<?xml version="1.0" encoding="windows-1252"?><SEC xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="http://si.ksc.nasa.gov/sidownloads/xml/specsintactSEC.xsd"><MTA NAME="SUBFORMAT" CONTENT="NEW"/><HDR><AST/><BRK/>
USACE / NAVFAC / AFCESA / NASA      UFGS-35 59 13.13 (April 2006)<BRK/>
                                    ------------------------------<BRK/>
Preparing Activity: <PRA>NAVFAC</PRA>          Replacing without change<BRK/>
                                    UFGS-02395 (May 2003)<BRK/>
<BRK/>
<HL4>UNIFIED FACILITIES GUIDE SPECIFICATIONS</HL4><BRK/>
<BRK/>
<HL4>References are in agreement with UMRL dated January 2009</HL4><BRK/>
<AST/><BRK/></HDR>
<BRK/>
<SCN>SECTION 35 59 13.13</SCN><BRK/>
<BRK/>
<STL>PRESTRESSED CONCRETE FENDER PILING</STL><BRK/>
<DTE>04/06</DTE><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This guide specification covers the requirements for <SCP>prestressed concrete 
fender piling</SCP>.<BRK/>
<BRK/>
Edit this guide specification for project specific requirements by adding, deleting, 
or revising text.  For bracketed items, choose applicable items(s) or insert 
appropriate information.<BRK/>
<BRK/>
Remove information and requirements not required in respective project, whether 
or not brackets are present.<BRK/>
<BRK/>
Comments and suggestions on this guide specification are welcome and should 
be directed to the technical proponent of the specification.  A listing of <URL HREF="http://65.204.17.188/report/ufgs.html">technical 
proponents</URL>, including their organization designation and telephone number, is 
on the Internet.<BRK/>
<BRK/>
Recommended changes to a UFGS should be submitted as a  <URL HREF="http://65.204.17.188/projnet/cms/public.html">Criteria Change Request 
(CCR)</URL>.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  The extent and location of the work to be accomplished should be indicated 
on the project drawings or included in the project specification.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Refer to NFESC TM 53-89-03, "Prestressed Concrete Fender Piling User 
Data Package" for details of these fender piles.  The following information 
shall be shown on the drawings:</NPR><BRK/>
<BRK/>
<NPR>1.  Locations and design loads of piles.</NPR><BRK/>
<BRK/>
<NPR>2.  Size, shape, and length of piles.</NPR><BRK/>
<BRK/>
<NPR>3.  Locations, sizes, and number of longitudinal ducts for prestressing steel.  
Unit stresses for prestressing strands or wire.</NPR><BRK/>
<BRK/>
<NPR>4.  Details of reinforcement and tendons.</NPR><BRK/>
<BRK/>
<NPR>5.  Soil data, where required.</NPR><BRK/>
<BRK/>
<NPR>6.  Embedment depth.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<PRT><TTL>PART 1   GENERAL</TTL><BRK/>
<BRK/>
<SPT><TTL>1.1   REFERENCES</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  This paragraph is used to list the publications cited in the text of 
the guide specification. The publications are referred to in the text by basic 
designation only and listed in this paragraph by organization, designation, 
date, and title.<BRK/>
 <BRK/>
Use the Reference Wizard's Check Reference feature when you add a RID outside 
of the Section's Reference Article to automatically place the reference in the 
Reference Article.  Also use the Reference Wizard's Check Reference feature 
to update the issue dates.<BRK/>
 <BRK/>
References not used in the text will automatically be deleted from this section 
of the project specification when you choose to reconcile references in the 
publish print process.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>The publications listed below form a part of this specification to the extent referenced.  The publications are 
referred to within the text by the basic designation only.</TXT><BRK/>
<BRK/>
<REF><ORG>ACI INTERNATIONAL (ACI)</ORG><BRK/><BRK/><RID>ACI 211.1</RID><RTL>(1991; R 2002) Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete</RTL><BRK/><BRK/><RID>ACI 212.3R</RID><RTL>(2004) Chemical Admixtures for Concrete</RTL><BRK/><BRK/><RID>ACI 214R</RID><RTL>(2002) Recommended Practice for Evaluation of Strength Test Results of Concrete</RTL><BRK/><BRK/><RID>ACI 318M</RID><RTL>(2008) Metric Building Code Requirements for Structural Concrete and Commentary</RTL><BRK/><BRK/><RID>ACI SP-66</RID><RTL>(2004) ACI Detailing Manual</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)</ORG><BRK/><BRK/><RID>AASHTO M 182</RID><RTL>(2005) Standard Specification for Burlap Cloth Made from Jute or Kenaf and Cotton Mats</RTL><BRK/><BRK/></REF><REF><ORG>AMERICAN WELDING SOCIETY (AWS)</ORG><BRK/><BRK/><RID>AWS D1.4/D1.4M</RID><RTL>(2005; Errata 2005) Structural Welding Code - Reinforcing Steel</RTL><BRK/><BRK/></REF><REF><ORG>ASTM INTERNATIONAL (ASTM)</ORG><BRK/><BRK/><RID>ASTM A 153/A 153M</RID><RTL>(2005) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware</RTL><BRK/><BRK/><RID>ASTM A 307</RID><RTL>(2007b) Standard Specification for Carbon Steel Bolts and Studs, 60 000 PSI Tensile Strength</RTL><BRK/><BRK/><RID>ASTM A 416/A 416M</RID><RTL>(2006) Standard Specification for Steel Strand, Uncoated Seven-Wire for Prestressed Concrete</RTL><BRK/><BRK/><RID>ASTM A 501</RID><RTL>(2007) Standard Specification for Hot-Formed Welded and Seamless Carbon Steel Structural Tubing</RTL><BRK/><BRK/><RID>ASTM A 53/A 53M</RID><RTL>(2007) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless</RTL><BRK/><BRK/><RID>ASTM A 563</RID><RTL>(2007a) Standard Specification for Carbon and Alloy Steel Nuts</RTL><BRK/><BRK/><RID>ASTM A 563M</RID><RTL>(2007) Standard Specification for Carbon and Alloy Steel Nuts (Metric)</RTL><BRK/><BRK/><RID>ASTM A 615/A 615M</RID><RTL>(2008b) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement</RTL><BRK/><BRK/><RID>ASTM A 706/A 706M</RID><RTL>(2008a) Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement</RTL><BRK/><BRK/><RID>ASTM A 82/A 82M</RID><RTL>(2007) Standard Specification for Steel Wire, Plain, for Concrete Reinforcement</RTL><BRK/><BRK/><RID>ASTM A 966/A 966M</RID><RTL>(2008) Standard Test Method for Magnetic Particle Examination of Steel Forgings Using Alternating Current</RTL><BRK/><BRK/><RID>ASTM C 1240</RID><RTL>(2005) Standard Specification for Silica Fume Used in Cementitious Mixtures</RTL><BRK/><BRK/><RID>ASTM C 136</RID><RTL>(2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates</RTL><BRK/><BRK/><RID>ASTM C 143/C 143M</RID><RTL>(2008) Standard Test Method for Slump of Hydraulic-Cement Concrete</RTL><BRK/><BRK/><RID>ASTM C 150</RID><RTL>(2007) Standard Specification for Portland Cement</RTL><BRK/><BRK/><RID>ASTM C 171</RID><RTL>(2007) Standard Specification for Sheet Materials for Curing Concrete</RTL><BRK/><BRK/><RID>ASTM C 172</RID><RTL>(2008) Standard Practice for Sampling Freshly Mixed Concrete</RTL><BRK/><BRK/><RID>ASTM C 309</RID><RTL>(2007) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete</RTL><BRK/><BRK/><RID>ASTM C 31/C 31M</RID><RTL>(2008a) Standard Practice for Making and Curing Concrete Test Specimens in the Field</RTL><BRK/><BRK/><RID>ASTM C 311</RID><RTL>(2007) Sampling and Testing Fly Ash or Natural Pozzolans for Use as a Mineral Admixture in Portland-Cement Concrete</RTL><BRK/><BRK/><RID>ASTM C 33</RID><RTL>(2007) Standard Specification for Concrete Aggregates</RTL><BRK/><BRK/><RID>ASTM C 39/C 39M</RID><RTL>(2005e1e2) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens</RTL><BRK/><BRK/><RID>ASTM C 494/C 494M</RID><RTL>(2008a) Standard Specification for Chemical Admixtures for Concrete</RTL><BRK/><BRK/><RID>ASTM C 595</RID><RTL>(2008) Standard Specification for Blended Hydraulic Cements</RTL><BRK/><BRK/><RID>ASTM C 618</RID><RTL>(2008a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete</RTL><BRK/><BRK/><RID>ASTM C 989</RID><RTL>(2006) Standard Specification for Ground Granulated Blast-Furnace Slag for Use in Concrete and Mortars</RTL><BRK/><BRK/><RID>ASTM D 1894</RID><RTL>(2008) Static and Kinetic Coefficients of Friction of Plastic Film and Sheeting</RTL><BRK/><BRK/><RID>ASTM D 2240</RID><RTL>(2005) Standard Test Method for Rubber Property - Durometer Hardness</RTL><BRK/><BRK/><RID>ASTM D 256</RID><RTL>(2006e1) Determining the Izod Pendulum Impact Resistance of Plastics</RTL><BRK/><BRK/><RID>ASTM D 4020</RID><RTL>(2005) Ultra-High-Molecular-Weight Polyethylene Molding and Extrusion Materials</RTL><BRK/><BRK/><RID>ASTM D 570</RID><RTL>(1998; R 2005) Standard Test Method for Water Absorption of Plastics</RTL><BRK/><BRK/><RID>ASTM D 638</RID><RTL>(2008) Standard Test Method for Tensile Properties of Plastics</RTL><BRK/><BRK/><RID>ASTM D 792</RID><RTL>(2008) Density and Specific Gravity (Relative Density) of Plastics by Displacement</RTL><BRK/><BRK/><RID>ASTM F 844</RID><RTL>(2007a) Washers, Steel, Plain (Flat), Unhardened for General Use</RTL><BRK/><BRK/></REF><REF><ORG>PRECAST/PRESTRESSED CONCRETE INSTITUTE (PCI)</ORG><BRK/><BRK/><RID>PCI MNL-116</RID><RTL>(1999) Manual for Quality Control for Plants and Production of Structural Precast Concrete Products</RTL><BRK/><BRK/></REF></SPT><SPT><TTL>1.2   SUBMITTALS</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL 
PROCEDURES and edit the following list to reflect only the submittals required 
for the project.  Submittals should be kept to the minimum required for adequate 
quality control.<BRK/>
<BRK/>
A “G” following a submittal item indicates that the submittal requires Government 
approval.  Some submittals are already marked with a “G”.  Only delete an existing 
“G” if the submittal item is not complex and can be reviewed through the Contractor’s 
Quality Control system.  Only add a “G” if the submittal is sufficiently important 
or complex in context of the project.<BRK/>
<BRK/>
For submittals requiring Government approval on Army projects, a code of up 
to three characters within the submittal tags may be used following the "G" 
designation to indicate the approving authority.  Codes for Army projects using 
the Resident Management System (RMS) are:  "AE" for Architect-Engineer; "DO" 
for District Office (Engineering Division or other organization in the District 
Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project 
Office.  Codes following the "G" typically are not used for Navy,  Air Force, 
and NASA projects.<BRK/>
<BRK/>
Choose the first bracketed item for Navy, Air Force and NASA projects, or choose 
the second bracketed item for Army projects.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Government approval is required for submittals with a "G" designation; submittals not having a "G" designation 
are [for Contractor Quality Control approval.][for information only.  When used, a designation following the 
"G" designation identifies the office that will review the submittal for the Government.]  The following shall 
be submitted in accordance with Section <SRF>01 33 00</SRF> SUBMITTAL PROCEDURES:</TXT><BRK/>
<BRK/>
<LST><SUB>SD-02 Shop Drawings</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Piles</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Driving helmets, capblocks, and pile cushions</SUB></ITM><BRK/>
<BRK/>
<LST><SUB>SD-05 Design Data</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Concrete mix design</SUB></ITM><BRK/>
<BRK/>
<ITM>  Submit a concrete mix design before concrete is placed, for each type of concrete used for 
the piles.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-06 Test Reports</SUB></LST><BRK/>
<BRK/>
<ITM><SUB>Aggregates</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Fly ash</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Silica fume</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Concrete</SUB></ITM><BRK/>
<BRK/>
<ITM>  Submit concrete cylinder compressive strength test results.</ITM><BRK/>
<BRK/>
<LST><SUB>SD-07 Certificates</SUB></LST><BRK/>
<BRK/>
<ITM>Precasting manufacturer's <SUB>quality control procedures</SUB></ITM><BRK/>
<BRK/>
<ITM>Suitability of pile driving <SUB>equipment</SUB></ITM><BRK/>
<BRK/>
[<ITM><SUB>Curing of piles</SUB></ITM>]<BRK/>
<BRK/>
[<ITM><SUB>Silica fume manufacturer's representative</SUB></ITM>]<BRK/>
<BRK/>
<ITM><SUB>Prestressing steel</SUB></ITM><BRK/>
<BRK/>
<ITM>Portland <SUB>cement</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Concrete mix design</SUB></ITM><BRK/>
<BRK/>
<ITM><SUB>Reinforcing steel</SUB></ITM><BRK/>
<BRK/>
[<ITM><SUB>Rubbing surface</SUB></ITM>]<BRK/>
<BRK/>
<ITM><SUB>Bolts, nuts, and washers</SUB></ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3   REQUIREMENTS</TTL><BRK/>
<BRK/>
<SPT><TTL>1.3.1   Piling Lengths and Quantity</TTL><BRK/>
<BRK/>
<TXT>Provide prestressed pretensioned concrete piles.  Base bids upon the number, size, and length of piles as indicated.  
Adjustments in the contract price will not be made for cutting off piles or for broken, damaged, or rejected 
piles.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.2   <SUB>Piles</SUB></TTL><BRK/>
<BRK/>
<TXT>Prepare in accordance with <RID>ACI SP-66</RID>.  Indicate placement of reinforcement including tendons.  Indicate location 
of special embedded or attached lifting devices, employment of pick-up points, support points other than pick-up 
points, and any other methods of pick-up.  [Provide certification of a professional engineer registered in any 
jurisdiction, that layout and details of reinforcement and tendons conform with that shown on the structural 
design drawings.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.3.3   Driving Helmets, Capblocks, and Pile Cushions</TTL><BRK/>
<BRK/>
<TXT>Show details of driving helmets, capblocks, and pile cushions.  Submit 2 weeks prior to [test] pile installation.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>1.4   QUALITY ASSURANCE</TTL><BRK/>
<BRK/>
<SPT><TTL>1.4.1   Quality Control Procedures</TTL><BRK/>
<BRK/>
<TXT>Submit [_____] copies of precasting manufacturer's quality control procedures established in accordance with <RID>
PCI MNL-116</RID>.</TXT><BRK/>
<BRK/>
<SPT>[<TTL>1.4.1.1   Curing of Piles</TTL><BRK/>
<BRK/>
<TXT>Submit proposed materials and methods.</TXT><BRK/>
<BRK/>
]</SPT></SPT><SPT><TTL>1.4.2   <SUB>Silica Fume Manufacturer's Representative</SUB></TTL><BRK/>
<BRK/>
<TXT>Provide statement that the manufacturer's representative will be present at plant to ensure proper mix, including 
high range water reducer (HRWR), and batching methods.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.3   <SUB>Aggregates</SUB></TTL><BRK/>
<BRK/>
<TXT>Prior to pile fabrication, submit certified test reports for the following tests specified in <RID>ASTM C 33</RID>:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Grading</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Amount of material finer than <MET>75 micrometers</MET> <ENG>No. 200 sieve</ENG></ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Organic impurities</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Soundness</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Clay lumps and friable particles</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Coal and lignite</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">g.  Weight of slag</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">h.  Abrasion of coarse aggregate</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">i.  Fineness modulus</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">j.  Reactive aggregates</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">k.  Freezing and thawing</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.4   <SUB>Fly Ash</SUB></TTL><BRK/>
<BRK/>
<TXT>Furnish fly ash test results performed within 6 months of submittal date.  Sampling and testing shall be in accordance 
with <RID>ASTM C 311</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.5   Silica Fume</TTL><BRK/>
<BRK/>
<TXT>Furnish silica fume test results performed within 6 months of submittal date.  Sampling and testing shall be 
in accordance with <RID>ASTM C 311</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.6   Portland Cement</TTL><BRK/>
<BRK/>
<TXT>Certification identifying cement; brand name, type, mill location, quantity to be used, size of lot represented 
by quality control sample, lot number, and destination of shipment.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>1.4.7   Concrete Mix Design</TTL><BRK/>
<BRK/>
<TXT>Certify, using a Government-approved independent commercial testing laboratory, that proportioning of mix is 
in accordance with <RID>ACI 211.1</RID> or <RID>ACI 318M</RID> for specified strength and is based on aggregate data which has been 
determined by laboratory tests during last 12 months.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 2   PRODUCTS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1   MATERIALS</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.1   <SUB>Cement</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Insert type of cement required.  Except where moderate or high sulfate 
resistance is required, permit option for Type I, II, III, IP, or IS.  For moderate 
sulfate resistance, specify Type II, III, IP(MS), or IS(MS) with a maximum tricalcium 
aluminate content of 8 percent.  For high sulfate resistance, specify Type III 
or V, with a maximum tricalcium aluminate content of 5 percent.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASTM C 150</RID>, [Type I, II, or III] [_____], or <RID>ASTM C 595</RID>, Type [IP(MS) or IS(MS)] [_____] blended cement except 
as modified herein.  The blended cement shall consist of a mixture of <RID>ASTM C 150</RID> cement and one of the following 
materials:  <RID>ASTM C 618</RID> pozzolan or fly ash, or <RID>ASTM C 989</RID> ground iron blast furnace slag.  The pozzolan/fly ash 
content shall not exceed 25 percent by weight of the total cementitious material.  The ground iron blast-furnace 
slag shall not exceed 50 percent by weight of total cementitious material.  [Cement shall have a maximum tricalcium 
aluminate content of [5] [8] percent.]</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.2   Water</TTL><BRK/>
<BRK/>
<TXT>Use potable water.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.3   Aggregates</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For piles in areas where reactive aggregates are found, provide for additional 
tests and certification to ensure that reactive aggregates will not be used.  
While not wholly conclusive, petrographic examination (ASTM C 295), chemical 
test (ASTM C 28/c 28M9), provide valuable indicators.  The mortar bar method 
(ASTM C 227), while more reliable, requires at least 6 months and preferably 
one year to yield results.  In areas where reactive aggregates cannot be avoided, 
specify use of low alkali cement.  Service records of concrete made with these 
materials along with tests should be used in evaluating these materials.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Include modification to ASTM C 33 when reactive aggregates could be encountered.  
More modifications may be required.  Additional tests and certifications may 
be required in the submittal paragraphs.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASTM C 33</RID>[, except as modified herein.  Provide aggregate free from any substance which may be deleteriously 
reactive with alkalies in cement in an amount sufficient to cause excessive expansion of concrete].  Do not mix, 
store in same stockpile, or use fine aggregates from different sources of supply in same concrete mix or same 
structure without approval.  Maximum coarse aggregate size shall be<MET> 19 mm</MET><ENG> 3/4 inch</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.4   Admixtures</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  For guidance in use of either water-reducing admixtures, set retarding 
admixtures, or combination of admixtures, refer to ACI 543R, "Recommendations 
for Design, Manufacture, and Installation of Concrete Piles."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>If required, <RID>ASTM C 494/C 494M</RID>, [Type A] [Type B] and <RID>ASTM C 618</RID>, Type [N] [F] [C].  Do not use admixtures containing 
chlorides.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.5   Mineral Admixtures</TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.5.1   Fly Ash and Pozzolan</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Fly ash, pozzolan, and slag cement may produce uneven discoloration of 
the concrete during the early stages of construction, depending upon the type 
of curing provided.  Fly ash or pozzolan meeting the specified test results, 
which are more stringent than ASTM C 618, should provide acceptable end results.  
Type C fly ash can be used as a replacement for up to 40 percent of the cement.   
Types F and C fly ash increase durability of concrete.  Type F fly ash and slag 
are replacements for some sand and aggregates also adding to durability.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASTM C 618</RID>, Type N, F, or C, except that the maximum allowable loss on ignition shall be 6 percent for Types 
N and F.  Add with cement.  Fly ash content shall not exceed 25 percent by weight of the total cementitious material.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.5.2   <SUB>Silica Fume</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use silica fume concrete for marine structures where low permeability 
and enhanced durability are necessary.  The silica fume and HRWR additive should 
be from the same manufacturer.   Since this is fairly new technology, the Contractor 
and batch plant may need help from the manufacturer.   Select weight percentage 
based on performance required.</NPR><BRK/>
<AST/><BRK/></NTE>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Use for high durability and low permeability.   The initial cost of the 
concrete will increase, and supervision at the batch plant, finishing, and curing 
is necessary.  A HRWR must be used with silica fume, the slump can be increased<MET>
 50 to 125 mm</MET><ENG> 2 to 5 inches</ENG> without reducing strength.   Finishing may be more 
difficult.  Proper curing is essential because there is a tendency for plastic 
shrinkage cracking.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT><RID>ASTM C 1240</RID>, provide silica fume that is a by-product of silicon or ferrosilicon production.  Provide [5] [7] 
[10] percent by weight of the total cementitious material.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.1.6   <SUB>Prestressing Steel</SUB></TTL><BRK/>
<BRK/>
<TXT>Use seven-wire stress-relieved or low-relaxation strand conforming to <RID>ASTM A 416/A 416M</RID> with a guaranteed minimum 
ultimate tensile strength of <MET>1861 MPa</MET> <ENG>270 ksi</ENG>.  Use prestressing steel free of grease, oil, wax, paint, soil, 
dirt, and loose rust.  Do not use prestressing strands or wire having kinks, bends, or other defects.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.7   <SUB>Reinforcing Steel</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If project has been designed for epoxy rebar, add ASTM A 934/A 934M, 
"Epoxy-Coated Prefabricated Steel Reinforcing Bars" in this paragraph and in 
the paragraph entitled "References."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>[<RID>ASTM A 615/A 615M</RID>] [<RID>ASTM A 966/A 966M</RID>] [<RID>ASTM A 966/A 966M</RID>], Grade 60 or <RID>ASTM A 706/A 706M</RID>.  Weld reinforcing 
steel in accordance with <RID>AWS D1.4/D1.4M</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.8   Ties and Spirals</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  If project has been designed for epoxy rebar, add ASTM A 934/A 934M, 
"Epoxy-Coated Prefabricated Steel Reinforcing Bars" in this paragraph and in 
the paragraph entitled "References."</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Steel, <RID>ASTM A 82/A 82M</RID> for spirals and <RID>ASTM A 615/A 615M</RID> for ties.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.9   Pipe Sleeves</TTL><BRK/>
<BRK/>
<TXT>Use <RID>ASTM A 53/A 53M</RID>, Grade B, or <RID>ASTM A 501</RID> galvanized pipe.  Sleeves shall be galvanized in accordance with <RID>
ASTM A 153/A 153M</RID> with chromate wash.  Do not place galvanized pipe in contact with any prestressing or reinforcing 
steel.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.10   <SUB>Bolts, Nuts, and Washers</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.10.1   Bolts</TTL><BRK/>
<BRK/>
<TXT><RID>ASTM A 307</RID>, Grade A.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.10.2   Nuts</TTL><BRK/>
<BRK/>
<TXT><MET><RID>ASTM A 563M</RID></MET><ENG><RID>ASTM A 563</RID></ENG>, Grade A, hex style.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.10.3   Washers</TTL><BRK/>
<BRK/>
<TXT><RID>ASTM F 844</RID>.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.1.11   Ultrahigh Molecular Weight Polyethylene (UHMWPE) <SUB>Rubbing Surface</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>2.1.11.1   General</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Materials including additives shall be traceable by original lot number.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Materials used shall be FDA approved or otherwise harmless to marine life.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Fabricated form shall be virgin resin.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.11.2   Resin</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  <RID>ASTM D 4020</RID>.  Virgin resin shall be homopolymer of ethylene and have an intrinsic viscosity 
(IV) between 22.0 and 28.0 dl/g.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  No reprocessed resin shall be used.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Resin shall be oil and moisture free (0.2 percent weight maximum).</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.1.11.3   Composition and Fabricated Form</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Resin shall comprise a minimum 95.0 percent by weight concentration in the formulation.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  The finished form shall maintain ultraviolet stability for a minimum of 25 years and be 
free of saltwater or petroleum product leachable materials.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  No unfused areas or light patches greater than <MET>300 micrometers</MET> <ENG>No. 50 sieve</ENG> shall be in 
the final fabricated form.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  The fabricated form shall have the following properties:</ITM><BRK/>
<MET><TBL><BRK/>
      Density (<RID>ASTM D 792</RID>)                   57.5-58.7 lb/cu.ft<BRK/>
      Tensile Strength (<RID>ASTM D 638</RID>)<BRK/>
          Ultimate, minimum                      31.7 MPa<BRK/>
          Ultimate Elongation, minimum           250 percent<BRK/>
      Impact Strength (<RID>ASTM D 256</RID>)<BRK/>
          Test Method A, Izod                    Non-break for all five<BRK/>
                                                 determinations in sample<BRK/>
      Hardness (<RID>ASTM D 2240</RID>), minimum        Shore D 65<BRK/>
      Coefficient of Friction (<RID>ASTM D 1894</RID>)<BRK/>
          Kinetic, maximum                       0.13<BRK/>
          Static, maximum                        0.20<BRK/>
      Water Absorption (<RID>ASTM D 570</RID>)          Nil<BRK/>
      Abrasion Index (relative to steel = 100),<BRK/>
          maximum                                10<BRK/></TBL>
</MET><ENG><TBL><BRK/>
      Density (<RID>ASTM D 792</RID>)                   0.92-0.94 g/cc<BRK/>
      Tensile Strength (<RID>ASTM D 638</RID>)<BRK/>
          Ultimate, minimum                      4600 psi<BRK/>
          Ultimate Elongation, minimum           250 percent<BRK/>
      Impact Strength (<RID>ASTM D 256</RID>)<BRK/>
          Test Method A, Izod                    Non-break for all five<BRK/>
                                                 determinations in sample<BRK/>
      Hardness (<RID>ASTM D 2240</RID>), minimum        Shore D 65<BRK/>
      Coefficient of Friction (<RID>ASTM D 1894</RID>)<BRK/>
          Kinetic, maximum                       0.13<BRK/>
          Static, maximum                        0.20<BRK/>
      Water Absorption (<RID>ASTM D 570</RID>)          Nil<BRK/>
      Abrasion Index (relative to steel = 100),<BRK/>
          maximum                                10<BRK/></TBL>
</ENG><BRK/>
<ITM INDENT="-0.33">e.  Color shall be black.</ITM><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>2.2   <SUB>CONCRETE</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>2.2.1   Contractor-Furnished <SUB>Concrete Mix Design</SUB></TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Insert the specified compressive strength, f'c.  Consider reducing average 
overstrength factor to produce a more economical concrete mix design, since 
these piles are not critical structural elements.  ACI 318M may be modified 
for a specified compressive strength, f'c, over<MET> 35 MPa</MET><ENG> 5000 psi</ENG> to permit a 
required average compressive strength, f'cr, of f'c plus<MET> 4.8 MPa</MET><ENG> 700 psi</ENG>.  Concrete 
may be proportioned in accordance with ACI 214R for the probability of 1 test 
in 10 falling below the specified compressive strength, f'c, if the mix design 
reflects actual concrete plant standard deviations and the resulting production 
concrete conforms to specified requirements.  Do not use lightweight or fiber-reinforced 
concrete.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Concrete shall have a minimum specified compressive strength, f'c, of [_____] psi at 28 days.  The minimum cement 
content shall be<MET> 354 kg/cu. meter</MET><ENG> 600 pounds per cubic yard</ENG> of concrete.  The design shall be prepared in accordance 
with <RID>ACI 211.1</RID> or <RID>ACI 318M</RID>.  The mix design shall be based on current materials previously evaluated by the concrete 
producer whose established methods of statistical quality control is in conformance with <RID>ACI 318M</RID>.  In the absence 
of such data, the Contractor shall sample and test the aggregates for the design of concrete.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.2   Concrete Mix Design Proportioning</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Water and cement ratio shall be equal to or less than 0.40.  If fly ash is used, the water 
and cement ratio shall be calculated as the weight of water divided by the weight of cement 
plus 60 percent of the weight of fly ash.  If silica fume is used, the water and cement ratio 
shall be calculated as the weight of water divided by the weight of cement plus the weight of 
silica fume.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Maximum aggregate size shall not exceed<MET> 19 mm</MET><ENG> 3/4 inch</ENG>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Air-entrainment shall be 5 to 8 percent.  Determine air void structure in accordance with <RID>
ACI 212.3R</RID>.  Spacing factor shall be less than<MET> 2.5 mm</MET><ENG> 0.01 inch</ENG>, the specific surface area shall 
be greater than<MET> 0.39 square meter per 0.000016 cubic meter</MET><ENG> 600 square inches per cubic inch</ENG> 
of air void volume, and the number of air voids per<MET> mm</MET><ENG> inch</ENG> of traverse shall be significantly 
greater than the numerical value of the percentage of air in the concrete.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.2.3   Trial Mixtures</TTL><BRK/>
<BRK/>
<TXT>Trial mixtures having proportions and consistencies of the proposed mix design shall be made to document the 
Contractor's ability to produce workable concrete which does not segregate or show excessive slump loss characteristics.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3   FABRICATION OF PRETENSIONED PILES</TTL><BRK/>
<BRK/>
<TXT>Piles shall be pretensioned concrete piles.  Workmanship shall conform to standard commercial practice in prestressing 
plants.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.3.1   Formwork</TTL><BRK/>
<BRK/>
<TXT>Provide forms of metal, braced and stiffened against deformation, accurately constructed, watertight, and supported 
on unyielding casting beds.  Forms shall permit movement of pile without damage during release of the prestressing 
force.  Make piles to dimensional tolerances in accordance with <RID>PCI MNL-116</RID> and as follows:</TXT><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Length: <MET> 10 mm per 3 meters</MET><ENG> 3/8 inch per 10 feet</ENG>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Cross section: <MET> plus 13 mm to minus 6 mm</MET><ENG> plus 1/2 inch to minus 1/4 inch</ENG>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Deviation from straight lines:  not more than<MET> 3 mm per 3 meters</MET><ENG> 1/8 inch per 10 feet</ENG> of 
length.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">d.  Pile head:  plus or minus<MET> 6 mm per 0.30 meter</MET><ENG> 1/4 inch per foot</ENG> of head dimension from true 
right angle plane.  Surface irregularities:  plus or minus<MET> 3 mm</MET><ENG> 1/8 inch</ENG>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">e.  Location of reinforcing steel</ITM><BRK/>
<BRK/>
<ITM>(1)  Main reinforcement: <MET> 3 to 6 mm</MET><ENG> 1/8 to 1/4 inch</ENG> from position designated on drawings.</ITM><BRK/>
<BRK/>
<ITM>(2)  Spacing of spiral:  plus or minus<MET> 13 mm</MET><ENG> 1/2 inch</ENG> from position designated on drawings.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">f.  Location of pipe sleeves from true position:  plus or minus<MET> 10 mm</MET><ENG> 3/8 inch</ENG>.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.2   Pretensioning</TTL><BRK/>
<BRK/>
<TXT>Measure tension to which steel is to be pretensioned by jack pressure read on a calibrated gage and verify by 
elongation of steel.  Use gage calibrated within last 6 months by a laboratory approved by Contracting Officer.  
Provide means for measuring elongation of steel to nearest<MET> 3 mm</MET><ENG> 1/8 inch</ENG>.  When difference between results of 
measurement and gage reading is more than 5 percent, determine cause of discrepancy and correct.  Give tensioning 
steel a uniform prestress prior to being brought to design prestress.  Induce same initial prestress in each 
unit when several units of prestressing steel in a pile are stretched simultaneously.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.3   Casting</TTL><BRK/>
<BRK/>
<SPT><TTL>2.3.3.1   Conveying</TTL><BRK/>
<BRK/>
<TXT>Clean conveying equipment thoroughly before each run.  Convey concrete from mixer to forms as rapidly as practicable 
by methods which will not cause segregation or loss of ingredients.  Deposit concrete as nearly as practicable 
to its final position.  During placing, make any free vertical drop of the concrete less than<MET> one meter</MET><ENG> 3 feet</ENG>
.  Remove concrete which has segregated in conveying or placing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.3.2   Placing and Casting</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select chamfer required.  Consult with local producers.  Where project 
requires a large quantity of piling, a specific value may be specified, otherwise, 
use a minimum or a range of values.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Perform concrete casting within 3 days after pretensioning steel; however, do not deposit concrete in forms until 
placement of reinforcement and anchorages have been inspected and approved by pile manufacturer's quality control 
representative.  Produce each pile of dense concrete straight with smooth surfaces with reinforcement retained 
in its proper position during fabrication.  Use vibrator with heads smaller than the minimum distance between 
steel for pretensioning.  Make surface of pile ends perpendicular to axis of pile.  Chamfer, [a minimum of <MET>19 
mm</MET> <ENG>3/4 inch</ENG>,] [[_____]<MET> mm</MET><ENG> inch</ENG>,] [between<MET> 19 and 28 mm</MET><ENG> 3/4 and 1 1/8 inch</ENG>,] ends of piles and corners of square 
piles.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3.4   <SUB>Curing of Piles</SUB></TTL><BRK/>
<BRK/>
<TXT>Cure piles using moist or accelerated curing.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.3.4.1   Moist Curing</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Impervious sheeting:  <RID>ASTM C 171</RID>; waterproof paper, clear or white polyethylene sheeting, 
or polyethylene-coated burlap.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Pervious sheeting:  <RID>AASHTO M 182</RID>.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">c.  Liquid membrane-forming compound:  <RID>ASTM C 309</RID>, white pigmented, Type 2, Class B.</ITM><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.4.2   Accelerated Curing</TTL><BRK/>
<BRK/>
<TXT>After placement of concrete, moist cure for a period of 4 hours.   Accelerate curing until concrete has reached 
specified release strength.   Enclose casting bed for accelerated curing with a suitable enclosure.   During 
application of steam or heat, increase the air temperature at a rate not to exceed<MET> 15.6 degrees C</MET><ENG> 60 degrees 
F</ENG> per hour.  Cure at a maximum temperature of<MET> 15.6 degrees C</MET><ENG> 160 degrees F</ENG> until concrete has reached specified 
release strength.  Reduce temperature at a rate not to exceed<MET> 15.6 degrees C</MET><ENG> 60 degrees F</ENG> per hour until a temperature 
of<MET> -7 degrees C</MET><ENG> 20 degrees F</ENG> above ambient air temperature is reached.  After accelerated curing, moist cure 
using either water or membrane curing until a total accelerated and moist curing time of 72 hours is achieved.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.3.5   Detensioning</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Specify "release strength."  Release strength of<MET> 30 MPa</MET><ENG> 4000 psi</ENG> (design 
strength of<MET> 35 MPa</MET><ENG> 5000 psi</ENG>) or 0.8 of the 28 day design strength is desirable; 
however, some regions use 0.7 of the design strength (<MET>25 MPa</MET><ENG>3500 psi</ENG> for design 
strength of<MET> 35 MPa</MET><ENG> 5000 psi</ENG>).  A minimum release strength of 0.6 of the design 
strength is required.  Check with local pile manufacturers.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Perform releasing of prestressed steel in pretensioned piles in such an order that eccentricity of prestress 
will be minimized.  Gradually release tension in strands from anchorage.  Detension after approval by pile manufacturer's 
quality control representative.  Perform transfer of prestressing force when concrete has reached a minimum compressive 
strength of [_____]<MET> MPa</MET><ENG> psi</ENG>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.3.6   Marking</TTL><BRK/>
<BRK/>
<TXT>Mark pile to identify in-place impact face.  Marking shall be clearly visible during driving.</TXT><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>2.4   PRODUCT QUALITY CONTROL</TTL><BRK/>
<BRK/>
<TXT>Where piling is manufactured in a plant with an established quality control program as attested to by a current 
certification in the PCI Certification Program for Quality Control, perform product <SUB>quality control procedures</SUB>
 in accordance with <RID>PCI MNL-116</RID>.  Where piling is manufactured by specialists or in plants not currently enrolled 
in the PCI Certification Program for Quality Control, set up a product quality control system in accordance with <RID>
PCI MNL-116</RID> and perform concrete and aggregate quality control testing using an independent commercial testing 
laboratory approved by the Contracting Officer in accordance with the following.</TXT><BRK/>
<BRK/>
<SPT><TTL>2.4.1   Aggregate Tests</TTL><BRK/>
<BRK/>
<TXT>Take samples of fine and coarse aggregate at the concrete batch plant and test.  Perform mechanical analysis 
(one test for each aggregate size) in accordance with <RID>ASTM C 136</RID> including determination of the specific gravity.  
Tabulate the results of the tests in accordance with <RID>ASTM C 33</RID>.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.2   Strength Tests</TTL><BRK/>
<BRK/>
<TXT>Sample concrete in accordance with <RID>ASTM C 172</RID> at the time the concrete is deposited for each production line.  
Compression tests shall conform to methods of <RID>ASTM C 39/C 39M</RID> and <RID>ASTM C 31/C 31M</RID>.  Perform slump tests in accordance 
with <RID>ASTM C 143/C 143M</RID>.  Mold at least six cylinders per day or for every<MET> 15 cubic meter</MET><ENG> 20 cubic yards</ENG> of concrete 
placed, whichever is greater.  Test two cylinders of the set at 7 days of 14 days, or at a time for establishing 
transfer of prestressing force (release strength) and removal of pile from forms.  Perform strength tests 28 
days after molding using the remaining cylinders of the set.  Cure the cylinders in the same manner as the piles 
and place at the point where the poorest curing conditions are offered.  This is the coolest point in the bed 
for steam curing.  Cylinders to be tested at 28 days shall be moist cured.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.3   Changes in Proportions</TTL><BRK/>
<BRK/>
<TXT>If, after evaluation of strength test results, the compressive strength is less than the specified compressive 
strength, make adjustments in the proportions and water content and changes in the temperature, moisture, and 
curing procedures as necessary to secure the specified strength.  Submit changes to the Contracting Officer in 
writing.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>2.4.4   Compressive Strength Test Results</TTL><BRK/>
<BRK/>
<TXT>Evaluate compression test results at 28 days in accordance with <RID>ACI 214R</RID> using a coefficient of variation of 
10 percent.  Evaluate the strength of concrete by averaging the test results (two specimens) of each set (four 
specimens) of standard cylinders tested at 28 days.  Not more than 10 percent of the individual specimens tested 
shall have an average compressive strength less than specified average compressive strength.</TXT><BRK/>
<BRK/></SPT>
</SPT></PRT><PRT><TTL>PART 3   EXECUTION</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1   PILE DRIVING</TTL><BRK/>
<BRK/>
<SPT><TTL>3.1.1   Driving Piles</TTL><BRK/>
<BRK/>
<TXT>Piles shall not be driven until 100 percent of design strength has been attained and until at least 14 days after 
detensioning.  Drive piles to the indicated tip elevation and to the minimum embedment depth shown on the drawings.  
Pile driving shall be conducted as one continuous operation.   The pile shall be driven until the resistance 
criterion is met.  During the initial driving and until the pile tip has penetrated beyond layers of very soft 
soil or below the bottom of prejetted or preformed holes, use a reduced rated driving energy of the hammer of 
not more than<MET> 20,235 Joules</MET><ENG> 15,000 foot-pounds</ENG> per blow or as otherwise directed by the Contracting Officer, 
to prevent high tension-wave driving stresses which could damage the pile.  Resistance criterion shall be 20 
blows for<MET> 0.3 m</MET><ENG> one foot</ENG> or less.  The Contracting Officer may modify the criteria based upon the actual hammer 
being used and its rated energy and its compatibility as verified by a pile test program.  <TST>If a pile fails to 
reach the indicated butt elevation or minimum embedment, the Contractor shall notify the Contracting Officer 
and perform corrective measures as directed.</TST>  Provide hearing protection when noise levels exceed 140 dB.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.2   Pile Driving Leads and Templates</TTL><BRK/>
<BRK/>
<TXT>Piles shall be driven with the hammer positioned in a fixed or swinging lead.  "Free hammer" will not be permitted.  
Swinging lead shall be used only in conjunction with a template system to spot the piles.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.3   Installation of Piles</TTL><BRK/>
<BRK/>
<TXT>Take care to avoid damage to piles during handling, when placing the pile in leads, and during pile-driving operations.  
Inspect piles when delivered, when in leads immediately before driving, and after installation.  No visible cracks 
will be permitted.  Notify the Contracting Officer of any visible cracks and perform corrective measures as directed.   
Laterally support piles during driving, but allow rotation in leads.  Take special care to maintain the pile 
orientation during driving.  Square the top of the pile to the longitudinal axis of the pile.  Maintain axial 
alignment of pile hammer with that of pile.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.4   Tolerances in Driving</TTL><BRK/>
<BRK/>
<TXT>Drive piles with a variation of not more than one percent from vertical for plumb piles.  Maintain and check 
axial alignment of pile and leads at start of pile driving and when the pile top is approximately<MET> 1.5 m</MET><ENG> 5 feet</ENG>
 above the indicated elevation.  Make intermediate checks of pile alignment if there is evidence of pile drifting.  <TST>
If subsurface conditions cause pile drifting beyond the allowable axial alignment tolerance, notify the Contracting 
Officer and perform corrective measures as directed.</TST>  Place butts within<MET> 50 mm</MET><ENG> 2 inches</ENG> of the location indicated.   
Manipulation of pile within specified tolerances is permitted, but do not manipulate piles more than one percent 
of their exposed length above the mudline.  Check piles for heave.  Redrive, to the indicated elevation, piles 
found to be heaved.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.5   Jetting and Predrilling Holes</TTL><BRK/>
<BRK/>
<TXT>If predrilled holes are used, the diameter of the hole shall not exceed the diagonal dimension of the pile and 
the hole shall be kept open until the pile is inserted and advanced to the bottom of the hole.  Piles shall be 
installed in holes immediately after predrilling to minimize the potential for sloughing and collapse of the 
hole.  Jetting of the pile to obtain penetration is permitted.  Discontinue jetting or predrilled hole at a depth 
of<MET> 1.5 m</MET><ENG> 5 feet</ENG> from the indicated tip elevation, and achieve the remaining penetration by driving.  Before starting 
the driving of the final<MET> 1.5 m</MET><ENG> 5 feet</ENG>, firmly seat the piles in place by the application of a number of reduced-energy 
hammer blows.  The Contractor shall arrange to provide an ample supply of water at adequate pressure for effective 
jetting.  <TST>The use and details of jetting or predrilled holes shall be approved by the Contracting Officer.</TST></TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.6   Splices</TTL><BRK/>
<BRK/>
<TXT>Splicing of piles is not permitted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.7   Buildup</TTL><BRK/>
<BRK/>
<TXT>Buildups are not permitted.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.8   Pile Cutoffs</TTL><BRK/>
<BRK/>
<TXT><TST>Cut off piles with a smooth level cut using pneumatic tools, sawing, or other suitable methods approved by the 
Contracting Officer.  The use of explosives for cutting is not permitted.</TST></TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.1.9   Patching</TTL><BRK/>
<BRK/>
<ITM INDENT="-0.33">a.  Embedded Lifting Loops.  Provide a<MET> 25 mm</MET><ENG> one inch</ENG> minimum conical depression around embedded 
lifting loops.  Cut off lifting loops at bottom of depression and patch depression with epoxy 
mortar.</ITM><BRK/>
<BRK/>
<ITM INDENT="-0.33">b.  Pile Butt.  Apply<MET> 25 mm</MET><ENG> one inch</ENG> thick layer of epoxy mortar cover over exposed prestressing 
strand on pile butt after driving.</ITM><BRK/>
<BRK/></SPT>
</SPT><SPT><TTL>3.2   <SUB>EQUIPMENT</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.1   Pile Hammers</TTL><BRK/>
<BRK/>
<TXT>Furnish a hammer having a capacity at least equal to the hammer manufacturer's recommendation for the total weight 
of pile and character of subsurface material to be encountered.  Obtain the required driving energy of the hammer, 
except for diesel hammers, by use of a heavy ram and a short stroke with low-impact velocity.  The pile hammer 
shall be capable of operating at a reduced energy level (1/2 to 2/3 of rated energy level) during seating of 
the piles in preformed holes and when driving through soft or loose materials.  The driving energy of the hammer, 
at final driving, shall be not less than<MET> 40.650 Joules</MET><ENG> 30,000 foot-pounds</ENG>.   At final driving, operate the pile 
hammer in accordance with the manufacturer's recommendation.  At final driving, operate diesel-powered hammers 
at the rate recommended by the manufacturer for hard driving.   Maintain sufficient pressure at the steam hammer 
so that (1) for double-acting hammer, the number of blows per minute during and at the completion of driving 
of a pile is equal approximately to that at which the hammer is rated; (2) for single-acting hammer, there is 
a full upward stroke of the ram; and (3) for differential-type hammer, there is a slight rise of the hammer base 
during each downward stroke.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.2   <SUB>Driving Helmets, Capblocks, and Pile Cushions</SUB></TTL><BRK/>
<BRK/>
<SPT><TTL>3.2.2.1   Driving Helmets or Caps and Pile Cushions</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Insert minimum and maximum thicknesses for pile cushion.  An absolute 
minimum would be<MET> 75 mm</MET><ENG> 3 inches</ENG> and the actual required thickness would depend 
upon pile length, hammer energy, design load, required final penetration resistance, 
and character of subsurface material to be encountered.   Generally thicker 
blocks are required for longer piles, larger hammers, and harder driving.  A 
wave equation analysis is useful in determining required thicknesses for pile 
cushion.  Minimum thickness is to protect head of pile.  Pile cushion should 
also have a maximum thickness to ensure effective driving.  Select when pile 
cushion is to be replaced.  It is generally recommended that a new pile cushion 
be used at the start of driving of each pile.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Use a steel driving helmet or cap, including a pile cushion between top of pile and driving helmet or cap, to 
prevent impact damage to pile.  The driving helmet or cap-and-pile cushion combination shall be capable of protecting 
the head of the pile, minimize energy absorption and dissipation, and transmit hammer energy uniformly over the 
top of the pile.   The driving helmet or cap shall fit sufficiently loose around the top of the pile so that 
the pile may be free to rotate without binding within the driving helmet.  The Contractor shall demonstrate to 
the satisfaction of the Contracting Officer that the equipment to be used on the project performs the above function.  
The pile cushion shall be of laminated construction using softwood boards with the grain parallel to the end 
of the pile.  The thickness of the pile cushion shall be<MET> 300 mm</MET><ENG> 12 inches</ENG> minimum.  The cushion shall not be 
changed near the end of driving.  Replace the pile cushion when it has become compressed beyond two-thirds of 
its original thickness, charred, or burned, or has become spongy or deteriorated in any manner.  Use new cushions 
for initial driving of each pile.  During redriving or restriking of piles, a used cushion assembly shall be 
used.  The Contractor shall submit to the Contracting Officer at least 2 weeks before the start of pile driving 
operations detailed drawings of the driving helmet and pile cushion to be used.</TXT><BRK/>
<BRK/></SPT>
<SPT><TTL>3.2.2.2   Hammer Cushion or Capblock</TTL><BRK/>
<NTE><BRK/>
<AST/><BRK/>
<NPR>NOTE:  Select either wood or aluminum/micarta capblock.  Delete inappropriate 
sentences.  An aluminum/micarta capblock is recommended because of its consistent 
elastic properties and long life.   If final pile penetration resistance is 
based on a wave equation analysis, the type capblock used should be the same 
as that used in the analysis.</NPR><BRK/>
<AST/><BRK/></NTE>
<BRK/>
<TXT>Use a hammer cushion or capblock between driving helmet or cap and hammer ram consisting of [a solid hardwood 
block with grain parallel to the pile axis and enclosed in a close-fitting steel housing] [aluminum and micarta 
(or equal) discs stacked alternately in a steel housing].  Use steel plates at top and bottom of capblock.  [Replace 
wood capblock when it becomes highly compressed, charred or burned, or becomes spongy or deteriorated in any 
manner.]  [Replace aluminum or micarta discs that have become damaged, split, or deteriorated in any manner.]  
[Do not replace wood capblock during final driving of any pile.]  Do not use small wood blocks, wood chips, rope, 
or other materials that permit excessive loss of hammer energy.</TXT><BRK/>
<BRK/></SPT>
</SPT></SPT><SPT><TTL>3.3   FIELD QUALITY CONTROL</TTL><BRK/>
<BRK/>
<SPT><TTL>3.3.1   Pile Records</TTL><BRK/>
<BRK/>
<TXT>For each pile, keep a record of the number of blows required for each<MET> 0.30 m</MET><ENG> foot</ENG> of penetration and the number 
of blows for the last<MET> 150 mm</MET><ENG> 6 inch</ENG> penetration or fraction thereof.  Include in the record the beginning and 
ending times of each operation during driving of pile, type and size of the hammer used, rate of operation, stroke 
or equivalent stroke for diesel hammer, type of driving helmet, and type and dimension of the hammer cushion 
(capblock) and pile cushion used.  Record re-tap data and any unusual occurrence during driving of the pile.  
Include in the record performance characteristics of jet pump, unassisted penetration of pile, jet-assisted penetration 
of pile, and tip elevation before driving and at end of driving.  <TST>Notify Contracting Officer 10 days prior to 
driving of piles.  Submit complete and accurate records of installed piles to Contracting Officer within 15 calendar 
days after completion of the pile driving.  Make pile-driving records available to the Contracting Officer at 
the job site within 24 hours of each day's pile driving.</TST>  A preprinted form for recording pile driving data is 
included at the end of this section.</TXT><BRK/>
<PGE/><MET><TBL><THD><BRK/>
<HL4>PILE DRIVING LOG</HL4><BRK/></THD>
<BRK/>
  CONTRACT NO.________________________  CONTRACT NAME_______________________<BRK/>
  CONTRACTOR_____________________________  TYPE OF PILE_____________________<BRK/>
  PILE LOCATION_____________  PILE SIZE: BUTT/TIP: ________  LENGTH_________<BRK/>
  GROUND ELEVATION_________________________  CUT OFF ELEVATION______________<BRK/>
  PILE TIP ELEVATION_________________  VERTICAL (_____)  BATTER 1 ON (_____)<BRK/>
  SPLICES ELEVATION____________________  COMPANY____________________________<BRK/>
<BRK/>
  HAMMER:       MAKE &amp; MODEL_________________  WT. RAM______________________<BRK/>
    STROKE______________________  RAM RATED ENERGY__________________________<BRK/>
    DESCRIPTION &amp; DIMENSIONS OF DRIVING CAP_________________________________<BRK/>
    CUSHION MATERIALS &amp; THICKNESS___________________________________________<BRK/>
<BRK/>
  INSPECTOR_________________________________________________________________<BRK/>
<BRK/>
  "DEPTH" COLUMN OF PILE DRIVING RECORD REFERENCED TO:<BRK/>
    _____________________ CUT-OFF ELEVATION<BRK/>
    _____________________ FINISH FLOOR ELEVATION<BRK/>
<BRK/>
  TIME:  START DRIVING_______  FINISH DRIVING________  DRIVING TIME_________<BRK/>
    INTERRUPTIONS (TIME, TIP ELEV. &amp; REASON)________________________________<BRK/>
  JET PRESSURE &amp; ELEVATIONS_________________________________________________<BRK/>
<BRK/>
  __________________________________________________________________________<BRK/>
<BRK/>
                DRIVING RESISTANCE<BRK/>
<BRK/>
  __________________________________________________<BRK/>
   DEPTH   NO. OF   DEPTH   NO. OF   DEPTH   NO. OF<BRK/>
     M     BLOWS      M     BLOWS      M     BLOWS<BRK/>
  __________________________________________________<BRK/>
     0      _____     5.4    _____    10.8    _____<BRK/>
     0.3    _____     5.7    _____    11.1    _____<BRK/>
     0.6    _____     6.0    _____    11.4    _____<BRK/>
     0.9    _____     6.3    _____    11.7    _____<BRK/>
     1.2    _____     6.6    _____    12.0    _____<BRK/>
     1.5    _____     6.9    _____    12.3    _____<BRK/>
     1.8    _____     7.2    _____    12.6    _____<BRK/>
     2.1    _____     7.5    _____    12.9    _____<BRK/>
     2.4    _____     7.8    _____    13.2    _____<BRK/>
     2.7    _____     8.1    _____    13.5    _____<BRK/>
     3.0    _____     8.4    _____    13.8    _____<BRK/>
     3.3    _____     8.7    _____    14.1    _____<BRK/>
     3.6    _____     9.0    _____    14.4    _____<BRK/>
     3.9    _____     9.3    _____    14.7    _____<BRK/>
     4.2    _____     9.6    _____    15.0    _____<BRK/>
     4.5    _____     9.9    _____    15.3    _____<BRK/>
     4.8    _____    10.2    _____    15.6    _____<BRK/>
     5.1    _____    10.5    _____    15.9    _____<BRK/>
<BRK/>
<BRK/>
  SHEET 1 OF 2<BRK/>
<PGE/>     16.2   _____    23.1    _____    29.7    _____<BRK/>
     16.5   _____    23.4    _____    30.0    _____<BRK/>
     16.8   _____    23.7    _____    30.3    _____<BRK/>
     17.1   _____    24.0    _____    30.6    _____<BRK/>
     17.4   _____    24.3    _____    30.9    _____<BRK/>
     17.7   _____    24.6    _____    31.2    _____<BRK/>
     18.0   _____    24.9    _____    31.5    _____<BRK/>
     18.3   _____    25.2    _____    31.8    _____<BRK/>
     18.6   _____    25.5    _____    32.1    _____<BRK/>
     18.9   _____    25.8    _____    32.4    _____<BRK/>
     19.2   _____    26.1    _____    32.7    _____<BRK/>
     19.5   _____    26.4    _____    33.0    _____<BRK/>
     19.8   _____    26.7    _____    33.3    _____<BRK/>
     20.1   _____    27.0    _____    33.6    _____<BRK/>
     20.4   _____    27.3    _____    33.9    _____<BRK/>
     20.7   _____    27.6    _____    34.2    _____<BRK/>
     21.0   _____    27.9    _____    34.5    _____<BRK/>
     21.3   _____    28.2    _____    34.8    _____<BRK/>
     21.6   _____    28.5    _____    35.1    _____<BRK/>
     21.9   _____    28.8    _____    35.4    _____<BRK/>
     22.2   _____    29.1    _____    35.7    _____<BRK/>
     22.5   _____    29.4    _____    36.0    _____<BRK/>
     22.8   _____<BRK/>
<BRK/>
  __________________________________________________________________________<BRK/>
<BRK/>
  Driving resistance in blows per 25 mm for last 0.30 m of penetration:<BRK/>
<BRK/>
  DEPTH________                                              DEPTH________<BRK/>
<BRK/>
  25mm___ 50mm___100mm___125mm___150mm___175mm___200mm___225mm___ 250mm___<BRK/>
<BRK/>
  275mm___300mm___<BRK/>
<BRK/>
  ELEV._______                                               ELEV.________<BRK/>
<BRK/>
  REMARKS___________________________________________________________________<BRK/>
<BRK/>
  __________________________________________________________________________<BRK/>
<BRK/>
<BRK/>
  CUT OFF ELEVATION:  FROM DRAWING                          ________________<BRK/>
<BRK/>
  TIP ELEVATION = GROUND ELEVATION - DRIVEN DEPTH =         ________________<BRK/>
<BRK/>
  DRIVEN LENGTH = CUT OFF ELEVATION - TIP ELEVATION =       ________________<BRK/>
<BRK/>
  CUT OFF LENGTH = PILE LENGTH - DRIVEN LENGTH =            ________________<BRK/>
<BRK/>
<BRK/>
  SHEET 2 OF 2<BRK/></TBL>
</MET><BRK/>
<PGE/><ENG><TBL><THD><BRK/>
<HL4>PILE DRIVING LOG</HL4><BRK/></THD>
<BRK/>
  CONTRACT NO.________________________  CONTRACT NAME_______________________<BRK/>
  CONTRACTOR_____________________________  TYPE OF PILE_____________________<BRK/>
  PILE LOCATION_____________  PILE SIZE: BUTT/TIP: ________  LENGTH_________<BRK/>
  GROUND ELEVATION_________________________  CUT OFF ELEVATION______________<BRK/>
  PILE TIP ELEVATION_________________  VERTICAL (_____)  BATTER 1 ON (_____)<BRK/>
  SPLICES ELEVATION____________________  COMPANY____________________________<BRK/>
<BRK/>
  HAMMER:       MAKE &amp; MODEL_________________  WT. RAM______________________<BRK/>
  STROKE______________________  RAM RATED ENERGY____________________________<BRK/>
  DESCRIPTION &amp; DIMENSIONS OF DRIVING CAP___________________________________<BRK/>
  CUSHION MATERIALS &amp; THICKNESS_____________________________________________<BRK/>
<BRK/>
  INSPECTOR_________________________________________________________________<BRK/>
<BRK/>
  "DEPTH" COLUMN OF PILE DRIVING RECORD REFERENCED TO:<BRK/>
  _____________________ CUT-OFF ELEVATION<BRK/>
  _____________________ FINISH FLOOR ELEVATION<BRK/>
<BRK/>
  TIME:  START DRIVING_______  FINISH DRIVING________  DRIVING TIME_________<BRK/>
  INTERRUPTIONS (TIME, TIP ELEV. &amp; REASON)__________________________________<BRK/>
  JET PRESSURE &amp; ELEVATIONS_________________________________________________<BRK/>
<BRK/>
  __________________________________________________________________________<BRK/>
<BRK/>
               DRIVING RESISTANCE<BRK/>
<BRK/>
  __________________________________________________<BRK/>
  DEPTH   NO. OF   DEPTH   NO. OF   DEPTH   NO. OF<BRK/>
   FT.    BLOWS     FT.    BLOWS     FT.    BLOWS<BRK/>
  __________________________________________________<BRK/>
    0    _____      18     _____     36     _____<BRK/>
    1    _____      19     _____     37     _____<BRK/>
    2    _____      20     _____     38     _____<BRK/>
    3    _____      21     _____     39     _____<BRK/>
    4    _____      22     _____     40     _____<BRK/>
    5    _____      23     _____     41     _____<BRK/>
    6    _____      24     _____     42     _____<BRK/>
    7    _____      25     _____     43     _____<BRK/>
    8    _____      26     _____     44     _____<BRK/>
    9    _____      27     _____     45     _____<BRK/>
   10    _____      28     _____     46     _____<BRK/>
   11    _____      29     _____     47     _____<BRK/>
   12    _____      30     _____     48     _____<BRK/>
   13    _____      31     _____     49     _____<BRK/>
   14    _____      32     _____     50     _____<BRK/>
   15    _____      33     _____     51     _____<BRK/>
   16    _____      34     _____     52     _____<BRK/>
   17    _____      35     _____     53     _____<BRK/>
<BRK/>
<BRK/>
  SHEET 1 OF 2<BRK/>
<PGE/>   54     _____     77     _____     99     _____<BRK/>
   55     _____     78     _____    100     _____<BRK/>
   56     _____     79     _____    101     _____<BRK/>
   57     _____     80     _____    102     _____<BRK/>
   58     _____     81     _____    103     _____<BRK/>
   59     _____     82     _____    104     _____<BRK/>
   60     _____     83     _____    105     _____<BRK/>
   61     _____     84     _____    106     _____<BRK/>
   62     _____     85     _____    107     _____<BRK/>
   63     _____     86     _____    108     _____<BRK/>
   64     _____     87     _____    109     _____<BRK/>
   65     _____     88     _____    110     _____<BRK/>
   66     _____     89     _____    111     _____<BRK/>
   67     _____     90     _____    112     _____<BRK/>
   68     _____     91     _____    113     _____<BRK/>
   69     _____     92     _____    114     _____<BRK/>
   70     _____     93     _____    115     _____<BRK/>
   71     _____     94     _____    116     _____<BRK/>
   72     _____     95     _____    117     _____<BRK/>
   73     _____     96     _____    118     _____<BRK/>
   74     _____     97     _____    119     _____<BRK/>
   75     _____     98     _____    120     _____<BRK/>
   76     _____<BRK/>
<BRK/>
  __________________________________________________________________________<BRK/>
<BRK/>
  DRIVING RESISTANCE IN BLOWS PER INCH FOR LAST FOOT OF PENETRATION:<BRK/>
<BRK/>
  DEPTH________                                              DEPTH________<BRK/>
<BRK/>
  1"___2"___3"___4"___5"___6"___7"___8"___9"___10"___11"___12"___<BRK/>
<BRK/>
  ELEV._______                                               ELEV.________<BRK/>
<BRK/>
  REMARKS___________________________________________________________________<BRK/>
<BRK/>
  __________________________________________________________________________<BRK/>
<BRK/>
<BRK/>
  CUT OFF ELEVATION:  FROM DRAWING                          ________________<BRK/>
<BRK/>
  TIP ELEVATION = GROUND ELEVATION - DRIVEN DEPTH =         ________________<BRK/>
<BRK/>
  DRIVEN LENGTH = CUT OFF ELEVATION - TIP ELEVATION =       ________________<BRK/>
<BRK/>
  CUT OFF LENGTH = PILE LENGTH - DRIVEN LENGTH =            ________________<BRK/>
<BRK/>
  SHEET 2 OF 2<BRK/></TBL>
</ENG><BRK/></SPT>
</SPT></PRT>    <END/><BRK/></SEC>