that 
could result in an unsatisfactory installation, including such items as open conduit ends left in the trench 
overnight and improper manhole entries.  The daily reports are to be reviewed, signed and sealed, on a weekly 
basis, by the registered engineer responsible for the system design.   Signed and sealed copies of the daily 
reports shall be submitted with the payment request.  Requests for payment shall be denied if the weekly review 
is not accomplished.</TXT><BRK/>
<BRK/>
<TXT>Upon completion of the work and before final acceptance, deliver to the Contracting Officer a  notarized Certificate 
of Compliance signed by a principal officer of both the manufacturing and the contracting firm, stating that 
the installation is satisfactory and in accordance with plans, specifications, and manufacturer's instructions.</TXT><BRK/>
<BRK/>
<TXT>The UHDS manufacturer will retain a copy of all daily reports and the Certificate of Compliance for 5 years after 
final acceptance of the system by the government.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.5   Protection</TTL><BRK/>
<BRK/>
<TXT>Protect casing coating from damage during unloading, storage, rigging and installation.  Protect casing and carrier 
pipe ends from water intrusion during unloading, storage, rigging and installation.  Protect piping and all accessories 
from damage due to exposure to UV light.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.6   Defective Material</TTL><BRK/>
<BRK/>
<TXT>The UHDS Manufacturer's Representative shall take prompt action to remove from the site all damaged or defective 
material, subject to rejection in accordance with the quality assurance provisions included in the manufacturer's 
submittals and printed instructions, and shall order prompt replacement of such material.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.5.7   Cathodic Protection</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Designer must indicate on the contract drawings that dielectric separation 
is shown where UHDS enter buildings or at or above transition from underground 
to aboveground piping.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Provide cathodic protection for all steel casing systems and all buried exposed metal.  Assume that 25 percent 
of the exterior of the UHDS is exposed metal.  Cathodic protection systems shall have a minimum design life of 
25 years and shall conform to [Section <SRF>26 42 13.00 20</SRF> CATHODIC PROTECTION BY GALVANIC ANODE][Section 
<SRF>26 42 19.00 20</SRF> CATHODIC PROTECTION BY IMPRESSED CURRENT].  Provide dielectric pipe flanges and unions and isolation 
devices at all points necessary.  Provide test stations at grade on each section of the piping system.  Isolation 
flanges and unions shall be rated for the service temperature and pressure.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.6   TESTS</TTL><BRK/>
<BRK/>
<TXT>Demonstrate leak-tightness of all piping systems by performing pressure tests (hydrostatic, pneumatic) and operational 
tests.  Pressure test heat distribution system in conformance with requirements stated in this specification 
and in printed instructions for the system supplied.  Tests shall include carrier piping and casing.  The carrier 
pipe shall be hydrostatically tested.  Casings of DDT systems shall be pneumatically tested.  Casing and end 
seals of WSL system will be tested for intrusion of water into the casing and insulation.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.6.1   Holiday Testing of Direct-Buried System Steel Casings</TTL><BRK/>
<BRK/>
<TXT>Test entire exterior surface of the casing including the bottom exterior surface of the casing for faults in 
coating after installation in trench prior to backfilling.  Use test method and voltage recommended by coating 
manufacturer.  Repair any holidays found and retest.  System shall not be backfilled until all holidays are eliminated.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.2   Pneumatic, Hydrostatic and Operational Tests</TTL><BRK/>
<BRK/>
<TXT>Before conducting heat distribution system tests, flush lines with high pressure water until discharge shows 
no foreign matter and are deemed clean to the satisfaction of the Contracting Officer.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.6.2.1   Pneumatic Test</TTL><BRK/>
<BRK/>
<TXT>The casing of DDT systems shall be pneumatically tested after welding and before field coating using air as the 
test medium.  The test pressure shall be<MET> 103 kPa </MET><ENG> 15 psig</ENG>.  Persons not working on the test operations shall 
be kept out of the testing area while testing is proceeding.  The test shall be made on the system as a whole 
or on sections that can be isolated.  Joints in sections shall be tested prior to backfilling when trenches must 
be backfilled before the completion of other pipeline sections.  The test shall continue for 24 hours from the 
time of the initial readings to the final readings of pressure and temperature.  The initial test readings of 
the instrument shall not be made for at least 1 hour after the casing has been subjected to the full test pressure, 
and neither the initial nor final readings shall be made at times of rapid changes in atmospheric conditions.  
There shall be no indication of reduction of pressure during the test after corrections have been made for changes 
in atmospheric conditions in conformity with the relationship T(1)P(2)=T(2)P(1), in which T and P denote absolute 
temperature and pressure, respectively, and the numbers denote initial (1) and final (2) readings.  Pressure 
shall be measured with a mercury manometer, inclined manometer(slope gauge), or an equivalent device so calibrated 
as to be read in increments of not greater than<MET> one kPa </MET><ENG> 0.1 psi</ENG>.  [Pressure shall be measured with a pressure 
gauge conforming to <RID>ASME B40.100</RID>.  A throttling type needle valve or a pulsation dampener and shutoff valve may 
be included.  The diameter of the face shall be at least<MET> 114 mm </MET><ENG> 4.5 inches</ENG> with a measurable range of<MET> 0 to 103 
kPa </MET><ENG> 0 to 15 psig</ENG> and graduations of not greater than<ENG> 0.1 psig </ENG><MET> 0.5 kPa</MET>.]  During the test, the entire system 
shall be completely isolated from all compressors and other sources of air pressure.  Each joint shall be tested 
while under test pressure by means of soap and water or an equivalent nonflammable solution prior to  backfilling 
or concealing any work.  The testing instruments shall be approved by the Contracting Officer.  All labor, materials 
and equipment for conducting the tests shall be furnished by the Contractor and shall be subject to inspection 
at all times during the tests.  The Contractor shall maintain proper safety precautions for air pressure testing 
at all times during the tests.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.2.2   Hydrostatic Test</TTL><BRK/>
<BRK/>
<TXT>Carrier piping shall be tested hydrostatically before insulation is applied at field joints and shall be proved 
tight at a pressure 1.5 times the heat distribution supply pressure of<MET> [_____] kPa </MET><ENG> [_____] psig</ENG> for 2 hours.  
There shall be no indication of reduction of pressure during the test.  Pressure shall be measured with a device  
calibrated as to be read in increments of not greater than<MET> one kPa </MET><ENG> 5.0 psi</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.6.2.3   Operational Test</TTL><BRK/>
<BRK/>
<TXT>Prior to acceptance of the installation, Contractor shall subject system to operating tests simulating actual 
operating conditions to demonstrate satisfactory functional and operating efficiency.  These operating tests 
shall cover a period of not less than six hours for each portion of system tested.  Conduct tests at times as 
the Contracting Officer may direct.</TXT> <BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  The contractor shall provide calibrated instruments, equipment, facilities and labor, at 
no additional cost to the Government.</ITM> <BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  When failures occur, repair problems then repeat test.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.6.3   Deficiencies</TTL><BRK/>
<BRK/>
<TXT>Deficiencies discovered shall be corrected at the Contractor's expense, to the satisfaction of the Contracting 
Officer.  Major deficiencies or failure to correct deficiencies, to the satisfaction of the Contracting Officer, 
may be considered cause for rejecting the entire installation.</TXT><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include Section UFGS 02559 VALVE MANHOLES AND PIPING AND EQUIPMENT IN 
VALVE MANHOLES as part of the contract specifications for this job when there 
are manhole or steam pits.  Include sealing of pipe penetrations through manhole 
walls in the design of the manhole.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/></SPT>
</SPT><SPT><TTL>3.7   VALVE MANHOLES</TTL><BRK/>
<BRK/>
<TXT>Valve manholes, piping, and equipment in valve manholes shall be in accordance with the contract drawings and 
Section <SRF>33 60 01</SRF> VALVE MANHOLES PIPING AND EQUIPMENT IN VALVE MANHOLES.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8   BURIED UTILITY WARNING AND IDENTIFICATION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.8.1   Plastic Marking Tape</TTL><BRK/>
<BRK/>
<TXT>Polyethylene plastic tape manufactured specifically for warning and identifying buried utility lines shall be 
supplied and installed.  Tape shall be buried above the pipe during the trench backfilling operation and shall 
be buried approximately<MET> 300 mm</MET><ENG> 12 inches</ENG> below grade.  Tape shall be [<MET>0.1 mm</MET><ENG>0.004 inch</ENG> thick polyethylene] [polyethylene 
with a metallic core].  Tape shall be acid and alkali-resistant and shall have a minimum strength of<MET> 12 MPa</MET><ENG> 1750 
psi</ENG> lengthwise and<MET> 10.3 MPa</MET><ENG> 1500 psi</ENG> crosswise with an elongation factor of 350 percent.  [The tape shall be 
manufactured with integral wires, foil backing or other means to enable detection by a metal detector when the 
tape is buried up to<MET> one meter</MET><ENG> 3 feet</ENG> deep.  The metallic core of the tape shall be encased in a protective jacket 
or provided with other means to protect it from corrosion.]  The tape shall be of a type specifically manufactured 
for marking and locating metallic underground utilities.  Tape shall be<MET> 150 mm</MET><ENG> 6 inches</ENG> wide and printed with 
a caution and identification of the piping system over the entire tape length.  Tape shall be yellow with bold 
black letters.  Tape color and lettering shall be unaffected by moisture and other substances contained in the 
backfill material.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.8.2   Markers for Underground Piping</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Indicate the location of the markers on the contract drawings for projects 
that require markers.  Delete the paragraph if not needed in the project</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Markers for underground piping shall be located along the distribution and service lines. Markers shall be placed 
as indicated approximately<MET> 600 mm</MET><ENG> 2 feet</ENG> to the right of the distribution system when facing in direction of 
flow in the supply line.  The marker shall be concrete<MET> 150 mm</MET><ENG> 6 inch</ENG> square or round section<MET> [600] [900] mm</MET><ENG> [2] 
[3] feet</ENG> long.  The top edge of the marker shall have a minimum<MET> 13 mm</MET><ENG> 1/2 inch</ENG> chamfer all around.  The letters 
[STEAM] [HTHW] [CONDENSATE] shall be impressed or cast on the top, and on one side of the markers to indicate 
the type of system that is being identified.  Each letter shall be formed with a V-shaped groove and shall have 
a width of stroke at least<MET> 6 mm</MET><ENG> 1/4 inch</ENG> at the top and depth of<MET> 6 mm</MET><ENG> 1/4 inch</ENG>.  The top of the marker shall 
protrude not more than<MET> [25] [50] [75] [100] mm</MET><ENG> [1] [2] [3] [4] inch(es)</ENG> above finished grade.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.9   THERMAL PERFORMANCE TESTING</TTL><BRK/>
<BRK/>
<TXT>The purpose of this section is to provide a basis for assuring the thermal performance of a heat distribution 
system procured under this specification.  The equipment and procedures specified herein shall assure acceptable 
thermal performance upon installation.  All materials and procedures described for this test shall be included 
as deliverables of the construction contract for the system unless otherwise noted.  The methods used for the 
prescribed thermal performance measurements have been verified by several successful field studies.  This work 
has clearly demonstrated that methods based on temperature measurements at the soil/casing interface are accurate, 
reliable, and repeatable.</TXT><BRK/>
<BRK/>
<SPT><TTL>3.9.1   Equipment</TTL><BRK/>
<BRK/>
<SPT><TTL>3.9.1.1   Casing Temperature Measurement</TTL><BRK/>
<BRK/>
<TXT>Before backfilling, temperature sensors shall be installed by adhesion with epoxy (epoxy used to adhere to exterior 
of casing shall be suitable to<MET> 260 degrees C</MET><ENG> 500 degrees F</ENG>) to the exterior of every other field closure after 
welding, once the field coating has been applied and cured.  A sensor shall be adhered with epoxy to the coated 
casing at the midpoint of every other pipe section between field joints, but no closer than<MET> 1.5 m</MET><ENG> 5 feet</ENG> to any 
guide on the interior of the casing.  After the sensors have been adhered to the casing, two complete wraps of 
duct tape shall be used to secure and protect the sensor.  In all cases the radial position of the sensor shall 
be at 45 degrees from the top of the conduit at either the 1:30 or 10:30 position.  The position chosen shall 
be the position facing away from the adjacent heat distribution system pipe, if present.  All sensors shall be 
type T thermocouples in accordance with <RID>ISA MC96.1</RID>, copper constantan 20 gauge thermocouples, made from special 
limits grade thermocouple wire (accuracy plus or minus<MET> 0.40 degrees C</MET><ENG> 0.75 degrees F</ENG>), with each conductor insulated 
and an overall jacket on all conductors.  Insulation on the thermocouple wires shall be suitable for service 
at temperature of carrier pipe.  No splicing or other connections will be allowed in the thermocouple wire between 
sensor location and termination point.  Each sensor shall be shown with a special symbol on the detailed design 
layout drawings and shall be identified by a number and/or letter code, starting from the upstream manhole.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.1.2   Carrier Pipe Temperature Measurement</TTL><BRK/>
<BRK/>
<TXT>Carrier pipe temperature shall be measured within the manhole where the terminal equipment will be located.  
Carrier pipe temperature shall be measured by a sensor adhered with epoxy, suitable to<MET> 260 degrees C</MET><ENG> 500 degrees 
F</ENG> directly to the exterior of the carrier pipe.  Sensors shall be type T thermocouples in accordance with <RID>ISA MC96.1</RID>
, copper constantan 20 gauge thermocouples, made from special limits grade thermocouple wire (accuracy plus or 
minus<MET> 0.40 degrees C</MET><ENG> 0.75 degrees F</ENG>), with each conductor insulated and an overall jacket on all conductors.  
Insulation on the thermocouple wires shall be suitable for service at temperature of carrier pipe.  No splicing 
or other connections will be allowed in the thermocouple wire between sensor location and termination point.  
The location of this sensor shall be at either the 1:30 or 10:30 position.  At the location of the sensor the 
carrier pipe shall be insulated with an approved calcium silicate insulation of<MET> 125 mm</MET><ENG> 5 inches</ENG> minimum thickness.  
This insulation shall extend at least<MET> 150 mm</MET><ENG> 6 inches</ENG> on each side of the actual sensor location and shall be 
clad with an aluminum jacket.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.1.3   Terminals</TTL><BRK/>
<BRK/>
<TXT>The wires from each casing or carrier pipe temperature sensor shall be extended into the nearest manhole and 
terminated in a <RID>NEMA ICS 4</RID> type 4 waterproof enclosure, of suitable size, mounted near the top of the manhole 
at a location near the manhole entrance so as to be accessible without entrance into the manhole, where possible.  
The termination of the sensor wires shall be with a connector type OMEGA Miniature Jack Panel (MJP-*-*-T) or 
exact equal.  The thermocouple jack panel shall be mounted to the back plate of the <RID>NEMA ICS 4</RID> type 4 enclosure.  
The temperature sensors shall be labeled at their termination within the <RID>NEMA ICS 4</RID> type 4 enclosure; a drawing 
showing the location of each temperature sensor shall be laminated and attached to the inside of the <RID>NEMA ICS 4</RID>
 type 4 enclosure.  The manufacturer's operating casing temperature factors for each temperature sensor location 
shall be laminated to a card attached to the inside of the <RID>NEMA ICS 4</RID> type 4 enclosure.  All temperature sensors 
shall be verified as operational by an independent laboratory, hired by the Contractor, after backfilling is 
complete but before the system is accepted.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.9.2   Initial Thermal Performance Test</TTL><BRK/>
<BRK/>
<TXT>After the system construction is complete, including all backfilling, and the system has reached operating condition 
for not less than 48 hours nor more than 168 hours, all of the temperature sensors shall be read by an independent 
laboratory with experience and equipment appropriate for the sensors used.  For each temperature sensor location 
the initial casing temperature shall be recorded.  All of the temperature values of the temperature sensors shall 
be tabulated and submitted in accordance with requirements herein.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.3   Warranty Thermal Performance Test</TTL><BRK/>
<BRK/>
<TXT>After not less than 9 months nor more than 11 months of continuous operation, all of the temperature values of 
the temperature sensors shall be read by an independent laboratory with experience and equipment appropriate 
for the sensors used.  The temperature shall be tabulated and submitted in accordance with requirements herein.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.9.4   System Failure</TTL><BRK/>
<BRK/>
<TXT>System shall be deemed a failure when the conduit surface temperature exceeds values in Table 3, that portion 
shall be repaired and temperatures again measured and recorded.</TXT><BRK/>
<MET><TBL><THD><BRK/>
<HL4>TABLE 3</HL4><BRK/>
<BRK/>
                    Carrier pipe         Acceptable Casing<BRK/>
                   Temperature TP         Temperature  TC<BRK/>
                     (degrees C)           (degrees C)<BRK/>
                  ----------------------------------------<BRK/></THD>
<BRK/>
                        121                   43<BRK/>
                        135                   47<BRK/>
                        149                   50<BRK/>
                        163                   54<BRK/>
                        177                   58<BRK/>
                        204                   65<BRK/>
                        218                   68<BRK/>
                        232                   72<BRK/></TBL>
</MET><ENG><TBL><THD><BRK/>
<HL4>TABLE 3</HL4><BRK/>
<BRK/>
                   Carrier Pipe    Acceptable Casing<BRK/>
                  Temperature TP    Temperature  TC<BRK/>
                   (degrees F)       (degrees F)<BRK/>
                  ----------------------------------<BRK/></THD>
<BRK/>
                      250               110<BRK/>
                      275               116<BRK/>
                      300               123<BRK/>
                      325               129<BRK/>
                      350               136<BRK/>
                      400               149<BRK/>
                      425               155<BRK/>
                      450               162<BRK/></TBL>
</ENG><BRK/>
<TXT>The following equations were used to calculate the above values:</TXT><BRK/>
<BRK/>
<TXT><ENG>TC, &lt;/=[(0.261) X (TP) + 44.3]</ENG><MET>TC, &lt;/=[(0.261) X (TP) + 11.5]</MET></TXT><BRK/>
<BRK/></SPT>
</SPT></PRT>    <END/><BRK/>
 </SEC>